Ref N° 24 - PRODUCED WATER HANDLING - PHILOSOPHY
Ref N° 24 - PRODUCED WATER HANDLING - PHILOSOPHY
Ref N° 24 - PRODUCED WATER HANDLING - PHILOSOPHY
&
CONSTRUCTION
1. INTRODUCTION
1.1. FOREWORD
1.2. OBJECTIVES
1.3. SCOPE
2. HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS
3. FUNCTIONAL REQUIREMENTS
3.1. GENERAL
3.2. SYSTEM CONFIGURATION
3.3. HYDROCYCLONES
3.4. PUMPS
3.5. CONTROL VALVES
3.6. DEGASSER VESSELS
3.7. FILTRATION
3.8. CHEMICAL INJECTION
3.9. SAMPLING & ANALYSIS
3.10. FLEXIBILITY
3.11. CORROSION & EROSION
4. SPARING AND MAINTENANCE REQUIREMENTS
5. LOCATION AND ACCESS REQUIREMENTS
6. START-UP REQUIREMENTS
7. COMMISSIONING REQUIREMENTS
1.1. FOREWORD
1.2. OBJECTIVES
1.3. SCOPE
The philosophy requirements apply to all items of equipment used in the handling
of produced wate
All facilities installed shall comply with the HSE Philosophy requirements in
addition to the following:
2.1 Produced water systems normally give rise to an HP/LP interface between
upstream production systems and downstream degassing and treatment
equipment. The design shall provide adequate protection facilities for scenarios
such as gas blow by.
3.1. GENERAL
3.1.1 The produced water handling facilities shall remove the oil and
particulates from the produced water to the specifications stated in the Basis
of Design. The recovered oil shall be recycled and clean water routed to
water injection system.
3.2.3 The pipework configuration shall account for any possible sand
contained in the produced water and the possibility of blockage.
Consideration shall be given to the future provision of sand removal
facilities (e.g. sand cyclones) on upstream systems.
3.3.1 The design shall allow future retrofit of enhanced coalescence devices
such as Cyclotech PECT-F.
3.3.4 The trims supplied with control valves shall be suitable for the predicted
start-up water rates. This may mean that a trim change or valve
change-out is required for the maximum water case, which tends to
occur late in field life. The ability to do this shall be incorporated in the
plant design.
3.3.6 Vent and drain connections will be provided to allow each hydrocyclone
vessel to be taken offline and dismantled individually. Drain
connections in produced water service should be routed to Closed
Drains, however care should be taken to ensure sand/solids are not
routed to the drains.
3.3.7 Sample points shall be provided at the inlet, outlet and reject streams
of each hydrocyclone vessel to enable assessment the hydrocyclone
vessel performance.
3.3.8 Valved connections shall be provided to allow the on-line fitting of local
pressure gauges to all inlet and outlet lines of each hydrocyclone
vessel.
3.3.9 Hydrocyclone liner types shall be common throughout the facility. This
is to allow optimum selection of the number of provided liners.
3.4.2 Pumps fitted in the produced water system should be designed as low
shear. The design shall be robust and able to withstand vibration, and
corrosion. They shall also be resistant to the presence of sand in the
produced water, if sand production is expected. The design shall avoid
the need for any inline items that could cause droplet shear.
3.4.4 Pump suction strainers shall be provided. The strainers shall be easy
to access and change out (e.g. lift-out basket type) for critical service
parallel units should be considered. A local differential pressure gauge
shall be provided. Strainers shall be robust and be capable of being
cleaned by a water pressure jet. Low suction pressure trip devices
should be located downstream of the strainer.
3.4.6 Casing drains for pumps in produced water service shall be piped to
closed drains.
3.5.3 The potential for cavitation of the produced water shall be considered
and addressed, especially for services where flow is from a pressurised
source into a low pressure or atmospheric system. Consideration shall
be given to installing such valves at a low point so that there is a
constant static head back pressure on the valve outlet.
3.5.4 Control valves need to be readily accessible and robust to allow easy
cleaning as they are a likely site for scale deposition.
3.6.1 Gas liberated from a produced water degasser vessel should be routed
to a low-pressure flare system for disposal.
3.6.4 Degasser inlet device design shall be such that it allows liberated gas
bubbles to assist in ‘floating’ oil droplets to the surface and thus
enhance separation efficiency.
3.6.6 When sand production is likely, the degasser shall be equipped with
proven sand washing facilities.
3.7. FILTRATION
3.7.4 A flow sharing system should be installed to prevent a filter that has
been backwashed from accepting more than its design flow.
Restriction orifice plates or preferably, a flow control loop may achieve
this for each unit.
3.7.6 Vent and drain connections shall be provided on each filter unit to allow
the unit to be drained prior to opening the unit.
3.7.7 Drain connections from produced water filter units shall be piped to
Closed Drains.
3.9.1 Sampling points shall be provided with sampling quills. These shall be
removable under line pressure and mechanically robust for main
process line flow rate and condition (e.g. slugging). Adequate space
shall be provided to allow use of an appropriate extraction tool.
3.9.2 Double block and bleed isolation will be provided on all sample points.
3.9.4 The design of the sampling points shall ensure that the gas liberated
when sampling will not activate gas detectors.
3.9.5 A sample point shall be provided at each outlet of the produced water
processing system. This sample point shall have the capability of
isokinetic sampling for oil-in-water content and analysis of sand
content.
3.10. FLEXIBILITY
3.10.2 If water injection is not available the cleaned produced water shall be
disposed to an alternative location, e.g. retention pond. The water
quality shall meet requirement for such alternative routes.
3.11.2 The layout of produced water system shall ensure any leaks does not
cause corrosion of other equipment
4.1 Reject oil control valves tend to have small trim sizes and therefore are
prone to blockage. Due to their small size, a spare valve shall be kept in
stock to allow rapid change-out.
5.2 For hydrocyclones, the main inlet and outlet vessel connections shall be
located on the vessel bottom. Hydrocyclone liners shall be installed from
the top downwards and be easily removable from the vessel. This is to
mitigate blockages due to sand, scale, etc
6. START-UP REQUIREMENTS
6.1 Consideration shall be given to the requirement to recycle any off spec.
product that may result from start-up activities.
6.2 Produced water will have to be recycled to clean-up system before forward
flow for re-injection is permitted.
7. COMMISSIONING REQUIREMENTS
7.1 All hydrocyclone vessels should be opened prior to commissioning to
check the quantity of liners that are installed, the fitted parts are as per
design, and that the parts inside the vessel have not been damaged in
transit.