Guideline 22
Guideline 22
Guideline 22
4. Eligibility................................................................................................. 6
9. Dispute Resolution............................................................................... 14
The goal of these Guidelines is to enable BPC electricity consumers to generate electricity
for their own use while selling any excess to BPC up to the limit as defined by the Ministry.
1. 2 Objectives
Consumer: means any person who is supplied with electricity for his/her own use by
BPC. Consumers who also generate will be referred to, herein, as “consumers”, although
in effect they are “consumer/generators”.
Consumption: Kilowatt hours (kWh) used by the consumer for his/her own use and
tracked by the BPC meter.
Export: Any kWh that is generated by the Rooftop Solar (RTS) system and sent to the
BPC grid through its Point of Connection.
Interconnection Agreement (ICA): A contract between the consumer and BPC that
details the terms and conditions of interconnecting an RTS system with the BPC grid. The
ICA, signed by both the consumer and BPC, and the Certificate of Completion constitutes
the Permit necessary for an RTS system.
Inverter: A power device that converts direct current to alternating current at a voltage
and frequency which enables the generator to be connected to the utility grid.
Licence: For RTS systems above 100 kW, a licence will be issued by BERA to verify that
the system meets the full intent and requirements of the Electricity Supply Act. The
Licence term will be for 15 years.
Photovoltaic Solar System: A small scale embedded generation system, also known as
PV system or solar power system, designed to supply usable solar power by means of
photovoltaics. The system is comprised of solar panels to absorb and convert sunlight
into electricity, a solar inverter to change the electric current from DC to AC, as well as
mounting, cabling, and other electrical accessories to set up a working system.
Rooftop Solar: PV systems owned by consumers at the same location at which they
receive a bill for electric service. The generation from these facilities is primarily intended
for self-use, with excess generation eligible to be sold back to the grid.
Utility: The electricity distribution service provider responsible for the electricity grid
infrastructure to which the consumer is connected.
Utility Network (or Utility Grid): The interconnected network of wires, transformers and
other equipment, covering all voltage ranges, and belonging to the Utility.
Abbreviations
AMI Advanced Metering Infrastructure
BERA Botswana Energy Regulatory Authority
DOE Botswana Department of Energy, under the Ministry of Mineral Resources,
Green Technology and Energy Security
kVA kilovolt-ampere (unit of electrical power, often similar in magnitude to kW)
kW kilowatt (unit of electrical power)
kWh kilowatt-hour
MMGE Ministry of Mineral Resources, Green Technology and Energy Security
MW Megawatt
PV Photovoltaic
RTS Rooftop Solar
The RTS will align with and operate for the duration of the NDP11 (March 2023);
and upon its completion be evaluated for changes.
The Department of Energy (DOE), under the Ministry of Mineral Resources, Green
Technology and Energy Security (MMGE) shall be responsible for the oversight and
policy direction of the Rooftop Solar Programme, providing general guidance
through the Rooftop Solar Guidelines.
BERA shall be responsible for developing the necessary regulations, aligned with
the Rooftop Solar Guidelines as needed to guide the interconnection process, set
tariffs, establish tariff methodologies, and oversee safety concerns. It will also be
responsible for issuing permits and/or licenses, as specified in further detail below.
The Consumer shall ensure compliance with the Guidelines in the event the
Consumer decides to sign up for the RTS Programme and meets the eligibility
criteria. Such compliance includes the engagement of a licensed Electrician,
Technician or Engineer to design the solar system; ensuring that the Consumer
obtains all the applicable permits and licenses as provided for in the Guidelines, and
ensuring the timely payment of all costs and charges that the Consumer is
responsible for as detailed in the Guidelines such as the installation costs.
The RTS systems should be designed with Islanding Protection feature to detect
loss of grid power and automatically (within two seconds) shuts off the solar inverter
irrespective of connected loads to stop feeding power back to the grid. The
Consumer may choose the design that allows their system to remain operational in
isolation from the grid for own consumption, which may require additional
equipment.
For all domestic and C&I projects in this Programme, the RTS consumer must obtain
a Permit, to ensure that its project meets all technical and safety standards. The
Permit constitutes the Interconnection Agreement and the Certificate of Completion,
as described below:
The term of the Permit (ICA) and/or Licence will be for 15 years, upon which time it
will require renewal. In event of Programme termination, an RTS-approved project
will be able to continue to operate under the terms and conditions of the Permit or
Licence until the expiration date of that Permit or Licence.
5.4.1 Potential RTS consumer applies with BPC to install a system of a certain
size on its property. Until the aggregate capacity limit is reached, consumers
gain access to the Programme on a first come-first served basis.
For PV systems greater than 100 kW, the application will be automatically
forwarded to BERA for review and issuance of a Licence to the consumer.
BERA will inform BPC of the issuance of such applicable authorization.
For PV systems greater than 100 kW, the conditional ICA will be signed by
the consumer and BPC, upon approval of the Licence by BERA.
5.4.3. If all documents are in order, BPC puts the consumer and the amount in
the queue. The capacity requested is subtracted from the running balance of
Programme capacity available. BPC will conduct necessary studies or
analyses to confirm availability request at the Point of Connection. BPC will
notify the consumer of the outcome of their application.
5.4.4 BPC will maintain a Registry of such systems, providing access to BERA,
that will include information provided from the Application and any other
relevant data. BPC will regularly monitor for Permits (ICA) expiring, while BERA
will monitor for licenses that may be expiring.
5.4.5 The consumer will have a set amount of time as determined by BERA,
upon application from BPC, to install and certify the system.
5.4.8 If the consumer does not receive certification for its system within the time
frame allowed, the capacity is added back into the Programme capacity
available and the consumer is removed from the Registry. BPC will determine,
in consultation with BERA and the Ministry, an appropriate timeframe allowed.
5.4.9 For good cause, if the consumer requests, BPC may grant an extension
to the deadline, in consultation with BERA.
5.4.10 If the consumer is removed from the Registry, it then must reapply anew
in order to be placed back on the Registry.
5.5.1 Renewal of System – BPC will notify a consumer within 60 days of the
expiration of the Permit. If planning to renew, the consumer must submit its
intent to do so and complete the Application Process from 6.4.6 above. Upon
receipt of Certificate of Completion, BERA will renew the term of Licence for
projects above 100 kW.
In the event of operating conditions that may result in BPC electrical grid parameters
not meeting minimum quality of supply, safety standards or non-availability of an off-
taker, it may become necessary to curtail Rooftop Solar consumers. It is expected
that these limitations would be of a temporary nature, applied only during abnormal
system conditions or low load periods.
BPC has the right to deny access to any RTS consumer to interconnect with the
system grid. It is mandatory that all consumers wishing to install a Rooftop Solar
system, regardless of generation capacity, complete the relevant sections of the
application process in full, and that the Conditional ICA is signed by BPC before
system installation commences. BPC will ensure that, amongst other
considerations, there is availability of capacity to accommodate the Rooftop Solar
system. If the consumer is willing to take on the necessary upgrades and its
associated costs to interconnect, then BPC may consider the Application.
Consumers should not purchase equipment prior to signing the Conditional ICA, as
approval is not guaranteed and BPC shall not be held liable for equipment expenses
where approval is denied.
If a consumer decides to remove or cease operation of the RTS system, BPC must
be notified, and BPC must verify that the system has been physically disconnected
from the grid. For projects above 100 kW, the consumer will also need to notify
BERA of the discontinuance of the Licence. Costs to remove wiring which connects
the inverters with the grid will be borne by the consumer. BPC will provide a
Certificate of Compliance that the system has complied with removal and
decommissioning procedures and update the Registry as such.
7. Technical Standards
RTS systems should comply with the necessary standards and regulations in order
for the system to be approved and put into operation. In addition to the legislation
listed above in Section 3.3, BPC, in consultation with BERA, will provide the
minimum applicable technical standards as contemplated in the RTS rules and
regulations to the RTS Programme on its website as well as referenced within the
ICA’s terms and conditions to ensure full compliance, a consumer should engage
a licensed Electrician, Technician or Engineer.
Consumers should be in good standing with BPC. RTS applicants in arrears will not
be considered.
8.4. Billing
Consumers are billed according to the regular billing cycle for kWh. Excess kWh
generated and exported to the grid over the consumer’s use are credited towards
the next billing cycle. The kWh generated less consumed should be clearly
represented on each monthly bill.
The meter will register the energy imported from BPC and the excess energy
exported to BPC. These two, energy imported from and exported to BPC will be
reconciled on monthly basis to also reflect the Net energy. For every kWh the
consumer exports to the grid, they will receive a credit of 1kWh. The credit received
shall not be in monetary terms but in kWh. Any excess energy exported by the
consumer will be rolled over to the next billing cycle. Only the charges relating to the
kWh units, energy part, of the consumer bill are affected, the fixed charge part, non-
energy part of the consumer’s bill will not be credited for excess energy exported to
BPC. If, over any particular month, the customer is a net importer (their net export
is negative), the customer will be billed for the energy supplied during that month as
per the approved BPC tariff schedule.
8.6. Arrearages
9. Dispute Resolution
Any disputes between BPC and the RTS consumer may be resolved promptly through
mutual consultations. Further grievance shall have recourse under the relevant
regulations under BERA’s jurisdiction.
BPC will periodically audit a sample of RTS systems, as per the procedures approved by
BERA, conducting an inspection of such systems to ensure all technical and safety
standards are met. Thereafter, BPC will submit in its audit findings to BERA. All
documentation and information pertaining to the auditing and site visits will be retained
by BPC for BERA and the Ministry to review upon request.
11. Non-compliance
If at any time an RTS system is not complying with the Guidelines, Rules or associated
regulations for this Programme (e.g., technical, safety, environmental), BPC may
disconnect the consumer’s system immediately and without notice, and notify BERA of
the system’s non-compliance. BERA has the authority to impose sanctions for non-
compliance with Guidelines and Rules.
BPC will report on a quarterly basis the performance of the Rooftop Solar Programme.
The report should include the following data and analyses:
At the end of the first 12-month term of the Programme, the Ministry will announce its
determination of aggregate maximum capacity within the system grid.
13. Amendments
The Minister reserves the right, at his discretion, to change or modify these Guidelines at
any time. If the minister makes a change to the Guidelines, any application that has been
filed will be processed under the (old) Guidelines in effect at the time the application was
filed.
Implementation of the RTS Programme will be subject to all applicable policies and
relevant laws of the Republic of Botswana.