Document 3
Document 3
Document 3
@RBI 2018
TOPIC OUTCOMES:
2
@RBI 2018
INTRODUCTION
@RBI 2018
PRESTRESS LOSS
■ Early attempts to produce prestressed concrete was not successful due to loss
of prestress transferred to concrete after few years.
■ In other words, loss in prestress is the difference between initial prestress and
the effective prestress that remains in a member.
■ Loss of prestress is the difference between the initial tensile stress in prestressing
tendons at the time the tendons were seated in their anchorages, and the
effective prestress at a particular time considered.
Loss of Prestress
KPo
Time( t)
@RBI 2018
TYPES OF PRESTRESS LOSSES
The initial prestress in concrete undergoes a gradual reduction with time from the
stage of transfer due to various causes which is known as ‘loss of prestress’.
Pre-tensioning Post-tensioning
@RBI 2018
Losses in Various Prestressing Systems
@RBI 2018
PRESTRESS LOSS
iii. Friction between tendon and tendon duct, and wobble effect
i. Concrete creep
@RBI 2018
Prestress Losses
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
As per BS EN 1992-1-1 2004
@RBI 2018
When determining the immediate losses ΔPi(x): (see 5.10.4 and
5.10.5):
- losses due to elastic deformation of concrete ΔPel
- losses due to short term relaxation ΔPr
- losses due to friction ΔPμ(x)
- losses due to anchorage slip ΔPsl
@RBI 2018
@RBI 2018
@RBI 2018
Prestress Losses
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
Immediate Losses
Elastic Shortening of Concrete
■ In pre-tensioned concrete, when the prestress is transferred to concrete,
the member shortens and the prestressing steel also shortens in it.
Hence there is a loss of prestress.
@RBI 2018
■ Loss of prestress mainly depends on modular ratio and average stress in
concrete at the level of steel.
■ The change in strain in tendon is equal to the strain in concrete (εc) at the
level of tendon due to prestressing force.
@RBI 2018
Elastic Shortening
Pre-tensioned Members:
operation of pre-
tensioning through various
stages by animation. Prestressing
Pre-tensioning of a member
bed
Pre-tensioned Axial Members
P
i Original length of
Length after elastic shortening member at transfer
of prestress
P
0
ε
P
p
i i
ε ε
p c
P
0 0
P' e 2 A
σcp = 1 +
A I
@RBI 2018
Concrete strain = σ cp /Ecm, thus reduction in steel strain = σ cp /Ecm
σ cp
and the reduction in steel stress = Es = α eσ cp
E
cm
Es/Ecm = αe
thus loss in prestress force = α eσ cp Ap
Ecm = based on
where Ap = area of tendons concrete
strength, see
= P' e 2 A Table 6.11 of text
α e Ap 1 +
A I book OR Table
3.1 of BS EN
P' e 2 A 1992-1-1- 2004
Hence , P’ = Po - α e Ap 1 +
A I
Po
Ap e 2 A
Remaining prestress force, P’ = 1+ αe 1 +
A I @RBI 2018
■ In pre-tensioned construction, full loss will be present.
Po
P’ = Ap e 2 A
1 + 0.5α e 1 +
A I
@RBI 2018
EXAMPLE 1: Loss due to Elastic Shortening of Concrete
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
Immediate Losses
Frictional Loss
@RBI 2018
Post-tensioned Members
Friction is generated due to curvature of tendon, and vertical
component of the prestressing force.
5
@RBI 2018
Loss Due to Friction :
(Section 5.10.5.2, BS EN 1992-1-1-2004
~ This effect may be divided into unintentional profile variations, and those due to
designed curvature of ducts.
Px = Po e − µθ
Where θ = sum of angular displacement over distance x.
@RBI 2018
In accordance to the code, loss due to friction can be estimated from:
@RBI 2018
EXAMPLE 5: Loss due to friction
A concrete beam of 10m span, 100mm wide and 300 mm deep is prestressed by 3
cables. The area of each cable is 200 mm2 and initial stress in the cable is 1200
N/mm2. Cable 1 is parabolic with eccentricity of 50 mm above the centroid at the
supports and 50 mm below the centre of span. Cable 2 is also parabolic with zero
eccentricity at the supports and 50 mm below the centroid at the center of span.
Cable 3 is straight with uniform eccentricity of 50mm below neutral axis..
If the cables are tensioned from one end only, estimate the percentage loss of
stress in each cable due to friction. Assume K=0.005 per metre. Given the equation
of parabolic cable is: Y = (4e/L2) (xL- x2)
@RBI 2018
dy1
1
N.A.
2
3
50 mm
300 mm N.A.
50 mm
@RBI 2018
Prestress Losses
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
Immediate Losses
- Anchorage Slip
■ In most Post-tensioning systems when the tendon force is transferred from
the jack to the anchoring ends, the friction wedges slip over a small
distance.
■ Anchorage block also moves before it settles on concrete.
■ Loss of prestress is due to the consequent reduction in the length of the
tendon.
■ Certain quantity of prestress is released due to this slip of wire through the
anchorages.
@RBI 2018
■ Amount of slip depends on type of wedge and stress in the wire
■ The magnitude of slip can be known from the tests or from the patents of the anchorage
system.
■ Due to setting of anchorage block, as the tendon shortens, there develops a reverse friction.
@RBI 2018
Loss Due to Draw -In During Anchorage :
(Section 5.10.5.3, BS EN 1992-1-1-2004)
In most post-tensioning systems, when the cable is tensioned and the jack is
released to transfer prestress to concrete, the friction wedges, employed to grip
the wires, slip over a small distance before the wires are firmly housed between
the wedges.
The magnitude of slip depends upon the type of wedge and the stress in the
wires.
𝑃𝑃𝑃𝑃 𝑃𝑃 𝐸𝐸𝑠𝑠 ∆
=∆ =
𝐴𝐴𝐸𝐸𝑠𝑠 𝐴𝐴 𝐿𝐿
@RBI 2018
■ Anchorage loss can be accounted for at the site by over-extending the tendon
during prestressing operation by the amount of draw-in before anchoring.
■ Loss of prestress due to slip can be calculated:
P Es∆
=
A L
where,∆ = Slip of anchorage
L= Length of cable
A= Cross-sectional area of the cable
Es= Modulus of Elasticity of steel
P = Prestressing Force in the cable.
@RBI 2018
EXAMPLE 4: LOSS DUE TO ANCHORAGE SLIP (DRAW-IN)
A concrete beam is post-tensioned by a cable carrying an initial stress of 1000
N/mm2. The slip at the jacking end was observed to be 5mm. The modulus of
elasticity of steel is 210 kN/mm2. Estimate the percentage loss of stress due to slip
if the length of the beam is (a) 30m and (b) 3m
P Es∆
Solution: =
A L
(a) For 30m long beam,
Loss of stress = (210x103 x 5)/(30x103) = 35 N/mm2
Percentage loss of stress = (35/1000)x100 = 3.5%
(b) For 3m long beam
Loss of stress = (210x103x 5)/(3x103) = 350 N/mm2
Percentage loss of stress = (350/1000)x100 = 35%
@RBI 2018
Prestress Losses
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
Time Dependent Losses
- Concrete Creep
■ Time-dependent increase of deformation under sustained load.
■ Due to creep, the prestress in tendons decreases with time.
■ Factors affecting creep and shrinkage of concrete
• Age
• Applied Stress level
• Density of concrete
• Cement Content in concrete
• Water-Cement Ratio
• Relative Humidity and
• Temperature
@RBI 2018
■ Creep is due to sustained (permanent) loads only. Temporary loads are
not considered in calculation of creep.
■ Since the prestress may vary along the length of the member, an
average value of the prestress is considered.
■ Prestress changes due to creep, which is related to the instantaneous
prestress.
■ To consider this interaction, the calculation of creep can be iterated over
small time steps.
@RBI 2018
P' e2 A
σ cp = 1 +
A I
Ap e 2 A
Es P ' 1 +
A I
@RBI 2018
EXAMPLE 2: Loss due to creep in concrete
A post-tensioned concrete beam of rectangular section, 100mm wide and 300mm deep, is stressed by
a parabolic cable with zero eccentricity at the supports and an eccentricity of 50mm at the centre of
span. The area of the cable is 200mm2 and final stress in cable is 1200 N/mm2.
If the ultimate creep strain is 30x10-6 mm/mm per N/mm2 of stress and modulus of elasticity of steel
is 210 kN/mm2, compute the loss of stress in steel only due to creep of concrete.
Solution:
A = (100x300) mm2 P’ = Ap x σpe = 200 x 1200 x 10-3 = 240
kN
I = 100x3003/12 = 2.25x108 mm4 e = 50 mm
P' e2 A
σ cp = 1 +
A I
Stress in concrete at the level of tendon,
At support section, e = 0,
σcp = 240x103 / (100x300) = 8 N/mm2
@RBI 2018
At centre of span; e = 50mm; σcp = 8 ( 1 + 0.33)
= 10.7 N/mm2
Average stress, σcp = 9.3 N/mm2
@RBI 2018
Prestress Losses
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
Time Dependent Losses
- Shrinkage of Concrete
■ Time-dependent strain measured in an unloaded and unrestrained
specimen at constant temperature.
@RBI 2018
* Due to Shrinkage of Concrete:
a) aggregate used;
ε cs Es
■ The loss in steel stress is given by: hence,
@RBI 2018
Example 3: Loss due to shrinkage of concrete
Solution
Initial stress in wires, fpi = Po/Aps= (300x103/300) = 1000 N/mm2
@RBI 2018
Prestress Losses
Time
Immediate
Dependent
Elastic Anchorage
Friction
Shortening Slip
@RBI 2018
Time Dependent Losses
- Steel relaxation
decrease in the stress is due to the fact that some of the initial elastic strain
is transformed in to inelastic strain under constant strain.
stress decreases according to the remaining elastic strain.
@RBI 2018
Loss Due to Time-Dependent
May combine all three * (creep and shrinkage of concrete and relaxation of steel)
@RBI 2018
Where :
@RBI 2018
ESTIMATION OF PRESTRESS LOSSES AT MID-SPAN
A post-tensioned beam shown in Figure below is stressed by two tendons with a parabolic profile and having
a total cross-sectional area Ap = 7500 mm2. The total initial prestress force is Po = 10500 kN and the total
characteristics strength is Ppk= 14000 kN. Assume the following data for estimating losses.
Coefficient of friction, µ = 0.19; wobble factor k = -0.01/m.
Elastic modulus Ecm (transfer) = 32 kN/mm2 ; Es = 200 kN/mm2.
Creep coefficient ɸ ∞, 𝑡𝑡0 = 1.6
Shrinkage strain 𝜀𝜀 (𝑡𝑡, 𝑡𝑡0 ) = 330 X 10-6
The tendon supplier specifies class 2 strands with a 1000 hour relaxation loss of 2.5 per cent at 70 percent of
the characteristic strength.
L= 30 m
e= 0
1800
ec= 640
ᶿ
Cross-sectional area, A = 1.05 m2 1200
Second moment of are, I = 0.36 m4
@RBI 2018
@RBI 2018
@RBI 2018
@RBI 2018
REFERENCES
59
@RBI 2018