Dense Bituminous Macadam (hereinafter referred to as
“DBM”) is a binder course used in the construction of all
SPONSORED
flexible roads. DBM is used for roads with more number of
heavy commercial vehicles.
FEELING LUCKY
Machinery
Introduction to EVM
1. Hot mix plant of suitable capacity
2. End Dumpers
3. Paver Finisher
4. Vibratory Rollers of capacity 80-100 KN static weight or
PROJECT MANAGEMENT
pneumatic tyred roller of capacity 120-150KN weight. Introduction to Earned Value
5. Bitumen sprayer Management
6. Camber board and 3 m straight edge APRIL 22, 2021
7. Mechanical broom
8. Air Compressor
9. Water Tanker L&T
10. Survey kit etc.,
Material
1. Paving Bitumen of penetration grade VG 30 shall be used
NEWS
generally and in accordance with clause 505.2.1 of L&T bags contract from
MoRT&H. Chennai Metro Rail
2. Coarse aggregate shall be of clean, strong, durable, Corporation Limited
MAY 15, 2021
cubical shape and free from other deleterious matter
and adherent coating as per clause 505.2.5 of MoRT&H. Methodology of Earthwork
3. Los Angeles Abrasion value for coarse aggregate shall
not be more than 35% when tested as per IS: 2386 (Part
4).
4. Aggregate Impact Value shall not be more than 27%
METHODOLOGY
when tested as per IS: 2386 (Part 4). Construction Methodology of
5. Flakiness and Elongation Indices (Combined) shall not be Earthwork
more than 35% when tested as per IS: 2386 (Part 1). SEPTEMBER 15, 2020
10. The filler shall be satisfy as per MoRT&H specification. What is Fusion Bonded Epoxy
Coating (FBE Coating)
Preparation of Material
Aesthetics of Bridges
Dense Bituminous Macadam works shall be carried as per
the MoRT&H Clause 505. Curing of Concrete in
Construction works
The aggregate for Dense Bituminous Macadam shall
conform to requirements specified in the table 500.8 of Construction Methodology of
Bituminous Concrete
MoRT&H specifications.
Methodology of Rectification
Bitumen: Viscosity grade paving bitumen confirming to IS:
path in DBM
73-2006. The grade shall be used as per requirement.
November 2022
April 2022
February 2022
May 2021
April 2021
January 2021
The proportioning shall be done by determining the
September 2020
individual gradation of the individual ingredients and the
blend determined by trail and error method so as to July 2020
achieve the gradation specified. Dense Bituminous
June 2020
Macadam shall be constructed as per the MoRT&H
specifications, Clause 505.
CATEGORIES
As per MS-2 sixth edition, VA (Air Voids), VMA (Voids in
Mineral Aggregates), VFB (Voids filled with Bitumen), Stability Buildings
and flow shall be determined for the material so blended.
Construction
The mixture shall meet the requirements as per MoRT&H Equipment
table 500.11.
Facts
Mix Design with proportion of all materials grading/test
Infra works
reports shall be submitted to respective authorities and trail
patch shall be constructed before actual commencement Methodology
of Dense Bituminous Macadam work.
News
5. The mix shall be unloaded gently into the paver hopper Comments feed
and paving shall be started uniformly within the required
WordPress.org
temperature.
Rectification Procedure
1. Any high spots in the existing black topped surface shall
be removed by manual or other method, and all loose
material shall be removed to the required specifications.
2. Where the maximum thickness of profile corrective
course will be not more than 75 mm, the profile
corrective course shall be constructed as an integral
part of the overlay course. In other cases, the profile
corrective course shall be constructed as a separate
layer, adopting such construction procedures and using
such equipment, to lay the specified type of material, to
the thickness and tolerance as specified for the course to
be provided.
3. The profile corrective course shall be laid to tolerance
and densities as specified for wearing course if it is laid
integral with the wearing course. The profile corrective
course shall be laid to tolerance and densities as
specified for base course, it it is to be covered with a
wearing course layer.
4. The levels shall be checked before paving and after
compaction with respect to the designated levels. If there
is any variation in the levels, the same shall be adjusted
in further paving.
5. Initial or break down rolling shall be carried out
immediately following close to the paver in longitudinal
direction from lower edge to upper edge with 80 – 100 KN
static weight of smooth wheeled roller. The speed of the
roller shall be maintained not more than 5 Km/hr.
6. Intermediate rolling shall be done with 80-100 KN static
weight of vibratory roller or with a pneumatic tyred roller
of 120-150 KN weight having Tyre pressure of atleast 0.56
Mpa and it should be continues till the required
compaction is achieved.
7. Traffic shall be allowed after completion of the final
rolling when the mix has cooled down to the surrounding
temperature.
Quality Control
This shall be done as per table 900-3 of MOST (Ministry of
Surface Transport).
Environmental Control
1. While producing or crushing of aggregates in the crusher
plant care should be taken in respect of controlling and
minimizing flow of duct, noise and use of blasting
materials such as dynamite, safety aspects to workers
are also vital and should be taken of.
2. Care will be taken to prevent spilling of material from the
trucks during transportation.
3. Excess material, if any, after using in the pavement
should be carefully disposed off in the designated area.