Domestic Building Contract 2018 Specimen
Domestic Building Contract 2018 Specimen
Domestic Building Contract 2018 Specimen
Guidance
Contractor when there is more than one contractor (see item
H ). However, if the Client does not do this (as is common
practice) the Client’s duties as a domestic client are
automatically transferred to the Contractor as Principal
Notes
Contractor. Before the Works commence, the Architect or
Designer can take on the Client’s duties under CDM 2015, on
the condition that there is a written agreement to do so
between the Client and the Architect or Designer. Further
guidance can be obtained from the Health & Safety Executive
(www.hse.gov.uk).
• The Client also has rights under the Contract, including the
G
Domestic Guidance
right to terminate the Contractor’s employment due to any of
the reasons set out in clause 12.
These guidance notes explain the provisions of the Contract and
Contractor’s Rights and Obligations
IN
provide step-by-step guidance on what to consider when
H
conditions under which the Client and the Contractor have the Contract and by the agreed date (see clause 2). This
agreed the Work will be carried out, as well as the Contract could include designing part of the Works, if applicable
Price. It is essential, therefore, that the information provided in – complying with instructions from the Architect/Contract
the Contract Details, including choice of optional items, is the Administrator (see clause 5)
IS
same as that upon which the Contractor submitted its tender,
and that any changes have been agreed before being included. – taking out insurance policies (see item J and clause 6)
– collaborating with the Client to resolve any events that may
delay the completion of or add to the costs of the Works (see
Summary of the Contract clause 3).
BL
• The Contract is divided into three parts: the Agreement, the • The Contractor also has the right under the Contract to:
Contract Details and the Contract Conditions. Other – suspend its obligations because the Client has failed to pay
documents (called ‘Contract Documents’) may also form part an amount due (see clause 8)
of the Contract if they are listed in the Contract Details.
– terminate its employment due to any of the reasons set out
• The Contract is between the Client (the person who orders the in clause 12.
PU
construction work, known as the ‘Works’) and the Contractor
(the person or organisation carrying out the Works). Together
they are referred to as the ‘Parties’ to the Contract. Administering the Contract
• The Contract is administered by the Architect/Contract
When to Use this Contract Administrator.
• The RIBA Domestic Building Contract is suitable for work • The Architect/Contract Administrator is the person named in
carried out on the Client’s home (including renovations, item G of the Contract Details. The Architect/Contract
extensions, maintenance and new buildings). Administrator is not a party to the Contract but is appointed
A
by the Client under a separate contract (contracts suitable for
• The RIBA Domestic Building Contract is not suitable if the professional services appointments are published by the RIBA).
Works are for commercial purposes or if the Client is not the
owner and present or intended occupier. • The administrative duties of the Architect/Contract
IB
Administrator include to:
– act impartially in administering the Contract
Client’s Rights and Obligations
– issue instructions (see clause 5)
• The Client has various obligations under the Contract,
– reject defective work (see clause 5)
R
including:
– visit the Site and other locations (see clause 5)
– providing a description of the work required (see the
Agreement and Contract Details) – certify the value of work properly completed (see clause 7)
– paying the Contractor for work completed (see the – make decisions on various issues, such as Revisions of Time
Agreement and clause 7) and additional payment (see clause 9).
– providing for the administration of the Contract (see clause 5)
• The Client can act as the Contract Administrator if item T is
– making any other appointments that are required, such as selected in the Contract Details. The Client should only
cost consultants and structural engineers choose to act as the Contract Administrator in very limited
circumstances, for instance where the Works are very
– collaborating with the Contractor to resolve any events that
simple or the Client has experience of undertaking such a role.
may delay the completion or add to the cost of the Works
This is important because there are situations where the
(see clause 3)
Architect/Contract Administrator is required to act impartially.
Royal Institute of British Architects – taking out insurance policies, where applicable (see
guidance note for item J ).
Failure to carry out this role appropriately may result in the
Works costing more and finishing later than envisaged.
Additionally, selecting this option may cause a potential Main Items – professional indemnity insurance, covering the Contractor’s If the Parties cannot reach agreement on a person to act as Contract Conditions
Contractor to quote a higher price, due to the problems liability for failure to provide advice or services of a Mediator, Adjudicator or Arbitrator, the Contract provides that
associated with not having an independent Contract • Items A and B – the Client and the Contractor: Give professional standard, including design services (only an appointment shall be made by the Royal Institute of British • The clauses within the Contract Conditions allocate the risks
Administrator. information about the Parties to the Contract. Please note that required if item P of the Contract Details is selected) Architects. of the Works between the Parties and set out the Parties’
any changes to this information will need to be agreed and – other insurance, such as buildings and/or contents rights and obligations.
confirmed to both Parties and the Architect/Contract Optional Items
Contract Documents Administrator in writing.
insurance, which the Parties may agree upon that may be
required for the Works. • The Contract Conditions support the items in the Contract
• Item O – Programme: Select this item if the Contractor is Details and so are divided into two sections: ‘Main Clauses’
• The Contract Documents describe, in detail, the Works that • Item C – Description of the Works and Site Address: Insurance is a highly technical subject and the wordings of required to show the sequence in which it intends to carry out
the Client wants the Contractor to carry out, including any and ‘Optional Clauses’.
Provides a description of the Works and the address of the policies can vary significantly between insurers, so the Parties the Works.
restrictions/limitations that apply. Site and indicates whether the Site will be occupied while the are advised to consult with insurance brokers in making • The Main Clauses always apply. The Optional Clauses will only
Works are being carried out. decisions on the insurance requirements. • Item P – Contractor Design: Select this item if it is agreed apply if the corresponding optional item is selected in the
• It is best practice for the Client to appoint a construction that the Contractor is to design parts of the Works. Provide a
professional to prepare the Contract Documents. • Item D – Contract Documents: Lists the documents that Contract Details.
• Item K – Contract Price and Payments: The Parties may detailed and accurate description of the parts that the
form part of the Contract. These documents should be clearly either agree a lump sum for undertaking the whole of the Contractor is to design, and identify which Contract Document
G
• The choice of what constitutes Contract Documents depends identified and both Parties should initial them before attaching
on the complexity of the project. Complex projects will require Works or choose that the Contractor will prepare a Pricing each part is covered under. The Contractor will need to ensure
them to the Contract itself. Document for each item of the Works. If the latter is selected, there is adequate professional indemnity insurance to cover
considerably more detailed information. Further advice on the
extent of the requirements to be incorporated within Contract the rates specified in the Pricing Document will be used to any design it is responsible for. Item P allows a limit to be
• Item E – Contract Period: Sets out the Start Date and the value each completed item of the Works, and the Contract specified, but it should be adequate to cover the possible
Documents should be sought from the Architect/Contract
IN
Date for Completion of the Works. The Date for Completion Price will be calculated accordingly. The format of the Pricing liability. The Architect/Contract Administrator may be able to
Administrator. could be either a calendar date or a fixed period, such as Document should be appropriate to the work being carried advise on this point.
‘12 weeks after the Start Date’. ‘Restrictions on Working out, and agreed between the Parties, with assistance from the
• If the Contract Documents include more than one document, Hours’ refers to any time periods when the Client doesn’t want
the documents must all be consistent with each other in terms Architect/Contract Administrator. If VAT applies, the amount of • Item Q – Required Specialists: Select this item where it is
work or specific activities to take place (for example, early VAT should be stated in the item or on the schedule of rates agreed that the Client wants to use specific subcontractors or
of the extent of requirements. Having to resolve discrepancies mornings or weekends). and the Contractor will submit a valid VAT invoice separately. suppliers for parts of the Works. The Contractor retains control
H
within Contract Documents can result in disputes and
potential changes to the Contract Price and/or the Date for • Item F – Facilities: Identifies those facilities to be made The Parties should also specify the frequency at which over the Required Specialists and is responsible for their
Completion. available to the Contractor by the Client. Payment Certificates will be issued. If the duration of the performance.
Works is less than 45 days, the option of a single payment
• All documents to be included in the Contract Documents are • Items G and H – Architect/Contract Administrator and once Practical Completion of the whole of the Works has been • Item R – Completion in Sections: Select this item if the
IS
to be listed in item D and form part of the Contract between Other Appointments by the Client: Describe those certified should be selected. It is important to note that the Parties want the Works to be completed in Sections. Dividing
the Client and the Contractor. It is very important that they are professional appointments made by the Client, in connection Contract Price may increase (or decrease) as a result of the Works into Sections facilitates good management and
clearly identified and kept together with the rest of the with the Works, that are known at the time of signing the instructions given by the Architect/Contract Administrator. may be useful where the Site remains occupied during the
Contract. Contract. Works. Clearly describe what needs to be done to achieve
• Item L – Liquidated Damages: This should be a realistic Practical Completion for each Section. ‘Section value’ refers to
BL
• Item I – Consents, Fees and Charges: Identifies whether the estimate of the expected daily cost to the Client should the the proportion of the Contract Price covered by the Section.
The Agreement Client or the Contractor will be responsible for obtaining and Works not be completed on time and which should not be
paying for things like planning permission and Building extravagant and unconscionable. Advice on calculating • Item S1 – Milestone Payments: If this item is selected, the
• The Agreement is the part of the Contract that is signed and Regulations approval. Liquidated Damages may be sought from the Architect/ payment certificate frequency section of item K will not apply;
dated by both Parties and records the Client’s and the Contract Administrator. Note that if this section is left blank, the instead, Payment Certificates will be issued after each
Contractor’s rights and obligations under the Contract. It is • Item J – Insurance: Lists the insurance policies that are Client cannot recover Liquidated Damages but they may still milestone is completed. Clearly describe each milestone in
very important to make sure it is signed before the Works applicable to the Works and identifies who is responsible for have the right to claim general damages. detail and state the anticipated date for achieving it.
PU
commence. arranging and paying for them. For each insurance type, state
the minimum financial amount of cover it must provide, as well • Item M – Defects Fixing Period: This period begins once • Item S2 – Payment on Practical Completion of the Works:
• The Parties can choose whether to sign the Agreement as a as the basis on which that cover is calculated – either as an Practical Completion is certified. The Contractor must put Select this item if the Works will last for less than 45 days and
simple contract or as a deed. The decision should be amount for each and every claim, or a total of all claims right all defects identified during the Defects Fixing Period, it is appropriate to make payment only when Practical
dependent on the size, value and complexity of the Works as (aggregate) made over the period of the insurance. Also state otherwise the Client may get someone else to do it and Completion has been certified.
the choice determines the statutory limitation period within whether the policy will be in the joint names of the Client and charge the cost to the Contractor. Depending on the size and
which a Party can bring a claim for breach of contract: Contractor or specifically in the name of either the Contractor complexity of the Works, the Defects Fixing Period could be 3, • Item T – Client Acting as Contract Administrator: Select The RIBA Domestic Building Contract 2018 is endorsed by the following organisations:
– simple contract: 6 years from Practical Completion or date of or the Client. Having a joint names policy means, among other 6 or 12 months. this item if the Client wants to take on all the duties assigned to
breach, if earlier things, that either Party may make a claim under the policy, the Architect/Contract Administrator (see Administering the
and will be notified of any amendments to it. • Item N – Dispute Resolution: In a contract with a consumer
A
Contract in these Guidance Notes).
– deed: 12 years from Practical Completion or date of breach, Client, the Client has the right to refer any dispute to the
if earlier. When having work carried out on its property, the Client courts, but may wish to attempt to settle the matter by • Item U – Insurance Backed Guarantee: It is recommended
should inform its buildings and contents insurers and seek alternative means, such as negotiation or mediation. The that this guarantee should cover the whole of the Works as
• Because the RIBA Domestic Building Contract is a consumer written confirmation of the extent of cover provided by its own
IB
court may look favourably on any demonstration that the well as defective materials and workmanship in the event that
contract, the Client has the statutory right to cancel the insurance policies in respect of the Work. The Contract Details Parties have attempted an alternative dispute resolution the Contractor ceases to trade. The duration of the guarantee
contract within 14 days of signing it and the Contractor shall sets out the main insurance policies that should be in place. method prior to any legal proceedings. The use of any should be a minimum of one year after Practical Completion
Chartered Institute of
Architectural Technologists
Royal Society of Architects
in Wales
Royal Society of
Ulster Architects
Home Owners
Alliance
refund any money received from the Client, apart from This is not an exhaustive list and the specific circumstances processes other than legal proceedings must be negotiated has been certified.
any work, services or goods that the Client has agreed to pay and nature of the Works may require additional insurance. by the Parties, but only the Client can make the decision to
for. To cancel the Contract, the Client must send the The following are examples of insurances that typically should R use arbitration. • Item V – New Building Warranty: Select this item only if the © Royal Institute of British Architects 2018
Contractor a written notice of cancellation (see clause 12). be included in a contract for building work: Works are a new residential building. A New Building Warranty
A template notice of cancellation is provided in the Appendix. – Mediation – involves a third party helping the Parties to First published 2018
come to an agreement resolving their dispute. If managed provides insurance for some defects, inferior materials or poor Reprinted 2019
– ‘all risks’ insurance, in joint names (Client and Contractor), to
well, mediation can be less expensive than other methods of workmanship discovered after the Defects Fixing Period. The Published by RIBA Publishing, 66 Portland Place, London W1B 1AD
cover liability for damage to the Works, products and
Completing the Contract Details equipment dispute resolution and is therefore encouraged by the New Building Warranty cover must satisfy the Council of
Mortgage Lenders (CML) requirements and should
ISBN 978 1 85946 869 2
courts. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic,
– public liability insurance, covering the Contractor’s liability for commence no later than the expiry of the Defects Fixing
• The Contract Details describe the specific features of the mechanical, photocopying, recording or otherwise, without prior permission of the copyright owner.
damage to third party property and people. This includes – Adjudication – involves a third party providing an Period.
Works and are divided into two sections: Copyright Licence
personal injury to third parties other than the insured’s own independent decision on the dispute. The decision is binding 3 This publication is for the sole use of the purchaser.
– Main Items: general information required for most projects. employees and for damage to property belonging to third in law unless one of the Parties refers the matter to • Item W – Evidence of Ability to Pay the Contract Price: 3 You may use it for one building contract only.
3 You and the other party to your contract may distribute copies of this publication to advisers and to other persons as necessary in connection with the
parties arbitration or to the courts. This option can provide assurance to a Contractor working
– Optional Items: additional provisions that allow for more proper performance of your contract.
flexibility in control of the Works, which might be required in – employers’ liability insurance, covering the Contractor’s – Arbitration – is an alternative to court litigation and involves with a new Client. However, it is advised that this option is 7 In any other case, you may not distribute or reproduce the whole or part of this document in any work, whether in hard copy, electronic or any other
form, without the prior written consent of the RIBA.
more complex projects. If any of these are selected, the liability for personal injury to or the death of its employees. a third party (or parties) delivering a final and binding used sparingly. Evidence may be a bank reference or some 7 You may not use the RIBA initials or logo unless you are an RIBA chartered member or RIBA chartered practice.
corresponding ‘Optional Clauses’ in the Contract Conditions This includes employee illness or injury sustained as a result decision. form of guarantee.
will apply. of their employment
G
Domestic
IN
Building Contract 2018
H
IS
BL
PU
A
IB
R
R
IB
A
PU
BL
IS
H
IN
G
RIBA Domestic Building Contract 2018
Contract
Checklist
G
IN
ONCE THE CONTRACT DETAILS HAVE BEEN COMPLETED, AND BEFORE THE
AGREEMENT IS SIGNED, CHECK THIS LIST.
If you are unable to answer ‘yes’ to any of the following questions, you are
not ready to sign the Contract.
H
YES
Have the points of contact with the Client, the Architect/Contract Administrator and the
Contractor been agreed?
IS
Has the precise scope of the Works – in particular, if Contractor Design and/or
Required Specialist options have been selected – been agreed?
BL
Have the Contract Price and payment dates been agreed?
Have the Parties agreed who is responsible for payment of any fees and charges,
e.g. building control approvals or public utilities fees?
PU
Have the Start Date, the Date for Completion and the Programme (if selected) been agreed?
Have all the Contract Documents (drawings, specification, schedules, etc.) been agreed
and listed?
A
Have the arrangements for access, working hours and the use of facilities been agreed?
IB
Have the roles of Client, Principal Contractor and Principal Designer, under the CDM
Regulations 2015, been properly considered and clearly allocated to the relevant parties?
Have the Parties agreed and put in place the relevant insurance policies?
R
Has it been agreed whether any warranties or guarantees are required and, if so, who is
to provide them?
Have the Parties agreed and set out the preferred dispute resolution process, in case
something goes wrong?
Has all of the information contained within the Contract Details been completed?
Agreement
G
IN
This Agreement is between:
The Client (refer to item A of the Contract Details for full information)
H
AND
The Contractor (refer to item B of the Contract Details for full information)
Name:
Signature:
A
Address:
R
Signature:
The Client has the right to cancel this agreement within 14 days of signing it – see Appendix.
Name:
Signature:
G
Name:
Address:
IN
Signature:
H
OR
Company registration
number:
IS
BL
VAT registration
number:
Name:
Signature:
Name:
A
Address:
IB
Signature:
R
Name:
Signature:
Contract
Details
G
IN
Main Items
A. The Client (see clause 1)
H
Name:
Address:
IS
BL
Telephone number:
Email address:
PU
Name:
A
Address:
IB
Telephone number:
R
Email address:
Registered company
address
(if different to above):
Trade association
membership:
Description of
the Works:
Site address:
G
IN
Site will be occupied during the Works: Yes No
H
D. Contract Documents (see clause 1.1.2)
IS
Select the documents that apply and provide a reference number and date for each.
Additional documents can be listed in the blank spaces below.
Pricing Document
Specification
PU
Restrictions on
Working Hours:
G
F. Facilities (see clause 2.5)
The Contractor may have the free use of the following facilities at the Site (select all that apply):
IN
Electricity Parking Telephone Washroom/toilet Water
Other:
H
G.
IS
Architect/Contract Administrator (see clause 1.3)
Name:
BL
Address:
PU
Telephone number:
Email address:
Name:
IB
Address:
R
Telephone number:
Email address:
Responsibility for obtaining and paying for regulatory and statutory consents, fees and
charges as set out below:
Client Contractor
G
IN
Continue on a separate sheet if necessary.
H
The following insurance policies are required to be in place before the Works are started
(for each insurance type, state the type and amount of cover required, whether the amount is
IS
an aggregate or per claim and who is responsible for arranging it).
and equipment
All risks insurance in the joint names to £
cover damages to the existing structures
Other insurance policies, such as buildings and/or contents insurance (please specify)
Insurance type Amount Responsibility
(excluding Professional Indemnity (per claim/aggregate)
A
£
IB
£
R
Contract Price: £
VAT
(if applicable): £
G
Total (amount
£
including VAT ):
Contract Price calculated in accordance with the Pricing Document listed under item D.
IN
Interim Payment Frequency
The Interim Payment Date is at regular intervals (unless optional item S1 or S2 of the
H
Contract Details has been selected). Select the frequency of interim payments:
Interest rate: %
PU
(default 5% above the current Bank of England base rate, see clause 7.16).
OR
IB
Period
(minimum 3 months):
G
for a final decision, if necessary.
Where an Alternative Dispute Resolution mechanism has been selected to apply but a party
has not been named, or is unable to act upon appointment, then selection can be made by
IN
the Royal Institute of British Architects.
H
Name of Mediator:
Adjudication IS
(in accordance with the RIBA Adjudication Scheme for Consumer Contracts)
Name of Adjudicator:
Applies
BL
Final Dispute Resolution Process
Arbitration Applies
PU
Name of Arbitrator:
A
IB
R
Optional Items
O. Programme (see clause 14) Applies
Indicate the activities the Contractor will carry out to complete the Works, the start and finish
dates of each activity and the relationship of each activity to the others, which may include
lead and lag times.
G
IN
Continue on a separate sheet if necessary.
H
P. Contractor Design (see clause 15) Applies
IS
The Contractor is to design the parts of the Works listed below
(include reference to the relevant Contract Documents).
BL
Description Contract Document
(include location in document)
PU
The Client requires that the Contractor uses the following specialist(s) for the parts of the
Works identified at the tender stage and listed in the Contract Documents:
R
Section no:
Description:
G
Section start date:
Date of Completion
of the Section:
IN
Section value: £
£
Liquidated Damages: per day
H
Section no:
Description:
IS
BL
Section start date:
Date of Completion
PU
of the Section:
Section value: £
Liquidated Damages:
£ per day
A
Section no:
IB
Description:
R
Date of Completion
of the Section:
Section value: £
Liquidated Damages:
£ per day
Schedule of Milestones
Milestone no:
Description:
G
Date to be
achieved by:
Payment (value or
IN
% of Contract Price):
Milestone no:
H
Description:
Date to be
achieved by:
Payment (value or
IS
BL
% of Contract Price):
Milestone no:
PU
Description:
Date to be
achieved by:
Payment (value or
A
% of Contract Price):
Scope:
Duration:
G
Warranty provider:
Length of cover:
IN
Details of cover:
H
W.
IS
Evidence of Ability to Pay the Contract Price (see clause 22) Applies
BL
PU
A
IB
R
Contract
Conditions
G
IN
Definition of Terms
Architect1/Contract Administrator: the person or organisation that the Client appoints to carry
H
out the role described in clause 5 of the Contract.
Certificate of Practical Completion or Section Completion: a certificate that the Architect/
Contract Administrator issues to the Parties in accordance with clause 9.11.1 of the Contract.
Contract Price: the amount that the Client shall pay to the Contractor for carrying out and
BL
completing the Works, calculated in accordance with clause 7 of the Contract. Note: The Contract
Price may increase (or decrease) as a result of instructions given by the Architect/Contract
Administrator.
Date for Completion: the date stated in item E or item R (if applicable) of the Contract Details by
which the Contractor is required to achieve Practical Completion of the Works or a Section of the
Works.
PU
Defects Fixing Period: the period specified in item M of the Contract Details and described in
clause 10 of the Contract.
Final Date for Payment: the date, specified in clause 7, following the due date for interim or
final payment, by which a payment that is due should be paid.
Force Majeure: an exceptional event or circumstance (see clause 9) which:
A
Insurance Backed Guarantee: a scheme to protect the Client if the Contractor ceases to trade, or
to meet the costs of replacing defective materials and putting right poor workmanship. Some trade
associations provide guarantees of this kind on behalf of their members (see clause 20).
Interim (or Final) Payment Date: the date specified in clause 7 and item K of the Contract Details
R
representing the date on which the amount of any payment due under the Contract is calculated
and becomes due.
Liquidated Damages: a rate specified in item L and/or optional item R of the Contract Details, that
may be deducted by the Client if the Contractor fails to complete the Works or a Section of the
Works by the relevant Date for Completion.
1
‘Architect’ is a legally protected designation to be used only by persons registered under the Architects Act 1997.
Material Breach: a Material Breach of the Contract means that there has been a failure to perform
a major part of the Contract. This failure has to be serious enough to prevent the continuous
progress of the Works so that the Contract cannot be completed. For example, a Material Breach
could be:
• persistent failure to engage sufficient labour
• failure to comply with statutory obligations, particularly those regarding health and safety
• a ny criminal act or evidence of corruption.
New Building Warranty: a warranty that provides insurance for some defects, inferior materials or
poor workmanship discovered after the Defects Fixing Period (see clause 21).
G
Partial Possession: when the Client takes over the use of part of the Works from the Contractor
(see clause 9).
Parties: the signatories to the Agreement: the Client and the Contractor described in items A and B
IN
of the Contract Details.
Pay Less Notice: a notice that one Party may issue to the other, in accordance with clause 7,
indicating an intention to pay less than the sum shown as due on a Payment Certificate or Payment
Notice.
H
Payment Certificate: a certificate that the Architect/Contract Administrator issues, in accordance
with clause 7, showing the amount to be paid, how it was calculated and the period in which the
payment is due.
IS
Payment Notice: a notice that the Contractor issues to the Client, in accordance with clause 7,
showing the payment that the Contractor considers is due and how it was calculated.
Practical Completion: when the Works or a Section of the Works is certified complete in
accordance with clause 9.
BL
Pricing Document: a document provided in accordance with item D (and item K, where applicable)
and completed by the Contractor, to show a breakdown of the pricing of the Works. The Pricing
Document may be used for the assessment of the cost of the ongoing Works, and also as the basis
for calculating Interim Payments or valuing changes to the Contract Price.
Programme: (where item O is selected in the Contract Details) a programme is a plan of the
PU
Section: part of the Works separately identified and described for start and completion in item R of
the Contract Details.
Working Hours: standard working hours are Monday to Friday, between 08.30 and 17.30 excluding
R
bank holidays and public holidays, unless alternative arrangements are specified in item E of the
Contract Details.
Works: work or services described in the Contract Details that the Contractor (and its
subcontractors) is to carry out, including all incidental work to ensure that the work or services are
completed properly.
Main Clauses
1. Client
1.1 The Client shall provide the Contractor with access to the Site for the following purposes:
1.1.1 pre-construction inspection
1.1.2 carry out and complete the Works set out in the Contract Documents, from the
Start Date until the Date for Completion
G
1.1.3 fulfilling its obligations during the Defects Fixing Period.
1.2 The Client shall provide the Contractor with access to any part(s) of the Works or part(s)
of a Section of the Works taken over from the Contractor prior to Practical Completion
IN
(under Clause 9.12).
1.3 The Client has appointed the Architect/Contract Administrator identified in item G of the
Contract Details and other appointments identified in item H of the Contract Details in
connection with the Contract, and will inform the Contractor of any other appointments or
H
replacements.
1.4 The Client may postpone access to the Site or Sections of the Site. The Contractor may be
entitled to a Revision of Time and any costs that result from this.
1.5 IS
The Client shall comply with all of the relevant health and safety legislation.
BL
2. Contractor
Obligation
2.1 T he Contractor shall:
PU
2.1.1 carry out and complete the Works in accordance with the Contract, in good and
workmanlike manner, by the Date for Completion
2.1.2 be responsible for obtaining all regulatory and statutory consents, fees and
charges as set out under item I of the Contract Details
2.1.3 comply with all of the relevant health and safety legislation
2.1.4 comply with all statutory obligations applicable to the Works.
A
2.3 The Contractor shall ensure that a suitably qualified representative is available during the
Works to answer queries and receive instructions on its behalf.
2.4 The Contractor shall take all reasonable steps and precautions to ensure that security is
R
2.5 The Contractor may use, free of charge, the Client’s facilities listed in item F of the
Contract Details and shall be responsible for any loss or damage arising from such use.
2.6 The Contractor shall be solely responsible for carrying out the Works and for the
performance of all subcontractors and suppliers, including any Required Specialists listed
in item Q of the Contract Details (if selected).
3. Collaborative Working
Pre-start Meeting
3.1 Atleast 10 days before the Start Date, the Parties and the Architect/Contract Administrator
are to meet and:
3.1.1 s et out expectations from each other
3.1.2 s et
out the administration and communication procedures, including any specific
rules on written and electronic communications
G
3.1.3 i dentify
potential and actual risks and set out procedures to deal with them, to
include the preparation of a Risk Register, if appropriate.
IN
3.2 If
an event occurs which affects or is likely to affect the progress of the Works and/or the
Contract Price, the Parties shall:
3.2.1 n otify
each other and the Architect/Contract Administrator of the event as soon as
they become aware of it
H
3.2.2 work together to resolve the event. If necessary the Architect/Contract
Administrator may hold a meeting with the Parties and other related stakeholders
to do this
3.3
3.2.3
If
t ake
IS
reasonable steps to minimise the effects of the event on the Contract.
either Party fails to comply with clause 3.2, the Architect/Contract Administrator takes
this into account when considering any time and/or cost implications arising from the event
BL
and advises on changes to the Date for Completion and/or Contract Price.
3.5 Any cost savings resulting from the changes shall be divided equally between the Parties.
A
4. Assignment
4.1 Neither Party shall assign its rights or benefits under the Contract without informing and
IB
5. Architect/Contract Administrator
R
5.1 he Architect/Contract Administrator is not a Party to the Contract but administers the
T
Contract, issuing instructions and certificates and taking decisions.
5.3 T he Architect/Contract Administrator may visit the Site (including off-site locations in
connection with the Works).
Instructions
5.4 T he Architect/Contract Administrator may issue the following instructions:
5.4.1 requiring change to the Works
5.4.2 p ostponing the Works or one or more Sections of the Works
5.4.3 resolving any inconsistency in the Contract Documents or in a previous instruction
5.4.4 rejecting work not in accordance with the Contract
5.4.5 requiring further documents.
G
5.5 he Architect/Contract Administrator may instruct that work be uncovered and
T
inspected/tested and:
5.5.1 i f
the work is not in accordance with the Contract, the Contractor shall bear the
IN
time and/or costs of the instruction and of correcting the defects
5.5.2 i f
the work is in accordance with the Contract, the Date for Completion and
Contract Price shall be adjusted to take account of the time and costs incurred in
connection with the instruction.
H
5.6 T he Contractor shall comply with Architect/Contract Administrator’s instructions promptly.
5.7 If the Architect/Contract Administrator gives an oral instruction, such instruction will
5.8 IS
subsequently be confirmed in writing to the Contractor promptly.
If the Contractor fails to comply with an Architect/Contract Administrator’s instruction, the
Architect/Contract Administrator may issue the Contractor with a 7-day notice to comply.
If the Contractor fails to comply within the 7-day period, then the Architect/Contract
BL
Administrator may advise the Client to employ and pay other contractors to carry out the
instruction and:
5.8.1 the Client shall have the right to employ other contractors to carry out the instruction
5.8.2 the Contractor shall cooperate with the new contractors
PU
5.10 The Contractor shall not be entitled to any adjustment to the Contract Price and/or Date for
Completion if the inconsistency is in or between the documents set out under item P of the
IB
Contract Details.
relevant an instruction under clause 5.9, the Contractor shall calculate the effect (if any) of
the instruction on the Contract Price and/or the Date for Completion, and submit details to
the Architect/Contract Administrator.
5.12 If the Contractor submits a calculation in accordance with clause 5.11, the Architect/
Contract Administrator and the Contractor aim to agree on any Revision of Time and/or
additional payment implications promptly.
5.13 If the Architect/Contract Administrator and the Contractor are unable to agree or the
Contractor fails to submit the calculation within 7 days, the Architect/Contract Administrator
will determine the appropriate adjustment to the Date for Completion and/or Contract Price.
5.14 Within 7 days of receiving a change to Works instruction, the Contractor shall notify the
Architect/Contract Administrator if it believes that any of the following apply:
5.14.1 the instruction is not in accordance with the Contract
5.14.2 i mplementing the instruction would have adverse health and safety implications
5.14.3 the instruction adversely affects any part of the Works designed by the Contractor
(if applicable).
5.15 On receiving a notification under clause 5.14, the Architect/Contract Administrator may
modify, amend, withdraw or confirm the instruction. The Contractor shall comply accordingly.
G
6. Risks, Liability and Insurance
IN
Client’s Liability
6.1 In so far as the event has not been caused by the Contractor, or its employees or agents,
in carrying out the Works, the Client’s liability includes:
H
6.1.1 d amage to existing structures and fixtures
6.1.2 d amage to neighbouring property caused by the carrying out of the Works.
6.2
Contractor’s Liability
IS
In so far as the event has not been caused by the Client, or its employees or agents,
in carrying out the Works, the Contractor’s liability includes:
BL
6.2.1 l oss of or damage to the Works
6.2.2 l oss of or damage to the property
6.2.3 l oss of or damage to products and equipment
6.2.4 d eath
of or bodily harm to any person working for the Contractor, arising in
connection with the Works during the course of their employment
PU
6.2.5 d eath of or bodily harm to a third party caused by the carrying out of the Works
6.2.6 a ny other loss or damage that is not the liability of the Client.
Practical Completion. The Contractor shall give assurances to the Client that any Required
Specialists, as indicated in item Q of the Contract Details, have adequate insurance in
relation to their portion of the Works.
IB
6.4 No later than 10 days before the Start Date, and after that on request, the Client or
Contractor shall provide the Architect/Contract Administrator with evidence of up-to-date
and adequate insurance stated to be its responsibility. If this evidence is not provided by
either Party, then the Architect/Contract Administrator will notify the other Party, which shall
R
take out the required insurance instead and the Contract Price will be adjusted accordingly.
Interim Payments
7.1 Until the final payment due date is fixed under clause 7.13, the Interim Payment Date will
be as described in item K of the Contract Details or, where applicable, under item S1 or
item S2 of the Contract Details.
7.2 No later than 7 days before each Interim Payment Date, the Contractor may send the
Architect/Contract Administrator an application for payment which complies with the
requirements of clause 7.5.
7.3 No later than 5 days after each Interim Payment Date, the Architect/Contract Administrator
will send the Parties a Payment Certificate which complies with the requirements of
clause 7.5.
7.4 If the Architect/Contract Administrator does not issue a Payment Certificate as required by
clause 7.3 then:
the Contractor’s application for payment under clause 7.2 shall become a Payment
G
7.4.1
Notice; or
7.4.2 if the Contractor has not submitted an application for payment under clause 7.2,
they may do so at any time after the expiry of the period in which the Architect/
IN
Contract Administrator may send a Payment Certificate and this shall become a
Payment Notice.
H
7.5 Any application for payment, Payment Certificate or Payment Notice shall state the:
7.5.1 date and period to which it relates
7.5.2
7.5.3
7.5.4
IS
value of work completed in accordance with the Contract
amount of any adjustments required in accordance with the Contract
amount of any Retention
BL
7.5.5 total amount included in previous Payment Certificates or Payment Notices
7.5.6 balance due (from the Client to the Contractor or from the Contractor to the Client)
at the relevant payment due date.
7.6 Unless a Pay Less Notice is given in accordance with clause 7.9, the Client or the
Contractor, whichever is making the payment, shall pay to the other Party the amount set
PU
out in the Payment Certificate or Payment Notice (as applicable) by the Final Date for
Payment.
7.7 Subject to clause 7.8, the Final Date for Payment of an interim payment and the final
payment shall be 14 days after the relevant payment due date.
7.8 Where a Payment Notice is given under clause 7.4.2 or 7.12.2, the Final Date for Payment of
the sum stated in the notice shall be postponed by the same number of days that it took
A
the Contractor to issue the Payment Notice after the 5-day period in clause 7.3 or 7.12.1
expired (as applicable).
7.9 If, in respect of any payment, the Client or the Contractor intends to pay less than the sum
IB
set out in the Payment Certificate or Payment Notice (as applicable) it shall no later than
5 days prior to the Final Date for Payment give written notice (a Pay Less Notice) to the
other Party.
R
7.10 The Pay Less Notice shall state the sum that the paying Party considers due at the date the
notice is given and the basis upon which this is calculated.
7.11.3 if the Architect/Contract Administrator and the Contractor are unable to agree, or if
the Contractor fails to send a calculation then, no later than 14 days after the end of
the 30 day period referred to in clause 7.11.2, the Architect/Contract Administrator
will calculate the final Contract Price and notify it to the Contractor in writing
7.11.4 the final Contract Price is subject to resolution of any defects arising during the
Defects Fixing Period.
Final Payment
7.12 No later than 5 days after the end of the Defects Fixing Period or, where applicable, the
period set out in clause 7.11, whichever is the later:
G
7.12.1 the Architect/Contract Administrator shall issue a final Payment Certificate which
complies with the requirements of clause 7.5 representing the amount due for final
payment, or
IN
7.12.2 if the Architect/Contract Administrator fails to issue a final Payment Certificate as
required by clause 7.12.1, then the Contractor may issue a final Payment Notice at
any time after the expiry of the period in clause 7.12, which complies with the
requirements of clause 7.5.
H
7.13 The payment due date for the final payment shall be the date of issue of the final Payment
Certificate under clause 7.12.1 or the date of issue of the final Payment Notice under
clause 7.12.2 (as applicable).
7.14
Retention IS
The Retention percentage shall be 5% of the Contract Price for the Works or a Section of
the Works. This shall be reduced to 2.5% after Practical Completion is certified and all
BL
Retention shall be released in the final Payment Certificate.
VAT
7.15 C ontractor’s VAT invoice, if applicable:
7.15.1 the
Contractor shall issue the Client with a valid VAT invoice for every Payment
PU
Certificate or Payment Notice on or before the Final Date for Payment of that
Payment Certificate or Payment Notice
7.15.2 the Client shall pay the invoice promptly.
8.1 If the Client fails to pay an amount that is due to the Contractor after the Final Date for
Payment has passed:
R
8.1.1 the
Contractor may issue the Client with a 7-day notice of its intention to suspend
some or all of its obligations under the Contract
8.1.2 thenotice shall state the amount owed and the date that the suspension will take
effect
8.1.3 i f
the Client fails to make payment within the 7-day notice period, the Contractor
may suspend some or all of its obligations.
8.2 If the Contractor suspends some or all of its obligations following the procedure in
clause 8.1, then it shall be entitled to a Revision of Time, reasonable expenses and costs
resulting from the suspension.
Force Majeure
9.1 If Force Majeure occurs, either Party shall inform the other Party and the Architect/Contract
Administrator promptly. If it becomes necessary, the Architect/Contract Administrator may
instruct the Contractor to stop all or part of the Works.
9.2 Force Majeure may entitle the Contractor to an application for a Revision of Time and/or
additional payment.
G
Revision of Time
9.3 The Contractor may apply (with supporting documentation) for a Revision of Time if the
IN
Works are or are likely to be delayed by any of the following:
9.3.1 the Architect/Contract Administrator issues a change to Works instruction
9.3.2 the Client defers or withdraws access to the Site
9.3.3 the Client or its agents cause delay or disruption to the Works or part of the Works
H
9.3.4 the Client or its agents cause the Works or part of the Works to be suspended
9.3.5 subject to clause 5.5.1, an instruction issued for work to be uncovered and
9.3.6 IS
inspected/tested under clause 5.5
the action or omission of a utility company or statutory body, subject to advance
warning notification under clauses 3.2 and 3.3
an event under clause 8 (Contractor’s Right to Suspend)
BL
9.3.7
9.4 The Contractor shall inform the Architect/Contract Administrator of any event affecting the
progress of the Works and shall apply for a Revision of Time, with supporting
documentation, within a reasonable time of its occurrence.
PU
9.5 The Architect/Contract Administrator and the Contractor shall aim to agree on the Revision
of Time promptly.
9.6 If the Architect/Contract Administrator and the Contractor are unable to agree a Revision of
Time, the Architect/Contract Administrator may make a reasonable assessment of the
Revision of Time, taking into consideration all the supporting documentation.
Additional Payment
A
9.7 If an event attributable to the Client or its agents adds costs to the Works, the Contractor
shall inform the Architect/Contract Administrator and shall apply for an adjustment to the
IB
Contract Price (with supporting documentation) within a reasonable time of its occurrence.
9.8 The Architect/Contract Administrator and the Contractor shall aim to agree the additional
payment promptly.
R
9.9 If the Architect/Contract Administrator and the Contractor are unable to agree an additional
payment, the Architect/Contract Administrator may make a reasonable assessment, taking
into consideration all the supporting documentation.
Practical Completion
9.10 For Practical Completion to occur, the following must apply:
9.10.1 any requirements stated in the Contract Documents and required by law shall have
been satisfied
9.10.2 no aspect of the Works or Section of the Works shall be outstanding
9.10.3 the Works shall be uncluttered and safe.
9.11 W hen the Contractor considers that Practical Completion of the Works or a Section of the
Works has been achieved, it shall notify the Architect/Contract Administrator:
9.11.1 i f
the Architect/Contract Administrator agrees that Practical Completion has been
achieved for the Works or a Section of the Works, the Architect/Contract
Administrator issues a Certificate of Practical Completion
9.11.2 w hen
Practical Completion has been certified, the Contractor is entitled to half the
amount currently retained in accordance with clause 7.14.
Partial Possession
G
9.12 T he Client may request to take over any part(s) of the Works or part(s) of a Section of the
Works before Practical Completion of the Works or the relevant Section. If doing so will not
interfere with achieving Practical Completion of the remainder of the Works, the Contractor
shall agree to the request.
IN
9.13 O nce Partial Possession is agreed:
9.13.1 theArchitect/Contract Administrator issues a notice clearly identifying the part(s)
taken over and the date of takeover, as well as any outstanding work and
arrangements for access by the Contractor
H
9.13.2 Practical Completion will be deemed to have taken place on the date of takeover
for the relevant part(s)
9.13.3
9.13.4
the
i n
IS
Defects Fixing Period for that part(s) shall start from that date
respect of the Contract Price for that part of the Works, the Contractor is
entitled to half the amount currently retained in accordance with clause 7.14.
BL
10. Liquidated Damages and Defects Fixing Period
Liquidated Damages
PU
10.1 If the Contractor does not achieve Practical Completion of the Works or a Section of the
Works on the relevant Date for Completion, taking into consideration any Revision of Time,
the Client shall be entitled to deduct Liquidated Damages at the rate stated in item L or
item R of the Contract Details.
Works, and shall last for the period stated in item M of the Contract Details.
10.3 he Contractor shall remedy all defects associated with the Works notified to them during
T
IB
10.4 W hen the Architect/Contract Administrator is satisfied that all defects are fixed, the
Architect/Contract Administrator issues a certificate of making good defects.
R
10.5 If the Contractor fails to fix any defects notified to them during the Defects Fixing Period,
then the Architect/Contract Administrator issues the Contractor with a notice to fix
the defects.
10.6 If the Contractor fails to comply with a notice under clause 10.5 promptly, the Client may
employ others to fix the defects. The Contractor shall be liable for any resulting costs.
G
11.2 The Contract is governed by the law of England and Wales.
11.3 The Contract does not limit other legal remedies available to the Parties.
11.4 Unless otherwise stated in the Contract, third parties have no rights under the Contract.
IN
11.5 If any court finds that some of the clauses in the Contract are unenforceable, the remaining
clauses shall remain in force, including clause 13 (Dispute Resolution).
H
that legislation.
11.7 The Contract is the entire agreement between the Parties. Any change to the Contract that
the Parties agree shall be written down and signed by both Parties.
11.8
Communication and Notices IS
All communication, notifications and notices under the Contract shall be in writing and,
BL
unless specifically stated otherwise under clause 3.1.2, shall be issued to the Parties with a
copy to the Architect/Contract Administrator.
11.9 All notices relating to suspension and/or termination of the Contract shall only be effective
from the date of delivery. Such notices are to be sent to the Parties by recorded delivery to
the addresses stated in items A and B of the Contract Details or as they may have been
PU
amended by notice.
12.2 If the Contractor fails to remedy the default within 14 days of receiving notice of intention to
terminate, the Contractor’s employment may be terminated by the Architect/Contract
Administrator issuing the Contractor with a notice of termination.
12.4 If the Client fails to remedy the default within 14 days of receiving the notice, the Contractor
may terminate its employment under the Contract by issuing the Client with a notice of
termination.
G
12.6 Either Party may terminate the Contractor’s employment if any event not caused by and not
the responsibility of the Parties prevents the Works from being carried out for a continuous
period of 60 days.
IN
Consequence on Termination
12.7 If the Contractor’s employment is terminated by either Party, except under clause 12.6,
for a reason:
H
12.7.1 s et
out under clauses 12.1 and 12.2, the Client shall be entitled to the costs
incurred in employing another contractor to complete the Works and to any other
reasonable costs incurred due to the termination
12.8
12.7.2 s et
IS
out under clauses 12.3 and 12.4, the Contractor shall be entitled to payment
for all costs and losses it incurred because of the termination, along with all
payments due under the Contract.
T he balance of payment due under clause 12.7.1 shall not be calculated until the related
BL
Works are completed by another contractor.
12.9 T he balance of payment due under clause 12.7.2 is within 14 days of either the Contractor
making an application for payment or the Architect/Contract Administrator certifying the
final payment due, whichever occurs first.
PU
12.11 The Client may cancel the Contract within 14 days of signing it and the Contractor shall
refund any payments received from the Client. However, if within the 14 days of signing the
Contract the Client agrees in writing for the Contractor to undertake any work and/or provide
services and/or goods, the Client shall be liable to pay for that work, services and/or goods.
R
Negotiation or Mediation
13.1 In the event of any dispute or difference arising under the Contract, the Parties may attempt
to settle the dispute, in the first instance, by negotiation or mediation as specified in item N
of the Contract Details.
Adjudication
13.2 Where it is stated in item N of the Contract Details that adjudication applies:
13.2.1 either Party may give notice at any time of its intention to refer a dispute or
difference to an Adjudicator
13.2.2 the appointment of the Adjudicator shall be made in accordance with the
procedure identified in item N of the Contract Details
13.2.3 the referral of the dispute to an Adjudicator shall be made within 7 days of the
issue of the notice
G
13.2.4 the Parties may agree who shall act as the Adjudicator or the Adjudicator shall be
a person nominated, at the request of either Party, by the nominating body
specified in item N of the Contract Details
IN
13.2.5 the Adjudicator may allocate between the Parties the costs relating to the
adjudication, including the fees and expenses of the Adjudicator
13.2.6 the adjudication rules will be as stated in item N of the Contract Details.
13.3 If the initial/preferred dispute resolution process is not successful, the dispute shall be
H
referred to the final resolution process, as set out in item N of the Contract Details.
Arbitration
13.4
13.4.1
IS
Where it is stated in item N of the Contract Details that arbitration applies:
where in item N as an alternative to litigation in the Contract Details an arbitration
agreement is made and either Party requires a dispute or difference (except in
BL
connection with the enforcement of any decision of an Adjudicator) to be referred
to arbitration, then that Party shall serve on the other Party a notice of arbitration
to that effect and the dispute or difference shall be referred to a person to be
agreed between the Parties or, failing agreement within 14 days of the date on
which the notice is served, a person appointed by the appointing body specified in
item N in the Contract Details on the application of either Party
PU
13.4.2 the Client or the Contractor may litigate any claim for a financial remedy which
does not exceed the financial limit provided by order made under section 91 of the
Arbitration Act 1996
13.4.3 in such arbitration the Construction Industry Model Arbitration Rules (CIMAR)
current at the date of the referral shall apply
13.4.4 the Arbitrator shall not have the power referred to in section 38(3) of the
Arbitration Act 1996.
A
Legal proceedings
IB
13.5 Either Party may start court proceedings to settle the dispute at any time.
R
Optional Clauses
14. Programme
14.1 If item O of the Contract Details is selected, then the Contractor shall submit a Programme,
in the format agreed, to the Architect/Contract Administrator no later than the date of the
pre-start meeting.
G
15. Contractor Design
IN
15.1 If item P of the Contract Details is selected, the Contractor shall:
15.1.1 u se
reasonable skill, care and diligence to the standard that a professional
designer competent in designing Works of a similar nature would use
15.1.2 subject to clause 15.1.1 ensure that its design is in accordance with the Client’s
H
specifications as stated in the Contract Documents.
15.2 At least 21 days before carrying out any part of the Works listed under item P of the
Contract Details, the Contractor shall submit details of its design to the Architect/Contract
15.3
Administrator for comment.
IS
T he Contractor shall notify the Architect/Contract Administrator of any discrepancies that it
finds between its designs and those designs prepared by, or on behalf of, the Client.
BL
15.4 T he Contractor retains the intellectual property rights in its design but grants the Client an
irrevocable licence and permission to use the design for the Works.
15.5 T he Contractor shall ensure that there is adequate professional indemnity insurance for its
design responsibilities, as set out in item P of the Contract Details, and that it remains in
place until the end of the limitation period.
PU
16.1 If item Q of the Contract Details is selected, then the following clauses shall apply:
16.1.1 theContractor is solely responsible for all the work, services and performance of
A
16.1.4 the Contractor is responsible for ensuring that insurance is maintained in respect
of work carried out by Required Specialists.
16.2 he Contractor shall, at the Start Date or thereafter as appropriate, employ the Required
T
Specialists to undertake the part(s) of the Works described in item Q of the Contract
Details.
16.3 he Contractor shall be responsible for any delay or additional costs arising from the
T
termination and replacement of a Required Specialist.
17.1 If item R of the Contract Details is selected, then the Works shall be divided into Sections
as described in the schedule under that item.
18.1 If item S1 or item S2 of the Contract Details is selected, then the part of item K of the
G
Contract Details regarding payment certificate frequency shall not apply.
18.2 If item S1 of the Contract Details is selected, then the Interim Payment Date shall be the
dates on which the milestones are achieved.
IN
18.3 hen the Architect/Contract Administrator is satisfied that a milestone has been achieved it
W
will notify the Parties.
18.4 If item S2 of the Contract Details is selected, the Interim Payment Date shall be 7 days after
the Architect/Contract Administrator has certified Practical Completion.
H
19.
19.1
Client Acting as Contract Administrator
IS
If item T of the Contract Details is selected, then the Client shall act as the Contract
Administrator for the Works. The Client shall carry out all duties and bear all the
BL
responsibilities of the Architect/Contract Administrator’s role under the Contract.
20.1 If item U of the Contract Details is selected, then the Contractor shall provide, before
the Start Date, evidence of the Insurance Backed Guarantee and the nature of the cover.
The guarantee shall:
20.1.1 b e issued by a reputable organisation
20.1.2 b e for the benefit of the Client
20.1.3 b ecome effective if the Contractor ceases to trade.
A
21.1 If item V of the Contract Details is selected, then the Contractor shall provide the Client with
a New Building Warranty, as set out in that item, within a reasonable period following
Practical Completion.
R
22.1 If item W of the Contract Details is selected, then the Client shall provide evidence of its
ability to pay the Contract Price within 21 days of receiving a request from the Contractor.
Such request shall be made no later than 21 days prior to the Start Date.
22.2 If the Client fails to provide such evidence, the Contractor may suspend some or all of its
obligations under clause 8 of the Contract.
Appendix
G
IN
Notice of Cancellation
H
The Client has the right to cancel the Contract, for any reason, by sending (including by email)
a notice of cancellation to the Contractor within 14 days of signing the Agreement.
The Client [Client’s name] hereby gives notice that the RIBA
Domestic Building Contract 2018 entered into with the Contractor
[Contractor’s name or name of business] on [date stated at end of Agreement
PU
section] is cancelled.
Yours sincerely
[Client’s signature]
[Date]
A