INTEGRATED ENGINEERING GROUP

Checked &
Rev. Status Issue date Made by
Approved by
ENGINEERING
00 In Work 13.04.2023 ENGINEER
MANAGER

RIG UP PROCEDURE
HWUHALL-RUP

This document contains IEG Oilfield Services Pte Ltd. legal entity proprietary and confidential information that is legally privileged and is intended
only for the person or entity to which it is addressed and any unauthorised use is strictly prohibited. It is provided for limited purpose and shall not
be reproduced, stored electronically, transferred to other documents, disseminated or disclosed to any third parties without the prior written
consent of the relevant IEG Oilfield Services Pte Ltd legal entity. Any attachments are subject to the specific restrictions and confidentiality
regulations stated therein and shall be treated accordingly. The document is to be returned upon request and in all events upon completion of use
for which it was provided.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 2 of 57
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 3 of 57

TABLE OF CONTENS
1. GENERAL INFORMATION .............................................................................................................. 4

2. PREPARATION FOR INSTALLATION ........................................................................ 4

3. HWUHALL INSTALLATION ......................................................................................... 5

4. INSTALLATION LAYOUT ............................................................................................ 6


4.1 Beak Down Top-Level Assembly of HWUHALL. ...............................................6
4.2 Capping Beam & Skidding System ...................................................................7
4.3 Skid Beam .......................................................................................................11
4.4 Sub Structure & Skidding System ...................................................................14
4.5 Tie Beam & Tie Beam Connection part. ..........................................................18
4.6 SS-Adaptor (ADS) ...........................................................................................22
4.7 Escape Platform & Ladder (ESL) ....................................................................25
4.8 Outrigger .........................................................................................................29
4.9 Work Window & Window Walk Around ...........................................................32
4.10 SS-Adaptor Platform (ADS-02) .......................................................................34
4.11 Sub Structure Ladder (SS-LD) ........................................................................36
4.12 Work Window Ladder (WW-LD) ......................................................................40
4.13 Hydraulic Jack Structure .................................................................................42
4.14 Work Basket & Work Basket Riser..................................................................44
4.15 Escape Telescopic Vertical Ladder .................................................................46
4.16 Work Basket Ladder (WB-LD) ........................................................................48
4.17 Gin Pole ..........................................................................................................54
4.18 Tong Arm ........................................................................................................56

5. RIG DOWN ................................................................................................................. 57


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 4 of 57

1. GENERAL INFORMATION

Purpose of the Rig Up Procedure is for the safe and detailed working practices for
personnel to conduct Rig Up process on the Hydraulic Workover Unit Halliburton,
thereafter described as HWUHALL.

This procedure will describe a systematic step by step installation guideline on the
safe operation for HWUHALL.

The HWUHALL is installed and utilized on both land and off-shore locations. On
land the crane is necessary for lifting each assembly part HWUHALL and setting it
down on the BOP wellhead/platform. For off-shore operation the various packages
comprising the HWUHALL are assembled, erected, or installed using the platform
cranes and equipment.

2. PREPARATION FOR INSTALLATION


Prior to erecting the HWUHALL (installation over the wellhead/platform) take
following steps to ensure a quick and trouble-free installation. Company safety
procedures shall be adhered to during all phases of the testing. Extreme caution
shall be exercised during rigging up to ensure the safety of all personnel within the
vicinity.

All personnel involved with Rigging Up shall have read the procedure before starting
the test.

2.1 Ensure a layout plan for locating the fuel tank, power pack, skid beam, sub
structure, work area, ladder / staircase, gin pole, jack structure, work basket,
etc.…, so that crane lifting up, guying the unit, and installation of the work
basket is facilitated. Be sure to consider access to pipe rack and/or others
item to be inserted or extracted from the well.

2.2 Ensure that reliable and adequate anchors are available with a holding
capability equal to or greater than the strength of the guywire.

2.3 Inspect all item for possible damage incurred during transport or loading/off-
loading operations.

2.4 Ensure that all safety rules and regulations have been implemented to protect
installation personnel equipment.

2.4.1 Protective Gears

ALWAYS WEAR PERSONAL PROTECTIVE EQUIPMENT


SUCH AS SAFETY GLASSES, PROTECTIVE CLOTHING,
SAFETY SHOES, EAR PLUGS, WORKING HARNESS
(WORKING AT HEIGHT) AND SAFETY HELMET AS
DEEMED NECESSARY
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 5 of 57

WORKING AREA TO BE CLEARLY DEFINED AND


CORDONED OFF, ONLY WORKERS THAT ARE
INVOLVED ARE TO BE ALLOWED IN THE DEFINED
WORKING AREA AND TO BE IN PROPER PPE,
WORKERS WITHOUT PROPER PPE MUST BE
IDENTIFIED AND ESCORTED OUT OF THE WORKING
AREA

2.4.2 Lifting and Handling

ENSURE ALL LIFTING GEARS USED IN OPERATION


ARE CLEARLY TAGGED AND CERTIFICATION STILL
VALID AND STAY CLEAR OF EQUIPMENT DURING
LIFTING
BEFORE ANY LIFTING, LIFTING SUPERVISOR AND
TEAM TO DO A WALKABOUT AND DOUBLE CONFIRM
ALL EQUIPMENT IS CLEARED TO USE, AND SHALL
HAVE READ THE TEST PROCEDURE PRIOR TO
COMMENCING ANY TESTING
IF POSSIBLE, REMOVE HEARING PROTECTION FOR
LIFTING. TO ENSURE CLEAR INSTRUCTIONS AND
WARNING CAN BE GIVEN CLEARLY

3. HWUHALL INSTALLATION
The following general sequence installation of the HWUHALL.

1. Attach crane to sub assembly of HWUHALL (skid beam, sub structure, ss-
adaptor, etc..) and lift over wellhead/platform area.

2. Align each sub assembly properly (refer to installations layout for detail) and
secure with bolts and nuts.

3. Install guywire from sub structure, work basket, and gin pole to anchors to
ensure complete stability of the unit. CAUTIONS, keep unnecessary
personnel clear of the wellhead/platform area and do not allow anyone on
the unit until guying operations are completed and checked.

4. Disconnect crane from the sub assembly of unit.

5. Connect all hoses from the hose basket.

6. Refer to the specific section of installation layout for each sub assembly rigging
up.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 6 of 57

4. INSTALLATION LAYOUT

4.1 Beak Down Top-Level Assembly of HWUHALL.

TOP LEVEL ASEMBLY


1. Capping Beam & Gripper Jack
2. Skid Beam
3. Sub Structure & Tie Beam
4. SS-Adaptor
5. Escape Ladder
6. Sub Structure Ladder
7. Outrigger
8. Window Walk Around & Window Structure
9. Work Window Ladder
10. Hydraulic Jack Structure
11. Work Basket & WB-Riser
12. Escape Telescopic Vertical Ladder
13. Work Basket Ladder
14. Gin Pole
15. Tong Arm
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 7 of 57

4.2 Capping Beam & Skidding System

4.2.1 Assembly Preparation

ITEM
DESCRIPTION QTY.
NO.

1 CAPPING BEAM BODY 1


2 UPER PAD CAPPING BEAM 2
3 LOWER PAD CAPPING BEAM 4
4 UPER PAD CAPPING BEAM - INSIDE 2
5 STUD BOLT, M24x3.0x260mm 20
6 HEX BOLT, M24x3.0x200mm W/ 60mm Thread LG 18
7 HEX BOLT, M24x3.0x140mm W/ 60mm Thread LG 4
8 SPRING WASHER, M24 42
9 PLAIN WASHER, M24 18
10 HEX NUT, M24x3.0 58
11 GRIPPER JACK CLAMP 1
12 OE21D-100-CYLINDER 1
13 PIN OD. 95, Ø79.5 - 50mm Length 1
14 COTTER PIN, Ø8 - 140mm Length 1
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 8 of 57

GRIPPER JACK CLAMP

ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 HWU-200T-GTC-01 MAIN CLAMP BODY 1
2 HWU-200T-GTC-02 ADJUST CLAMP PLATE 2
3 HWU-200T-GTC-03 SHEAVE PINS 175 LG 2
4 HWU-200T-GTC-04 CLAMP EXTENSION 4
5 HWU-200T-GTC-05 BOTTOM CLAMP PLATE 1
6 HWU-200T-GTC-06 STOPER TONG DIES 2
7 HWU-200T-GTC-07 EXTENSION SHIM PLATE 2
8 BUY PART UP LIFT HYDRAULIC CYLINDER 1
9 BUY PART COTTER PIN 8.0 x 140mm LG 2
10 BUY PART SLOTTED SPRING PINS D3 x 22mm 8
11 BUY PART TONG DIES 98.4 x 31.2 x 12.7mm 4
12 BUY PART TONG DIES 63.5 x 31.2 x 12.7mm 8
13 BUY PART SPRING WASHER, M10 4
14 BUY PART SPRING WASHER, M25 15
15 BUY PART HEX BOLT, M24 x 3.0 x 120 LG 16
16 BUY PART HEX BOLT, M10 x 1.5 x 60 LG 4
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 9 of 57
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 10 of 57

4.2.2 Installation

CAPPING BEAM & SKIDDING SYSTEM

1. Stud Bolt, M24 X 3.0 X 260 mm Lg, c/w Hex Nut, Flat Washer & Spring Washer,
Qty.: 40 sets. Apply Torque: min. 700 – max.1700 ft.lb

2. Socket Head Cap Screw, M24 X 3.0 X 260 mm Lg, Qty.: 32 sets. Apply Torque:
min. 700 – max.1700 ft.lb
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 11 of 57

4.3 Skid Beam

4.3.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 12 of 57

ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 HWU-SKB-01 NEW MAIN BEAM 1
2 HWU-SKB-01 NEW MAIN BEAM 1
3 HWU-SKB-02 SIDE BEAM 2
4 HWU-SKB-03 SUPPORT BEAM 6
5 HWU-SKB-04 MAIN BEAM EXTENSION 2
6 HWU-SKB-04 MAIN BEAM EXTENSION 2
7 HWU-SKB-05 LOWER CONNECTION PLATE 2
8 HWU-SKB-05 LOWER CONNECTION PLATE 2
9 HWU-SKB-06 UPPER CONNECTION PLATE 4
10 HWU-SKB-06 UPPER CONNECTION PLATE 4
11 HWU-SKB-07 SIDE CONNECTION PLATE 4
12 HWU-SKB-07 SIDE CONNECTION PLATE 4
13 BUY PART REGULAR FLAT WASHER M72 48
HEX BOLT, M72 X 6.0 X 260 mm
14 BUY PART 24
LG, W/ 169 mm THREAD LG
15 BUY PART HEX NUT, M36 X 4.0 76
16 BUY PART HEX NUT, M72 X 6.0 24
17 BUY PART PLAIN WASHER, M36 304
18 BUY PART SPRING LOCK WASHER, M36 152
HEX BOLT, M36 X 4.0 X 160 mm LG, W/ 84 mm
19 BUY PART 16
THREAD LG
HEX BOLT, M36 X 4.0 X 200 mm LG, W/ 84 mm
20 BUY PART 64
THREAD LG
21 BUY PART Hex Bolt M36 x 4.0 x 150 mm Lg, W/84 mm LG Thread 48
22 BUY PART Hex Bolt M36 x 4.0 x 130 mm Lg, W/60 mm LG Thread 24
23 BUY PART HEX NUT, M36 x 4.0 76
24 BUY PART SPRING LOCK WASHER, M36 152
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 13 of 57

4.3.2 Installation

SKID BEAM

1. Hex Bolt, M24 X 3.0 X 200 mm Lg, w/ 60 mm Lg Thread, c/w Hex Nut, Flat
Washer & Spring Washer, Qty.: 36 sets. Apply Torque: min. 700 – max.1700 ft.lb

2. Hex Bolt, M24 X 3.0 X 140 mm Lg, w/ 60 mm Lg Thread, c/w Hex Nut, Flat
Washer & Spring Washer, Qty.: 8 sets. Apply Torque: min. 700 – max.1700 ft.lb
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 14 of 57

4.4 Sub Structure & Skidding System

4.4.1 Assembly Preparation

SUB STRUCTURE ASSEMBLY


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 15 of 57

ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 HWU-200T-SS-01 SUB BASE BEAM 1
2 HWU-200T-SS-02 LEG STRUCTURE 1
3 HWU-200T-SS-04 WASHER, Ø OD 150 x 25 THK 4
4 HWU-200T-SS-05 SUB STRUCTURE CYLINDER PIN 2
5 HWU-200T-SS-06 PAD EYE CYLINDER 4
6 HWU-200T-SS-07 GUIDE BAR 4
7 HWU-200T-SS-09 SUB STRUCTURE CLAMP 6
8 HWU-200T-SS-10 SUB STRUCTURE STEP LADDER 2
9 HWU-200T-SS-11 PIPE SUPPORT BODY 4
10 BUY PART SPILT COTTER PIN, 8 X 100mm LG 10
HEX BOLT, Gr. 8.8, M36 x 4.0 x
11 BUY PART 4
150 Full Thread
12 BUY PART PLAIN WASHER, M36 44
HEX BOLT, Gr. 8.8, M36 x 4.0 x
13 BUY PART 4
90 Full Thread
14 BUY PART PLAIN WASHER, M24 32
15 BUY PART PLAIN WASHER, M30 32
16 BUY PART LOCK WASHER, M24 32
17 BUY PART LOCK WASHER, M30 32
18 BUY PART LOCK WASHER, M36 40
HEX BOLT, M24 X 3.0 X 110 mm,
19 BUY PART 16
W/ 54 mm LG THREAD
HEX BOLT, M30 X 3.5 X 120 mm,
20 BUY PART 16
W/ 66 mm LG THREAD
HEX BOLT, Gr. 8.8, M36 x 4.0 x
21 BUY PART 8
160 W/84 Thread LG
22 BUY PART HEX NUT, M24 x 3.5 16
23 BUY PART HEX NUT, M30 x 3.5 16
24 BUY PART HEX NUT, M36 x 3.0 20
HEX BOLT, Gr. 8.8, M36 x 4.0 x
25 BUY PART 12
200 W/ 84 mm Thread LG
26 HWU-200T-SS-11-04 PIN LOCK SIZE Ø 36 mm x 100 mm LG 8
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 16 of 57

SUB STRUCTURE CYLINDER CLAMP


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 17 of 57

4.4.2 Installation

SUB STRUCTURE & SKIDDING SYSTEM


1. Hex Bolt, M36 x 4.0 x 160 mm LG, w/ 84 mm Thread, c/w Hex Nut, Flat Washer
& Spring Washer, Qty.: 8 sets. Apply Torque: min. 1800 – max. 4300 ft.lb

2. Hex Bolt, M30 X 3.5 X 120 mm Lg, c/w Hex Nut, Flat Washer & Spring Washer,
Qty.: 16 sets. Apply Torque: min. 1400 – max. 3300 ft.lb

3. Hex Bolt, M36 x 4.0 x 200 mm LG, w/ 84 mm Thread, c/w Hex Nut, Flat Washer
& Spring Washer, Qty.: 8 sets. Apply Torque: min. 1800 – max. 4300 ft.lb

4. Hex Bolt, M36 x 4.0 x 160 mm LG, w/ 84 mm Thread, c/w Hex Nut, Flat Washer
& Spring Washer, Qty.: 8 sets. Apply Torque: min. 1800 – max. 4300 ft.lb

5. Hydraulic Cylinder of Sub Structure (OE21D 125-70-900MP1).


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 18 of 57

4.5 Tie Beam & Tie Beam Connection part.

4.5.1 Assembly Preparation

TIE BEAM ASSEMBLY


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 19 of 57

ITEM NO. PART NUMBER DESCRIPTION QTY.


1 HWU-SKB-03A SUPPORT BEAM 1
2 HWU-HAL-ST-01 STOOL STUCTURE-L 1
3 HWU-HAL-ST-02 STOOL STUCTURE-R 1
4 HWU-HAL-ST-03 HEX BOLT, M20x2.5x100 Full Thread 2
5 HWU-HAL-ST-04 STUD BOLT, M24x3.0x310 4
6 HWU-HAL-ST-05 BUSHING 2
7 HWU-HAL-ST-06 LOCKING ARM 2
8 BUY PART COTTER PIN, 6.3 mm X 63 mm LG 8
9 BUY PART LOCK WASHER, M36 12
10 BUY PART HEX BOLT, M36x4.0x140 Full Thread 12
11 BUY PART LOCK WASHER, M24 8
12 BUY PART HEX NUT, M24x3.0 8

TIE BEAM OPEN POSITION BEFORE INSTALLATION


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 20 of 57

TIE BEAM CONNECTION PART - 01 (CYLINDER SIDE), QTY.: 2 SETS

ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 HWU-HAL-TBC-01 TIE BEAM CONNECTION-01 1
2 HWU-HAL-TBC-01-1 CONNECTION PIN 2
3 BUY PART Hair Pin Ø5mm 2

TIE BEAM CONNECTION PART - 02 (OTHER SIDE), QTY.: 2 SETS


ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 HWU-HAL-TBC-02 TIE BEAM CONNECTION-01 1
2 HWU-HAL-TBC-01-1 CONNECTION PIN 2
3 BUY PART Hair Pin Ø5mm 2
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 21 of 57

4.5.2 Installation

TIE BEAM & CONNECTOR


1. Lock Pin Ø 18 mm, w/ hair pin Ø 3mm Qty.: 8 sets.
2. HEX BOLT, M20 x 2.5 x 100 Full Thread.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 22 of 57

4.6 SS-Adaptor (ADS)

4.6.1 Assembly Preparation

Attention:
Item no. 2 (Platform Adaptor (ADS-02)) will install after Window Walk Around Installed.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 23 of 57

ITEM
PART NUMBER DESCRIPTION QTY.
NO.

1 HWU-HAL-ADS-01 ADAPTER STRUCTURE 1


2 HWU-HAL-ADS-02 PLATFORM ADAPTER 2
3 HWU-HAL-ADS-03 LOCK SPACER OUTRIGGER 8
4 HWU-HAL-ADS-04 LOCKING PLATFROM 1 2
5 HWU-HAL-ADS-05 LOCKING PLATFROM 2 2
6 HWU-HAL-ADS-06 BUSHING RING 8
7 HWU-HAL-ADS-07 LOCKING PIN 4
8 HWU-HAL-ADS-08 HEX BOLT, M24 x 3.0 (Custom) 4
9 BUY PART Cotter Pin (Hairpin) DIN 11024 Dia. 5mm 4
10 BUY PART Cotter Pin (Hairpin) DIN 11024 Dia. 6mm 8

HEX BOLT, M24 x3.0 x 100 Full


11 BUY PART 8
Thread (Galvanized)

12 BUY PART HEX BOLT, 1- 8'' UNC 2.5 x 12'' LG 24


13 BUY PART LOCK WASHER 1'' 24

HEX BOLT, M20 x 2.5 x 180mm W/ 52


14 BUY PART 4
Thread LG

15 BUY PART SPRING WASHER, M20 8


16 BUY PART HEX NUT, M20x2.5 4
17 HWU-HAL-ADS-09 STOPPER PLATFORM 4
18 BUY PART HEX BOLT, M12 x 1.75 x 45 Full Thread 16
19 BUY PART SPRING WASHER, M12 16
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 24 of 57

4.6.2 Installation

SS - ADAPTOR

1. Hex Bolt, M36 x 4.0 x 150 mm LG, w/ Washer plate Ø150 mm x 25 mm THK,
Qty.: 4 sets. Apply Torque: min. 1800 – max.4300 ft.lb
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 25 of 57

4.7 Escape Platform & Ladder (ESL)

4.7.1 Assembly Preparation

Item No. Description Qty.


1 Escape Ladder Platform 1
2 Escape Ladder -02 1
3 Escape Ladder -03 1
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 26 of 57

Escape Ladder Platform


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 27 of 57

4.7.2 Installation

ESCAPE PLATFORM LADDER (ESL)

1. References position distance of escape platform to sub structure is 1540 mm.


Hex Bolt, M20 x 2.5 x 110 mm LG, w/ Plain Washer (narrow), Qty.: 8 sets.
Apply Torque: min. 300 ft.lb – max. 700 ft.lb.
2. Connection support (ESL to Substructure).
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 28 of 57

ESCAPE LADDER 02 & 03 (ESL)

1. Hook Up Escape Vertical Ladder-02 to SS Adaptor & 03 to ESL platform.


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 29 of 57

4.8 Outrigger

4.8.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 30 of 57

ITEM
PART NUMBER DESCRIPTION QTY.
NO.

1 HWU-HALL-OR-01 OUTRIGGER STRUCTURE-1 1

2 HWU-HALL-OR-02 OUTRIGGER STRUCTURE-2 1

3 HWU-HALL-OR-03 OUTRIGGER STRUCTURE-3 1

4 HWU-HALL-OR-04 OUTRIGGER ROLLER 2

5 HWU-HALL-OR-05 PIPE 0.5 SCH 40 x 55 mm LG 2

6 HWU-HALL-OR-06 SLEEVE BEARING 2

G-2130 SHACKLE, CROSBY 3/4" (WLL:


7 BUY PART 1
4.75 TON) / EQUIV.

HEX BOLT, M14 X 2.0 X 130mm LG, W/


8 BUY PART 2
40mm LG THREAD

HEX BOLT, M24 X 3.0 X 100 mm LG,


9 BUY PART 12
W/ 54 mm THREAD LG

HEX BOLT, M30 x 3.5 x 160mm LG, W/


10 BUY PART 3
72mm LG THREAD

HEX BOLT, M36 X 4.0 X 220 mm LG,


11 BUY PART 2
W/ 97 mm LG THREAD

12 BUY PART HEX NUT, M14 X 2 2

13 BUY PART HEX NUT, M24 X 3.0 12


14 BUY PART HEX NUT, M30 X 3.5 3

15 BUY PART HEX NUT, M36 X 4.0 2

HG-228 TURN BUCKLE JAW&JAW SIZE


16 BUY PART 2
7/8 X 12 / EQUIV.

17 BUY PART Hairpin Cotter Pin_3mm (10-16mm) 2

18 BUY PART Hairpin Cotter Pin_5mm (20-28mm) 12

Hairpin Cotter Pin_6mm (28mm-


19 BUY PART 5
40mm)

20 BUY PART PLAIN WASHER M14 4

21 BUY PART PLAIN WASHER M24 24

22 BUY PART PLAIN WASHER, M30 6


23 BUY PART PLAIN WASHER, M36 4

24 BUY PART SPRING LOCK WASHER M24 12


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 31 of 57

4.8.2 Installation

OUTRIGGER (4 SETS)

1. Hex Bolt, M24 x 3.0 x 100 mm LG, c/w Custom Flat Washer Ø110mm x 25 mm
Thk, Qty.: 8 sets. Apply Torque: min. 700 ft.lb – max. 1700 ft.lb.

2. Hex Bolt, M36 X 4.0 X 220 mm LG, W/ 97 mm LG Thread, w/ Plain washer, Hex
nut & Hairpin 6mm, Qty.: 8 sets. Apply Torque: min. 1800 ft.lb – max. 4300 ft.lb.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 32 of 57

4.9 Work Window & Window Walk Around

4.9.1 Assembly Preparation

Item No. Description Qty.


1 Work Window Assembly 1
2 Window Walk Around 1
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 33 of 57

4.9.2 Installation

OPEN LOCK

WORK WINDOW & WINDOW WALK AROUND

1. Hex Bolt, 1”- 8 UNC x 12” Lg, w/ 1.75” Lg Thread, c/w Hex Nut, Qty.: 24 sets.
Apply Torque: min. 550 ft.lb – max. 1300 ft.lb
2. SS-Adaptor Locking Platform, with Pin 30 mm x 310 mm LG & Wing Hex Nut,
M24 x 3.0, Qty.: 4 sets
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 34 of 57

4.10 SS-Adaptor Platform (ADS-02)

4.10.1 Assembly Preparation

ITEM NO. DESCRIPTION QTY.


1 PLATFORM STRUCTURE 1
2 GRATING BASE 1
3 HEX BOLT, M20 x 2.5 x 110 LG_Custom 4
4 HEX BOLT, M20 x 2.5 x 110 LG_Custom 4
5 PIN LOCK 4

ITEM 3 ITEM 4 ITEM 5


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 35 of 57

4.10.2 Installation

SS – ADAPTOR PLATFORM (ADS-02, 2 SETS)

1. HEX BOLT, M20 x 2.5 x 110 mm LG_Custom, Qty.: 8 sets


2. HEX BOLT, M20 x 2.5 x 110 mm LG_Custom, Qty.: 8 sets
3. Pin Lock Ø 6mm, Qty.: 8 sets
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 36 of 57

4.11 Sub Structure Ladder (SS-LD)

4.11.1 Assembly Preparation

ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 SS-LD-01 SUBSTRUCTURE LADDER-01 1
2 SS-LD-02 SUBSTRUCTURE LADDER-02 1
3 SS-LD-03 SUBSTRUCTURE LADDER-03 1
4 SS-LD-04 SUBSTRUCTURE LADDER-04 1
5 SS-LD-SP-01 SUPPORT LADDER-01 2
6 SS-LD-SP-02 SUPPORT LADDER-02 2
7 SS-LD-PIN LOCK PIN LOCK SUB STRUCTURE LADDER 1
8 BUY PART STUD BOLT, M30 x 3.5 x 120 mm LG 8
9 BUY PART HEX NUT, M30x3.5 16
10 BUY PART SPRING WASHER, M30 14
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 37 of 57

4.11.2 Installation

SUB STRUCTURE LADDER - 02

1. Distance references of SSLD-02 is 3780 mm, install support ladder (SS-LD-SP-


01) and lock by Stud Bolt, M30 x 3.5 x 120 mm LG, w/ Hex Nut & Washer, Qty.:
4 sets.
2. Ladder locking plate by Hex bolt, M20 x 2.5 x 130 Full Thread, w/ Plain Washer,
Qty.: 8 sets.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 38 of 57

SUB STRUCTURE LADDER - 04

1. Lock by SSLD-Pin Lock Ø 48 mm, Qty.: 2 sets.


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 39 of 57

SUB STRUCTURE LADDER - 03

1. Hook up SSLD-03 to SSLD-04.


2. Install support ladder (SS-LD-SP-02), Qty.: 2 sets.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 40 of 57

4.12 Work Window Ladder (WW-LD)

4.11.1 Assembly Preparation

Item No. PART NUMBER Description Qty.


1 WW-LD-01 Work Window Ladder 1
2 WW-LD-PF-01 WW-Ladder Platform Bottom 1
3 WW-LD-PF-01-02 WW-Ladder Platform Top 1
4 WW-HL-SP WW-Hollow Support Assembly 2
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 41 of 57

4.11.2 Installation

WORK WINDOW LADDER

1. Hook Up Work Window Ladder to mounting ladder on Window Walk Around.


2. Ladder locking plate by Hex Bolt, M12 x1.75 x 60 mm LG, w/ Plain Washer, Hex
Nut, & Hairpin Ø 2.5 mm.
3. Connect Turn Buckle Jaw-Jaw 7/8” x 12 to pad eye on Window Walk Around.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 42 of 57

4.13 Hydraulic Jack Structure

4.13.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 43 of 57

4.13.2 Installation

HYDRAULIC JACK STRUCTURE

1. Connect Hydraulic Jack Structure to Work Window Structure by bolting.

2. Gin Pole mounting side.


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 44 of 57

4.14 Work Basket & Work Basket Riser

4.14.1 Assembly Preparation

Item Description Qty.


No.
1 Work Basket Assembly 1
2 Work Basket Riser 2
3 Clamp Escape Telescopic Vertical 1
Ladder
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 45 of 57

4.14.2 Installation

WORK BASKET & WORK BASKET RISER

1. Connect WB - Riser to Hydraulic Jack Structure by bolting.


2. Connect WB – Riser Top to WB – Riser Bottom by bolting.
3. Connect WB – Structure to WB – Riser Top by bolting.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 46 of 57

4.15 Escape Telescopic Vertical Ladder

4.15.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 47 of 57

4.15.2 Installation

ESCAPE TELESCOPIC VERTICAL LADDER

1. Landing on Platform SS-Adaptor.

2. Locking by using clamp with pin lock Ø 28 mm x 248 mm Lg & Hairpin Ø 6 mm,
Qty.: 1 set.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 48 of 57

4.16 Work Basket Ladder (WB-LD)

4.15.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 49 of 57

ITEM
PART NUMBER DESCRIPTION QTY.
NO.
1 HWU-WB-LD-01 ASSY WORK BASKET LADDER-01 1
2 HWU-WB-LD-02 ASSY WORK BASKET LADDER-02 1
3 HWU-WB-LD-PF-02 ASSY WORK BASKET PLATFORM 1
4 HWU-WW-HL-SP_ASSY HOLLOW SUPPORT 1
5 HWU-WB-HL-SP-PIN HOLLOW SUPPORT PIN 1
6 HWU-WB-PP-SP-PIN_02 HOLLOW SUPPORT PIN_02 1
7 BUY PART SPLIT PIN, M5 x 56 LG 4
8 BUY PART HEX BOLT, M10 x 1.5 x 45 2
9 BUY PART HEX NUT, M10 x 1.5 2
10 HWU-GL GRAVITY LOCKING 30
11 BUY PART SPLIT PIN, M5 x 45 1
12 BUY PART SPLIT PIN, M3.2 x 25 1
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 50 of 57

4.16.2 Installation

WORK BASKET LADDER PLATFORM (WB-LD-PF-02)

1. Pin Support Ladder, Ø28 mm x 263 mm Lg, w/ Hairpin Ø 6mm, Qty.: 2 sets.

2. Hex Bolt, M20 x 2.5 x 80 mm Lg, w/ Hex Nut, Plain Washer & Lock Washer, Qty.:
8 sets. Apply Torque: min. 250 ft.lb – max. 550 ft.lb
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 51 of 57

WORK BASKET LADDER - 02 (WB-LD-02)

1. Hook up to handrail & thread pin mounting ladder on work basket, lock by Hex
Nut, M24 x 3.0, Qty.: 3 pcs.

2. Hook up to work basket ladder platform mounting hole (WB-LD-PF-02).

3. Locking to work basket ladder platform locking plate by Hex Bolt, M10 x 1.5 x 45
mm Lg, w/ Hex Nut, Qty.: 2 sets.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 52 of 57
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 53 of 57

WORK BASKET LADDER - 01 (WB-LD-01)

1. Hook up to Window Walk Around Top.

2. Locking to Window Walk Around Top by bolting, Hex Bolt, M12 x 1.75 x 60 mm
Lg, c/w Hex Nut, Washer, & Hairpin Ø 2.5 mm. Qty.: 1 set

3. Connect Turn buckle Jaw-Jaw 7/8” x 12 to pad eye on Window Walk Around Top,
Qty.: 1 set.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 54 of 57

4.17 Gin Pole

4.17.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 55 of 57

4.17.2 Installation

GIN POLE

1. Locking Gin Pole to Jack Structure by pin on gin pole mounting.


2. Locking Gin pole on Work Basket.
Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 56 of 57

4.18 Tong Arm

4.18.1 Assembly Preparation


Document: HWUHALL-RUP
Revision: 00 – In Work
RIG UP PROCEDURE Issue date: 13.04.2023
Page: 57 of 57

4.18.2 Installation

TONG ARM

1. Connect to Tong Arm slot on Work Basket Riser beside the Gin Pole.

5. RIG DOWN
Please reverse all step by step of Rig Up sequence for doing Rig Down.