MEP - Detail
MEP - Detail
MEP - Detail
Rev.: 0
Date of Issue: Sep 2023 MEP CONSTRUCTION
Doc No.: MEP-23-07 METHODOLOGY
ELECTRICAL PLUMBING
MEP
MECHANICAL
6
OPERATION DEPARTMENT
Rev.: 0
Date of Issue: Sep 2023 MEP CONSTRUCTION
Doc No.: MEP-23-07 METHODOLOGY
• Mechanical:-
The Mechanical installations mainly cover HVAC works.
• Electrical:-
The Electrical Installations is covering all electrical works, fire alarm system, telephone
system, BMS, low voltage system.
• Plumbing:-
The Plumbing Installations is covering drainage system, water supply distributions, sanitary
ware installations and related works.
7
OPERATION DEPARTMENT
Rev.: 0
Date of Issue: Sep 2023 MEP CONSTRUCTION
Doc No.: MEP-23-07 METHODOLOGY
SECTION 1
MEP ACTIVITY LIST
This covers all the MEP activities in detail, describing 1st 2nd & final fix. Each activity
has been given an individual code number.
This code number can be used as a basic reference code while preparing the MEP
Program. The first two digit of activity code is representing the system:-
KY : Project Milestones
PL : Plumbing System
FF : Fire Fighting System
AC : HVAC System
EL : Electrical System
Each service has separate activity lists i.e. plumbing, fire fighting, electrical, HVAC.
In the last column you will find the relevant method statement reference no. for the
particular activity. Refer these method statements to know more detail about the
activity installation procedures, quality of work, safety requirement implementation
and resources (material, equipment & personnel).
8
PROJECT MILESTONES REQUIREMENTS
Type Area Code Description
9
PLUMBING SYSTEM
Type Area Code Description
Typ.
Underground Floor PL-01 Underground Piping
Embedded in Typ. PL-02 Putting sleeves in concrete slab
Concrete Floor PL-03 Embedded pipe in concrete slab
Typ. PL-04 Cutting & Chasing in block walls
1st Fix
Floor PL-05 Putting Pipes (water supply / drainage) in block walls
Typ. PL-06 Horizontal Drainage Piping
Floor PL-07 Horizontal Water Supply Piping
PL-08 Drainage Pipe Water Leakage Testing
PL-09 Water Supply Water Leakage Testing
PL-10 Vertical (Riser) Drainage Piping
PL-11 Vertical (Riser) Water Supply Piping
2nd Fix PL-12 Floor Drain (Trap) Fixing
PL-13 Water Heater Installation
PL-14 Bath Tub / Shower Tray Installation
Basement PL-15 Sewage Lift Pump Installation & Piping
/ Mech. PL-16 Water Transfer Pump Installation & Piping
Floor / PL-17 Water Booster Pump Installation & Piping
Roof PL-18 Erection of Water Tank & Connections
PL-19 Sanitary Ware Installation
Typ.
Final Fix PL-20 Sanitary Fixture Fixing
Floor
PL-21 Water Meter Fixing
PL-22 Pre commission water transfer & Booster pumps
PL-23 Pre commission floor water heaters
Testing & Pre- PL-24 Overhead Roof Water Tank fill up
Tower
Commissioning PL-25 Flushing & checking leaks in WS pipes
PL-26 Flushing & checking leaks in drainage pipes
PL-27 Simultaneous flow test on drainage risers
PL-28 Test and commission water transfer & booster pumps
Commissioning PL-29 Commissioning water supply PRV's
Tower
& Handover PL-30 Commissioning floor water heaters
PL-31 Commissioning of bath tubs & sanitary ware
10
OPERATION DEPARTMENT
Rev.: 0
Date of Issue: Sep 2023 MEP CONSTRUCTION
Doc No.: MEP-23-07 METHODOLOGY
13
ELECTRICAL SYSTEM
Type Area Code Description
Embed. in Conc. Tower & EL-01 Embedded Conduits in Concrete
Podium
EL-02 Marking on Block walls
Tower &
1st Fix EL-03 Cutting & Chasing in block walls
Podium
EL-04 Fix Conduits, GI Boxes in Block Walls
EL-05 G.I. & PVS Surface Conduiting
EL-06 Installation of Distribution Boards
EL-07 Installation of Sub-Main Boards
EL-08 Installation of Main LV Panel
EL-09 Erect Cable Trays
EL-10 Cable Trucking
EL-11 Earthing System
EL-12 LV Cabling
EL-13 ELV Cabling
Tower & EL-14 Main LV Cable Termination
Podium EL-15 Sub main Cable Termination
2nd Fix EL-16 Wiring for Lighting & Small Power
EL-17 Wiring for ELV System
EL-18 Wiring for Fire Fighting System
EL-19 Circuit Continuity Test
EL-20 Ceiling Rose & Flexible Drops
EL-21 Distribution Boards Dressing
EL-22 Bus bar Installation
EL-23 Lightning Protection System
EL-24 Transformer Installation
EL-25 Generator Installation
Basement
EL-26 ATS Panel Installation
EL-27 LV Cabling from Transformer to LV Panel
Tower EL-28 Fixing Fire Alarm & Light Fittings
Final Fix
& EL-29 Fixing Switches, Sockets & Accessories
Podium
EL-30 Circuit continuity test by bus riser
Testing & Pre- EL-31 Continuity test LV wiring
Tower &
Commissioning
Podium EL-32 Pre commissioning ELV fixtures
EL-33 Final test and commissioning bus risers
EL-34 Test and commission variable frequency drive
EL-35 Lighting protection earth resistance test
Commissioning
Tower & EL-36 Floor MDB, SMDB, MCC panel commissioning
& Handover
Podium EL-37 Test and commission light fixtures
EL-38 Test and commission ELV final fixtures
14
OPERATION DEPARTMENT
Rev.: 0
Date of Issue: Sep 2023 MEP CONSTRUCTION
Doc No.: MEP-23-07 METHODOLOGY
1 Chillers Installation
9 AHU Installation
10 FCU Installation
11 MCC Installation
15
LIST OF TESTING AND COMMISSIONING ACTIVITIES
ELECTRICAL
Sr. No. Activity Description
16
LIST OF TESTING AND COMMISSIONING ACTIVITIES
PLUMBING
Sr. No. Activity Description
17
LIST OF TESTING AND COMMISSIONING ACTIVITIES
FIRE FIGHTING
Sr. No. Activity Description
4 Commissioning of FHC's
5 Commissioning of Sprinklers
18
LIST OF TESTING AND COMMISSIONING ACTIVITIES
HVAC
Sr. No. Activity Description
19