Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

CGK Spectators Stand at DR - Aloo Gumbi Sec School

Download as pdf or txt
Download as pdf or txt
You are on page 1of 96

REPUBLIC OF KENYA

DEPARTMENT OF PUBLIC WORKS

PROPOSED CONSTRUCTION OF 2NO SPECTATOR STANDS AT DR. ALOO


GUMBI SECONDARY SCHOOL-KISUMU
EAST SUB-COUNTY

SPECIFICATION AND BILLS OF QUANTITIES

FOR

CONSTRUCTION OF 2NO SPECTATOR STANDS

CLIENT
DR.ALOO GUMBI SECONDARY SCHOOL
P.O BOX
KISUMU

PROJECT MANAGER
DEPARTMENT OF PUBLIC WORKS
P.O. BOX 821 - 40100
KISUMU

April, 2021
STANDARD TENDER DOCUMENT

FOR

PROCUREMENT OF WORKS

(BUILDING AND ASSOCIATED


CIVIL ENGINEERING WORKS)

1
TABLE OF CONTENTS

PAGE

INTRODUCTION …………………………………………1

SECTION I: INVITATION TO TENDER ……………………………… 2

SECTION II: INSTRUCTIONS TO TENDERERS …………………….. 3 - 14

SECTION III: CONDITIONS OF CONTRACT …………..…………….. 15- 36

SECTION IV: APPENDIX TO CONDITIONS OF


CONTRACT ……………………………………………… 37 - 39

SECTION V: SPECIFICATIONS ……………………………………… 40 - 41

SECTION VI: DRAWINGS ……………………………………………… 42

SECTION VII: BILLS OF QUANTITIES ………………………………. 43 - 46

SECTION VIII: STANDARD FORMS …………………………………… 47 - 66

2
INTRODUCTION

1.1 This standard tender document for procurement of works has been prepared for use by
procuring entities in Kenya in the procurement of works (i.e. Buildings and associated Civil
Engineering Works).

1.2 The following guidelines should be observed when using the document:-
(a) Specific details should be furnished in the Invitation to tender and in the special
conditions of contract (where applicable). The tender document issued to tenderers
should not have blank spaces or options.

(b) The instructions to tenderers and the General Conditions of Contract should remain
unchanged. Any necessary amendments to these parts should be made through Appendix
to instructions to tenderers and special conditions of contract respectively.

1.3
(b) Information contained in the invitation to tender shall conform to the data and information
in the tender documents to enable prospective tenderers to decide whether or not to
participate in the tender and shall indicate any important tender requirements

(c) The invitation to tender shall be as an advertisement in accordance with the regulations or
a letter of invitation addressed to tenderers who have been prequalified following a request
for prequalification.

1.4 The cover of the document shall be modified to include:-

I. Tender number.
II. Tender name.
III. Name of procuring entity.
IV. Delete name and address of PPOA.

3
SECTION I
INVITATION FOR TENDERS

Tender reference No. (……………………………..)

Tender Name (PROPOSED CONSTRUCTION OF 2NO SPECTATOR STANDS AT DR.


ALOO GUMBI SECONDARY SCHOOL-KISUMU
EAST SUB-COUNTY)

1.1 The (KISUMU EAST CDF) invites sealed tenders for the construction of (PROPOSED
CONSTRUCTION OF 2NO SPECTATOR STAND)
1.2 Interested eligible candidates may obtain further information and inspect tender documents
(and additional copies) at, (KISUMU EAST CONSTITUENCY DEVELOPMENT FUND-
KISUMU) during normal working hours.

QUALIFICATION FOR TENDERING

1.1 MANDATORY REQUIREMENTS

1.2 Tenderers MUST include the following information and documents with their Tenders:

a) Certified copy of Certificate of Incorporation,


b) Certified copy of VALID Registration Certificate with the National Construction Authourity in
the classes specified in the tender notice.
c) VAT and PIN registration,
d) A copy of VALID Tax Compliance Certificate from Kenya Revenue Authority (KRA),
e) Bid bond – 2% of the tender sum for general tenders,
f) Certified copy of RECENT CR12 FORM from registrar of companies.
g) Certified copy of Single Business Permit preferably from Kisumu County.
h) Bidders shall SEQUENTIALLY SERIALIZE ALL PAGES for each tender document
submitted failure to which the bidder shall be disqualified.
i) Certified copy of relevant (Small works & Engineering) Certificate of registration for access to
government procurement opportunities (AGPO) from the ministry of National Treasury for
tenders in the special categories.
j) Bid declaration for special category duly signed and stamped
Certification must be by a commissioner for oaths.

Other requirements are as specified in the tender notice and this tender document.
4
1.3 OTHER REQUIREMENTS

As specified in the tender documents covering the following

I. Eligibility.
II. Similar previous experience.
III. Current workload.
IV. Plant and Equipment holding.
V. Professional and technical personnel.
VI. Audited financial statements for the last three years (2015 – 2017) provided. Companies registered
within the last one year should submit certified bank statements for at least twelve months or the
duration of registration
VII. Litigation history or Current Sworn Affidavit.

Any form of canvassing will lead to automatic disqualification.


The complete set of tender documents may be downloaded from the County’s website ie Completed Tender
Documents are to be enclosed in plain sealed envelopes marked with Tender name and reference number and
deposited in the Tender Box located at the Main Reception, Kisumu East CDF or to be addressed to The
chief officer department of Roads transport and public works, County Government of Kisumu, P.O Box
2738-40100 Kisumu so as to be received on or before ……………………………….., at ………………..

a) Prices quoted should be net inclusive of all taxes, must be in Kenya shillings and shall remain
valid for 90 days from the closing date of tender.

b) Tenders will be opened immediately thereafter in the presence of the candidates or their
representatives who choose to attend at Kisumu East CDF
c) Late bids will be not be accepted.
________________________________

d) . Tenders must be accompanied by an original tender Security of 2% of the tender sum in form of
a guarantee acceptable under the Public Procurement and Asset Disposal Act, 2015 and Public
Procurement and Disposal Regulations 2006 payable to the County Government of KISUMU.

5
e) Interested eligible candidates may obtain further information and inspect Tender Documents and
the Design Drawings at Kisumu East CDF Office at the Department Procurement Office during
normal working hours.

For:

6
SECTION II

INSTRUCTIONS TO TENDERERS

TABLE OF CONTENTS PAGE

CLAUSE PAGE

1. General …………………………………………………. 4

2. Tender Documents ………………………………… 6-7

3. Preparation of Tenders ………………………………… 7-8

4. Submission of Tenders ………………………………… 10 - 11

5. Tender Opening and Evaluation ……………………… 11 - 13

6. Award of Contract …………………………………………13 - 14

7
INSTRUCTIONS TO TENDERERS.

1. General/Eligibility/Qualifications/Joint venture/Cost of tendering

1.1 The Employer as defined in the Appendix to Conditions of Contract invites tenders for Works
Contract as described in the tender documents. The successful tenderer will be expected to
complete the Works by the Intended Completion Date specified in the tender documents.

1.2 All tenderers shall provide the Qualification Information, a statement that the tenderer
(including all members of a joint venture and subcontractors) is not associated, or has not
been associated in the past, directly or indirectly, with the Consultant or any other entity that
has prepared the design, specifications, and other documents for the project or being proposed
as Project Manager for the Contract. A firm that has been engaged by the Employer to
provide consulting services for the preparation or supervision of the Works, and any of its
affiliates, shall not be eligible to tender.

1.3 All tenderers shall provide in the Form of Tender and Qualification Information, a preliminary
description of the proposed work method and schedule, including drawings and charts, as
necessary.

1.4 In the event that pre-qualification of potential tenderers has been undertaken, only tenders
from pre-qualified tenderers will be considered for award of Contract. These qualified
tenderers should submit with their tenders any information updating their original pre-
qualification applications or, alternatively, confirm in their tenders that the originally
submitted pre-qualification information remains essentially correct as of the date of tender
submission.

1.5 Where no pre-qualification of potential tenderers has been done, all tenderers shall include the
following information and documents with their tenders , unless otherwise stated:

(a) copies of original documents defining the constitution or legal status, place of
registration, and principal place of business; written power of attorney of the signatory
of the tender to commit the tenderer:

(b) total monetary value of construction work performed for each of the last five years:

(c) experience in works of a similar nature and size for each of the last five years, and
details of work under way or contractually committed; and names and addresses of
clients who may be contacted for further information on these contracts;

(d) major items of construction equipment proposed to carry out the Contract and an
undertaking that they will be available for the Contract.

8
(e) qualifications and experience of key site management and technical personnel
proposed for the Contract and an undertaking that they shall be available for the
Contract.

(f) reports on the financial standing of the tenderer, such as profit and loss statements and
auditor’s reports for the past five years;

(g) evidence of adequacy of working capital for this Contract (access to line(s) of credit
and availability of other financial resources);

(h) authority to seek references from the tenderer’s bankers;

(i) information regarding any litigation, current or during the last five years, in which the
tenderer is involved, the parties concerned and disputed amount; and

(j) proposals for subcontracting components of the Works amounting to more than 10
percent of the Contract Price.

1.6 Tenders submitted by a joint venture of two or more firms as partners shall comply with the
following requirements, unless otherwise stated:

(a) the tender shall include all the information listed in clause 1.5
above for each joint venture partner;

(b) the tender shall be signed so as to be legally binding on all


partners;

(c) all partners shall be jointly and severally liable for the execution
of the Contract in accordance with the Contract terms;

(d) one of the partners will be nominated as being in charge,


authorised to incur liabilities, and receive instructions for and on behalf of all partners
of the joint venture; and

(e) the execution of the entire Contract, including payment, shall be


done exclusively with the partner in charge.

1.7 To qualify for award of the Contract, tenderers shall meet the following minimum qualifying
criteria;

(a) annual volume of construction work of at least 2.5 times the estimated annual cashflow for
the Contract;

(b) experience as main contractor in the construction of at least

(c) two works of a nature and complexity equivalent to the Works


over the last 10 years (to comply with this requirement, works cited should be at least 70
percent complete);

9
(d) proposals for the timely acquisition (own, lease, hire, etc.) of the essential equipment
listed as required for the Works;

(e) a Contract manager with at least five years’ experience in works of an equivalent nature
and volume, including no less than three years as Manager; and

(f) liquid assets and/or credit facilities, net of other contractual commitments and exclusive of
any advance payments which may be made under the Contract, of no less than 4 months of
the estimated payment flow under this Contract.

1.8 The figures for each of the partners of a joint venture shall be added together to determine the
tenderer’s compliance with the minimum qualifying criteria of clause 1.7 (a) and (e);
however, for a joint venture to qualify, each of its partners must meet at least 25 percent of
minimum criteria 1.7 (a), (b) and (e) for an individual tenderer, and the partner in charge at
least 40 percent of those minimum criteria. Failure to comply with this requirement will
result in rejection of the joint venture’s tender. Subcontractors’ experience and resources will
not be taken into account in determining the tenderer’s compliance with the qualifying
criteria, unless otherwise stated.

1.9 Each tenderer shall submit only one tender, either individually or as a partner in a joint
venture. A tenderer who submits or participates in more than one tender (other than as a
subcontractor or in cases of alternatives that have been permitted or requested) will cause all
the proposals with the tenderer’s participation to be disqualified.

1.10 The tenderer shall bear all costs associated with the preparation and submission of his tender,
and the Employer will in no case be responsible or liable for those costs.

1.11 The tenderer, at the tenderer’s own responsibility and risk, is encouraged to visit and examine
the Site of the Works and its surroundings, and obtain all information that may be necessary
for preparing the tender and entering into a contract for construction of the Works. The costs
of visiting the Site shall be at the tenderer’s own expense.

1.12 The procuring entity’s employees, committee members, board members and their relative
(spouse and children) are not eligible to participate in the tender.

1.13 The price to be changed for the tender document shall not exceed Kshs.5,000/=

1.14 The procuring entity shall allow the tenderer to review the tender document free of charge
before purchase.

2. Tender Documents

2.1 The complete set of tender documents comprises the documents listed below and any addenda
issued in accordance with Clause 2.4.

(a) These Instructions to Tenderers


(b) Form of Tender and Qualification Information
(c) Conditions of Contract
(d) Appendix to Conditions of Contract
(e) Specifications
10
(f) Drawings
(g) Bills of Quantities
(h) Forms of Securities

2.2 The tenderer shall examine all Instructions, Forms to be filled and Specifications in the tender
documents. Failure to furnish all information required by the tender documents, or
submission of a tender not substantially responsive to the tendering documents in every
respect will be at the tenderer’s risk and may result in rejection of his tender.

2.3 A prospective tenderer making an inquiry relating to the tender documents may notify the
Employer in writing or by cable, telex or facsimile at the address indicated in the letter of
invitation to tender. The Employer will only respond to requests for clarification received
earlier than seven days prior to the deadline for submission of tenders. Copies of the
Employer’s response will be forwarded to all persons issued with tendering documents,
including a description of the inquiry, but without identifying its source.

2.4 Before the deadline for submission of tenders, the Employer may modify the tendering
documents by issuing addenda. Any addendum thus issued shall be part of the tendering
documents and shall be communicated in writing or by cable, telex or facsimile to all
tenderers. Prospective tenderers shall acknowledge receipt of each addendum in writing to the
Employer.
7
2.5 To give prospective tenderers reasonable time in which to take an addendum into account in
preparing their tenders, the Employer shall extend, as necessary, the deadline for submission
of tenders, in accordance with Clause 4.2 here below.

11
3. Preparation of Tenders

3.1 All documents relating to the tender and any correspondence shall be in English language.

3.2 The tender submitted by the tenderer shall comprise the following:

(a) These Instructions to Tenderers, Form of Tender, Conditions of Contract, Appendix to


Conditions of Contract and Specifications;

(b) Tender Security;

(c) Priced Bill of Quantities ;

(d) Qualification Information Form and Documents;

(e) Alternative offers where invited; and

(f) Any other materials required to be completed and submitted by the tenderers.

3.3 The tenderer shall fill in rates and prices for all items of the Works described in the Bill of
Quantities. Items for which no rate or price is entered by the tenderer will not be paid for
when executed and shall be deemed covered by the other rates and prices in the Bill of
Quantities. All duties, taxes, and other levies payable by the Contractor under the Contract, or
for any other cause relevant to the Contract, as of 30 days prior to the deadline for submission
of tenders, shall be included in the tender price submitted by the tenderer.

3.4 The rates and prices quoted by the tenderer shall only be subject to adjustment during the
performance of the Contract if provided for in the Appendix to Conditions of Contract and
provisions made in the Conditions of Contract.

3.5 The unit rates and prices shall be in Kenya Shillings.

3.6 Tenders shall remain valid for a period of sixty (60) days from the date of submission.
However in exceptional circumstances, the Employer may request that the tenderers extend
the period of validity for a specified additional period. The request and the tenderers’
responses shall be made in writing. A tenderer may refuse the request without forfeiting the
Tender Security. A tenderer agreeing to the request will not be required or permitted to
otherwise modify the tender, but will be required to extend the validity of Tender Security for
the period of the extension, and in compliance with Clause 3.7 - 3.11 in all respects.

12
3.7 The tenderer shall furnish, as part of the tender, a Tender Security in the amount and form
specified in the appendix to invitation to tenderers. This shall be in the amount not exceeding
2 percent of the tender price

3.8 The format of the Tender Security should be in accordance with the form of Tender Security
included in Section G - Standard forms or any other form acceptable to the Employer . Tender
Security shall be valid for 30 days beyond the validity of the tender.

3.9 Any tender not accompanied by an acceptable Tender Security shall be rejected. The Tender
Security of a joint venture must define as “Tenderer” all joint venture partners and list them in
the following manner: a joint venture consisting of”…………”,”…………”,and “…………”.

3.10 The Tender Securities of unsuccessful tenderers will be returned within 28 days of the end of
the tender validity period specified in Clause 3.6.

3.11 The Tender Security of the successful tenderer will be discharged when the tenderer has
signed the Contract Agreement and furnished the required Performance Security.

3.12 The Tender Security may be forfeited

(a) if the tenderer withdraws the tender after tender opening during the period of tender
validity;

(b) if the tenderer does not accept the correction of the tender price, pursuant to Clause
5.7;

(c) in the case of a successful tenderer, if the tenderer fails within the specified time limit
to

(i) sign the Agreement, or

(ii) furnish the required Performance Security.

3.13 Tenderers shall submit offers that comply with the requirements of the tendering documents,
including the basic technical design as indicated in the Drawings and Specifications.
Alternatives will not be considered, unless specifically allowed in the invitation to tender. If
so allowed, tenderers wishing to offer technical alternatives to the requirements of the
tendering documents must also submit a tender that complies with the requirements of the
tendering documents, including the basic technical design as indicated in the Drawings and
Specifications. In addition to submitting the basic tender, the tenderer shall provide all
information necessary for a complete evaluation of the alternative, including design
calculations, technical specifications, breakdown of prices, proposed construction methods
and other relevant details. Only the technical alternatives, if any, of
the lowest evaluated tender conforming to the basic technical requirements shall be
considered.

3.14 The tenderer shall prepare one original of the documents comprising the tender documents as
described in Clause 3.2 of these Instructions to Tenderers, bound with the volume containing
the Form of Tender,

13
and clearly marked “ORIGINAL”. In addition, the tenderer shall submit copies of the tender,
in the number specified in the invitation to tender, and clearly marked as “COPIES”. In the
event of discrepancy between them, the original shall prevail.

3.15 The original and all copies of the tender shall be typed or written in indelible ink and shall be
signed by a person or persons duly authorised to sign on behalf of the tenderer, pursuant to
Clause 1.5 (a) or 1.6 (b), as the case may be. All pages of the tender where alterations or
additions have been made shall be initialled by the person or persons signing the tender.

3.16 Clarification of tenders shall be requested by the tenderer to be received by the procuring
entity not later than 7 days prior to the deadline for submission of tenders.

3.17 The procuring entity shall reply to any clarifications sought by the tenderer within 3 days of
receiving the request to enable the tenderer to make timely submission of its tender.

3.18 The tender security shall be in the amount of 0.5 – 2 per cent of the tender price.

4. Submission of Tenders

4.1 The tenderer shall seal the original and all copies of the tender in two inner envelopes and one
outer envelope, duly marking the inner envelopes as “ORIGINAL” and “COPIES” as
appropriate. The inner and outer envelopes shall:
10
(a) be addressed to the Employer at the address provided in the invitation to tender;

(b) bear the name and identification number of the Contract as defined in the invitation to
tender; and

(c) provide a warning not to open before the specified time and date for tender opening.

4.2 Tenders shall be delivered to the Employer at the address specified above not later than the
time and date specified in the invitation to tender. However, the Employer may extend the
deadline for submission of tenders by issuing an amendment in accordance with Sub-Clause
2.5 in which case all rights and obligations of the Employer and the tenderers previously
subject to the original deadline will then be subject to the new deadline.

4.3 Any tender received after the deadline prescribed in clause 4.2 will be returned to the tenderer
un-opened.

4.4 Tenderers may modify or withdraw their tenders by giving notice in writing before the
deadline prescribed in clause 4.2. Each tenderer’s modification or withdrawal notice shall be
prepared, sealed, marked,
and delivered in accordance with clause 3.13 and 4.1, with the outer and inner envelopes
additionally marked “MODIFICATION”and “WITHDRAWAL”, as appropriate. No
tender may be modified after the deadline for submission of tenders.

4.5 Withdrawal of a tender between the deadline for submission of


tenders and the expiration of the period of tender validity specified in the invitation to tender
or as extended pursuant to Clause 3.6 may result in the forfeiture of the Tender Security
pursuant to Clause 3.11.
14
4.6 Tenderers may only offer discounts to, or otherwise modify the prices of their tenders by
submitting tender modifications in accordance with Clause 4.4 or be included in the original
tender submission.

5. Tender Opening and Evaluation

5.1 The tenders will be opened by the Employer, including modifications made pursuant to
Clause 4.4, in the presence of the tenderers’ representatives who choose to attend at the time
and in the place specified in the invitation to tender. Envelopes marked “WITHDRAWAL”
shall be opened and read out first. Tenderers’ and Employer’s representatives who are present
during the opening shall sign a register evidencing their attendance.

5.2 The tenderers’ names, the tender prices, the total amount of each tender and of any alternative
tender (if alternatives have been requested or permitted), any discounts, tender modifications
and withdrawals, the presence or absence of Tender Security, and such other details as may be
considered appropriate, will be announced by the Employer at the opening. Minutes of the
tender opening, including the information disclosed to those present will be prepared by the
Employer.

5.3 Information relating to the examination, clarification, evaluation, and comparison of tenders
and recommendations for the award of Contract shall not be disclosed to tenderers or any
other persons not officially concerned with such process until the award to the successful
tenderer has been announced. Any effort by a tenderer to influence the Employer’s officials,
processing of tenders or award decisions may result in the rejection of his tender.

5.4 To assist in the examination, evaluation, and comparison of tenders, the Employer at his
discretion, may ask any tenderer for clarification of the tender, including breakdowns of unit
rates. The request for clarification and the response shall be in writing or by cable, telex or
facsimile but no change in the price or substance of the tender shall be sought, offered, or
permitted except as required to confirm the correction of arithmetic errors discovered in the
evaluation of the tenders in accordance with Clause 5.7.

5.5 Prior to the detailed evaluation of tenders, the Employer will determine whether each tender
(a) meets the eligibility criteria defined
in Clause 1.7;(b) has been properly signed; (c) is accompanied by the required securities; and
(d) is substantially responsive to the requirements of the tendering documents. A substantially
responsive tender is one which conforms to all the terms, conditions and specifications of the
tendering documents, without material deviation or reservation. A material deviation or
reservation is one (a) which affects in any substantial way the scope, quality, or performance
of the works; (b) which limits in any substantial way, inconsistent with the tendering
documents, the Employer’s rights or the tenderer’s obligations under the Contract; or (c)
whose rectification would affect unfairly the competitive position of other tenderers
presenting substantially responsive tenders.

5.6 If a tender is not substantially responsive, it will be rejected, and may not subsequently be
made responsive by correction or withdrawal of the nonconforming deviation or reservation.

15
5.7 Tenders determined to be substantially responsive will be checked for any arithmetic errors.
Errors will be corrected as follows:

(a) where there is a discrepancy between the amount in figures and the amount in words,
the amount in words will prevail; and

(b) where there is a discrepancy between the unit rate and the line item total resulting from
multiplying the unit rate by the quantity, the unit rate as quoted will prevail, unless in
the opinion of the Employer, there is an obvious typographical error, in which case the
adjustment will be made to the entry containing that error.

(c) In the event of a discrepancy between the tender amount as stated in the Form of
Tender and the corrected tender figure in the main summary of the Bill of Quantities,
the amount as stated in the Form of Tender shall prevail.

(d) The Error Correction Factor shall be computed by expressing the difference between
the tender amount and the corrected tender sum as a percentage of the corrected
Builder’s Work (i.e. Corrected tender sum less P.C. and Provisional Sums)

(e) The Error Correction Factor shall be applied to all Builder’s Work (as a rebate or
addition as the case may be) for the purposes of valuations for Interim Certificates and
valuation of variations.

(f) the amount stated in the tender will be adjusted in accordance with the above
procedure for the correction of errors and, with
concurrence of the tenderer, shall be considered as binding upon the tenderer. If the
tenderer does not accept the corrected amount, the tender may be rejected and the
Tender Security may be forfeited in accordance with clause 3.11.

5.8 The Employer will evaluate and compare only the tenders determined to be substantially
responsive in accordance with Clause 5.5.

5.9 In evaluating the tenders, the Employer will determine for each tender the evaluated tender
price by adjusting the tender price as follows:

(a) making any correction for errors pursuant to clause 5.7;

(b) excluding provisional sums and the provision, if any, for contingencies in the Bill of
Quantities, but including Dayworks where priced competitively.

(c) making an appropriate adjustment for any other acceptable variations, deviations, or
alternative offers submitted in accordance with clause 3.12; and

(d) making appropriate adjustments to reflect discounts or other price modifications


offered in accordance with clause 4.6

5.10 The Employer reserves the right to accept or reject any variation, deviation, or alternative
offer. Variations, deviations, and alternative offers and other factors which are in excess of
the requirements of the tender documents or otherwise result in unsolicited benefits for the
Employer will not be taken into account in tender evaluation.
16
5.11 The tenderer shall not influence the Employer on any matter relating to his tender from the
time of the tender opening to the time the Contract is awarded. Any effort by the Tenderer to
influence the Employer or his employees in his decision on tender evaluation, tender
comparison or Contract award may result in the rejection of the tender.

5.12 Firms incorporated in Kenya where indigenous Kenyans own 51% or more of the share
capital shall be allowed a 10% preferential bias provided that they do not sub-contract work
valued at more than 50% of the Contract Price excluding Provisional Sums to an
non-indigenous sub-contractor.

6. Award of Contract

6.1 Subject to Clause 6.2, the award of the Contract will be made to the tenderer whose tender has
been determined to be substantially
responsive to the tendering documents and who has offered the lowest evaluated tender price,
provided that such tenderer has been determined to be (a) eligible in accordance with the
provision of Clauses 1.2, and (b) qualified in accordance with the provisions of clause 1.7 and
1.8.

6.2 Notwithstanding clause 6.1 above, the Employer reserves the right to
accept or reject any tender, and to cancel the tendering process and reject all tenders, at any
time prior to the award of Contract, without thereby incurring any liability to the affected
tenderer or tenderers or any obligation to inform the affected tenderer or tenderers of the
grounds for the action.

6.3 The tenderer whose tender has been accepted will be notified of the award prior to expiration
of the tender validity period in writing or by cable, telex or facsimile. This notification
(hereinafter and in all Contract documents called the “Letter of Acceptance”) will state the
sum (hereinafter and in all Contract documents called the “Contract Price”)that the Employer
will pay the Contractor in consideration of the execution, completion, and maintenance of the
Works by the Contractor as prescribed by the Contract. At the same time the other tenderers
shall be informed that their tenders have not been successful.

The contract shall be formed on the parties signing the contract.

6.4 The Agreement will incorporate all agreements between the Employer and the successful
tenderer. Within 14 days of receipt the successful tenderer will sign the Agreement and return
it to the Employer.

6.5 Within 21 days after receipt of the Letter of Acceptance, the successful tenderer shall deliver
to the Employer a Performance Security in the amount stipulated in the Appendix to
Conditions of Contract and in the form stipulated in the Tender documents. The Performance
Security shall be in the amount and specified form

6.6 Failure of the successful tenderer to comply with the requirements of clause 6.5 shall
constitute sufficient grounds for cancellation of the award and forfeiture of the Tender
Security.

17
6.7 Upon the furnishing by the successful tenderer of the Performance Security, the Employer
will promptly notify the other tenderers that their tenders have been unsuccessful.

6.8 Preference where allowed in the evaluation of tenders shall not be allowed for contracts not
exceeding one year (12 months)

6.9 The tender evaluation committee shall evaluate the tender within 30 days of the validity
period from the date of opening the tender.

6.10 The parties to the contract shall have it signed within 30 days from the date of notification of
contract award unless there is an administrative review request.

6.11 Contract price variations shall not be allowed for contracts not exceeding one year (12
months)

6.12 Where contract price variation is allowed, the valuation shall not exceed 15% of the original
contract price.

6.13 Price variation request shall be processed by the procuring entity within 30 days of receiving
the request.

6.14 The procuring entity may at any time terminate procurement proceedings before contract
award and shall not be liable to any person for the termination.

6.15 The procuring entity shall give prompt notice of the termination to the tenderers and on
request give its reasons for termination within 14 days of receiving the request from any
tenderer.

6.16 A tenderer who gives false information in the tender document about its qualification or who
refuses to enter into a contract after notification of contract award shall be considered for
debarment from participating in future public procurement.

7. Corrupt and Fraudulent practices

7.1 The procuring entity requires that tenderers observe the highest standards of ethics during
procurement process and execution of contracts. A tenderer shall sign a declaration that he has
not and will not be involved in corrupt and fraudulent practices.

18
Section B

TENDER EVALUATION CRITERIA

CONTENTS

Tender Evaluation Criteria……………………………………………….11-20

Determination of Responsiveness…………………………………………11-16

Detailed Technical Examination…………………………………………16-17

Financial Evaluation………………………………………………………...18-20

Combination of Technical, Tender Sums Comparison and Financial Score…20

19
TENDER EVALUATION CRITERIA

After tender opening, the tenders will be evaluated in 4 Stages, namely:

1. Preliminary Evaluation &Determination of Responsiveness


2. Technical Evaluation
3. Financial Evaluation.
4. Determination of the Most Responsive Bidder.
5. Recommendation

1. PRELIMINARY EVALUATION&
DETERMINATION OF RESPONSIVENESS
This stage of evaluation shall involve examination of the pre-qualification conditions as
set out in the Tender Advertisement Notice or Letter of Invitation to Tender and any other
conditions stated in the bid document.

These conditions may include the following:

a) Certified copy of Certificate of Incorporation,

b) Certified copy of VALID Registration Certificate with the National


Construction Authourity in the classes specified in the tender notice.

c) VAT and PIN registration,

d) A copy of VALID Tax Compliance Certificate from Kenya Revenue


Authority (KRA),

e) Bid bond – 2% of the tender sum,

f) Certified copy of RECENT CR12 FORM from registrar of companies.


g) Certified copy of Single Business Permit preferably from Kisumu
County.

h) Bidders shall sequentially serialize all pages for each tender


document submitted failure to which the bidder shall be disqualified.

Any other conditions included in the advertisement notice/Invitation letter.

Certification must be by a commissioner for oaths.


Note:
The bid security shall be in accordance with clauses 16.1 and 16.2 of Instruction to
Tenderers which states as follows:

20
Clause 16.1 The bidder shall furnish, as part of his bid, a bid security in the amount
shown in the Appendix to instruction to tenderers. The bid security must be in form of a
certified cheque, bank draft, an irrevocable letter of credit or a guarantee from a
reputable Bank/ Insurance approved by PPOA located in the Republic of Kenya

Clause 16.2 of Instruction to Tenderers, “the unconditional Tender surety shall be in


Kenya shillings and be in form of a certified cheque, bank draft, an irrevocable letter of
credit or a guarantee from a reputable Bank/ Insurance approved by PPOA located in the
Republic of Kenya. The format of the surety shall be in accordance with the sample form
included in the tender documents and the tender surety shall be valid for 150 days from
the date of tender opening”.

Clause 26.2 of Instruction to Tenderers: “For the purposes of this clause, a substantially
responsive tender is one which conforms to all terms and condition and specifications of
the tender document without material deviation or reservation and has a valid
Bank/Insurance guarantee”.

The employer may seek further clarification/confirmation if necessary to confirm


authenticity/compliance of any condition of the tender.

The tenderers who do not satisfy any of the above requirements shall be considered
Non-Responsive and their tenders will not be evaluated further

21
2. TECHNICAL EVALUATION
The tender document shall be examined based on clause 4 of the Instruction to
Tenderers which states as follows:

In accordance with clause 4.4 of Instruction to Tenderers, ‘the tenderers shall provide
such evidence of their continued eligibility satisfactory to the Employer as the
Employer shall reasonably request’. The tenderers shall be required to fill the Standards
Forms provided for the purposes of providing the required information. The tenderers
may also attach the required information if they so desire.

The award of points for the STANDARD FORMS considered in this section shall be as
shown below:

PARAMETER MAXIMUM POINTS


I. Form of Tender --------------------------------------------------------------- 1.5
II. Tender Questionnaire - ---------------------------------------------------------2.5
III. Confidential Business Questionnaire ---------------------------------------- 2.5
IV. Key personnel - ------------------------------------------------------------------7.5
V. Contract Completed in the last Five (5) years - -----------------------------7.5
VI. Schedules of on-going projects ------------------------------------------------ 5
VII. Schedules of contractors equipment ----------------------------------------- 5
VIII. Audited Financial Report for the last 3 years------------------------------- 5
IX. Evidence of Financial Resources --------------------------------------------- 5
X. Name, Address and Telephone of Banks (Contractor to provide) ------- 2.5
XI. Litigation History------------------------------------------------------------------ 1
XII. Sanctity of the tender document as in accordance with clause 5 of
instruction to tenderer ----------------------------------------------------------- 5
TOTAL 50

22
The detailed scoring plan shall be as shown in table 1 below: -

TABLE 1:

Ite Description Point Max.


m Scored Point
i Form of Tender 1.5
o Signed and stamped -----------------------------------------------1.5
o Signed but not stamped or vice versa ---------------------------1
o Not signed nor stamped------------- ------------------------------ 0
ii Tender Questionnaire Form 2.5
o Completely filled ---------------------------------------------------2.5
o Partially filled ---- -------------------------------------------------1.5
o Not filled --------------------------------------------------------------0
iii Confidential Business Questionnaire Form. 2.5
o Completely filled ------------------------------------------------- 2.5
o Partially filled ----------------------------------------------------- 1.5
o Not filled ----------------------------------------------------------- 0
iv Key Personnel (Attach evidence) 7.
Director of the firm 2 5
o Holder of degree or diploma in relevant Engineering field------2
o Holder of certificate in relevant Engineering field---------------1.5
o Holder of trade test certificate in relevant Engineering field--- 1
o No relevant certificate -----------------------------------------------0
At least 1No. degree/diploma of key personnel in relevant 2
Engineering field
o With over 10 years relevant experience ------------------------2
o With over 5 years relevant experience ------------------------- 1.5
o With under 5 years relevant experience ------------------------ 0.5
At least 1No certificate holder of key personnel in relevant 1.5
Engineering field
o With over 10 years relevant experience ----------------------- 1.5
o With over 5 years relevant experience ------------------------ 1
o With under 5 years relevant experience ------------------------0.5

23
At least 2No artisan (trade test certificate in relevant Engineering 2
field)
o Artisan with over 10 years relevant experience -------------- 2
o Artisan with under 10 years relevant experience ------------- 1.5
o Non skilled worker with over 10 years relevant experience--0.5
v Contract completed in the last five (5) years (Max of 5 No. Projects) 7.5
[Attach Documentary Evidence]
o Project of similar nature, complexity and magnitude ------7.5
o Project of similar nature but of lower value than the one in
consideration------------------------------------------------------- 4
o No completed project of similar nature ------------------------- 0
vi On-going projects (Max of 5 No. Projects) 5
[Attach Documentary Evidence]
o Project of similar nature, complexity and magnitude ---- 5
o Project of similar nature but of lower value than the one in
consideration –--------------------------------------------------3.5
o No ongoing project of similar nature - -----------------------0
vii Schedule of contractors equipment and transport (proof or evidence 2 5
of ownership)
o Means of transport (Vehicle) -------------------------------- 2
o No means of transport ---------------------------------------- 0

24
For each specific equipment required in the installation of the 3
Work being tendered for.
(Maximum No. of equipment to be considered – 3 No.) ----------- 3
Financial Report 5
viii
Audited financial report (last three (3) years)
o Turn over greater or equal to 5 times the cost of the project ----5
o Turn over greater or equal to 3 times the cost of the project –-- 3
o Turn over greater or equal to the cost of the project ------------ 2
o Turn over below the cost of the project -------------------------- 1
ix Evidence of Financial Resources (cash in hand, lines of credit, 5
over draft facility etc)
o Has financial resources equal or above the cost of the project--
5
o Has financial resources below the cost of the project -------2.5
o Has not indicated sources of financial resources ------------0
x Name, Address and Telephone of Banks (Contractor to provide) 2.5
o Provided ---------------------------------------------------------- 2.5
o Not provided ------------------------------------------------------- 0
xi Litigation History 1
o Provided -------------------------------------------------------------1
o Not Provided --------------------------------------------------------0

xii Sanctity of the Tender Document 5


o Having the document intact
(not tempered with in any way) ------------------------------------5
o Having mutilated or modified the tender document-----------0

TOTAL 50

Any bidder who scores 35 points and above shall be considered for further evaluation.

The Technical Evaluation Score will be carried forward to STAGE 4

25
3. FINANCIAL EVALUATION
The evaluation shall be in two sections
1. Preliminary examinations and
2. Tender sum Comparisons

A) PRELIMINARY EXAMINATIONS

The preliminary examination in the Financial Evaluation shall be in accordance with


clause 26 of Instruction to Tenderers.

The parameter to be considered under this section includes the following:


Arithmetic errors and comparison of rates.

(1) Arithmetic Errors

The bid shall be checked for arithmetic errors based on the rates and the total sums
indicated in the bills of quantities.

Confirmation shall be sought in writing from the tenderers whose tender sums will be
determined to have a significant arithmetic error to their disadvantage, to confirm
whether they stand by their tender sums. The error shall be treated as per clause 27 of
Instructions to Tenderers.

Non-compliance with the above shall lead to automatic disqualification from


furtherevaluation.

Discount if any shall be treated as an error in pursuant to clause 27 of Instructions


toTenderers.

(2) Comparison of rates


The evaluation committee will compare rates from different bidders and note consistency
of rates and front loading. The evaluation committee will judge and make an appropriate
decision giving evidence.

B) TENDER SUMS COMPARISONS

In this section, tender sums will be compared to the average of all sums for bidders who
have qualified from STAGE 3A and score awarded to a maximum of 20 as shown below.

26
1 Preliminary Average

a. The tender sums of various binders, who qualify at STAGE 3A and the engineer's
estimates, shall be reduced by omitting PC sums, provisional sums and
contingency from the respectful amounts. The average of the reduced amounts so
obtained shall be calculated.

b. Any tenderer whose tender percentage deviation is 20% higher or lower than the
average obtained above, will be deemed to be unreasonably high or low and shall
not be included in determining the mean in table 3, their bids will not be evaluated
further. The Engineer's estimate will also be subjected to the same treatment.

The detailed scoring plan shall be as shown in table 2 below: TABLE 3

Item Description Score Max.


score
I o Tender Sums: (The tender sums of bidders, who qualify at STAGE 3A and 20
the engineer's estimates, shall be reduced by omitting PC sums, provisional
sums and contingency from the respectful amounts. The average of the
adjusted tender sums so obtained shall be calculated. The deviation of the
reduced amounts in respect of each bidder from the average shall then be
worked out as a percentage of the average (Rounded off to one (1) decimal
point) and scores allocated as follows :-)

o Deviation of between 0% and 1% ------------------------------------ 20


o Deviation of between 1.1% and 2% ---------------------------------- 18.5
o Deviation of between 2.1% and 3% ----------------------------------- 16.2
o Deviation of between 3.1% and 4% ----------------------------------- 15.5
o Deviation of between 4.1% and 5% ------------------------------------ 14
o Deviation of between 5.1% and 6% ----------------------------------- 12.5
o Deviation of between 6.1% and 7% ------------------------------------- 11
o Deviation of between 7.1% and 8% ----------------------------------- 10.5
o Deviation of between 8.1% and 9% ------------------------------------- 8
o Deviation of between 9.1% and 10% ---------------------------------- 7.5
o Deviation of between 10.1% and 11% ---------------------------------- 6.5
o Deviation of between 11.1% and 12% ---------------------------------- 6.0
o Deviation of between 12.1% and 13% --------------------------------- 4.8
o Deviation of between 13.1% and 14% ---------------------------------- 3.5
o Deviation of between 14.1% and 15% ----------------------------------- 3
o Deviation of between 15.1% and 16% ----------------------------------- 2.5
o Deviation of between 16.1% and 17% ------------------------------------ 1.8
o Deviation of between 17.1% and 18% ---------------------------------- 1.5
o Deviation of between 18.1% and 19% --------------------------------------- 1
o Deviation of between 19.1% and 20% --------------------------------------0.5
o Deviation of 20.1% and above -------------------------------------- 0
TOTAL 20

The Tender sum score will be carried forward to STAGE 4

27
C) FINANCIAL SCORE

The Evaluation Team shall compare the prices offered by the tenderers and the Financial
Scores (Fs) will be determined using the formulae below. The financial score will be
allocated a maximum of 30%.

Fs = 30 x Fm/F

Where: Fs is the Financial Score


Fm is the Lowest Priced Responsive Bidsum
F is the Bid Price under consideration

4. DETERMINATION OF THE MOST RESPONSIVE BIDDER

The evaluation team shall combine Technical Evaluation Score, Tender Sums
Comparison Score and Financial Score as below:

Technical Evaluation Score (TEs) + Tender Sums Comparison Score (TSCs)


+Financial Score (Fs)

FINAL SCORE =TEs + TSCs + Fs


= 50% +20%+30%

5. RECOMMENDATION
The Evaluation Committee shall recommend to the client for award, the
Bidder with highest score from Technical and Financial evaluation.

28
29
SECTION III CONDITIONS OF CONTRACT

Table of Contents
1 Definitions ………………………………………………… 15
2 Interpretation……………………………………………… 17
3 Language and Law ………………………………………… 17
4 Project Manager’s Decisions……………………………… 17
5 Delegation………………………………………………… 18
6 Communications ………………………………………… 18
7 Sub Contracting ………………………………………… 18
8 Other Contractors ……………………………………… 18
9 Personnel ………………………………………………… 18
10 Works……………………………………………………… 19
11 Safety and temporary works ……………………………… 19
12 Discoveries ………………………………………………… 19
13 Work Programme ………………………………………… 19 -20
14 Possession of site ………………………………………… 20
15 Access to site …………………………………………… 20
16 Instructions ……………………………………………… 20
17 Extension or Acceleration of completion date ………… 20
18 Management Meetings ………………………………… 21
19 Early Warning …………………………………………… 21
20 Defects …………………………………………………… 21 - 22
21 Bills of Quantities ………………………………………… 22
22 Variations ………………………………………………… 22- 23
23 Payment certificates, currency of payments and
Advance Payments ……………………………………… 23
24 Compensation events …………………………………… 25 - 27
25 Price Adjustment ………………………………………… 27 - 29
26 Retention ………………………………………………… 29
27 Liquidated Damages……………………………………… 29
28 Securities ………………………………………………… 29
29 Day Works ……………………………………………… 29 - 30
30 Liability and Insurance …………………………………… 30 - 31
31 Completion and taking over ……………………………… 31
32 Final Account …………………………………………… 31

30
33 Termination ……………………………………………… 31 - 32
34 Payment upon termination ………………………………… 32 - 33
35 Release from performance ………………………………… 33
36 Corrupt gifts and payments of commission ………………33 - 34
37 Settlement of Disputes ………………………………………34 - 36

31
CONDITIONS OF CONTRACT

1. Definitions

1.1 In this Contract, except where context otherwise requires, the following terms
shall be interpreted as indicated;

“Bill of Quantities” means the priced and completed Bill of Quantities forming
part of the tender.

“Compensation Events” are those defined in Clause 24 hereunder.

“The Completion Date” means the date of completion of the Works as certified
by the Project Manager, in accordance with Clause 31.

“The Contract” means the agreement entered into between the Employer and the
Contractor as recorded in the Agreement Form and signed by the parties including
all attachments and appendices thereto and all documents incorporated by
reference therein to execute, complete, and maintain the Works,

“The Contractor” refers to the person or corporate body whose tender to carry
out the Works has been accepted by the Employer.

“The Contractor’s Tender”is the completed tendering document submitted by


the Contractor to the Employer.

“The Contract Price” is the price stated in the Letter of Acceptance and
thereafter as adjusted in accordance with the provisions of the Contract.

“Days” are calendar days; “Months” are calendar months.

“A Defect” is any part of the Works not completed in accordance with the
Contract.

“The Defects Liability Certificate” is the certificate issued by Project Manager


upon correction of defects by the Contractor.

“The Defects Liability Period” is the period named in the Contract Data and
calculated from the Completion Date.

“Drawings” include calculations and other information provided or approved by


the Project Manager for the execution of the Contract.

“Dayworks” are Work inputs subject to payment on a time basis for labour and
the associated materials and plant.

“Employer”, or the “Procuring entity” as defined in the Public Procurement


Regulations (i.e. Central or Local Government administration, Universities, Public
Institutions and Corporations, etc) is the party who employs the Contractor to
carry out the Works.

32
“Equipment” is the Contractor’s machinery and vehicles brought temporarily to
the Site for the execution of the Works.

“The Intended Completion Date” is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date may be
revised only by the Project Manager by issuing an extension of time or an
acceleration order.

“Materials” are all supplies, including consumables, used by the Contractor for
incorporation in the Works.

“Plant” is any integral part of the Works that shall have a mechanical, electrical,
chemical, or biological function.

“Project Manager” is the person named in the Appendix to Conditions of


Contract (or any other competent person appointed by the Employer and notified
to the Contractor, to act in replacement of the Project Manager) who is responsible
for supervising the execution of the Works and administering the Contract and
shall be an “Architect” or a “Quantity Surveyor” registered under the Architects
and Quantity Surveyors Act Cap 525 or an “Engineer” registered under Engineers
Registration Act Cap 530.

“Site” is the area defined as such in the Appendix to Condition of Contract.

“Site Investigation Reports” are those reports that may be included in the
tendering documents which are factual and interpretative about the surface and
subsurface conditions at the Site.

“Specifications” means the Specifications of the Works included in the Contract


and any modification or addition made or approved by the Project Manager.

“Start Date” is the latest date when the Contractor shall commence execution of
the Works. It does not necessarily coincide with the Site possession date(s).

“A Subcontractor” is a person or corporate body who has a Contract with the


Contractor to carry out a part of the Work in the Contract, which includes Work
on the Site.

“Temporary works” are works designed, constructed, installed, and removed by


the Contractor which are needed for construction or installation of the Works.

“A Variation” is an instruction given by the Project Manager which varies the Works.

“The Works” are what the Contract requires the Contractor to construct, install, and
turnover to the Employer, as defined in the Appendix to Conditions of Contract.

2. Interpretation

2.1 In interpreting these Conditions of Contract, singular also means plural, male also
means female or neuter, and the other way around. Headings have no
significance. Words have their normal meaning in English Language unless

33
specifically defined. The Project Manager will provide instructions clarifying
queries about these Conditions of Contract.

2.2 If sectional completion is specified in the Appendix to Conditions of Contract,


reference in the Conditions of Contract to the Works, the Completion Date and the
Intended Completion Date apply to any section of the Works (other than
references to the Intended Completion Date for the whole of the Works).

2.3 The following documents shall constitute the Contract documents and shall be
interpreted in the following order of priority;

(1) Agreement,

(2) Letter of Acceptance,

(3) Contractor’s Tender,

(4) Appendix to Conditions of Contract,

(5) Conditions of Contract,

(6) Specifications,

(7) Drawings,

(8) Bill of Quantities,

(9) Any other documents listed in the Appendix to Conditions of Contract as


forming part of the Contract.

Immediately after the execution of the Contract, the Project Manager


shall furnish both the Employer and the Contractor with two copies
each of all the Contract documents. Further, as and when necessary
the Project Manager shall furnish the Contractor [always with a copy
to the Employer] with three [3] copies of such further drawings or
details or descriptive schedules as are reasonably necessary either
to explain or amplify the Contract drawings or to enable the
Contractor to carry out and complete the Works in accordance with
these Conditions.

3. Language and Law

3.1 Language of the Contract and the law governing the Contract shall be English
language and the Laws of Kenya respectively unless
otherwise stated.

4 Project Manager’s Decisions

4.1 Except where otherwise specifically stated, the Project Manager will decide
contractual matters between the Employer and the Contractor in the role
representing the Employer.

34
5 Delegation

5.1 The Project Manager may delegate any of his duties and responsibilities to others
after notifying the Contractor.

6 Communications

6.1 Communication between parties shall be effective only when in writing. A notice
shall be effective only when it is delivered.

7 Subcontracting

7.1 The Contractor may subcontract with the approval of the Project Manager, but
may not assign the Contract without the approval of the Employer in writing.
Subcontracting shall not alter the Contractor’s obligations.

8 Other Contractors

8.1 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities etc. as listed in the Appendix to Conditions of Contract and
also with the Employer, as per the directions of the Project Manager. The
Contractor shall also provide facilities and services for them. The Employer may
modify the said List of Other Contractors etc., and shall notify the Contractor of
any such modification.

9 Personnel

9.1 The Contractor shall employ the key personnel named in the Qualification
Information, to carry out the functions stated in the said Information or other
personnel approved by the Project Manager. The Project Manager will approve
any proposed replacement of key personnel only if their relevant qualifications
and abilities are substantially equal to or better than those of the personnel listed in
the Qualification Information. If the Project Manager asks the Contractor to
remove a person who is a member of the Contractor’s staff or work force, stating
the reasons, the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the Work in the Contract.

10 Works

10.1 The Contractor shall construct and install the Works in accordance with the
Specifications and Drawings. The Works may commence on the Start Date and
shall be carried out in accordance with the Program submitted by the Contractor,
as updated with the approval of the Project Manager, and complete them by the
Intended Completion Date.

35
11 Safety and Temporary Works

11.1 The Contractor shall be responsible for the design of temporary works. However
before erecting the same, he shall submit his designs including specifications and
drawings to the Project Manager and to any other relevant third parties for their
approval. No erection of temporary works shall be done until such approvals are
obtained.

11.2 The Project Manager’s approval shall not alter the Contractor’s responsibility for
design of the Temporary works and all drawings prepared by the Contractor for
the execution of the temporary or permanent Works, shall be subject to prior
approval by the Project Manager before they can be used.

11.3 The Contractor shall be responsible for the safety of all activities on the Site.

12. Discoveries

12.1 Anyth ing of historical or other interest or of significant value unexpectedly


discovered on Site shall be the property of the Employer. The Contractor shall
notify the Project Manager of such discoveries and carry out the Project
Manager’s instructions for dealing with them.

13. Work Program

13.1 Within the time stated in the Appendix to Conditions of Contract, the Contractor
shall submit to the Project Manager for approval a program showing the general
methods, arrangements, order, and timing for all the activities in the Works. An
update of the program shall be a program showing the actual progress achieved on
each activity and the effect of the progress achieved on the timing of the
remaining Work, including any changes to the sequence of the activities.

The Contractor shall submit to the Project Manager for approval an updated
program at intervals no longer than the period stated in the Appendix to
Conditions of Contract. If the Contractor does not submit an updated program
within this period, the Project Manager
may withhold the amount stated in the said Appendix from the next payment
certificate and continue to withhold this amount until the next payment after the
date on which the overdue program has been submitted. The Project Manager’s
approval of the program shall not alter the Contractor’s obligations. The
Contractor may revise the program and submit it to the Project Manager again at
any time. A revised program shall show the effect of Variations and
Compensation Events.

14. Possession of Site

14.1 The Employer shall give possession of all parts of the Site to the Contractor. If
possession of a part is not given by the date stated in the Appendix to Conditions
of Contract , the Employer will be deemed to have delayed the start of the relevant
activities, and this will be a Compensation Event.

36
15. Access to Site

15.1 The Contractor shall allow the Project Manager and any other person authorised
by the Project Manager, access to the Site and to any place where work in
connection with the Contract is being carried out or is intended to be carried out.

16. Instructions

16.1 The Contractor shall carry out all instructions of the Project Manager which are in
accordance with the Contract.

17. Extension or Acceleration of Completion Date

17.1 The Project Manager shall extend the Intended Completion Date if a
Compensation Event occurs or a variation is issued which makes it impossible for
completion to be achieved by the Intended Completion Date without the
Contractor taking steps to accelerate the remaining Work, which would cause the
Contractor to incur additional cost. The Project Manager shall decide whether and
by how much to extend the Intended Completion Date within 21 days of the
Contractor asking the Project Manager in writing for a decision upon the effect of
a Compensation Event or variation and submitting full supporting information. If
the Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay caused by such failure shall not be
considered in assessing the new (extended) Completion Date.

17.2 No bonus for early completion of the Works shall be paid to the Contractor by the
Employer.

18. Management Meetings

18.1 A Contract management meeting shall be held monthly and attended by the
Project Manager and the Contractor. Its business shall be to review the plans for
the remaining Work and to deal with matters raised in accordance with the early
warning procedure. The Project Manager shall record the minutes of management
meetings and provide copies of the same to those attending the meeting and the
Employer. The responsibility of the parties for actions to be taken shall be
decided by the Project Manager either at the management meeting or after the
management meeting and stated in writing to all who attended the meeting.

19. Early Warning

19.1 The Contractor shall warn the Project Manager at the earliest opportunity of
specific likely future events or circumstances that may adversely affect the quality
of the Work, increase the Contract Price or delay the execution of the Works. The
Project Manager may require the Contractor to provide an estimate of the expected
effect of the future event or circumstance on the Contract Price and Completion
Date. The estimate shall be provided by the Contractor as soon as reasonably
possible.

37
19.2 The Contractor shall cooperate with the Project Manager in making and
considering proposals on how the effect of such an event or circumstance can be
avoided or reduced by anyone involved in the Work and in carrying out any
resulting instructions of the Project Manager.

20. Defects

20.1 The Project Manager shall inspect the Contractor’s work and notify the Contractor
of any defects that are found. Such inspection shall not affect the Contractor’s
responsibilities. The Project Manager may instruct the Contractor to search for a
defect and to uncover and test any Work that the Project Manager considers may
have a defect. Should the defect be found, the cost of uncovering and making
good shall be borne by the Contractor, However, if there is no defect found, the
cost of uncovering and making good shall be treated as a variation and added to
the Contract Price.

20.2 The Project Manager shall give notice to the Contractor of any defects
before the end of the Defects Liability Period, which begins at Completion, and is
defined in the Appendix to Conditions of Contract. The Defects Liability Period
shall be extended for as long as defects remain to be corrected.

20.3 Every time notice of a defect is given, the Contractor shall correct the notified
defect within the length of time specified by the Project Manager’s notice. If the
Contractor has not corrected a defect within the time specified in the Project
Manager’s notice, the Project Manager will assess the cost of having the defect
corrected by other parties and such cost shall be treated as a variation and be
deducted from the Contract Price.

21. Bills Of Quantities

21.1 The Bills of Quantities shall contain items for the construction, installation, testing
and commissioning of the Work to be done by the Contractor. The Contractor
will be paid for the quantity of the Work done at the rate in the Bills of Quantities
for each item.

21.2 If the final quantity of the Work done differs from the quantity in the Bills of
Quantities for the particular item by more than 25 percent and provided the
change exceeds 1 percent of the Initial Contract price, the Project Manager shall
adjust the rate to allow for the change.

21.3 If requested by the Project Manager, the Contractor shall provide the Project
Manager with a detailed cost breakdown of any rate in the Bills of Quantities.

22. Variations

22.1 All variations shall be included in updated programs produced by the Contractor.

22.2 The Contractor shall provide the Project Manager with a quotation for carrying out
the variations when requested to do so. The Project Manager shall assess the
quotation, which shall be given within seven days of the request or within any

38
longer period as may be stated by the Project Manager and before the Variation is
ordered.

22.3 If the work in the variation corresponds with an item description in the Bills of
Quantities and if in the opinion of the Project Manager, the quantity of work is not
above the limit stated in Clause 21.2 or the timing of its execution does not cause
the cost per unit of quantity to change, the rate in the Bills of Quantities shall be
used to calculate the value of the variation. If the cost per unit of quantity
changes, or
if the nature or timing of the work in the variation does not correspond with items
in the Bills of Quantities, the quotation by the Contractor shall be in the form of
new rates for the relevant items of Work.

22.4 If the Contractor’s quotation is unreasonable, the Project Manager may order the
variation and make a change to the Contract price, which shall be based on the
Project Manager’s own forecast of the effects of the variation on the Contractor’s
costs.

22.5 If the Project Manager decides that the urgency of varying the Work would
prevent a quotation being given and considered without delaying the Work, no
quotation shall be given and the variation shall be treated as a Compensation
Event.

22.6 The Contractor shall not be entitled to additional payment for costs that could
have been avoided by giving early warning.

22.7 When the Program is updated, the Contractor shall provide the Project Manager
with an updated cash flow forecast.

22.8

23. Payment Certificates, Currency of Payments and Advance Payments

23.1 The Contractor shall submit to the Project Manager monthly applications for
payment giving sufficient details of the Work done and materials on Site and the
amounts which the Contractor considers himself to be entitled to. The Project
Manager shall check the monthly application and certify the amount to be paid to
the Contractor within 14 days. The value of Work executed and payable shall be
determined by the Project Manager.

23.2 The value of Work executed shall comprise the value of the quantities of the items
in the Bills of Quantities completed, materials delivered on Site, variations and
compensation events. Such materials shall become the property of the Employer
once the Employer has paid the Contractor for their value . Thereafter, they shall
not be removed from Site without the Project Manager’s instructions except for
use upon the Works.

23.3 Payments shall be adjusted for deductions for retention. The Employer shall pay
the Contractor the amounts certified by the Project Manager within 30 days of the
date of issue of each certificate. If the Employer makes a late payment, the
Contractor shall be paid simple interest on the late payment in the next payment.
Interest shall be calculated on the basis of number of days delayed at a rate three

39
percentage points above the Central Bank of Kenya’s average rate for base
lending prevailing as of the first day the payment becomes overdue.

23.4 If an amount certified is increased in a later certificate or as a result of an award


by an Arbitrator, the Contractor shall be paid interest upon the delayed payment as
set out in this clause. Interest shall be calculated from the date upon which the
increased amount would have been certified in the absence of dispute.

23.5 Items of the Works for which no rate or price has been entered in will not be paid
for by the Employer and shall be deemed covered by other rates and prices in the
Contract.

23.6 The Contract Price shall be stated in Kenya Shillings. All payments to the
Contractor shall be made in Kenya Shillings and foreign currency in the
proportion indicated in the tender, or agreed prior to the execution of the Contract
Agreement and indicated therein. The rate of exchange for the calculation of the
amount of foreign currency payment shall be the rate of exchange indicated in the
Appendix to Conditions of Contract. If the Contractor indicated foreign
currencies for payment other than the currencies of the countries of origin of
related goods and services the Employer reserves the right to pay the equivalent at
the time of payment in the currencies of the countries of such goods and services.
The Employer and the Project Manager shall be notified promptly by the
Contractor of an changes in the expected foreign currency requirements of the
Contractor during the execution of the Works as indicated in the Schedule of
Foreign Currency Requirements and the foreign and local currency portions of the
balance of the Contract Price shall then be amended by agreement between
Employer and the Contractor in order to reflect appropriately such changes.

23.7 In the event that an advance payment is granted, the following shall apply:-

a) On signature of the Contract, the Contractor shall at his request, and


without furnishing proof of expenditure, be entitled to an advance of 10%
(ten percent) of the original amount of the Contract. The advance shall not
be subject to retention money.

b) No advance payment may be made before the Contractor has submitted


proof of the establishment of deposit or a directly
liable guarantee satisfactory to the Employer in the amount of the advance
payment. The guarantee shall be in the same currency as the advance.

c) Reimbursement of the lump sum advance shall be made by deductions


from the Interim payments and where applicable from the balance owing
to the Contractor. Reimbursement shall begin when the amount of the
sums due under the Contract reaches 20% of the original amount of the
Contract. It shall have been completed by the time 80% of this amount is
reached.

40
The amount to be repaid by way of successive deductions shall be calculated by means of
the formula:

R = A(x1 – x11)
80 – 20
Where:

R = the amount to be reimbursed

A = the amount of the advance which has been granted

X1 = the amount of proposed cumulative payments as a


percentage of the original amount of the Contract. This
figure will exceed 20% but not exceed 80%.

X11 = the amount of the previous cumulative payments as a


percentage of the original amount of the Contract. This
figure will be below 80%but not less than 20%.

d) with each reimbursement the counterpart of the directly liable guarantee


may be reduced accordingly.

24. Compensation Events

24.1 The following issues shall constitute Compensation Events:

(a) The Employer does not give access to a part of the Site by the Site
Possession Date stated in the Appendix to Conditions of Contract.

(b) The Employer modifies the List of Other Contractors, etc., in a way that
affects the Work of the Contractor under the Contract.

(c) The Project Manager orders a delay or does not issue drawings,
specifications or instructions required for execution of the Works on time.

(d) The Project Manager instructs the Contractor to uncover or to carry out
additional tests upon the Work, which is then found to have no defects.

(e) The Project Manager unreasonably does not approve a subcontract to be


let.

(f) Ground conditions are substantially more adverse than could reasonably
have been assumed before issuance of the Letter of Acceptance from the
information issued to tenderers (including the Site investigation reports),
from information available publicly and from a visual inspection of the
Site.

(g) The Project Manager gives an instruction for dealing with an unforeseen
condition, caused by the Employer or additional work required for safety
or other reasons.

41
(h) Other contractors, public authorities, utilities, or the Employer does not
work within the dates and other constraints stated in the Contract, and they
cause delay or extra cost to the Contractor.

(i) The effects on the Contractor of any of the Employer’s risks.

(j) The Project Manager unreasonably delays issuing a Certificate of


Completion.

(k) Other compensation events described in the Contract or determined by the


Project Manager shall apply.

24.2 If a compensation event would cause additional cost or would prevent the Work
being completed before the Intended Completion Date, the Contract Price shall be
increased and/or the Intended Completion Date shall be extended. The Project
Manager shall decide whether and by how much the Contract Price shall be
increased and whether and by how much the Intended Completion Date shall be
extended.

24.3 As soon as information demonstrating the effect of each compensation event upon
the Contractor’s forecast cost has been provided by the Contractor, it shall be
assessed by the Project Manager, and the Contract Price shall be adjusted
accordingly. If the Contractor’s forecast is deemed unreasonable, the Project
Manager shall adjust the Contract Price based on the Project Manager’s own
forecast. The
Project Manager will assume that the Contractor will react competently and
promptly to the event.

24.4 The Contractor shall not be entitled to compensation to the extent that the
Employer’s interests are adversely affected by the Contractor not having given
early warning or not having co-operated with the Project Manager.

24.5 Prices shall be adjusted for fluctuations in the cost of inputs only if provided for in
the Appendix to Conditions of Contract.

24.6 The Contractor shall give written notice to the Project Manager of his intention to
make a claim within thirty days after the event giving rise to the claim has first
arisen. The claim shall be submitted within thirty days thereafter.

Provided always that should the event giving rise to the claim of continuing effect,
the Contractor shall submit an interim claim within the said thirty days and a final
claim within thirty days of the end of the event giving rise to the claim.

25. Price Adjustment

25.1 The Project Manager shall adjust the Contract Price if taxes, duties and other
levies are changed between the date 30 days before the submission of tenders for
the Contract and the date of Completion. The adjustment shall be the change in
the amount of tax payable by the Contractor.

25.2 The Contract Price shall be deemed to be based on exchange rates current at the
date of tender submission in calculating the cost to the Contractor of materials to

42
be specifically imported (by express provisions in the Contract Bills of Quantities
or Specifications) for permanent incorporation in the Works. Unless otherwise
stated in the Contract, if at any time during the period of the Contract exchange
rates shall be varied and this shall affect the cost to the Contractor of such
materials, then the Project Manager shall assess the net difference in the cost of
such materials. Any amount from time to time so assessed shall be added to or
deducted from the Contract Price, as the case may be.

25.3 Unless otherwise stated in the Contract, the Contract Price shall be deemed to
have been calculated in the manner set out below and in sub-clauses 25.4 and 25.5
and shall be subject to adjustment in the events specified thereunder;

(i) The prices contained in the Contract Bills of Quantities shall be deemed to
be based upon the rates of wages and other
emoluments and expenses as determined by the Joint Building Council of
Kenya (J.B.C.) and set out in the schedule of basic rates issued 30 days
before the date for submission of tenders.A copy of the schedule used by
the Contractor in his pricing shall be attached in the Appendix to
Conditions of Contract.

(ii) Upon J.B.C. determining that any of the said rates of wages or other
emoluments and expenses are increased or decreased, then the Contract
Price shall be increased or decreased by the amount assessed by the Project
Manager based upon the difference, expressed as a percentage, between
the rate set out
in the schedule of basic rates issued 30 days before the date for submission
of tenders and the rate published by the J.B.C. and applied to the quantum
of labour incorporated within the amount of Work remaining to be
executed at the date of publication of such increase or decrease.

(iii) No adjustment shall be made in respect of changes in the rates of wages


and other emoluments and expenses which occur after the date of
Completion except during such other period as may be granted as an
extension of time under clause 17.0 of these Conditions.

25.4 The prices contained in the Contract Bills of Quantities shall be deemed to be
based upon the basic prices of materials to be permanently incorporated in the
Works as determined by the J.B.C. and set out in the schedule of basic rates issued
30 days before the date for submission of tenders. A copy of the schedule used by
the Contractor in his pricing shall be attached in the Appendix to Conditions of
Contract.

25.5 Upon the J.B.C. determining that any of the said basic prices are increased or
decreased then the Contract Price shall be increased or decreased by the amount to
be assessed by the Project Manager based upon the difference between the price
set out in the schedule of basic rates issued 30 days before the date for submission
of tenders and the rate published by the J.B.C. and applied to the quantum of the
relevant materials which have not been taken into account in arriving at the
amount of any interim certificate under clause 23 of these Conditions issued
before the date of publication of such increase or decrease.

43
25.6 No adjustment shall be made in respect of changes in basic prices of materials
which occur after the date for Completion except during such other period as may
be granted as an extension of time under clause 17.0 of these Conditions.

25.7 The provisions of sub-clause 25.1 to 25.2 herein shall not apply in respect of any
materials included in the schedule of basic rates.

26. Retention

26.1 The Employer shall retain from each payment due to the Contractor the proportion
stated in the Appendix to Conditions of Contract until Completion of the whole of
the Works. On Completion of the whole of the Works, half the total amount
retained shall be repaid to the Contractor and the remaining half when the Defects
Liability Period has passed and the Project Manager has certified that all defects
notified to the Contractor before the end of this period have been corrected.

27. Liquidated Damages

27.1 The Contractor shall pay liquidated damages to the Employer at the rate stated in
the Appendix to Conditions of Contract for each day that the actual Completion
Date is later than the Intended Completion Date. The Employer may deduct
liquidated damages from payments due to the Contractor. Payment of liquidated
damages shall not alter the Contractor’s liabilities.

27.2 If the Intended Completion Date is extended after liquidated damages have been
paid, the Project Manager shall correct any overpayment of liquidated damages by
the Contractor by adjusting the next payment certificate. The Contractor shall be
paid interest on the overpayment, calculated from the date of payment to the date
of repayment, at the rate specified in Clause 23.30

28. Securities

28.1 The Performance Security shall be provided to the Employer no later than the date
specified in the Letter of Acceptance and shall be issued in an amount and form
and by a reputable bank acceptable to the Employer, and denominated in Kenya
Shillings. The Performance Security shall be valid until a date 30 days beyond the
date of issue of the Certificate of Completion.

29. Dayworks

29.1 If applicable, the Dayworks rates in the Contractor’s tender shall be used for small
additional amounts of Work only when the Project Manager has given written
instructions in advance for additional work to be paid for in that way.

44
29.2 All work to be paid for as Dayworks shall be recorded by the Contractor on Forms
approved by the Project Manager. Each completed form shall be verified and
signed by the Project Manager within two days of the Work being done.

29.3 The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks
forms.

30. Liability and Insurance

30.1 From the Start Date until the Defects Correction Certificate has been issued, the
following are the Employer’s risks:

(a) The risk of personal injury, death or loss of or damage to property


(excluding the Works, Plant, Materials and Equipment), which are due to;

(i) use or occupation of the Site by the Works or for the purpose of the
Works, which is the unavoidable result of the Works, or

(ii) negligence, breach of statutory duty or interference with any legal


right by the Employer or by any person employed by or contracted
to him except the Contractor.

(b) The risk of damage to the Works, Plant, Materials, and Equipment to the
extent that it is due to a fault of the Employer or in Employer’s design, or
due to war or radioactive contamination directly affecting the place where
the Works are being executed.

30.2 From the Completion Date until the Defects Correction Certificate has been
issued, the risk of loss of or damage to the Works, Plant, and Materials is the
Employer’s risk except loss or damage due to;

(a) a defect which existed on or before the Completion Date.

(b) an event occurring before the Completion Date, which was not itself the
Employer’s risk

(c) the activities of the Contractor on the Site after the Completion Date.

30.3 From the Start Date until the Defects Correction Certificate has been issued, the
risks of personal injury, death and loss of or damage to property (including,
without limitation, the Works, Plant, Materials, and Equipment) which are not
Employer’s risk are Contractor’s risks.

The Contractor shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start Date to the end of the Defects Liability
Period, in the amounts stated in the Appendix to Conditions of Contract for the
following events;
(a) loss of or damage to the Works, Plant, and Materials;
(b) loss of or damage to Equipment;
(c) loss of or damage to property (except the Works, Plant, Materials, and
Equipment) in connection with the Contract, and
(d) personal injury or death.

45
30.4 Policies and certificates for insurance shall be delivered by the Contractor to the
Project Manager for the Project Manager’s approval before the Start Date. All
such insurance shall provide for compensation required to rectify the loss or
damage incurred.

30.5 If the Contractor does not provide any of the policies and certificates required, the
Employer may effect the insurance which the Contractor should have provided
and recover the premiums from payments otherwise due to the Contractor or, if no
payment is due, the payment of the premiums shall be a debt due.

30.6 Alterations to the terms of an insurance shall not be made without the approval of
the Project Manager. Both parties shall comply with any conditions of insurance
policies.

31. Completion and taking over

31.1 Upon deciding that the Works are complete, the Contractor shall issue a written
request to the Project Manager to issue a Certificate of Completion of the Works.
The Employer shall take over the Site and the Works within seven [7] days of the
Project Manager’s issuing a Certificate of Completion.

32. Final Account

32.1 The Contractor shall issue the Project Manager with a detailed account of the total
amount that the Contractor considers payable to him by the Employer under the
Contract before the end of the Defects Liability Period. The Project Manager shall
issue a Defects Liability Certificate and certify any final payment that is due to the
Contractor within 30 days of receiving the Contractor’s account if it is correct and
complete. If it is not, the Project Manager shall issue within 30 days a schedule
that states the scope of the corrections or additions that are necessary. If the final
account is still unsatisfactory after it has been resubmitted, the Project Manager
shall decide on the amount payable to the Contractor and issue a Payment
Certificate. The Employer shall pay the Contractor the amount due in the Final
Certificate within 60 days.

33. Termination

33.1 The Employer or the Contractor may terminate the Contract if the other party
causes a fundamental breach of the Contract. These

fundamental breaches of Contract shall include, but shall not be limited to, the
following;

(a) the Contractor stops work for 30 days when no stoppage of work is shown
on the current program and the stoppage has not been authorised by the
Project Manager;

(b) the Project Manager instructs the Contractor to delay the progress of the
Works, and the instruction is not withdrawn within 30 days;

46
(c) the Contractor is declared bankrupt or goes into liquidation other than for a
reconstruction or amalgamation;

(d) a payment certified by the Project Manager is not paid by the Employer to
the Contractor within 30 days (for Interim Certificate) or 60 days (for Final
Certificate)of issue.

(e) the Project Manager gives notice that failure to correct a particular defect
is a fundamental breach of Contract and the Contractor fails to correct it
within a reasonable period of time determined by the Project Manager;

(f) the Contractor does not maintain a security, which is required.

33.2 When either party to the Contract gives notice of a breach of Contract to the
Project Manager for a cause other than those listed under Clause 33.1 above, the
Project Manager shall decide whether the breach is fundamental or not.

33.3 Notwithstanding the above, the Employer may terminate the Contract for
convenience.

33.4 If the Contract is terminated, the Contractor shall stop work immediately, make
the Site safe and secure, and leave the Site as soon as reasonably possible. The
Project Manager shall immediately thereafter arrange for a meeting for the
purpose of taking record of the Works executed and materials, goods, equipment
and temporary buildings on Site.

34. Payment Upon Termination

34.1 If the Contract is terminated because of a fundamental breach of Contract by the


Contractor, the Project Manager shall issue a certificate for the value of the Work
done and materials ordered and delivered to Site up to the date of the issue of the
certificate. Additional liquidated damages shall not apply. If the total amount due
to the Employer exceeds any payment due to the Contractor, the difference shall
be a debt payable by the Contractor.

34.2 If the Contract is terminated for the Employer’s convenience or because of a


fundamental breach of Contract by the Employer, the Project Manager shall issue
a certificate for the value of the Work done, materials ordered, the reasonable cost
of removal of equipment, repatriation of the Contractor’s personnel employed
solely on the
Works, and the Contractor’s costs of protecting and securing the Works.

34.3 The Employer may employ and pay other persons to carry out and complete the
Works and to rectify any defects and may enter upon the Works and use all
materials on the Site, plant, equipment and temporary works.

34.4 The Contractor shall, during the execution or after the completion of the Works
under this clause remove from the Site as and when required, within such
reasonable time as the Project Manager may in writing specify, any temporary
buildings, plant, machinery, appliances, goods or materials belonging to or hired
by him, and in default the Employer may (without being responsible for any loss

47
or damage) remove and sell any such property of the Contractor, holding the
proceeds less all costs incurred to the credit of the Contractor.
Until after completion of the Works under this clause the Employer shall not be
bound by any other provision of this Contract to make any payment to the
Contractor, but upon such completion as aforesaid and the verification within a
reasonable time of the accounts therefore the Project Manager shall certify the
amount of expenses properly incurred by the Employer and, if such amount added
to the money paid to the Contractor before such determination exceeds the total
amount which would have been payable on due completion in accordance with
this Contract the difference shall be a debt payable to the Employer by the
Contractor; and if the said amount added to the said money be less than the said
total amount, the difference shall be a debt payable by the Employer to the
Contractor.

35. Release from Performance

35.1 If the Contract is frustrated by the outbreak of war or by any other event entirely
outside the control of either the Employer or the Contractor, the Project Manager
shall certify that the Contract has been frustrated. The Contractor shall make the
Site safe and stop Work as quickly as possible after receiving this certificate and
shall be paid for all Work carried out before receiving it.

36. Corrupt gifts and payments of commission

The Contractor shall not;

(a) Offer or give or agree to give to any person in the service of the

Employer any gift or consideration of any kind as an inducement or reward for


doing or forbearing to do or for having done or forborne to do any act in relation
to the obtaining or execution of this or any other Contract for the Employer or for
showing or forbearing to show favour
or disfavour to any person in relation to this or any other contract for the
Employer.

(b) Enter into this or any other contract with the Employer in connection with which
commission has been paid or agreed to be paid by him or on his behalf or to his
knowledge, unless before the Contract is made particulars of any such commission
and of the terms and conditions of any agreement for the payment thereof have
been disclosed in writing to the Employer.

Any breach of this Condition by the Contractor or by anyone employed by him or


acting on his behalf (whether with or without the knowledge of the Contractor)
shall be an offence under the provisions of the Public Procurement Regulations
issued under The Exchequer and Audit Act Cap 412 of the Laws of Kenya.

37. Settlement Of Disputes

37.1 In case any dispute or difference shall arise between the Employer or the Project
Manager on his behalf and the Contractor, either during the progress or after the
completion or termination of the Works, such dispute shall be notified in writing
by either party to the other with a request to submit it to arbitration and to concur

48
in the appointment of an Arbitrator within thirty days of the notice. The dispute
shall be referred to the arbitration and final decision of a person to be agreed
between the parties. Failing agreement to concur in the appointment of an
Arbitrator, the Arbitrator shall be appointed by the Chairman or Vice Chairman of
any of the following professional institutions;

(i) Architectural Association of Kenya

(ii) Institute of Quantity Surveyors of Kenya

(iii) Association of Consulting Engineers of Kenya

(iv) Chartered Institute of Arbitrators (Kenya Branch)

(v) Institution of Engineers of Kenya

On the request of the applying party. The institution written to first by the
aggrieved party shall take precedence over all other institutions.

37.2 The arbitration may be on the construction of this Contract or on any matter or
thing of whatsoever nature arising thereunder or in connection therewith,
including any matter or thing left by this Contract to the discretion of the Project
Manager, or the withholding by the Project Manager of any certificate to which
the Contractor may claim to be entitled to or the measurement and valuation
referred to in clause 23.0 of these conditions, or the rights and liabilities of the
parties subsequent to the termination of Contract.

37.3 Provided that no arbitration proceedings shall be commenced on any dispute or


difference where notice of a dispute or difference has not been given by the
applying party within ninety days of the occurrence or discovery of the matter or
issue giving rise to the dispute.

37.4 Notwithstanding the issue of a notice as stated above, the arbitration of such a
dispute or difference shall not commence unless an attempt has in the first
instance been made by the parties to settle such dispute or difference amicably
with or without the assistance of third parties. Proof of such attempt shall be
required.

37.5 Notwithstanding anything stated herein the following matters may be referred to
arbitration before the practical completion of the Works or abandonment of the
Works or termination of the Contract by either party:

37.5.1 The appointment of a replacement Project Manager


upon the said person ceasing to act.

37.5.2 Whether or not the issue of an instruction by the Project


Manager is empowered by these Conditions.

37.5.3 Whether or not a certificate has been improperly withheld


or is not in accordance with these Conditions.

37.5.4 Any dispute or difference arising in respect of war risks or war damage.

49
37.6 All other matters shall only be referred to arbitration after the completion or
alleged completion of the Works or termination or alleged termination of the
Contract, unless the Employer and the Contractor agree otherwise in writing.

37.7 The Arbitrator shall, without prejudice to the generality of his powers, have
powers to direct such measurements, computations, tests or valuations as may in
his opinion be desirable in order to determine the rights of the parties and assess
and award any sums which ought to have been the subject of or included in any
certificate.

37.8 The Arbitrator shall, without prejudice to the generality of his powers,

have powers to open up, review and revise any certificate, opinion, decision,
requirement or notice and to determine all matters in dispute which shall be
submitted to him in the same manner as if no such certificate, opinion, decision
requirement or notice had been given.

37.9 The award of such Arbitrator shall be final and binding upon the parties.

50
SECTION IV – APPENDIX TO CONDITIONS OF CONTRACT

THE EMPLOYER IS

Name: -
_________________________________________________________________________

Address: ______________________________________________________________________

Name of Authorised Representative: ____________________________________________

Telephone: _______________________

Facsimile: ________________________

The Project Manager is

Name:
_________________________________________________________________________

Address:
_______________________________________________________________________

Telephone: _______________________

Facsimile: ________________________

The name (and identification number) of the Contract is _________________________

______________________________________________________________________________
___

The Works consist of____________________________________________________________

______________________________________________________________________________
__

The Start Date shall be _________________________________________________________

The Intended Completion Date for the whole of the Works shall be
______________________________________________________________________________
___

The following documents also form part of the Contract:


______________________________________________________________________________
___

______________________________________________________________________________
___

51
The Contractor shall submit a revised program for the Works within ________ days of delivery
of the Letter of Acceptance.

The Site Possession Date shall be _______________________________________________

The Site is located at __________________________________________________ and is


defined in drawings nos._________________________________________________________

______________________________________________________________________________
__

The Defects Liability period is ________________________ days.

Other Contractors, utilities etc., to be engaged by the Employer on the Site


Include those for the execution of ;

1.____________________________________________

2.______________________________________________

3._____________________________________________

4._____________________________________________

The minimum insurance covers shall be;

1. The minimum cover for insurance of the Works and of Plant and Materials in
respect of the Contractor’s faulty design is____________________

2. The minimum cover for loss or damage to Equipment is____________________

3. The minimum for insurance of other property is____________________________

4. The minimum cover for personal injury or death insurance

 For the Contractor’s employees is___________________________________

 And for other people is______________________________________________

The following events shall also be Compensation Events:

1.
__________________________________________________________________________

2.
__________________________________________________________________________

3.
__________________________________________________________________________

4.
__________________________________________________________________________
52
The period between Program updates is ________________ days.

The amount to be withheld for late submission of an updated Program is ________

______________________________________________________________________________
__

The proportion of payments retained is ______________________ percent.

The Price Adjustment Clause _____________________________ (shall/shall not) apply

The liquidated damages for the whole of the Works is Kshs. _____________(per day)

The Performance Security shall be for the following minimum amounts equivalent as a
percentage of the Contract Price--------------- percent (2%)

The Completion Period for the Works is___________________________[Weeks]

The rate of exchange for calculation of foreign currency payments is ______________________.

The schedule of basic rates used in pricing by the Contractor is as attached [Contractor to
attach].

Advance Payment _____________________________shall/ shall not be granted.

53
SECTION V - SPECIFICATIONS

Notes for preparing Specifications

1.0 Specifications must be drafted to present a clear and


precise statement of the required standards of materials,
and workmanship for tenderers to respond realistically and
competitively to the requirements of the Employer and ensure
responsiveness of tenders. The Specifications should require that
all materials, plant, and other supplies to be permanently
incorporated in the Works be new, unused, of the most recent or
current models, and incorporating all recent improvements in
design and materials unless provided otherwise in the Contract.
Where the Contractor is responsible for the design of any part of
the permanent Works, the extent of his obligations must be stated.

2.0 Specifications from previous similar projects are useful and may
not be necessary to re-write specifications for every Works
Contract.

3.0 There are considerable advantages in standardizing General


Specifications for repetitive Works in recognized public sectors,
such as highways, urban housing, irrigation and water supply. The
General Specifications should cover all classes of workmanship,
materials and equipment commonly involved in constructions,
although not necessarily to be used in a particular works contract.
Deletions or addenda should then adapt the General Specifications
to the particular Works.

4.0 Care must be taken in drafting Specifications to ensure they are not
restrictive. In the Specifications of standards for materials, plant
and workmanship, existing Kenya Standards should be used as
much as possible, otherwise recognized international standards may
also be used.

5.0 The Employer should decide whether technical solutions to


specified parts of the Works are to be permitted. Alternatives are
appropriate in cases where obvious (and potentially less costly)
alternatives are possible to the technical solutions indicated in
tender documents for certain elements of the Works, taking into
consideration the comparative specialized advantage of potential
tenderers.

The Employer should provide a description of the selected parts of


the Works with appropriate reference to Drawings, Specifications,
Bills of Quantities, and Design or Performance criteria, stating that
the alternative solutions shall be at least structurally and
functionally equivalent to the basic design parameters and
Specifications.

54
Such alternative solutions shall be accompanied by all information
necessary for a complete evaluation by the Employer, including
drawings, design calculations, technical specifications, breakdown
of prices, proposed construction methodology, and other relevant
details. Technical alternatives permitted in this manner shall be
considered by the Employer each on its own merits and
independently of whether the tenderer has priced the item as
described in the Employer’s design included with the tender
documents.

55
SECTION VI - DRAWINGS

Note 1. A list of drawings should be inserted here

2. The actual drawings including Site plans should be annexed in a


separate booklet.

56
SECTION VII - BILL OF QUANTITIES

Notes for preparing Bills of Quantities

1.0 The objectives of the Bills of Quantities are;

(a) to provide sufficient information on the quantities of Works to be performed to


enable tenders to be prepared efficiently and accurately; and

(b) when a Contract has been entered into, to provide a priced Bill of Quantities for
use in the periodic valuation of Works executed.

In order to attain these objectives, Works should be itemized in the Bill of


Quantities in sufficient detail to distinguish between the different classes of
Works, or between Works of the same nature carried out in different locations or
in other circumstances which may give rise to different considerations of cost.
Consistent with these requirements, the layout and content of the Bill of Quantities
should be as simple and brief as possible.

2.0 The Bills of Quantities should be divided generally into the following sections:

(a) Preliminaries.

The preliminaries should indicate the inclusiveness of the unit prices, and should
state the methods of measurement which have been adopted in the preparation of
the Bill of Quantities and which are to be used for the measurement of any part of
the Works.

The number of preliminary items to be priced by the tenderer should be limited to


tangible items such as site office and other temporary works, otherwise items such
as security for the Works which are primarily part of the Contractor’s obligations
should be included in the Contractor’s rates.

(b) Work Items

(i) The items in the Bills of Quantities should be grouped into sections to
distinguish between those parts of the Works which by nature, location,
access, timing, or any other special characteristics may give rise to
different methods of construction, or phasing of the Works, or
considerations of cost. General items common to all parts of the Works
may be grouped as a separate section in the Bill of Quantities.

(ii) Quantities should be computed net from the Drawings, unless directed
otherwise in the Contract, and no allowance should be made for bulking,
shrinkage or waste. Quantities should be rounded up or down where
appropriate.

57
(iii) The following units of measurement and abbreviations are recommended
for use.

Unit Abbreviation Unit Abbreviation


cubic meter m3 or cu m millimeter mm
hectare ha month mon
hour h number nr
kilogram kg square meter m2 or sq m
lump sum sum square millimeter mm2 or sq mm
meter m week wk
metric ton (1,000 t
kg)

(iv) The commencing surface should be identified in the description of


each item for Work involving excavation, boring or drilling, for
which the commencing surface is not also the original surface. The
excavated surface should be identified in the description of each
item for Work involving excavation for which the excavated
surface is not also the final surface. The depths of Work should be
measured from the commencing surface to the excavated surface,
as defined.

(c) Daywork Schedule

A Daywork Schedule should be included if the probability of unforeseen work, outside the
items included in the Bill of Quantities, is relatively high. To facilitate checking by the
Employer of the realism of rates quoted by the tenderers, the Daywork Schedule should
normally comprise:

(i) a list of the various classes of labour, and


materials for which basic Day work rates or
prices are to be inserted by the tenderer,
together with a statement of the conditions
under which the Contractor will be paid for
Work executed on a Day work basis; and

(ii) a percentage to be entered by the tenderer against each basic


Day work Subtotal amount for labour, materials and plant
representing the Contractor’s profit, overheads, supervision
and other charges.

58
(d) Provisional Quantities and Sums
(i) Provision for quantity contingencies in any particular
item or class of Work with a high expectation of
quantity overrun should be made by entering specific
“Provisional Quantities” or “Provisional Items” in the
Bill of Quantities, and not by increasing the quantities
for that item or class of Work beyond those of the Work
normally expected to be required. To the extent not
covered above, a general provision for physical
contingencies (quantity overruns) should be made by
including a “Provisional Sum” in the Summary of the
Bill of Quantities. Similarly, a contingency allowance
for possible price increases should be provided as a
“Provisional Sum” in the Summary of the Bill of
Quantities. The inclusion of such provisional sums often
facilitates budgetary approval by avoiding the need to
request periodic supplementary approvals as the future
need arises.

(ii) Provisional sums to cover specialized works normally carried out


by Nominated Sub Contractors should be avoided and instead Bills
of Quantities of the specialised Works should be included as a
section of the main Bills of Quantities to be priced by the Main
Contractor. The Main Contractor should be required to indicate the
name (s) of

the specialised firms he proposes to engage to carry out the specialized


Works as his approved domestic sub-contractors. Only provisional sums
to cover specialized Works by statutory authorities should be included in
the Bills of Quantities.

(e) Summary

The Summary should contain a tabulation of the separate parts of


the Bills of Quantities carried forward, with provisional sums for
Daywork, for physical (quantity) contingencies, and for price
contingencies (upward price adjustment) where applicable.

59
APPENDIX TO CONDITIONS OF CONTRACT

Name of Employer:
KISUMU EAST CONTITUENCY DEVELOPMENT FUND
P.O BOX
KISUMU

Name of Employer’s Representative: THE PUBLIC WORKS, P.O. BOX 2738-40100,


KISUMU

Name of Project Manager: PUBLIC WORKS

The name of Contract is: (PROPOSED CONSTRUCTION OF 2NO SPECTATOR


STANDS AT DR. ALOO GUMBI SECONDARY SCHOOL-KISUMU
EAST SUB-COUNTY)
Tender No: …………………………………..

Scope of the Works: AS PER BILLS OF QUANTITIES IN THIS TENDER


DOCUMENT, AND THE CONTRACT AGREEMENT

The Tender Opening Date and Time will be on


…………………………………………………………at ………. at (KISUMU EAST CDF
OFFICE) The Start Date shall be as stated in the Project Manager’s Notice to commence work.
The Intended Completion period for the whole of the Works shall be ……. from the date of
commencement.
The Site Possession Date shall be the date site is handed over to the Contractor by the Project
Manager. The Site is located at KISUMU COUNTY The Defects Liability Period is 6
MONTHS

Amount of Tender Security is Kshs………………………………………… (2% of the Tender


Price) in the Form of Tender Security or a Banker’s Cheque, from a reputable Commercial Bank,
to the Employer.

The amount of Performance Security is 10% of CONTRACT PRICE in form of a Performance


bank Guarantee, from a reputable Commercial Bank, acceptable to the Employer.

Retention Money will be 0% of the INTERIM CERTIFICATE with a limit of 10% of the
Contract Price or such other sum as shall become payable. SECTION VIII –

Section

STANDARD FORMS

60
(i) Form of Invitation for Tender………………….…. 158
(ii) Form of Tender…………………………….………… 159
(iii) Appendix to form tender……………………………...160
(iii) Qualification Information……………….…………. 161
1. Individual Tenderers………………. 163
2. Joint Ventures……………………… 164
3. Line of Credit……………………………165
4. Declaration form………………………..166
5. Details of Contractor’s Experience… 167
6. Details of Ongoing Projects………… 168
7. Schedule of Key Personnel………… 169
8. Details of Subcontractors………….. 170
9. Schedule of Plants and Equipment..171
(iv) Tender Questionnaire………………………………….. 172
(v) Confidential Business Questionnaire…………. 173-174
(vi) Schedule of Particulars……………………………… …175
1. Particulars of Firm…………………… 175
2. Particulars of Insurance……………. ..177

(vi) Certificate of Bidder’s Pre-site Visit……………………177


(vii) Supervision Check List…………………………………….178

61
(I) FORM OF INVITATION FOR TENDER

_______________________[date]

To: _____________________________________ [name of Contractor]


_____________________________________[address]
_____________________________________
_____________________________________

Dear Sirs:

Reference:______________________________________________[Contract Name]

You have been prequalified to tender for the above project.

We hereby invite you and other prequalified tenderers to submit a tender for the execution and
completion of the above Contract.

A complete set of tender documents may be purchased by you from ____


________________________________________________________________________
[mailing address, cable/telex/facsimile numbers].

Upon payment of a non-refundable fee of Kshs __________________________

All tenders must be accompanied by ________________number of copies of the same and a


security in the form and amount specified in the tendering documents, and must be delivered to
________________________________________________________________________
[address and location]

at or before _______________________(time and date). Tenders will be opened immediately


thereafter, in the presence of tenderers’ representatives who choose to attend.

Please confirm receipt of this letter immediately in writing by cable/facsimile or telex.

Yours faithfully,

_____________________________________ Authorized Signature

_____________________________________ Name and Title

62
(II) FORM OF TENDER
TO: __________________________[Name of Employer) ____________[Date]
__________________________[Name of Contract]

Dear Sir,

1. In accordance with the Conditions of Contract, Specifications, Drawings and Bills of


Quantities for the execution of the above named Works, we, the undersigned offer to
construct, install and complete such Works and remedy any defects therein for the sum of
Kshs._____________________________[Amount in figures]Kenya
Shillings_________________________________________________________________
__________________________[Amount in words]

2. We undertake, if our tender is accepted, to commence the Works as


soon as is reasonably possible after the receipt of the Project Manager’s notice to
commence, and to complete the whole of the Works comprised in the Contract within the
time stated in the Appendix to Conditions of Contract.

3. We agree to abide by this tender until ___________________[Insert date], and it shall


remain binding upon us and may be accepted at any time before that date.

4. Unless and until a formal Agreement is prepared and executed this tender together with your
written acceptance thereof, shall constitute a binding Contract between us.

5. We understand that you are not bound to accept the lowest or any tender you may receive.

Dated this ____________________ day of _________________2017

Signature __________________in the capacity of___________________

duly authorized to sign tenders for and on behalf of

___________________________________________________[Name of Tenderer]

of_________________________________________________[Address of Tenderer]

Witness; Name______________________________________

Address_____________________________________

Signature___________________________________

Date_______________________________________

63
APPENDIX TO FORM OF TENDER

(This Appendix forms part of the Tender)

CONDITIONS OF CONTRACT CLAUSE AMOUNT


Bid Security (Bank Guarantee or Insurance) 2% of the tender sum
Amount of Performance Security 10.1 10%
(Unconditional Bank Guarantee)
Submitted by the 15th day from the date of award
Submission of Performance Security letter

Not later than 14 (fourteen) days after issuance of


Work Programme to be submitted 14.1 Order to Commence

Not later than 14 (fourteen) days after issuance of


Cash flow estimate to be submitted 14.3 Order to Commence

Minimum amount of Contractors All Risk 23.2 0.3% of the Contract Price
Insurance Cover

Submission of Contractors All Risk Insurance Submitted by the 15th day from the date of
Cover award letter
Period for commencement, from Engineer’s order
to commence 41.1 14 days

Time for completion 43.1 12 Weeks


Advance Payment 60.12 N/A
Amount of liquidated damages 47.1 0.1 % of the contract price per day.

Limit of liquidated damages 47.1 5% of Contract Value

Defects Liability period 49.1 6 months


Percentage of Retention 60.3 10% of Interim Payment Certificate

Limit of Retention Money 60.3 10% of Contract Price


Minimum amount of interim certificates 60.2 …………..

The Chartered Institute of Arbitrators – Kenya


Appointer of Arbitrator 67(3) Branch.

Notice to Employer and Engineer 68.2 The Employer’s address is:

Kisumu East Constituency Development Fund


County Government of Kisumu
P.O. Box
KISUMU

The Project Manager’s address is:


Public Works
P.O Box 821
KISUMU

64
Signature of Tenderer………………………………… Date……………………

65
(IV) OTHER SUPPLEMENTARY INFORMATION

1. Financial reports for the last three years, balance sheets, profit and loss statements, auditors’
reports etc. List them below and attach copies.
………………………………………………………………………
………………………………………………………………………

2. Evidence of access to financial resources to meet the qualification requirements. Cash in


hand, lines of credit etc. List below and attach copies of supporting documents (bank to fill
attached form).
………………………………………………………………………
………………………………………………………………………

3. Name, address, telephone, telex, fax numbers of the Tenderer’s Bankers who may provide
reference if contacted by the Employer.
…………………………………………………………………………
…………………………………………………………………………

• Submit copies of audited profit and loss statements and balance sheet for
the last three calendar years and estimated projection for the next two
years with certified English translation where appropriate.

• Give turnover figures for each of the last three (3) financial years. Quote in
millions and decimal thereof.
Type of \Work Year Year Year
Kshs. Kshs. Kshs.
Building works
Other civil engineering works
Other (specify)
Total

SUMMARY OF ASSETS AND LIABILITIES OF THE AUDITED


FINANCIAL STATEMENTS OF THE LAST THREE (3) FINANCIAL
YEARS
Year Year Year
Kshs. Kshs. Kshs.
1. Total Assets
2. Current Assets
3. Bank credit Line Value
4. Total Liabilities
5. Current Liabilities
6. Net worth (1-4)
7. Working capital (2+3-4)

Name/Address of Commercial Bank providing credit line


Total amount of credit line KShs.……………..………………………………

Attach certified copies of financial bank statements of the last three years.
Attach a certified copy of Undertaking of the Bank to providing the credit.

66
Information on current litigation in which the Tenderer is involved.

OTHER PARTY (IES) CAUSE OF DISPUTE AMOUNT INVOLVED (KSHS)

I certify that the above information is correct.

…………………… ……………………… ………………………


Name/Title Signature Date

67
(V) QUALIFICATION INFORMATION

1. Individual Tenderers or Individual Members of Joint Ventures

1.1 Constitution or legal status of tenderer (attach copy or Incorporation Certificate);


Place of registration: ____________________________

Principal place of business _____________________________

Power of attorney of signatory of tender ____________________

1.2 Total annual volume of construction work performed in the last five years
VOLUME
YEAR CURRENCY VALUE

1.3 Work performed as Main Contractor on works of a similar nature and volume over
the last five years. Also list details of work under way or committed, including
expected completion date.

[Fill in the Details as described in the Table attached on Pages S-6 and S-7]

1.4 Major items of Contractor’s Equipment proposed for carrying out the Works. List
all information requested in the table provided.

[Fill in the Details as described in the Table attached on Page S-10]

1.5 Qualifications and experience of key personnel proposed for administration and
execution of the Contract.

[Fill in the Details as described in the Table attached on Page S-8]


1.6 .

__________________________________________________________________
____________________________________________________________

1.7 Statement of compliance with the requirements of Clause 1.2 of the Instructions to
Tenderers.
____________________________________________________________
_____________________________________________

1.8 Proposed program (work method and schedule) for the whole of the Works.
Attached a detailed proposed work plan for the execution of the Works described.

68
2 Joint Ventures

2.4 The information listed in 1.1 – 1.10 above shall be provided for each partner of the
joint venture.

2.5 The information required in 1.11 above shall be provided for the joint venture.

2.6 Attach the power of attorney of the signatory(ies) of the tender authorizing
signature of the tender on behalf of the joint venture

2.7 Attach the Agreement among all partners of the joint venture ( and which is
legally binding on all partners), which shows that:

a) all partners shall be jointly and severally liable for the execution of the
Contract in accordance with the Contract terms;

b) one of the partners will be nominated as being in charge, authorized to


incur liabilities and receive instructions for and on behalf of any and all
partners of the joint venture; and

a) the execution of the entire Contract, including payment, shall be done


exclusively with the partner in charge.

69
1. LETTER OF CREDIT

To:
FUND MANAGER
KISUMU EAST CONSTITUENCY DEVELOPMENT FUND
P.O BOX
KISUMU

RE: LINE OF CREDIT FOR (CONTRACT DETAILS)

Reference is made to inquiry from our Customer ……………………………….. of P.O. Box


……………………………. in regard to line of Credit for financing above tender. We wish to
state as following.

1. M/S ……………………………………………………..(name of tender) has


satisfactorily conducted an account dominated in Kenya Shillings with us for a period of
more than one year.
2. Currently the above named Customer enjoys
1. A Bank Overdraft facility of Kshs …………. …….
2. A bank loan of Kshs ………………………….
3. As per the prudential norms for Financing which MUST be fulfilled by our customer, we
are in a position to provide a line of credit to M/s ……………………………….
(tenderer name) for Kshs ……………

This information is given in strict confidence, and without any guarantee or liability on the part
of the bank or any of its officers.

Yours Faithfully

Bank Authorised Signatory

70
3. DECLARATION FORM

Date
To:
FUND MANAGER
KISUMU EAST CONSTITUENCY DEVELOPMENT FUND
P.O BOX
KISUMU

The tenderer i.e. (name and address)

declare the following:

a) Has not been debarred from participating in public procurement.

b) Has not been involved in and will not be involved in corrupt and fraudulent practices
regarding public procurement.

Name/Title Signature Date

(To be signed by authorized representative and officially stamped)

71
4. DETAILS OF CONTRACTOR’S EXPERIENCE

In the table below, give a brief summary of the Company’s major Road Works carried out and
completed in the last FIVE years. The works listed should be similar to the Works described in this
tender.

DESCRIPTION OF WORKS, TOTAL CONTRACT YEAR


CLIENT AND CONTACT PERSON VALUE OF PERIOD COMPLET
WORKS (YEARS) ED
(KSH.)

Note: Attach relevant documentary evidence.

I certify that the above Road Works were successfully carried out and completed by ourselves.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

72
5. DETAILS OF ONGOING PROJECTS

In the table below, give a brief summary of the Company’s major Road Works that are currently
ongoing. The works listed should be similar to the Works described in this tender.

INTENDED %
DESCRIPTION OF CONTR- DATE OF DATE OF TOTAL COMPLE-
WORKS, CLIENT AND ACT COMMEN- COMPLE- VALUE OF TED TO
CONTACT PERSON PERIOD CEMENT TION WORKS DATE

Note: Attach relevant documentary evidence.

I certify that the above Road Works are being carried out by ourselves and that the above
information concerning them is correct.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

73
6. SCHEDULE OF KEY PERSONNEL

In the table below, give the details of the Tenderer’s Key Technical Personnel who will be
responsible for the major activities of the works described in this tender, both at the Headquarters
and at the Site.

NATIONA-LITY SUMMARY OF
DESIGNATION NAME QUALIFICATIONS AND
EXPERIENCE

Note: Attach the CVs of the Key Personnel.

I certify that the above information is correct.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

74
7. DETAILS OF SUB-CONTRACTORS

If the Tenderer wishes to sublet any portions of the works under any heading, he must give below
the details of the sub-contractors he intends to employ for each portion.

Failure to comply with this requirement may invalidate the tender.

PORTION OF WORKS
FULL NAME AND TO BE SUB- SUB-CONTRACTOR’S
ADDRESS OF THE SUB- CONTRACTED AND EXPERIENCE IN SIMILAR
CONTRACTOR CONTRACT VALUE WORKS

Note: Attach relevant evidence.

I certify that the above information is correct.

……………………… …………………………. …………………………


(Title) (Signature) (Date)

75
1 7. SCHEDULE OF PLANT AND EQUIPMENT

OWNERSHIP
PARTICULARS TYPE/ SERIAL YEAR WHER VALU OWNE TO HIRE PURCHA PRESEN WEEK
OF EACH RATIN NO. & OF E E D HIRE PURCHASESE T WHEN
UNIT G REG. NO. MANUF MADE (Give (Give (Give details(Give LOCATI AVAIL
A- SR. No. name as stated in details as ON ABLE
CTURE and Reg. and the stated in ON
No) address Footnote) the SITE
of Footnote)
Owner)

Note *Details of each machine/equipment in more than one of the same make or type must be given separately. Items to be imported pursuant
to the conditions of contract to be indicated together with seller’s name, address and CIF value. Details of proposed hire or hire purchase
to be submitted giving names and addresses of hiring/selling party and serial number/engines number.

**Before the award of Contract, the Project Manager may carry out physical verification of the availability of the plant and equipment
listed on the schedule

76
2 (IV) TENDER QUESTIONNAIRE

Please fill in BLOCK LETTERS.

1. Full names of Tenderer [Name of the Firm]


………………………………………………………………………………………
………………………………………………………………………………………

2. Full address of Tenderer to which tender correspondence is to be sent (unless an agent has
been appointed below)
………………………………………………………………………………………
………………………………………………………………………………………
……………………………………………………………………………………….

3. Telephone/Cellphone number (s) of Tenderer

………………………………………………………………………………………
………………………………………………………………………………………
4. Telex/Fax address of Tenderer

………………………………………………………………………………………
………………………………………………………………………………………
5. Name of Tenderer’s Representative to be contacted on matters of the Tender during the
tender period

………………………………………………………………………………………
6. Details of tenderer’s nominated agent (if any) to receive tender notices. This is essential if
the tenderer does not have his registered address in Kenya (name, address, telephone, telex)
………………………………………………………………………………………

………………………………………………………………………………………

_______________________
Signature of Tenderer

Make copy and deliver to:____________________________________________


(Name of Employer)

77
(V) CONFIDENTIAL BUSINESS QUESTIONNAIRE

You are requested to give the particulars indicated in Part 1 and either Part 2(a), 2(b) or 2(c) and
2(d) whichever applies to your type of business.

You are advised that it is a serious offence to give false information on this Form.
Part 1 – General

Business Name ………………………………………………………………………

Location of business premises; Country/Town……………………….

Plot No……………………………………… Street/Road …………………………

Postal Address……………………………… Tel No………………………………..

Nature of Business…………………………………………………………………..

Current Trade Licence No…………………… Expiring date…………………

Maximum value of business which you can handle at any time: K. pound………………………..

Name of your bankers………………………………………………………………

Branch…………………………………………………………………………………
Part 2 (a) – Sole Proprietor

Your name in full…………………………………… Age…………………………

Nationality………………………………… Country of Origin…………………

*Citizenship details …………………………………………………………………

Part 2 (b) – Partnership


Give details of partners as follows:

Name in full Nationality Citizenship Details Shares

1……………………………………………………………………………………

2……………………………………………………………………………………

3……………………………………………………………………………………

Part 2(c) – Registered Company:

Private or public……………………………………………………………

State the nominal and issued capital of the Company-

Nominal Kshs…………………………………………………………………

78
Issued Kshs……………………………………………………………………

Give details of all directors as follows:

Name in full . Nationality. Citizenship Details*. Shares.

1. ………………………………………………………………………………………

2. ………………………………………………………………………………………

3. ………………………………………………………………………………………

4. ………………………………………………………………………………………

Part 2(d) – Interest in the Firm:

Is there any person / persons in …………… ………(Name of Employer) who has interest in
this firm? Yes/No………………………(Delete as necessary)

I certify that the information given above is correct.

……………………… ……………………… …………………


(Title) (Signature) (Date)

 Attach proof of citizenship

79
(VI) SCHEDULE OF PARTICULARS

1. PARTICULARS OF FIRM

Name of Company:

Postal Address:

Physical Address:

Tel. Nos. ……………………………………………………….


Fax No. ……………………………………………………….
E-mail: ……………………………………………………….

Full names of Directors and their citizenship:

Registered Office, address and


Telephone/Cellphone No.

Workshop, Yard, Stores address:

Type of services the Company provides:

Registration with Government Departments:

Name and address of Company’s bankers:

Statements by Company’s bankers on financial


status (attach copy):

Date: ……………………………… Signed: ……………..……………….

80
2. PARTICULARS OF INSURANCE

Sn Type of Insurance Name of Company Registered Address

1 Insurance of Works

2 Plant and Machinery

3 Public Liability

4 Workmen’s Compensation

5 Employer’s Liability

6 Personal Accident

NOTE: Certified photocopies of the relevant insurance policies should


accompany these particulars.
Date: …………………………. Signed: …………………………………..

81
CERTIFICATE OF BIDDER’S VISIT TO SITE

This is to certify that

[Name/s]…………………………………………………………………………………………

……………………………………………………………………………………………………

Being the authorized representative/Agent of [Name of bidder]

………………………………………………………………………………………………………

………………………………………………………………………………………………………

participated in the organised inspection visit of the site of the works for the

held on………………………..day of……………………………20………………..

Signed…………………………………………………………………………………………..
(Employer’s Representative)

……………………………………… …………………………………..
(Name of Employer’s Representative) (Designation

NOTE: This part is to be completed at the


time of the organized site visit.

82
Project
Name:

1. This check list is for Sub-County Engineer to check contractor's work


execution process.

2. Fill in date of checking as (day/month), mark as indicated in Filling Example,


and state remarks.

3. Put this check list in the Monthly Progress Report.

During
before execution
Date Date Date Date Date Date Date Date Date

Item Check Point

/ / / / / / / / /

Works Execution
1 Execution Programme
(including its revised
system in version
1- if any) is submitted
general 1 before the
date specified in
contract
document
Works Execution
Programme
properly reflects the
1- given
2
specifications and site
conditions
Execution procedures
are in
1-
3 accordance with Works
Execution Programme
2 Equipment All equipment used are
holding 2- properly mobilized in
1
accordance with Works
Execution Programme
All equipment used is
well
2-
2 maintained during the
execution of works
Contractor' Qualified technical staff
3 s of
in-house
staff 3- contractor are properly
COUNTY GOVERNMENT OF KISUMU
1 assigned 83
as specified in
Works
Execution Programme
LETTER OF ACCEPTANCE
[Letterhead paper of the Employer]

_______________________[date]

To: _______________________
[name of the Contractor]

_____________________
[address of the Contractor]

Dear Sir,

This is to notify you that your Tender dated ___________________________


for the execution of ________________________________________________
[name of the Contract and identification number,as given in the Tender documents] for the Contract
Price of Kshs. __________________________ [amount in figures][Kenya
Shillings______________________________(amount in words) ] in accordance with the Instructions
to Tenderers is hereby accepted.

You are hereby instructed to proceed with the execution of the said Works in accordance with the
Contract documents.

Authorized Signature …………………………………………………………………

Name and Title of Signatory …………………………………………………………

Attachment : Agreement

COUNTY GOVERNMENT OF KISUMU 84


FORM OF AGREEMENT

THIS AGREEMENT, made the _________________ day of ________ 20 ______


between________________________________________________of [or whose registered office is
situated at]__________________________________________
(hereinafter called “the Employer”) of the one part AND
________________________________________________________of [or whose registered office
is situated at]_________________________________________
(hereinafter called “the Contractor”) of the other part.

WHEREAS THE Employer is desirous that the Contractor executes


________________________________________________________________________
(name and identification number of Contract ) (hereinafter called “the Works”) located
at______________________________[Place/location of the Works]and the Employer has accepted
the tender submitted by the Contractor for the execution and completion of such Works and the
remedying of any defects therein for the Contract Price of
Kshs___________________________[Amount in figures],Kenya
Shillings_____________________________________________[Amount in words].

NOW THIS AGREEMENT WITNESSETH as follows:

1. In this Agreement, words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to.

2. The following documents shall be deemed to form and shall be read and construed as part of
this Agreement i.e.

(i) Letter of Acceptance

(ii) Form of Tender

(iii) Conditions of Contract Part I

(iv) Conditions of Contract Part II and Appendix to Conditions of Contract

(v) Specifications

(vi) Drawings

(vii) Priced Bills of Quantities

3. In consideration of the payments to be made by the Employer to


the Contractor as hereinafter mentioned, the Contractor hereby
covenants with the Employer to execute and complete the Works and remedy any defects
therein in conformity in all respects with the provisions of the Contract.

4. The Employer hereby covenants to pay the Contractor in consideration of the execution and
completion of the Works and the remedying of defects therein, the Contract Price or such other

COUNTY GOVERNMENT OF KISUMU 85


sum as may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.

IN WITNESS whereof the parties thereto have caused this Agreement to be executed the day and year
first before written.

The common Seal of _________________________________________________

Was hereunto affixed in the presence of ________________________________

Signed Sealed, and Delivered by the said ______________________________

Binding Signature of Employer ________________________________________

Binding Signature of Contractor _______________________________________

In the presence of (i) Name_______________________________________

Address_____________________________________

Signature___________________________________

[ii] Name _______________________________________

Address_____________________________________

Signature____________________________________

COUNTY GOVERNMENT OF KISUMU 86


FORM OF TENDER SECURITY

WHEREAS ………………………………………..(hereinafter called “the Tenderer”) has submitted


his tender dated ………………………… for the construction of
………………………………………………………………………
…………………… (name of Contract)

KNOW ALL PEOPLE by these presents that WE ……………………… having our registered office
at ………………(hereinafter called “the Bank”), are bound unto
……………………………(hereinafter called “the Employer”) in the sum of
Kshs.……………………… for which payment well and truly to be made to the said Employer, the
Bank binds itself, its successors and assigns by these presents sealed with the Common Seal of the
said Bank this ……………. Day of ………20…………

THE CONDITIONS of this obligation are:

1. If after tender opening the tenderer withdraws his tender during the period of tender validity
specified in the instructions to tenderers
Or

2. If the tenderer, having been notified of the acceptance of his tender by the Employer during the
period of tender validity:

(a) fails or refuses to execute the form of Agreement in accordance with the Instructions to
Tenderers, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the Instructions
to Tenderers;

We undertake to pay to the Employer up to the above amount upon receipt of his first written
demand, without the Employer having to substantiate his demand, provided that in his demand
the Employer will note that the amount claimed by him is due to him, owing to the occurrence
of one or both of the two conditions, specifying the occurred condition or conditions.

This guarantee will remain in force up to and including thirty (30) days after the period of
tender validity, and any demand in respect thereof should reach the Bank not later than the said
date.
___________________________ ______________________________
[date[ [signature of the Bank]

___________________________ ______________________________
[witness] [seal]

COUNTY GOVERNMENT OF KISUMU 87


PERFORMANCE BANK GUARANTEE

To: _________________________(Name of Employer) ___________(Date)


__________________________(Address of Employer)

Dear Sir,

WHEREAS ______________________(hereinafter called “the Contractor”) has undertaken, in


pursuance of Contract No. _____________ dated _________ to execute _______________
(hereinafter called “the Works”);

AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish
you with a Bank Guarantee by a recognised bank for the sum specified therein as security for
compliance with his obligations in accordance with the Contract;

AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:

NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of
the Contractor, up to a total of Kshs. ________________ (amount of Guarantee in figures) Kenya
Shillings__________________________________________ (amount of Guarantee in words), and we
undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums
within the limits of Kenya Shillings _________________________ (amount of Guarantee in words)
as aforesaid without your needing to prove or to show grounds or reasons for your demand for the sum
specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before presenting
us with the demand.

We further agree that no change, addition or other modification of the terms of the Contract or of the
Works to be performed thereunder or of any of the Contract documents which may be made between
you and the Contractor shall in any way release us from any liability under this Guarantee, and we
hereby waive notice of any change, addition, or modification.

This guarantee shall be valid until the date of issue of the Certificate of Completion.

SIGNATURE AND SEAL OF THE GUARANTOR ___________________

Name of Bank ____________________________________________

Address ________________________________________________

Date ______________________________________________________

COUNTY GOVERNMENT OF KISUMU 88


BANK GUARANTEE FOR ADVANCE PAYMENT

To: ________________________ [name of Employer] ___________(Date)


________________________[address of Employer]

Gentlemen,

Ref: _______________________________________________[name of Contract]

In accordance with the provisions of the Conditions of Contract of the above-mentioned Contract,
We,_______________________________________[name and Address of Contractor] (hereinafter
called “the Contractor”) shall deposit with _______________________________[name of Employer]
a bank guarantee to guarantee his proper and faithful performance under the said Contract in an
amount of Kshs._____________[amount of Guarantee in figurers] Kenya
Shillings_____________________________________[amount of Guarantee in words].

We, ________________[bank or financial institution], as instructed by the Contractor, agree


unconditionally and irrevocably to guarantee as primary obligator and not as Surety merely, the
payment to ___________________________[name of Employer] on his first demand without
whatsoever right of objection on our part and without his first claim to the Contractor, in the amount
not exceeding Kshs________________________[amount of Guarantee in figures] Kenya Shillings
_____________________________________________________________[amount of Guarantee in
words], such amount to be reduced periodically by the amounts recovered by you from the proceeds of
the Contract.

We further agree that no change or addition to or other modification of the terms of the Contract or of
the Works to be performed thereunder or of any of the Contract documents which may be made
between ________________________[name of Employer] and the Contractor, shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any such change,
addition or modification.

No drawing may be made by you under this guarantee until we have received notice in writing from
you that an advance payment of the amount listed above has been paid to the Contractor pursuant to
the Contract.

This guarantee shall remain valid and in full effect from the date of the
advance payment under the Contract until
______________________________________________(name of Employer) receives full payment of
the same amount from the Contract.

Yours faithfully,

Signature and Seal __________________________________________________

Name of the Bank or financial institution ______________________________

Address ______________________________________________________________
COUNTY GOVERNMENT OF KISUMU 89
Date _________________________________________________________________

Witness: Name: ____________________________________________________

Address: __________________________________________________

Signature: ________________________________________________

Date: _____________________________________________________

COUNTY GOVERNMENT OF KISUMU 90


STATEMENT OF FOREIGN CURRENCY REQUIREMENTS

(See Clause 23] of the Conditions of Contract)

In the event of our Tender for the execution of____________________


__________________________(name of Contract) being accepted, we would require in
accordance with Clause 21 of the Conditions of Contract, which is attached hereto, the
following percentage:

(Figures)………………………… (Words)…………………………………

of the Contract Sum, (Less Fluctuations) to be paid in foreign currency.

Currency in which foreign exchange element is required:

………………………………………………………………………………………

Date: The ………… Day of …………….. 20…………….

Enter 0% (zero percent) if no payment will be made in foreign currency.

Maximum foreign currency requirement shall be _____________(percent) of the Contract


Sum, less Fluctuations.

_____________________
(Signature of Tenderer)

COUNTY GOVERNMENT OF KISUMU 91


DETAILS OF SUB-CONTRACTORS

If the Tenderer wishes to sublet any portions of the Works under any heading, he must give
below details of the sub-contractors he intends to employ for each portion.

Failure to comply with this requirement may invalidate the tender.

(1) Portion of Works to be sublet: ………………………………

[i) Full name of Sub-contractor


and address of head office: ………………………………

………………………………

(ii) Sub-contractor’s experience


of similar works carried out
in the last 3 years with
Contract value: ………………………………

………………………………

………………………………

(2) Portion of Works to sublet: ………………………………

(i) Full name of sub-contractor


and address of head office: ………………………………

………………………………

………………………………

(ii) Sub-contractor’s experience


of similar works carried out
in the last 3 years with
contract value: ……………………………

……………………………

____________________ _______________________
[Signature of Tenderer) Date

COUNTY GOVERNMENT OF KISUMU 92


LETTER OF NOTIFICATION OF AWARD

For

To:

RE: Tender No

Tender Name

This is to notify that the contract/s stated below under the above mentioned tender have been awarded
to you.

1. Please acknowledge receipt of this letter of notification signifying your acceptance.

2. The contract/contracts shall be signed by the parties within 30 days of the date of this letter but
not earlier than 14 days from the date of the letter.

3. You may contact the officer(s) whose particulars appear below on the subject matter of this
letter of notification of award.

(FULL PARTICULARS)

For Chief Officer

COUNTY GOVERNMENT OF KISUMU 93


FORM RB 1
REPUBLIC OF KENYA
PUBLIC PROCUREMENT ADMINISTRATIVE REVIEW BOARD
APPLICATION NO…………….OF……….….20……...

BETWEEN …………………………………………….APPLICANT AND

…………………………………RESPONDENT (Procuring Entity)

Request for review of the decision of the…………… (Name of the Procuring Entity) of
……………dated the…day of ………….20……….in the matter of Tender No………..…of
…………..20…
REQUEST FOR REVIEW
I/We……………………………,the above named Applicant(s), of address: Physical
address…………….Fax No……Tel. No……..Email ……………, hereby request the Public
Procurement Administrative Review Board to review the whole/part of the above mentioned decision
on the following grounds , namely:-
1.
2.
etc.
By this memorandum, the Applicant requests the Board for an order/orders that: -
1.
2. etc
SIGNED ……………….(Applicant)
Dated on…………….day of ……………/…20…

FOR OFFICIAL USE ONLY


Lodged with the Secretary Public Procurement Administrative Review Board on ………… day of
………....20….………
SIGNED
Board Secretary

COUNTY GOVERNMENT OF KISUMU 94


COUNTY GOVERNMENT OF KISUMU 95

You might also like