Construction of Arao Obunga Dispensary

Download as pdf or txt
Download as pdf or txt
You are on page 1of 114

COUNTY GOVERNMENT OF KISUMU

DEPARTMENT OF ROADS, TRANSPORT AND PUBLIC WORKS


Office of the Chief Officer - Roads, Transport and Public Works

PROPOSED CONSTRUCTION OF ARAO OBUNGA DISPENSARY

BILLS OF QUANTITIES

FOR ARAO OBUNGA

TENDER NO:CGK/H&S/19-20/053

CLIENT
DEPARTMENT OF HEALTH
COUNTY GOVERNMENT OF KISUMU
P.O BOX 2738-40100
KISUMU

PROJECT MANAGER
THE DIRECTOR PUBLIC WORKS
DEPARTMENT OF ROADS, TRANSPORT AND PUBLIC WORKS
P.O. BOX 2738 - 40100
KISUMU

November, 2019
STANDARD TENDER DOCUMENT

FOR

PROCUREMENT OF WORKS

(BUILDING AND ASSOCIATED


CIVIL ENGINEERING WORKS)
TABLE OF CONTENTS

PAGE

INTRODUCTION …………………………………………1

SECTION I: INVITATION TO TENDER ……………………………… 2

SECTION II: INSTRUCTIONS TO TENDERERS …………………….. 3 - 14

SECTION III: CONDITIONS OF CONTRACT …………..…………….. 15- 36

SECTION IV: APPENDIX TO CONDITIONS OF


CONTRACT ……………………………………………… 37 - 39

SECTION V: SPECIFICATIONS ……………………………………… 40 - 41

SECTION VI: DRAWINGS ……………………………………………… 42

SECTION VII: BILLS OF QUANTITIES ………………………………. 43 - 46

SECTION VIII: STANDARD FORMS …………………………………… 47 - 66


INTRODUCTION

1.1 This standard tender document for procurement of works has been prepared for use by
procuring entities in Kenya in the procurement of works (i.e. Buildings and associated
Civil Engineering Works).

1.2 The following guidelines should be observed when using the document:-
(a) Specific details should be furnished in the Invitation to tender and in the special
conditions of contract (where applicable). The tender document issued to
tenderers should not have blank spaces or options.

(b) The instructions to tenderers and the General Conditions of Contract should remain
unchanged. Any necessary amendments to these parts should be made through
Appendix to instructions to tenderers and special conditions of contract
respectively.

1.3
(b) Information contained in the invitation to tender shall conform to the data and
information in the tender documents to enable prospective tenderers to decide
whether or not to participate in the tender and shall indicate any important tender
requirements

(c) The invitation to tender shall be as an advertisement in accordance with the


regulations or a letter of invitation addressed to tenderers who have been
prequalified following a request for prequalification.

1.4 The cover of the document shall be modified to include:-

I. Tender number.
II. Tender name.
III. Name of procuring entity.
IV. Delete name and address of PPOA.
SECTION I
INVITATION FOR TENDERS

Tender reference No. CGK/H&S/19-20/053


Tender Name (PROPOSED CONSTRUCTION OF ARAO OBUNGA DISPENSARY)

1.1 The (COUNTY GOVERNMENT OF KISUMU) invites sealed tenders for the
construction of (PROPOSED CONSTRUCTION OF ARAO OBUNGA
DISPENSARY )

1.2 Interested eligible candidates may obtain further information and inspect tender
documents (and additional copies) at, (DEPARTMENT OF HEALTH PROSPERITY
HOUSE) during normal working hours.

QUALIFICATION FOR TENDERING

1.1 MANDATORY REQUIREMENTS

1.2 Tenderers MUST include the following information and documents with their Tenders:

a) Certified copy of Certificate of Incorporation,


b) Certified copy of VALID Registration Certificate with the National Construction
Authourity in the classes specified in the tender notice.
c) VAT and PIN registration,
d) A copy of VALID Tax Compliance Certificate from Kenya Revenue Authority (KRA),
e) Bid bond – 2% of the tender sum for general tenders,
f) Certified copy of RECENT CR12 FORM from registrar of companies.
g) Certified copy of Single Business Permit preferably from Kisumu County.
h) Bidders shall SEQUENTIALLY SERIALIZE ALL PAGES for each tender document
submitted failure to which the bidder shall be disqualified.
i) Certified copy of relevant (Small works & Engineering) Certificate of registration for
access to government procurement opportunities (AGPO) from the ministry of National
Treasury for tenders in the special categories.
j) Bid declaration for special category duly signed and stamped
Certification must be by a commissioner for oaths.

Other requirements are as specified in the tender notice and this tender document.
1.3 OTHER REQUIREMENTS

As specified in the tender documents covering the following

I. Eligibility.
II. Similar previous experience.
III. Current workload.
IV. Plant and Equipment holding.
V. Professional and technical personnel.
VI. Audited financial statements for the last three years (2015 – 2017) provided. Companies registered
within the last one year should submit certified bank statements for at least twelve months or the
duration of registration
VII. Litigation history or Current Sworn Affidavit.

Any form of canvassing will lead to automatic disqualification.


The complete set of tender documents may be downloaded from the County’s website ie
www.kisumu.go.ke . Completed Tender Documents are to be enclosed in plain sealed envelopes
marked with Tender name and reference number and deposited in the Tender Box located at the Main
Reception, County Government of Kisumu Headquarters, Prosperity House – 8th Floor or to be
addressed to The chief officer department of Roads ,transport and public works, County Government
of Kisumu, P.O Box 2738-40100 Kisumu so as to be received on or before
……………………………….., at ………………..

a) Prices quoted should be net inclusive of all taxes, must be in Kenya shillings and shall
remain valid for 90 days from the closing date of tender.

b) Tenders will be opened immediately thereafter in the presence of the candidates or their
representatives who choose to attend at Prosperity House- 8th floor Boardoom.
c) Late bids will be not be accepted.
________________________________

d) . Tenders must be accompanied by an original tender Security of 2% of the tender sum in


form of a guarantee acceptable under the Public Procurement and Asset Disposal Act, 2015
and Public Procurement and Disposal Regulations 2006 payable to the County Government
of KISUMU.

e) Interested eligible candidates may obtain further information and inspect Tender
Documents and the Design Drawings at County Government of Kisumu Headquarters, at
the Trade Department Procurement Office during normal working hours.
For:
Chief Officer
DEPARTMENT OF HEALTH
COUNTY GOVERNMENT OF KISUMU
P.O BOX 2738-40100
KISUMU
SECTION II

INSTRUCTIONS TO TENDERERS

TABLE OF CONTENTS PAGE

CLAUSE PAGE

1. General …………………………………………………. 4

2. Tender Documents ………………………………… 6-7

3. Preparation of Tenders ………………………………… 7-8

4. Submission of Tenders ………………………………… 10 - 11

5. Tender Opening and Evaluation ……………………… 11 - 13

6. Award of Contract …………………………………………13 - 14


INSTRUCTIONS TO TENDERERS.

1. General/Eligibility/Qualifications/Joint venture/Cost of tendering

1.1 The Employer as defined in the Appendix to Conditions of Contract invites tenders for
Works Contract as described in the tender documents. The successful tenderer will be
expected to complete the Works by the Intended Completion Date specified in the
tender documents.

1.2 All tenderers shall provide the Qualification Information, a statement that the tenderer
(including all members of a joint venture and subcontractors) is not associated, or has
not been associated in the past, directly or indirectly, with the Consultant or any other
entity that has prepared the design, specifications, and other documents for the project
or being proposed as Project Manager for the Contract. A firm that has been engaged
by the Employer to provide consulting services for the preparation or supervision of the
Works, and any of its affiliates, shall not be eligible to tender.

1.3 All tenderers shall provide in the Form of Tender and Qualification Information, a
preliminary description of the proposed work method and schedule, including drawings
and charts, as necessary.

1.4 In the event that pre-qualification of potential tenderers has been undertaken, only
tenders from pre-qualified tenderers will be considered for award of Contract. These
qualified tenderers should submit with their tenders any information updating their
original pre-qualification applications or, alternatively, confirm in their tenders that the
originally submitted pre-qualification information remains essentially correct as of the
date of tender submission.

1.5 Where no pre-qualification of potential tenderers has been done, all tenderers shall
include the following information and documents with their tenders , unless otherwise
stated:

(a) copies of original documents defining the constitution or legal status, place of
registration, and principal place of business; written power of attorney of the
signatory of the tender to commit the tenderer:

(b) total monetary value of construction work performed for each of the last five
years:

(c) experience in works of a similar nature and size for each of the last five years,
and details of work under way or contractually committed; and names and
addresses of clients who may be contacted for further information on these
contracts;

(d) major items of construction equipment proposed to carry out the Contract and
an undertaking that they will be available for the Contract.

(e) qualifications and experience of key site management and technical personnel
proposed for the Contract and an undertaking that they shall be available for the
Contract.
(f) reports on the financial standing of the tenderer, such as profit and loss
statements and auditor’s reports for the past five years;

(g) evidence of adequacy of working capital for this Contract (access to line(s) of
credit and availability of other financial resources);

(h) authority to seek references from the tenderer’s bankers;

(i) information regarding any litigation, current or during the last five years, in
which the tenderer is involved, the parties concerned and disputed amount; and

(j) proposals for subcontracting components of the Works amounting to more than
10 percent of the Contract Price.

1.6 Tenders submitted by a joint venture of two or more firms as partners shall comply with
the following requirements, unless otherwise stated:

(a) the tender shall include all the information listed in clause 1.5
above for each joint venture partner;

(b) the tender shall be signed so as to be legally binding on all


partners;

(c) all partners shall be jointly and severally liable for the execution
of the Contract in accordance with the Contract terms;

(d) one of the partners will be nominated as being in charge,


authorised to incur liabilities, and receive instructions for and on behalf of all
partners of the joint venture; and

(e) the execution of the entire Contract, including payment, shall be


done exclusively with the partner in charge.

1.7 To qualify for award of the Contract, tenderers shall meet the following minimum
qualifying criteria;

(a) annual volume of construction work of at least 2.5 times the estimated annual
cashflow for the Contract;

(b) experience as main contractor in the construction of at least

(c) two works of a nature and complexity equivalent to the Works


over the last 10 years (to comply with this requirement, works cited should be at
least 70 percent complete);

(d) proposals for the timely acquisition (own, lease, hire, etc.) of the essential
equipment listed as required for the Works;

(e) a Contract manager with at least five years’ experience in works of an equivalent
nature and volume, including no less than three years as Manager; and
(f) liquid assets and/or credit facilities, net of other contractual commitments and
exclusive of any advance payments which may be made under the Contract, of no
less than 4 months of the estimated payment flow under this Contract.

1.8 The figures for each of the partners of a joint venture shall be added together to
determine the tenderer’s compliance with the minimum qualifying criteria of clause 1.7
(a) and (e); however, for a joint venture to qualify, each of its partners must meet at
least 25 percent of minimum criteria 1.7 (a), (b) and (e) for an individual tenderer, and
the partner in charge at least 40 percent of those minimum criteria. Failure to comply
with this requirement will result in rejection of the joint venture’s tender.
Subcontractors’ experience and resources will not be taken into account in determining
the tenderer’s compliance with the qualifying criteria, unless otherwise stated.

1.9 Each tenderer shall submit only one tender, either individually or as a partner in a joint
venture. A tenderer who submits or participates in more than one tender (other than as
a subcontractor or in cases of alternatives that have been permitted or requested) will
cause all the proposals with the tenderer’s participation to be disqualified.

1.10 The tenderer shall bear all costs associated with the preparation and submission of his
tender, and the Employer will in no case be responsible or liable for those costs.

1.11 The tenderer, at the tenderer’s own responsibility and risk, is encouraged to visit and
examine the Site of the Works and its surroundings, and obtain all information that may
be necessary for preparing the tender and entering into a contract for construction of the
Works. The costs of visiting the Site shall be at the tenderer’s own expense.

1.12 The procuring entity’s employees, committee members, board members and their
relative (spouse and children) are not eligible to participate in the tender.

1.13 The price to be changed for the tender document shall not exceed Kshs.5,000/=

1.14 The procuring entity shall allow the tenderer to review the tender document free of
charge before purchase.

2. Tender Documents

2.1 The complete set of tender documents comprises the documents listed below and any
addenda issued in accordance with Clause 2.4.

(a) These Instructions to Tenderers


(b) Form of Tender and Qualification Information
(c) Conditions of Contract
(d) Appendix to Conditions of Contract
(e) Specifications
(f) Drawings
(g) Bills of Quantities
(h) Forms of Securities

2.2 The tenderer shall examine all Instructions, Forms to be filled and Specifications in the
tender documents. Failure to furnish all information required by the tender documents,
or submission of a tender not substantially responsive to the tendering documents in
every respect will be at the tenderer’s risk and may result in rejection of his tender.
2.3 A prospective tenderer making an inquiry relating to the tender documents may notify
the Employer in writing or by cable, telex or facsimile at the address indicated in the
letter of invitation to tender. The Employer will only respond to requests for
clarification received earlier than seven days prior to the deadline for submission of
tenders. Copies of the Employer’s response will be forwarded to all persons issued
with tendering documents, including a description of the inquiry, but without
identifying its source.

2.4 Before the deadline for submission of tenders, the Employer may modify the tendering
documents by issuing addenda. Any addendum thus issued shall be part of the
tendering documents and shall be communicated in writing or by cable, telex or
facsimile to all tenderers. Prospective tenderers shall acknowledge receipt of each
addendum in writing to the Employer.
7
2.5 To give prospective tenderers reasonable time in which to take an addendum into
account in preparing their tenders, the Employer shall extend, as necessary, the deadline
for submission of tenders, in accordance with Clause 4.2 here below.
3. Preparation of Tenders

3.1 All documents relating to the tender and any correspondence shall be in English
language.

3.2 The tender submitted by the tenderer shall comprise the following:

(a) These Instructions to Tenderers, Form of Tender, Conditions of Contract,


Appendix to Conditions of Contract and Specifications;

(b) Tender Security;

(c) Priced Bill of Quantities ;

(d) Qualification Information Form and Documents;

(e) Alternative offers where invited; and

(f) Any other materials required to be completed and submitted by the tenderers.

3.3 The tenderer shall fill in rates and prices for all items of the Works described in the
Bill of Quantities. Items for which no rate or price is entered by the tenderer will not be
paid for when executed and shall be deemed covered by the other rates and prices in the
Bill of Quantities. All duties, taxes, and other levies payable by the Contractor under
the Contract, or for any other cause relevant to the Contract, as of 30 days prior to the
deadline for submission of tenders, shall be included in the tender price submitted by
the tenderer.

3.4 The rates and prices quoted by the tenderer shall only be subject to adjustment during
the performance of the Contract if provided for in the Appendix to Conditions of
Contract and provisions made in the Conditions of Contract.

3.5 The unit rates and prices shall be in Kenya Shillings.

3.6 Tenders shall remain valid for a period of sixty (60) days from the date of submission.
However in exceptional circumstances, the Employer may request that the tenderers
extend the period of validity for a specified additional period. The request and the
tenderers’ responses shall be made in writing. A tenderer may refuse the request
without forfeiting the Tender Security. A tenderer agreeing to the request will not be
required or permitted to otherwise modify the tender, but will be required to extend the
validity of Tender Security for the period of the extension, and in compliance with
Clause 3.7 - 3.11 in all respects.

3.7 The tenderer shall furnish, as part of the tender, a Tender Security in the amount and
form specified in the appendix to invitation to tenderers. This shall be in the amount
not exceeding 2 percent of the tender price

3.8 The format of the Tender Security should be in accordance with the form of Tender
Security included in Section G - Standard forms or any other form acceptable to the
Employer . Tender Security shall be valid for 30 days beyond the validity of the tender.
3.9 Any tender not accompanied by an acceptable Tender Security shall be rejected. The
Tender Security of a joint venture must define as “Tenderer” all joint venture partners
and list them in the following manner: a joint venture consisting
of”…………”,”…………”,and “…………”.

3.10 The Tender Securities of unsuccessful tenderers will be returned within 28 days of the
end of the tender validity period specified in Clause 3.6.

3.11 The Tender Security of the successful tenderer will be discharged when the tenderer has
signed the Contract Agreement and furnished the required Performance Security.

3.12 The Tender Security may be forfeited

(a) if the tenderer withdraws the tender after tender opening during the period of
tender validity;

(b) if the tenderer does not accept the correction of the tender price, pursuant to
Clause 5.7;

(c) in the case of a successful tenderer, if the tenderer fails within the specified time
limit to

(i) sign the Agreement, or

(ii) furnish the required Performance Security.

3.13 Tenderers shall submit offers that comply with the requirements of the tendering
documents, including the basic technical design as indicated in the Drawings and
Specifications. Alternatives will not be considered, unless specifically allowed in the
invitation to tender. If so allowed, tenderers wishing to offer technical alternatives to
the requirements of the tendering documents must also submit a tender that complies
with the requirements of the tendering documents, including the basic technical design
as indicated in the Drawings and Specifications. In addition to submitting the basic
tender, the tenderer shall provide all information necessary for a complete evaluation of
the alternative, including design calculations, technical specifications, breakdown of
prices, proposed construction methods and other relevant details. Only the technical
alternatives, if any, of
the lowest evaluated tender conforming to the basic technical requirements shall be
considered.

3.14 The tenderer shall prepare one original of the documents comprising the tender
documents as described in Clause 3.2 of these Instructions to Tenderers, bound with the
volume containing the Form of Tender,
and clearly marked “ORIGINAL”. In addition, the tenderer shall submit copies of the
tender, in the number specified in the invitation to tender, and clearly marked as
“COPIES”. In the event of discrepancy between them, the original shall prevail.

3.15 The original and all copies of the tender shall be typed or written in indelible ink and
shall be signed by a person or persons duly authorised to sign on behalf of the tenderer,
pursuant to Clause 1.5 (a) or 1.6 (b), as the case may be. All pages of the tender where
alterations or additions have been made shall be initialled by the person or persons
signing the tender.
3.16 Clarification of tenders shall be requested by the tenderer to be received by the
procuring entity not later than 7 days prior to the deadline for submission of tenders.

3.17 The procuring entity shall reply to any clarifications sought by the tenderer within 3
days of receiving the request to enable the tenderer to make timely submission of its
tender.

3.18 The tender security shall be in the amount of 0.5 – 2 per cent of the tender price.

4. Submission of Tenders

4.1 The tenderer shall seal the original and all copies of the tender in two inner envelopes
and one outer envelope, duly marking the inner envelopes as “ORIGINAL” and
“COPIES” as appropriate. The inner and outer envelopes shall:
10
(a) be addressed to the Employer at the address provided in the invitation to tender;

(b) bear the name and identification number of the Contract as defined in the
invitation to tender; and

(c) provide a warning not to open before the specified time and date for tender
opening.

4.2 Tenders shall be delivered to the Employer at the address specified above not later than
the time and date specified in the invitation to tender. However, the Employer may
extend the deadline for submission of tenders by issuing an amendment in accordance
with Sub-Clause 2.5 in which case all rights and obligations of the Employer and the
tenderers previously subject to the original deadline will then be subject to the new
deadline.

4.3 Any tender received after the deadline prescribed in clause 4.2 will be returned to the
tenderer un-opened.

4.4 Tenderers may modify or withdraw their tenders by giving notice in writing before the
deadline prescribed in clause 4.2. Each tenderer’s modification or withdrawal notice
shall be prepared, sealed, marked,
and delivered in accordance with clause 3.13 and 4.1, with the outer and inner
envelopes additionally marked “MODIFICATION”and “WITHDRAWAL”, as
appropriate. No tender may be modified after the deadline for submission of tenders.

4.5 Withdrawal of a tender between the deadline for submission of


tenders and the expiration of the period of tender validity specified in the invitation to
tender or as extended pursuant to Clause 3.6 may result in the forfeiture of the Tender
Security pursuant to Clause 3.11.

4.6 Tenderers may only offer discounts to, or otherwise modify the prices of their tenders
by submitting tender modifications in accordance with Clause 4.4 or be included in the
original tender submission.
5. Tender Opening and Evaluation

5.1 The tenders will be opened by the Employer, including modifications made pursuant to
Clause 4.4, in the presence of the tenderers’ representatives who choose to attend at the
time and in the place specified in the invitation to tender. Envelopes marked
“WITHDRAWAL” shall be opened and read out first. Tenderers’ and Employer’s
representatives who are present during the opening shall sign a register evidencing their
attendance.

5.2 The tenderers’ names, the tender prices, the total amount of each tender and of any
alternative tender (if alternatives have been requested or permitted), any discounts,
tender modifications and withdrawals, the presence or absence of Tender Security, and
such other details as may be considered appropriate, will be announced by the
Employer at the opening. Minutes of the tender opening, including the information
disclosed to those present will be prepared by the Employer.

5.3 Information relating to the examination, clarification, evaluation, and comparison of


tenders and recommendations for the award of Contract shall not be disclosed to
tenderers or any other persons not officially concerned with such process until the
award to the successful tenderer has been announced. Any effort by a tenderer to
influence the Employer’s officials, processing of tenders or award decisions may result
in the rejection of his tender.

5.4 To assist in the examination, evaluation, and comparison of tenders, the Employer at
his discretion, may ask any tenderer for clarification of the tender, including
breakdowns of unit rates. The request for clarification and the response shall be in
writing or by cable, telex or facsimile but no change in the price or substance of the
tender shall be sought, offered, or permitted except as required to confirm the
correction of arithmetic errors discovered in the evaluation of the tenders in accordance
with Clause 5.7.

5.5 Prior to the detailed evaluation of tenders, the Employer will determine whether each
tender (a) meets the eligibility criteria defined
in Clause 1.7;(b) has been properly signed; (c) is accompanied by the required
securities; and (d) is substantially responsive to the requirements of the tendering
documents. A substantially responsive tender is one which conforms to all the terms,
conditions and specifications of the tendering documents, without material deviation or
reservation. A material deviation or reservation is one (a) which affects in any
substantial way the scope, quality, or performance of the works; (b) which limits in any
substantial way, inconsistent with the tendering documents, the Employer’s rights or
the tenderer’s obligations under the Contract; or (c) whose rectification would affect
unfairly the competitive position of other tenderers presenting substantially responsive
tenders.

5.6 If a tender is not substantially responsive, it will be rejected, and may not subsequently
be made responsive by correction or withdrawal of the nonconforming deviation or
reservation.

5.7 Tenders determined to be substantially responsive will be checked for any arithmetic
errors. Errors will be corrected as follows:
(a) where there is a discrepancy between the amount in figures and the amount in
words, the amount in words will prevail; and

(b) where there is a discrepancy between the unit rate and the line item total
resulting from multiplying the unit rate by the quantity, the unit rate as quoted
will prevail, unless in the opinion of the Employer, there is an obvious
typographical error, in which case the adjustment will be made to the entry
containing that error.

(c) In the event of a discrepancy between the tender amount as stated in the Form of
Tender and the corrected tender figure in the main summary of the Bill of
Quantities, the amount as stated in the Form of Tender shall prevail.

(d) The Error Correction Factor shall be computed by expressing the difference
between the tender amount and the corrected tender sum as a percentage of the
corrected Builder’s Work (i.e. Corrected tender sum less P.C. and Provisional
Sums)

(e) The Error Correction Factor shall be applied to all Builder’s Work (as a rebate
or addition as the case may be) for the purposes of valuations for Interim
Certificates and valuation of variations.

(f) the amount stated in the tender will be adjusted in accordance with the above
procedure for the correction of errors and, with
concurrence of the tenderer, shall be considered as binding upon the tenderer. If
the tenderer does not accept the corrected amount, the tender may be rejected
and the Tender Security may be forfeited in accordance with clause 3.11.

5.8 The Employer will evaluate and compare only the tenders determined to be
substantially responsive in accordance with Clause 5.5.

5.9 In evaluating the tenders, the Employer will determine for each tender the evaluated
tender price by adjusting the tender price as follows:

(a) making any correction for errors pursuant to clause 5.7;

(b) excluding provisional sums and the provision, if any, for contingencies in the
Bill of Quantities, but including Dayworks where priced competitively.

(c) making an appropriate adjustment for any other acceptable variations,


deviations, or alternative offers submitted in accordance with clause 3.12; and

(d) making appropriate adjustments to reflect discounts or other price modifications


offered in accordance with clause 4.6

5.10 The Employer reserves the right to accept or reject any variation, deviation, or
alternative offer. Variations, deviations, and alternative offers and other factors which
are in excess of the requirements of the tender documents or otherwise result in
unsolicited benefits for the Employer will not be taken into account in tender
evaluation.
5.11 The tenderer shall not influence the Employer on any matter relating to his tender from
the time of the tender opening to the time the Contract is awarded. Any effort by the
Tenderer to influence the Employer or his employees in his decision on tender
evaluation, tender comparison or Contract award may result in the rejection of the
tender.

5.12 Firms incorporated in Kenya where indigenous Kenyans own 51% or more of the share
capital shall be allowed a 10% preferential bias provided that they do not sub-contract
work valued at more than 50% of the Contract Price excluding Provisional Sums to an
non-indigenous sub-contractor.

6. Award of Contract

6.1 Subject to Clause 6.2, the award of the Contract will be made to the tenderer whose
tender has been determined to be substantially
responsive to the tendering documents and who has offered the lowest evaluated tender
price, provided that such tenderer has been determined to be (a) eligible in accordance
with the provision of Clauses 1.2, and (b) qualified in accordance with the provisions of
clause 1.7 and 1.8.

6.2 Notwithstanding clause 6.1 above, the Employer reserves the right to
accept or reject any tender, and to cancel the tendering process and reject all tenders, at
any time prior to the award of Contract, without thereby incurring any liability to the
affected tenderer or tenderers or any obligation to inform the affected tenderer or
tenderers of the grounds for the action.

6.3 The tenderer whose tender has been accepted will be notified of the award prior to
expiration of the tender validity period in writing or by cable, telex or facsimile. This
notification (hereinafter and in all Contract documents called the “Letter of
Acceptance”) will state the sum (hereinafter and in all Contract documents called the
“Contract Price”)that the Employer will pay the Contractor in consideration of the
execution, completion, and maintenance of the Works by the Contractor as prescribed
by the Contract. At the same time the other tenderers shall be informed that their
tenders have not been successful.

The contract shall be formed on the parties signing the contract.

6.4 The Agreement will incorporate all agreements between the Employer and the
successful tenderer. Within 14 days of receipt the successful tenderer will sign the
Agreement and return it to the Employer.

6.5 Within 21 days after receipt of the Letter of Acceptance, the successful tenderer shall
deliver to the Employer a Performance Security in the amount stipulated in the
Appendix to Conditions of Contract and in the form stipulated in the Tender
documents. The Performance Security shall be in the amount and specified form

6.6 Failure of the successful tenderer to comply with the requirements of clause 6.5 shall
constitute sufficient grounds for cancellation of the award and forfeiture of the Tender
Security.
6.7 Upon the furnishing by the successful tenderer of the Performance Security, the
Employer will promptly notify the other tenderers that their tenders have been
unsuccessful.

6.8 Preference where allowed in the evaluation of tenders shall not be allowed for contracts
not exceeding one year (12 months)

6.9 The tender evaluation committee shall evaluate the tender within 30 days of the validity
period from the date of opening the tender.

6.10 The parties to the contract shall have it signed within 30 days from the date of
notification of contract award unless there is an administrative review request.

6.11 Contract price variations shall not be allowed for contracts not exceeding one year (12
months)

6.12 Where contract price variation is allowed, the valuation shall not exceed 15% of the
original contract price.

6.13 Price variation request shall be processed by the procuring entity within 30 days of
receiving the request.

6.14 The procuring entity may at any time terminate procurement proceedings before
contract award and shall not be liable to any person for the termination.

6.15 The procuring entity shall give prompt notice of the termination to the tenderers and on
request give its reasons for termination within 14 days of receiving the request from
any tenderer.

6.16 A tenderer who gives false information in the tender document about its qualification or
who refuses to enter into a contract after notification of contract award shall be
considered for debarment from participating in future public procurement.

7. Corrupt and Fraudulent practices

7.1 The procuring entity requires that tenderers observe the highest standards of ethics
during procurement process and execution of contracts. A tenderer shall sign a
declaration that he has not and will not be involved in corrupt and fraudulent practices.
Section B

TENDER EVALUATION CRITERIA

CONTENTS

Tender Evaluation Criteria……………………………………………….11-20

Determination of Responsiveness…………………………………………11-16

Detailed Technical Examination…………………………………………16-17

Financial Evaluation………………………………………………………...18-20

Combination of Technical, Tender Sums Comparison and Financial Score…20


TENDER EVALUATION CRITERIA

After tender opening, the tenders will be evaluated in 4 Stages, namely:

1. Preliminary Evaluation &Determination of Responsiveness


2. Technical Evaluation
3. Financial Evaluation.
4. Determination of the Most Responsive Bidder.
5. Recommendation
1. PRELIMINARY EVALUATION&

DETERMINATION OF RESPONSIVENESS
This stage of evaluation shall involve examination of the pre-qualification conditions as set out in the
Tender Advertisement Notice or Letter of Invitation to Tender and any other conditions stated in the
bid document.

These conditions shall include the following:

a) Certified copy of Certificate of Incorporation,


b) Certified copy of VALID Registration Certificate with the National Construction
Authority in the class 5(Five) and above.
c) VAT and PIN registration,
d) A copy of VALID Tax Compliance Certificate from Kenya Revenue Authority
(KRA),
e) Bid bond – 2% of the tender sum,
f) Certified copy of CR12 form from registrar of companies.
g) Certified copy of Single Business Permit preferably from Kisumu County.
h) Bidders shall SEQUENTIALLY SERIALIZE ALL PAGES for each tender
document submitted failure to which the bidder shall be disqualified.
i) Certified copy of relevant (Small works & Engineering) Certificate of registration
for access to government procurement opportunities (AGPO) from the ministry of
National Treasury for tenders in the special categories.
j) Bid declaration for special category duly signed and stamped
Any other conditions included in the advertisement notice/Invitation letter.

Certification must be by a commissioner for oaths.


Note:
The bid security shall be in accordance with clauses 16.1 and 16.2 of Instruction to Tenderers which
states as follows:

Clause 16.1 The bidder shall furnish, as part of his bid, a bid security in the amount shown in the
Appendix to instruction to tenderers. The bid security must be in form of a certified cheque, bank
draft, an irrevocable letter of credit or a guarantee from a reputable Bank/ Insurance approved by
PPOA located in the Republic of Kenya

Clause 16.2 of Instruction to Tenderers, “the unconditional Tender surety shall be in Kenya shillings
and be in form of a certified cheque, bank draft, an irrevocable letter of credit or a guarantee from a
reputable Bank/ Insurance approved by PPOA located in the Republic of Kenya. The format of the
surety shall be in accordance with the sample form included in the tender documents and the tender
surety shall be valid for 150 days from the date of tender opening”.

Clause 26.2 of Instruction to Tenderers: “For the purposes of this clause, a substantially responsive
tender is one which conforms to all terms and condition and specifications of the tender document
without material deviation or reservation and has a valid Bank/Insurance guarantee”.

The employer may seek further clarification/confirmation if necessary to confirm


authenticity/compliance of any condition of the tender.

The tenderers who do not satisfy any of the above requirements shall be considered Non-
Responsive and their tenders will not be evaluated further
2. TECHNICAL EVALUATION

The tender document shall be examined based on clause 4 of the Instruction to Tenderers which states
as follows:

In accordance with clause 4.4 of Instruction to Tenderers, ‘the tenderers shall provide such evidence
of their continued eligibility satisfactory to the Employer as the Employer shall reasonably request’.
The tenderers shall be required to fill the Standards Forms provided for the purposes of providing the
required information. The tenderers may also attach the required information if they so desire.

The award of points for the STANDARD FORMS considered in this section shall be as shown below:

PARAMETER MAXIMUM POINTS


I. Form of Tender --------------------------------------------------------------- 3
II. Tender Questionnaire - ---------------------------------------------------------5
III. Confidential Business Questionnaire ---------------------------------------- 5
IV. Key personnel - ------------------------------------------------------------------15
V. Contract Completed in the last Five (5) years - -----------------------------15
VI. Schedules of on-going projects ------------------------------------------------ 10
VII. Schedules of contractors equipment ----------------------------------------- 10
VIII. Audited Financial Report for the last 3 years------------------------------- 10
IX. Evidence of Financial Resources --------------------------------------------- 10
X. Name, Address and Telephone of Banks (Contractor to provide) ------- 5
XI. Litigation History------------------------------------------------------------------ 2
XII. Sanctity of the tender document as in accordance with clause 5 of
instruction to tenderer ----------------------------------------------------------- 10
TOTAL 100
The detailed scoring plan shall be as shown in table 1 below: -

TABLE 1:

Item Description Point Max.


Scored Point
i Form of Tender 3.0
o Signed and stamped -----------------------------------------------3.0
o Signed but not stamped or vice versa ---------------------------2.0
o Not signed nor stamped------------- ------------------------------ 0
ii Tender Questionnaire Form 5.0
o Completely filled ---------------------------------------------------5.0
o Partially filled ---- -------------------------------------------------3.0
o Not filled --------------------------------------------------------------0
iii Confidential Business Questionnaire Form. 5.0
o Completely filled ------------------------------------------------- 5.0
o Partially filled ----------------------------------------------------- 3.0
o Not filled ----------------------------------------------------------- 0
iv Key Personnel (Attach evidence) 15.0
Director of the firm 4.0
o Holder of degree or diploma in relevant Engineering field------4.0
o Holder of certificate in relevant Engineering field---------------3.0
o Holder of trade test certificate in relevant Engineering field--- 2.0
o No relevant certificate -----------------------------------------------0
At least 1No. degree/diploma of key personnel in relevant Engineering field 4.0
o With over 10 years relevant experience ------------------------4.0
o With over 5 years relevant experience ------------------------- 3.0
o With under 5 years relevant experience ------------------------ 1.0
At least 1No certificate holder of key personnel in relevant Engineering field 3.0
o With over 10 years relevant experience -----------------------3.0
o With over 5 years relevant experience ------------------------ 2
o With under 5 years relevant experience ------------------------1.0
At least 2No artisan (trade test certificate in relevant Engineering field) 4.0
o Artisan with over 10 years relevant experience -------------- 4.0
o Artisan with under 10 years relevant experience ------------- 3.0
o Non skilled worker with over 10 years relevant experience—1.0
v Contract completed in the last five (5) years (Max of 5 No. Projects) 15.0
[Attach Documentary Evidence]
o 5 projects of similar nature, complexity and magnitude ------15.0
o 5 projects of similar nature but of lower value than the one in consideration------
8
o No completed project of similar nature ------------------------- 0
vi On-going projects (Max of 5 No. Projects) 10.0
[Attach Documentary Evidence]
o Project of similar nature, complexity and magnitude ---- 5.0
o Project of similar nature but of lower value than the one in consideration --------
3.0
o No ongoing project of similar nature - -----------------------2
vii Schedule of contractors equipment and transport (proof or evidence of ownership) 4.0 10.0
o Means of transport (Vehicle) -------------------------------- 4.0
o No means of transport ---------------------------------------- 0
For each specific equipment required in the installation of the 6.0
Work being tendered for.
(Maximum No. of equipment to be considered – 3 No.) ----------- 6
Financial Report 10.0
viii
Audited financial report (last three (3) years)
o Turn over greater or equal to 5 times the cost of the project ----10
o Turn over greater or equal to 3 times the cost of the project –-- 6
o Turn over greater or equal to the cost of the project ------------ 4
o Turn over below the cost of the project -------------------------- 2
ix Evidence of Financial Resources (cash in hand, lines of credit, over draft 10.0
facility etc)
o Has financial resources equal or above the cost of the project--10
o Has financial resources below the cost of the project ------- 5.0
o Has not indicated sources of financial resources ------------ 0

x Name, Address and Telephone of Banks (Contractor to provide) 5.0


o Provided ---------------------------------------------------------- 5.0
o Not provided ------------------------------------------------------- 0
xi Litigation History 2.0
o Provided ------------------------------------------------------------- 2.0
o Not Provided -------------------------------------------------------- 0.0

xii Sanctity of the Tender Document 10.0


o Having the document intact
(not tempered with in any way) ------------------------------------ 10.0
o Having mutilated or modified the tender document------------- 0.0

TOTAL 100

DETERMINATION OF TECHNICAL SCORE

Technical shall be calculated as bidder’s score divided by 100 times 50 marks.

Ts = Bidder’s score x 50
100

Any bidder who scores 35 points and above shall be considered for further evaluation.
3. FINANCIAL EVALUATION

The evaluation shall be in two sections


1. Preliminary examinations
2. Tender sum Comparisons

A) PRELIMINARY EXAMINATIONS

The preliminary examination in the Financial Evaluation shall be in accordance with clause 26 of
Instruction to Tenderers.

The parameter to be considered under this section includes the following:


Arithmetic errors and comparison of rates.

(1) Arithmetic Errors

The bid shall be checked for arithmetic errors based on the rates and the total sums indicated in the
bills of quantities.

Confirmation shall be sought in writing from the tenderers whose tender sums will be determined to
have a significant arithmetic error to their disadvantage, to confirm whether they stand by their tender
sums. The error shall be treated as per clause 27 of Instructions to Tenderers.

Non-compliance with the above shall lead to automatic disqualification from further evaluation.

Discount if any shall be treated as an error in pursuant to clause 27 of Instructions to Tenderers.

(2) Comparison of rates


The evaluation committee will compare rates from different bidders and note consistency of rates and
front loading. The evaluation committee will judge and make an appropriate decision giving evidence.

RECOMMENDATION

The evaluation committee shall recommend to the client after tender sums comparisons, for award the
lowest bidder among those who achieve a score of 75% and above in STAGE 2 above
SECTION III CONDITIONS OF CONTRACT

Table of Contents
1 Definitions ………………………………………………… 15
2 Interpretation……………………………………………… 17
3 Language and Law ………………………………………… 17
4 Project Manager’s Decisions……………………………… 17
5 Delegation………………………………………………… 18
6 Communications ………………………………………… 18
7 Sub Contracting ………………………………………… 18
8 Other Contractors ……………………………………… 18
9 Personnel ………………………………………………… 18
10 Works……………………………………………………… 19
11 Safety and temporary works ……………………………… 19
12 Discoveries ………………………………………………… 19
13 Work Programme ………………………………………… 19 -20
14 Possession of site ………………………………………… 20
15 Access to site …………………………………………… 20
16 Instructions ……………………………………………… 20
17 Extension or Acceleration of completion date ………… 20
18 Management Meetings ………………………………… 21
19 Early Warning …………………………………………… 21
20 Defects …………………………………………………… 21 - 22
21 Bills of Quantities ………………………………………… 22
22 Variations ………………………………………………… 22- 23
23 Payment certificates, currency of payments and
Advance Payments ……………………………………… 23
24 Compensation events …………………………………… 25 - 27
25 Price Adjustment ………………………………………… 27 - 29
26 Retention ………………………………………………… 29
27 Liquidated Damages……………………………………… 29
28 Securities ………………………………………………… 29
29 Day Works ……………………………………………… 29 - 30
30 Liability and Insurance …………………………………… 30 - 31
31 Completion and taking over ……………………………… 31
32 Final Account …………………………………………… 31
33 Termination ……………………………………………… 31 - 32
34 Payment upon termination ………………………………… 32 - 33
35 Release from performance ………………………………… 33
36 Corrupt gifts and payments of commission ………………33 - 34
37 Settlement of Disputes ………………………………………34 - 36
CONDITIONS OF CONTRACT

1. Definitions

1.1 In this Contract, except where context otherwise requires, the following terms
shall be interpreted as indicated;

“Bill of Quantities” means the priced and completed Bill of Quantities forming
part of the tender.

“Compensation Events” are those defined in Clause 24 hereunder.

“The Completion Date” means the date of completion of the Works as certified
by the Project Manager, in accordance with Clause 31.

“The Contract” means the agreement entered into between the Employer and the
Contractor as recorded in the Agreement Form and signed by the parties including
all attachments and appendices thereto and all documents incorporated by
reference therein to execute, complete, and maintain the Works,

“The Contractor” refers to the person or corporate body whose tender to carry
out the Works has been accepted by the Employer.

“The Contractor’s Tender”is the completed tendering document submitted by


the Contractor to the Employer.

“The Contract Price” is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the Contract.

“Days” are calendar days; “Months” are calendar months.

“A Defect” is any part of the Works not completed in accordance with the
Contract.

“The Defects Liability Certificate” is the certificate issued by Project Manager


upon correction of defects by the Contractor.

“The Defects Liability Period” is the period named in the Contract Data and
calculated from the Completion Date.

“Drawings” include calculations and other information provided or approved by


the Project Manager for the execution of the Contract.

“Dayworks” are Work inputs subject to payment on a time basis for labour and
the associated materials and plant.

“Employer”, or the “Procuring entity” as defined in the Public Procurement


Regulations (i.e. Central or Local Government administration, Universities, Public
Institutions and Corporations, etc) is the party who employs the Contractor to
carry out the Works.
“Equipment” is the Contractor’s machinery and vehicles brought temporarily to
the Site for the execution of the Works.

“The Intended Completion Date” is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date may be
revised only by the Project Manager by issuing an extension of time or an
acceleration order.

“Materials” are all supplies, including consumables, used by the Contractor for
incorporation in the Works.

“Plant” is any integral part of the Works that shall have a mechanical, electrical,
chemical, or biological function.

“Project Manager” is the person named in the Appendix to Conditions of


Contract (or any other competent person appointed by the Employer and notified
to the Contractor, to act in replacement of the Project Manager) who is responsible
for supervising the execution of the Works and administering the Contract and
shall be an “Architect” or a “Quantity Surveyor” registered under the Architects
and Quantity Surveyors Act Cap 525 or an “Engineer” registered under Engineers
Registration Act Cap 530.

“Site” is the area defined as such in the Appendix to Condition of Contract.

“Site Investigation Reports” are those reports that may be included in the
tendering documents which are factual and interpretative about the surface and
subsurface conditions at the Site.

“Specifications” means the Specifications of the Works included in the Contract


and any modification or addition made or approved by the Project Manager.

“Start Date” is the latest date when the Contractor shall commence execution of
the Works. It does not necessarily coincide with the Site possession date(s).

“A Subcontractor” is a person or corporate body who has a Contract with the


Contractor to carry out a part of the Work in the Contract, which includes Work
on the Site.

“Temporary works” are works designed, constructed, installed, and removed by


the Contractor which are needed for construction or installation of the Works.

“A Variation” is an instruction given by the Project Manager which varies the Works.

“The Works” are what the Contract requires the Contractor to construct, install, and
turnover to the Employer, as defined in the Appendix to Conditions of Contract.

2. Interpretation

2.1 In interpreting these Conditions of Contract, singular also means plural, male also
means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning in English Language unless
specifically defined. The Project Manager will provide instructions clarifying
queries about these Conditions of Contract.

2.2 If sectional completion is specified in the Appendix to Conditions of Contract,


reference in the Conditions of Contract to the Works, the Completion Date and the
Intended Completion Date apply to any section of the Works (other than
references to the Intended Completion Date for the whole of the Works).

2.3 The following documents shall constitute the Contract documents and shall be
interpreted in the following order of priority;

(1) Agreement,

(2) Letter of Acceptance,

(3) Contractor’s Tender,

(4) Appendix to Conditions of Contract,

(5) Conditions of Contract,

(6) Specifications,

(7) Drawings,

(8) Bill of Quantities,

(9) Any other documents listed in the Appendix to Conditions of Contract as


forming part of the Contract.

Immediately after the execution of the Contract, the Project Manager


shall furnish both the Employer and the Contractor with two copies
each of all the Contract documents. Further, as and when necessary
the Project Manager shall furnish the Contractor [always with a copy
to the Employer] with three [3] copies of such further drawings or
details or descriptive schedules as are reasonably necessary either
to explain or amplify the Contract drawings or to enable the
Contractor to carry out and complete the Works in accordance with
these Conditions.

3. Language and Law

3.1 Language of the Contract and the law governing the Contract shall be English
language and the Laws of Kenya respectively unless
otherwise stated.

4 Project Manager’s Decisions

4.1 Except where otherwise specifically stated, the Project Manager will decide
contractual matters between the Employer and the Contractor in the role
representing the Employer.
5 Delegation

5.1 The Project Manager may delegate any of his duties and responsibilities to others
after notifying the Contractor.

6 Communications

6.1 Communication between parties shall be effective only when in writing. A notice
shall be effective only when it is delivered.

7 Subcontracting

7.1 The Contractor may subcontract with the approval of the Project Manager, but
may not assign the Contract without the approval of the Employer in writing.
Subcontracting shall not alter the Contractor’s obligations.

8 Other Contractors

8.1 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities etc. as listed in the Appendix to Conditions of Contract and
also with the Employer, as per the directions of the Project Manager. The
Contractor shall also provide facilities and services for them. The Employer may
modify the said List of Other Contractors etc., and shall notify the Contractor of
any such modification.

9 Personnel

9.1 The Contractor shall employ the key personnel named in the Qualification
Information, to carry out the functions stated in the said Information or other
personnel approved by the Project Manager. The Project Manager will approve
any proposed replacement of key personnel only if their relevant qualifications
and abilities are substantially equal to or better than those of the personnel listed in
the Qualification Information. If the Project Manager asks the Contractor to
remove a person who is a member of the Contractor’s staff or work force, stating
the reasons, the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the Work in the Contract.

10 Works

10.1 The Contractor shall construct and install the Works in accordance with the
Specifications and Drawings. The Works may commence on the Start Date and
shall be carried out in accordance with the Program submitted by the Contractor,
as updated with the approval of the Project Manager, and complete them by the
Intended Completion Date.
11 Safety and Temporary Works

11.1 The Contractor shall be responsible for the design of temporary works. However
before erecting the same, he shall submit his designs including specifications and
drawings to the Project Manager and to any other relevant third parties for their
approval. No erection of temporary works shall be done until such approvals are
obtained.

11.2 The Project Manager’s approval shall not alter the Contractor’s responsibility for
design of the Temporary works and all drawings prepared by the Contractor for
the execution of the temporary or permanent Works, shall be subject to prior
approval by the Project Manager before they can be used.

11.3 The Contractor shall be responsible for the safety of all activities on the Site.

12. Discoveries

12.1 Anyth ing of historical or other interest or of significant value unexpectedly


discovered on Site shall be the property of the Employer. The Contractor shall
notify the Project Manager of such discoveries and carry out the Project
Manager’s instructions for dealing with them.

13. Work Program

13.1 Within the time stated in the Appendix to Conditions of Contract, the Contractor
shall submit to the Project Manager for approval a program showing the general
methods, arrangements, order, and timing for all the activities in the Works. An
update of the program shall be a program showing the actual progress achieved on
each activity and the effect of the progress achieved on the timing of the
remaining Work, including any changes to the sequence of the activities.

The Contractor shall submit to the Project Manager for approval an updated
program at intervals no longer than the period stated in the Appendix to
Conditions of Contract. If the Contractor does not submit an updated program
within this period, the Project Manager
may withhold the amount stated in the said Appendix from the next payment
certificate and continue to withhold this amount until the next payment after the
date on which the overdue program has been submitted. The Project Manager’s
approval of the program shall not alter the Contractor’s obligations. The
Contractor may revise the program and submit it to the Project Manager again at
any time. A revised program shall show the effect of Variations and
Compensation Events.

14. Possession of Site

14.1 The Employer shall give possession of all parts of the Site to the Contractor. If
possession of a part is not given by the date stated in the Appendix to Conditions
of Contract , the Employer will be deemed to have delayed the start of the relevant
activities, and this will be a Compensation Event.
15. Access to Site

15.1 The Contractor shall allow the Project Manager and any other person authorised
by the Project Manager, access to the Site and to any place where work in
connection with the Contract is being carried out or is intended to be carried out.

16. Instructions

16.1 The Contractor shall carry out all instructions of the Project Manager which are in
accordance with the Contract.

17. Extension or Acceleration of Completion Date

17.1 The Project Manager shall extend the Intended Completion Date if a
Compensation Event occurs or a variation is issued which makes it impossible for
completion to be achieved by the Intended Completion Date without the
Contractor taking steps to accelerate the remaining Work, which would cause the
Contractor to incur additional cost. The Project Manager shall decide whether and
by how much to extend the Intended Completion Date within 21 days of the
Contractor asking the Project Manager in writing for a decision upon the effect of
a Compensation Event or variation and submitting full supporting information. If
the Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay caused by such failure shall not be
considered in assessing the new (extended) Completion Date.

17.2 No bonus for early completion of the Works shall be paid to the Contractor by the
Employer.

18. Management Meetings

18.1 A Contract management meeting shall be held monthly and attended by the
Project Manager and the Contractor. Its business shall be to review the plans for
the remaining Work and to deal with matters raised in accordance with the early
warning procedure. The Project Manager shall record the minutes of management
meetings and provide copies of the same to those attending the meeting and the
Employer. The responsibility of the parties for actions to be taken shall be
decided by the Project Manager either at the management meeting or after the
management meeting and stated in writing to all who attended the meeting.

19. Early Warning

19.1 The Contractor shall warn the Project Manager at the earliest opportunity of
specific likely future events or circumstances that may adversely affect the quality
of the Work, increase the Contract Price or delay the execution of the Works. The
Project Manager may require the Contractor to provide an estimate of the expected
effect of the future event or circumstance on the Contract Price and Completion
Date. The estimate shall be provided by the Contractor as soon as reasonably
possible.
19.2 The Contractor shall cooperate with the Project Manager in making and
considering proposals on how the effect of such an event or circumstance can be
avoided or reduced by anyone involved in the Work and in carrying out any
resulting instructions of the Project Manager.

20. Defects

20.1 The Project Manager shall inspect the Contractor’s work and notify the Contractor
of any defects that are found. Such inspection shall not affect the Contractor’s
responsibilities. The Project Manager may instruct the Contractor to search for a
defect and to uncover and test any Work that the Project Manager considers may
have a defect. Should the defect be found, the cost of uncovering and making
good shall be borne by the Contractor, However, if there is no defect found, the
cost of uncovering and making good shall be treated as a variation and added to
the Contract Price.

20.2 The Project Manager shall give notice to the Contractor of any defects
before the end of the Defects Liability Period, which begins at Completion, and is
defined in the Appendix to Conditions of Contract. The Defects Liability Period
shall be extended for as long as defects remain to be corrected.

20.3 Every time notice of a defect is given, the Contractor shall correct the notified
defect within the length of time specified by the Project Manager’s notice. If the
Contractor has not corrected a defect within the time specified in the Project
Manager’s notice, the Project Manager will assess the cost of having the defect
corrected by other parties and such cost shall be treated as a variation and be
deducted from the Contract Price.

21. Bills Of Quantities

21.1 The Bills of Quantities shall contain items for the construction, installation, testing
and commissioning of the Work to be done by the Contractor. The Contractor
will be paid for the quantity of the Work done at the rate in the Bills of Quantities
for each item.

21.2 If the final quantity of the Work done differs from the quantity in the Bills of
Quantities for the particular item by more than 25 percent and provided the
change exceeds 1 percent of the Initial Contract price, the Project Manager shall
adjust the rate to allow for the change.

21.3 If requested by the Project Manager, the Contractor shall provide the Project
Manager with a detailed cost breakdown of any rate in the Bills of Quantities.

22. Variations

22.1 All variations shall be included in updated programs produced by the Contractor.

22.2 The Contractor shall provide the Project Manager with a quotation for carrying out
the variations when requested to do so. The Project Manager shall assess the
quotation, which shall be given within seven days of the request or within any
longer period as may be stated by the Project Manager and before the Variation is
ordered.

22.3 If the work in the variation corresponds with an item description in the Bills of
Quantities and if in the opinion of the Project Manager, the quantity of work is not
above the limit stated in Clause 21.2 or the timing of its execution does not cause
the cost per unit of quantity to change, the rate in the Bills of Quantities shall be
used to calculate the value of the variation. If the cost per unit of quantity
changes, or
if the nature or timing of the work in the variation does not correspond with items
in the Bills of Quantities, the quotation by the Contractor shall be in the form of
new rates for the relevant items of Work.

22.4 If the Contractor’s quotation is unreasonable, the Project Manager may order the
variation and make a change to the Contract price, which shall be based on the
Project Manager’s own forecast of the effects of the variation on the Contractor’s
costs.

22.5 If the Project Manager decides that the urgency of varying the Work would
prevent a quotation being given and considered without delaying the Work, no
quotation shall be given and the variation shall be treated as a Compensation
Event.

22.6 The Contractor shall not be entitled to additional payment for costs that could
have been avoided by giving early warning.

22.7 When the Program is updated, the Contractor shall provide the Project Manager
with an updated cash flow forecast.

22.8

23. Payment Certificates, Currency of Payments and Advance Payments

23.1 The Contractor shall submit to the Project Manager monthly applications for
payment giving sufficient details of the Work done and materials on Site and the
amounts which the Contractor considers himself to be entitled to. The Project
Manager shall check the monthly application and certify the amount to be paid to
the Contractor within 14 days. The value of Work executed and payable shall be
determined by the Project Manager.

23.2 The value of Work executed shall comprise the value of the quantities of the items
in the Bills of Quantities completed, materials delivered on Site, variations and
compensation events. Such materials shall become the property of the Employer
once the Employer has paid the Contractor for their value . Thereafter, they shall
not be removed from Site without the Project Manager’s instructions except for
use upon the Works.

23.3 Payments shall be adjusted for deductions for retention. The Employer shall pay
the Contractor the amounts certified by the Project Manager within 30 days of the
date of issue of each certificate. If the Employer makes a late payment, the
Contractor shall be paid simple interest on the late payment in the next payment.
Interest shall be calculated on the basis of number of days delayed at a rate three
percentage points above the Central Bank of Kenya’s average rate for base
lending prevailing as of the first day the payment becomes overdue.

23.4 If an amount certified is increased in a later certificate or as a result of an award


by an Arbitrator, the Contractor shall be paid interest upon the delayed payment as
set out in this clause. Interest shall be calculated from the date upon which the
increased amount would have been certified in the absence of dispute.

23.5 Items of the Works for which no rate or price has been entered in will not be paid
for by the Employer and shall be deemed covered by other rates and prices in the
Contract.

23.6 The Contract Price shall be stated in Kenya Shillings. All payments to the
Contractor shall be made in Kenya Shillings and foreign currency in the
proportion indicated in the tender, or agreed prior to the execution of the Contract
Agreement and indicated therein. The rate of exchange for the calculation of the
amount of foreign currency payment shall be the rate of exchange indicated in the
Appendix to Conditions of Contract. If the Contractor indicated foreign
currencies for payment other than the currencies of the countries of origin of
related goods and services the Employer reserves the right to pay the equivalent at
the time of payment in the currencies of the countries of such goods and services.
The Employer and the Project Manager shall be notified promptly by the
Contractor of an changes in the expected foreign currency requirements of the
Contractor during the execution of the Works as indicated in the Schedule of
Foreign Currency Requirements and the foreign and local currency portions of the
balance of the Contract Price shall then be amended by agreement between
Employer and the Contractor in order to reflect appropriately such changes.

23.7 In the event that an advance payment is granted, the following shall apply:-

a) On signature of the Contract, the Contractor shall at his request, and


without furnishing proof of expenditure, be entitled to an advance of 10%
(ten percent) of the original amount of the Contract. The advance shall not
be subject to retention money.

b) No advance payment may be made before the Contractor has submitted


proof of the establishment of deposit or a directly
liable guarantee satisfactory to the Employer in the amount of the advance
payment. The guarantee shall be in the same currency as the advance.

c) Reimbursement of the lump sum advance shall be made by deductions


from the Interim payments and where applicable from the balance owing
to the Contractor. Reimbursement shall begin when the amount of the
sums due under the Contract reaches 20% of the original amount of the
Contract. It shall have been completed by the time 80% of this amount is
reached.
The amount to be repaid by way of successive deductions shall be calculated by means of
the formula:

R = A(x1 – x11)
80 – 20
Where:

R = the amount to be reimbursed

A = the amount of the advance which has been granted

X1 = the amount of proposed cumulative payments as a


percentage of the original amount of the Contract. This
figure will exceed 20% but not exceed 80%.

X11 = the amount of the previous cumulative payments as a


percentage of the original amount of the Contract. This
figure will be below 80%but not less than 20%.

d) with each reimbursement the counterpart of the directly liable guarantee


may be reduced accordingly.

24. Compensation Events

24.1 The following issues shall constitute Compensation Events:

(a) The Employer does not give access to a part of the Site by the Site
Possession Date stated in the Appendix to Conditions of Contract.

(b) The Employer modifies the List of Other Contractors, etc., in a way that
affects the Work of the Contractor under the Contract.

(c) The Project Manager orders a delay or does not issue drawings,
specifications or instructions required for execution of the Works on time.

(d) The Project Manager instructs the Contractor to uncover or to carry out
additional tests upon the Work, which is then found to have no defects.

(e) The Project Manager unreasonably does not approve a subcontract to be


let.

(f) Ground conditions are substantially more adverse than could reasonably
have been assumed before issuance of the Letter of Acceptance from the
information issued to tenderers (including the Site investigation reports),
from information available publicly and from a visual inspection of the
Site.

(g) The Project Manager gives an instruction for dealing with an unforeseen
condition, caused by the Employer or additional work required for safety
or other reasons.
(h) Other contractors, public authorities, utilities, or the Employer does not
work within the dates and other constraints stated in the Contract, and they
cause delay or extra cost to the Contractor.

(i) The effects on the Contractor of any of the Employer’s risks.

(j) The Project Manager unreasonably delays issuing a Certificate of


Completion.

(k) Other compensation events described in the Contract or determined by the


Project Manager shall apply.

24.2 If a compensation event would cause additional cost or would prevent the Work
being completed before the Intended Completion Date, the Contract Price shall be
increased and/or the Intended Completion Date shall be extended. The Project
Manager shall decide whether and by how much the Contract Price shall be
increased and whether and by how much the Intended Completion Date shall be
extended.

24.3 As soon as information demonstrating the effect of each compensation event upon
the Contractor’s forecast cost has been provided by the Contractor, it shall be
assessed by the Project Manager, and the Contract Price shall be adjusted
accordingly. If the Contractor’s forecast is deemed unreasonable, the Project
Manager shall adjust the Contract Price based on the Project Manager’s own
forecast. The
Project Manager will assume that the Contractor will react competently and
promptly to the event.

24.4 The Contractor shall not be entitled to compensation to the extent that the
Employer’s interests are adversely affected by the Contractor not having given
early warning or not having co-operated with the Project Manager.

24.5 Prices shall be adjusted for fluctuations in the cost of inputs only if provided for in
the Appendix to Conditions of Contract.

24.6 The Contractor shall give written notice to the Project Manager of his intention to
make a claim within thirty days after the event giving rise to the claim has first
arisen. The claim shall be submitted within thirty days thereafter.

Provided always that should the event giving rise to the claim of continuing effect,
the Contractor shall submit an interim claim within the said thirty days and a final
claim within thirty days of the end of the event giving rise to the claim.

25. Price Adjustment

25.1 The Project Manager shall adjust the Contract Price if taxes, duties and other
levies are changed between the date 30 days before the submission of tenders for
the Contract and the date of Completion. The adjustment shall be the change in
the amount of tax payable by the Contractor.

25.2 The Contract Price shall be deemed to be based on exchange rates current at the
date of tender submission in calculating the cost to the Contractor of materials to
be specifically imported (by express provisions in the Contract Bills of Quantities
or Specifications) for permanent incorporation in the Works. Unless otherwise
stated in the Contract, if at any time during the period of the Contract exchange
rates shall be varied and this shall affect the cost to the Contractor of such
materials, then the Project Manager shall assess the net difference in the cost of
such materials. Any amount from time to time so assessed shall be added to or
deducted from the Contract Price, as the case may be.

25.3 Unless otherwise stated in the Contract, the Contract Price shall be deemed to
have been calculated in the manner set out below and in sub-clauses 25.4 and 25.5
and shall be subject to adjustment in the events specified thereunder;

(i) The prices contained in the Contract Bills of Quantities shall be deemed to
be based upon the rates of wages and other
emoluments and expenses as determined by the Joint Building Council of
Kenya (J.B.C.) and set out in the schedule of basic rates issued 30 days
before the date for submission of tenders.A copy of the schedule used by
the Contractor in his pricing shall be attached in the Appendix to
Conditions of Contract.

(ii) Upon J.B.C. determining that any of the said rates of wages or other
emoluments and expenses are increased or decreased, then the Contract
Price shall be increased or decreased by the amount assessed by the Project
Manager based upon the difference, expressed as a percentage, between
the rate set out
in the schedule of basic rates issued 30 days before the date for submission
of tenders and the rate published by the J.B.C. and applied to the quantum
of labour incorporated within the amount of Work remaining to be
executed at the date of publication of such increase or decrease.

(iii) No adjustment shall be made in respect of changes in the rates of wages


and other emoluments and expenses which occur after the date of
Completion except during such other period as may be granted as an
extension of time under clause 17.0 of these Conditions.

25.4 The prices contained in the Contract Bills of Quantities shall be deemed to be
based upon the basic prices of materials to be permanently incorporated in the
Works as determined by the J.B.C. and set out in the schedule of basic rates issued
30 days before the date for submission of tenders. A copy of the schedule used by
the Contractor in his pricing shall be attached in the Appendix to Conditions of
Contract.

25.5 Upon the J.B.C. determining that any of the said basic prices are increased or
decreased then the Contract Price shall be increased or decreased by the amount to
be assessed by the Project Manager based upon the difference between the price
set out in the schedule of basic rates issued 30 days before the date for submission
of tenders and the rate published by the J.B.C. and applied to the quantum of the
relevant materials which have not been taken into account in arriving at the
amount of any interim certificate under clause 23 of these Conditions issued
before the date of publication of such increase or decrease.
25.6 No adjustment shall be made in respect of changes in basic prices of materials
which occur after the date for Completion except during such other period as may
be granted as an extension of time under clause 17.0 of these Conditions.

25.7 The provisions of sub-clause 25.1 to 25.2 herein shall not apply in respect of any
materials included in the schedule of basic rates.

26. Retention

26.1 The Employer shall retain from each payment due to the Contractor the proportion
stated in the Appendix to Conditions of Contract until Completion of the whole of
the Works. On Completion of the whole of the Works, half the total amount
retained shall be repaid to the Contractor and the remaining half when the Defects
Liability Period has passed and the Project Manager has certified that all defects
notified to the Contractor before the end of this period have been corrected.

27. Liquidated Damages

27.1 The Contractor shall pay liquidated damages to the Employer at the rate stated in
the Appendix to Conditions of Contract for each day that the actual Completion
Date is later than the Intended Completion Date. The Employer may deduct
liquidated damages from payments due to the Contractor. Payment of liquidated
damages shall not alter the Contractor’s liabilities.

27.2 If the Intended Completion Date is extended after liquidated damages have been
paid, the Project Manager shall correct any overpayment of liquidated damages by
the Contractor by adjusting the next payment certificate. The Contractor shall be
paid interest on the overpayment, calculated from the date of payment to the date
of repayment, at the rate specified in Clause 23.30

28. Securities

28.1 The Performance Security shall be provided to the Employer no later than the date
specified in the Letter of Acceptance and shall be issued in an amount and form
and by a reputable bank acceptable to the Employer, and denominated in Kenya
Shillings. The Performance Security shall be valid until a date 30 days beyond the
date of issue of the Certificate of Completion.

29. Dayworks

29.1 If applicable, the Dayworks rates in the Contractor’s tender shall be used for small
additional amounts of Work only when the Project Manager has given written
instructions in advance for additional work to be paid for in that way.
29.2 All work to be paid for as Dayworks shall be recorded by the Contractor on Forms
approved by the Project Manager. Each completed form shall be verified and
signed by the Project Manager within two days of the Work being done.

29.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks
forms.

30. Liability and Insurance

30.1 From the Start Date until the Defects Correction Certificate has been issued, the
following are the Employer’s risks:

(a) The risk of personal injury, death or loss of or damage to property


(excluding the Works, Plant, Materials and Equipment), which are due to;

(i) use or occupation of the Site by the Works or for the purpose of the
Works, which is the unavoidable result of the Works, or

(ii) negligence, breach of statutory duty or interference with any legal


right by the Employer or by any person employed by or contracted
to him except the Contractor.

(b) The risk of damage to the Works, Plant, Materials, and Equipment to the
extent that it is due to a fault of the Employer or in Employer’s design, or
due to war or radioactive contamination directly affecting the place where
the Works are being executed.

30.2 From the Completion Date until the Defects Correction Certificate has been
issued, the risk of loss of or damage to the Works, Plant, and Materials is the
Employer’s risk except loss or damage due to;

(a) a defect which existed on or before the Completion Date.

(b) an event occurring before the Completion Date, which was not itself the
Employer’s risk

(c) the activities of the Contractor on the Site after the Completion Date.

30.3 From the Start Date until the Defects Correction Certificate has been issued, the
risks of personal injury, death and loss of or damage to property (including,
without limitation, the Works, Plant, Materials, and Equipment) which are not
Employer’s risk are Contractor’s risks.

The Contractor shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start Date to the end of the Defects Liability
Period, in the amounts stated in the Appendix to Conditions of Contract for the
following events;
(a) loss of or damage to the Works, Plant, and Materials;
(b) loss of or damage to Equipment;
(c) loss of or damage to property (except the Works, Plant, Materials, and
Equipment) in connection with the Contract, and
(d) personal injury or death.
30.4 Policies and certificates for insurance shall be delivered by the Contractor to the
Project Manager for the Project Manager’s approval before the Start Date. All
such insurance shall provide for compensation required to rectify the loss or
damage incurred.

30.5 If the Contractor does not provide any of the policies and certificates required, the
Employer may effect the insurance which the Contractor should have provided
and recover the premiums from payments otherwise due to the Contractor or, if no
payment is due, the payment of the premiums shall be a debt due.

30.6 Alterations to the terms of an insurance shall not be made without the approval of
the Project Manager. Both parties shall comply with any conditions of insurance
policies.

31. Completion and taking over

31.1 Upon deciding that the Works are complete, the Contractor shall issue a written
request to the Project Manager to issue a Certificate of Completion of the Works.
The Employer shall take over the Site and the Works within seven [7] days of the
Project Manager’s issuing a Certificate of Completion.

32. Final Account

32.1 The Contractor shall issue the Project Manager with a detailed account of the total
amount that the Contractor considers payable to him by the Employer under the
Contract before the end of the Defects Liability Period. The Project Manager shall
issue a Defects Liability Certificate and certify any final payment that is due to the
Contractor within 30 days of receiving the Contractor’s account if it is correct and
complete. If it is not, the Project Manager shall issue within 30 days a schedule
that states the scope of the corrections or additions that are necessary. If the final
account is still unsatisfactory after it has been resubmitted, the Project Manager
shall decide on the amount payable to the Contractor and issue a Payment
Certificate. The Employer shall pay the Contractor the amount due in the Final
Certificate within 60 days.

33. Termination

33.1 The Employer or the Contractor may terminate the Contract if the other party
causes a fundamental breach of the Contract. These

fundamental breaches of Contract shall include, but shall not be limited to, the
following;

(a) the Contractor stops work for 30 days when no stoppage of work is shown
on the current program and the stoppage has not been authorised by the
Project Manager;

(b) the Project Manager instructs the Contractor to delay the progress of the
Works, and the instruction is not withdrawn within 30 days;
(c) the Contractor is declared bankrupt or goes into liquidation other than for a
reconstruction or amalgamation;

(d) a payment certified by the Project Manager is not paid by the Employer to
the Contractor within 30 days (for Interim Certificate) or 60 days (for Final
Certificate)of issue.

(e) the Project Manager gives notice that failure to correct a particular defect
is a fundamental breach of Contract and the Contractor fails to correct it
within a reasonable period of time determined by the Project Manager;

(f) the Contractor does not maintain a security, which is required.

33.2 When either party to the Contract gives notice of a breach of Contract to the
Project Manager for a cause other than those listed under Clause 33.1 above, the
Project Manager shall decide whether the breach is fundamental or not.

33.3 Notwithstanding the above, the Employer may terminate the Contract for
convenience.

33.4 If the Contract is terminated, the Contractor shall stop work immediately, make
the Site safe and secure, and leave the Site as soon as reasonably possible. The
Project Manager shall immediately thereafter arrange for a meeting for the
purpose of taking record of the Works executed and materials, goods, equipment
and temporary buildings on Site.

34. Payment Upon Termination

34.1 If the Contract is terminated because of a fundamental breach of Contract by the


Contractor, the Project Manager shall issue a certificate for the value of the Work
done and materials ordered and delivered to Site up to the date of the issue of the
certificate. Additional liquidated damages shall not apply. If the total amount due
to the Employer exceeds any payment due to the Contractor, the difference shall
be a debt payable by the Contractor.

34.2 If the Contract is terminated for the Employer’s convenience or because of a


fundamental breach of Contract by the Employer, the Project Manager shall issue
a certificate for the value of the Work done, materials ordered, the reasonable cost
of removal of equipment, repatriation of the Contractor’s personnel employed
solely on the
Works, and the Contractor’s costs of protecting and securing the Works.

34.3 The Employer may employ and pay other persons to carry out and complete the
Works and to rectify any defects and may enter upon the Works and use all
materials on the Site, plant, equipment and temporary works.

34.4 The Contractor shall, during the execution or after the completion of the Works
under this clause remove from the Site as and when required, within such
reasonable time as the Project Manager may in writing specify, any temporary
buildings, plant, machinery, appliances, goods or materials belonging to or hired
by him, and in default the Employer may (without being responsible for any loss
or damage) remove and sell any such property of the Contractor, holding the
proceeds less all costs incurred to the credit of the Contractor.
Until after completion of the Works under this clause the Employer shall not be
bound by any other provision of this Contract to make any payment to the
Contractor, but upon such completion as aforesaid and the verification within a
reasonable time of the accounts therefore the Project Manager shall certify the
amount of expenses properly incurred by the Employer and, if such amount added
to the money paid to the Contractor before such determination exceeds the total
amount which would have been payable on due completion in accordance with
this Contract the difference shall be a debt payable to the Employer by the
Contractor; and if the said amount added to the said money be less than the said
total amount, the difference shall be a debt payable by the Employer to the
Contractor.

35. Release from Performance

35.1 If the Contract is frustrated by the outbreak of war or by any other event entirely
outside the control of either the Employer or the Contractor, the Project Manager
shall certify that the Contract has been frustrated. The Contractor shall make the
Site safe and stop Work as quickly as possible after receiving this certificate and
shall be paid for all Work carried out before receiving it.

36. Corrupt gifts and payments of commission

The Contractor shall not;

(a) Offer or give or agree to give to any person in the service of the

Employer any gift or consideration of any kind as an inducement or reward for


doing or forbearing to do or for having done or forborne to do any act in relation
to the obtaining or execution of this or any other Contract for the Employer or for
showing or forbearing to show favour
or disfavour to any person in relation to this or any other contract for the
Employer.

(b) Enter into this or any other contract with the Employer in connection with which
commission has been paid or agreed to be paid by him or on his behalf or to his
knowledge, unless before the Contract is made particulars of any such commission
and of the terms and conditions of any agreement for the payment thereof have
been disclosed in writing to the Employer.

Any breach of this Condition by the Contractor or by anyone employed by him or


acting on his behalf (whether with or without the knowledge of the Contractor)
shall be an offence under the provisions of the Public Procurement Regulations
issued under The Exchequer and Audit Act Cap 412 of the Laws of Kenya.

37. Settlement Of Disputes

37.1 In case any dispute or difference shall arise between the Employer or the Project
Manager on his behalf and the Contractor, either during the progress or after the
completion or termination of the Works, such dispute shall be notified in writing
by either party to the other with a request to submit it to arbitration and to concur
in the appointment of an Arbitrator within thirty days of the notice. The dispute
shall be referred to the arbitration and final decision of a person to be agreed
between the parties. Failing agreement to concur in the appointment of an
Arbitrator, the Arbitrator shall be appointed by the Chairman or Vice Chairman of
any of the following professional institutions;

(i) Architectural Association of Kenya

(ii) Institute of Quantity Surveyors of Kenya

(iii) Association of Consulting Engineers of Kenya

(iv) Chartered Institute of Arbitrators (Kenya Branch)

(v) Institution of Engineers of Kenya

On the request of the applying party. The institution written to first by the
aggrieved party shall take precedence over all other institutions.

37.2 The arbitration may be on the construction of this Contract or on any matter or
thing of whatsoever nature arising thereunder or in connection therewith,
including any matter or thing left by this Contract to the discretion of the Project
Manager, or the withholding by the Project Manager of any certificate to which
the Contractor may claim to be entitled to or the measurement and valuation
referred to in clause 23.0 of these conditions, or the rights and liabilities of the
parties subsequent to the termination of Contract.

37.3 Provided that no arbitration proceedings shall be commenced on any dispute or


difference where notice of a dispute or difference has not been given by the
applying party within ninety days of the occurrence or discovery of the matter or
issue giving rise to the dispute.

37.4 Notwithstanding the issue of a notice as stated above, the arbitration of such a
dispute or difference shall not commence unless an attempt has in the first
instance been made by the parties to settle such dispute or difference amicably
with or without the assistance of third parties. Proof of such attempt shall be
required.

37.5 Notwithstanding anything stated herein the following matters may be referred to
arbitration before the practical completion of the Works or abandonment of the
Works or termination of the Contract by either party:

37.5.1 The appointment of a replacement Project Manager


upon the said person ceasing to act.

37.5.2 Whether or not the issue of an instruction by the Project


Manager is empowered by these Conditions.

37.5.3 Whether or not a certificate has been improperly withheld


or is not in accordance with these Conditions.

37.5.4 Any dispute or difference arising in respect of war risks or war damage.
37.6 All other matters shall only be referred to arbitration after the completion or
alleged completion of the Works or termination or alleged termination of the
Contract, unless the Employer and the Contractor agree otherwise in writing.

37.7 The Arbitrator shall, without prejudice to the generality of his powers, have
powers to direct such measurements, computations, tests or valuations as may in
his opinion be desirable in order to determine the rights of the parties and assess
and award any sums which ought to have been the subject of or included in any
certificate.

37.8 The Arbitrator shall, without prejudice to the generality of his powers,

have powers to open up, review and revise any certificate, opinion, decision,
requirement or notice and to determine all matters in dispute which shall be
submitted to him in the same manner as if no such certificate, opinion, decision
requirement or notice had been given.

37.9 The award of such Arbitrator shall be final and binding upon the parties.
SECTION IV – APPENDIX TO CONDITIONS OF CONTRACT

THE EMPLOYER IS

Name: -
_________________________________________________________________________

Address: ______________________________________________________________________

Name of Authorised Representative: ____________________________________________

Telephone: _______________________

Facsimile: ________________________

The Project Manager is

Name:
_________________________________________________________________________

Address:
_______________________________________________________________________

Telephone: _______________________

Facsimile: ________________________

The name (and identification number) of the Contract is _________________________

______________________________________________________________________________
___

The Works consist of____________________________________________________________

______________________________________________________________________________
__

The Start Date shall be _________________________________________________________

The Intended Completion Date for the whole of the Works shall be
______________________________________________________________________________
___

The following documents also form part of the Contract:


______________________________________________________________________________
___

______________________________________________________________________________
___
The Contractor shall submit a revised program for the Works within ____7____ days of delivery
of the Letter of Acceptance.

The Site Possession Date shall be ____________Not later than 14 days after signing of Contract
Agreement failure to which the project stands terminated____________________________

The Site is located at __________________________________________________ and is


defined in drawings nos._________________________________________________________

______________________________________________________________________________
__

The Defects Liability period is ___________180_____________ days.

Other Contractors, utilities etc., to be engaged by the Employer on the Site


Include those for the execution of ;

1.____________________________________________

2.______________________________________________

3._____________________________________________

4._____________________________________________

The minimum insurance covers shall be;

1. The minimum cover for insurance of the Works and of Plant and Materials in
respect of the Contractor’s faulty design is____________________

2. The minimum cover for loss or damage to Equipment is____________________

3. The minimum for insurance of other property is____________________________

4. The minimum cover for personal injury or death insurance

• For the Contractor’s employees is___________________________________

• And for other people is______________________________________________

The following events shall also be Compensation Events:

1.
__________________________________________________________________________

2.
__________________________________________________________________________

3.
__________________________________________________________________________
4.
__________________________________________________________________________

The period between Program updates is ________________ days.

The amount to be withheld for late submission of an updated Program is ________

______________________________________________________________________________
__

The proportion of payments retained is ___________10___________ percent.

The Price Adjustment Clause _____________________________ (shall/shall not) apply

The liquidated damages for the whole of the Works is Kshs. _____________(per day)

The Performance Security shall be for the following minimum amounts equivalent as a
percentage of the Contract Price--------------- percent (2%)

The Completion Period for the Works is___________________________[Weeks]

The rate of exchange for calculation of foreign currency payments is ______________________.

The schedule of basic rates used in pricing by the Contractor is as attached [Contractor to
attach].

Advance Payment SHALL NOT be granted.


SECTION V - SPECIFICATIONS

Notes for preparing Specifications

1.0 Specifications must be drafted to present a clear and


precise statement of the required standards of materials,
and workmanship for tenderers to respond realistically and
competitively to the requirements of the Employer and ensure
responsiveness of tenders. The Specifications should require that
all materials, plant, and other supplies to be permanently
incorporated in the Works be new, unused, of the most recent or
current models, and incorporating all recent improvements in
design and materials unless provided otherwise in the Contract.
Where the Contractor is responsible for the design of any part of
the permanent Works, the extent of his obligations must be stated.

2.0 Specifications from previous similar projects are useful and may
not be necessary to re-write specifications for every Works
Contract.

3.0 There are considerable advantages in standardizing General


Specifications for repetitive Works in recognized public sectors,
such as highways, urban housing, irrigation and water supply. The
General Specifications should cover all classes of workmanship,
materials and equipment commonly involved in constructions,
although not necessarily to be used in a particular works contract.
Deletions or addenda should then adapt the General Specifications
to the particular Works.

4.0 Care must be taken in drafting Specifications to ensure they are not
restrictive. In the Specifications of standards for materials, plant
and workmanship, existing Kenya Standards should be used as
much as possible, otherwise recognized international standards may
also be used.

5.0 The Employer should decide whether technical solutions to


specified parts of the Works are to be permitted. Alternatives are
appropriate in cases where obvious (and potentially less costly)
alternatives are possible to the technical solutions indicated in
tender documents for certain elements of the Works, taking into
consideration the comparative specialized advantage of potential
tenderers.

The Employer should provide a description of the selected parts of


the Works with appropriate reference to Drawings, Specifications,
Bills of Quantities, and Design or Performance criteria, stating that
the alternative solutions shall be at least structurally and
functionally equivalent to the basic design parameters and
Specifications.
Such alternative solutions shall be accompanied by all information
necessary for a complete evaluation by the Employer, including
drawings, design calculations, technical specifications, breakdown
of prices, proposed construction methodology, and other relevant
details. Technical alternatives permitted in this manner shall be
considered by the Employer each on its own merits and
independently of whether the tenderer has priced the item as
described in the Employer’s design included with the tender
documents.
SECTION VI - DRAWINGS

Note 1. A list of drawings should be inserted here

2. The actual drawings including Site plans should be annexed in a


separate booklet.
SECTION VII - BILL OF QUANTITIES

Notes for preparing Bills of Quantities

1.0 The objectives of the Bills of Quantities are;

(a) to provide sufficient information on the quantities of Works to be performed to


enable tenders to be prepared efficiently and accurately; and

(b) when a Contract has been entered into, to provide a priced Bill of Quantities for
use in the periodic valuation of Works executed.

In order to attain these objectives, Works should be itemized in the Bill of


Quantities in sufficient detail to distinguish between the different classes of
Works, or between Works of the same nature carried out in different locations or
in other circumstances which may give rise to different considerations of cost.
Consistent with these requirements, the layout and content of the Bill of Quantities
should be as simple and brief as possible.

2.0 The Bills of Quantities should be divided generally into the following sections:

(a) Preliminaries.

The preliminaries should indicate the inclusiveness of the unit prices, and should
state the methods of measurement which have been adopted in the preparation of
the Bill of Quantities and which are to be used for the measurement of any part of
the Works.

The number of preliminary items to be priced by the tenderer should be limited to


tangible items such as site office and other temporary works, otherwise items such
as security for the Works which are primarily part of the Contractor’s obligations
should be included in the Contractor’s rates.

(b) Work Items

(i) The items in the Bills of Quantities should be grouped into sections to
distinguish between those parts of the Works which by nature, location,
access, timing, or any other special characteristics may give rise to
different methods of construction, or phasing of the Works, or
considerations of cost. General items common to all parts of the Works
may be grouped as a separate section in the Bill of Quantities.

(ii) Quantities should be computed net from the Drawings, unless directed
otherwise in the Contract, and no allowance should be made for bulking,
shrinkage or waste. Quantities should be rounded up or down where
appropriate.
(iii) The following units of measurement and abbreviations are recommended
for use.

Unit Abbreviation Unit Abbreviation


cubic meter m3 or cu m millimeter Mm
hectare ha month mon
hour h number nr
kilogram kg square meter m2 or sq m
lump sum sum square millimeter mm2 or sq mm
meter m week wk
metric ton (1,000 t
kg)

(iv) The commencing surface should be identified in the description of


each item for Work involving excavation, boring or drilling, for
which the commencing surface is not also the original surface. The
excavated surface should be identified in the description of each
item for Work involving excavation for which the excavated
surface is not also the final surface. The depths of Work should be
measured from the commencing surface to the excavated surface,
as defined.

(c) Daywork Schedule

A Daywork Schedule should be included if the probability of unforeseen work, outside the
items included in the Bill of Quantities, is relatively high. To facilitate checking by the
Employer of the realism of rates quoted by the tenderers, the Daywork Schedule should
normally comprise:

(i) a list of the various classes of labour, and


materials for which basic Day work rates or
prices are to be inserted by the tenderer,
together with a statement of the conditions
under which the Contractor will be paid for
Work executed on a Day work basis; and

(ii) a percentage to be entered by the tenderer against each basic


Day work Subtotal amount for labour, materials and plant
representing the Contractor’s profit, overheads, supervision
and other charges.
(d) Provisional Quantities and Sums
(i) Provision for quantity contingencies in any particular
item or class of Work with a high expectation of
quantity overrun should be made by entering specific
“Provisional Quantities” or “Provisional Items” in the
Bill of Quantities, and not by increasing the quantities
for that item or class of Work beyond those of the Work
normally expected to be required. To the extent not
covered above, a general provision for physical
contingencies (quantity overruns) should be made by
including a “Provisional Sum” in the Summary of the
Bill of Quantities. Similarly, a contingency allowance
for possible price increases should be provided as a
“Provisional Sum” in the Summary of the Bill of
Quantities. The inclusion of such provisional sums often
facilitates budgetary approval by avoiding the need to
request periodic supplementary approvals as the future
need arises.

(ii) Provisional sums to cover specialized works normally carried out


by Nominated Sub Contractors should be avoided and instead Bills
of Quantities of the specialised Works should be included as a
section of the main Bills of Quantities to be priced by the Main
Contractor. The Main Contractor should be required to indicate the
name (s) of

the specialised firms he proposes to engage to carry out the specialized


Works as his approved domestic sub-contractors. Only provisional sums
to cover specialized Works by statutory authorities should be included in
the Bills of Quantities.

(e) Summary

The Summary should contain a tabulation of the separate parts of


the Bills of Quantities carried forward, with provisional sums for
Daywork, for physical (quantity) contingencies, and for price
contingencies (upward price adjustment) where applicable.
ITEM
NO. DESCRIPTION UNIT QTY. KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY FOR


COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 1

PRELIMINARIES

A Erection and maintenance of a Publicity Sign board in compliance


with the Public Works design through out the duration of the Project
Sum 15,000 00

B Erection and maintenance of a Site Store/office through out the


duration of the Project Sum 50,000 00

TOTAL FOR PRELIMINARIES CARRIED TO SUMMARY KSHS. 65,000 00


ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO.1

SUBSTRUCTURE

(All Provisional)

NOTES

1 The Tenderer's attention is drawn to the Preliminaries


Contract Particulars Clause 8.0 which states that the
Standard Method of Measurement is the June 2008
Edition. Per Clause D5(g) of this S.M.M all
excavations in this BoQ have been measured NET
and no allowance has been made for working space
and the tenderer is shall price for the excavations
accordingly.

2 Cement for all Structural Works in these Bills of


Quantities shall strictly be Grade 32.5

3 Cement for Non-Structural Works in these Bills of


Quantities shall be Grade 32.5

4 All Reinforcement in these Bills of Quantities shall be


to BS 4449:1997 with the following characteristic; a)
Grade 460 B high strength type 2 Ribbed bars with
proof stress of 460N/mm²; allow for cutting, bending,
hoisting and fixing including all necessary trying wires
and spacer stools;

Substructures 2/1
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

SUBSTRUCTURES (CONT'D)

Excavations & Earthworks

A Clear site of all grass, shrubs and grab up; remove from
site m2 345

B Excavate to remove top vegetable soil average 150mm


deep; remove from site m3 52

C Excavate for strip foundations not exceeding 1.5 m


deep from reduced level m3 113

D Ditto for Column Bases not exceeding 1.5 m deep from


reduced level m3 4

E Allow for keeping excavations free from water by


baling or pumping as required including provision of
drains, etc., as described Item

F Allow for maintaining and supporting sides of


excavations and for keeping free from fallen materials
as described Item

Disposal

G Backfilling around foundations & columns m3 75

H Load and cart away surplus spoil m3 38

Imported filling

I 300mm Thick approved hardcore under floor bed well


compacted m2 257

J 40mm Thick Murram or quarry dust blinding to


hardcore m2 257

Carried to Collection

Substructures 2/2
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

SUBSTRUCTURES (CONT'D)

Damp proof membrane as described :-

A 1000 Gauge polythene sheet dampproof membrane to


horizontal surfaces m2 257

Anti-termite treatment

B Chemical anti-termite treatment executed by an


approved specialist under a ten-year guarantee to
horizontal surfaces of the floor slab and around the
plinth, e.t.c. m2 257

Concrete Class ( 1:3:6 ) in 50mm thick blinding under :-

C Strip foundations for masonry walling m2 97

D Column bases m2 25

Vibrated reinforced concrete class 20 in:

E Colum Bases m3 4

F Columns m3 1

G Strip foundations m3 19

H 150 mm Thick slab m2 257

I Ground Beam m3 8

Reinforcement

Reinforcement to BS 4449:1997 with the following


characteristic; a) Grade 460 B high strength type 2
Ribbed bars with proof stress of 460N/mm²; allow for
cutting, bending, hoisting and fixing including all
necessary trying wires and spacer stools

J D12 Kg 499

K D10 Kg 1,153

L D8 Kg 376

Carried to Collection
Substructures 2/3
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

SUBSTRUCTURES (CONT'D)

Steel mesh fabric reinforcement to B.S. 4483

A Ref. A142 Layer of fabric mesh reinforcement laid in


bed with 150mm side and end laps m2 257

Sawn formwork to:

B Sides of column bases m2 16

C Sides of column m2 20

D Sides of strip foundations m2 63

E Sides of Ground Beam m2 110

F Edges of floor beds 75 - 150mm high m 79

Quarry dressed natural stone walling in cement sand


mortar (1:3) with minimum crushing strength of 7.0
2
N/mm

G 200mm Thick walling m2 188

1000 Gauge polythene sheet damp proof course laid on


and including cement sand (1:3) levelling screed

H 200mm Wide m 140

Cement sand ( 1:4 ) render to :-

I 12mm Thick render to wall externally m2 39

Prepare and apply two coats of bituminous paint to :-

J Rendered walls externally m2 39

Carried to Collection

Substructures 2/4
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

COLLECTION

Page No. 2/2

Page No. 2/3

Page No. 2/4

TOTAL FOR SUBSTRUCTURES CARRIED TO


SUMMARY

Substructures 2/5
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF
DISPENSARY FOR COUNTY GOVERNMENT
OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO.2

RC SUPERSTRUCTURE

Concrete Class 20mm in:-

A Columns m3 3

Concrete Class 20mm in:-

B Beams m3 8

Reinforcement; as before described

C D12 Kg 633

C D8 Kg 450

Sawn formwork to :-

E Vertical sides of columns m2 49

F Sides and soffites of beams m2 110

TOTAL FOR RC SUPERSTRUCTURE


CARRIED TO SUMMARY

RC Superstructure 2/6
ITEM DESCRIPTION UNIT QTY RATE KSHS.

BILLS OF QUANTITIES

ELEMENT NO.4

ROOF CONSTRUCTION, COVERINGS


AND RAINWATER DISPOSAL

ROOF CONSTRUCTION

The following in sawn softwood timber including fabricating, hoisting and


fixing in position approximately 12,000mm above ground floor level as per
Structural Engineer's drawing

Treated Sawn cypress

Rates to include all necessary bolting and/or nailing

A 75 x 50 mm Purlins m 266

B 100 x 50 mm Common Rafters m 172

C 100 x 50 mm Wall plate m 69

D 100 x 50 mm Tie beam m 155

E 100 x 50 mm Kingpost m 39

F 100 x 50 mm Struts m 179

Wrot treated prime grade cypress

G 38mm thick tongued and grooved eaves filling V-jointed and secretly nailed
onto and including 50mm x 50mm sawn cypress brackets with mosquito wire
gauze in between m2 54

H 225mm x 38mm thick fascia board fixed onto ends of rafters m 89

Carried to Collection
ROOF COVERINGS

A Roof covering as GCI Sheet roofing gauge 28 including roof vents to suppliers
recommendations m2 286

B 150mm diameter half round ridge tile to match roof tiles m 33

Prepare surfaces and apply one coat of aluminium wood primer and two
finishing coats of gloss oil paint on:
C General wood surfaces m2 54

D Wood surfaces 200 - 300mm girth m 89

Rainwater goods

E 200mm dia. PVC gutter fixed onto fascia board with approved mild steel straps
at every 1,000mm centres m 52

F Extra over ditto for stopped ends No. 4

G Ditto for forming 150mm x 150mm hole for down pipe No. 4

H 150mm dia.PVC rain water down pipe fixed onto walls with approved mild steel
support brackets at 1,000mm centres m 12

I Extra over ditto for swan neck projection with 600mm offset No. 4

J Ditto horse-shoe ditto with 300mm offset No. 4

K 150mm Diameter cast-iron fulbora outlets No. 4

Carried to Collection
COLLECTION

Page No. 2/10

Page No. 2/11

TOTAL FOR ROOF CARRIED TO SUMMARY


ITEM
NO. DESCRIPTION UNIT QTY. RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO. 5

EXTERNAL WALLS

Approved local natural stonework; squared and


machine dressed or precast concrete blocks; bedded in
cement mortar (1:4); reinforced with 25mm wide x
20mm gauge hoop iron strapping every alternate course

A 200mm Thick walls m2 150

B Ditto Gable walls m2 22

TOTAL FOR EXTERNAL WALLS CARRIED TO


SUMMARY

External Walls 2/14


ITEM
NO. DESCRIPTION UNIT QTY. RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO. 6

INTERNAL WALLS

Approved local natural stonework; squared and


machine dressed or precast concrete blocks; bedded in
cement mortar (1:4); reinforced with 25mm wide x
20mm gauge hoop iron strapping every alternate course

A 2000mm Thick walls m2 115

TOTAL FOR INTERNAL WALLS CARRIED TO


SUMMARY

Internal Walls 2/16


ITEM
NO. DESCRIPTION UNIT QTY. RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO. 7

WINDOWS

STEEL WINDOWS

Supply and fix the following purpose made casement


windows comprising of 50 x 50 x 16 G and 25 mm "Z"
section framing including all coupling mullions etc;and
complete with bronze handles ,peg stays and other
ironmongery; factory primed with red oxide primer
including cutting and pining fixing lugs to concrete or
masonry work jambs ; bedding in cement and sand
(1:3) mortar , pointing all round frames in mastic
,easing ,oiling and adjusting opening lights on
completion, including 4 mm glazing; All as per the
architect's Schedule of windows

A Size 1500 x 1500 mm high No. 16

Precast concrete weathered and throated window cills

B Window cill over all size 275 x 100 mm high with 3


No m 72
labour.
C Prepare and apply three coats gloss paint m2 72

Glazing

B 4mm thick clear sheet glass in panes 0.1-0.5sm fixed in


steel window panes with putty sm 36

TOTAL FOR WINDOWS CARRIED TO


SUMMARY

Windows 2/17
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO. 8

DOORS

Flush Doors

45mm Thick blockboard semi -solid core flush door


with hardwood lipping; including 5mm Thick clears
glass to 300mm fanlight

A Size 900 x 2400 mm high door No. 14

Steel Door

Supply and fix the following steel casement door


fabricated from 50mm x 25mm x 3mm thick
Rectangular Hollow Section ( R.H.S) mild steel
framing infilled with 14 gauge mild steel sheet factory
primed in red oxide or zinc chromate primer including
6mm thick clear glass infill complete with all necessary
purpose made ironmongery, and locks to Architect's
details and approval

B Size 1500 x 2400 mm high door No. 3

Frames

Sawn softwood frame

C 150 x 30 mm Thick frames with two labours m 92

Carried to Collection

Doors 2/19
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

DOORS (CONT'D)

A 80 x 20 mm Architraves with two labours m 92

Ironmongery

Supply and fix the following ironmongery as applicable


or equal and approved ironmongery with matching

B 100 mm Mild Steel Butt Hinges Prs 42

C Two lever mortice lock including 2 No. Lever Handles Set 14

Painting and decorating

Prepare and apply three coats matt emulsion paint to

D Timber surfaces m2 61

E Surfaces 100 - 200 mm girth m 92

Touch up primer,prepare and apply three coats of gloss


oil paint to

F Metal surfaces m2 22

Carried to Collection

COLLECTION

Page No. 2/17

Page No. 2/18

TOTAL FOR DOORS CARRIED TO SUMMARY

Doors 2/20
ITEM
NO. DESCRIPTION UNIT QTY RATE KSHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

BILLS OF QUANTITIES

SECTION NO. 2

ELEMENT NO. 9

EXTERNAL FINISHES

Floor Finishes

Cement Sand (1:4) screed as described

A 15 mm Thick finished to receive tiles m2 27

Supply and fix with and including Sika Ceramic 100g


grey adhesive and grouting with Sika tile grout and
pointing to match. Rate to include breakage and
cutting waste

B 400 x 400 mm Ceramic tiles in patterns as directed m2 27

C 100 mm Skirting tile cut out of tiles above m 5

TOTAL FOR EXTERNAL FINISHES CARRIED


TO SUMMARY

External Finishes 2/21


ITEM DESCRIPTION UNIT QTY RATE KSHS.

BILLS OF QUANTITIES

ELEMENT NO.10

FINISHES

Floor Finishes

15mm Thick cement sand(1:3) backing screed to receive terrazzo/ceramic


A tiles(m.s) m2 230

B 400x400mm ceramic tiles m2 230

C Ditto 100mm high skirting m 138

Walls

D 12mm thick gauged plaster cement sand lime 1:1:6 with a smooth float to
m2 402
walls internally

Ceiling

E Approved soft board ceiling fixed to brandering m2 257

F 10 x 75mm ditto cornice plugged and nailed to battens m 162

G Extra-over ditto in access door size 450 x 600mm including framing in 75 no 1

Prepare and apply 3 coats permaplast long lasting exterior first grade
plastic emulsion paint as ''crown;; or any other equal and approved paint to:

H Ceiling m2 257

I Walls m2 402

Brandering

J 50 x 50mm sawn cypress brandering m 399

K 50 x 75mm ditto m 414

TOTAL FOR FINISHES CARRIED TO SUMMARY


ITEM
NO. SHS. CTS.

#REF!

BILLS OF QUANTITIES

SECTION NO. 2

SUMMARY

1. SUBSTRUCTURES

2. RC SUPERSTRUCTURE

3 ROOF

4 EXTERNAL WALLS

5 INTERNAL WALLS

6 WINDOWS

7 DOORS

8 EXTERNAL FINISHES

9 INTERNAL FINISHES

TOTAL FOR BUILDER'S WORK CARRIED


TO MAIN SUMMARY KSHS.

Summary 2/26
ITEM
NO. DESCRIPTION UNIT QTY. KSHS. CTS.

#REF!

BILLS OF QUANTITIES

SECTION NO. 3

PRIME COST AND PROVISIONAL SUMS

A Allow the Prime Cost Sum of Kenya Shillings One Hundred


and Forty Thousand Only for Electrical Works Sum 140,000 00

B Allow a Provisional Sum of Kenya Shillings Twenty


thousand for Project Management and Supervision Sum 20,000 00

C Allow a Provisional Sum of Kenya Shillings Fifty Thousand


for Contigencies Sum 50,000 00

D Allow a Provisional Sum of Kenya Shillings Twenty


Thousand for Environmental and Social Impact Assessment Sum 20,000 00

E Allow a Provisional Sum of Kenya Shillings Six Thousand


for Material Tests Sum 6,000 00

TOTAL FOR PRIME COST AND PROVISIONAL


SUMS CARRIED TO SUMMARY KSHS. 236,000 00

PC and Provisionals Sums 3/1


ITEM
NO. DESCRIPTION SHS. CTS.

PROPOSED CONSTRUCTION OF DISPENSARY


FOR COUNTY GOVERNMENT OF KISUMU

MAIN SUMMARY

1. PRELIMINARIES

2. BUILDER'S WORKS

3 PROVISIONAL SUMS

TOTAL CARRIED TO FORM OF TENDER KSHS.


INCLISIVE 16% VAT

EMPLOYER: CONTRACTOR

NAME: …………………...…………………… NAME: …………………...……………………

……………………………………..…………. ……………………………………..………….

ADDRESS: ………….…………………………. ADDRESS: ………….………………………….

………………………………………………….. …………………………………………………..

SIGNATURE: …………………………………. SIGNATURE: ………………………………….

DATE: …………………………………………. DATE: ………………………………………….

Main Summary MS/1


APPENDIX TO CONDITIONS OF CONTRACT

Name of Employer: Chief Officer


DEPARTMENT OF HEALTH
COUNTY GOVERNMENT OF KISUMU
P.O BOX 2738-40100
KISUMU

Name of Employer’s Representative: THE CHIEF OFFICER, ROADS TRANSPORT AND


PUBLIC WORKS, P.O. BOX 2738-40100, KISUMU

Name of Project Manager: THE DIRECTOR PUBLIC WORKS

The name of Contract is: PROPOSED CONSTRUCTION OF ARAO OBUNGA DISPENSARY


Tender No: … CGK/H&S/19-20/053

Scope of the Works: AS PER BILLS OF QUANTITIES IN THIS TENDER


DOCUMENT, AND THE CONTRACT AGREEMENT

The Tender Opening Date and Time will be on


…………………………………………………………at ………. at (PROSPERITY HOUSE,
FORMER NYANZA HEADQUARTERS) The Start Date shall be as stated in the Project
Manager’s Notice to commence work.
The Intended Completion period for the whole of the Works shall be ……. from the date of
commencement.
The Site Possession Date shall be the date site is handed over to the Contractor by the Project
Manager. The Site is located at KISUMU COUNTY The Defects Liability Period is 6
MONTHS
The Contractor shall submit a revised program for the Works within ____7____ days of delivery
of the Letter of Acceptance.

The Site Possession Date shall be ____________Not later than 14 days after signing of Contract
Agreement failure to which the project stands terminated____________________________

Amount of Tender Security is Kshs………………………………………… (2% of the Tender


Price) in the Form of Tender Security or a Banker’s Cheque, from a reputable Commercial Bank,
to the Employer.

The amount of Performance Security is 10% of CONTRACT PRICE in form of a Performance


bank Guarantee, from a reputable Commercial Bank, acceptable to the Employer.

Retention Money will be 10% of the INTERIM CERTIFICATE with a limit of 10% of the
Contract Price or such other sum as shall become payable. SECTION VIII –
Section

STANDARD FORMS

(i) Form of Invitation for Tender………………….…. 158


(ii) Form of Tender…………………………….………… 159
(iii) Appendix to form tender……………………………...160
(iii) Qualification Information……………….…………. 161
1. Individual Tenderers………………. 163
2. Joint Ventures……………………… 164
3. Line of Credit……………………………165
4. Declaration form………………………..166
5. Details of Contractor’s Experience… 167
6. Details of Ongoing Projects………… 168
7. Schedule of Key Personnel………… 169
8. Details of Subcontractors………….. 170
9. Schedule of Plants and Equipment..171
(iv) Tender Questionnaire………………………………….. 172
(v) Confidential Business Questionnaire…………. 173-174
(vi) Schedule of Particulars……………………………… …175
1. Particulars of Firm…………………… 175
2. Particulars of Insurance……………. ..177

(vi) Certificate of Bidder’s Pre-site Visit……………………177


(vii) Supervision Check List…………………………………….178
(I) FORM OF INVITATION FOR TENDER

_______________________[date]

To: _____________________________________ [name of Contractor]


_____________________________________[address]
_____________________________________
_____________________________________

Dear Sirs:

Reference:______________________________________________[Contract Name]

You have been prequalified to tender for the above project.

We hereby invite you and other prequalified tenderers to submit a tender for the execution and
completion of the above Contract.

A complete set of tender documents may be purchased by you from ____


________________________________________________________________________
[mailing address, cable/telex/facsimile numbers].

Upon payment of a non-refundable fee of Kshs __________________________

All tenders must be accompanied by ________________number of copies of the same and a


security in the form and amount specified in the tendering documents, and must be delivered to
________________________________________________________________________
[address and location]

at or before _______________________(time and date). Tenders will be opened immediately


thereafter, in the presence of tenderers’ representatives who choose to attend.

Please confirm receipt of this letter immediately in writing by cable/facsimile or telex.

Yours faithfully,

_____________________________________ Authorized Signature

_____________________________________ Name and Title


(II) FORM OF TENDER
TO: __________________________[Name of Employer) ____________[Date]
__________________________[Name of Contract]

Dear Sir,

1. In accordance with the Conditions of Contract, Specifications, Drawings and Bills of


Quantities for the execution of the above named Works, we, the undersigned offer to
construct, install and complete such Works and remedy any defects therein for the sum of
Kshs._____________________________[Amount in figures]Kenya
Shillings_________________________________________________________________
__________________________[Amount in words]

2. We undertake, if our tender is accepted, to commence the Works as


soon as is reasonably possible after the receipt of the Project Manager’s notice to
commence, and to complete the whole of the Works comprised in the Contract within the
time stated in the Appendix to Conditions of Contract.

3. We agree to abide by this tender until ___________________[Insert date], and it shall


remain binding upon us and may be accepted at any time before that date.

4. Unless and until a formal Agreement is prepared and executed this tender together with your
written acceptance thereof, shall constitute a binding Contract between us.

5. We understand that you are not bound to accept the lowest or any tender you may receive.

Dated this ____________________ day of _________________2017

Signature __________________in the capacity of___________________

duly authorized to sign tenders for and on behalf of

___________________________________________________[Name of Tenderer]

of_________________________________________________[Address of Tenderer]

Witness; Name______________________________________

Address_____________________________________

Signature___________________________________

Date_______________________________________
(III) APPENDIX TO FORM OF TENDER

(This Appendix forms part of the Tender)

CONDITIONS OF CONTRACT CLAUSE AMOUNT


Bid Security (Bank Guarantee or Insurance) 2% of the tender sum
Amount of Performance Security 10.1 10%
(Unconditional Bank Guarantee)
Submitted by the 14th day from the date of award
Submission of Performance Security letter

Not later than 7 (seven) days after contract signing


Work Programme to be submitted 14.1 & Issuance of Order to Commence

Not later than 14 (fourteen) days after issuance of


Cash flow estimate to be submitted 14.3 Order to Commence

Minimum amount of Contractors All Risk 23.2 0.3% of the Contract Price
Insurance Cover

Submission of Contractors All Risk Insurance Submitted by the 14th day from the date of
Cover award letter
Period for commencement, from Engineer’s order
to commence 41.1 14 days

Time for completion 43.1 12 Weeks


Advance Payment 60.12 N/A
Amount of liquidated damages 47.1 0.1 % of the contract price per day.

Limit of liquidated damages 47.1 5% of Contract Value

Defects Liability period 49.1 6 months


Percentage of Retention 60.3 10% of Interim Payment Certificate

Limit of Retention Money 60.3 10% of Contract Price


Minimum amount of interim certificates 60.2 Kshs. 500,000 for projects above this amount

The Chartered Institute of Arbitrators – Kenya


Appointer of Arbitrator 67(3) Branch.

Notice to Employer and Engineer 68.2 The Employer’s address is:

The Chief Officer


Department of Health
County Government of Kisumu
P.O. Box 2378-40100
KISUMU

The Project Manager’s address is:


Director Public Works
County Government of Kisumu
P.O. Box 2378-40100
KISUMU

Signature of Tenderer………………………………… Date……………………


(IV) OTHER SUPPLEMENTARY INFORMATION

1. Financial reports for the last three years, balance sheets, profit and loss statements, auditors’
reports etc. List them below and attach copies.
………………………………………………………………………
………………………………………………………………………

2. Evidence of access to financial resources to meet the qualification requirements. Cash in


hand, lines of credit etc. List below and attach copies of supporting documents (bank to fill
attached form).
………………………………………………………………………
………………………………………………………………………

3. Name, address, telephone, telex, fax numbers of the Tenderer’s Bankers who may provide
reference if contacted by the Employer.
…………………………………………………………………………
…………………………………………………………………………

• Submit copies of audited profit and loss statements and balance sheet for
the last three calendar years and estimated projection for the next two
years with certified English translation where appropriate.

• Give turnover figures for each of the last three (3) financial years. Quote in
millions and decimal thereof.
Type of \Work Year Year Year
Kshs. Kshs. Kshs.
Building works
Other civil engineering works
Other (specify)
Total

SUMMARY OF ASSETS AND LIABILITIES OF THE AUDITED


FINANCIAL STATEMENTS OF THE LAST THREE (3) FINANCIAL
YEARS
Year Year Year
Kshs. Kshs. Kshs.
1. Total Assets
2. Current Assets
3. Bank credit Line Value
4. Total Liabilities
5. Current Liabilities
6. Net worth (1-4)
7. Working capital (2+3-4)

Name/Address of Commercial Bank providing credit line


Total amount of credit line KShs.……………..………………………………

Attach certified copies of financial bank statements of the last three years.
Attach a certified copy of Undertaking of the Bank to providing the credit.
Information on current litigation in which the Tenderer is involved.

OTHER PARTY (IES) CAUSE OF DISPUTE AMOUNT INVOLVED (KSHS)

I certify that the above information is correct.

…………………… ……………………… ………………………


Name/Title Signature Date
(V) QUALIFICATION INFORMATION

1. Individual Tenderers or Individual Members of Joint Ventures

1.1 Constitution or legal status of tenderer (attach copy or Incorporation Certificate);


Place of registration: ____________________________

Principal place of business _____________________________

Power of attorney of signatory of tender ____________________

1.2 Total annual volume of construction work performed in the last five years
VOLUME
YEAR CURRENCY VALUE

1.3 Work performed as Main Contractor on works of a similar nature and volume over
the last five years. Also list details of work under way or committed, including
expected completion date.

[Fill in the Details as described in the Table attached on Pages S-6 and S-7]

1.4 Major items of Contractor’s Equipment proposed for carrying out the Works. List
all information requested in the table provided.

[Fill in the Details as described in the Table attached on Page S-10]

1.5 Qualifications and experience of key personnel proposed for administration and
execution of the Contract.

[Fill in the Details as described in the Table attached on Page S-8]


1.6 .

__________________________________________________________________
____________________________________________________________

1.7 Statement of compliance with the requirements of Clause 1.2 of the Instructions to
Tenderers.
____________________________________________________________
_____________________________________________

1.8 Proposed program (work method and schedule) for the whole of the Works.
Attached a detailed proposed work plan for the execution of the Works described.

2 Joint Ventures

2.4 The information listed in 1.1 – 1.10 above shall be provided for each partner of the
joint venture.
2.5 The information required in 1.11 above shall be provided for the joint venture.

2.6 Attach the power of attorney of the signatory(ies) of the tender authorizing
signature of the tender on behalf of the joint venture

2.7 Attach the Agreement among all partners of the joint venture ( and which is
legally binding on all partners), which shows that:

a) all partners shall be jointly and severally liable for the execution of the
Contract in accordance with the Contract terms;

b) one of the partners will be nominated as being in charge, authorized to


incur liabilities and receive instructions for and on behalf of any and all
partners of the joint venture; and

c) the execution of the entire Contract, including payment, shall be done


exclusively with the partner in charge.
2. LETTER OF CREDIT

To:
The Chief Officer
Department of Health
County Government of Kisumu,
P.O. Box 2738-40100
Kisumu

RE: LINE OF CREDIT FOR (CONTRACT DETAILS)

Reference is made to inquiry from our Customer ……………………………….. of P.O. Box


……………………………. in regard to line of Credit for financing above tender. We wish to
state as following.

1. M/S ……………………………………………………..(name of tender) has


satisfactorily conducted an account dominated in Kenya Shillings with us for a period of
more than one year.
2. Currently the above named Customer enjoys
1. A Bank Overdraft facility of Kshs …………. …….
2. A bank loan of Kshs ………………………….
3. As per the prudential norms for Financing which MUST be fulfilled by our customer, we
are in a position to provide a line of credit to M/s ……………………………….
(tenderer name) for Kshs ……………

This information is given in strict confidence, and without any guarantee or liability on the part
of the bank or any of its officers.

Yours Faithfully

Bank Authorised Signatory


3. DECLARATION FORM

Date
To:
The Chief Officer
Department of Health
County Government of Kisumu,
P.O. Box 2738-40100
kisumu

The tenderer i.e. (name and address)

declare the following:

a) Has not been debarred from participating in public procurement.

b) Has not been involved in and will not be involved in corrupt and fraudulent practices
regarding public procurement.

Name/Title Signature Date

(To be signed by authorized representative and officially stamped)

69
4. DETAILS OF CONTRACTOR’S EXPERIENCE

In the table below, give a brief summary of the Company’s major Road Works carried out and
completed in the last FIVE years. The works listed should be similar to the Works described in this
tender.

DESCRIPTION OF WORKS, TOTAL CONTRACT YEAR


CLIENT AND CONTACT PERSON VALUE OF PERIOD COMPLET
WORKS (YEARS) ED
(KSH.)

Note: Attach relevant documentary evidence.

I certify that the above Road Works were successfully carried out and completed by ourselves.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

70
5. DETAILS OF ONGOING PROJECTS

In the table below, give a brief summary of the Company’s major Road Works that are currently
ongoing. The works listed should be similar to the Works described in this tender.

INTENDED %
DESCRIPTION OF CONTR- DATE OF DATE OF TOTAL COMPLE-
WORKS, CLIENT AND ACT COMMEN- COMPLE- VALUE OF TED TO
CONTACT PERSON PERIOD CEMENT TION WORKS DATE

Note: Attach relevant documentary evidence.

I certify that the above Road Works are being carried out by ourselves and that the above
information concerning them is correct.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

71
6. SCHEDULE OF KEY PERSONNEL

In the table below, give the details of the Tenderer’s Key Technical Personnel who will be
responsible for the major activities of the works described in this tender, both at the Headquarters
and at the Site.

NATIONA-LITY SUMMARY OF
DESIGNATION NAME QUALIFICATIONS AND
EXPERIENCE

Note: Attach the CVs of the Key Personnel.

I certify that the above information is correct.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

72
7. DETAILS OF SUB-CONTRACTORS

If the Tenderer wishes to sublet any portions of the works under any heading, he must give below
the details of the sub-contractors he intends to employ for each portion.

Failure to comply with this requirement may invalidate the tender.

PORTION OF WORKS
FULL NAME AND TO BE SUB- SUB-CONTRACTOR’S
ADDRESS OF THE SUB- CONTRACTED AND EXPERIENCE IN SIMILAR
CONTRACTOR CONTRACT VALUE WORKS

Note: Attach relevant evidence.

I certify that the above information is correct.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

73
1 7. SCHEDULE OF PLANT AND EQUIPMENT

OWNERSHIP
PARTICULARS TYPE/ SERIAL YEAR WHER VALU OWNE TO HIRE PURCHA PRESEN WEEK
OF EACH RATIN NO. & OF E E D HIRE PURCHASESE T WHEN
UNIT G REG. NO. MANUF MADE (Give (Give (Give details(Give LOCATI AVAIL
A- SR. No. name as stated in details as ON ABLE
CTURE and Reg. and the stated in ON
No) address Footnote) the SITE
of Footnote)
Owner)

Note *Details of each machine/equipment in more than one of the same make or type must be given separately. Items to be imported pursuant
to the conditions of contract to be indicated together with seller’s name, address and CIF value. Details of proposed hire or hire purchase
to be submitted giving names and addresses of hiring/selling party and serial number/engines number.

**Before the award of Contract, the Project Manager may carry out physical verification of the availability of the plant and equipment
listed on the schedule

74
2 (IV) TENDER QUESTIONNAIRE

Please fill in BLOCK LETTERS.

1. Full names of Tenderer [Name of the Firm]


………………………………………………………………………………………
………………………………………………………………………………………

2. Full address of Tenderer to which tender correspondence is to be sent (unless an agent has
been appointed below)
………………………………………………………………………………………
………………………………………………………………………………………
……………………………………………………………………………………….

3. Telephone/Cellphone number (s) of Tenderer

………………………………………………………………………………………
………………………………………………………………………………………
4. Telex/Fax address of Tenderer

………………………………………………………………………………………
………………………………………………………………………………………
5. Name of Tenderer’s Representative to be contacted on matters of the Tender during the
tender period

………………………………………………………………………………………
6. Details of tenderer’s nominated agent (if any) to receive tender notices. This is essential if
the tenderer does not have his registered address in Kenya (name, address, telephone, telex)
………………………………………………………………………………………

………………………………………………………………………………………

_______________________
Signature of Tenderer

Make copy and deliver to:____________________________________________


(Name of Employer)

75
(V) CONFIDENTIAL BUSINESS QUESTIONNAIRE

You are requested to give the particulars indicated in Part 1 and either Part 2(a), 2(b) or 2(c) and
2(d) whichever applies to your type of business.

You are advised that it is a serious offence to give false information on this Form.
Part 1 – General

Business Name ………………………………………………………………………

Location of business premises; Country/Town……………………….

Plot No……………………………………… Street/Road …………………………

Postal Address……………………………… Tel No………………………………..

Nature of Business…………………………………………………………………..

Current Trade Licence No…………………… Expiring date…………………

Maximum value of business which you can handle at any time: K. pound………………………..

Name of your bankers………………………………………………………………

Branch…………………………………………………………………………………
Part 2 (a) – Sole Proprietor

Your name in full…………………………………… Age…………………………

Nationality………………………………… Country of Origin…………………

*Citizenship details …………………………………………………………………

Part 2 (b) – Partnership


Give details of partners as follows:

Name in full Nationality Citizenship Details Shares

1……………………………………………………………………………………

2……………………………………………………………………………………

3……………………………………………………………………………………

Part 2(c) – Registered Company:

Private or public……………………………………………………………

State the nominal and issued capital of the Company-

Nominal Kshs…………………………………………………………………

76
Issued Kshs……………………………………………………………………

Give details of all directors as follows:

Name in full . Nationality. Citizenship Details*. Shares.

1. ………………………………………………………………………………………

2. ………………………………………………………………………………………

3. ………………………………………………………………………………………

4. ………………………………………………………………………………………

Part 2(d) – Interest in the Firm:

Is there any person / persons in …………… ………(Name of Employer) who has interest in
this firm? Yes/No………………………(Delete as necessary)

I certify that the information given above is correct.

……………………… ……………………… …………………


(Title) (Signature) (Date)

• Attach proof of citizenship

77
(VI) SCHEDULE OF PARTICULARS

1. PARTICULARS OF FIRM

Name of Company:

Postal Address:

Physical Address:

Tel. Nos. ……………………………………………………….


Fax No. ……………………………………………………….
E-mail: ……………………………………………………….

Full names of Directors and their citizenship:

Registered Office, address and


Telephone/Cellphone No.

Workshop, Yard, Stores address:

Type of services the Company provides:

Registration with Government Departments:

Name and address of Company’s bankers:

Statements by Company’s bankers on financial


status (attach copy):

Date: ……………………………… Signed: ……………..……………….

78
2. PARTICULARS OF INSURANCE

Sn Type of Insurance Name of Company Registered Address

1 Insurance of Works

2 Plant and Machinery

3 Public Liability

4 Workmen’s Compensation

5 Employer’s Liability

6 Personal Accident

NOTE: Certified photocopies of the relevant insurance policies should


accompany these particulars.
Date: …………………………. Signed: …………………………………..

79
CERTIFICATE OF BIDDER’S VISIT TO SITE

This is to certify that

[Name/s]…………………………………………………………………………………………

……………………………………………………………………………………………………

Being the authorized representative/Agent of [Name of bidder]

………………………………………………………………………………………………………

………………………………………………………………………………………………………

participated in the organised inspection visit of the site of the works for the

held on………………………..day of……………………………20………………..

Signed…………………………………………………………………………………………..
(Employer’s Representative)

……………………………………… …………………………………..
(Name of Employer’s Representative) (Designation

NOTE: This part is to be completed at the


time of the organized site visit.

80
Project
Name:

1. This check list is for Sub-County Engineer to check contractor's work


execution process.

2. Fill in date of checking as (day/month), mark as indicated in Filling Example,


and state remarks.

3. Put this check list in the Monthly Progress Report.

During
before execution
Date Date Date Date Date Date Date Date Date

Item Check Point

/ / / / / / / / /

Works Execution
1 Execution Programme
(including its revised
system in version
1- if any) is submitted
general 1 before the
date specified in
contract
document
Works Execution
Programme
properly reflects the
1- given
2
specifications and site
conditions
Execution procedures
are in
1-
3 accordance with Works
Execution Programme
2 Equipment All equipment used are
holding 2- properly mobilized in
1
accordance with Works
Execution Programme
All equipment used is
well
2-
2 maintained during the
execution of works
Contractor' Qualified technical staff
3 s of
in-house
staff 3- contractor are properly
COUNTY GOVERNMENT OF KISUMU
1 assigned 81
as specified in
Works
Execution Programme
LETTER OF ACCEPTANCE
[Letterhead paper of the Employer]

_______________________[date]

To: _______________________
[name of the Contractor]

_____________________
[address of the Contractor]

Dear Sir,

This is to notify you that your Tender dated ___________________________


for the execution of ________________________________________________
[name of the Contract and identification number,as given in the Tender documents] for the Contract
Price of Kshs. __________________________ [amount in figures][Kenya
Shillings______________________________(amount in words) ] in accordance with the Instructions
to Tenderers is hereby accepted.

You are hereby instructed to proceed with the execution of the said Works in accordance with the
Contract documents.

Authorized Signature …………………………………………………………………

Name and Title of Signatory …………………………………………………………

Attachment : Agreement

COUNTY GOVERNMENT OF KISUMU 82


FORM OF AGREEMENT

THIS AGREEMENT, made the _________________ day of ________ 20 ______


between________________________________________________of [or whose registered office is
situated at]__________________________________________
(hereinafter called “the Employer”) of the one part AND
________________________________________________________of [or whose registered office
is situated at]_________________________________________
(hereinafter called “the Contractor”) of the other part.

WHEREAS THE Employer is desirous that the Contractor executes


________________________________________________________________________
(name and identification number of Contract ) (hereinafter called “the Works”) located
at______________________________[Place/location of the Works]and the Employer has accepted
the tender submitted by the Contractor for the execution and completion of such Works and the
remedying of any defects therein for the Contract Price of
Kshs___________________________[Amount in figures],Kenya
Shillings_____________________________________________[Amount in words].

NOW THIS AGREEMENT WITNESSETH as follows:

1. In this Agreement, words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.

2. The following documents shall be deemed to form and shall be read and construed as part of
this Agreement i.e.

(i) Letter of Acceptance

(ii) Form of Tender

(iii) Conditions of Contract Part I

(iv) Conditions of Contract Part II and Appendix to Conditions of Contract

(v) Specifications

(vi) Drawings

(vii) Priced Bills of Quantities

3. In consideration of the payments to be made by the Employer to


the Contractor as hereinafter mentioned, the Contractor hereby
covenants with the Employer to execute and complete the Works and remedy any defects
therein in conformity in all respects with the provisions of the Contract.

4. The Employer hereby covenants to pay the Contractor in consideration of the execution and
completion of the Works and the remedying of defects therein, the Contract Price or such other

COUNTY GOVERNMENT OF KISUMU 83


sum as may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.

IN WITNESS whereof the parties thereto have caused this Agreement to be executed the day and year
first before written.

The common Seal of _________________________________________________

Was hereunto affixed in the presence of ________________________________

Signed Sealed, and Delivered by the said ______________________________

Binding Signature of Employer ________________________________________

Binding Signature of Contractor _______________________________________

In the presence of (i) Name_______________________________________

Address_____________________________________

Signature___________________________________

[ii] Name _______________________________________

Address_____________________________________

Signature____________________________________

COUNTY GOVERNMENT OF KISUMU 84


FORM OF TENDER SECURITY

WHEREAS ………………………………………..(hereinafter called “the Tenderer”) has submitted


his tender dated ………………………… for the construction of
………………………………………………………………………
…………………… (name of Contract)

KNOW ALL PEOPLE by these presents that WE ……………………… having our registered office
at ………………(hereinafter called “the Bank”), are bound unto
……………………………(hereinafter called “the Employer”) in the sum of
Kshs.……………………… for which payment well and truly to be made to the said Employer, the
Bank binds itself, its successors and assigns by these presents sealed with the Common Seal of the
said Bank this ……………. Day of ………20…………

THE CONDITIONS of this obligation are:

1. If after tender opening the tenderer withdraws his tender during the period of tender validity
specified in the instructions to tenderers
Or

2. If the tenderer, having been notified of the acceptance of his tender by the Employer during the
period of tender validity:

(a) fails or refuses to execute the form of Agreement in accordance with the Instructions to
Tenderers, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the Instructions
to Tenderers;

We undertake to pay to the Employer up to the above amount upon receipt of his first written
demand, without the Employer having to substantiate his demand, provided that in his demand
the Employer will note that the amount claimed by him is due to him, owing to the occurrence
of one or both of the two conditions, specifying the occurred condition or conditions.

This guarantee will remain in force up to and including thirty (30) days after the period of
tender validity, and any demand in respect thereof should reach the Bank not later than the said
date.
___________________________ ______________________________
[date[ [signature of the Bank]

___________________________ ______________________________
[witness] [seal]

COUNTY GOVERNMENT OF KISUMU 85


PERFORMANCE BANK GUARANTEE

To: _________________________(Name of Employer) ___________(Date)


__________________________(Address of Employer)

Dear Sir,

WHEREAS ______________________(hereinafter called “the Contractor”) has undertaken, in


pursuance of Contract No. _____________ dated _________ to execute _______________
(hereinafter called “the Works”);

AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish
you with a Bank Guarantee by a recognised bank for the sum specified therein as security for
compliance with his obligations in accordance with the Contract;

AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:

NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of
the Contractor, up to a total of Kshs. ________________ (amount of Guarantee in figures) Kenya
Shillings__________________________________________ (amount of Guarantee in words), and we
undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums
within the limits of Kenya Shillings _________________________ (amount of Guarantee in words)
as aforesaid without your needing to prove or to show grounds or reasons for your demand for the sum
specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before presenting
us with the demand.

We further agree that no change, addition or other modification of the terms of the Contract or of the
Works to be performed thereunder or of any of the Contract documents which may be made between
you and the Contractor shall in any way release us from any liability under this Guarantee, and we
hereby waive notice of any change, addition, or modification.

This guarantee shall be valid until the date of issue of the Certificate of Completion.

SIGNATURE AND SEAL OF THE GUARANTOR ___________________

Name of Bank ____________________________________________

Address ________________________________________________

Date ______________________________________________________

COUNTY GOVERNMENT OF KISUMU 86


BANK GUARANTEE FOR ADVANCE PAYMENT

To: ________________________ [name of Employer] ___________(Date)


________________________[address of Employer]

Gentlemen,

Ref: _______________________________________________[name of Contract]

In accordance with the provisions of the Conditions of Contract of the above-mentioned Contract,
We,_______________________________________[name and Address of Contractor] (hereinafter
called “the Contractor”) shall deposit with _______________________________[name of Employer]
a bank guarantee to guarantee his proper and faithful performance under the said Contract in an
amount of Kshs._____________[amount of Guarantee in figurers] Kenya
Shillings_____________________________________[amount of Guarantee in words].

We, ________________[bank or financial institution], as instructed by the Contractor, agree


unconditionally and irrevocably to guarantee as primary obligator and not as Surety merely, the
payment to ___________________________[name of Employer] on his first demand without
whatsoever right of objection on our part and without his first claim to the Contractor, in the amount
not exceeding Kshs________________________[amount of Guarantee in figures] Kenya Shillings
_____________________________________________________________[amount of Guarantee in
words], such amount to be reduced periodically by the amounts recovered by you from the proceeds of
the Contract.

We further agree that no change or addition to or other modification of the terms of the Contract or of
the Works to be performed thereunder or of any of the Contract documents which may be made
between ________________________[name of Employer] and the Contractor, shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any such change,
addition or modification.

No drawing may be made by you under this guarantee until we have received notice in writing from
you that an advance payment of the amount listed above has been paid to the Contractor pursuant to
the Contract.

This guarantee shall remain valid and in full effect from the date of the
advance payment under the Contract until
______________________________________________(name of Employer) receives full payment of
the same amount from the Contract.

Yours faithfully,

Signature and Seal __________________________________________________

Name of the Bank or financial institution ______________________________

Address ______________________________________________________________
COUNTY GOVERNMENT OF KISUMU 87
Date _________________________________________________________________

Witness: Name: ____________________________________________________

Address: __________________________________________________

Signature: ________________________________________________

Date: _____________________________________________________

COUNTY GOVERNMENT OF KISUMU 88


STATEMENT OF FOREIGN CURRENCY REQUIREMENTS

(See Clause 23] of the Conditions of Contract)

In the event of our Tender for the execution of____________________


__________________________(name of Contract) being accepted, we would require in
accordance with Clause 21 of the Conditions of Contract, which is attached hereto, the
following percentage:

(Figures)………………………… (Words)…………………………………

of the Contract Sum, (Less Fluctuations) to be paid in foreign currency.

Currency in which foreign exchange element is required:

………………………………………………………………………………………

Date: The ………… Day of …………….. 20…………….

Enter 0% (zero percent) if no payment will be made in foreign currency.

Maximum foreign currency requirement shall be _____________(percent) of the Contract


Sum, less Fluctuations.

_____________________
(Signature of Tenderer)

COUNTY GOVERNMENT OF KISUMU 89


DETAILS OF SUB-CONTRACTORS

If the Tenderer wishes to sublet any portions of the Works under any heading, he must give
below details of the sub-contractors he intends to employ for each portion.

Failure to comply with this requirement may invalidate the tender.

(1) Portion of Works to be sublet: ………………………………

[i) Full name of Sub-contractor


and address of head office: ………………………………

………………………………

(ii) Sub-contractor’s experience


of similar works carried out
in the last 3 years with
Contract value: ………………………………

………………………………

………………………………

(2) Portion of Works to sublet: ………………………………

(i) Full name of sub-contractor


and address of head office: ………………………………

………………………………

………………………………

(ii) Sub-contractor’s experience


of similar works carried out
in the last 3 years with
contract value: ……………………………

……………………………

____________________ _______________________
[Signature of Tenderer) Date

COUNTY GOVERNMENT OF KISUMU 90


LETTER OF NOTIFICATION OF AWARD

For

To:

RE: Tender No: CGK/H&S/19-20/053

Tender Name: PROPOSED CONSTRUCTION OF ARAO OBUNGA DISPENSARY

This is to notify that the contract/s stated below under the above mentioned tender have been awarded
to you.

1. Please acknowledge receipt of this letter of notification signifying your acceptance.

2. The contract/contracts shall be signed by the parties within 30 days of the date of this letter but
not earlier than 14 days from the date of the letter.

3. You may contact the officer(s) whose particulars appear below on the subject matter of this
letter of notification of award.

(FULL PARTICULARS)

For Chief Officer

COUNTY GOVERNMENT OF KISUMU 91


FORM RB 1
REPUBLIC OF KENYA
PUBLIC PROCUREMENT ADMINISTRATIVE REVIEW BOARD
APPLICATION NO…………….OF……….….20……...

BETWEEN …………………………………………….APPLICANT AND

…………………………………RESPONDENT (Procuring Entity)

Request for review of the decision of the…………… (Name of the Procuring Entity) of
……………dated the…day of ………….20……….in the matter of Tender No………..…of
…………..20…
REQUEST FOR REVIEW
I/We……………………………,the above named Applicant(s), of address: Physical
address…………….Fax No……Tel. No……..Email ……………, hereby request the Public
Procurement Administrative Review Board to review the whole/part of the above mentioned decision
on the following grounds , namely:-
1.
2.
etc.
By this memorandum, the Applicant requests the Board for an order/orders that: -
1.
2. etc
SIGNED ……………….(Applicant)
Dated on…………….day of ……………/…20…

FOR OFFICIAL USE ONLY


Lodged with the Secretary Public Procurement Administrative Review Board on ………… day of
………....20….………
SIGNED
Board Secretary

COUNTY GOVERNMENT OF KISUMU 92


COUNTY GOVERNMENT OF KISUMU 93