1) Ethiopia Profile On Meat Processing and Preserving
1) Ethiopia Profile On Meat Processing and Preserving
1) Ethiopia Profile On Meat Processing and Preserving
TABLE OF CONTENT
I. EXECUTIVE SUMMARY ........................................................................................................................................5
LIST OF TABLES
Table 1Installed capacity and utilized capacity of Slaughter house in Ethiopia ........................................... 15
Table 2 Volume of imported processed meat from 2012 to 2021 in kg ....................................................... 16
Table 3 Future forecast of import of processed meat by trend adjusted exponential smoothing method...... 17
Table 4 Projected Demand for meat in Ethiopia .......................................................................................... 19
Table 5 Volume of Exported meat from 2012 to 2021 in kg ........................................................................ 19
Table 6 Future forecast of export of processed meat by trend adjusted exponential smoothing method ...... 20
Table 7 Demand supply gap Analysis .......................................................................................................... 21
Table 8 Production programme .................................................................................................................... 25
Table 9 Approximate cut out weight for cattle ............................................................................................. 25
Table 10 Building costs ............................................................................................................................... 27
Table 11 Land lease period in Addis Abeba ................................................................................................ 28
Table 12 Land lease floor price in Addis Abeba .......................................................................................... 28
Table 13 Lists of meat processing machineries ............................................................................................ 29
Table 14 Annual manpower costs ................................................................................................................ 30
Table 15 Initial Fixed investment costs ........................................................................................................ 34
Table 16 Raw materials input plan in Birr'000' ............................................................................................ 36
Table 17 Utilities of the factory’000”Birr .................................................................................................... 37
Table 18 Overhead costs .............................................................................................................................. 39
Table 19 Depreciation in Birr"000" ............................................................................................................. 40
Table 20 Source of revenue in Birr"000" ..................................................................................................... 43
Table 21 Annual total production costs”000” .............................................................................................. 46
Table 22 Calculation of working capital ...................................................................................................... 47
Table 23 Projected Net income statement "000" .......................................................................................... 48
Table 24 Debt services schedule and computation ....................................................................................... 49
Table 25 Projected Cash flow statement ...................................................................................................... 50
Table 26 Total investment costs”000” ......................................................................................................... 51
Table 27 Total Assets .................................................................................................................................. 51
Table 28 Sources of finance ......................................................................................................................... 52
LIST OF FIGURES
Figure 1 process flow chart for cattle meat processing unit ......................................................................... 23
I. Executive summary
This project profile is prepared to assess the viability of running meat processing factory, in Addis
Abeba city administration. Hence Market, Technical, Organizational and Financial study was made
This project profile on meat processing factory has been developed to support the decision –making
process based on a cost benefit analysis of the actual project viability. This profile includes
marketing study, production and financial analysis, which are utilized to assist the decision-makers
when determining if the business concept is viable. According to the latest data sourced from
Ethiopian investment commission (EIC) there are more about 44 companies registered to involve in
The location of the plant will be decided on the basis of access to raw materials, infrastructure
namely power, water, transport and telecom to easy access to international market.
The factory at full capacity operation can produce 17.68million kg of canned meat, per year based
The total investment capital including establishing the factory is Birr 1.09billion. Out of the total
investment capital, the owners will cover Birr 327.50million (30 %) while the remaining balances
amounting to Birr 764.15million (70 %) will be secured from bank in the form of term loan.
As indicated in the financial study, the cash flow projection of the project shows surplus from the
first year on. The net cash flows of the project range from Birr 447 million in the first year to Birr
654 million at the end of the 10th year of operation. At the end of the 10th year of operation period
the cumulative cash balance reaches Birr 6.26 billion. The Benefit-cost ratio and Net present value
(NPV) have been calculated at 17% discount factor (D.F) for 10 years of the project activity.
Accordingly, the project has NPV of 3.69 billion Birr at 17%D.F. and the benefit-cost ratio of 1.09
at 17% D.F.
Therefore, from the aforementioned overall market technical and financial analysis we can conclude
1. Background information
1.1. Introduction
Ethiopia has one of the largest livestock populations in Africa and the tenth in the world. The country
had 59.5 million heads of cattle, 30.70 million heads of sheep, 30.20 million heads of goats, 56.53
millions of poultry and 1.21 million heads of a camel. Cattle in Ethiopia provide draught power,
income for farming communities, means of savings and investment. It is central to the Ethiopian
economy contributing about 45% to the agricultural GDP, supporting the livelihoods of 70 % of the
population, 18.7% to the national GDP and 16–19% to the total foreign exchange earning of the
country. Meat is the most valuable livestock product and for many people serves as their first-choice
source of animal protein which provides all the essential amino acids and various micronutrients in
proper proportion to the human beings. Meat defined as all animal tissues suitable as food for human
consumption. This includes all processed or manufactured products prepared from animal tissues.
Meat production and consumption is an important in the Ethiopian economy. The annual
contribution of cattle meat production in Ethiopia is accounts for over 70% of the total red meat
production and over 50% of the total meat output in Sub Saharan Africa. The Country’s export
performance reached its peak in 2016/17 by exporting 19,779.20 tons of meat. In the same period
under review, the meat export (chilled shoats, beef carcass and offal) value has picked up from 1.7
million USD to 92.65 million USD. Among these shoat carcass account 80.35 million dollar
its taste or to extend its shelf life. Methods of meat processing include salting, curing, fermentation
, smoking, and/or the addition of chemical preservatives. Processed meat is usually composed
of pork or beef, but also poultry, while it can also contain offal or meat by-products such as blood.
Processed meat products include bacon, ham, sausages, salami, corned beef, jerky, hot dog, lunch
meat, canned meat and meat-based sauces. Meat processing includes all the processes that change
fresh meat with the exception of simple mechanical processes such as cutting, grinding or mixing.
of Ethiopia in the middle of Oromia Region. The absolute location is around the intersection point
of 901’48’’N latitude and 38°44′24″E longitudes. This is very near to the geographical center of the
country. It is, therefore, equidistant to the peripheral areas or is equally accessible to almost all parts
of Ethiopia. Addis Ababa is located on a well-watered plateau surrounded by hills and mountains.
The city is in the highlands on the edge of the Ethiopian rift valley or the eastern slopes of the Entoto
Mountain ranges bordering the Great Rift Valley. The total area of Addis Ababa is about 540 km 2
of which 18.2 km2 are rural. Addis Ababa’s built-up urban area spans 474 km2. It is also the largest
million people in 2022. Of the total population 22.9% (24 million people) live in urban areas.
Ethiopia’s urban population is expected to triple by 2037 (World Bank, 2015). Addis Ababa hosts
an estimated 3,859,638 people. Currently, Addis Ababa is experiencing an annual growth rate of
The transformation of Addis Ababa has especially been rapid since 1991. According to the data from
the city’s Bureau of Finance and Economic Development (2006), per capital income of Addis Ababa
has grown from USD 788.48 in 2010 to USD 1,359 in 2015. The city also achieved a decline in the
poverty index from a high of 29.6 in 2012 to 22.0 in 2014. Moreover, the current poverty headcount
index for Addis Ababa is estimated at 18.9 while the poverty severity account for 5 and 1.8 index
points respectively. Even though, the poverty status of Addis Ababa has an improvement over
previous years, there is still much work to be done to curb both the incidence and severity of poverty.
The major contributor to the economic growth of the city is the implementation of publicly financed
mega urban projects like condominium housing, the Light Rail Transit, the international airport and
industrial zone development (The state of Addis Ababa, 2017). The existence of international large
and medium-size enterprises in and around Addis Ababa have also significant role in creating huge
opportunity for employment and technology transfer. Furthermore, there are strong demand for
goods and services following the existence of many embassies and inter-governmental organizations
like the African Union, the United Nations Economic Commission for Africa.
The manufacturing sector’s contribution to Addis Ababa’s GDP is high. Despite the fact that 86%
of the industries in the city are micro and small scale (cottage and handicrafts, and small-scale), the
majority of the country’s large and medium scale industries are found in the city. Noticeable
The service sector is both the largest contributor to the city’s economy and the largest employer. It
contributes to 76.4% of the city’s GDP while industry’s share makes up (almost all) the rest. This
sector is dominated by three major sub-sectors: Transport and communication; Real estate, Renting
and Business services; and Trade, Hotel and Restaurants. According to the state of Ethiopian Cities
2015 report, the service sector has also been responsible for more than 50% of the growth in the
estimated annual growth of the city’s GDP. Although 75% of employment in the city is also
generated in the service sector, a large proportion of the employed work in low skill and low paying
jobs as shop salespersons, petty and 'gullit' traders, sales workers in small shops, domestic helpers
Analysis of the economic structure of Addis Ababa reveals that the services sectors (63%) dominates
with industry (36%) in second place indicating that these sectors account for almost all of the Addis
Addis Ababa has a great share in the economy of the country due to its attractiveness to businesses,
companies, individuals and foreign direct investment. Overall primacy index of the city is 24.8 based
on urban employment and unemployment survey (CSA 2015). According to the State of Addis
Ababa 2017 report, the simultaneous high rates of economic growth and urbanization in Addis
Ababa indicates a likely further rising dominance of the city in Ethiopia’s economy as well as
market. The total meat production increase from 578,240 tons in 2004 to 749,430tons in year 2014
and decreased to 596,765 tons in year 2017. Despite the fact that Ethiopia is the tenth largest
livestock population in the world, the production of meat is still low and contributed to about 0.2
percent of the world total meat production, of which most is sheep and goat meat. This ranked
Ethiopia the 55th largest meat producing country in the world. The reasons behind low production
of meat in Ethiopia are due to low off-take rates, most animals slaughtered and exported live were
not produced in commercially oriented manner and sell only in need of cash or when animals get
too old after serving for draft purpose and inability to fulfill minimum standard required in the
international market for processed meat. The trend of meat production in Ethiopia shows it was
general and particularly for beef due to preference for eating meat. Meat consumption is often an indicator of
economic status of a country or an individual. People with a higher social or economic status demand a greater
amount of high-quality meat products. The per capita consumption of meat in developed countries is much
higher than in developing countries. Countries whose population consumes the least amount of meat are
located in Africa and Asia. Developed countries consumed a consistent level of 77 kg of meat per capita
annually, while developing countries struggled to maintain a diet with only 25 kg of meat per capita annually.
With the fast growth of Ethiopian economy and population, the domestic demand for meat is increasing;
however, the country is one of the lowest per capita of meat consumption in the world which is 8 kg, of which
about 5.3 kg comes from beef. This is due to low per capita incomes, non-commercial oriented animal
husbandry practices, high domestic meat prices and the fasting days over 200 days per year by the Orthodox
Christians.
should be given the resource potential. Currently there are about 15 export slaughter houses
(including 8 under establishment) with installed capacity of 140,702 tons/year while they utilized
23%of their installed capacity and more than 29 abattoirs (with installed capacity 588,123 cattle/year
and 317,785 goat/year) serving the local market. Notwithstanding, illegal or informal killing of
animals is highly practiced for domestic consumption at the backyard of practically all households
especially for shoats whereas for cattle killing at village level to share among a group of neighbors
or close families is common which is called” Kircha‟. Municipal level domestic abattoirs are
growing time to time with the growth of urbanization whereas modern slaughter houses are mainly
population share is only 17 percent (as of 2012, World Bank 2015). The city is the only urban area
diversity and depth of skills, innovation, and technology transfers. Thus, investors will be benefited
The capital is the country’s main industrial hub. The city dominates industrial capacity in almost all
the braches of light manufacturing that Ethiopia prioritizes. As a result Addis Ababa completely
dominates production in various subsectors. This can be taken as the political and social stability of
the city.
Overall, the city has a beautiful environment, favorable location, and strong industrial base. Its
advantage as an economic powerhouse of the country and human resource center are the most
Moreover, investors will be getting a comprehensive set of incentives for priority sectors. These
include:
Customs duty free privilege on capital goods and construction materials, and on spare parts
whose value is not greater than 15% of the imported capital goods’ total value.
Investors have the right to redeem a refund of customs duty paid on inputs (raw materials
and components) when buying capital goods or construction materials from local
manufacturing industries.
Additional 2-4 years income tax exemption for exporting investors located within industrial
Loss Cary forward for half of the tax holiday period. Several export incentives, including
Duty Draw-Back, Voucher, Bonded Factory, and Manufacturing Warehouse, and Export
Employment opportunity
Investment is expected to provide direct and indirect employment. These range from
Through the use of locally available materials and exporting products, the investment
product. These eventually attract taxes including VAT which will be payable to the
government hence increasing government revenue while the cost of local materials will be
payable directly to the producers. In addition, domestic products save foreign exchange and
2. Marketing study
2.1. Market analysis summary
The current drive and emphasis by the government on the diversification of the industrial base away
from the other sector presents an opportunity for production industry to a valuable contribution
towards achieving goal. Having undertaken a thorough and comprehensive research of the market
we realized that there was a vast opportunity for domestic products. Aware of the fact operating in
such a market is largely dependent on good networking, the promoter intends to establish networks
and strategic relationships with various wholesalers and retailers to ensure a steady stream of orders.
In so doing the owner intend to ensure that the products they produce are of extremely high quality
2.1.2. Import
The supply of meat has been met both through import and domestic production. Although there is
no apparent trend in the growth of import processed meat has continuously been appearing in the
import statistics.
Year Net weight CIF value in CIF value in Total TAX in Total value Unit price
(in Kg) (ETB) USD ETB in ETB per Kg
2012 23,550 23,019 4,474,642 250,461 3,010,368 168,501
2013 13,693 13,562 3,297,673 175,407 2,222,705 118,228
2014 70,819 68,302 6,971,171 346,074 1,603,664 79,612
2015 156,298 134,265 8,694,265 418,356 5,706,053 274,567
2016 48,788 42,093 1,559,541 72,206 993,346 45,991
2017 47,260 45,529 2,662,536 109,945 1,427,669 58,953
2018 17,434 16,454 639,316 - 405,182 20,877
2019 - - - - - -
2020 139,106 119,911 7,640,960 - 1,363,544 -
2021 181,872 151,100 16,191,912 - 4,950,736 -
Source: Ethiopia customs Authority
As it has been shown in table 3 import of processed meat which was 23,019 kg at the beginning of
the period (2012) has increased to 151,100kg by the end of, 2021. A closer observation at the data
set reveals that imported processed meat over the study period has shown varying patterns. Based
on the data obtained from Ethiopia customs Authority, the annual average volume of imported
Table 3 Future forecast of import of processed meat by trend adjusted exponential smoothing method
The demand for meat can be influenced by a number of factors. The size of population and its growth
rate, disposable income prices and culture are few among many variables. With the fast growth of
Ethiopian economy and population, the domestic demand for meat is increasing; however, the
country is one of the lowest per capita of meat consumption in the world which is 8 kg, of which
about 5.3 kg comes from beef. This is due to low per capita incomes, non-commercial oriented
animal husbandry practices, high domestic meat prices and the fasting days over 200 days per year
by the Orthodox Christians Nevertheless, for the purpose of this study, attempts have been made to
forecast the likely future demand for meat on the basis of the following assumptions:
iv. According to International Journal of Food Science and Agriculture, 2019 consumption of
Table 6 Future forecast of export of processed meat by trend adjusted exponential smoothing method
When we see the historical supply volume of meat in Ethiopia there is no apparent trend in the
growth. Hence, it is found difficult to objectively forecast the future supply volume. Single
exponential smoothing method was used, for import forecasting purposes. A 2.5% growth rate,
equivalent to population growth of our country, is also assumed for local supply increase, for new
as well as expansion projects for domestic suppliers of the existing slaughters’ house.
cured, canned, and other meat products, and the rendering of inedible and discarded remains into
useful by-products such as lards and oils. Meat is exposed to a series of wide range of processes viz.
curing or preserving processes such as salting, wet pickling, drying, cooking and canning, sausage
manufacture, ham curing. All these processing techniques are aimed at inhibiting the microbial
spoilage and increasing the shelf life of the meat. Major principles involved in meat processing are
use of heat, low temperature, smoking, modified atmosphere packaging and ionizing radiations. The
methods of preservation are mainly grouped in three categories i.e. control by temperature, by
Freezing is an excellent process for preserving the quality of meat for long periods. Freezing is often
used to preserve meats during shipment over long distances or for holding until long times of storage.
Its effectiveness depends on ice crystal formation and rate of lowering of temperature. When the
temperature of storage is below - 18C2, changes occur at a very slow rate in the muscle of warm
blooded animals. Quality of frozen meat depends on various factors such as rate of freezing,
packaging etc. When muscle tissue is frozen rapidly, small both intra and extra cellular ice crystals
are formed which cause little damage to the meat structure. While large ice crystals are formed in
slow rate of freezing causing compactness of muscle fiber. The process of denaturation can be
accelerated with a resulting decrease in water holding capacity of tissue. Loss of water holding
capacity of the muscle along with mechanical damage to cells by ice crystals is responsible in large
parts of thaw exudates. To protect quality loss due to changes in protein, anti-freezing compounds
or cryoprotectants i.e. polydextrose, polyphosphate are added to meat formulations. Rapid freezing
can be obtained by using air blast freezers either on batch or continuous basis which employs -20 to
-40C2 cold air. Large size meat cuts are vacuum packaged to prevent lipid oxidation and
discoloration due to formation of metmyoglobin. Retail meat is packed in low permeability films
environmental and social due to development projects occur in different forms. An Environmental
and Social Impact Assessment (ESIA) has to be carried out to study the potential environmental and
social impacts due to the production processed meat. Potential environmental and social impacts due
to the production of meat based products on attributes like air quality, noise, water quality, soil, flora,
socio-economic, etc. have to be assessed as part of the ESIA study. Appropriate mitigation measures
to help minimize/avoid impacts from the development have to be recommended in the study. The
measures. For the purpose of including environmental costs, the costs of wastewater treatment plant
and solid waste incineration systems are included in the cost of machinery and equipment. Social
The annual production capacity of the plant in full capacity is 500 heads of cattle per day, their
weight is 400kg each. The production capacity is based on projected demand and realistic market
share that could be captured. The production commences three shift and 260 working days a year.
The annual production program for the year 1 to year 4 is indicated in Table 8 below. The plant
initially produces 70 % of its annual rated capacity bound to initial operating problems such as
machine set up and marketing. The production capacity will increase by 10 % and attain its full
3.2. Engineering
3.2.1. Land, buildings and civil works
The required area (m2) and construction cost for the production facilities essential for the successful
operation of the processing plant is shown in Table10. A total area ready for the processing plant is
50,000m2 out of which 24,900m2 is to be covered by building while uncovered area of 25,100m2 is
left open for parking, storage of waste materials and future expansions. In order to estimate the land
lease cost of the project profiles it is assumed that all the project will be located in different land
level from level 1/1 to level 4/3, their current market lease price is from 39,073.31 birr per M 2 to
2,800.71 birr per M 2respectively. Therefore, for the profile a land lease rate of birr 3,885 per M 2
The cost of construction of building should be appropriate to the size and expected profitability of
business, costs of building generally differs by the type of construction materials used, the type of
foundation, wall height and location. The current building cost for simple storage and processing
room is from 10,000 Birr per m2 to 25,000 Birr per m2. The total construction cost of buildings and
2
civil works, at a rate of Birr 20,000 per m is estimated at Birr 402.80 million. Therefore, the total
cost of land lease and construction of buildings and civil works is estimated at Birr 597 million.
The proposed plant layout comprises the following buildings and structures.
Sources: - city government of Addis Abeba land development and management bureau
SCHRÖDER Maschinenbau
GmbH & Co. KG
Esch 11
33824 Werther, Germany
Tel.: +49 5203 9700 0
Fax.: +49 5203 9700 79
The selection of structure of the envisaged project is made based on the existing structure of
manufacturing plants operating in the country, the capacity, complexity and technology mix of the
plant. Organizational structure principles such as specialization, coordination, and
departmentalization are also considered for design of structure that best suits the envisaged project
5. Financial Analysis
5.1. General
The financial analysis evaluation of the project, under consideration has been carried out for meat
processing cost estimates of the envisaged factory are mainly consisted of capital investment as well
as operating and maintenance costs. The capital investment costs include fixed investment costs
(initial fixed investment and replacement costs) and working capital, while operating and
maintenance costs comprise current expenses related to material inputs, labour, utility, repair and
maintenance costs, spare parts, Overheads, Sales and distribution, interest and depreciation
expenses.
The financial analysis and evaluation has been conducted taking assumptions:
1. It is assumed that about 70% of the total capital investment costs including the working
capital requirement could be covered through development bank loans of short and long-
term credits. The remaining balance 30% will be covered by equity capital contribution of
2. Even though the project might secure loans under different term and conditions as well as
from different financial sources, for the purpose of calculation of debt service scheduling,
the current development bank of Ethiopia credit terms and conditions have been used.
Consequently. It is assumed that the project will secure loan facility on the basis of 11.5 %
3. Even though the estimated project production life is more 10 years, the financial analysis has
been undertaken for a period interval covering the first 10 years only, during which time
most of the capital assets are assumed to be deprecated, debts recovered and pay-back period
accomplished.
4. It is assumed that the project will be start up production activity at 70 % capacity. During
years 2 & year 3 the projects is anticipated to gradually increase capacity utilization to reach
100% in year 4. Therefore, starting from year 4 the project will be operational at full capacity.
5. For the project under reference promotional, sales and distribution expenses have been
6. Maintenance and spare parts costs are 1.5% of the fixed investment costs.
S/No Fixed investment Unit of Quantity Unit price Total Amount Remarks
type measurement
1 Land Square meter 50,000 3,885 194,250,000.00 The period of land
lease will be 70
birr/M2 years and 10% of
2 Buildings and civil Square meter 5,100 lump sum 402,800,000.00 the total lease
works amount will be
paid in the first
year
Sub total 597,050,000.00
3 Machineries set 2 Lump sum 120,000,000.00
4 Transformer set 1 Lump sum 2,000,000.00
5 Weighbridge Set 1 Lump sum 4,000,000.00
6 Truck and vehicles Pcs 2 Lump sum 12,000,000.00
7 Furniture and Pcs 500,000.00
fixture
SUB TOTAL 138,500,000.00
Fixed capital 735,550,000.00
investment costs
8 pre-operational 2,000,000.00
expenses
Working capital 354,099,000.00
TOTAL INVESTMENT COSTS 1,091,649,000.00
Working capital is the financial means required for smooth operation and maintenance of a project
mathematically, it is a difference between current assets and current liabilities. In the particular case
of the project under consideration, the current assets comprise receivables, inventories (local and
imported material inputs, spare parts, work in progress, and products ready for delivery) and cash in
Fixed capital investment costs and working capital requirements are assumed to be financed by
equity capital of the owner and through loans of short and long-term credits.
As stated earlier even though the company obtains loans under different terms and condition as well
as from different sources, for the purpose of calculation of debt service scheduling the current
development bank of Ethiopia credit terms and conditions have been used. Accordingly, it is
assumed that the company will be able to obtain loan 70% of the total investment costs and the
remaining balance that of the total investment costs will be expected to be covered by equity
As it is depicted in Annex Table 21 major categories of the total production costs are assembled into
In the project under study the basic material inputs are cattle (Oxen, bulls, and cows), labelled cans and salt.
Therefore, the current prevailing local and international market prices have been used for estimation of
material inputs costs. At full capacity operation the material inputs costs are estimated at Birr 10.05 billion
per annum.
Project year 1 2 3 4
Materials input for Quantity at full Unit
meat processing Description Capacity price
1 Cattle Average weight 400kg 500 cattle/day 75,000 6,825,000 7,800,000 8,775,000 9,750,000
2 Can 1000gm, holding capacity 68, 000pcs/day 15 185,640 212,160 238,680 265,200
5.5.2. Utilities
In estimating costs of utility expenses for operation and maintenance of the project, Costs of fuel, oil and
lubricant, electricity and water consumptions have been taken in to consideration, the rates of which have
been estimated on the basis of the proposed capacity utilization program of the project and at the current
official charging rates. At full capacity operation the project will have the following utility expense per annum
Start-up Full
Utility”000”Birr Capacity
Capacity utilization 70 % 80 % 90 % 100 %
Project year 1 2 3 4
Item description Unit of measurement
Fuel
Gasoline for service vehicle 50km*260days*37Birr/LIT*8km/Li 29.575 33.80 38.025 42.250
Gasoline for transport truck (200km*300days*37Birr/LIT*5km/Li)*3 655.20 748.80 842.40 936.00
Sub-Total
684.775 782.6 880.425 978.25
Change of oil and lubricant 10% of the fuel consumption
68.48 78.26 88.04 97.83
Sub-Total
753.25 860.86 968.47 1,076.08
Electricity 260days*24 hrs*650kwh* 0.4736Birr/kwh 2,839 3,245 3,650 4,056
In the expenses under this title have been considered cost estimates required for annual repair and
maintenance works including spare parts expenses. These costs include the annual repair expenses
of structures and civil works as well as repair and maintenance expenses of machinery and equipment
including accessory and general service facilities. The repair and maintenance and spare parts costs
“organization and Management” section of this study. In the estimation of salaries and wages, the
official minimum wage has been taken in to account. At full capacity operation the costs of salaries
In the expenses under this title have been included land and building taxes, buildings, vehicles as
well as machinery and equipment insurance, vehicles annual inspection; postage, telephone and e.
mail, stationery and office supplies; printing and copying; audit fee; cash indemnity etc. The
Insurance
Building and Civil works 0.10% 402.80 402.80 402.80 402.80
Machinery and Equipment 0.20% 240.00 240.00 240.00 240.00
Motor vehicle and Truck 1% 120.00 120.00 120.00 120.00
Vehicles annual inspection and 15,000 Birr per annum per vehicle
registration 45.00 45.00 45.00 45.00
Work cloth Two times per annum per workers at
800 Birr 65.60 65.60 65.60 65.60
Cleaning and sanitation An estimate of 300 Birr/day 78.00 78.00 78.00 78.00
Sub Total
28,701.40 28,701.40 28,701.40 28,701.40
Administration Overhead “000’ Birr
Audit fee 40,000 Birr per annum 40.00 40.00 40.00 40.00
Office cleaning and sanitation 2,000 Birr per month 24.00 24.00 24.00 24.00
Stationery and office supplies 2,000 Birr per month 20.00 20.00 20.00 20.00
Printing and Copy 2,000 Birr per month 24.00 24.00 24.00 24.00
Sub Total 108.00 108.00 108.00 108.00
credit terms and conditions for newly establishing projects have been used to compute the financial
costs, estimated to be incurred in connection with that of the total investment costs assumed to be
covered through loan financing. The amount of the loan capital to be obtained and the financial costs
to be incurred thereof have been determined depending on the amount of fixed investment cost and
pre-production expenses.
5.5.7. Depreciation
Depreciation charges should be taken in to account as part of the total production costs in order to
calculate the total production costs, the net working capital and the gross or net-profit. For the given
project under reference, the fixed assets and the pre-production capital expenditures have been
depreciated and amortized respectively on “a straight line” depreciation method basis using the
The rationale uses for the estimation of the depreciation and the amortization rates is based on the
expected service life of the assets and repayment capacity of the project under consideration. Based
on the above charging rates and consideration of the above facts, the total annual depreciation cost
Period Start-up
Structure and civil works 402,800,000.00 5% of original value 20,140 20,140 20,140 20,140
Machinery and equipment 120,000,000.00 15 % of original value 18,000 18,000 18,000 18,000
Motor vehicles and trucks 12,000,000.00 15 % of original value 1,800 1,800 1,800 1,800
Office equipment and furniture 500,000.00 20 % of original value 100 100 100 100
annual fixed cost, and divided by Annual sales less Annual variable cost.
A. BEP production
To determine BEP production volume, divided BEP sales by the unit selling price (USP)
165,510x 100%
= 8,153,600−7,345,14
= 20.47%
= 41%
= 137%
Project capital investment costs are the sum of fixed capital investment (fixed investment plus pre-
production capital expenses) and net working capital at full capacity, with fixed capital constituting
the resources required for constructions and civil works, importation and installation of production
machinery and equipment and general service facilities, whereas, the working capital corresponding
to the resources needed for operation of the project totally and partially.
As it has been revealed in Annex Table 21 the total annual operating costs excluding depreciation
and interest are estimated to range from 7.3billion Birr in year 1 to 10.45 billion Birr in year 4 and
then after remain constant for the rest of the project life.
The total annual production costs including depreciation and interest increase from 7.46billion Birr
in year 1 to 10.566 billion Birr in year 4 then starts declining until it reaches 10.48 billion Birr in
year 10.
In according to Annex Table 22 requirement for the total working capital has been found to range
from 354 Million Birr to in year 1 to 483 Million Birr in year 4 and then and then after remain
In the assumptions used to compute the working capital, basically care has been taken to cover costs
of consumable materials inventory (material input, spare parts stock, work in progress and product
For financial analysis and evaluation of the given project, the current cattle price, and packing
materials buying price and final packed meat price at the project gate has been taken as a basis. As
it has been stated earlier the project is envisaged to reach full capacity operation four years after
commencement of production activities which are assumed to begin with 70% of the estimated total
capacity.
At full capacity operation the project is envisaged to have the following revenue components.
Project year 1 2 3 4 5
Unit price
Product type
1 Canned meat 600/kg 7,425,600 8,486,400 9,547,200 10,608,000 10,608,000
2 By product like blood, 40% of total 50birr/kg 728,000 832,000 936,000 1,040,000 1,040,000
fatty tissue, skin, weight of the
organs and etc. cattle will be
sold as by
products
TOTAL 8,153,600 9,318,400 10,483,200 11,648,000 11,648,000
Thus, according to the computation in Annex Table 23 and Annex Table 25, the net income and cash
flow statements analysis revealed that at full capacity operation the project will generate a total
income (gross revenue) amounting to 11.64 billion Birr per annum. The corresponding Annex Table
23 of “Net Income Statement” shows a steady growth of gross profit starting from 692 million Birr
in year 1 reaching the peak of 1.1billion Birr in year 10. In its 10 years of manufacturing activities,
the project is expected to generate a total net profit of 6.68 billion Birr and contribute 3.6billion Birr
According to the current investment Law, machinery and equipment are anticipated to be imported
duty- free. The liquidity position of the project is very strong. The corresponding Annex Table 25
of “Cash Flow Statement” shows the positive cumulative cash balance of Birr 6.2 billion and the
project will not face any cash shortage throughout its production life.
The computation of the pay-back period as depicted in Annex table 30 indicates that the project will
be able to reimburse itself from its net cash-income within one year after commencement of
production activities, the period which is considered to be very good for the project of this nature.
In Annex Table 31 of the Benefit-cost ratio and Net present value (NPV) have been calculated at
17% discount factor (D.F) for 10 years of the project activity. Accordingly, the project has NPV of
3.69billion Birr at 17%D.F. and the benefit-cost ratio of 1.09at 17% D.F. These results are most
appreciable, especially, when related to the external capital borrowing interest rate which ranges
The project under study when implemented will have BEP at about 20.47% operation of the
estimated full capacity. In addition to this, finally, summary of financial efficiency tests have been
conducted in Annex table 29, Accordingly, all efficiency ratios indicated positive trends and
consequently, it can be inferred that the project can operate in the frame work of free market
ANNEXES
ANNEX II
Project Year 1 2 3 4 5 6 7 8 9 10
Cost category
I. Material inputs 7,036,164 8,041,330 9,046,496 10,051,662 10,051,662 10,051,662 10,051,662 10,051,662 10,051,662 10,051,662
II. Labor 7,884 7,884 7,884 7,884 7,884 7,884 7,884 7,884 7,884 7,884
III. Utility 6,251 7,129 8,007 8,886 8,886 8,886 8,886 8,886 8,886 8,886
IV. Repair and Maintenance and spare 8,120 8,120 8,120 8,120 8,120 8,120 8,120 8,120 8,120 8,120
parts (0.5 % of fixed costs)
VI Direct overheads 28,701 28,701 28,701 28,701 28,701 28,701 28,701 28,701 28,701 28,701
A. Direct Production costs 7,087,120 8,093,164 9,099,208 10,105,253 10,105,253 10,105,253 10,105,253 10,105,253 10,105,253 10,105,253
VII. Administration over head 108 108 108 108 108 108 108 108 108 108
VIII. Marketing and Promotional expense
244,608 279,552 314,496 349,440 349,440 349,440 349,440 349,440 349,440 349,440
3 % of sales revenue
B. Operating costs 7,331,836 8,372,824 9,413,812 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801
Interest 87,377 82,747 77,028 70,650 63,539 55,610 46,769 36,911 25,919 13,664
Depreciation 41,440 41,440 41,440 41,440 40,940 40,840 34,009 20,140 20,140 20,140
C. Total production costs 7,460,653 8,497,011 9,532,280 10,566,891 10,559,280 10,551,251 10,535,579 10,511,852 10,500,860 10,488,605
ANNEX IV
CALCULATION OF WORKING CAPITAL REQUIREMENTS
ANNEX VI
Project year 1 2 3 4 5 6 7 8 9 10
Item description
8,153,600 9,318,400 10,483,200 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000
Product sales revenue
7,460,653 8,497,011 9,532,280 10,566,891 10,559,280 10,551,251 10,535,579 10,511,852 10,500,860 10,488,605
Less total production costs
Gross profit 692,947 821,389 950,920 1,081,109 1,088,720 1,096,749 1,112,421 1,136,148 1,147,140 1,159,395
Tax 242,531 287,486 332,822 378,388 381,052 383,862 389,347 397,652 401,499 405,788
Net profit 450,416 533,903 618,098 702,721 707,668 712,887 723,074 738,496 745,641 753,607
Accumulated 450,416 984,318 1,602,416.40 2,305,137 3,012,805 3,725,692 4,448,766 5,187,262 5,932,903 6,686,510
undistributed profit
ANNEX VII
DEBT SERVICE SCHEDULE AND COMPUTATION
PAYMENT OF EQUAL ANNUAL INSTALLMENTS
Total
A. Debt service
1. First year Loan
a. Interest 87,377 82,747 77,028 70,650 63,539 55,610 46,769 36,911 25,919 13,664
b. Repayment of principal 44,609 49,739 55,459 61,837 68,948 76,877 85,718 95,576 106,567 118,822
ANNEX VIII
CASH-FLOW STATEMENT
FOR
FINANCIAL PLANING
Table 25 Projected Cash flow statement
Item description
A. Cash - inflow 10,653,733 9,562,587 10,727,389 11,892,188 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000
1. Financial resource 2,500,133
(total) 244,187 244,189 244,188
2. Sales revenue 8,153,600 9,318,400 10,483,200 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000
B. Cash – outflow 10,206,486 9,036,983 10,123,310 11,209,864 10,968,340 10,971,150 10,976,635 10,984,940 10,988,786 10,993,075
1. Total assets schedule 2,500,133 244,187 244,189 244,188
including replacement
2. Operating costs 7,331,836 8,372,824 9,413,812 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801
3. Debt service (total)
a. Interest 87,377 82,747 77,028 70,650 63,539 55,610 46,769 36,911 25,919 13,664
b. Repayment 44,609 49,739 55,459 61,837 68,948 76,877 85,718 95,576 106,567 118,822
4. Tax 242,531 287,486 332,822 378,388 381,052 383,862 389,347 397,652 401,499 405,788
C. Surplus (Deficit) 447,247 525,604 604,079 682,324 679,660 676,850 671,365 663,060 659,214 654,925
D. Cumulative cash balance 447,247 972,851 1,576,930 2,259,254 2,938,914 3,615,764 4,287,129 4,950,189 5,609,403 6,264,328
ANNEX XII
TOTAL INVESTMENT COSTS
Table 26 Total investment costs”000”
ANNEX XIII
TOTAL ASSETS
ANNEX XIV
SOURCES OF FINANCE
Table 28 Sources of finance
ANNEX XI
SUMMARY OF FINANCIAL EFFECIENCY TESTS
Table 29 Summary of financial efficiency tests
Project year
Project year 1 2 3 4 5 6 7 8 9 10
Capacity utilization 70% 80% 90% 100%
Financial ratio in %
1. Gross profit : Revenue 8% 9% 9% 9% 9% 9% 10% 10% 10% 10%
2. Net profit : Revenue 6% 6% 6% 6% 6% 6% 6% 6% 6% 6%
3. Net profit : initial investment 41% 47% 52% 58% 58% 58% 59% 61% 61% 62%
4. Net profit : Equity 138% 144% 149% 154% 155% 156% 158% 162% 163% 165%
5. Gross profit : Initial investment 63% 72% 81% 89% 89% 90% 91% 93% 94% 95%
6. Operating costs : Revenue 90% 90% 90% 90% 90% 90% 90% 90% 90% 90%
ANNEX XV
CALCULATIONS OF PAYBACK PERIOD
Table 30 Calculation of payback period”000”
ANNEX XVI
CALCULATIONS OF NET PRESENT VALUE AT 17% D.F.