Plant Design Project Final 2
Plant Design Project Final 2
Plant Design Project Final 2
SUPERVISOR:
EXECUTIVE SUMMARY
Gebeng, Pahang is chosen as our plant site because its development is based on
petrochemical and chemical industry. The industrial land is located nearby Gebeng
bypass which eases traffic flow from the industrial land to Kuantan Port, links Kuala
Lumpur and Kuantan directly via East Coast Highway. Gebeng has been selected as our
plant location due to the lowest land price ranging from RM 15.00 – 30.00 / ft 2. The
future expansion and project enlargement is made possible with enough land for project
continuation. Furthermore, the abundance of raw material in the same city will also
reduce the cost of transportation of the raw material as well as the availability of good
transportation and port facilities.
The operation of the proposed plant is 340 days annually and 24 hours daily in
which the remaining amount of operation time will be reserved for plant maintenance
and repair of unit operations down time. With the presence of CeCu catalyst, the
iii
TABLE OF CONTENT
Locations
1.3.3 Matrix for Site Selection
1.4 Process Selection
1.4.1 Direct Synthesis from Carbon Dioxide and
Methanol
1.4.2 Transesterification of methanol and propylene
carbonate using CeCu
1.4.3 Oxidative Carbonylation of Methanol
12.10.1 Introduction
12.10.2 Plant Startup
12.10.3 Plant Shutdown
14.0 CONCLUSION
APPENDICES
Appendix A: Material Safety Data Sheet (MSDS)
Appendix B: Raw Material Supplier
Appendix C: Physical and Chemical Properties
Appendix D: Manually Developed Design and Stream
Summary Table
xi
REFERENCES
vi
LIST OF FIGURES
LIST OF TABLES
oxidative carbonylation of methanol or even direct synthesis from carbon dioxide and
methanol. Some has been very well incorporated and commercialized into major
companies venturing into this field of production especially in Asia Pacific namely
China and Japan.
The physical and chemical properties of dimethyl carbonate and relevant raw
materials required in its production are shown in Appendix C.
Dialkyl carbonates can be handled safely without the special precautions due to
their moderate toxicity in comparison with the conventional carbonylating (i.e.
phosgene) and alkylating agents (i.e. alkyl halides and dimethyl sulphate) which are
some of the toxic materials. Besides, the formation of inorganic salts as byproducts and
the related disposal problems are avoided. The third advantage of dialkyl carbonates is
their appreciable selectivity following the hard–soft acid–base (HSAB) principle. With
changes in reaction temperature, the nucleophilic substitution on DMC follows two
different mechanisms therefore, low temperatures allow carboxymethylation reaction,
whereas high temperatures give methylation derivatives. It can also be used for synthesis
of diphenyl carbonate, isocyanate and allyl diglycol carbonate ester as well as for the
synthesis of various kinds of carbamate pesticides such as carbaryl. It can also be
utilised as an intermediate of organic synthesis such as anisole, dimethoxybenzene,
alkylated aryl amines, symmetrical diamine urea and methyl carbazate. In the
4
Dimethyl carbonate (DMC) finds use as a solvent in paints, inks and coatings.
This is because DMC has an ultra-low MIR value, which is a chemical's ability to form
atmospheric ozone. The lower the MIR value, the less ozone generated and safer it is.
Dimethyl Carbonate is also a medium evaporating polar solvent with a low toxicity and
methanol like odor. Besides the environmental friendly characteristics, it offers a low
vapor pressure, suitable liquid temperature range and unique solubility property essential
for paints, inks and coatings. DMC is a viable alternative to acetate esters and ketones in
most applications, from paints to adhesives, taking advantage of its good solvency
power. DMC also acts as an intermediate in the synthesis of polymers, pesticides,
antioxidants and high performance resins.
The potential demand for DMC could be much higher. Its main use as an
intermediate in polycarbonate production currently accounts for just over half of its
consumption. Polycarbonate is a type of plastics known for their optical transparency,
impact resistance, and high dielectric strength. For example, polycarbonates are found
in DVD and Blu-ray discs, safety goggles, eyeglass lenses, bullet-resistant windows,
electrical insulators, aircraft and missile components. This abundance and variety of
applications generates substantial demand for DMC and makes production a viable
investment.
5
There is future potential demand as a possible fuel additive. DMCs possible use
as a gasoline blending component has been under consideration for some years, due to
its very high oxygen content (53 weight percent), good blending octane and freedom
from phase separation, low toxicity and rapid biodegradability. The high oxygen content
of DMC makes it a candidate to replace MTBE as an oxygenated fuel additive. Usually
10% of MTBE (methyl tertbutyl ether) is added while only 3.3% DMC is needed. The
oxygen content of a DMC molecule is 53% whereas the oxygen content of MTBE
molecule is 17%. Automotive emission tests at Amoco showed that at the same weight
percent oxygen in the fuel, DMC reduced total hydrocarbon, carbon monoxide and
formaldehyde more than did MTBE. The use of dimethyl carbonate as a gasoline
blending component in major regions such as North America and China is uncertain. In
6
the United States, while MTBE is largely phased out, ethanol remains the major gasoline
blending agent. In China, MTBE still appears to be the gasoline addictive of choice.
is sufficiently exothermic to ignite the reaction products. Heat is also generated by the
interaction with caustic solutions. Flammable hydrogen is generated by mixing with
alkali metals and hydrides.
Dimethyl carbonate should be kept away from ignition sources by incorporating
explosion-proof equipment. Ignition sources include heat, sparks, open flames or even
hot surfaces whereas explosion-proof equipment can involve electrical, ventilating and
lighting equipment. Besides, measures should be taken as well for prevention in the
build-up of electrostatic charges. This can be done by using only non-sparking tools and
ground or bond containers and receiving equipment.
The two key drivers of dimethyl carbonate production are two of its largest
applications in the industries of polycarbonates and paints and coatings. The
polycarbonate is the tough material having few grades that are optically transparent. This
8
material is widely used in the engineering and various applications. It offers properties
such as extrusion and injection molding technique to develop products with various
shapes and size, excellent heat and UV resistance, and thermo-formation.
Polycarbonates are currently in very high demand from the rapidly growing end-user
industries of automotive and electronics. Both industries are currently in full swing and
are expected to continue growing in the near future. As a result, the higher demand for
polycarbonates becomes a driver for the manufacture of dimethyl carbonate. Similarly,
the paints and coatings industry is being boosted by the construction industry,
consequently upping the demand for dimethyl carbonate. Increasing demand from food
and beverage packaging and the medical packaging application is also expected to boost
the growth of the polycarbonate market during the years to come. The welcoming
demand of polycarbonate will be good news to the production of dimethyl carbonate
over the years.
The demand of dimethyl carbonate goes hand in hand with the success of
polycarbonate industry. According to reports on “Polycarbonate Market for Electronics,
Packaging, Construction, Automotive, Optical Media and Other Applications: Global
Industry Perspective, Comprehensive Analysis and Forecast, 2014 – 2020”, the global
demand for polycarbonate was valued at USD 13.50 billion in 2014, and is expected to
reach USD 18.50 billion in 2020, growing at a CAGR of 5.8% between 2015 and 2020.
The needs of dimethyl carbonate as the starting material towards polycarbonate
production is proven crucially important in many years to come.
Dimethyl carbonate market size was valued over USD 410 million in 2015 and is
forecast to experience gains exceeding 5% CAGR by 2024. By the end of 2016, this
market revenue should be reaching US$440 million. The global market for dimethyl
carbonate is expected to progress at a CAGR of 6.6% between 2015 and 2023 in terms
of revenue. By the end of 2023, the market is expected to be valued at US$690.1
million. In terms of volume, dimethyl carbonate global production is expected to weigh
in at 599 kilo tons.
The global polycarbonate industry was valued at over USD 14 billion in 2015
and is projected to reach USD 22 billion by 2024, at over 5% CAGR. The industry will
expand at a rapid pace, particularly in Asia Pacific due to robust growth in the regional
automotive and electronics sectors. Emerging economies in Asia Pacific are expected to
be major markets for electronics due to modernization, such as increasing smartphone
customer base, along with increasing consumer disposable income. This is expected to
boost electrical components demand. This will consequently boost industry growth.
11
The key players involved with the production of dimethyl carbonate include
Dongying City Longxing Chemical Co., Ltd., Shandong Shida Shenghua Chemical
Group Co., Ltd., Alfa Aesar, EMD Millipore Corporation, HaiKe Chemical Group,
Akzo Nobel N.V., UBE Industries Limited, Tangshan Chaoyang Chemical Co., Ltd.,
and BASF SE.
12
Figure 1.3: U.S Dimethyl Carbonate Market Size by Application from 2013-2024 (USD
Million)
Source: Dimethyl Carbonate Market Size by Application Industry Analysis Report,
Regional Outlook, Growth Potential, Price Trends, Competitive Market Share &
Forecast, 2016 – 2024
1.2.3 Asia Pacific Outlook
By the end of 2023, the Asia Pacific demand for dimethyl carbonate is expected
to be at 49.26% of the market. Europe comes in at second place in terms of demand
followed by North America in third. Asia Pacific, particularly led by China, India,
Indonesia, dominated the global dimethyl carbonate market size in 2015. In addition, the
region is forecast to experience highest gains mainly owing to robust growth in the
electronics, automotive and paints & coatings on account of increasing consumer
disposable income. Furthermore, upgrading customer preferences towards colorful and
high quality paints will complement industry growth by 2024.
expected to dominate the global dimethyl carbonate market by almost 50% of the total
supply with a compounded annual growth rate of 6.6%.
The total value and volume of imports in India, based on the source from Zauba
Technologies and Data Services Pvt Ltd, are USD 19,407,021 and 13,467.508 MTA
respectively in 2016 which shows the great demand in India in years to come. The top
suppliers of dimethyl carbonate in India as shown in Table and Figure proves that the
DMC market demand in Asia Pacific is dominated mainly by China and Japan.
Table 1.2: Top Suppliers of DMC in India (Zauba Technologies and Data Services,
2016)
TOP SUPPLIERS (COUNTRY) TOTAL VALUE OF IMPORT (USD)
China 18,621,017
Japan 783,712
15
since the economic potential of our country can be increased following the exports of
dimethyl carbonate based on their growing future demand. It will be a great investment
in the long run if this dimethyl carbonate manufacturing plant is made successful.
The average market prices of dimethyl carbonate in 2017 and the previous four
years are tabulated in Table 1.1 below in which they are sourced from available
information in ICIS Chemical Business and Platts Global Petrochemical Index and
Zauba Technologies and Data Services.
The methanol industry in Malaysia accounts for only around three percent of the
overall production in the Asia-Pacific region. Its demand is expected to increase in the
18
coming years quite significantly due to a healthy demand from the formaldehyde-based
resin and automobile fuel sector. The growth in demand for methanol in Malaysia is
expected to be at the rate of five percent during the forecast period, and the majority of
domestic demand would be fulfilled by imports. This correlates well with the global
demand and supply as shown in Figure 1.5 that is expected to experience steady growth
in years to come as the average increase in total capacity of plants worldwide is fuelled
by the higher operating rate required.
Figure 1.7: Global Methanol Supply and Demand (Source: IHS 2013)
Figure 1.8: Global Methanol Demand Based on Applications (Source: IHS 2013)
The methanol market in Malaysia is highly consolidated, with only one player,
PETRONAS. The company accounted for 100% of the installed capacity in the region
during 2011. The domestic demand was fulfilled by in-house production and the
majority of in-house production was exported to Japan and China.
The location of a new plant is crucial towards the sustainability and production
capacity of the manufacture of a particular chemical product or any industrial-grade
materials. Judging on a long-term basis, a chemical plant has to be strategically and
safely located to prevent untoward incidents to the public and environment as well as to
accommodate the competitive and economical perspective of market opportunities.
These major concerns are guided by various factors that are to be taken into
consideration which include the tax incentives, land price and availability, utility tariff,
logistics, labour, availability of raw materials and market supply.
For the construction of our new dimethyl carbonate manufacturing plant, three
major industrial locations have been considered that is mainly focused in Peninsular
Malaysia due to better market prospects and industrial development. The locations
include as the following:
The suitable and conducive land for the construction of a sustainable and
functional dimethyl carbonate manufacturing plant should be widely available at
selected locations. This also refers to the hectares of land or area accessible to our
plant’s needs. Our 15,000 MTA-production capacity chemical plant will require
approximately 10 acres of land that will also provide space for auxiliary and additional
buildings and facilities such as warehouse, cafeteria, cooling water and others. The land
price is defined in terms of RM per square feet and it should be sufficiently low to
reduce expenses.
22
i) Gebeng, Pahang
The major tax incentives for companies that invest in the manufacturing sector
are the Pioneer Status or Investment Tax Allowance. Eligibility for Pioneer Status or
Investment Tax Allowance is based on certain priorities, including the levels of value-
added, technology used and industrial linkages.
exemption period commencing from its Production Day (defined as the day its
production level reaches 30% of capacity).
A company granted Investment Tax Allowance (ITA) gets an allowance of 60%
on qualifying capital expenditure (factory, plant, machinery and other equipment
used for the approved project) incurred within five years from the date the first
qualifying capital expenditure is made.
Companies can offset this allowance against 70% of statutory income for each
year of assessment. Any unutilized allowances can be carried forward to
subsequent years until fully utilized. The remaining 30% of the statutory income
will be taxed at the prevailing company tax.
Pioneer Status with income tax exemption of 100% of statutory income for a
period of 5 years; or Investment Tax Allowance of 100% on the qualifying
capital expenditure incurred within a period of 5 years. The allowance can be
offset against 100% of statutory income for each year of assessment.
Stamp duty exemption for all clusters promoted by East Coast Economic Region
Development Council (ECERDC) on transfer or lease of land or building.
Withholding Tax Exemption (WTE) on royalty and technical fees
Pioneer status (PS) with income tax exemption of 100% of statutory income for a
period of 10 years. Unabsorbed capital allowances and accumulated losses incurred
during the pioneer period can be carried forward and deducted from the post pioneer
income of the company Businesses are entitled to 10 years exemption from corporate
24
tax. Investment Tax allowance (ITA) of 100% of qualifying capital expenditure incurred
within a period of 5 years. The allowance can be used to offset against 100% of statutory
income in each year of assessment. Unutilized allowances can be carried forward until
fully absorbed.
Tariff related incentives such as full exemption from import duty on raw materials and
components; exemption of import duty and sales tax on machinery and equipment;
drawback of excise duty, sales tax and import duty paid. Dividends paid from the
exempt income are exempted from tax in the hands of its shareholder. Incentives for
export, R&D and manpower training
Pioneer Status referring to income tax exemption of 70% or 100% on the statutory
income for five years. Investment Tax referring to investment tax allowance of 60% or
100% on the qualifying capital expenditure for five years. The allowance can be utilized
to offset against statutory income. Reinvestment Allowance referring to reinvestment
allowance of 50% for 15 years on the qualifying capital expenditure. The allowance can
be offset against 70% or 100% of the statutory income. Accelerated Capital Allowance
referring to an accelerated capital allowance consisting of an initial allowance of 40%
and an annual allowance of 20% is available for the three years after the reinvestment
allowance period
i) Gebeng, Pahang
26
INDUSTRIAL
Consumption:
Band 1 0 - 20 m3 @ RM 0.85/m3
Band 2 20 - 40 m3 @ RM 1.05/m3
Band 3 40 - 200 m3 @ RM 1.30/m3
Band 4 >200 m3 @ RM 1.45/m3
Minimum charge RM30.00 (Use in the Approved Industrial
Zones)
1.3.2.5 Logistics
Meeting customer demand and providing superior service is one of the most
important benefits of good logistics management. Logistics management is also
important for creating visibility into a company’s supply chain. Proper logistics
management drives increased revenue. Improved customer service can bring a good
reputation to a company’s brand and generate more business, and supply chain visibility
creates opportunity for major cost savings in operations. Logistics management will give
a company control over inbound freight, keep inventory at optimal levels, organize the
reverse flow of goods, and utilize freight moves on the proper transportation modes
where all of which can cut costs significantly.
1.3.2.6 Labour
Labour includes both physical and mental work undertaken for some monetary
reward. In this way, workers working in factories are included in labour. Land and
capital are considered as the passive factors of production, because they alone cannot
start the production process. Production from land and capital starts only when a man
makes efforts. Production begins with the active participation of man. Therefore, labour
is an active factor of production. Production can be started only with the help of labour.
It means labour is the beginning of production.
29
In all three suggested locations, local labour of adequate skills can be scouted
and trained to operate the plant. Available labour can be found from polytechnics,
universities and human resources and technical skills developer around the local states.
1.3.2.7 Raw materials
Jetty that import and export 33 km from Sultan Ahmad International Airport
goods Shah Airport 7 km to the nearest
60 km from Senai Approximately 8.2 km to the highway
International Airport nearest highway 24 km to Penang Port
20 km from the nearest
North-South Highway
interchange
1 2 3
Water tariff :
Water tariff : Water tariff :
0 - 20 m3 @ RM 0.85/m3
0 – 35 m3 @ RM2.80/m3 0 – 227 m3 @ RM0.92/m3
20 - 40 m3 @ RM 1.05/m3
Utility tariff 0.10 >35 m @ RM3.30/m
3 3
>227 m @ RM0.84/m
3 3
40 - 200 m3 @ RM 1.30/m3
>200 m3 @ RM 1.45/m3
1 3 2
Total 1.00 1.60 2.70 1.70
Remark: Rating from 1-3, 1 is the worst while 3 is the best.
33
Based on overall score obtained from the matrix, it is best to choose Gebeng,
Pahang as our Plant Site. Gebeng industrial land focusing on industry that based on
petrochemical and chemical. The industrial land is located nearby Gebeng bypass which
eases traffic flow from the industrial land to Kuantan Port, links Kuala Lumpur and
Kuantan directly via East Coast Highway. A few criteria that we considered while
making judgment for site selection. We put availability of suitable land as the most
importance criteria, followed by land price and marketing area, then raw material
supply, and lastly, the logistics and utility tariff. Gebeng has been selected as our plant
location due to the lowest land price ranging from RM 15.00 – 30.00 / ft 2 compare to
Tanjung Langsat and Batu Kawan. The future expansion and project enlargement made
possible with enough land for the project continuation. Furthermore, the abundant of raw
material in the same city will also reduce the cost of transportation of the raw material as
well as the availability of good transportation and port facilities. As a conclusion,
building a dimethyl carbonate-producing plant in Gebeng will definitely give us huge
advantages.
flammable and abundant. Notably, this route, yielding water as the sole by-product, has
the same atom economy as oxidative carbonylation. Furthermore, the utilization of CO 2
avoids the risk of explosion caused by the co-existence of oxygen and carbon monoxide.
From the above, it is considered as an attractive and sustainable route for dialkyl
carbonates synthesis based on green chemistry principles.
Methylformate as a waste
The market prices of the chemicals that are used in this process route are listed in
Table 1.13.
The market prices of the chemicals that are used in this process route are listed in
Table 1.14.
Water - -
*Currency rate: USD 1 = RM4.44
1.4.2.2 Economic Potential
The market prices of the chemicals that are used in this process route are listed in
Table 1.15.
CHAPTER 2
Process synthesis is the step in design where the design team selects the
component parts and how to interconnect them to create the flowsheet for the
production of dimethyl carbonate (DMC). Furthermore, it involves identification of
the processing route to produce the desired product, investigation of chemical
reactions needed, selection and design of the operations involved in the processing
route, as well as calculations of utility requirements, the calculations of waste and
emissions to the surroundings and many more. In this chapter, all the five key steps
of process synthesis were analyzed and determined by the design team accordingly.
Table 2.1 shows the data from the chemistry laboratory focusing on several
reaction paths for manufacturer of DMC from several sources. Most of the reactions
paths of producing DMC are well known due to DMC have been commodity
chemicals for many years. Therefore, the design team proposed to carry out process
synthesis for newer substance as the data emerging from the research.
42
The challenge is to guide the chemists away from those reaction paths that
lead to processes that are costly to build and operate, and to arrive at designs that are
economical and environmentally friendly. Furthermore, another supercritical
challenge is to arrive at designs as fast as possible, to be able to capture the market
before another company develops a competitive process or chemical. Therefore, the
principal reaction pathways of DMC production as follows:
By the information given before, the design team would reject reaction path 1
(Direct Synthesis of Carbon Dioxide and Methanol) due to the low conversion of
methanol and low yield of DMC. Therefore, this leaves the other reaction paths (2
and 3) as potentially attractive to be selected on the basis of chemical prices. For this
case, the gross profit of the reaction is taken as a basis for choosing the best reaction
path. Table 2.2 shows the gross profit for all three reaction path mention early.
Table 2.2: Gross Profit for Production of Dimethyl Carbonate (Based on Chemical
Prices in Table 2.1)
Reaction Overall Reaction Gross Profit
Path (RM/kg of DMC)
1 CO2 + 2CH3OH → (CH3O)2CO + H2O 2.65
2 C3H6O + CO2 → C4H6O3 4.57
C4H6O3 + 2CH3OH → (CH3O)2CO + C3H8O2
3 2CH3OH + 1/2O2 + CO → (CH3O)2CO + H2O 3.09
Reaction path 2 and 3 which have highest gross profit will proceed to the next
step of screening that considers the several key selection criteria involving mainly on
conversion and operating conditions. The reactions involved are transesterification of
methanol and propylene carbonate using CeCu catalyst and oxidative carbonylation
45
The ratings code of 1, 2 and 3 will represent the level of ratings with 1 being
the lowest while 3 being the highest. These codes will be multiplied with the
weightage and the point of every characteristic will be summed up. The highest
points collected will be selected for the next procedure which focuses on the
subsequent steps. The matrix for the process selection is shown in Table 2.3.
46
3 1 2
According to the total marks obtained from the matrix, Reaction 2 is highly
preferred. Although most chemical plants of the industry uses the oxidative
carbonylation of methanol process in the production of dimethyl carbonate, however,
the transesterification of propylene carbonate has seen its application tremendously
promising in recent years and more research proves influential towards better
productivity. Reaction 2 has the best potential toward production and in terms of
sustainability of the industry, although there is still much research needed to improve
the yield and conversion and thus, reduce the amounts of wastes. In this case, the use
of the cerium-cupric, CeCu catalyst would be further add to sustainability positively.
Besides, the conversion of the raw material and the DMC yield is improved
significantly compared to the other considered reactions. Despite the complex by-
products produced by Reacion 2, the fact that propylene glycol can be sold outweigh
the handling of the by-product itself which further enhances the gross profit of this
reaction. In fact, Reaction 2 does not cause potential explosion as compared to that of
Reaction 3 in which the combination of carbon monoxide and oxygen are possible
ignition sources. The operating temperature for all three reactions are not too
extremely high but Reaction 2 boasts the lowest operating pressure which proves
vital in having a safe operation. In short, Reaction 2 is better than Reaction 1 and 3 in
most of the top aspects especially in terms of the gross profit and dimethyl carbonate
yield.
49
In this step, the possible sources and sinks are matched accordingly so that,
the total mass flow into a rector equals the total mass flow out. The plant is proposed
to produce 15,000 MTA of 99% purity of DMC. The mixing operation is introduced
to eliminate the differences in flow rates when a sink is supplied by two or more
sources. In other cases, a single source is divided among several sinks. The
propylene oxide and carbon dioxide are matched with their sinks into the propylene
carbonate synthesis reactor. It is assumed that propylene oxide and carbon dioxide
enter the reactor in the stoichiometric ratio of 1:1.097 as in reaction 2. This is
because it is not practical to design the reactor for complete conversion of limiting
reactant (Propylene Oxide); instead, the reactor effluent emerges with some of the
limiting reactant still present and is then usually subjected to a separation process to
remove the unrecovered reactant from the product. However, for this case the
unreacted carbon dioxide does not undergoes separation process because it does not
affect the next reaction due to its inert property. The experimental data indicates
100% conversion of propylene oxide at the reactor condition 250°C and 19.74 atm.
From the Figure 2.1, it can be clearly seen that the flow rates of 1185.11 kg/hr
propylene oxide and 985.28 kg/hr of carbon dioxide produce 2083.65 kg/hr of
propylene carbonate and 87.13 kg/hr of carbon dioxide respectively.
Figure 2.2: Flow Diagram of Chemical Distribution in the System with Recycled
Stream
Next, the propylene carbonate source from the reactor is sent to its sink in the
transesterification operation, which operates at 150°C and 1 atm. Only 65% of
propylene oxide is converted to dimethyl carbonate with a by-product of propylene
glycol. To satisfy the overall material balance, 2083.65 kg/hr of propylene carbonate
must produce 1838.24 kg/hr of dimethyl carbonate and 1552.76 kg/hr of propylene
glycol. The additional propylene carbonate and methanol needed are computed by
mass balance to equal 704.16 kg/hr and 1121.97 kg/hr respectively. Since, the
reaction converts 65% of propylene carbonate and methanol into dimethyl carbonate,
the unconverted reactants can be recycled back to the reactor. Therefore, the recycle
stream is introduced and the mass balance is calculated using the following formula.
From that, the total mass flow rate into and out of the reactor as well as the recycle
stream can be calculated based on the assumptions listed below:
¿ 1,838.24 kg /hr
1−x
× Stoichiometric feed of propylene carbonate
x
1−0.65 kg
× 2083.65 of propylene carbonate
0.65 hr
¿ 1121.97 kg /hr
1−x
× Stoichiometric feed of methanol
x
1−0.65 kg
× 1307.72 of methanol
0.65 hr
=704.16 kg/hr
52
The second reactor operates at 150°C and 1 atm which involve the main
reaction to produce dimethyl carbonate (DMC). Propylene carbonate produced from
the previous reaction is used together with methanol to undergo transesterification
process towards DMC production with a conversion rate of 65% for both raw
materials.
Apart from the production of the propylene glycol by-product, there will also
be unreacted methanol and propylene carbonate present in the outlet stream of the
second reactor. The separations of these chemicals are based on their respective
boiling points. Up to this point of process flow, both alternatives possess similar
route of reaction. The following separation description is based on the respective
alternative.
can be recycled back to the mixer before Reactor 2 whereas the latter can be sold in
the market that can further improve the profit of this process.
2.1.3.2 Alternative 2 Separation Process Description
The bottoms product from the first distillation column will be directed to the
second distillation column (Column 2) which separates the desired DMC product
from propylene carbonate (C4H6O3) and propylene glycol (C3H8O2) to achieve a
higher purity level of DMC up to 99%. Dimethyl carbonate has the second lowest
boiling point and based on the direct sequence choice, DMC is valid as the next
component to be separated because its greater volatility as compared to propylene
carbonate and propylene glycol. The gaseous DMC will be condensed accordingly to
obtain its liquid state.
Table 2.5: Comparison between Alternative 1 (Figure 2.3) and Alternative 2 (Figure
2.4)
SIMILARITIES
ALTERNATIVE 1 ALTERNATIVE 2
Separation follows a part of the direct Separation follows the direct sequence:
sequence:
DMC-Methanol / Propylene carbonate- DMC / Methanol / Propylene
Propylene glycol carbonate / Propylene glycol
Follow Heuristic 2 Follows Heuristic 2
Azeotropic mixture of DMC-Methanol Azeotropic mixture of DMC-Methanol
is separated first from PC and PG. The is not separated first from PC and PG
most difficult separation is done the instead, methanol is separated first.
last.
Follows Heuristic 4 Violates Heuristic 4
The desired DMC product which The desired DMC product which
requires the highest purity is separated requires the highest purity is not
at the end of the sequence. separated at the end of the sequence
instead, at the second component
separation.
piping system.
Follows Heuristic 3
Violates Heuristic 3
Separation favors near equimolar Separation does not favor near
amounts of distillate and bottoms equimolar amounts of distillate and
bottoms
Follows Heuristic 6 Violates Heuristic 6
Figure 2.5 and 2.6 shows the temperature, pressure and phase changes for the process flow diagrams shown above. The elaborations of
the specific changes are done as below.
Figure 2.5: Flow Diagram of Difference Elimination in Temperature, Pressure and Phase Change Operations for First Alternative
59
Figure 2.6: Flow Diagram of Difference Elimination in Temperature, Pressure and Phase Change Operations for Second Alternative
60
The effluent from the CSTR contains liquid propylene carbonate at 250°C
and 19.7 atm from the complete conversion of the reaction between carbon dioxide
and propylene oxide. For proper handling and safety purposes, pressure change is
done from 19.7 atm to 1 atm which is then followed by a consequent temperature
61
change to 150°C. These conditions are in accordance with the required operating
conditions for the next main reaction involving the production of dimethyl carbonate.
In packed bed reactor (PBR), the main reaction towards the production of
dimethyl carbonate from methanol and propylene carbonate occurs at 150°C and 1
atm as required in the presence of CeCu catalyst. Its effluent consists of unreacted
methanol and propylene carbonate; by-product propylene glycol and dimethyl
carbonate itself. The effluent will undergo an increase in pressure from 1 atm to 2
atm before entering the distillation column at 2 atm. The increased pressure is
selected on the basis of relative volatility of the components so that the azeotropic
mixture of DMC-methanol can be separated easily and effectively.
Pressure Temp.
change change
Liquid PG Liquid PG
188°C, 1 atm Temp. 25°C, 1 atm
change
The top product from the second distillation column involved in the
separation of propylene carbonate and propylene glycol consists mainly of propylene
glycol at 188°C and 1 atm. Propylene glycol can be sold to existing market as
another source of profit. Hence, it is better to convert the propylene glycol into the
liquid state which can be handled easily and conveniently. Pressure and temperature
change operations might be involved to achieve the desired outcome.
The top product from the high pressure column, a segment of the pressure
swing distillation column, involved in the separation of the azeotropic mixture of
dimethyl carbonate and methanol consists mainly of methanol at 137°C and 10 atm.
64
Methanol can be recycled back prior to the methanol inlet to PBR for the production
of dimethyl carbonate. Hence, it is required to purify further the distillate product
from the high pressure column to complement this need. Pressure and temperature
change operations might be involved to achieve the operating conditions of the
following low pressure column.
The top product from low pressure column which is liquid methanol is
discharge at 62°C and 1 atm. The liquid methanol is recycling back to the feed
stream. However the liquid methanol produced need to be cool down to 30°C in
order to meet the conditions of feed methanol.
In Step 5 of Task Integration step, all the reaction and process will be
substitute with appropriate and suitable unit processes. The possible flow diagrams
of this step is show figure 2.7 and figure 2.8 respectively based on flow diagram in
step 4. Basically, both flow diagram is almost the same and only differ in term of
their separation part in order to get the desired product (dimethyl carbonate). Based
on the figures above, figure 2.7 has been selected for the production of Dimethyl
Carbonate. This is because process flow diagram in figure 2.7 is roughly more
economical than figure 2.8 as the number of unit operation involved in that process is
less. Moreover, the separation part in the first alternative is highly preferable as it
follow the heuristics rules which are very helpful to determine the optimum final
design. Table 2.6 shows the summary and description of every unit operations used
in the production of dimethyl carbonate based on the chosen alternative flow diagram
(Figure 2.7).
66
Cooler Function:
(E100,E-101, E-102) To decrease the temperature
D-100:
Operating Temperature: 150 oC
Operating Pressure: 2 atm
Top Product: CH3OH, DMC
Bottom Product: C3H8O2, C4H6O3
D-101:
Operating Temperature: 198 oC
Operating Pressure: 1 atm
Top Product: C3H8O2
Bottom Product: C4H6O3
Heater Function:
(H-100, H-101, H-102, H-103) To increase the temperature
HPC:
Operating Temperature: 150oC
Operating Pressure: 10 atm
LPC:
Operating Temperature: 50oC
Operating Pressure: 1 atm
Mixer Function:
(M-100, M-101) To mixer the feed stream and recycle
stream
Pump Function:
(P-100, P-101, P-102) To increase the pressure
Reactor Function:
(SR-1, SR-2) Place for desired reaction to occur
Valve Function:
(V-100, V-101, V-102) To decrease the pressure
72
A CO2 stream (Stream 1) and a C3H6O stream (Stream 4) which consist of their
pure gaseous and liquid form respectively is directed to temperature and pressure change
unit operations in the form of compressor, pump and heaters where all the feed streams
are converted to vapor phase prior entering the first reactor. These streams (Stream 1 and
Stream 4) are then fed into a plug flow reactor (SR-1) where both components are
reacted and converted to form propylene carbonate as one of the main raw materials for
the DMC production. The reaction conversion is 100 % and there is no particular side
reaction with other by-products.
Stream 7 as the outlet stream of the PFR channels the C4H6O3 to an expander (C-
101) for pressure reduction operation from 19.7 to 1 atm which cause a consequent
phase change from vapor to liquid in Stream 8. This is followed by a mixer (MIX-100)
that combines Stream 8 with the recycle C4H6O3 stream (Stream 29). The resulting
73
The reactor outlet (Stream 11) is then fed into a pump to increase the pressure
from 1 to 2 atm where it is then fed into a distillation column (DC-100). It is meant to
separate the azeotropic DMC-CH3OH mixture (Stream 13) from C4H6O3 and C3H8O2.
The bottoms product of DC-100 (Stream 16) is further separated at the distillation
column (DC-101) at 1 atm to Stream 28 and Stream 29 which consists of a major portion
of C3H8O2 and C4H6O3 respectively. The distillate C3H8O2 product from DC-101 (Stream
28) is then fed to a cooler to reduce the temperature from 187.69°C to 25°C and it can be
sold at 99.98% purity. Stream 29 consists of 99.9% C4H6O3 with very minor traces of
C3H8O2 which can be recycled back to the PBR for DMC production.
As for the distillate products from DC-100 (Stream 13), DMC is separated from
CH3OH using pressure-swing distillation consisting of a High-Pressure Column (HPC-
100) and a Low-Pressure Column (LPC-100). Stream 13 is first fed to a pump and heater
to satisfy the required operating HPC conditions at 10 atm. Pressure swing distillation is
deemed to be a simpler and more economical method of azeotropic separation which
involves the use of two columns at different pressures.
In the High-Pressure Column (HPC-100), almost 99% of the DMC molar flow
rate is collected in the bottoms product of HPC-100 (Stream 19) at 99% purity before
subsequent pressure and temperature reduction operation. The distillate product (Stream
17) from HPC-100 is temperature- and pressure-adjusted to 50°C and 1 atm respectively
according to the operating conditions of the following Low-Pressure Column (LPC-
74
100). LPC-100 aims to recover as much CH3OH as possible for the purpose of recycling
back to the PBR through Stream 23. It also prevent build-up of inerts such as CO2 or
DMC in the PBR if left uncontrolled.
75
CHAPTER 3
3.1 Introduction
This plant design project will involve the manual calculations of the material and
energy balance within the process based on simple and quick methods in Systematic
Methods of Chemical Process Design (Biegler et al., 1997) and other several methods in
Transport Processes and Unit Operations (Geankoplis, C.J., 1993). The manual
calculations will be shown briefly in the following sub-chapters based on equipment and
the process simulation is executed using Aspen Plus simulator.
76
Material balances are the some of the basic parts of a process design. Mass and
matter cannot be created nor destroyed, as stated by the law of conservation of mass.
This statements tells us that mass and matter could only enter and exit a system, be it in
the same form or another form. Additional mass could not be created in the system nor
be reduced within the system unless mass enters or leaves the system respectively. The
general equation of the law of mass conservation is shown for a particular component:
Input = Output
This dimethyl carbonate production plant does not involve any mass destruction
or generation as described. It involves purely the mass inlet that is equal to the mass
outlet. All material balance calculations will be based on the mass basis for evaluation
purposes.
Antoine Equation constants can be used to determine the partial pressure of each
pure component especially with those which are related to the vapor phase in the system.
The equation is as follows:
B
ln P° = A –
T ( K ) +C
77
S8 S32 S9
kmol/hr kg/hr kmol/hr kg/hr kmol/hr kg/hr
CO2 1.9726 86.8147 - - 1.9726 86.8147
C4H6O3 20.4100 2083.656 10.9900 1121.969 31.4000 3205.6266
9 7
Total 22.3826 2170.471 10.9900 1121.969 33.3726 3292.4413
6 7
1
DMC 20.4121 1838.722 20.4100 1838.538 0.0021 0.1839
0 1
C3H8O2 20.4100 1552.996 0.0020 0.1522 20.4080 1552.8447
9
Total 75.7667 5304.893 44.3599 2629.593 31.4068 2675.2993
0 7
Streams S12 S13/16
Total mole 75.7667 75.7667
Total mass 5304.8930 5304.8930
7 3
Total 31.4068 2675.299 20.4136 1553.120 10.9932 1122.2684
3 9
Streams S27 S28/29
Total mole 31.4068 31.4068
Total mass 2675.2293 2675.2293
At the steady-state condition, the first law of thermodynamics for an open system
is deduced as shown below:
Similar to the assumptions made for the material balances, ideal properties are
also assumed in the evaluation for the energy balances. The detailed assumptions used to
calculate the energy flow rate of each streams are listed below:
i) The kinetic and potential energies for these streams are neglected and
only enthalpy changes are considered in the calculations.
ii) All processes in the equipment are at steady-state conditions.
iii) Pressure (Po) and temperature (To) are taken at 1 atm and 298.15 K
respectively for the standard reference state or datum for enthalpy where
∆H=0.
iv) For preliminary calculations, there is no ∆H of mixing or pressure effect
on ∆H.
v) No other heat outlet or inlet from the surrounding, each unit operation
and pipe in the system is assumed perfectly insulated.
102
The reference state for the components are at liquid state with 298.15 K and 1
atm. The general formula of specific enthalpy for gas and liquid mixtures are:
∆Hv (T,y) = ∑
k
y k(∆ H o + C o (T) dT + ∆ H k )
f ,k ∫ p, k vap
∆HL (T,y) = ∑
k
y k(∆ H o + C o (T) dT )
f ,k ∫ p, k
where
-393.50 (g)
Propylene carbonate C4H6O3 -613.80
Methanol CH3OH -238.60
Dimethyl carbonate (CH3O)2CO -607.27
Propylene glycol C3H8O2 -501.00
The reference state for the components are at liquid state with 298.15 K and 1
atm except for carbon dioxide which is at vapour state at the specified conditions. The
general formula of specific capacities for gas and liquid mixtures are:
k k 0.38
T c −T 2
∆Hvap,k (T2) = ∆Hvap,k (Tb) x k k
T c −T b
Pipeline
For Stream 1,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, -78 °C, 1 atm)
6 kJ
Ḣ 1=−8.89× 10
h
For Stream 22,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, 52°C, 1 atm)
kJ
Ḣ 22=−0.772 ×106
h
For Stream 34,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, -65°C, 1 atm)
6 kJ
Ḣ 34=−8.88× 10
h
106
C-100
H-100
107
For Stream 3,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, 250 °C, 1 atm)
→ Carbon dioxide (g, 250 °C, 19.7 atm)
kJ
Ḣ 3=−8.60× 106
h
P-100
For Stream 4,
C3H6O (l, 25 °C, 1 atm) → C3H6O (l, 15 °C, 1 atm)
6 kJ
Ḣ 4 =−2.49 ×10
h
For Stream 5,
C3H6O (l, 25 °C, 1 atm) → C3H6O (l, 18.49 °C, 1 atm) → C3H6O (l, 18.49 °C, 19.7 atm)
kJ
Ḣ 5=−2.48× 106
h
H-101
For Stream 6,
C3H6O (l, 25 °C, 1 atm) → C3H6O (l, 34.2 °C, 1 atm) → C3H6O (g, 34.2 °C, 1 atm)
→ C3H6O (g, 250 °C, 1 atm) → C3H6O (g, 250 °C, 19.7 atm)
6 kJ
Ḣ 6=−1.69× 10
h
109
SR-1
For Stream 7,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, 250 °C, 1 atm)
110
C-101
For Stream 8,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, 196.5°C, 1 atm)
7 kJ
Ḣ 8=−1.27× 10
h
MIX-100
111
For Stream 9,
Carbon dioxide (g, 25 °C, 1 atm) → Carbon dioxide (g, 355.9°C, 1 atm)
7 kJ
Ḣ 9=−1.78× 10
h
For Stream 32,
C4H6O3 (l, 25°C, 1 atm) →C4H6O3 (l, 196.5°C, 1 atm)
6 kJ
Ḣ 32=−6.38 ×10
h
112
E-102
SR-2
113
P-101
114
MIX-101
115
H-103
116
References : C4H6O3 (l, 25°C, 1 atm), CH3OH (l, 25°C, 1 atm), (CH3O)2CO (l,
150°C, 1 atm), C3H8O2 (l, 25°C, 1 atm), CO2 (g, 25°C, 1 atm)
117
P-102
118
H-102
119
HPC-100
120
References : CH3OH (l, 25°C, 1 atm), (CH3O)2CO (l, 150°C, 1 atm), C3H8O2 (l,
25°C, 1 atm), CO2 (g, 25°C, 1 atm)
ṅin Ĥin ṅout Ĥout ṅout ṅout
Substance (kmol/h) (kJ/mol) (kmol/h) (kJ/mol) (kmol/h) (kmol/h)
E-103
6 kJ
Ḣ 18=−5.97 × 10
h
VLV-101
VLV-102
VLV-100
124
LPC-100
125
References : CH3OH (l, 25°C, 1 atm), (CH3O)2CO (l, 150°C, 1 atm), CO2 (g, 25°C,
1 atm)
ṅin Ĥin ṅout Ĥout ṅout Ĥout
Substance (kmol/h) (kJ/mol) (kmol/h) (kJ/mol) (kmol/h) (kJ/mol)
DC-101
127
References : C4H6O3 (l, 25°C, 1 atm), CH3OH (l, 25°C, 1 atm), (CH3O)2CO (l,
150°C, 1 atm), C3H8O2 (l, 25°C, 1 atm)
ṅin Ĥin ṅout Ĥout ṅout Ĥout
Substance (kmol/h) (kJ/mol) (kmol/h) (kJ/mol) (kmol/h) (kJ/mol)
CHAPTER 4
4.1 Introduction
The process simulation of this chemical plant design is executed using a software
called ASPEN PLUS to precede the calculations. Appendix E shows the stream
summary table based on manual calculations whereas Appendix F illustrates the overall
process flow diagram and stream summary table obtained from process simulation.
The software used for the simulation, modelling and optimization of all flow
sheets was Aspen PLUS, a process simulator software that is used to create or simulate
models and optimize flow sheets. A model created in PLUS environment also features
the possibility to have sub models inside a top level model. To simulate a flow sheet, the
process is run while PLUS calculates the degrees of freedom and solves the
multivariable system. PLUS features as well the possibility to use initialization
procedures instead of assigning initial conditions on the models. Although it is really
handy, it may be time consuming especially in the column models which are really
sensitive to initial guesses.
130
A computer based process simulator is a useful tool for designers and plant
operators in a number of ways. The ability to imagine and simulate the operations of
one’s own plant is a very crucial capability. A computer generated simulator could
provide information vital for the users to substitute data that are not readily available
from the control instrumentation and literature. Simulations of the plant could also be
used to cross check the actual performance comparing to the simulated work load and
efficiency. Thus, errors and mistakes such as faulty instruments and instrument could be
readily identified and rectified.
For the current project, the simulator program used is called Aspen PLUS. The
simulation carried out for this project is to compare the results of manual calculations
and the simulated values to provide assurance that the assumptions and calculations
made were correct and as close as possible to actual plant operations.
After obtaining all the necessary information and values for each stream, the
manually-calculated values were compared with the simulated values to verify the
validity of the manual calculations and justify the assumptions made. ARD or
percentage error is calculated based on the equation shown below. The calculations for
error is the same for both mass balance and energy balance as well as equipment duties.
As shown in Table 4.1, most of the streams have low percentage errors which are
less than the limit set at 15%. As a whole, the process is still deemed acceptable since
most streams register percentage errors within the limit set.
As shown in Table 4.2, most of the streams have commendable low percentage
errors which are still lesser than the limit set at 15%. Among the largest errors obtained
was found in Stream 6 at 14.996% with justifications of this error provided. As a whole,
the process is still deemed acceptable since most streams register percentage errors
within the limit set.
133
4.4.2.1 Justifications
CHAPTER 5
INNOVATION POTENTIAL
The process flow diagram for the production of dimethyl carbonate has been
developed based on the reference of previous research studies and existing patented
designs. The patented design and new process flow design that has been developed are
shown in the Appendix E. There were some significant changes or modifications made
that would improve the production rate and efficiency of the dimethyl carbonate. The
summarized modifications and their respective effects is concluded in Table 5.1.
velocitye.
Purification system Crude CO2 and propylene Pure CO2 and propylene oxide
for reactants is oxide are fed into the Plug are bought by distributors and
absent Flow Reactor (PFR). Possible manufacturers. Purification
purification systems for the systems are not required to
reactants are required for this avoid purchasing additional
operation. equipment for the purification
of the reactants. High purity
of CO2 and propylene oxide
are necessary for the reaction.
Recycling of There is no methanol recycle Methanol recovered from
methanol recovered operation executed which leads Low Pressure Column is large
to a large amount of waste and enough to be sufficiently
methanol wastage as well as recycled back prior entering
eventual high cost of purchase the Packed Bed Reactor
of methanol. (PBR). This can eliminate
problems posed when
methanol recycle operation is
not executed.
Pressure-swing Extractive distillation is used Pressure-swing distillation
distillation which requires an additional consists of two separate
technique is used to solvent. The solvent requires columns namely High
deal with DMC- further another separation Pressure Column and Low
methanol operation to recycle it for Pressure Column. It is used
azeotropic mixture wastage reduction purposes. when the azeotropic
Water is usually selected as the temperature and composition
solvent but it will eventually are sensitive to the operating
form another azeotropic pressure. DMC-methanol
mixture with methanol. This mixture falls in this category.
also means a far more costly It may cause high energy cost
solvent such as aniline is but it is an environmental-
137
CHAPTER 6
6.1 Introduction
Energy usage is one of the driving forces of the chemical industry, where heating
and cooling of material flow is needed to achieve the optimal conditions for the
production of certain waste or the decomposition of unneeded waste. However, most
energy consumption first seen in designs are usually wasteful, as energy circulation does
not occur in the original design. Therefore, it is crucial to conduct energy recovery
within the compounds of the production plant.
comparison with the utility consumption after the integration. Through this, energy
utilities could be optimised with the reduction of external utilities and the operating cost
of obtaining the utilities.
Steps:
1. Extract data, such as ΔT and average heat capacity, Cp from the
simulator.
2. TS and TT are shifted according to the ΔTmin, which in most cases are
10°C. The shifted temperatures are set up in intervals and similar values
are removed.
a. For hot streams, TS & TT are shifted by deducting ½ ΔTmin.
b. For cold streams, TS & TT are shifted by adding ½ ΔTmin.
140
To calculate the energy recovery of the process, the crucial part is data extraction
where the backbone of the process energy stream dissected. The plant consists of ten
heat exchangers, E-100, E-101, E-102, E-103, E-104, H-100, H-101 H-102 and H-103
and consists of two type of stream, hot and cold. Hot streams possess surplus energy
which needs to be stripped from it while cold stream is deficit in term of energy. Thus,
pinch analysis is able to calculate the energy recovered from those streams.
Composite curve is one of the good methods to set energy targets. Nevertheless,
it is inconvenient because to integrate energy for a plant, one has to base on a graphical
illustration. This inevitably will cause errors in read values because of parallax errors
making exact reading difficult to achieve. To solve this, a more systematic approach is
proposed here. This is known as the Problem Table Algorithm, which has been briefly
touched upon in the earlier part of this chapter. For this plant, ΔTmin is chosen to be
10°C, not through economic analysis but according to practical constraints. It is assumed
that shell-and-tube heat exchangers are used in this plant and therefore, the suggested
ΔTmin is 10°C (Seider, 2004).
a) Process streams are selected from Process Flow Diagram (PFD) of the
proposed plant. Selection is based on the presence of heat exchanger units
along the stream.
b) Determine hot streams and cold streams. Hot streams are streams that
need to be cooled down. Cold streams are just the opposite.
142
c) Fix ΔTmin.
d) Obtain values of flow rate (F), specific heat capacity (CP) and stream
temperature (T) from simulation results.
e) Evaluate FCP and ΔH.
f) Evaluate shifted temperature, TS for Tsupply and Ttarget.
• For hot streams, Ts,supply = Tsupply - ΔTmin/2
Ts,target = Ttarget - ΔTmin/2
• For cold streams, Ts,supply = Tsupply + ΔTmin/2
Ts,target = Ttarget + ΔTmin/2
g) List shifted temperature from top to bottom in an increasing manner.
Remove duplicates if any.
h) Evaluate ΔTint for every interval.
i) Sketch hot and cold streams with an arrowed straight line going from their
respective Tsupply to Ttarget. This way, cold streams will have straight lines
with an arrow pointing upward whereas hot streams will have arrow pointing
downward.
j) Evaluate ΣFCP,Hot – ΣFCP,Cold for every shifted temperature interval.
k) Evaluate ΔH by multiplying results from step (j) with their respective
temperature intervals. Negative values mean deficit of heat whereas positive
values mean surplus of heat.
l) Draw a heat cascade table and insert all evaluated ΔH values from top to
bottom into the table. Cascade the heat from higher to lower TS.
m) Draw another similar table and add the largest negative heat flow to the top
of the heat cascade table and cascade the heat all the way down the table.
n) Determine the pinch point. Pinch point occurs at the interval where the heat
flow is zero.
o) Determine the minimum heating, QH,min and cooling, QC,min
requirements. QH,min is the value of the largest negative heat flow added to
the top of the table. QC,min is the resultant value of heat flow at the bottom
table after cascading of heat flow.
Actual Shifted
Type HEX Tin Tout T′in T′out FCP ∆T Q
(oC) (oC) (oC) (oC) (kW/oC) (oC) (kW)
C1 H-100 200.8 250.0 205.8 255 0.28 71 14
C2 H-101 18.5 250.0 23.5 255 1.22 232 283
C3 H-102 10.8 150.0 15.8 155 2.54 56 353
C4 H-103 30.0 150.0 35 155 2.20 120 264
H1 E-100 183.9 25.0 178.9 20 1.05 46 167
H2 E-101 187.7 25.0 182.7 20 1.21 163 197
H3 E-102 196.0 150.0 191 145 5.09 45 234
H4 E-103 137.0 50.0 132 45 0.52 65 45
H5 E-104 241.8 196.0 236.8 191 0.66 87 30
H6 E-105 62.0 30.0 57 25 0.59 32 19
144
Figure 6.1 clearly shows the process-to-process heat exchange where the pinch
analysis could minimize the heating and cooling utility.
147
The design for the heat exchanger network is started at the pinch point. There are
several rules that must be considered during the design. As mentioned before,
assumption has been made that no individual exchanger should have a temperature
difference smaller than ΔTmin. Besides, in order to achieve the energy target, set by the
composite curves, there must be no heat transfer across the pinch either by process-to-
process heat transfer or inappropriate use of utilities. To comply with this rules, the
process should be divided at the pinch, where the design is done based on the above and
below pinch.
For the above pinch design, the following rules must be fulfilled:
i. The temperature differences of the hot and cold streams must be greater or equal
to ΔTmin. (≥10°C).
ii. Above the pinch, only heater (eg. steam, heating oil) can be used up to QH,min.
ii. Only can pair stream where the cold stream CpC is greater or equal to hot stream
CpH (CpC ≥ CpH)
iii. Check that the temperature profile of stream matching is not crossing.
For the below pinch design, the following rules must be fulfilled:
i. The temperature differences of the cold and hot streams must be greater or equal
to ΔTmin (≥10°C).
148
ii. Below the pinch, only cooler (eg. cooling water, refrigerant) can be used up to
QC,min.
iii. Only can pair stream where the cold stream CpC is smaller or equal to hot stream
CpH (CpC ≤ CpH)
iv. Check that the temperature profile of stream matching is not crossing
196
H1 2 150
188
H2 3 25
241
H3 8 5 196
90
H4 1 25
137
H5 4 50
62
H6 7 6 30
179
250 8 7 C1
18
250 H 5 C2
219.44 kW
94
150 1 C3
30
150 6 4 3 2 C4
Heating=488.89 kW
Cooling=269.45 kW
Heat recovered:
Heating=488.89 kW−219.44 kW
150
Heating=269.45 kW
Cooling=269.45 kW −0 kW
Cooling=269.45 kW
269.45
Heating= × 100 %
488.88
Heating=55 %
269.45
Cooling= ×100 %
269.45
Cooling=100 %
151
CHAPTER 7
PROCESS OPTIMIZATION
7.1 Introduction
Any kind of process that systematically comes up with solutions that are better
than the previews solution is known as a process optimisation Optimization can be used
in different tasks such as new system design, the synthesis of a new processing network,
and the retrofit design and operational improvements in heat exchanger, reactor, and
separation networks. This kind of process performs searches in a large search space,
hitting small, low probability targets Thus, optimisation used in chemical engineering to
find the best available option for a problem (Klemes, 2011).
can be changed by manipulating the decision variables. There are two types of system
properties that determine this function:
a) Parameters
A set of characteristics that do not differ with respect to the choice to be made.
b) Variables
A set of characteristics that are allowed to differ (Klemes, 2011). Some of the
variables are specified by the decision maker or are manipulated by the
optimization tools; these are referred to as specifications or decision variables
(Klemes, 2011). The remaining variables are termed dependent variables, and
their values are determined by the specifications and the system’s internal
relationships
For this plant, the optimization process was conducted on distillation column,
DC-101. The objective function is to minimize the total cost emerge during operating
the equipment while, increase the profit of selling the product. Reflux ratio and number
of stages of the distillation column were set as the variable. The constraints is to achieve
154
at least 99% of propylene carbonate recovery. Other variables such as feed condition,
feed stage, operating pressure and temperature were at constant value to act as a
parameter.
α x
∑ αi−θi , f =1−q
i
α x
∑ αi −θ
i ,d
=Rm +1
i
N m=
[(
log
xL , D D
xH , D D )( xH , B B
x L, B B )]
log [ α L ,av ]
α L ,av = √α LD α LB
155
N −N m R−Rm
Y= ,X=
N +1 R +1
Y =1−e
[( 1+54.4 X
11 +117.2 X )( XX−1 )]
0.5
From the equation listed above, it can be noticed that the number of stages
required will be dependent on the reflux ratio. Table 7.1 shows the extracted data to for
the graph of optimization.
156
350000
300000
Annualized Cost, $
250000
200000
150000
100000
50000
0
1 6 11 16 21 26 31
Number of Trays,N
From the Figure 7.1, the capital cost decreases initially and increases afterwards.
Meanwhile, the total operation cost increases linearly as number of stages decrease. The
optimum condition of DC-101 is where the lowest total annualized cost achieved at
$186,523.3596 with optimum reflux ratio of 0.2681 and optimum number of stages of 9.
Table 7.2: Comparison Before and After Optimization for Distillation Column (DC-
101)
Before Optimization After Optimization
Annualized Capital 27532.1375 22090.4212
Cost ($)
Operating Cost ($) 281272.3545 164432.9383
Total Cost ($) 308804.4920 186,523.3596
Total Saved ($) 122281.1324
Percentage Saved 60.40%
The results shown are quite significant, with a cost saving of about 60.40%, a
large amount of about $122281.1324 is conserved for other purposes of the plant, which
shows the capability of what optimization could improve for the plant.
160
CHAPTER 8
8.1 Introduction
Equipment sizing is the one of the important parts in the plant design project
especially when analyzing the feasibility and profitability of the plant. This is because it
involves the calculation of the equipment design as well as their respective cost which
includes the type of constructing material, length of vessel, diameter of pipelines and
some even the inner diameter. After implementing heat integration, there are 25
equipment that are involved in the dimethyl carbonate production plant. This include
major equipment such as reactors, distillation columns, flash columns, heat exchangers,
pumps and relief valves. In this section, the summary of the sizing and costing of each
equipment is outlined.
8.2 Reactors
Reactor is the heart of the chemical plant where the reactions take place to
convert the raw materials to desired products. There are a few main parameters needed
to be considered in order to design the reactor. The first parameter is the type of reactor.
161
In this chemical plant, the reactors used are Plug Flow Reactor (PFR) and Packed Bed
Reactor (PBR).
The plug flow reactor involves the reaction between carbon dioxide and
propylene oxide in gaseous forms to produce propylene carbonate as one of the raw
materials needed for the production of dimethyl carbonate later on.
Main reaction:
Conversion: 96%
Assumptions made: - Steady state condition
- Exothermic reaction
162
Main reaction:
Conversion: 65%
Assumptions made: - Steady state condition
163
- Exothermic reaction
Table 8.2: Packed Bed Reactor (SR-2) Equipment Specification Sheet
Equipment Specification Sheet
Item No : SR-2
Identification : Packed Bed Reactor
Function : To produce dimethyl carbonate and propylene glycol (by-product) from
transesterification reaction between propylene carbonate and methanol
Technical Specification Design Sizing
Design Type Vertical Diameter (m) 1.5556
Material of Construction Carbon steel Height (m) 6.2224
Volume (m3) 11.8254
Operating Condition
Temperature (°C) 150
Pressure (atm) 1
Equipment cost estimation : RM 1,069,034.44
The separation columns used in this chemical plant include ordinary distillation
columns and a flash column aimed to facilitate desired separation of the components to
obtain a highly pure final dimethyl carbonate product.
8.4 Compressor
8.5 Expander
8.6 Pumps
Temperature (°C) 18
Pressure (atm) 19.7
Equipment cost estimation : RM 53,062.26
There are a wide variety of heat exchangers is available for heating, cooling,
condensing, and vaporizing process streams, particularly liquids and gases. The heat
exchangers used in this chemical plant include nine double-pipe heat exchangers and a
shell-and-tube heat exchanger aimed to transfer heat between the streams in the
production of dimethyl carbonate. For heat exchange surface areas of less than 200 ft 2,
double-pipe heat exchangers are selected over shell-and-tube heat exchangers.
8.8 Heaters
8.9 Mixers
Costing
Equipment Cost (RM)
Propeller 19,661.94
Pressure vessel 21,578.40
TOTAL COST 41,240.34
CHAPTER 9
MECHANICAL DESIGN
9.1 Introduction
The detailed sample calculations for the mechanical design of DC-100 are
provided in the Appendix. The mechanical design calculations are conducted based on
Chemical Engineering Volume 6, Systematic Methods of Chemical Process Design and
A Guide to Chemical Engineering Process Design and Economics.
There are several major parameters that requires consideration when the
mechanical engineering design of a pressure vessel or a separation column is involved.
The parameters discussed are as the following.
Pressure vessels are constructed from plain carbon steels, low and high alloy
steels, other alloys, clad plate, and reinforced plastics. Selection of a suitable material
must take into account the suitability of the material for fabrication (particularly
welding) as well as the compatibility of the material with the process environment. The
pressure vessel design codes and standards include lists of acceptable materials; in
accordance with the appropriate material standards.
Thus, the process vessels that are in contact with corrosive materials or operating
at high temperature will be fabricated. In this plant, most equipment will use stainless
steel 304 instead of the higher cost of stainless steel 316 despite its better resistance to
corrosion especially for more saline or chloride-exposed environments. It is because the
stainless steel 304 is still deemed sufficient for the corrosive components existing in the
178
process streams of dimethyl carbonate production. All the other process vessels shall use
carbon steel as the material of construction.
The “corrosion allowance” is the additional thickness of metal added to allow for
material lost by corrosion and erosion, or scaling. The allowance to be used should be
agreed between the customer and manufacturer. Corrosion is a complex phenomenon
and it is not possible to give specific rules for the estimation of the corrosion allowance
required for all circumstances. The allowance should be based on experience with the
material of construction under similar service conditions to those for the proposed
design.
For carbon and low-alloy steels, where severe corrosion is not expected, a
minimum allowance of 2.0 mm should be used; where more severe conditions are
179
anticipated, this should be increased to 4.0 mm. Most design codes and standards specify
a minimum allowance of 1.0 mm.
Vessel shell
Vessel fitting (man-way, nozzles)
Internal fitting, plate (plus the fluid on the plates), heating and cooling coils
External fitting, ladders, platforms, piping
Auxiliary equipment which is not self-supported, condenser, agitators
Insulation
Weight of liquid to fill vessel (the vessel will be filled for hydraulic
pressure test and may fill with process liquid due to offset (miss-
operating).
180
There will be a minimum wall thickness required to ensure that any vessel is
sufficiently rigid to withstand its own weight, and any incidental loads. As a general
guide the wall thickness of any vessel should not be less than the values given below;
the values include a corrosion allowance of 2 mm. The maximum wall thickness will
include vessels internal pressure and design pressure.
The end of cylindrical vessels is closed by head of various shapes such as flat
plates, hemispherical heads, ellipsoidal or torispherical heads. The choices of the
closure for the vessels in the dimethyl carbonate production plant were based on the
operating pressure.
181
The strength of a welded joint will depend on the type of joint and the quality of
the welding. The soundness of welds is checked by visual inspection and by non-
destructive testing (radiography). The possible lower strength of a welded joint
compared with the virgin plate is usually allowed for in design by multiplying the
allowable design stress for the material by a “welded joint factor” J. The value of the
joint factor used in design will depend on the type of joint and amount of radiography
required by the design code. Typical values are shown in Table 9.2. Taking the factor as
1.0 implies that the joint is equally as strong as the virgin plate; this is achieved by
radiographing the complete weld length, and cutting out and remaking any defects. The
use of lower joint factors in design, though saving costs on radiography, will result in a
thicker, heavier, vessel, and the designer must balance any cost savings on inspection
and fabrication against the increased cost of materials.
The method used to support a vessel will depend on the size, shape, and weight
of the vessel; the design temperature and pressure; the vessel location and arrangement;
and the internal and external fittings and attachments. Horizontal vessels are usually
mounted on two saddle supports; Figure 9.1. Skirt supports are used for tall, vertical
columns; Figure 9.2. Brackets, or lugs, are used for all types of vessel; Figure 9.3. The
supports must be designed to carry the weight of the vessel and contents, and any
superimposed loads, such as wind loads. Supports will impose localized loads on the
vessel wall, and the design must be checked to ensure that the resulting stress
concentrations are below the maximum allowable design stress. Supports should be
designed to allow easy access to the vessel and fittings for inspection and maintenance.
Figure 9.2: Typical Skirt-Support Designs (a) Straight Skirt (b) Conical Skirt
Figure 9.3: Bracket Supports (a) Supported on Legs (b) Supported from Steel-Work
184
The overall drawing shows the mechanical design of engineering that indicates
the important dimension of the equipment. Also, the equipment specification data sheet
was prepared for the equipment along with its estimated cost in the dimethyl carbonate
production plant. It must be emphasized that the estimated cost of the equipment was
based on the results of economic analysis and fixed capital cost which is presented in the
Chapter 9. The detailed sample calculations for this mechanical design are shown in the
Appendix.
(in)
Wind loading (kN/m)
Bending moment (MNm)
Head and Closure Design Analysis of Stress
Type Horizontal pressure
stress (N/mm2)
Thickness (mm) Longitudinal pressure
stress (N/mm2)
Dead weight stress
(N/mm2)
Bending stress (N/mm2)
Longitudinal stress
(N/mm2)
Upwind
Downwind
Elastic stability
(N/mm2)
Skirt Support Design
Total weight loading (kN)
Bending moment at skirt base (kNm)
Bending stress (N/mm2)
Maximum resultant stress (N/mm2)
Tensile strength
Compressive strength
Skirt thickness (mm)
Cost per equipment
186
CHAPTER 10
Waste Treatment
10.1 Introduction
This chapter will deal with wastes generated from the production of dimethyl
carbonate. Raw materials that were used in the production will undergo a series of
processing steps and generate several by-products as well as the desired product in
which unwanted products can be sold to generate additional income or utilized in other
environmental-friendly ways. Since it is impossible to achieve a complete (100%)
conversion rate of the raw materials into valuable products, the generation of residual
waste is inevitable and alternatives are introduced to reduce the detrimental effects
caused by these residual waste towards the environment and society.
considerations whereby the treated waste can be recovered for production purposes or
sold as another useful by-product. With that, there are two approaches identified to deal
with the waste generated by any form of industry namely waste minimization and end-
of-pipe treatment.
The end-of-pipe treatment, on the other hand, involves the transformation of the
waste generated into another form of useful or less harmful materials or components by
physical, chemical and biological methods or the combination of several methods. This
ensures the safe discharge of the transformed waste that will not cause extreme
detrimental effects to the environment. Hazardous waste materials, despite the treatment
made, can be directed to established waste treatment facilities or organizations such as
the waste management center of Kualiti Alam at Port Dickson, Negeri Sembilan.
in-situ waste reduction due to the fact that generation or accumulation of the waste
materials will still occur in a recycle loop. Waste treatment should only be considered
before the final preferable disposal option is considered when these two preferred
options are no longer possible.
Figure 10.1 below shows the hierarchy of waste management in the order from
the most preferred options to the least preferred ones.
The waste minimization and waste treatment plant is entitled to achieve the
following objectives as stated below when dealing with waste generation.
a) Reduce waste treatment and disposal cost, raw material purchasing cost and
other operating costs such as utility costs.
b) Meet state and national waste minimization and treatment policy goals.
c) Reduce potential environmental liabilities.
d) Protect public health and workers’health.
1) A primary standard to protect public health. The Clean Air Act mandated
primary standards to be based entirely on health-related information, without
considering the cost of attaining the standard.
2) A second standard to protect public welfare. Public welfare includes soils, water,
crops, vegetation, buildings, property, animals, wildlife, weather visibility,
transportation and other economic values as well as personal being.
The Clean Air Act, which was last amended in 1990, requires EPA to set
National Ambient Air Quality Standards for pollutants considered harmful to public
health and the environment.
The EPA Office of Air Quality Planning and Standards (OAQPS) has set
National Ambient Air Quality Standards for six principal pollutants, which are called
“criteria” pollutants. They are listed as in Table 10.5 as shown below.
Table 10.3: ‘Criteria’ Pollutants under National Ambient Air Quality Standards
Pollutant Primary / Averaging Level Form
Secondary Time
Carbon monoxide Primary 8 hours 9 ppm Not to be
(CO) 1 hour 35 ppm exceeded more
than once per
year
Lead (Pb) Primary and Rolling 3 0.15 Not to be
192
10.5 Methodology
This chapter deals with the methodology of the evaluation work of waste
minimization in dimethyl carbonate production plant. They include:
CHAPTER 11
11.1 Introduction
As a matter of fact, the design of a control system will involve a large number of
theoretical and practical considerations such as the quality of the control response,
stability of the operating plant, the reliability of the control system, the range of control
and ease of start-up, shut down and change over, the ease of operation and the cost of
control system.
196
There are several reasons behind the provision of automated process control in a
chemical plant, be it from safety, production, operating or economic perspectives. In
other words, it could be seen as constraints or conditions in which the process control
will operate within the boundaries of the stated constraints or conditions. The
requirements that are involved and considered in relation to process control will be
discussed in the following section.
11.2.1 Safety
For a typical chemical process, the primary requirement is the safe operation for
the well-being of people in the plant and conservation of economic resources of the
process in terms of safety measures allocation. Therefore, it would be best that the
operating conditions including pressure, temperature, concentration of certain
components and other parameters are ensured within the safety limits in order to reduce
the risk of any serious, life-threatening accidents or incidents such as explosions.
A plant should achieve the desired production rate and product quality during the
initial design of the plant. The process control design in this plant will complement the
plant to effectively and efficiently produce 15,000 MTA of dimethyl carbonate from the
transesterification of methanol and propylene carbonate. Besides the production rate, the
purity of dimethyl carbonate should be taken into consideration too whereby a specific
standard should be achieved.
197
Process control is also created to reduce the excessive utilization of raw materials
or utilities while maintaining the product quality at specified levels. With that, the plant
will be able to conserve economic resources and at the same time, still reaping the
profits at higher margins. Also, other constraints are also satisfied through the
establishment of process control systems.
In process control design, there are several controller configurations that can be
considered to be implemented according to the needs of the plant itself. The most
common controller strategy is the feedback control which is followed by feed forward
control. Some other type of controller strategies discussed includes cascade control and
ratio control.
198
rates. Ratio control could be used to specify relative amounts of components in blending
operations, maintain a stoichiometric ratio of reactants to a reactor, keeping a specified
reflux ratio for a distillation column and holding the fuel-air ratio to a furnace at the
optimum value.
PA Pressure Alarm
LA Level Alarm
It is important for reactors to have control systems of their own because they are the most crucial parts in a chemical plant in
the production of the desired component. The stability of the reactor needs to be maintained in a way that is able to sustain the
productivity of the plant as well as the safety of all those that are involved in the plant operation.
reaction rate is
maintained
To maintain the pressure of the reactors (SR-1 and SR-2) at 19.7
Control Objective 2 :
atm and 1 atm respectively
Controlled Measured Manipulated Control
Disturbances Justifications
variables variables variables configuration
Pressure of reactor Pressure of Amount of mass Flow rate inlet to Feedback The pressure should
reactor flow leaving the reactor be controlled to
reactor prevent accidents
such as explosions
as well as to
maintain the
reaction rate
204
(a)
205
(b)
Figure 11.1: Process Control Loop of Reactors (a) SR-1, (b) SR-2
206
The distillation column serves to separate the desired product from the other by-products or undesired materials. The
distillation column, however, is quite sensitive to changes in operating conditions such as temperature, pressure and others. Therefore,
it is important that a process control system is present to prevent off-sets in the operating conditions of the separation unit.
The low pressure column in this plant will function almost similarly to a flash column which also operates on the basis of
pressure and temperature change. Therefore, it is important that these conditional parameters are kept in check in order to obtain
products of high purity and quality. In order to achieve this, process control design is important for the flash column to be fully
functional and efficient.
The pressure-reducing valves in this chemical plant aim mainly to create a reduction in pressure for liquid-phase streams in
order to complement the operating pressures required for individual unit operations and to achieve suitable product condition for
proper storage. This explains the need for a process control system to ensure the pressure reduction operation functions as desired
without compromising the feasibility of the process and the safety of the personnel involved directly with it.
Figure 11.14: Process & Instrumentation Diagram (P&ID) for DMC Production Plant
235
CHAPTER 12
PROCESS SAFETY
12.1 Introduction
Safety, hazard and risks are some of the issues or terms that are closely related to
a chemical process safety. Safety or loss prevention is the prevention of accidents by
using appropriate technologies or procedural methods to identify the hazards created by
a chemical plant and to eliminate them before an accident occurs. Hazard, on the other
hand, is defined as any possible unpredictable factors that have the potential to cause an
accident whereas risk is related to the extent of probability of a particular hazard that
will result in an accident.
Therefore, due to the emergence of the knowledge and awareness of these danger
signs, many significant advanced technologies and progressive methods have been
created and implemented in chemical process safety ever since. Safety is important in
the development of scientific disciplines nowadays which include many highly technical
and complex theories and practices. The chemical industry has traditionally devoted
considerable attention to safety, beginning with the research and development of new
processes through plant design and construction. In a chemical plant, the main hazards
usually involve toxic and corrosive chemicals, explosions, fires and accidents which is
rather common as well among other industrial activities. The Health and Safety at Work
236
Act 1974 provided a new legal administrative framework to promote, simulate and
encourage even higher standards of health and safety at work.
Loading and offloading should only be allowed at carefully selected sites where
necessary facilities are installed. It should be within but near the perimeter fence, in
paved, leveled or concreted areas. The bay must be clearly marked and provided with
238
light roofs and upper side coverings to protect against sun and driving rain, but without
end wall for easy through-transit of vehicles and good natural ventilation. Only vehicles
approved for the liquid in question may be used (King, R., 1990).
Some of the checklist when dealing with the transport of hazardous chemicals at
further distances include:
A chemical plant has to be located sufficiently far from any housing areas in
order to minimize the probability of harming the public during any explosion, fire or
toxic release events which may cause catastrophic effects to the affected surrounding. A
good plant layout includes little or minimum possible movement of chemical materials
during the operations and one that involves unidirectional flow of the materials during
operations without involving any back tracking. There has to be maximum visibility,
minimum handling and maximum accessibility to the chemicals that can ensure proper
security with maximum flexibility.
239
A chemical plant should be designed in a way so that the sudden failure of one or
more utility supplies do not prove disastrous or undermine the feasibility and hence, the
safety of the process. The routing of service supplies should be as secure as possible.
The position of underground supplies should be clearly marked on drawings and, where
possible, by ground posts. Underground supplies must be adequately protected from
heavy vehicles. The different utility supplies are described as follows:
12.2.4.1 Electricity
The use of flameproof and intrinsically safe electrical equipment and conduit is
to reduce the risk of flammable gases, vapors and dusts. A ‘hazardous zone drawing’ is
made when all sources of leaks of flammable materials have been identified. This will
show the categories of electrical equipment that are allowed in each zone.
equipment must be properly grounded with entire wiring and electrical component
should comply with the standards of the local authority. Besides, there is a necessity to
have regular check and maintenance on all equipment to prevent future accidents.
12.2.4.2 Steam
12.2.4.5 Refrigerant
Many of the refrigerants formerly in common use are flammable (e.g. propylene)
and toxic (e.g. ammonia). Refrigeration plants using refrigerants other than water should
be designed so that the refrigerant is always under a positive pressure when the plant is
running.
12.2.5 Flammability
Flammability simply means the ease with which a material burns in air (or
occasionally in some other stated gas such as O2). It applies to gases, liquids and solids.
In most process industries, it is of the highest concerns regarding the flammability of
gases, liquids and their vapors and of dispersed dusts and liquid droplets in which all are
referring to as fuels. The result of ignition can be a fire or explosion or sometimes both.
Accidental fires and explosions of flammable air mixtures often follow the
escape of combustible materials, which may result from an uncontrolled reaction or an
explosion within the process or storage plant. The constructional materials used in the
process industries are mostly of low flammability, although the plant and structure used
often require fire protection. Flammable gases and vapors of flammable liquids are in
many ways more dangerous than the liquids themselves. This is because they are
242
invisible, cannot easily be contained and may travel considerable distance before they
reach an ignition source and ignite.
12.2.6 Explosion
Explosion in the vapor spaces of fixed roof storage tanks have seen its constant
number of events in recent years. The combustion reaction occurs in premixed medium
and is expanded by "flame propagation" through the premixed medium. The flame
propagation phenomenon is mainly governed by the combustion reaction rate, and the
propagation speed is relatively fast. The reason for the large number of explosion is that
explosive mixtures are present in the vapor space of many storage tanks. It is almost to
be certain that a source of ignition will never turn up, particularly if the liquid in the tank
has a low conductivity so that static charges can accumulate on the liquid. For this
reason, many companies insist that fixed roof storage tanks containing hydrocarbons
above their flash points must be blanketed with nitrogen. Other companies insist that
such hydrocarbons are stored only in floating roof tanks.
12.2.7 Leaks
Leakage of process materials is one of the major hazards faced by most process
industries. Most of the materials handled will not burn or explode unless mixed with air
in certain proportions. To prevent fires and explosions, the fuel must be kept in the plant
244
and the air out of the plant. The latter is relatively easier because most plants operate at
atmospheric pressure. Nitrogen (N2) is widely used to keep air out of low-pressure
equipment such as storage tanks, stacks, centrifuges and equipment which is de-
pressurized for maintenance.
The main problem in preventing fires and explosions is thus preventing the
process material from leaking out of the plant to maintain plant integrity. Similarly, if
toxic or corrosive materials are handled, they are hazardous only when they leak. Many
leaks have been discussed under other headings, including leaks which occurred during
maintenance, as the result of human error, or as the result of overfilling storage tanks.
Other leaks have occurred as the result of pipe or vessel failures.
Methanol can enter the body either through the respiratory system, skin or the
digestive tract, and toxicity effects on the body are similar regardless of the pathway.
While certain risks, particularly those associated with skin contact or accidental
ingestion, are easily mitigated by use of proper fuel handling procedures and controls,
the risks associated with exposure to evaporative or tailpipe emissions from methanol
vehicles are far more complex and less well understood. Inhalation exposure risk
scenarios vary in concentration levels and duration: methanol concentrations in confined
or poorly-ventilated areas such as personal garages can be fairly high, but the time of
exposure may be fairly short.
Apart from these direct risks, this paper also discusses the indirect risks of
methanol use, including exhaust emissions of air toxics such as formaldehyde and life-
cycle emissions of climate-changing “greenhouse” gases. There is also the indirect
health risk of greenhouse gas emissions resulting from methanol fuel production.
245
However, the potential public health and/or welfare impact of greenhouse gas emissions
poses a significant global challenge and widespread use of either coal or natural gas for
methanol fuel production could exacerbate an already critical situation. Traditional
methods of producing methanol from coal release approximately twice the equivalent
CO2 emissions per unit energy as conventional petroleum, unless measures are taken to
reduce or displace the carbon emissions. These broader consequences of methanol fuel
use must be measured relative to the considerable human health challenges posed by the
continued use of petroleum-based fuels (Brusstar et al., n.d.).
A few basic safety rules that must be observed by workers when dealing directly
and indirectly with a chemical process in a plant involve the following:
No smoking or eating
No drinking of alcoholic liquor
No drinking, except from water fountains
Safety instructions and danger signs must be observed
Wear all personal protective equipment provided and replace damaged
items immediately
Do not enter processing areas other than your own place of work
Do not temper with faulty equipment or electrical fitting; report such faults
to supervisors
Get immediate medical attention for injuries, however minor they appear
Report all accidents to super visors
Do not lose temper, or indulge in ‘horse-play’
Know the location of fire alarms, extinguishers and escape routes
When in doubt; ask supervisors
246
several impervious and resistant materials such as natural or synthetic rubber, PVC-
coated fabrics or leather. These are useful for workers exposed to quite a wide range of
chemicals, oils and hydrocarbons.
Harmful substances often enter the body through the skin of the hands,
particularly through cuts and abrasion. Several types of gloves, gauntlets and mittens in
a variety of materials are available to protect the hands from corrosive chemicals and
other harmful substances, as well as abrasion, cuts, extremes of temperature and high
voltages.
Gloves must also be used when the worker’s hands are clean apart from regular
248
cleaning of any fabric and leather gloves. It must be ensured that the gloves have the
right size and length for the particular job and must be replaced if cuts, tears, holes or
defects are present.
The main risks of head injury in the workplaces include when there is a
possibility that a worker may be struck on his head by a falling or flying object or when
a worker may strike his head against a protruded object or may be struck by a swinging
object. The safety helmet selected should satisfy certain performance requirements
including shock absorption, resistance to penetration; and be adjustable to fit and make
comfortable to the user. Certainly, the safety helmet can never be effective unless it is
properly worn for the purpose.
Other safety head wears include welders’ helmets to which visors or face shields
are attached, acoustic helmets for those exposed to high noise levels, bump caps and
scalp protectors for protection against bruising in confined places, shot-blasting helmets
and air-stream helmets. The use of safety helmet, like other personal protective
equipment, is always regarded as the last resort for accident prevention. In principle,
reducing or controlling the risks of injury at source should be considered first.
249
Safety shoes are required where the potential for serious injury to the foot may
result from an employee's daily job duties. Foot injuries may occur in areas where there
are rolling or falling objects, objects piercing the sole, or where feet are exposed to
electrical hazards.
Most safety foot wears are designed to protect the toes from impact or crushing
from falling objects. Other hazards against which safety footwear is available include
penetration trough the mid-sole and upper, oil and chemical penetration, slipping, heat
and metal turnings. Antistatic rubber footwear has sufficiently high electrical resistance
to protect against electrocution hazards while allowing electrostatic charges to dissipate
harmlessly.
The majority of impact injuries result from flying or falling objects, or sparks
striking the eye. Most of these objects are smaller than a pin head and can cause serious
injury such as punctures, abrasions, and contusions. While working in a hazardous area
where the worker is exposed to flying objects, fragments, and particles, primary
protective devices such as safety spectacles with side shields or goggles must be worn.
Secondary protective devices such as face shields are required in conjunction with
primary protective devices during severe exposure to impact hazards.
The main forms of protection are safety spectacles, safety goggles and shields.
Safety spectacles have toughened glass or plastic lenses in various tints, with plastic or
metal frames and may have ventilated side shields for protection against low-energy
droplets and particles. Safety goggles which enclose the eyes completely, with or
250
without ventilation, and which are kept position by an elastic headband, provide more
complete protection than spectacles but are less comfortable to wear. Conditions where
goggles should be considered include work in dusty atmospheres, work in injurious
chemicals (in fine sprays or mists form), work with toxic and irritating gases; and work
where impact from large particles are possible.
Respiratory Protective Equipment (RPEs) are of two main types; respirators and
breathing apparatus. Respirators depend on the oxygen in the air surrounding the
wearer for respiration and provide means for removing the hazardous contaminants
from the air before it is breathed. They may not be used in oxygen-deficient
atmospheres or in ones that present an immediate danger to life.
1. Self-contained closed circuit which the exhaled air is passed through a chemical
which replaces its carbon dioxide with oxygen.
air cylinder, routinely used in industry for tasks such as cleaning and paint
spraying.
4. Fresh air hose in which air suitable for respiration is drawn from an adjacent
uncontaminated area through a larger-diameter hose by the breathing of the
wearer, with or without a blower.
In straight pipe, only compressive stresses exits, due to which it will bend to
252
form an arc of a circle to accommodate the expansion. Since this is not desirable, by
providing expansion loop in the pipeline, the change in length due to thermal expansion
is contained within the loop. In addition to this, at high temperature, creep phenomena
set in which slowly relaxes the stresses developed.
The regulations require that the MSDS be updated to reflect significant new
information in these areas. It should be referred to the supplier's MSDS for dimethyl
253
carbonate for more detailed information regarding safety, health, and/or toxicity data.
The supplier's MSDS can be contacted for specific recommendations on handling
dimethyl carbonate under regular operations and in emergencies. Supervisory and
operating staff must have access to the MSDS and receive training on hazardous
chemicals in their work area.
Dimethyl carbonate is partitioned into air and water with negligible amounts in
soil, sediment and biota. In the aqueous environment it is considered to be readily
biodegradable. Its low partition coefficient suggests that dimethyl carbonate has low
bioaccumulation potential. The following information indicates that dimethyl carbonate
is not environmentally hazardous.
to be studied further.
PBT/vPvB conclusion Dimethyl carbonate is neither PBT nor vPvB based
on biodegradation and bioaccumulation results and
no hazard to aquatic species.
Care must be taken in the handling and disposal of laboratory-sized and larger
samples of ethylene. Laboratory and sample storage facilities should be appropriate for
the associated risks. Test and handling procedures should be clear and the laboratory
and operating personnel well trained. Methods for in-plant disposal of samples include
venting to a control device such as a flare or controlled incineration at a remote site
with remote control of the ignition source to help protect personnel and property.
Where,
E is the equivalent exposure for the working shift
C is the concentration during any period of time T where the concentration
remains constant
T is the duration in hours of the exposure at the concentration C
build-up of electrostatic charges. This can be done by using only non-sparking tools and
ground or bond containers and receiving equipment.
There are two basic types of vessels that can be used to store dimethyl
carbonate namely, pressurized or cylindrical (bullet tanks) and flat bottom storage
tanks. The most common way to store liquid dimethyl carbonate is in flat bottom
insulated tanks at atmospheric pressure. For smaller capacities, liquid dimethyl
carbonate can be stored in pressurized vessels (cylinders or spheres). They are
generally constructed to ASME Boiler & Pressure Vessel Code Section VIII.
Site layout for a plant consists of the process units involved which is located in
the main plant and other auxiliary buildings. The layout, which refers to each
department, must be arranged in order to give maximum work productivity, efficiency and
minimum operational costs. The layout of plant must consider three main factors
namely, comfort, ability and safety; economical flow of material and the area utilized to
build the plant.
The auxiliary building and services required on the site in additional to the main
process units are as follows:
Office (administration)
Utilities such as boiler, power generation, cooling water
Storage for raw material and product
Storage for maintenance and operating supply
Waste treatment plant
Laboratory
258
Maintenance workshop
Canteen and prayer room
According to Figure 12.1 above, the utilities building is located near the process
section to give the most economical flow of supplies such as steam to the process units
and is important in reducing heat losses by steam. In the plant layout above, it also
shows the location of offices and other facilities in the plant. This plant layout is
developed to ensure the safety for the workers and all the assets in the plant.
The hazard and operability studies or HAZOP for short is a formal procedure
used to identify hazards present in a chemical process plant. The usage of HAZOP
helps in the identification of all the possible errors and problems which could arise
from the operations and processes. It is considered systematic, effective,
comprehensive, and flexible and is well accepted by the chemical and petrochemical
industries. Typically, HAZOP is intended to be a formal safety audit and review of an
operating plant or a modification of the plant to ensure that the probabilities of major
accidents could be eliminated and the consequences could be reduced to acceptable
levels as compared to before the modification. Although this maybe the case, HAZOP
could be applied during the design stage as to enable any modifications to be
incorporated into the final design before construction of the plant.
around the plants compound. For the case of HAZOP, it is done through the
experiences of engineers and their understanding of the processes, to determine
possible hazards that could arise due to deviation from suitable conditions of the
processes. The conclusion of the studies will suggest suitable routes to eliminate the
possible errors that could occur through the addition of proper instruments or safety
procedures.
Advantages
Disadvantages
There are a set of procedures and specific terms that are to be used and obeyed
when conducting the HAZOP studies. The specific terms mentioned are guide words,
which are used to describe possible deviations of certain parameters involved from the
ideal process condition, and thereby shows a more standardized way of mentioning
parameter changes and acknowledge the consequences of the deviations accordingly.
Procedures:
Reaction -
Sample -
In this dimethyl carbonate production plant, HAZOP studies are done on several
unit operations of the plant design which includes two units of reactors, one unit of flash
column, four units of distillation columns, heat exchangers; heaters, three units of
pumps, three units of pressure-reducing valves, a compressor and a gas expander. The
264
HAZOP studies will only be done once for similar units and are displayed in the
following section.
265
12.8.1 Reactor
FUNCTION OF UNIT To house the production of propylene carbonate from the reaction between carbon
dioxide and propylene oxide
FUNCTION OF STUDY Vessel – To provide area for the reaction occur
NODES
Heating jacket – To provide heating to maintain temperature at desire conditions
preceding
equipment
Temperature High 1. Feed or supply 1. Runaway reaction 1. Install high
temperature is too can cause pressure temperature alarm
high build up, might 2. Install temperature
result in explosion controller
Low 1. Feed temperature is 1. Cause low yield of 1. Install low
too low production temperature alarm
2. Install automated
temperature controller
3. Install heating jacket
using steam as a
medium
Pressure High 1. Outlet pipe blocked 1. Cause reverse flow 1. Regular cleaning of
2. Temperature in vessel 2. Runaway reaction reactor piping system
too high 2. Install relief valve
3. Install high pressure
alarm
Low 1. Reactor leakage 1. Low reaction yield 1. Install low pressure
obtain alarm
268
FUNCTION OF UNIT To house the transesterification reaction of methanol and propylene carbonate to
produce DMC
FUNCTION OF STUDY Vessel – To provide area for the reaction occur
NODES
Heating jacket – To provide heating to maintain temperature at desire conditions
5. Install automated
pump
Flow High 1. Control valve failure 1. Runaway reaction 1. Install high level
2. Increase pumping 2. Overload reaction control alarm
capacity in vessel 2. Install automated
3. Controller fails and 3. Pressure build up pump
valve fully open might occur 3. Install automated
valve
Low 1. Control valve failure 1. Lower the 1. Install low level
2. Controller fails and production rate control alarm
valve fully closed 2. Install automated
3. Pump failure valve
4. Pipe leakage 3. Maintenance pump
4. Regular checking and
maintenance piping
system
Reverse 1. Pressure in reactor is 1. Damage the 1. Install a one way
higher than inlet flow pipelines and flow valve
preceding
equipment
272
reactor condition
Reaction Low 1. Low temperature 1. Low productivity 1. Install low
2. Low pressure rate temperature alarm
3. Low feed 2. *same as above 2. Install low pressure
3. *same as above alarm
3. Install low flow
alarm
Study Node Heating Jacket
PARAMETERS ACTION REQUIRED
GUIDE POSSIBLE CAUSES POSSIBLE
WORDS CONSEQUENCES
Flow No 1. Unavailability of 1. Low temperature 1. Look for several
heating steam at reactor vessel supplier of heating
2. Heating steam pipe resulting in lower steam
clogged production yields 2. Regular checking and
maintenance vessel
and pipe
Flow High 1. Valve failure 1. Overheating of 1. Install high level
2. Controller fails and reactor vessel, control alarm
valve fully open result in runaway 2. Install automated
reaction valve
274
FUNCTION OF Reboiler – A type of heat exchanger typical used to provide heat to the bottom of
STUDY NODES
distillation column
FUNCTION OF Reboiler – A type of heat exchanger typical used to provide heat to the bottom of
STUDY NODES
distillation column
Flow Low 1. Blockage in pipe 1. Column dry out 1. Install low level
2. Control valve shut 2. Changes in product alarm
down quality 2. Install automated
3. Valves fail pump
4. Tube leakage and 3. Install automated
blocking valve
5. Pump failure 4. Regular
checking
maintenance
procedure and
schedule
5. Emergency plant
shut down
High 1. Control valve is fully 1. Flooding in the 1. Install high level
opened
column control alarm
2. Increase pumping
2. Changes in product 2. Check
capacity
quality maintenance
3. Control valves failure
3. Temperature procedure and
decrease schedule
4. Rise in bottom 3. Install double
283
control valve
4. Regular
checking and
maintenance
pumping system
Reverse 1. Too high pressure 1. No operation 1. Install check
inside the column 2. Pressure build up valve
2. Pump failure inside the column or
at the reboiler
Temperature High 1. High temperature of 1. Product quality 1. Install high
the feed stream becomes temperature
2. Steam flow inlet into significantly low alarm at the
reboiler increase 2. Low purity of column
3. Faulty separation obtain 2. Control the
instrumentation and 3. Can cause flooding steam flow into
control inside the column reboiler
4. Heater control failure 4. Cause pressure 3. Control the
5. Coolant at condenser changes inside the temperature of
fail to operate well column feed stream
4. Check the
284
instrumentation
conditions
Low 1. Low temperature of 1. Product quality 1. Install low
the feed stream becomes temperature
2. Loss of heating significantly low alarm
(steam leaking) 2. Low purity of 2. Install automated
3. Reducing pressure separation obtain temperature
4. Faulty 3. Can cause flooding controller
instrumentation and inside the column 3. Control the
control 4. Cause pressure steam flow into
5. Depressurization of changes inside the reboiler
liquefied gas column
Reflux More 1. Control valve fail to 1. Increase reflux ratio 1. Install level
operate well 2. Increase the duty at controller inside
2. Pumping failure the condenser and reflux drum
reboiler 2. Install alarm
level for rising
of drum level
Less 4. Control valve fail to 1. Reduce reflux ratio 1. Install level
operates well 2. Reduce the purity or controller inside
285
bottom stream
Pressure Low 1. Generation of vacuum 1. Low separation 1. Install low
conditions obtain pressure alarm
2. Undetected leakage 2. Flooding inside the 2. Regular
3. Low gas release column maintenance the
4. Changes in piping system of
viscosity/density of column
compound
High 1. Steam heating enter at 1. Can damage the 1. Install high
high pressure column pressure alarm
2. Flooding occur
12.8.3 Pump
UNIT
PARAMETERS ACTION REQUIRED
GUIDE POSSIBLE CAUSES POSSIBLE
WORDS CONSEQUENCES
Flow No 1. Pipe or pump 1. Pipe clog 1. Regular maintenance
rupture 2. No pumping fluid and checking the
2. Large leaking in occur piping and pumping
pipelines system
3. Blockage in pipe 2. Install flow detector
Low 1. Valve not fully 1. Compound 1. Install automated
open released valve
2. Pump failure 2. Reduce production 2. Install flow controller
rate 3. Regular maintenance
3. Cavitation occur the pump
inside pump
4. Defective pump
12.8.4 Valve
pipelines
Flow Less 1. Pipe blockage 1. Temperature of 1. Install low level alarm
2. Fouling of valve process fluid 2. Cleaning the pipelines
3. Valve not fully increase
open
More 1. Control faults 1. Increase pressure 1. Install high level alarm
2. Valve failure inside valve 2. Install automated valve
2. Valve maybe controller
damage
OPERATION
IDEAL TEMPERATURE(oC) 90 PRESSURE (atm) 1
CONDITIONS
FUNCTION OF To decrease the pressure of bottom product stream from HPC to 1 atm
UNIT
PARAMETERS ACTION REQUIRED
GUIDE POSSIBLE CAUSES POSSIBLE
WORDS CONSEQUENCES
Pressure High 1. Valve malfunction 1. Can cause damage 1. Install high pressure
2. Valve isolated to valve alarm
2. Reverse flow of 2. Schedule regular
liquid occur maintenance of valve
Low 1. Valve fail to open 1. Compound released 1. Install pressure low
2. Blockage of to atmosphere alarm
blanket gas 2. Gas dissolving in 2. Update procedure to
regulating valve liquid handle valve fail open
3. Undetected
leakage in
pipelines
Flow Less 1. Pipe blockage 1. Temperature of 1. Install low level alarm
process fluid
298
12.8.5 Compressor
12.8.8 Mixer
Fault tree analysis is an effect and cause diagram that uses standard symbols
developed in the defense industry and is used heavily in safety engineering. It is a
structured approach for analyzing the root causes of a failure in the equipment which
are not yet fully understood. In fault tree analysis, overall undesired system failures
could be broken down further to component failure modes and operator actions for
better comprehension of the failure. Although there are other methods to assess the
failure of systems, experts feel that fault tree analysis is better suited to understand
layers and relationships of causes of equipment failures.
Where,
312
The fault tree development consists of multiple levels of basic events and sub-
events linked together by OR and AND gates. The minimal cut set analysis is present to
rearrange the fault tree developed so that basic events that appear in different parts of the
fault tree is not double counted in the quantitative analysis. The results of the minimal
cut set analysis is a new fault tree, logically equivalent to the original, consisting of an
OR gate beneath the top event, whose inputs are the minimal cut sets. Each minimal cut
set is an AND gate containing a set of basic inputs. A software could be used to generate
the minimal cut set using the Boolean Algebra.
313
12.9.3 Analysis
The analysis will be done on several equipment utilized by the designed plant.
The equipment chosen for the analysis include the reactor, pump, flash column and
distillation column. The equipment stated here will represent their respective major
equipment categories of the plant.
314
Figure 12.3: Fault Tree Analysis for Reactors (SR-1 & SR-2)
315
Overpressure of reactor
P (D, OR) = P(1)+P(2) = 1- [(1-0.1306) x (1-0.0430)]
= 0.1679 (probability of pressure alarm failing)
P(E, OR) = P(3) + P(4) + P(5) = 1-[(1-0.1306) x (1-0.2517) x (1-0.0276)]
= 0.3674 (probability of pressure control system failing)
P(B, AND) = P(D) × P(E)×P(6) = 0.1679 × 0.3674 × 0.0218
= 0.013 (probability of overpressure)
Overheating of reactor
P(F, OR) = P(7) + P(8) = 1-[(1-0.1975) x (1-0.0430)]
= 0.2320 (probability of temperature alarm failing)
P(G, OR) = P(9) + P(10) + P(11) = 1-[(1-0.1975) x (1-0.2517) x (1-0.0276)
= 0.4161 (probability of temperature control system failing)
P(C, AND) = P(F) × P(G) = 0.2320 × 0.4161
= 0.0965 (probability of overheating)
Failure of reactor
P(A, OR) = P(B) + P(C) = 1-[(1-0.013)-(1-0.0965)]
= 0.1082
316
Figure 12.5: Fault Tree Analysis for Distillation Column (DC-100, DC-101 & HPC-100)
319
Figure 12.6: Fault Tree Analysis for Pumps (P-100, P-101 & P-102)
321
Overpressure of pump
P(C,OR) = P(1) + P(2) = 1-[(1-0.1306) x (1-0.0430)]
= 0.1679 (probability of alarm failure)
P(B,AND) = P(C) × P(3) = 0.1679 × 0.0218
= 0.0037 (probability of overpressure)
Failure of pump
P(A, OR) = P(B) + P(4) = 1-[(1-0.0037) x (1-0.4001)]
= 0.4023
322
Figure 12.7: Fault Tree Analysis for Valves (VLV-100, VLV-101 & VLV-102)
323
Overpressure of valve
P (D, OR) = P(1)+P(2) = 1- [(1-0.1306) x (1-0.0430)]
= 0.1679 (probability of pressure alarm failing)
P(E, OR) = P(3) + P(4) + P(5) = 1-[(1-0.1306) x (1-0.2517) x (1-0.0276)]
= 0.3674 (probability of pressure control system failing)
P(B, AND) = P(D) × P(E)×P(6) = 0.1679 × 0.3674 × 0.0218
= 0.013 (probability of overpressure)
Overflow in valve
P(F, OR) = P(7) + P(8) = 1-[(1-0.6737) x (1-0.0430)]
= 0.6877 (probability of flow alarm failing)
P(G, OR) = P(9) + P(10) + P(11) = 1-[(1-0.6737) x (1-0.2517) x (1-0.0276)
= 0.7626 (probability of flow control system failing)
P(C, AND) = P(F) × P(G) = 0.6877 × 0.7626
= 0.5244 (probability of overflow)
Failure of valve
P(A, OR) = P(B) + P(C) = 1-[(1-0.013)-(1-0.5244)]
= 0.5306
324
Figure 12.8: Fault Tree Analysis for Heaters (H-100 & H-101)
325
Overpressure of heater
P (D, OR) = P(1)+P(2) = 1- [(1-0.1306) x (1-0.0430)]
= 0.1679 (probability of pressure alarm failing)
P(E, OR) = P(3) + P(4) + P(5) = 1-[(1-0.1306) x (1-0.2517) x (1-0.0276)]
= 0.3674 (probability of pressure control system failing)
P(B, AND) = P(D) × P(E)×P(6) = 0.1679 × 0.3674 × 0.0218
= 0.013 (probability of overpressure)
Failure of heater
P(A, OR) = P(B) + P(C) = 1-[(1-0.013)-(1-0.0965)]
= 0.1082
12.9.10 Summary
The probability of failure for each equipment studied are shown in Table 11.4
above. The same probability of failure of 0.1082 was found for the reactors, distillation
columns, flash column and heaters. This results in the possible 0.1145 faults per year
and the minimum time before a fault (MTBF) happens will be about 9 years. In fact,
the pump is of greater importance as the parts of the motor could easily be damaged, be
it the electric motor or the pump section. Therefore, it has a higher probability to face
failure during the operation of the plant, resulting in about 0.5147 faults per year and
minimum time before the fault happens is about 2 years. This goes the same for
pressure-reducing valves which face even more significant effect from possible damage
due to their 0.7563 faults per year rate which is the highest among the rest. Besides, it
is expected for the valves to be replaced after about 1.5 years before they are
permanently disabled.
12.10.1 Introduction
A plant start-up involves a point in the project in which process fluids and
conditions are established with an intent of making products. It is also defined as the
327
On the other hand, a plant shutdown can be defined as a scheduled down period
for a plant for scheduled maintenance for an extended period of time. Shutdowns
provide unique opportunities to a maintenance department not normally available
during standard operation or even during short shutdown periods. It is essential to
conduct a plant maintenance shutdown to keep the facility running smoothly despite it
can be timely and causes loss in production but the benefits of scheduled maintenance
of the machinery can help to prevent future failures and decreases downtime.
The startup and shutdown of a plant must be handled safely and easily, yet
flexible enough to be carried out in several ways. The operating limits of the plant must
not be exceeded and dangerous mixtures must not be formed. It is occasionally
necessary to introduce additional equipment, sampling point, instrumentation and lines
and identify their uses on the engineering line diagram. There are several important
aspects that needs to be taken into consideration during the startup and shutdown of the
plant.
1) Before the man-ways covers are installed on the towers or vessels, a final
inspection should be made of the interiors of each tower and vessels for
328
1) The ‘Turn-around Work list’ is to be prepared to include all items for repair,
cleaning, inspection and modification.
2) The detailed plan of the shutdown and turnaround for the day to day and
probably hour by hour schedule of the sequence of the events are to be prepared.
3) Before shutting down, the following should be checked:
The firefighting equipment are to be correctly located.
The personal protective equipment are to be available for immediate use.
All items that are required for the shutdown of the unit operations should be
made available. These items include blinds, hoses for steaming out circuits and
equipment, hoses for draining circuit equipment of liquid, connections for connecting
those hoses.
1. Losses of utility supply such as cooling water, electricity, steam and others.
2. Mechanical failure of equipment prevents normal operation or result in a
serious fire or leak.
3. An emergency response plan should be prepared for the safety of the
employees and public. The two steps should be taken during the event of an
330
CHAPTER 14
CONCLUSION
Due to the need for methanol resources as the more essential raw material and
land availability purposes, the planned location of the plant will be at Gebeng, Pahang
because this industrial land focuses mainly on industry that is based on petrochemical
332
and chemical industry which can serve as a great marketing prospect. Although raw
material availability is the primary concern, other factors were also taken into account
such as land prices, utilities provision, marketing potential and others. Since the Gebeng
area is close the Gebeng bypass which is strategically located near to the Kuantan Port
that links Kuala Lumpur and Kuantan directly via East Coast Highway, it would not be a
problem in terms of transportation access. Besides, Gebeng also possesses some of the
cheapest land prices in the nation and the abundance of raw materials is present as well.
The innovation potential in this process and plant design is the application of
CeCu catalyst which could potentially replace most commercially available catalysts in
the industry that is used to produce dimethyl carbonate. The catalyst used in most
previous research and process is the ion-exchange resin. Although ion-exchange resin
is commercially available, it can only be used in a few cycles and requires continuous
maintenance gradually. Therefore, CeCu catalyst is a promising development in this
aspect despite it is still currently new within lab-scale production. However, it still
shows great potential as it could provide about 72% conversion of methanol and
propylene carbonate as compared to the original rate at 16%. Another innovation
incorporated in this design is the application of pressure-swing distillation in dealing
with the separation of azeotropic DMC-methanol mixture in contrary with extractive
distillation. This is because the former is more environmental-friendly and avoid the
use of an additional separating agents with only changes being made to the operating
pressure.
The operation of this plant will run for 24 hours a day, 7 days a week and about
340 days a year (8200 hours), allowing about 20 days or more for plant shut down for
maintenance and equipment check. The resulting flow for each component is viewed on
an hour basis. The consumption of carbon dioxide and propylene oxide is about 1 ton
and 1.2 tons per hour respectively (feeds into reactor), dimethyl carbonate production
about 2 tons per hour and propylene glycol at about 1.5 tons per hour. Due to the use of
the CeCu catalyst, the conditions can be lowered to about 150°C, as compared to other
catalysts, which may result in greater reaction temperature of about 500-600°C. The
333
reaction pressure at 1 atm is sufficient enough to provide a pressurized condition for the
transesterification of propylene carbonate and methanol.
Manual calculations were conducted for both mass and energy balances with
basis from chemical engineering principles. Assumptions were also made while
required data was obtained from literature study and research, thereby rendering the
calculations to be rather accurate. The HYSYS simulation program was also used to
simulate the planned process and this provided a basis of comparison for the manual
calculations and the assumptions made for the calculations. As a result, the difference
between the manual and simulated results were all below 15%, with the highest
difference at about 14%. This low percentage difference proved that the calculations
were quite close to that of actual conditions and therefore, the design could proceed
without making any major alterations.
situations involving the failure of control systems. These control systems could be
made fully automated to alert personnel to the possible risk of any system failures. In
addition, the fault tree analysis was also conducted on major equipment of the plant to
foresee the possible risk of facing equipment failure and with that, operators can be
notified beforehand regarding to equipment which are more susceptible to failure.
The economic analysis for the plant involved the estimation of the payback
period as well as the rate of return. With the MARR set at 20%, an internal rate of
return (IRR) or Discounted Cash Flow Rate of Return (DCFRR) of 65.67% is quite
favourable as it yields high returns for the plant. With EMIP at 2.15 years, the
investment in the plant will be secure about .2.15 years, when the investment capital
mostly be gathered after that period of time. The breakeven point at 41 thousand tons of
dimethyl carbonate production per year justified the plant to operate at a capacity of
15,000 metric tons per year. Lastly, the short payback period would also peak investors
interest in the plant, as within 6 years of the plant design being conceive, the plant
could regain all of its capital spending and begin to profit afterwards.