Technical Specifications (MES SPEC - NO.17T6017-SP)
Technical Specifications (MES SPEC - NO.17T6017-SP)
Technical Specifications (MES SPEC - NO.17T6017-SP)
SPECIFICATIONS
COPY RIGHT & PROPERTY RIGHT
This document is the property of MITSUI ENGINEERING & SHIPBUILDING CO., LTD (MES).
The data or information hereon shall not be copied, reproduced, loaned or used in whole
or in part, for any purpose, without a written permission from MES.
CONTENTS
SECTION 1. GENERAL
1-1. General
1-2. Features
1-3. Applicable Standards and Rules
1-4. Design Condition and Criteria
1-5. Delivery Condition
1-6. Scope of Quotation
1-7. Tools and Accessories
1-8. Documents and Drawings
1-9. Reserve Right for Alteration of Design
1-10. Guarantee
SECTION 2. MANUFACTURING
2-1. Design and Manufacturing
2-2. Materials
2-3. Inspection
2-4. Painting
2-5. Packing and Transportation
2-6. Field Erection, Adjusting and Test
1 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
ATTACHMENTS;
1. General Arrangement ................................................ 17T6017-GA
2. Gantry Runway Rail Tolerances ................................ 1-C311-3
3. Specifications of Crane Management System ........... 17T6017-CMS
4. Sub-Contractors and Suppliers List ........................... 17T6017-SL
1 - 2
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
SECTION 1. GENERAL
1-1. GENERAL
(1) This Specifications, together with the attached drawings, provides all the criteria for the
design and construction of the crane to be used for handling of containers.
The crane registered in the trade name of PORTAINER® CRANE is a rail-mounted, electric
powered, semi-rope trolley, travelling tower, hinged boom, gantry type container handling
crane.
(2) If there is the item with ”(OPTION)” in SECTION 7, the item is not included in tender price.
It shall be quoted separately.
(3) The crane shall be designed for easy maintenance and easy replacement.
Patent Note
Certain assemblies and components of the equipment described in this Specifications are either
covered by valid Japan, U.S. and other foreign patents or are the subject of patent applications
presently pending in Japan, U.S. and in certain countries.
1-2. FEATURES
All motions required for container handling shall be operated from operator’s cab located
under the trolley, and it provides rapid, safe, efficient handling of containers by a single
operator.
The operator’s cab, which is located under the trolley, travels with the trolley and provides
the operator with full visibility at all times.
(3) Control
The variable voltage control system of Inverter is applied to the main hoist, trolley traverse,
boom hoist and gantry travel. Systems are digitally controlled using PLC for smooth
operation as well as easy adjustment and maintenance with their diagnostic functions.
1 - 3
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(4) Structure
Gantry structure shall be of welded rigid frame, box type construction and field joints shall be
made by high-strength bolts or field-welding.
As for the safety device, the automatically stop limit switches shall be provided, which work
at both hoist and lower ends, both trolley traverse ends, and boom rise and lower ends.
In addition, emergency stop push buttons shall be provided on the crane to shut control
power and power of the electrical motors in case of emergency.
Spreader tilting device shall be provided to adjust the container to match the variations of
ship trim.
The Crane to be furnished under this Specifications shall be designed and manufactured, except
where modified by this Specifications, in accordance with the standard specifications listed below.
These are to be considered equivalent to the national standard specified in the Purchaser’s
specification.
1 - 4
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Note : As for details not specifically described in the above standards, the standards of crane
maker and the standards of material and equipment suppliers shall be applied.
The structural design shall be based on the structural calculation standard for
MITSUI-PACECO PORTAINER® CRANE, except those modified herein.
a. Load factor
Service factor : 1.17
Impact factor : 1.6
b. Wind load
Speed (m/s)
Operating condition 20
Stowed condition 40
c. Earthquake load
Horizontal direction : 0.2G
The mechanical design and machine elements shall be based on the Japanese Industrial
Standard practices and Manufacture’s Standard practices, except where prescribed in this
Specifications.
a. Classification of mechanisms
1 - 5
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Class of operation T8 T8 T4 T4
State of loading L2 L2 L3 L2
Classification of M8 M8 M5 M4
mechanisms
Load factor 1.30 1.30 1.16 1.12
b. Bearings
Bearings have the following B-10 bearing life based on average container load at rated
speed.
B-10 life
Main Hoist 25,000 Hr
Trolley Traverse 25,000 Hr
Gantry Travel 3,200 Hr
Boom Hoist 3,200 Hr
c. Gearing
Main hoist, boom hoist, trolley traverse and gantry travel gearing shall be calculated
based on ISO standard or AGMA standard.
d. Wire rope
Wire rope for main hoist and boom hoist shall have a safety factor of not less than 5,
considering reeving efficiency, based on the manufacturer’s catalog breaking strength
for the following design loads:
Gantry rail installations on docks for cranes shall be set by the Purchaser, and it shall be set
in accordance with attached ”GANTRY RUNWAY RAIL TOLERANCES (1-C311-3).
1 - 6
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Operating Condition
Load : 61 tons
60 tons / wheel 48 tons / wheel
Wind : 20 m/sec
Boom : Down
Stowed condition
Load : Without load
48 tons / wheel 65 tons / wheel
Wind : 40 m/sec
Boom : Up
The equipment shall be delivered on the “DAT Kijing, Western Kalimantan, Indonesia”.
1 - 7
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
OUT OF
CONTRACTOR’S
ITEM Q’TY CONTRACTOR’S
WORK
WORK
Portainer 2 ○
Telescopic spreader 2 ○
Export packing - ○
Loading work - ○
Transportation to site - ○
Note) Electric power for testing at site shall be prepared by the Purchaser.
1 - 8
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
OUT OF
CONTRACTOR’S
ITEM Q’TY CONTRACTOR’S
WORK
WORK
Spare parts - ○
Installation ○
Installation ○
Installation ○
Design - ○
Installation ○
1 - 9
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
OUT OF
CONTRACTOR’S
ITEM Q’TY CONTRACTOR’S
WORK
WORK
Design - ○
Cable drum for
crane power Supply ○
supply in the pit
Installation ○
Design - ○
Covers with cable
guide for the cable Supply ○
pit
Installation ○
Design - ○
Junction box for
crane power Supply ○
supply in the pit
Installation ○
1 - 10
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) Tools
(2) Accessories
1 - 11
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
The Contractor shall submit the following drawings for approval as a rule before beginning
manufacture:
The Contractor shall submit the following in (3 copies) as final drawings and manuals:
1 - 12
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Manuals for:
j. Instruction and maintenance manuals
They shall include the following documents.
o Repair and maintenance manuals
o Inspection items list for dailiy , weekly, monthly and annual inspection
o Circuit diagram
o Maintenance manuals for bought-in components
o Instruction manual of drive system
o Instruction manual of PLC Control System
o Maintenance manual of spreader
k. Operation manual
a. Mill sheet
b. Shop inspection report
c. Test certificate of wire rope
d. Inspection report at site
(4) Language
(5) Filing
The final drawings shall be reduced to A3 size which letters shall be readable.
Final submittals shall be bound in a two-ring or post binder which has a good durability.
When the strength, efficiency and function of the crane will not be affected, the Purchaser will be
requested to approve of the contractor’s partial alteration or correction of the specification and
the attachment after due consultation with the Purchaser.
1 - 13
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
1-10. GUARANTEE
(1) The Contractor shall guarantee that the main structures, mechanical and electrical
components and paint thereof shall be free from all defects in design, materials, equipment
and workmanship in accordance with current industrial standards while in normal container
handling use and service for period of 12 months from the date of taking over or 16 months
from the date of FOB Japan, whichever comes earlier.
(2) If any defects due to design, materials, equipment and workmanship are found within the
said period, the Contractor shall improve, repair or replace the said defect without any
charge to the Purchaser.
(3) The Contractor shall not be responsible for any consequential damage and defect arising
from the original defect or damage.
Also, the Contractor shall not responsible for damage or defect due to the equipment or
service supplied by the Purchaser, and not responsible for damages or defects due to the
results of abuse of mishandling or misuse by the Purchaser.
1 - 14
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
SECTION 2. MANUFACTURING
(1) Design
b. The Contractor shall basically manufacture the crane after receiving the Purchaser’s
approval.
The dwgs. for approval shall be returned within two (2) weeks.
(2) Workmanship
b. Parts which require heat treatment from the viewpoint of strength among those parts,
such as gears, shaft, wheels and screws rods, shall be subjected to suitable heat
treatment depending on respective requirements.
c. Major parts made of forged steel or cast iron shall be annealed so as to eliminate
residual stresses.
d. Holes for bolts shall be made by drill, and these holes shall be free from burrs or the
like.
(3) Welding
a. Each welding part shall be free from defects such as cracks, undercuts, overlaps or
craters, which are detrimental to the weld strength.
b. The welding work shall be carefully performed by skilled welders who have at least
passed the examination mentioned in "Standard Qualification procedure for Welding
Technique" which is specified in JIS Z 3801, or welders equivalent to those having the
above qualification.
c. Welding shall mainly adopt arc welding and CO2 gas shielded arc welding.
d. All major welds which are subjected to over 84% of allowable stress shall be
inspected and guaranteed by X-ray test or ultrasonic test for up to 10% of butt weld
length to be inspected.
2 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
In this case, the allowable stress of the welded parts shall be 100% of basic allowable
stress.
2-2. MATERIALS
(1) The materials used for major parts of this crane shall be of the high quality and free from
defects of any kind, and also of recent manufacture.
(2) All materials shall conform to the applicable specification of Japanese Industrial Standard,
Japanese Standard of Crane Structures or equivalent.
(3) The following materials or equivalent shall be selected for main parts of the crane by the
Contractor.
Portion Material
Steel structural parts SS400, SM400, SM490, SM490Y, SM520, SM570, STK400,
STK490, STKR400, STKR490, NK(KA, KA32, KA36), AB/BV/LR(A,
AH32, AH36), NV(NVA, NVA32, NVA36)
Bolts and nuts SS400, S35C, S45C, SNC436, SCM435, SCM440, SUS304, F8T,
F10T, S10T
Drum SS400, SM400, SM490, SM490Y, SM520
Rope sheave S25C, S35C, S45C, SC450, SS400, FCD450, FCD500
Shaft and pin S35C, S45C, SNCM625, SCM430, SCM440
Brake wheel FC250, FCD450, FCD500, SM400, SM490, SS400,
Manufacturer’s standard
Brake shoe SS400, FC200
Pinion S45C, SCM415, SCM420, SCM435, SCM440, SNC631
Gear S40C, S45C, SCM415, SCM420, SCM430, SCM435, SCM440
Wheel SSW-Q, SSW-R, SCMn2, S35C, SCM440
Bush LBC3, PBC3, OILLESS BUSH, TEGO
Bearing housing SS400, SM400, SC450, FCD450, FCD500
Gear box SS400, SM400, SC450, FC200, FC250, FCD450
2 - 2
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
2-3. INSPECTION
The Contractor shall submit an inspection and test procedure to the Purchaser and shall
conduct the test and inspection after getting an approval from the Purchaser in accordance
with the approved inspection and test procedure.
Furthermore, when the tests and inspections are finished, the Contractor shall collect the
test or inspection results in order for preparation of the test reports, and shall submit them
to the Purchaser.
If the Purchaser requires that the inspection at work shop is performed by the third
inspection, the number of times and contents which are inspected by him shall be proposed
by the Contractor and discussed with the Purchaser as the inspection is usually performed
by self-inspection according to ISO 9001 certificate.
For the materials adopted for the following components, the Contractor shall submit the mill
sheet or material test reports to the Purchaser, which are prepared based on JIS or
Manufacturer’s standards, or the test records prepared by other manufacturer.
o Portal
o Boom
o Forestay
o Trolley girder
o Equalizer beam and bogie
o Trolley frame
o Spreader frame
o Pinion and gears for main hoist, trolley traverse, gantry travel and boom hoist.
o Gantry wheels and trolley wheels.
o Twist-lock
c. Wire ropes
2 - 3
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
d. Electric motors
The electrical equipment manufacturer shall supply various tables and graphs for
each main A.C motor which shall contain the following information.
o Line voltages
o Line currents
o Other references’ as considered appropriate
The electrical equipment manufacturer shall also supply test reports for transformer
and etc.
o Dimensional check
o Inspection for fabrication and appearance
o Running test of each drive mechanism with no-load condition.
o All coupled machinery shall be checked for smooth operation.
c. The total assembly inspection and reeving of ropes shall not be carried out at factory
if Portainer is assembled at site.
2-4. PAINTING
(1) All paint works including surface preparation and application of shop primer shall be
performed in compliance with the Specifications, contractor’s practice and Maker’s
recommendations at works.
(2) Exterior (exposed) surface shall be coated in accordance with following coating system.
(3) Interior surface of non Air-tight areas which has big holes shall be painted with shop primer
and undercoat. Air-tight areas of interior surface of the box and tubular sections shall not
be coated.
(4) Machinery units and electrical equipment shall be shop-finished in accordance with the
standard practice of respective manufacturers.
2 - 4
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(5) Generally, galvanized parts, chromium plated parts, brass, bronze, aluminum, stainless
steel, plastic, glass, rubber, etc. shall not be coated with paint except otherwise specified.
COATING SYSTEM
Total 220 μm
(1) Packing
b. All packing and protection shall be carried out in accordance with the Contractor’s
practice.
c. After shop assembly, the crane shall be carried on the barge/ship in the totally
assembled condition.
d. Before the voyage, the crane shall be secured sufficiently to endure the various
external forces during the voyage.
(2) Transportation
(3) Storage
The Purchaser shall be requested to provide an erection area including storage area.
2 - 5
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
a. No load test
d. Insulation test
2 - 6
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) Type of crane : Self-propelled trolley, hinged boom type gantry crane
(4) Test load for over load test : 125% of rated load
(5) Container type : ISO 20’, 40’ and up to 53’ containers with ISO
corner fittings at 20’, 40’ or 45’ position
(9) Lift
a. Above the top of : 36.0 m
seaside rail
b. Below the top of : 17.0 m
seaside rail
c. Total lift : 53.0 m
3 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(13) Gantry rail level : Same level on landside and seaside rail
(15) Overall length of : Gantry travel range from central feeding point
gantry travel shall be +/-300 m.
(20) Speed
a. Hoisting and lowering
(a) only spreader : 180 m/min
(b) rated load : 80 m/min
3 - 2
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
a. Blank
b. Auxiliary power for space heater, aviation obstruction light and others from wharf
level.
AC400V, 50 Hz, Three-phase
a. AC motor
A.C. 400V, 50 Hz, three-phase
(3) Control
a. Flood light:
AC200V, 50 Hz, single-phase
b. Fluorescent light:
AC200V, 50 Hz, single-phase
c. Incandescent light:
AC200V, 50 Hz, single-phase
(7) The Portainer is equipped with one (1) diesel engine and one (1) AC generator to
supply the electricity for container handling operation. Refer to the Section. 7-1.
3 - 3
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) Portal frame shall be of welded rigid frame, box type construction except A frame
supports and leg diagonals, and shall have enough strength and rigidity.
(2) Field connections shall basically be made by high strength bolting and/or field welding.
(3) High strength bolting shall conform to JIS B1186-70 specification and are not
galvanized.
(4) Jacking points of the crane shall be provided on the sill beam.
4-2. GIRDER
(2) The trolley girders shall be connected to the tower frame by high strength bolting or
welding.
(4) The trolley rail shall be JIS 37 kg/m rail except at boom hinge. The rails at boom
hinge shall be of short rail shaped from JIS 73 kg/m rail.
(5) Two end stoppers for buffers shall be provided to the end of the girder.
4-3. BOOM
(2) The boom shall be hinged at the heel end, and a wire rope hoisting system shall be
provided to the end of the boom so that the boom structure can be raised into a near
vertical position for clearing ship’s superstructure and rigging.
(3) When the crane boom is in the load-handling position (lowered), it is supported near its
4 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(4) Control box for raising and lowering the boom structure shall be provided on the
waterside tie beam near the boom hinge point.
(5) The boom structure shall be provided with its own system of walkways to provide
access to all parts requiring service and maintenance.
(6) Two end stoppers for trolley buffers shall be provided to the end of the boom.
(1) The trolley shall be a self-propelled type. It can travel from the back-reach end of the
girder to the out reach end of the boom.
(2) The trolley frame shall be of welded, rigid frame construction using welded and/or
rolled structural sections and shaped steel lateral bracing.
(3) They shall be so designed and manufactured as to be robust enough to withstand the
various forces caused at the time of acceleration and deceleration of its traversing
movement at high speed.
(4) The trolley frame shall be supported with four (4) wheels.
(5) The trolley frame shall be fitted with safety pads so that it does not fall down even if the
wheels and axles shall be damaged or broken.
(6) The operator’s cab shall be suspended under the land side end of the trolley frame by
means of suitable brackets, and traverse with the trolley.
(7) The festoon cable traction arm for power supply for the trolley traversing and the
junction box, shall be located on the trolley.
(8) Hydraulic bumpers shall be provided at four corners of the trolley frame for safety.
Each pair shall be capable of absorbing and dissipating the impact of collision against
the end stop of the traversing at 70% rated speed with power off.
4 - 2
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) The machinery house shall be constructed of welded steel plate and shaped steel
construction, and installed on the land side leg tie beam.
(2) The machinery house shall be of a suitable size for access around all machinery and
electrical parts to allow for maintenance and servicing.
(3) The machinery house shall be furnished with main hoist and boom hoist driving
machinery, as well as electrical equipment.
(4) An access hatch shall be provided in the machinery house deck, sized to permit
removal of the largest piece of equipment to ground level, by virtue of an overhead
service hoist provided for this purpose.
(5) Removable stanchions with safety handrails shall be provided around the opening of
access hatch.
(6) Two weather-proof metal sliding doors with lock and safety glass window in upper
panel shall be provided.
(7) The boom hoist wire rope shall not pass through the roof of the machinery house but
through the waterside end of the machinery house and the opening shall be equipped
with flexible rubber plates.
(8) The machinery house shall be pressure ventilated by two forced air blowers to permit
ample cooling effect from filtered air, to ensure satisfactory operation of all machinery.
(9) Well air-conditioned electrical room, which includes skeleton type electrical panels,
shall be installed in the machinery house.
(1) The operator’s cab shall be designed taking into the consideration of visibility,
operation ability and safety under all crane operations, and it shall be fixed securely
under the trolley.
(2) The cab shall be of a steel construction, and it shall have windows with tinted glass
and safety glass on all sides in order to provide excellent visibility for all the operations
controlled therefrom.
(3) A sliding access door with a lock shall be provided on the rear wall.
Access to cab shall be via a suitable platform provided at the landside leg, and also
access ladder from/to the trolley shall be provided for maintenance service.
4 - 3
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(4) The walls shall be covered with two (2) layers of steel plate and glass wool in between
for minimizing thermal gain.
(5) The floor shall be covered with two (2) layers of steel plate, and the space between two
(2) plates shall be used for electric wiring.
(6) The control desks, foot-switch and an air conditioner shall be provided.
(7) A bucket seat, adjustable for height and distance from the front window shall be
provided and it shall be so arranged that the operator can comfortably reach all the
controls and a foot switch.
(8) A service platform for cleaning the bottom glass window of the cab shall be provided
under the operator’s cab.
These incidental structural parts shall be designed and manufactured on the basis of the
following contractors standards. Stairways, ladders and platforms shall have double handrails
and toe boards.
Stairs, ladders, platforms and walkways, except those welded to structures, shall be protected
by hot dipped galvanizing instead of painting.
(1) Stairways
a. Width
main stairway : 600 mm (abt. 23”)
sub-stairway : 500 mm (abt. 19”)
(2) Ladders
4 - 4
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(3) Handrails
c. The handrail shall be made of steel pipe, and its stanchion shall be made of
angle shaped steel.
a. Width
main walkway : 600 mm (abt. 23”)
sub-walkway : 500 mm (abt. 19”)
b. The floor plates shall be made of expanded metal except machinery house.
4 - 5
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) The main hoist equipment shall be furnished in the machinery house.
(3) The output shaft shall be directly coupled to the drum with a spline gear coupler specially
selected for vertical shear resistance and torque rating.
(4) The reduction gear shall be of the totally enclosed, oil bath lubricated type.
(5) The brake shall be provided on the input shaft of the gear reducer which works at the time
of cutting off the electric power supply.
(6) The hoist ropes shall be wound on to the drum in a single layer.
(7) Automatic slow-down and stop limit switches for hoisting and lowering shall be provided.
(8) The back-up limit switch for the highest level shall be installed on the trolley.
(9) The main hoist reeving shall be four (4) fall system reeved through by two (2) ropes.
(1) The spreader can be adjusted to the trim, list and skew.
(3) The spreader tilting device shall consist of four (4) sets of screw-jacks and AC motors,
and be arranged at the end of girder.
(4) All three (3) motions shall be controlled from the operator’s cab.
(5) The mechanical type snag load protection shall be also incorporated into the spreader
tilting mechanism.
Note : Specified angles shall be adjustable angles by individual motion at 4 m above the ground
level to the bottom surface of the spreader with spreader only.
5 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) Local control switch boxe to allow convenient re-reeving of main hoist rope and boom
hoist shall be provided near the driving device in the machinery house.
(1) The trolley traverse equipment shall be self propelled trolley type and they shall be
furnished on the trolley.
(2) The trolley shall be of hanging typed trolley according to adopting of the mono box girder
and boom structures.
(3) Each set of the trolley traverse equipment shall consist of;
One (1) set of gear reducer, one (1) AC electric motor, one (1) AC thruster disk brake, one
(1) wheel, one (1) wheel shaft and couplings at each corner.
(4) The four (4) sets of hollow shaft typed gear reducers shall be applied so that the overall
width of the trolley is kept minimum.
(5) The brakes shall work at the time of cutting of the electric power supply.
(6) Trolley traverse shall be controlled so as to automatically slow-down and stop at both
ends of trolley traverse.
(7) The back-up limit switches at both ends of trolley traverse shall be provided.
(8) The trolley wheels shall be of double flanged type to pass through the sub rails which are
installed at boom hinge.
(1) The boom hoist equipment shall be furnished in the machinery house.
(3) The output shaft shall be directly coupled to the drum with a spline gear coupler specially
selected for vertical shear resistance and torque rating.
(4) The reduction gear shall be of totally enclosed, oil bath lubricated type.
(5) The brake shall be provided on the input shaft of the gear reducer which works at the time
5 - 2
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(6) The hoist ropes shall be wound onto the drum in single layer. Two separate ropes shall
be used.
(7) The automatic slow-down and stop limit switch for the hoisting and lowering function shall
be provided.
(8) The boom hoist shall be interlocked with main hoist and trolley drive so that main hoist and
trolley traverse shall be operated only when boom is at horizontal position.
Also the boom hoist shall be interlocked by means of a limit switch so that it can be
operated only when the trolley is located in the parked area.
(1) The crane shall be carried on double-flanged, forged steel crane wheels, mounted in
equalizer trucks and equalizing beams to ensure even distribution of wheel load.
(2) Each corner shall be fitted with four (4) sets of gantry travel driven and braked system.
Therefore, 50 % wheels of the total number of wheels shall be driven and braked.
(4) Energy absorbing bumpers shall be provided on each corner. Each pair shall be capable
of absorbing and dissipating the impact of collision against the end stop of the gantry
travel at 70% speed with power off.
(5) Rail sweeps shall be provided in front of the outer wheels at each corner.
a. Two (2) sets of stowage pins shall be provided, one (1) at each rail side gantry sill
beam to hold the crane from moving longitudinally (gantrying) under stowed conditions.
b. These stowage pins shall be manually inserted into the runway anchor brackets.
c. The stowage pins shall be interlocked with the gantry travelling circuits, to prevent
gantry motion unless all pins are fully released.
5 - 3
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) The type of crane parking brake shall be self-lock, electro-hydraulically released rail clamp.
(2) The crane shall be equipped with parking brakes for each rail, and capable of holding the
crane at a gust wind load of 35 m/sec.
(3) These rail brakes shall be automatically activated according to the gantry motion.
(4) The brake shall be automatically activated at emergency condition, such as cutting off the
electric power supply.
(5) The brake shall be interlocked with gantry travelling motors, to prevent gantry motion
unless they are released.
5-9. HEADBLOCK
(1) The head block shall be suspended by the main hoist ropes through sheaves.
(2) The connection between head-block and spreader shall be manually operated twist-lock
type, quick-change connection.
(3) Interlocks shall be provided to prevent hoisting unless the twist-locks are fully engaged.
(4) Electric power supply from trolley shall be via a single multi-core cable, which
automatically coils or uncoils into/from a collector tub mounted on the head-block, during
hoisting/lowering motions.
(5) Manlift space fenced with handrail shall be prepared on the headblock.
(1) The spreader shall be of the telescopic type, and capable of handling two (2) 20’
containers with an adjustable shift(gap) for 0 to 1.6m at the same time in addition to
handling single 45ft, 40 ft and 20 ft containers without interchange of the spreader.
(2) The spreader shall be connected by twist-locks to the head block, such twist-locks will be
operated manually.
(3) The spreader shall have two (2) sets of extending rigid “U” frame beam units supported in
a rigidly braced stationary frame, and sliding on hardened rails on guide shoes.
(4) The telescopic frame motion shall be driven by the hydraulic motor and chains.
5 - 4
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(5) The spreader-bar sliding extension members shall be hydraulically held in place at the 20
feet, 40 feet and 45 feet position.
(6) A hydraulically actuated twist-lock assembly shall be mounted at each of the four (4)
corners of the spreader. Also, four (4) sets of the twist-lock assembly shall be mounted at
the center housing for 2-20’ container handling.
(7) The spreader shall have four (4) eye-plates for lifting damaged containers. Each
eye-plate shall bear 10.1 MT in case of vertical load.
(8) An indication lamp shall be provided in the operator’s cab to indicate whether twist-locks
are in the “locked” or “un-locked” position.
(9) Each corner of the spreader shall have an independently controllable, hydraulically
actuated guide flipper providing at least seven (7) inches of gather effect.
(10) One (1) electro-hydraulic power unit (one motor, one pump type) shall be mounted on the
spreader.
(12) Electrical connections between head-block and spreader shall be via quick release
plug/sockets or couplings.
(14) Sensing device for the landing of the spreader shall be provided, and interlocks shall be
provided so that the twist-lock can be rotated only when the spreader is landed on a container.
(1) The electrically operated boom latching device shall be provided on the top of the A frame
to hold the boom secure in the stowed position.
(2) The boom latch shall engage automatically to lock the boom at the stowed position and
shall be remotely released by push button at the boom hoist control box provided near the
foot of A frame.
(3) Bumpers shall be provided to absorb the shock of the boom entering the latches.
5 - 5
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) The machinery house shall be furnished with a long lift service hoist with electric drive to
hoist, long-travel (gantry) and cross-travel (trolley).
(2) This hoist shall be able to lift the heaviest component, reach to all major machinery items,
and be able to lower same to dock (ground) level via access hatch in machinery house
floor.
(3) The lift above machine deck shall be selected so that the largest component except main
hoist gear reducer assembly can be carried over the machines on the deck.
(1) A hydraulically operated catenary trolley rope tensioner shall be furnished to maintain
proper rope tension during trolley traverse operation.
(2) The catenary trolley rope tensioner shall consist of one (1) set of the electro-hydraulic
power unit, two (2) hydraulic cylinders, and two (2) tension sheaves provided at cylinder
rod end.
5-14. LUBRICATION
(1) Oil lubrication shall be provided for totally enclosed gear reducers, including oil level
indication, and grease lubrication shall be provided for open gears.
(2) Lubrication for other mechanical operating parts shall be by means of high pressure
grease gun.
(3) The lubricating fittings of journals of bearings shall be readily accessible, or shall have
lubrication points ganged to battery plates at a proper platform.
(1) The machinery house shall be pressure ventilated to permit ample cooling effect from
filtered air, to ensure satisfactory operation of all machinery.
5 - 6
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(1) The purpose of the supports is to reduce the slack due to rope catenaries and permit
accurate positioning of the spreader and lifted load.
(2) The catenary rope support system shall consist of two (2) catenary support trolleys, one
(1) set of rope tensioner and rope reeving system.
One trolley is provided between the main trolley and girder end, and the other one is
provided between the main trolley and boom end.
(3) When the main trolley traverse, each catenary support trolley is located around the
midpoint between the trolley and both ends of the trolley runway.
(4) In case of articulated boom, before the boom is hoisted, seaside catenary support trolley
shall be located near boom articulate pin to support main hoist and trolley traverse rope by
the shift device.
An elevator shall be furnished at the land side leg and the specification shall be as follows:
(1) Type : Rack-pinion type
(2) Load capacity : 240kg
(3) Speed : Approx. 22m/min.
(4) Operation : Semi-automatic control
(5) Cage dimension : Approx. 0.75×1.0×2.2 (m)
(6) No. of landing floor : 3
o Machinery house level
o Operator’s cab level
o Near the top of the sill beam
(7) Power supply : Cable trolley type
(1) A air compressor with horse reel shall be provided in the machinery house.
(2) Capacity
Q’ty : 1 set/crane
Output : 2.2 kw
Rated pressure : 9.0 kg/cm2
Delivery rate : 165 l/min.
5 - 7
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
a. The rope drum shall be of rolled, welded, steel construction, and its rope grooves shall
be machined accurately to suit the rope.
b. The drum shall be furnished with ball or roller bearing on its shaft end.
c. The drums shall be designed with sufficient length to spool the maximum length of rope
required in a single layer. In addition, two (2) dead turns shall remain on the drum at
each anchored end and one (1) spare turn at the other end.
d. The drum pitch diameter shall be selected using a minimum of thirty (30) times of the
rope diameter.
(2) Sheaves
a. The sheave shall be made of ductile cast iron and its rope groove shall be machined
smoothly.
c. The sheave pitch diameter for the main hoist and trolley traverse shall be selected using
a minimum of thirty (30) times of the rope diameter.
d. The boom hoist equipment shall be designed using a minimum of twenty-five (25) times
of the rope diameter for the sheave pitch diameter.
e. The diameter of equalizer sheave shall not be less than sixteen (16) times of the rope
diameter.
b. The main hoist ropes shall be equivalent to 6xFi(29) construction, 180 kg/mm2, and right
regular lay with independent wire rope center.
c. The boom hoist ropes shall be equivalent to 6xFi(29) construction, 180 kg/mm2, and right
regular lay with independent wire rope center.
(4) Gears
5 - 8
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
a. The gear box shall be of split type, and the flanged jointing face shall be specially
considered for the prevention of oil leakage.
b. Vent cap, oil level gauge and drain plug shall be provided for maintenance and
inspection.
(6) Couplings
The connection between motor shaft and reducer, and those portions which need flexible
connection shall be made by coupling with flexible couplings.
Brake wheel shall have sufficient resistance against wear and impact, permit minimum
temperature rise, remain free from deformation and cracks, and be well-balanced.
(8) Wheels
a. Gantry wheels shall be of double flanged type and trolley wheels shall be of double
flanged type, and tread width shall be determined taking into consideration the
installation error of gantry and trolley-rails.
b. All wheels shall have full strength against maximum wheel load.
c. Wheel axles shall be furnished with ball or roller bearings.
d. Wheel size shall be determined based on manufacturer’s standard.
(9) Bearings
a. Shafts and pins shall be designed taking into consideration the dynamic load and
reduced strength due to notch effect.
b. Shafts and pins shall be machined carefully in consideration of their use.
5 - 9
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
All keys and keyways shall be in accordance with the requirements of JIS.
a. All screws and threads shall be in accordance with "Metric system" of ISO.
b. Where practical, all screws, bolts, nuts, washers and other miscellaneous fastenings
and fittings shall be held in such a manner that they shall not come loose due to
vibration.
a. Name plate
Name plates incorporating the maker’s name and the safe working load of the crane,
of sufficient size to be readily legible from ground level, shall be secured in agreed
positions on the crane.
b. Labels
o The label which indicates the motion and the direction of the motion shall be
attached close to each controller in the operator’s cab.
o The label indicating the performance of the equipment shall be attached to proper
place inside the operator’s cab.
o Above labels shall be written in English.
a. Rubber hose
In case of 35 kg/cm2 and 70 kg/cm2 working pressure, rated pressure of hose shall be
105 kg/cm2.
In case of 140 kg/cm2 and 175 kg/cm2 working pressure, rated pressure of hose shall
be 210 kg/cm2.
b. Hydraulic cylinder
Cylinders rods shall be steel with Ni-Cr metal coating and/or stainless steel with Cr
metal coating.
5 - 10
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
a. Model : PTH - 60 - 80
b. Specification of components
Q’ty Specification
Pillow block 2
5 - 11
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
b. Specification of components
Q’ty Specification
b. Specification of components
Q’ty Specification
Pillow block 1
5 - 12
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
b. Specification of components
Q’ty Specification
Intermediate 8
equalizer beam
Main equalizer 4
beam
5 - 13
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
6-1. GENERAL
Since the electrical equipment is subject to vibration and saline environment, the electrical shall
be designed and manufactured for operation in these conditions. Also the water-proof and
corrosion-proof shall be considered for outdoor equipment.
The power shall be supplied to the crane by means of a magnetic coupler or hydro-dynamic
typed motor driven cable reel with round type three (3) cores + earth flexible cable.
Electrical power shall be supplied to the trolley by means of multi-core cables and cable
carriers with anti-friction bearings. (Festoon system)
Electrical power shall be supplied to the spreader by means of a single multi-core cable which
automatically coils and uncoils into a cable winding tub mounted on the head-block, during
hoisting/lowering motions.
Motors located in the main machinery house shall have drip-proof enclosures, whilst ones
mounted on the exterior shall be weather-proof totally-enclosed, non-ventilated, or fan-cooled
enclosure.
Main hoist motor and boom hoist motor shall have cooling fan.
Main hoist, trolley traverse, boom hoist and gantry travel motors shall also be fitted with space
heater.
Electric motors shall be specified on TABLE 1. ”MOTOR LIST”.
6 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(2) Brakes
The electrical brakes for all motions shall be designed so that if the control power is dienergized
all brakes may close immediately.
a. Main hoist
The brake shall be AC thruster operated disk type. Two (2) brakes shall be provided
per one (1) set of the main hoist eqipment. The each braking torque shall be more
than 100% of rated hoisting load torque.
b. Trolley
The brake shall be AC thruster operated disk type. The brake torque shall be more
than 100% of rated motor torque.
c. Gantry
The brakes shall be DC magnetic operated disk type integrated into motor. The
brake torque shall be more than 100% of rated motor torque.
d. Boom hoist
The brake shall be AC thruster operated disk type. The brake torque shall be more
than 150% of rated load torque. One (1) emergency electro hydraulic disk brake
shall be provided.
(3) Panels
a. Control panels
Control panels shall be open type and installed in the walk-in type electrical room.
The control panels shall be designed for easy maintenance access, with items of
equipment front mounted and front assembled.
All components installed in the panels shall be provided with symbol markers on which
the same symbol as one used on elementary diagrams shall be printed.
The high voltage incoming panels shall be of cubicle type and installed in the
machinery house.
This panel is used for disconnecting of supplying power.
6 - 2
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
The high voltage combination panels shall be of cubicle type and installed in the
machinery house.
This panel is used for supplying power to main circuits of main hoist/gantry and
trolley/boom hoist.
Power supply for the auxiliary motors and other miscellaneous auxiliary devices shall
also be supplied from this panel.
In the panel, power fuses, magnetic contactor, etc. are fitted.
(Operation of the magnetic contactor of the each panel will be made by push button
switch in the panel.)
Transistor power conversion panel shall be open type and installed in the walk-in type
electrical room.
Three (3) Transistor power conversion units from AC to DC shall be provided for main
motions of the crane, and DC common bus is applied for the emergency case.
Two (2) power conversion units from DC to AC of them shall be used for
hoist/gantry/boom drive, and the other four (4) units shall be used for trolley drive.
All power conversion units shall be variable voltage variable frequency control system.
(4) Transformers
The high-voltage transformer shall be dry type and equipped with two, 2-1/2 percent taps
above and below normal at the high voltage windings. Protection plates for contacting
between high voltage and low voltage winding shall be grounded. Low voltage
transformers shall be dry type. All transformers shall be continuous rating.
The resistor shall be made of steel plate and open grid type.
a. Two (2) master controllers shall be provided. One (1) master controller shall be used
for hoist/gantry (cross slot universal type). The other master controller shall be used
for trolley-drive function.
b. Each master controller shall be provided with "0" notch mechanical interlock and
stepless type.
c. Signal transmitter fitted in the controller is used for the speed control signal reference.
6 - 3
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
a. Main hoist
Dual limit switches shall be provided, one is an encoder type and the other is a
weighted lever type.
An encoder shall be activated at each upper and lower end, and in addition, an
“Ultimate stop limit switch” is also provided; that is a weighted lever type, and
open-circuited by the spreader-bar/head-block making direct contact with the switch
when they are hoisted towards the trolley.
b. Trolley
An encoder actuates to decelerate the trolley before each end of trolley traveling on
trolley rails, in addition, limit switches at each end of trolley rails shall be able to
decelerate and stop the trolley even if the master controller is held in the full speed
position.
c. Boom hoist
Boom hoist and boom hook shall be able to operate by the push button switch on the
boom operation control box installed on the waterside leg tie beam..
Further, the gantry travel shall be able to operate at the boom operation control box.
A suitable interlocking switch shall be provided to prevent the crane boom from being
raised unless trolley is in the designated parked position, and to prevent the trolley and
main hoist from being moved unless the boom is in the fully lowered position.
Also interlocking switch shall be provided, so that gantry travel can’t operate if boom is
in-operation, and inversely boom hoisting can’t operate if gantry travel is in-operation.
d. Limit switches and protections are specified on TABLE 3. "LIMIT SWITCHES AND
PROTECTIONS".
6 - 4
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
One (1) boom operation control box shall be installed on the waterside leg tie beam.
Boom hoist, latch and gantry travelling shall be operated by means of push button
switches fitted on boom operation control box.
Emergency stop push buttons for all major operating functions (Hoist, Trolley & Gantry,
etc.) shall be provided on the control desk, boom operation control box, at four ground
level positions of each leg, machinery house, trolley and E-room, total of nine (9).
6 - 5
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
If main electrical protective devices should be tripped, the related crane operation shall be
stopped and at the same time, the common fault indication lamp and buzzer installed on
the cab control desk shall be energized.
Green lights shall be mounted on the cab control desk to indicate electrical power on.
The contents of the trouble can be confirmed by means of fault display devices of the
electric panel in the machinery house.
Fault diagnostic display is mounted on the control cabinet located in the machinery house.
Faults are stored in the programmable controller memory in the order in which they occur.
A door mounted pushbutton is used to read out each fault, and a key switch to reset the
system.
One (1) spreader indicating box shall be installed in the operator’s cab.
6 - 6
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
The load cells which detect overload with an accuracy of plus and minus 10% when the
spreader has no tilting angle.
6-4. CONTROL
Programmable logic controller shall be used to perform the control logic function on the
crane in place of hardwired relay logic.
Major drive controls including all interlocking and sequencing functions for main hoist,
trolley traverse, boom hoist and gantry travel control, except the emergency-stop and end
of gantry travel limit switches function will be performed by the PLC.
All limit switches, operator control devices and other input/output devices to be wired
directly to closest I/O rack. Inputs and outputs shall be grouped by motion or function.
To minimize number of connections, all external I/O connections shall be in I/O rack
mounted closest to cable entry.
All main drive motions shall be of the speed control, which shall utilize Inverter control.
A.C. motor driving shall be powered from Transistor power conversion units which
respectively supply power for main hoist/gantry travel and trolley traverse/boom hoist
motions, with provision for simultaneous operation of main hoist and trolley traverse or
gantry and trolley traverse functions.
6 - 7
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
The main hoist motor shall be automatically driven with higher speeds by means of field
weakening at light load.
Motors for other auxiliary equipment shall be squirrel cage induction motor and started by
direct-on-line method.
(1) Lighting
A lighting system shall provide adequate illumination for all ladders, platforms, walkways,
machinery enclosures and cab. A system of floodlighting shall provide adequate lighting to
all work areas, including vessel’s cell areas. The illumination of more than average 100
Lux. under the crane measured at ground level shall be achieved.
The ballasts for floodlights shall be high power-factor type. (As for voltage, please refer to
item 6-2.)
Fluorescent lights installed in the machinery house shall be glow-start type, and equipped
with Acrylic resin cover.
Aircraft warning lights shall be installed on the boom and the top of the mast.
Two (2) sets of ventilating fan shall be provided for ventilation in the machinery house.
Ventilation fans shall be equipped with filter.
1 set of window wipers and washers shall be provided on the operator’s cab. Power
source for these shall be DC 24V supplied from cab distribution panel.
6 - 8
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
The crane operator can inform directly to personnel on ground level and vessel. A
voice is announced through five speakers installed on the side of operator’s cab and
each gantry leg.
b. Warning alarm
During gantry travelling, electronic warning sound is given by four (4) speakers
mounted on the gantry legs. Warning alarm shall be activated automatically by
gantry motion.
c. Siren sound
For making attention to personnel on the pier or vessel, siren sound is activating by
pressing a foot switch in the operator’s cab.
If these three system are used at the same time, warning alarm and alarm sound becomes
feeble compare with loudspeaker’s voice.
4-rotating warning lights shall be installed at four corners of the crane legs. These lights
shall be automatically activated by gantry motion.
(7) Anemometer
Anemometer shall be provided for monitoring wind velocity. The anemometer shall have
one adjustable alarm set point for alarm sound.
Two (2)-pole 15A, single-phase convenient receptacle with plug shall be provided as
follows.
6 - 9
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Welding receptacles
Three (3)-poles + Earth pole, three phase, 60A welding receptacle with plug shall be
provided at the following locations.
(9) Intercommunication
a. System components
b. Control
o The lowering motion shall be automatically stopped when all the hoist wires
become slack. This rope tension shall be detected by load cells in the hoist
wires.
o The hoisting speed shall be limited to preset (slow speed) values while the load
cells detect slack in the main hoist wires, and then, when the load cells detect
tension equally in all hoist ropes, the speed can increase according to the setting
of the master controller.
o The slack-rope system shall be able to be switched out of circuit in the event of
any malfunction, allowing the crane to operate normally. This isolation switch
6 - 10
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
o The Load cells which detect overload with an accuracy to plus and minus 10%
when the spreader has no tilting and make alarm with warning lamp shall be
provided on the dead end of the hoisting wire ropes.
In case that the device shall make alarm when the spreader is having some tilting
angle, the operator may check whether the alarm stop or not by operating the
tilting to zero (0) degree.
(1) All wire shall be laid in steel conduits and cable ducts.
Cables on the crane shall be protected against mechanical damage. Wherever practical,
the conduit system shall be concealed within the crane’s structure.
(3) Cables and wiring shall be adequately sized to meet current-carrying requirements.
(4) The conductor sectional area for cables and wires except for internal ones of panels and
others shall be as follows :
o Control circuits except for communication signal circuits : more than 1.25 mm2
(5) All conductors (internal and external to control panels) shall be labeled at both ends with
plastic tubing wire markers.
6 - 11
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
(6) Flexible conduits shall be used for the junction to the inlet of electric machines.
6 - 12
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
MOTORS LIST
Table 1 (1/2)
NO. USE OUTPUT SYN.SPEED VOLTAGE RATING INSULA ENCLOSURE NOTE Q’TY
(KW) (RPM) (V) TION
1 Main hoist motor 420 800/1800 AC400 class Cont. F Drip-proof Squirrel cage 2
Totally enclosed
2 Trolley traverse motor 60 1800 AC400 class Cont. F Ditto 4
outdoor
3 Boom hoist motor 180 1800 AC400 class 30 min F Drip-proof Ditto 1
Totally enclosed
4 Gantry travel motor 13 1800 AC400 class 30 min. F Ditto 16
outdoor
7 Spreader trim, list, skew 5.5 1500 AC400 30 min. E Ditto Ditto 4
9 Trolley rope tension pump 2.2 1500 AC400 Cont. E Ditto Ditto 1
6 - 13
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Table 1 (2/2)
NO. USE OUTPUT SYN.SPEED VOLTAGE RATING INSULA ENCLOSURE NOTE Q’TY
(KW) (RPM) (V) TION
11 M.H. motor cooling fan 7.5 1500 AC400 Cont. E Totally enclosed Squirrel cage 2
12 B.H. motor cooling fan 1.5 1500 AC400 Cont. E Ditto Ditto 1
13 Air compressor 2.2 1500 AC400 Cont. E Ditto Ditto 1
7.5(Hoist) 1
Machinery house 0.75(Traverse) E
14 1500 AC400 Cont. Ditto Ditto 2
maintenance hoist
0.75(Travel)
2
15 Man lift 5.5 1500 AC400 Cont. E Ditto Ditto 1
Note : Above specifications may be chnaged at the design stage.
BRAKES LIST
Table 2
VOLTAGE
NO. USE TYPE RATING Q’TY
(V)
6 - 14
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
6 - 15
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Table 3 (2/2)
6 - 16
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Table 4 (1/2)
Speaker:
Side of operator’s
cab 1
Gantry leg 4
6 - 17
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
Table 4 (2/2)
6 - 18
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD
The Portainer is equipped with one (1) diesel engine and one (1) AC generator to supply the
electricity for container handling operation.
Battery : DC24V
(2) Generator
(3) The electrical equipment used for this Transtainer shall endure fluctuation of ±10% of
rated voltage, ±5% of frequency or less than 10% of total sum of both.
7 - 1
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
DATE :
PROJECT NO. :
MES JOB NO. :
REVISION :
NOTE :
GANTRY RAILS SHALL BE INSTALLED WITH THE TOLERANCES WHICH
ARE DESCRIBED IN THIS DOCUMENT, IN ORDER TO MAINTAIN THE
CRANES’ PROPER PERFORMANCE.
( 5JMI451 / 1-C311-3 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
レール 10 m
上下方向の高低差 レール10 mにつき RAIL ピアノ線または
BEND OF RAIL UP AND < ±5 mm < ±10 mm トランジット
DOWN FOR 10 m BY TRANSIT
上面TOP 側面SIDE
レール継目のくい違い 上面側面ともに
< 0.5 mm < 1.0 mm 鋼尺で測定する。
JOINT DIFFERENCE BOTH TOP AND SIDE BY STEEL SCALE
レール継目のすきま
鋼尺で測定する。
< 5 mm < 5 mm BY STEEL SCALE
JOINT GAP
スパン
ホイルベースの範囲内で
レールの水平差 1 SPAN トランジットで
FOR WHEEL BASE LENGTH < スパン×
1 測定する。
< スパン× SPAN 500
HIGHT DIFFERENCE BY TRANSIT
SPAN 1000
勾配 トランジットで
1 1
< < 測定する。
500 200 10 mごとに測定する
INCLINATION BY TRANSIT
CHECK EVERY 10 m
( 5JMI451 / 1-C311-3 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
( 5JMI451 / 1-C311-3 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
SPECIFICATIONS
( 5JMI613 / 1-C109-15 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
CONTENTS
( 5JMI613 / 1-C109-15 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
PART 1. GENERAL
This crane management system shall be installed on the crane, and includes the
following functions.
( 5JMI613 / 1-C109-15 )
-1-
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
OUT OF
ITEM Q’TY CONTRACTOR’S CONTRACTOR’S
WORK
WORK
UPS
System adjustment - ○
Instruction manuals for maintenance and 1 ○
operation set
( 5JMI613 / 1-C109-15 )
-2-
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
This system shall be connected with crane’s hardware and software through the
crane control units.
For the outline of the system, please refer to Fig.1 SYSTEM CONFIGURATION.
( 5JMI613 / 1-C109-15 )
-3-
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
CRANE CONTROL
UNIT CRANE COMPUTER
M
CPU
MAIN MOTORS
COM. ETHERNET CRT
I/F LCD
UNIT CONTROL
LIMIT SWITCH
M KEYBOARD
~ I/F
MEMORY
DISK
HD
I/F
UPS
I/F USB
CVD/CD-ROM
MODEM
-4-
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
-5-
( 5JMI613 / 1-C109-12 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
-6-
( 5JMI613 / 1-C109-12 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
2. Watch Monitor
1) Operation Stand-By It displays operation condition data or
interlock data for each motion.
2) Watch Monitor It displays the condition of each equipment
(digital data and analog data).
3. Fault Records
1) Fault Record It displays electric fault records.
2) Fault Help Message Edit It edits help messages for each fault.
4. Trace Back
1) Fault Trace Back It displays the fault trace back data (analog
& digital) on the graph or the list.
2) Manual Trace Back It displays the analog & digital data which
was manually collected 1 minute on the
graph or the list.
5. Operation Data
1) Business Record It acquires various operation data and it
displays acquisition data by the list or the
graph.
2) Handling Report
3) Loading Container Graph
4) Unloading Container Graph
5) Container Quantity
6) Working Time Excel Save It preserves working time data in Business
Record
to MS-Excel file.
6. Maintenance
1) Spare Parts Management It displays spare parts data.
2) Maintenance Parts Management It displays present operation results every
each maintenance part.
-7-
( 5JMI613 / 1-C109-12 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
7. Utility
1) Date Time Set It changes date and time of monitoring
system.
2) Operation Data Save/Load It keeps already acquired operation data in
the floppy disk etc. Also, It copies the
operation data of the floppy disk etc. to the
monitoring system.
3) Trace Back Data Save/Load It keeps acquired trace back data in the
floppy disk etc.
Also, it restores kept trace back data in the
floppy disk etc. to the monitoring system.
4) Maintenance Data Save/Load The maintenance data can be preserved at
the floppy disk.
The maintenance data which was preserved
in the floppy disk can be restored as the FD
maintenance data.
5) All Data Save/Load It makes all data backups in the monitoring
system at the floppy disk etc.
6) Password Edit It edits password data for CMS login.
7) Operation Master Table Edit The operation company data and the
operator data to use in operation data mode
can be edited.
8) File Converter It converts operation data, fault data and
maintenance data to text file(*.csv).
-8-
( 5JMI613 / 1-C109-12 )
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
-9-
( 5JMI613 / 1-C109-12 )
MES SPEC. No.17T6017-SL
DATA NO. 1C603-17a
FOR
NOTE) Selection of the following sub-contractors and suppliers listed shall be at manufacturer’s option.
Other sub-contractors and suppliers equivalent to them may be selected with prior notice.
No. Name of components Sub-contractor and supplier’s name Location
1
(1C603-17a.doc)
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
2
(1C603-17a.doc)
MITSUI ENGINEERING &
SHIPBUILDING CO., LTD.
3
(1C603-17a.doc)