Short Circuit Calcs
Short Circuit Calcs
The task may seem overwhelming at first, but following a methodical step-by-step
procedure can keep you from getting tripped up
When you apply these requirements to a circuit breaker, you must calculate the
maximum 3-phase fault current the breaker will be required to interrupt. This current
can be defined as the short-circuit current available at the terminals of the protective
device.
You can assume that 3-phase short circuits are “bolted,” or have no impedance. In
addition, a 3-phase short circuit can be considered a balanced load, which means you
can use a single-phase circuit to analyze one of the phases and the neutral.
Distribution equipment, such as circuit breakers, fuses, switchgear, and MCCs, have
interrupting or withstand ratings defined as the maximum rms values of symmetrical
current. A circuit breaker can't interrupt a circuit at the instant of inception of a short.
Instead, due to the relay time delay and breaker contact parting time, it will interrupt
the current after a period of five to eight cycles, by which time the DC component
will have decayed to nearly zero and the fault will be virtually symmetrical.
Closing a breaker against an existing fault makes it possible to intercept the peak of
the asymmetrical short-circuit current, which is greater than the rms value of the
symmetrical current. For this reason, equipment is also tested at a particular test X/R
ratio value typical to a particular electrical apparatus, such as switchgear,
switchboards, or circuit breakers, and is designed and rated to withstand and/or close
and latch the peak asymmetrical current described above.
The classical approach and the method defined by ANSI/IEEE are two such industry-
accepted methods for
calculating short circuits.
Both methods assume that
the fault impedance is zero
(bolted short circuit) and the
pre-fault voltage is constant
during the evolution of the
fault. In actuality, the fault
has its own impedance, and
the voltage drop, due to the
short-circuit current, lowers
the driving voltage.
The IEEE standard permits the exclusion of all 3-phase induction motors below 50 hp
and all single-phase motors. Hence, no reactance adjustment is needed for these
motors. The Chart at right clarifies the ANSI/IEEE procedure.
Classical calculation. Begin by converting all impedances to “per unit” values. Per
unit base values and formulae used are as follows:
Sbase =100MVA
Vbase =26.4 kV
Let's run through an example calculation to make this discussion a little more
tangible. Refer to the one-line diagram in the Figure above with the following input
data:
ZFault=(Zutility+ZT1)||ZMotor1||ZMotor2=(0.0021+j0.083+0.005+j0.07)||(0.49+j13.8)||
(29.8+j298)=0.166+j2.817 pu=2.823ej86.6
The peak duty the breaker is required to close and latch may be evaluated using the
following formula, which constitutes a multiplier to the rms current, which was
calculated above:
Use Table 1, page 1 in ANSI C37.06-1997 Preferred Ratings and Related Required
Capabilities to rate new switchgear. It's useful in comparing calculated duty (4,916A
and 12,692A) and standard ratings. The Table includes sample values extracted from
the ANSI table.
For each network, Thevenin equivalent resistance and Thevenin equivalent reactance
will then be combined in order to obtain the equivalent Thevenin impedance. This is
the significant difference between the ANSI/IEEE procedure and the classical
calculation method.
Then they'll be combined as total fault impedance ZFault, which will yield ISC3-phase and
IPeak according to the formulas.
In this case, the total fault resistance and fault reactance (with adjustments) will be
calculated separately as already seen.
ISC3-phase, symmetrical duty is calculated as it was in the classical method. However, it's
typically characterized by a smaller magnitude because the Zfault “interrupting” current
is larger than the one in the momentary network calculation.
Which method is better? Both methods basically provide the same results. There are
no theoretical reasons to prefer one to the other, only practical reasons. The
ANSI/IEEE approach is the evolution of a method conceived in the '70s in the United
States, when no computer-assisted calculations were available. ANSI/IEEE C37.010-
1999 can only be used at medium or high voltages and only at 60 Hz. Calculation
programs have been developed to determine fault currents that apply the multiplier
factors called for in this standard. In fact, some clients may ask for the application of
this calculation methodology by contract. Manufacturers may also recall the
ANSI/IEEE standard in their catalogues. The classical method is used mainly in low-
voltage studies and can also be applied at 50 Hz. It's a well-known procedure because
it's a common topic in every “power system” college course.