Structural Drawings 2
Structural Drawings 2
Structural Drawings 2
830
Line of
830
830
830
220 500 10mm polystyrene isolation joint 500mm x 220mm 500mm x 220mm THREE TO BE TESTED AT SEVEN DAYS, THE
s.o.p. Existing Building 220 280 between existing building r.c. column. r.c. column. REMAINDER AT TWENTY EIGHT DAYS. THE RESULTS
G G G G TO BE FORWARDED TO THE ENGINEER.
220
360
360
465 360 350
220
220
10
10
9. CONTRACTOR TO CONSTRUCT A BLINDING LAYER
P2 P3 P5 P6 IF SOIL CONDITIONS RESULT IN REINFORCEMENT
700
700
Line of new r.c. foundation. s.o.p.
480
480
480
350 150 500 COVER NOT BEING MAINTAINED.
P1 P7
110
3070
12. ALL SINGLE SKIN BRICKWORK TO BE STOPPED 2
A A
5745
5745
5745
5745
3195
100 220 380 Line of new r.c. foundation. COURSES BELOW SOFFIT OF SLAB AND COMPLETED
ALL R.C. GROUND BEAMS ARE : AFTER PROPS HAVE BEEN REMOVED.
4335
800mm deep x 700mm wide 13. ALL CONCRETE PLASTER AND BRICKWORK PLASTER
450 250 INTER-FACES TO RECEIVE V-JOINTS.
with t.o.c. @ + 1349,235 lvl.
240
14. THE ENGINEER REQUIRES 24HRS NOTICE FOR ALL
INSPECTIONS.
P8 P9 10mm polystyrene isolation joint
700
700
220
220 between existing building
and new r.c. foundation.
500mm x 220mm
240
4690 320 380
1265
565
350
250
250
100
100
r.c. column.
9900
P 10 P 11 P 12 P 13
30 320
500mm x 220mm
700
500
700
500
700
Gx Gx Gx r.c. column. Gx
500mm x 220mm
10770
250
r.c. column.
250
500 130
100
350
100
220 220 260
13350
13350
100 340 260 100 220 380
Existing
700 4690 700 3755 700 465 10
Note : Brickwork Strapping : Building
11010 o/a concrete
4225
3525
3525
All brickwork to be 'strapped/tied' to r.c. columns,
4635
4635
4635
4635
shear walls and other concrete vertical elements with
30mm wide x 1,2mm thk. x 800mm long galvanised steel Line of new r.c. foundation.
straps. 100mm of steel strap shot fired to column and
700mm of steel strap built into brick wall every 3rd course. 100 700 1015
700
Each brick skin (at every 3rd course) to be tied to r.c. 465 550
columns, shear walls and other concrete vertical elements. 220 220 260 700mm x 220mm 350 350 Line of Existing
120
120
120
220 120
r.c. column. Building
Line of new
P 14 P 15 P 16
340
340
r.c. foundation.
60 640
700
700
700
10
1170
1170
640
640
410
10
J J J 100 1170mm x 220mm J
240
240
1170mm x 220mm
530
530
1105
870
950
810
810
810
830
r.c. shear wall.
830
830
830
100 r.c. shear wall. 100
100
P 17
220
80
BRICKWORK NOTES : 10mm polystyrene isolation joint
K K K K
100
between existing building
100
220
135
- All brickwork (solid brick walls or cavity brick walls) below surface bed level 100
2690
and new r.c. foundation.
3870
to have brickforce in every course. 110 110
- All solid brick walls above surface bed level are 220mm wide or 110mm wide 340 220 140
3390
2870mm x 220mm
1880
1880
1880
2285
2400
2580
- All parapet walls are 220mm wide or 110mm wide with brickforce built in
2500
2500
10
every course. 100 220 380 4460
230
100
- All cavity brick walls above surface bed level are 340mm wide with 110mm
P 18 P 19 wide outer skin brickwork with 120mm central cavity with 3,15mm Ø x 300mm
700
700
500
700
long galvanised butterfly wire ties built vertically into brickwork every 3rd
course and horizontally at max. 500mm centres above surface bed level
and built vertically into brickwork in every course below surface bed level and
100
100
210 295 horizontally at max. 500mm centres. 240 220 240
- All brickwork to Architect's detail in Class 2 mortar.
250 2100 2225 855 975 2215 970 705 340 900 4490 700 200 4260 700 310
100 195
90 5400 5400
900 1010
450
5390 5860
1 2 3 11560
440 5400 5400 320
PILING LAYOUT
1 2 3
PILING NOTES :-
1. ALL PILING TO BE CARRIED OUT IN ACCORDANCE WITH SABS 1200F.
FOUNDATION LAYOUT
2. THE RESPONSIBILITY FOR THE DESIGN AND PERFORMANCE OF ALL PILES
SHALL LIE WITH THE PILING CONTRACTOR AND THE PILING CONTRACTOR SHALL
SUPPLY A 'PILING GUARANTEE' OR A 'PILING LIABILITY INSURANCE POLICY' IN THIS REGARD. REV DESCRIPTION BY DATE
THE 'PILING GUARANTEE OR A 'PILING LIABILITY INSURANCE POLICY' IS TO BE IN PLACE FOR
A MINIMUM PERIOD OF 3 YEARS AFTER THE FINAL PILE HAS BEEN INSTALLED. THE PILING
CONTRACTOR'S PILE DESIGN ENGINEER MUST SUBMIT A 'CERTIFICATE OF STABILITY'
TO THE PRINCIPAL STRUCTURAL ENGINEER ON COMPLETION OF THE PILING CONTRACT.
150
r.c. surface bed slab.
150
6. PILE CUT-OFF LEVEL TO BE 50mm ABOVE SOFFIT OF THE GROUND BEAM OR AS INDICATED
ON THE PILING LAYOUTS WITH 500mm PILE REBAR PROJECTION. PROJECT
445
7. PILE INTEGRITY TESTING IS TO BE CARRIED OUT ON ALL PILES BY AN INDEPENDENT +1349,235 lvl. UMALUSI OFFICES
GEOTECHNICAL ENGINEER. NO 'IN-HOUSE' INTEGRITY TESTING BY THE PILING CONTRACTOR
WILL BE ACCEPTED.
ADDITIONS AND ALTERATIONS
800mm deep x 700mm wide
CL
8. ALL PILE SETTING OUT IS TO BE CARRIED OUT BY THE PILING CONTRACTOR AND VERIFIED BY r.c. ground beam.
750
pile DETAILS
800
THE MAIN CONTRACTOR WHOM ASSUMES FULL RESPONSIBILITY FOR THE PILE SETTING OUT. Pile cut-off level.
ALL PILE POSITIONS ARE TO BE SET OUT BY THE PILING CONTRACTOR'S REGISTERED
ENGINEERING SURVEYOR.
See Piling Key. NEW ABLUTIONS BUILDING
PILING & FOUNDATION
50
9. THE FINAL PILING DESIGN IS TO BE SUBMITTED BY THE PILING CONTRACTOR TO THE
APPOINTED GEOTECHNICAL ENGINEER FOR APPROVAL. THE COST FOR THIS APPROVAL 450 250 STRUCTURAL LAYOUT & DETAILS
PROCESS IS TO BE PROVIDED FOR BY THE PILING CONTRACTOR. THE PILING CONTRACTOR 450 Ø pile
700
CAN ONLY COMMENCE WITH PILING, PENDING THE APPROVAL OF THE FINAL PILE DESIGN
350 350
FROM THE APPOINTED GEOTECHNICAL ENGINEER AND THE APPROVAL FROM THE
PRINCIPAL STRUCTURAL ENGINEER.
10. THE MAXIMUM PERMISSIBLE DEVIATION OF THE PILE POSITIONS SHALL BE 50mm.
225 225
11. ALL PILES ARE TO BE NEATLY TRIMMED TO PILE CUT-OFF LEVEL. THE TOP SURFACE OF ALL
TRIMMED PILES IS TO BE FINISHED 'LEVEL AND SMOOTH'. AN APPROVED NON-SHRINK
LEVELING CONCRETE GROUT MUST BE ALLOWED FOR THE BY CONTRACTOR TO ACHIEVE SECTION A - A
SUITE 106, ESSENVIEW BUILDING, STRATHMORE PARK,
THE 'LEVEL AND SMOOTH' FINISH REQUIREMENT NOTED ABOVE.
305 MUSGRAVE ROAD, DURBAN, 4001
e-mail : admin@mapafrica.co.za
12. TWO COPIES OF AN 'AS-BUILT' LOCATION DRAWING SIGNED BY THE PILING CONTRACTOR
FAX (031) 3092929 TEL. (031) 3095831
SHOWING THE PRECISE POSITION OF EVERY PILE SHALL BE SUPPLIED TO THE PRINCIPAL
STRUCTURAL ENGINEER. ANY PILE OUTSIDE THE TOLERANCE LIMITS SPECIFIED SHALL BE
CLEARLY HIGHLIGHTED ON THE 'AS-BUILT' LAYOUT. DESIGNED K.L. SCALES
COPYRIGHT RESERVED
DRAWN K.L. 1:50 1:25
APPROVED M.N. PL DATE 29/01/2020
500mm
step up
h See t.o.c. @ specifications.
to A r c lvl.
Paving + 1 3 4 9 ,3 3 0 Detail 'A' +1349,680 lvl fall AS INDICATED ON DRAWING
150
200 150
150
150
150
ving @
G t.o . p a G
150
6. ALL FOUNDATION EXCAVATIONS TO BE INSPECTED BY
sawcut joint
500
t.o. paving @
595
595
595
I.D.T. t.o.c. @ t.o.c. @ t.o.c. @ THE ENGINEER PRIOR TO CASTING OF CONCRETE.
445
445
+1349,330 lvl
sawcut joint
245
+1349,235 lvl +1349,235 lvl +1349,235 lvl 7. ALL REINFORCING FIXING TO BE INSPECTED BY
3500
See
THE ENGINEER PRIOR TO CASTING OF CONCRETE.
500mm x 220mm r.c. Detail 'A' 500mm x 220mm r.c.
240 220 240 100 220 380 8. SIX CUBES TO BE TAKEN PER POUR.
sawcut joint
column above & below. column above & below.
120 340 240 THREE TO BE TESTED AT SEVEN DAYS, THE
2515 REMAINDER AT TWENTY EIGHT DAYS. THE RESULTS
800mm deep x 700mm wide
800
800
800
500mm x 220mm r.c. TO BE FORWARDED TO THE ENGINEER.
column above & below. r.c. ground beam.
9. CONTRACTOR TO CONSTRUCT A BLINDING LAYER
All 110mm wide single skin walls 150mm thk. x 30MPa powerfloated concrete
IF SOIL CONDITIONS RESULT IN REINFORCEMENT
are to be constructed directly surface bed reinforced with mesh ref. 193
sawcut joint COVER NOT BEING MAINTAINED.
onto the top of the surface bed (min. 300mm laps) placed at 45mm cover from
top on 250µm SABS approved DPM on 10. ALL STRUCTURAL CONCRETE TO BE CURED FOR
slab (typical).
800mm deep x 700mm wide 800mm deep x 700mm wide A MINIMUM OF FIVE DAYS.
2 engineered layerworks as per Civil Engineers layouts. 700
r.c. ground beam.
700 565 700
r.c. ground beam. 11. BRICKWORK SHOWN HATCHED ARE LOAD BEARING.
Soil to be poisoned in accordance with SABS 1165.
See Certificate must be provided. T.o.c. @ +1349,830 lvl. ALL LOAD BEARING BRICKWORK TO BE 14MPa NFX.
450mm Ø pile 450mm Ø
150mm thk. x 30MPa powerfloated concrete Detail 'A' TOP OF ALL BRICKWORK TO RECEIVE 2 LAYERS OF
surface bed reinforced with mesh ref. 193 pile. 3 PLY MALTHOID ON SMOOTH RENDERED SURFACE.
(min. 300mm laps) placed at 45mm cover from 10mm wide Isolation Joint 12. ALL SINGLE SKIN BRICKWORK TO BE STOPPED 2
3500
top on 250µm SABS approved DPM on between new surface bed COURSES BELOW SOFFIT OF SLAB AND COMPLETED
ils.
ects deta
500mm
step up
engineered layerworks as per Civil Engineers layouts. it 2645 and existing surface bed. AFTER PROPS HAVE BEEN REMOVED.
Soil to be poisoned in accordance with SABS 1165. Paving
to A
g
r
@
c h
+1349,3
30 lvl.
All 110mm wide single skin walls See typical Isolation Joint detail. SECTION 1 - 1 SECTION 2 - 2 13. ALL CONCRETE PLASTER AND BRICKWORK PLASTER
t.o. pa v in
Certificate must be provided. T.o.c. @ +1349,830 lvl. are to be constructed directly 500mm x 220mm r.c. INTER-FACES TO RECEIVE V-JOINTS.
onto the top of the surface bed column above & below.
14. THE ENGINEER REQUIRES 24HRS NOTICE FOR ALL
I.D.T. slab (typical). INSPECTIONS.
250
250
Existing brickwork
are to be constructed directly 500mm x 220mm r.c. 'Dow Corning 813C' silicone
onto the top of the surface bed sealant (or equally approved)
column above & below.
slab (typical). on 10mm wide polystyrene backing. 10
150mm
step up
sawcut joint
2515 250
700mm x 220mm r.c.
sawcut joint
200mm thk. x 30MPa powerfloated concrete surface bed
1490
1500
mesh rebar
sawcut joint
column above & below. reinforced with 2 layers of mesh ref. 245 (min. 300mm laps)
150mm mesh rebar t.o.c. @ mesh rebar t.o.c. @
See placed at 60mm cover from top and 30mm cover from the
See step up 170mm fall +1349,830 lvl +1349,830 lvl
Detail 'B' bottom on 250µm SABS approved DPM on engineered
Detail 'B' E.D.T.
45
45
45
layerworks as per Civil Engineers layouts.
1170mm x 220mm r.c.
10
150
150
150
Top mesh will be sitting on R10 stools (90mm high)
wall above & below.
t.o.c. @ +1349,830 lvl @ 800mm c/c and each leg of the stool will be supported
J 350mm x 350mm
J on B1 bar of the bottom mesh.
edge thickening. 950mm x 220mm r.c. Soil to be poisoned in accordance with SABS 1165.
500
DPM DPM
wall above & below. 1 Certificate must be provided. T.o.c. @ +1349,680 lvl.
595
See detail.
K K Paving to
foundation Architects details
2755 t.o. paving @
cavity brickwork and specifications.
+1349,330 lvl
150mm thk. x 30MPa powerfloated concrete 3870mm x 220mm r.c. foundation
t.o.c @
walkway slab (to fall) reinforced with mesh ref. 193 brickwork
wall above & below. +1349,235 lvl
sawcut joint
170mm
170mm
170mm
fall
fall
engineered layerworks as per Civil Engineers layouts. 800mm deep x 700mm wide
Soil to be poisoned in accordance with SABS 1165. r.c. ground beam.
Certificate must be provided.
t.o.c. @ +1349,660 lvl
Existing brickwork
500mm x 220mm r.c.
column above & below. 350mm x 350mm INTERNAL DOOR THRESHOLD (I.D.T.)
edge thickening.
1 2 See detail. 3
Existing brickwork
SURFACE BED SLAB
45
45
BED
150
150
8 10 12 16 20 25 32 40 TOT
Note : Brickwork Strapping :
350
R 7 7 All brickwork to be 'strapped/tied' to r.c. columns,
Y shear walls and other concrete vertical elements with DPM
200
REV DESCRIPTION BY DATE
TOT 7 7 30mm wide x 1,2mm thk. x 800mm long galvanised steel DPM
Load bearing
straps. 100mm of steel strap shot fired to column and
50
brick wall /
700mm of steel strap built into brick wall every 3rd course.
r.c. column /
Each brick skin (at every 3rd course) to be tied to r.c. 50 r.c. shear wall.
columns, shear walls and other concrete vertical elements.
100 350
TYPICAL ISOLATION T1 FOR TENDER PURPOSES S.A. 24/06/2020
BRICKWORK NOTES :
- All brickwork (solid brick walls or cavity brick walls) below surface bed level 350mm x 350mm JOINT DETAIL (I.J.) professional person M.NAIR PrTechEng registration 200670211
PROJECT
30mm wide x 1,2mm thk. 8mm wide x 13mm deep
30mm wide x 1,2mm thk. galvanised steel strap
strap fixed to connecting 3mm wide x 40mm deep sawcut joint
'Dow Corning 813C' silicone sealant UMALUSI OFFICES
strap fixed to connecting wall with 'Hilti' drive pin reamed out to 8mm wide.
galvanised steel strap
built into brickwork every
10 joint
wall with 'Hilti' drive pin
built into brickwork every 10 joint
(or equally approved)
(or equally approved). ADDITIONS AND ALTERATIONS
10mm deep x 10mm wide 3rd course.
(or equally approved) shot fired into wall.
3rd course. Ø10mm backing
'Dow Corning 813C' silicone 340 8
shot fired into wall. cord. mesh rebar DETAILS
sealant (or equally approved)
applied to both sides of wall. 700 220 10mm deep x 10mm wide 700 110 120 110 NEW ABLUTIONS BUILDING
'Dow Corning 813C' silicone
40
45
sealant (or equally approved) GROUND FLOOR
150
75 75
applied to both sides of wall.
external wall
100
100
external wall
40
40
internal wall
30
DPM STRUCTURAL LAYOUT & DETAILS
110
110
30
30
220mm INTERNAL WALL CONNECTION DETAIL 340mm EXTERNAL CAVITY WALL CONNECTION DETAIL DESIGNED Y.R. SCALES
COPYRIGHT RESERVED
DRAWN Y.R. 1:50 1:25 1:10
110
110
10
THE ENGINEER PRIOR TO CASTING OF CONCRETE.
F F F F
220 280 Existing 220 280 280 220 8. SIX CUBES TO BE TAKEN PER POUR.
10
o/a concrete
500mm x 220mm 500mm x 220mm VOID la b
1180
830
830
Line of Existing Building
Building t f l o or s Line of Existing Building THREE TO BE TESTED AT SEVEN DAYS, THE
1180
1180
r.c. col. below. Line of Existing Building r.c. col. below. .c . f i r s
1070
1070
830
.
t h k . r 5 2 ,8 0 5 lv l
350
m REMAINDER AT TWENTY EIGHT DAYS. THE RESULTS
m
G G Line of existing building. G 25 5
@+1
3 G TO BE FORWARDED TO THE ENGINEER.
220
t.o .c .
350
350
10 350
350
220
100
10
10
10
10
10
10
10
9. CONTRACTOR TO CONSTRUCT A BLINDING LAYER
220
80
220
765mm deep x 220mm wide r.c. upstand beam
765mm deep x 220mm wide
10 960 10 r.c. col. above and below. 10. ALL STRUCTURAL CONCRETE TO BE CURED FOR
t.o.c. @ + 1356,630 lvl.
existing and new building. r.c. col. above and below. existing and new building. 11. BRICKWORK SHOWN HATCHED ARE LOAD BEARING.
t.o.c. @ +1357,310 lvl 500mm x 220mm o/a conc.
10 220 See Isolation Joint Note. (Typical). ALL LOAD BEARING BRICKWORK TO BE 14MPa NFX.
See Isolation Joint Note. (Typical).
r.c. col. above and below.
1000
5745
5745
5745
5745
220mm x 220mm Building to approved by the structural engineer COURSES BELOW SOFFIT OF SLAB AND COMPLETED
.c . 6 , 1 2 p r o ta i l
220
4915
4915
4915
r.c. col. above. r
. 5 r e prior to casting r.c. slab. 10 220 AFTER PROPS HAVE BEEN REMOVED.
thk 13 wate t's d ).
&
(or equally approved) on all exposed edges on 10mm wide polystyrene backing.
10380
r.c. d/stand beam r.c. d/stand beam 510mm deep x 220mm wide r.c. d/stand beam 510mm deep x 220mm wide r.c. d/stand beam r.c. col. above and below.
10550
9900
250
250
250
500
500
220
220
220
250
220
220
1430
275
t.o.c. @ + 1356,120 lvl. t.o.c. @ + 1356,120 lvl. t.o.c. @ + 1352,805 lvl. t.o.c. @ + 1352,805 lvl.
30
Note : Brickwork Strapping :
500
500
500
500
Gx Gx Gx Gx
280
280
345
30
765mm deep x 220mm wide r.c. upstand beam 30
30
30
500mm x 220mm 500mm x 220mm 500mm x 220mm 500mm x 220mm
10680
10680
10680
10550
r.c. col. below. r.c. col. below. shear walls and other concrete vertical elements with
250
250
r.c. col. above and below. r.c. col. above and below.
280
250
250
500
14320
570
2025
500mm x 220mm
straps. 100mm of steel strap shot fired to column and 10 220
r.c. col. above and below. b 500
700mm of steel strap built into brick wall every 3rd course. s la
130
o
1000
30 220 Each brick skin (at every 3rd course) to be tied to r.c.
t f lo l v l .
220mm x 220mm (Typical). Flashing between the new r.c. upstand beams .r c. 52,
. 3
3745
3745
3745
220
4635
4635
4635
4635
t.o.c. @ +1357,310 lvl to Architect's details & specifications. r.c. d/stand beam
25 t.o.
220
10 1015 o/a
t.o.c. @ + 1352,805 lvl.
1170mm x 220mm wide 700 existing building Void for Lift
350 350
r.c. shear wall above and below.
B 10mm wide isolation joint between C Line of Existing Building
1800
350 350 700mm x 220mm 1170mm x 220mm wide existing and new building. 700
1500
t.o.c. @ +1357,310 lvl
r.c. col. below. See Isolation Joint Note. (Typical).
1000
275 r.c. shear wall below. 510mm deep x 220mm wide 220 480
510mm deep x 220mm wide r.c. d/stand beam 510mm deep x 220mm wide r.c. d/stand beam r.c. d/stand beam 700mm x 220mm 10mm wide isolation joint between
220
220
765mm deep x 220mm wide
220
220
220
t.o.c. @ + 1356,120 lvl. t.o.c. @ + 1356,120 lvl. t.o.c. @ + 1352,805 lvl. r.c. col. above and below.
r.c. upstand beam Outside face of See Isolation Joint Note. (Typical).
80
1170
520
t.o.c. @ + 1356,630 lvl. new brickwork pier.
1170
640
220
120
220mm x 220mm
1170
220mm x 220mm
1170
1170
310 420
420
950
950
730
10
950mm x 220mm wide
1070
r.c. col. above. r.c. col. above. 1170mm x 220mm wide
J J J J
730
950
r.c. shear wall below. r.c. shear wall above and below.
210
650
t.o.c. @ +1357,310 lvl t.o.c. @ +1357,310 lvl
C
530
650
650
10 1015
830
830
830
830
3650
950mm x 220mm wide Steel support angle for brickwork.
120
300
300
220
r.c. shear wall above and below. See detail and Section C - C and Section D - D.
220
K K K 240 240 K
120
120
220mm x 220mm
180
765mm deep x 220mm wide
180
3870
r.c. upstand beam r.c. upstand beam r.c. col. above. Steel support angle for brickwork. 220 5050 220 2880 220 1500 220
Outside face of Steel support angle for brickwork. Outside face of new
t.o.c. @ + 1356,630 lvl. t.o.c. @ +1357,310 lvl t.o.c. @ + 1356,630 lvl. t.o.c. @ +1357,310 lvl
3650
See detail and Section C - C
2200
700
2400
220 2535 220 2535 220 2310 220 2310 220 795 220 Line of Existing Building
2580
230
11805 10
Line of entrance canopy r.c. slab above.
5400 5400 10mm wide isolation joint between BRICKWORK NOTES :
500
existing and new building. - All brickwork (solid brick walls or cavity brick walls) below surface bed level
See Isolation Joint Note. (Typical). to have brickforce in every course. 500mm x 220mm
- All solid brick walls above surface bed level are 220mm wide or 110mm wide r.c. col. above and below.
1 2 3 with brickforce built in every 3rd course. 130
Line of Existing Building
- All parapet walls are 220mm wide or 110mm wide with brickforce built in 220 5080 220 1025
every course. 5520 230
ROOF SLAB PLAN - All cavity brick walls above surface bed level are 340mm wide with 110mm
wide outer skin brickwork with 120mm central cavity with 3,15mm Ø x 300mm
350
long galvanised butterfly wire ties built vertically into brickwork every 3rd
course and horizontally at max. 500mm centres above surface bed level
340 340 and built vertically into brickwork in every course below surface bed level and
1 2 3
horizontally at max. 500mm centres.
+ 1357,310 lvl. + 1357,310 lvl. - All brickwork to Architect's detail in Class 2 mortar.
230mm wide parapet wall.
230
230mm wide parapet wall.
230
FIRST FLOOR SLAB PLAN
110 120 110 120
r.c. column behind. r.c. column behind.
680
680
110 110 CL CL CL
75mm Ø rainwater
t.o.c. @ + 1356,630 lvl. overflow pipe. t.o.c. @ + 1356,630 lvl. anchor anchor anchor
765mm deep x 220mm wide 765mm deep x 220mm wide
Screed to falls to Architect's r.c. upstand beam. Brickwork to be 'strapped/tied' to r.c. beam with Screed to falls to Architect's r.c. upstand beam. Brickwork to be 'strapped/tied' to r.c. beam with 500 500 500 500
specification and details. 30 30mm wide x 1,2mm thk. x 200mm long galvanised specification and details. 30mm wide x 1,2mm thk. x 200mm long galvanised centres 100 centres All structural steel angles and flats
1445
1445
t.o.c. @ t.o.c. @
510
510
typical typical
75
765
+ 1356,120 lvl. steel straps. 100mm of steel strap shot fired to r.c. beam + 1356,120 lvl. steel straps. 100mm of steel strap shot fired to r.c. beam
50
100
100
100
55
50
50
roof slab. and 100mm of steel strap built into brick wall every and 100mm of steel strap built into brick wall every galvanised to ISO 1461 or EN 10240.
roof slab.
2nd course @ 750mm centres. 2nd course @ 750mm centres.
255
255
255
CL CL
200
200
150
150
50
50
150
200
100
100
100
255
SECTION A - A 340
SUPPORT ANGLE DETAIL 950mm x 220mm wide
240
510mm deep x 220mm wide r.c. upstand beam
existing and new building.
220
220
r.c. shear wall above and below. See Isolation Joint Note. (Typical).
t.o.c. @ + 1354,335 lvl.
SECTION B - B
220
640
700mm x 220mm b
640
y s la
r.c. col. above and below. p l.
J no J
950
,
460 . c a 8 0 lv f in g
1170
1170
340 c o
950
. , 0
M20 CHEMICAL ANCHOR SPECIFICATION : 240 220 .r 4 p ro ils
120
th k + 1 3 5 a te r d e ta
830
830
110 120 110 Fischer M20 (8.8) galvanised H.D. Anchor Studs m w c t 's .
M20 CHEMICAL ANCHOR SPECIFICATION : 5m @ s, C
2 5 . o . c . o f a l l c h it e i o n s )
220
340mm wide cavity wall.
(with embedment length = 200mm) with Fischer
FIS-V-360 Chemical Mortar or equally approved Fischer M20 (8.8) galvanised H.D. Anchor Studs K t dt
e e t
r
o A c if ic a
t K CLIENT
r s
Screed to falls to Architect's (S c F B O d s p e
3430
3870
3870
Chemical Anchors with 'ETA' ( European Technical (with embedment length = 200mm) with Fischer
t.o.c. @ + 1354,335 lvl. specification and details. FIS-V-360 Chemical Mortar or equally approved 510mm deep x 220mm wide
& an
Approval).
2200
t.o.c. @ 220 240
2480
Chemical Anchors with 'ETA' ( European Technical r.c. downstand beam.
1860
255mm thk. r.c. canopy slab.
2700
3870mm x 220mm wide
255
2580
+ 1354,080 lvl. Screed to falls to Architect's t.o.c. @
2400
2400
Approval). 255mm thk. r.c. canopy slab. 460
r.c. shear wall below.
510
255
280
510mm deep x 220mm wide r.c. col below UMALUSI OFFICES
500
340mm wide cavity wall.
r.c. upstand beam. 340
ADDITIONS AND ALTERATIONS
220
220
220
110 120 110 340mm wide cavity wall. 220mm wide 510mm deep x 220mm wide
r.c. shear wall. 130 Line of Existing Building
r.c. downstand beam. DETAILS
220 120
220 120
220 5080 220
NEW ABLUTIONS BUILDING
255mm thk. r.c. first floor slab t.o.c. @
1530
255
CL
55
200
100
50
510
F
255
255
CL 2 3
200
50
150
100
255
255
510
50
150
100
255
255
See chemical anchor specification. 110 120 110 340 Brickwork Steel Support Angle :
510
100x100x10L welded to
255
220
6260
surface bed.
10. ALL STRUCTURAL CONCRETE TO BE CURED FOR
A MINIMUM OF FIVE DAYS.
10mm thk. polystyrene
300 10 11. BRICKWORK SHOWN HATCHED ARE LOAD BEARING.
New brick wall spacer strip
ALL LOAD BEARING BRICKWORK TO BE 14MPa NFX.
PLAN. strap fixed to connecting TOP OF ALL BRICKWORK TO RECEIVE 2 LAYERS OF
wall with 'Hilti' drive pin 3 PLY MALTHOID ON SMOOTH RENDERED SURFACE.
concertina ties : (or equally approved) 12. ALL SINGLE SKIN BRICKWORK TO BE STOPPED 2
30mm wide x 1,2mm thk. shot fired into wall. COURSES BELOW SOFFIT OF SLAB AND COMPLETED
See Detail 'B' for brickwork galvanised steel strap AFTER PROPS HAVE BEEN REMOVED.
strapping to r.c. column. built into brickwork every
13. ALL CONCRETE PLASTER AND BRICKWORK PLASTER
3rd course.
150
INTER-FACES TO RECEIVE V-JOINTS.
14. THE ENGINEER REQUIRES 24HRS NOTICE FOR ALL
Existing r.c. Existing r.c. Existing r.c.
D column column column 300
INSPECTIONS.
be d
ce
su rf a See Detail 'B' for brickwork new brick wall Existing r.c. column
ng New 220mm wide brickwork
ti
E x is to be constructed on existing strapping to r.c. column.
surface bed. ELEVATION
Existing brick wall.
DETAIL 'A'
BRICKWORK STRAPPING TO
New 220mm wide brickwork to
Existing brick wall.
Existing brick wall. EXISTING R.C. COLUMN
existing 220mm wide brickwork REV DESCRIPTION BY DATE
connection. See Detail 'C'.
Existing
r.c. column. Strap fixed to connecting r.c. CLIENT
220
PROJECT
10mm deep x 10mm wide
'Dow Corning 813C' silicone
New brick wall.
700 10 10mm wide polystyrene
sealant (or equally approved) 700 230
UMALUSI OFFICES
spacer strip.
ADDITIONS AND ALTERATIONS
100
30mm wide x 1,2mm thk. Varies column with 'Hilti' drive pin
30
DETAILS
galvanised steel strap built (or equally approved)
EXISTING MAIN BUILDING
230
into brickwork every 3rd course. shot fired into r.c. column.
30
40
3730
3820
7. ALL REINFORCING FIXING TO BE INSPECTED BY
THE ENGINEER PRIOR TO CASTING OF CONCRETE.
A A 8. SIX CUBES TO BE TAKEN PER POUR.
EXISTING FIRST FLOOR SLAB
THREE TO BE TESTED AT SEVEN DAYS, THE
3360 o/a steel angle
3015 o/a steel angle REMAINDER AT TWENTY EIGHT DAYS. THE RESULTS
180 500 500 500 500 500 500 180 TO BE FORWARDED TO THE ENGINEER.
200 500 500 500 500 500 315 M20 chemical anchors @ 500mm centres as shown. 9. CONTRACTOR TO CONSTRUCT A BLINDING LAYER
M20 chemical anchors @ 500mm centres as shown.
185
IF SOIL CONDITIONS RESULT IN REINFORCEMENT
I.J.
See chemical anchor specification. (Typical)
10
140
I.J.
500
500
a Slab Infilll Steel Support Angle : a
ll p
i ll p
i
A MINIMUM OF FIVE DAYS.
in f 100x100x10L welded to A in f
500
a
500
Slab Infilll Steel Support Angle : sl s 100x100x10mm thk. flat with
100x100x10L welded to r .c. n gle 6mm full penetration bevel weld .r c. ngle ALL LOAD BEARING BRICKWORK TO BE 14MPa NFX.
) a a) el a TOP OF ALL BRICKWORK TO RECEIVE 2 LAYERS OF
P a te e l
10380
10380
P
2870
500
2780
100x100x10mm thk. flat with fixed to the side of the existing r.c. slab M te
500
M
25 s (2 5 o n s 3 PLY MALTHOID ON SMOOTH RENDERED SURFACE.
6mm full penetration bevel weld k . ( d on with M20 chemical anchors. .
th k rte d
t h te 12. ALL SINGLE SKIN BRICKWORK TO BE STOPPED 2
m p or m
500
fixed to the side of the existing r.c. slab See chemical anchor specification. o
500
m A A 5m u pp A A COURSES BELOW SOFFIT OF SLAB AND COMPLETED
with M20 chemical anchors. 2 5 5 su
p
A Soffit of steel angle @ +1352,550 lvl. w
2 5 s A AFTER PROPS HAVE BEEN REMOVED.
ew Ne
500
See chemical anchor specification. (Typical).
500
N
Soffit of steel angle @ +1352,550 lvl. 13. ALL CONCRETE PLASTER AND BRICKWORK PLASTER
INTER-FACES TO RECEIVE V-JOINTS.
(Typical).
I.J.
I.J.
10
10
14. THE ENGINEER REQUIRES 24HRS NOTICE FOR ALL
185
140 INSPECTIONS.
200 500 500 500 500 500 315
3005 o/a concrete slab 10
180 500 500 500 500 500 500 180
3015 o/a steel angle I.J. 2510
3350 o/a concrete slab 10
EXISTING FIRST FLOOR SLAB I.J.
3360 o/a steel angle 2040
3780
3780
125 5400 5400
A A
REV DESCRIPTION BY DATE
O O J J
3 4
9 10 T1 FOR TENDER PURPOSES S.A. 24/06/2020
R.C. SLAB INFILL PANEL ON EXISTING FIRST FLOOR R.C. SLAB INFILL PANEL ON EXISTING FIRST FLOOR
CL CL CL
anchor anchor anchor
PROJECT
500 500 500 500 10mm deep x 10mm wide
centres centres 'Dow Corning 813C' silicone UMALUSI OFFICES
typical typical
All structural steel angles and flats New 255mm thk. (25MPa)
sealant (or equally approved) ADDITIONS AND ALTERATIONS
on 10mm thk. polystyrene backing.
100 to be grade S355JR hot-dipped r.c. slab infill panel
First floor t.o.c. Existing first floor slab. galvanised to ISO 1461 or EN 10240. supported on steel angles. First floor t.o.c. Existing first floor slab.
50 50 DETAILS
@ + 1352,805 lvl. @ + 1352,805 lvl.
EXISTING MAIN BUILDING
55
55
NEW R.C. SLAB IN-FILL PANELS
50 50
100
100
CL CL
ON THE EXISTING FIRST FLOOR SLAB
255
255
50
200
255
150
200
150
100
Slab Infill Steel Support Angle : 100x100x10mm thk. flat fixed to the side of the
100x100x10L welded to existing r.c. slab with 1 No. M20 chemical anchor. Slab Infilll Steel Support Angle : 100x100x10mm thk. flat fixed to the side of
100x100x10mm thk. flat with 100x100x10L welded to r.c. slab with 1 No. M20 chemical anchor.
6mm full penetration bevel weld.
Soffit of steel angle @ +1352,550 lvl.
TYPICAL ELEVATION See chemical anchor specification.
100x100x10mm thk. flat with See chemical anchor specification.
6mm full penetration bevel weld
R.C. SLAB INFILL PANEL fixed to the side of the existing r.c. slab
with M20 chemical anchors.
SUITE 106, ESSENVIEW BUILDING, STRATHMORE PARK,
50
5 ALL BOLTS TO BE GRADE 8.8 BOLTS AND TO BE UB rafter.
HOT DIPPED GALVANISED TO SANS 121:2011 (ISO 1461:2009(E)). e) RETAINING WALLS = 25 MPa
Existing face brickwork to be
200
6. ALL COMMERCIAL QUALITY H.D. BOLTS, PURLINS AND GIRTS Existing r.c. column f) SURFACE BEDS = 30 MPa
carefully removed and replaced g) BLINDING = 10 MPa
TO HAVE A MIN. GRADE STRESS OF 200 MPa.
300
400
after CHS tube tie end plate is CL
7. ALL STRUCTURAL STEELWORK, H.D BOLTS, NUTS installed. 5. COVER TO REINFORCEMENT :-
200
UB rafter
AND WASHERS TO BE HOT DIPPED GALVANISED 0,55mm thk. 'Klip-Tite Zincal / Colorplus AZ150' 16mm thk. plate cleat 31 8 AS INDICATED ON DRAWING
TO SANS 121:2011 (ISO 1461:2009 (E)). ALL STRUCTURAL roof sheeting at 2° pitch. Colour of sheeting with 1 No. 28mm Ø hole 240
50
STEEL TUBES ARE TO BE HOT-DIPPED GALVANISED TO to Architects specification. for M24 bolt. 6. ALL FOUNDATION EXCAVATIONS TO BE INSPECTED BY
SANS 32 / EN 10240. 220x400x20mm thk. end plate Existing THE ENGINEER PRIOR TO CASTING OF CONCRETE.
130x16mm thk. plate cleat
GALVANISING CERTIFICATE FOR ALL STEELWORK IS TO slot welded to tube tie with See CHS tube tie with 2 No. M24 chemical anchors. r.c. column. 7. ALL REINFORCING FIXING TO BE INSPECTED BY
BE SUBMITTED TO THE ENGINEER ON COMPLETION. 1 No. 28mm Ø hole for M24 bolt. End Plate Detail '2'. See chemical anchor specification. s.o.p THE ENGINEER PRIOR TO CASTING OF CONCRETE.
8. IF THE GALVANISING IS DAMAGED OR SCRATCHED DURING 130x16mm thk. plate cleat 220 8. SIX CUBES TO BE TAKEN PER POUR.
THE INSTALLATION PROCESS, IT MUST BE 'TOUCHED UP' WITH slot welded to tube tie with THREE TO BE TESTED AT SEVEN DAYS, THE
1 No. 28mm Ø hole for M24 bolt. e t ie 240
'PLASCON PLASCOZINC POLY GALV PRIMER' OR EQUALLY
. CH S tu b REMAINDER AT TWENTY EIGHT DAYS. THE RESULTS
APPROVED. ,5 m m th k radius = 65mm UB Rafter TO BE FORWARDED TO THE ENGINEER.
x4 Flashing to
9. 2 SETS OF FABRICATION SHOP DRAWINGS (HARDCOPIES) ARE 115 mm Ø
TO BE DELIVERED TO THE ENGINEER'S OFFICES FOR REVIEW AND
315 290 Architects details END PLATE DETAIL '1' 9. CONTRACTOR TO CONSTRUCT A BLINDING LAYER
Flashing to and specifications. IF SOIL CONDITIONS RESULT IN REINFORCEMENT
APPROVAL BEFORE COMMENCING WITH ANY FABRICATION. Architects details COVER NOT BEING MAINTAINED.
radius = 65mm and specifications.
13 0
NOTE : EMAIL SUBMISSION OF ELECTRONIC (PDF) COPIES OF SHOP 10. ALL STRUCTURAL CONCRETE TO BE CURED FOR
13.0°
DRAWINGS WILL NOT BE ACCEPTED. See Purlin to Brickwork CL A MINIMUM OF FIVE DAYS.
2° fall
10. CERTIFICATES CONFIRMING THE GRADE STRESS OF ALL End Plate Detail '3'.
existing 11. BRICKWORK SHOWN HATCHED ARE LOAD BEARING.
STEELWORK, PURLINS, GIRTS, H.D BOLTS AND BOLTS SPECIFIED r.c. column ALL LOAD BEARING BRICKWORK TO BE 14MPa NFX.
IS TO BE SUBMITTED TO THE ENGINEER ON COMPLETION. TOP OF ALL BRICKWORK TO RECEIVE 2 LAYERS OF
150
310
11. THE STRUCTURAL STEELWORK CONTRACTOR IS TO 220 3 PLY MALTHOID ON SMOOTH RENDERED SURFACE.
50 s lo t See UB rafter
VERIFY ALL SETTING OUT DIMENSIONS ON SITE
End Plate Detail '1'. 12. ALL SINGLE SKIN BRICKWORK TO BE STOPPED 2
PRIOR TO FABRICATION. 203x133x25 UB rafter COURSES BELOW SOFFIT OF SLAB AND COMPLETED
240x100x8mm thk.
plate stiffners. AFTER PROPS HAVE BEEN REMOVED.
600 13. ALL CONCRETE PLASTER AND BRICKWORK PLASTER
50
16mm thk. plate cleat welded Existing face brickwork to be INTER-FACES TO RECEIVE V-JOINTS.
555 300 to UB rafter with 1 No. carefully removed and replaced s.o.p
50
28mm Ø hole for M24 bolt. after UB rafter end plate is installed. 14. THE ENGINEER REQUIRES 24HRS NOTICE FOR ALL
M24 CHEMICAL ANCHOR SPECIFICATION :
100
INSPECTIONS.
Fischer M24 (8.8) galvanised H.D. Anchor Studs 235 16mm thk. plate cleat
950
(with embedment length = 350mm) with Fischer 1600 with 1 No. 28mm Ø hole
410
210
310
410
1600 for M24 bolt.
FIS-V-360 Chemical Mortar or equally approved 200
Chemical Anchors with 'ETA' ( European Technical
100
4585
Approval).
50
410x220x20mm thk. Existing
M12 CHEMICAL ANCHOR SPECIFICATION : end plate with 2 No. r.c. column.
150 M24 chemical anchors.
Fischer M12 (8.8) galvanised H.D. Anchor Studs Existing r.c. column
See chemical anchor 240x100x8mm thk.
(with embedment length = 220mm) with Fischer 35 80 35 110 110 REV DESCRIPTION BY DATE
Existing specification. plate stiffners.
FIS-V-360 Chemical Mortar or equally approved Face of existing
typical purlin cleat brick wall. 220
55 90 40
Chemical Anchors with 'ETA' ( European Technical r.c. column.
welded to rafter
185
Approval). 150x185x10mm thk.
plate with 4 No. M12 bolts. CHS Tube Tie
END PLATE DETAIL '2'
3230
203x133x25 UB rafter T1 FOR TENDER PURPOSES S.A. 24/06/2020
220
Face of existing 70
2 3 4 r.c. column. 70 40 30
30
38
11490
CLIENT
210
100
175
150
345 5400 5400 345
37
rafter bracing:
30
100x100x8L fixed to10mm thk. plate 30 145 30
gussets welded to rafter web A 4 rows 175x75x20x2,5mm thk.
CRLC purlins.
with 2 No. M20 bolts each end. 205 210x205x10mm thk. end plate
with 4 No. M12 chemical anchors
existing concrete thru' brickwork cladding, into existing
concrete. See chemical anchor specification. PROJECT
surface bed
@ +1349,830 lvl
PURLIN TO BRICKWORK UMALUSI OFFICES
Existing paving
Existing paving END PLATE DETAIL '3' ADDITIONS AND ALTERATIONS
50x50x3L false rafter
203x133x25 UB rafter
203x133x25 UB rafter
203x133x25 UB rafter
DETAILS
See End Plate Detail '1' sag angles: 50x50x3L with EXISTING MAIN BUILDING
& End Plate Detail '2'. end cleats:50x50x3L with
2 No. M12 bolts for each NEW STRUCTURAL STEEL CANOPY
See End Plate Detail '1' cleat (typical).
& End Plate Detail '2'. See End Plate See End Plate Detail '1'
STRUCTURAL DETAILS
See End Plate See End Plate
220
220
Detail '3'.
A A
See End Plate
SECTION A - A
130
130
130
1290
1290
830
830
Detail '3'.
110
110
B B
220
110
110
220
110
t.o.c @ 'Vastrap' plate 'Vastrap' plate
345
1420 o/a 300mm centres. See chemical +1352,805 lvl. 2. THIS DRAWING TO BE READ IN CONJUNCTION WITH
'Vastrap' plate anchor specification. t.o. 'Vastrap' plate 500 235 110 t.o.c. floor finish
110
t.o.c. @ THE ARCHITECTURAL DRAWINGS.
10
220
1 1 @ +1352,805 lvl @ +1352,835 lvl +1352,805 lvl 3. ALL CONCRETE WORK TO COMPLY WITH SABS 1200G.
30
30
690
345
345
115
335
4. CONCRETE CLASS :-
110
CL
255
50x50x5L cleat a) PILECAPS & GROUND BEAMS = 25 MPa
80
'Vastrap' plate
b) STRIP FOOTINGS & BASES = 25 MPa
735 o/a
110
s.o.p End plate detail, CL End plate detail, as shown on CL CL c) COLUMNS, SHEAR & LIFT WALLS = 30 MPa
Existing as shown on Section B - B. 200 PFC stringer d) SLABS, BEAMS & STAIRCASES = 25 MPa
post post Hand / knee rail. post Existing first floor
500
500
r.c. column. CL Section B - B. 180 PFC beam See balustrade note. e) RETAINING WALLS = 25 MPa
Hand / knee rail. r.c. slab.
post 200 PFC post Remove existing face brickwork Stitch weld f) SURFACE BEDS = 30 MPa
See balustrade note. 200 PFC
200 PFC post 200 PFC stringer 200 PFC post carefully and re-construct 'Vastrap plate
Existing stringer. g) BLINDING = 10 MPa
brickwork after the 150x75x10L on site.
75
75
1910
20
weld plate to cleat under pattern
'Vastrap' plate
30
THE ENGINEER PRIOR TO CASTING OF CONCRETE.
30
'Vastrap' plate
1100 o/a
200 PFC stringer TYPICAL STEEL TREAD IF SOIL CONDITIONS RESULT IN REINFORCEMENT
75
Hand / knee rail. Hand / knee rail. COVER NOT BEING MAINTAINED.
200 PFC post 200 PFC post 200 PFC post
1180 110 See balustrade note. See balustrade note.
10. ALL STRUCTURAL CONCRETE TO BE CURED FOR
1125 2900 2300 100 1 Remove existing face brickwork A MINIMUM OF FIVE DAYS.
1290 75 200 345
CL CL CL 200 PFC stringer. carefully and re-construct 11. BRICKWORK SHOWN HATCHED ARE LOAD BEARING.
350 830 385 post post 130x150x10mm thk end plate 130 235 110 brickwork after the 180 PFC ALL LOAD BEARING BRICKWORK TO BE 14MPa NFX.
post
1565 A 280 with 4 No. M12 bolts.
30 70 30 810
end plate is installed. TOP OF ALL BRICKWORK TO RECEIVE 2 LAYERS OF
3 PLY MALTHOID ON SMOOTH RENDERED SURFACE.
CL PLAN ON STRUCTURAL STEEL STAIRCASE 400mm x 360mm x 40 200 40
40 70 40
12. ALL SINGLE SKIN BRICKWORK TO BE STOPPED 2
A B post 70
1200mm high r.c. plinth. 200 200
150
COURSES BELOW SOFFIT OF SLAB AND COMPLETED
60
120
75
40
82
75 200x75x12mm thk. end plate 30 40 'Vastrap' floor plate AFTER PROPS HAVE BEEN REMOVED.
37
200x75x12mm thk. end plates with 2 No. M20 bolts. 35 flush with top of stringer.
40 35 40 13. ALL CONCRETE PLASTER AND BRICKWORK PLASTER
240
160
360
75 500
75
with 2 No. M20 bolts. CL
INTER-FACES TO RECEIVE V-JOINTS.
38
post 180 PFC tie fixed Existing first floor
45 90 45 6
210
120
83
14. THE ENGINEER REQUIRES 24HRS NOTICE FOR ALL
40
flush with underside of r.c. slab.
55 90 55
55 90 55
55 90 55
60
'Vastrap' plate notch 30 150 30 INSPECTIONS.
200 PFC end beam 280x240x16mm thk. base plate
186
60 280 60
200
200
200
PFC tie to suit.
105
200 PFC post with 4 No. M20 chemical anchors.
200 PFC stringer 400 See chemical anchor specification.
180
CL 110 115 110
75
180x70x10mm thk. end plate 180 PFC cross-beam post 335 10 70
200 PFC stringer 200 PFC stringer
with 2 No. M20 bolts. top flush with u/s 'Vastrap' plate. SECTION B - B
STRINGER SPLICE DETAIL TYPICAL BASE PLATE 345
END BEAM TO STRINGER DETAIL 210x180x12mm thk.
CONNECTION DETAIL CROSS-BEAM TO STRINGER A B CL CL CL end plate with 2 No. M16
chemical anchors. See
CONNECTION DETAIL steel
post
steel
post
steel
post chemical anchor specification.
REV DESCRIPTION BY DATE
180 PFC beam 830 385 1125 2900 2300 CL
s.o.p. steel
500
1560 2250 850 1965 post
1525 1 1
537 345
345
35
landing
360 100
257
257
t.o. first floor finish 200 PFC T1 FOR TENDER PURPOSES S.A. 24/06/2020
1060 300 2000
280
280
280
280
beam
centre
@ +1352,835 lvl
plinth
line
typ.
CL
professional person M.NAIR PrTechEng registration 200670211
75
steel
200
200 PFC stringer post 100 400 400 100 300 400 300 300 400 300
typical
PROJECT MANAGER | PRINCIPAL AGENT
1175
1175
1175
1735
1175
1735
1175
815
1735
200 200 200 200
180 PFC beam
centre
plinth
360
typ.
75 100 200
line
BALUSTRADE NOTE : CL
280
280
280
50x50x5L cleats 'Mentis' Ball and Tube heavy duty steel
100
9 risers @ 180mm
shop welded to 'Vastrap' industrial hand rail / knee rail and posts post
280
100
85 1725 2100 1000 1300 1000
plate (or equally approved) (or equally approved). Fixed to top of
bolted to stringer/beam with stringers as per manufacturer's centre centre centre centre
1620
CL
20 specification and details (typical). line line line line
M12 bolts @ max. 250mm 0P post
FC 1735x1725x300mm deep
centres (typical). plinth plinth plinth plinth
st r r.c. base with 4 No. CLIENT
in g 350 830 385
er CL 400x360x1200mm high 1735x1000x300mm deep
1565 r.c. plinths. r.c. base with 2 No.
1130 35 steel
post 400x360x1200mm high
30 landing
A B FOUNDATION PLAN r.c. plinths.
780 35 2000
180 PFC t.o.c. r.c. bases @ +1348,375 lvl
STRUCTURAL STEEL NOTES :
3175
3175
200 PFC stringer beam.
3260
3260
CL t.o.c. r.c. plinths @ +1349,575 lvl
3035
8 risers @ 180mm
(or equally approved) bolted to 4. ALL PURLINS AND GIRTS TO BE COMMERCIAL GRADE AND TO BE
stringer with M12 bolts. Stringer 30 GALVANISED IN ACCORDANCE WITH SANS 4998 / ISO 4998:1996
splice. 100 100 20
1440
0P typ FOR 'STRUCTURAL QUALITY'.
FC M12 CHEMICAL ANCHOR SPECIFICATION : DETAILS
200 PFC post
er
200 PFC post
175
SANS 32 / EN 10240.
Fischer M16 (8.8) galvanised H.D. Anchor Studs
GALVANISING CERTIFICATE FOR ALL STEELWORK IS TO
85
grout
25
85
grout
85
25
grout
25
grout below base plate 9. 2 SETS OF FABRICATION SHOP DRAWINGS (HARDCOPIES) ARE M20 CHEMICAL ANCHOR SPECIFICATION : SUITE 106, ESSENVIEW BUILDING, STRATHMORE PARK,
(typical). TO BE DELIVERED TO THE ENGINEER'S OFFICES FOR REVIEW AND Fischer M20 (8.8) galvanised H.D. Anchor Studs 305 MUSGRAVE ROAD, DURBAN, 4001
APPROVAL BEFORE COMMENCING WITH ANY FABRICATION. (with embedment length = 300mm) with Fischer e-mail : admin@mapafrica.co.za
t.o.c. r.c. bases NOTE : EMAIL SUBMISSION OF ELECTRONIC (PDF) COPIES OF SHOP FIS-V-360 Chemical Mortar or equally approved
FAX (031) 3092929 TEL. (031) 3095831
400x360x1200mm high
@ +1348,375 lvl r.c. plinth (typical). DRAWINGS WILL NOT BE ACCEPTED. Chemical Anchors with 'ETA' ( European Technical
(typical) 10. CERTIFICATES CONFIRMING THE GRADE STRESS OF ALL Approval). DESIGNED S.M. SCALES
STEELWORK, PURLINS, GIRTS, H.D BOLTS AND BOLTS SPECIFIED COPYRIGHT RESERVED
Note : 50mm blinding to all foundation DRAWN S.M. 1:10 1:20 1:50
r.c. base
(typical)
MAX. 1200
4. ALL WORK AREAS TO BE REINSTATED (PREMIX,
DEEP
MORTAR BENCHING
450 X 450 LIGHT DUTY / FRL CONCRETE, ETC.)
100
NEW 250mm Ø CL 34 UPVC STORMWATER PIPE (1 SAND : 3 SAND)
1:10 FALL 110 Ø CL 34 UPVC PIPE 450 X 600 HEAVY DUTY 5. MUNICIPALITY TO EXECUTE ALL CONNECTIONS INTO
COBBLE
NEW 110mm Ø CL34 LAID AT 1:80 GRADE TO CAST IRON GRID INLET
NEW TYPE A SEWER PRECAST RING MANHOLE GRATING AND FRAME
BRICKWORK TO MUNICIPAL LINES.
SEWER PIPE CLOSEST STORMWATER MH SUIT GRATING
6. SUPPLY AND INSTALLATION TO COMPLY WITH SANS
230
NEW STORMWATER 150mm THICK 25MPA
HEADWALL WITH 1m WIDE STORMWATER SUMP (TYPE A) 630 CONCRETE FOUNDATION 230mm THICK 1200.
1260
600
SWHW 1 MOD AASHTO DENSITY 8. THIS DRAWING IS TO BE READ IN CONJUNCTION
STORMWATER
IL=1348.50 230mm THICK
PIPE 20mm THICK WITH THE ARCHITECTURAL AND STRUCTURAL
BRICKWORK WITH
NEW 110mm Ø CL34 HP HIGH POINT SECTION X-X NFX LOAD BEARING
PLASTER TO ALL
INTERNAL WALLS ENGINEERS DRAWINGS.
SEWER PIPE BRICKWORK.
NEW BLOCK PAVED 1:5 1:5 9. ALL WORK IS TO BE EXECUTED IN ACCORDANCE
230
WALKWAYS. REFER END CAP ON WATER LINE BRICKWORK TO BE
COBBLED TO SUIT MORTAR BENCHING
WITH SANS 1200.
TO LAYERWORKS
DETAIL NEW FIG. 12 KERB X GRATING (1 CEMENT: 3 SAND)
TIE INTO EXISTING SEWER SWMH 4 NEW BLOCK PAVED CAR PARK
50
MANHOLE AT INVERT LEVEL. CL=1349.55 EDGE RESTRAINT STORMWATER
100
150
CONTRACTOR TO PROVE IL=1348.65 25MPA CONCRETE 1. STORMWATER PIPES CONSIST OF 250mm NOMINAL
115
EXISTING LINE PRIOR TO 100 230 600 230 100 BASE
1349.75 1349.75 NEW BLOCK PAVED WALKWAYS DIAMETER - HD CL 34 UPVC PIPES
CONSTRUCTION NEW
FALL
300
SMH 4 SAINT GOBAIN PRODUCT No 2. ALL UPVC PIPES TO COMPLY WITH SANS 966
FALL
CL= C.O.S 2934 OR SIMILAR APPROVED 1260 STANDARDS.
IL= 1348.30 1349.82 1349.82 300 x 300 CAST IRON LIGHT
115
DUTY COVER AND FRAME 3. ALL JOINTS TO BE 'SPIGOT AND SOCKET' TYPE.
NEW 110mm Ø CL34
SEWER PIPE PLAN SECTION X-X 4. ALL STORMWATER PIPES TO BE LAID ON CLASS B
NEW SEWER GULLY
50
X BEDDING.
NEW FIG. 12 KERB NEW 250mm Ø CL34 50 115 300 115 50
EDGE RESTRAINT UPVC STORMWATER
630
STORMWATER MANHOLE - TYPE B WATER
PIPE
450mm X 600mm MANHOLE DETAIL 1. BEDDING TO SUIT FLEXIBLE PIPES.
TIE INTO EXISTING SEWER
PLAN 2. PIPES TO BE INSTALLED WITH ALL COUPLINGS AND
MANHOLE AT INVERT LEVEL.
CONTRACTOR TO PROVE
SWMH 4
CL=1349.55
(MAX. 1500mm DEEP ; PIPES < 450mm Ø ) TO BE TESTED AND DISINFECTED.
EXISTING LINE PRIOR TO IL=1348.75 BLOCK A SCALE 1:20
NEW 3. MINIMUM COVER TO PIPES TO BE 800MM.
CONSTRUCTION SMH 3
CL= C.O.S
NEW 250mm Ø CL34
UPVC STORMWATER
STORMWATER MANHOLE - TYPE A
IL= 1345.55 SLEEVES
PIPE 300 X 300 SUMP DETAIL 1. ALL SLEEVES UNDER ROADWAYS AND PARKING
SMH 2
CL=1349.55 SWMH 3 (MAX. 500mm DEEP ; PIPES < 200mm ∅ ) HD PRECAST CONCRETE
AREAS TO BE CONCRETE ENCASED 150mm ALL
IL=1348.65 CL=1349.60 REFER TO BULK ROUND WITH 25MPA CONCRETE AT 28 DAYS
PROPOSED NEW
IL=1348.85 NTS COVERS AND FRAMES IN
LAYERWORKS STRENGTH.
ABLUTION. DETAIL VERGES / HD POLYMER COVERS
SWMH 2 AND FRAMES WITHIN ROADWAYS
CL=1349.60 GROUND LEVEL MATERIAL COMPLIANCE TESTING
IL=1348.90
1. RESULTS OF COMPACTION AND CBR TESTS ON
NEW 1m WIDE X 3m INSITU SUB-BASE MATERIAL AND FILLED SUB-BASE
SWMH 1 LONG X 0.23m THICK 750mm Ø PRECAST
CL=1349.60 CONCRETE MANHOLE
MATERIAL MUST BE SUBMITTED TO THE ENGINEER
RENO MATTRESS
75
150
KERB LINE 1349.67 NEW FIG. 6 NON-MOUNTABLE MAXIMUM 200mm THICK 2. COMPACTION TESTS 1 PER 200m2 NOTE :
KERB WITH 300mm WIDE CLASS B BEDDING LAYERS TO 93% MOD COMPACTION TESTS WILL ALSO BE REQUIRED FOR
NEW BLOCK PAVED CONCRETE CHANNEL SELECTED FILL FOR AASHTO
WALKWAYS. REFER TO BEDDING BLANKET EACH OF THE VARYING UPPER LAYERWORKS I.E G7,
BLOCK B 1349.80
50
LAYERWORKS DETAIL COMPACTED UNIFORMLY G5 AND G2 THAT IS IMPORTED AND COMPACTED IN
1349.74 IN LAYERS WITH LIGHT CLASS B BEDDING 25MPA CONCRETE BASE WITH
1349.65 PLACE.
250
TIE INTO COMPACTION OF PIPE SELECTED GRANULAR MESH REF. 245 PLACED 50mm
71 1349.76 BOTTOM OF CONCRETE
EXISTING MATERIAL PLACED AND
WATER LINE 1349.77 COMPACTED IN UNIFORM SEWER
INSITU GROUND TO BE
1349.95 70 LAYERS ON BOTH SIDES
FA
x = D/4 COMPACTED TO 95% MOD. 1. ALL SEWER PIPES ARE 160mm NOMINAL DIAMETER
OF THE PIPE FOR
LL
FALL 150 RING OD 150 AASHTO.
DEMOLISH PORTION OF SUBJECT TO x BEING BEDDING CRADLE CLASS 34 HEAVY DUTY UPVC PIPES.
EXISTING KERB LINE AND NEW FIG. 12 KERB NOT LESS THAN 100mm AND 300 PIPE OD 300
CONSTRUCT NEW 80mm 1349.94 EDGE RESTRAINT 69
NOT MORE THAN 200mm 2. ALL SEWER PIPES TO BE LAID ON CLASS B BEDDING.
EXISTING G-BLOCK PAVING. REFER TO 3. ALL SEWER PIPES TO COMPLY WITH SANS 1601
KERB LINE LAYERWORKS DETAIL BELOW
68 NEW 80mm G-BLOCK
SEWER MANHOLE - TYPE A STANDARDS.
1349.94
PAVERS TO MATCH
EXISTING TYPICAL PIPE BEDDING DETAIL (0.0m TO 1.5m DEEP)
NEW FIG. 6
67 N.T.S
NON-MOUNTABLE 1349.66 FALL SCALE 1:20 SCALE (mm)
KERB 1349.97
1349.90 1349.82
FAL
66 1349.91 0 10 20
L
NEW BLOCK PAVED No. REFERENCE DRAWINGS
WALKWAYS. REFER
65 NEW FIG. 6
TO LAYERWORKS
DETAIL NON-MOUNTABLE
KERB
64
63
BLOCK C D
EXISTING BLOCK NOTES OUTLET\INLET DIMENSIONS IN mm FOR :
PAVED CARPARK 1349.75
62
O = 90° ; = 1:1,5 ; h = 300mm & H = 600mm
FALL
230 75
1350.15
1349.83 ALL EXPOSED CORNERS 10 x 10
DISSIPATERS O 3
CHAMFERED 375 875 1000 1720
FALL
= S/V (D+H-h-150)
THICK 1:3 CEMENT/SAND MORTAR
1000 MINIMUM
DEMOLISH KERBS AND TIE INTO
WITH WOOD FLOAT FINISH PROJECT MANAGER / PRINCIPAL AGENT
EXISTING BLOCK PAVED ROAD 1350.02 750 1250 1250 2300
LEVELS WITH NEW 80mm G-BLOCK
PAVERS TO MATCH EXISTING EXISTING
= V/S = GRADIENT TO SUIT FILL OR NATURAL
KERB LINE
+-30° +-30° GROUND SLOPE (1:1,5 MAX.)
B
75 75
A 23
0 0
A
23 H = 300 MIN. ; 900 MAX.
D + 150 B
CLASS 20/19
ADDITIONS AND ALTERATIONS
150
CONTINUOUS
CONCRETE MESH REF. 193 REINFORCEMENT
75
HAUNCHING DETAILS
75
100
CLASS 20/19 BRICKWORK HEADWALL
150
150
CLASS 20/19 PANELS.
PROPOSED NEW PARKING AND
H
CONCRETE
150mm RIP & RECOMPACT TO 93% 100 125 100 CONCRETE 75 75 75 6000 L x 2000 W x 230 H
BEDDING INSITU MATERIAL TO BE WINGWALL
MOD. AASHTO DENSITY BEDDING V REMO MATTRESS
RIPPED TO A DEPTH OF 150mm BULK SERVICES LAYOUT
MINIMUM
S
FIG. 6 NON-MOUNTABLE FIG. 12 KERB EDGE AND RECOMPACTED TO 93%
D + 200
MOD AASHTO
D
WALKWAY LAYERWORKS DETAIL
D
KERB DETAIL RESTRAINT DETAIL DETAIL GRADIENT AS
250
NTS CONCRETE V-DRAIN CHANNEL SPECIFIED
h
N.T.S N.T.S
DETAILS APRONSLAB
SCALE 1:10
600
75 R12 AT 600
400
S.O.P
ANCHOR BARS
300 SUITE 102, WHEELER HOUSE 1ST FLOOR, APTUS HOUSE
80mm THICK TYPE S-A (G-BLOCK) BLOCK PAVERS SURFACE BED TO STRUCTURAL F.G.L
CROSSFALL 14A MAZENOD ROAD, RIVERWORLD PARK
PLACED OF 20mm THICK CLEAN COARSE RIVER SAND ENGINEER'S DETAIL UNLESS OTHERWISE DIRECTED MORNINGSIDE, DURBAN 53 AUTUMN ROAD, RIVONIA
BEDDING F.R.L ALLOWANCES TO BE MADE: BY ENGINEER ON SITE 200
130
130
e-mail : admin@mapafrica.co.za
1:10
150mm THICK G2 BASE COMPACTED TO 150mm THICK G2 BASE L website : www.mapafrica.co.za
CLASS 20/19
100% MOD. AASHTO DENSITY COMPACTED TO 100% MOD. 300mm WIDE CLASS CONTINUOUS TEL. (031) 309 5831 TEL. (011) 234 3819
1. PROVE EXISTING SEWER LINE AND
100
FIG. 6 NON-MOUNTABLE 3. PROVE EXISTING SERVICES LOCATED SCALE 1:20 DRAWN K.G AS SHOWN
WITHIN NEW CAR PARK AREA.
ACCESS SCOOP LAYERWORKS DETAIL BULK LAYERWORKS DETAIL KERB WITH 270mm WIDE 4. REMOVAL OF TREES AS SHOWN ON THE
APPROVED S.S PL DATE 2020.01.27
Date : 2020.06.24
DRAWING ISSUE RECORD year 20
Page 1 of 1 month 06
date 24
Distribution
Client Umalusi
Project Manager LDM Project Managers E
Architect PGA Architects E
QS LDM Quantity Surveyors E
Mechanical Eng. LSG International E
Electrical Eng. Ibuya Consulting E
Contractor
200-309-302 New Ablution Building - Roof Slab, Entrance Canopy Slab & First A0 T1
Floor Slab
Existing Main Building - New Brick Wall Cast on Existing Ground
200-309-303 A1 T1
Floor Surface Bed
Existing Main Building - New R.C. Slab Infill Panels on the Existing
200-309-304 A1 T1
First Floor Slab
200-309-500 Existing Main Building - New Structural Steel Canopy A1 T1
200-309-501 Existing Main Building - New Structural Steel Fire Escape Staircase A1 T1
CIVIL LAYOUTS