Conditions of Contract - Proforma
Conditions of Contract - Proforma
Conditions of Contract - Proforma
CONDITIONS OF CONTRACT
Agreement/Work-order.
The company shall, in addition to other remedial steps to be taken as provided in the conditions
of contract, be entitled to cancel the contract in full or in part, if the contractor
a. makes default in proceeding with the works with due diligence and continues to do so even af-
ter a notice in writing from the Engineer-in-charge, then on the expiry of the period as specified in
the notice
Or
b. fails to achieve a monthly agreed quantity of 70% (Seventy percent) for a period of 6(six) con-
secutive month or for cumulative period of six months within any continuous period of
18(eighteen) months, save and except to the extent of non-availability caused by i) a Force
Majeure event or ii) an act of omission of company, not occurring due to any default of the con-
tractor.
Note: - In such cases the contractor may be Banned for minimum one year from participating in
future bidding allowing the present business to continue without going into termination of the con-
tract. (Not to be part of Tender Document- Procedure for banning of business shall be followed as
per Guidelines of Banning of Business.)
Or
c. commits default/breach in complying with any of the terms and conditions of the contract and
does not remedy it or fails to take effective steps for the remedy to the satisfaction of the Engineer-
in-charge, then on the expiry of the period as may be specified by the Engineer-in-charge in a notice
in writing
Or
d. fails to complete the work or items of work with individual dates of completion, on or before the
date/dates of completion or as extended by the company, then on the expiry of the period as may
be specified by the Engineer-in-charge in a notice in writing
Or
e. shall offer or give or agree to give any person in the service of the company or to any other per-
son on his behalf any gift or consideration of any kind as an inducement or reward for act/acts of
favour in relation to the obtaining or execution of this or any other contract for the company
Or
f. obtains a contract with the company as a result of ring tendering or other non- bonafide method
of competitive tendering
Or
g. transfers, sublets, assigns the entire work or any portion thereof without the prior approval in
writing from the Engineer-in-charge. The Engineer-in- charge may give a written notice; can-
cel/terminate the whole contract or portion of it in default. The approving authority shall be TAA or
CMD if originally awarded by empowered Committee of Directors headed by Chairman/FDs/CMD or
Board.
The Engineer-in-charge may by giving a written notice, cancel the whole contract or portion of it in
default.
10.1 The contract shall also stand terminated under any of the following circumstances:
a) If the contractor being an individual in the case of proprietary concern or in the case of a
partnership firm any of its partners is declared insolvent under the provisions of Insolvency Act
for the time being in force, or makes any conveyance or assignment of his effects or composition
or arrangement for the benefit of his creditors amounting to proceedings for liquidation or
composition under any Insolvency Act.
b) In the case of the contractor being a company, its affairs are under liquidation either by a
resolution passed by the contractors company or by an order of court, not being a voluntary
liquidation proceedings for the purpose of amalgamation or reorganization, or a receiver or
62
CONDITIONS OF CONTRACT
manager is appointed by the court on the application by the debenture holders of the
contractor's company, if any.
c) If the contractor shall suffer an execution being levied on his/their goods, estates and allow it to
be continued for a period of 21 (twenty-one) days.
d) On the death of the contractor being a proprietary concern or of any of the partners in the case
of a partnership concern and the company is not satisfied that the legal representative of the
deceased proprietor or the other surviving partners of the partnership concern are capable of
carrying out and completing the contract. The decision of the company in this respect shall be
final and binding which is to be intimated in writing to the legal representative or to the
partnership concern.
10.2 On termination of the contract or on cancellation of the contract, the Engineer- in-charge shall
have powers:
a. To take possession of the site and carry out balance work through any other agency.
b. To give the contractor or his representative of the work, 7 (seven) days’ notice in writing for tak-
ing final measurement for the works executed till the date of cancellation or termination of the
contract. The Engineer-in-Charge shall fix the time for taking such final measurement and intimate
the contractor in writing. The final measurement shall be carried out at the said appointed time
notwithstanding whether the contractor is present or not. Any claim as regards measurement
which the contractor is to make shall be made in writing within 7 (seven) days of taking final meas-
urement by Engineer-In-charge as aforesaid and if no such claim is received, the contractor shall be
deemed to have waived all claims regarding above measurements and any claim made thereafter
shall not be entertained.
c. After giving notice to the contractor to measure up the work of the contractor and to take such
whole or the balance or part thereof, as shall be unexecuted out of his hands and to give it to an-
other contractor or take up departmentally, to complete the work. The contractor whose contract
is terminated shall not be allowed to participate in future bidding for period of minimum one year.
In such an event, the contractor shall be liable for loss/damage suffered by the employer because
of action under this clause and to compensate for this loss or damage, the employer shall be enti-
tled to recover higher of the following:
ii) 20% of value of incomplete work. The value of the incomplete work shall be calculated for the
items and quantities remaining incomplete (as per provision of agreement) at the agreement rates
including price variation as applicable on the date, when notice in writing for termination of work
was issued to the contractor.
It is being clarified that the above liability is over and above the penalties payable by the contractor
on account of shortfall in quantities as per provision of clause 6.
The amount to be recovered from the contractor as determined above, shall, without prejudice to
any other right or remedy available to the employer as per law or as per agreement, will be recov-
ered from any money due to the contractor on any account or under any other contract and in the
event of any shortfall, the contractor shall be liable to pay the same within 30 days. In case of fail-
ure to pay the same the amount shall be debt payable.
63
CONDITIONS OF CONTRACT
In the event of above course being adopted by the Engineer-in-charge, the contractor shall have no
claim to compensation for any loss sustained by him by reasons of his having purchased materials,
equipments or entered into agreement or made advances on any account or with a view to the
execution of work or performance of the contract. And in case action is taken under any of provi-
sion aforesaid, the contractor shall not be entitled to recover or to be paid any sum for any work
thereof or actually performed under this contract unless and until the engineer-in-charge has certi-
fied in writing the performance of such work and value payable in respect thereof and he shall only
be entitled to be paid the value so certified.
The need for determination of the amount of recovery of any extra cost/expenditure or of any
loss/damage suffered by the company shall not however arise in the case of termination of the
contract for death/demise of the contractor as stated in 10.1(d).
The contractor shall carry out the instructions given in this respect by the Engineer-In Charge & if
such suspension exceeds 45 (forty-five) days, the contractor will be compensated on mutually agreed
terms.
If at any time after acceptance of the tender the company decides to abandon or reduce the scope of
work for any reason whatsoever the company, through its Engineer-in-Charge, shall give notice in
writing to that effect to the contractor and contractor shall act accordingly in the matter. In the event
of abandonment, the contractor shall have no claim to any payment of compensation or otherwise
whatsoever, other than those mentioned below: -
a) to pay reasonable amount assessed and certified by the Engineer-in-Charge of the expenditure
incurred, if any, by the contractor on preliminary works at site e.g. temporary access roads,
temporary construction for labour and staff quarters, office accommodation, storage of
materials, water storage tanks and water supply for the work including supply to labour/ staff
quarters, office etc.
b) to pay the contractor at the contract rates full amount for works executed and measured at site
up to the date of such abandonment.
c) to pay for the materials brought to site or to be delivered at site, which the contractor is legally
liable to pay, for the purpose of consumption in works carried out or were to be carried out but
for the foreclosure, including the cost of purchase and transportation and cost of delivery of such
materials. The materials to be taken over by the company should be in good condition and the
company may allow at its discretion the contractor to retain the materials in full or in part if so
desired by him and to be transported by the contractor from site to his place at his own cost with
64
CONDITIONS OF CONTRACT
due permission of the EIC.
d) to take back the materials issued by the company but remaining unused, if any, in the work on
the date of abandonment/reduction in the work, at the original issue price less allowance for any
deterioration or damage caused while in custody of the contractor.
e) to pay for the transportation of tools and plants of the contractor from site to contractor's place
or to any other destination, whichever is less.
10.4.01 The contractor shall, if required by the Engineer-in-Charge, furnish to him books of accounts,
papers, relevant documents as may be necessary to enable the Engineer-in-Charge to assess the
amounts payable in terms of clauses 10.4 (a) (c) & (e) of the contract. The contractor shall not have
any claim for compensation for abandonment of the work, other than those as specified above.
If the progress of the work or of any portion of the work is unsatisfactory, the Engineer-in-Charge,
after giving the contractor 15 days’ notice in writing, without cancelling or terminating the contract,
shall be entitled to employ another Agency for executing the job or to carry out the work
departmentally or contractually through tendering / limited tendering process, either wholly or
partly, debiting the contractor with cost involved in engaging another Agency or with the cost of
labour and the prices of materials, as the case may be. The certificate to be issued by the Engineer-
in-Charge for the cost of the work so done shall be final and conclusive and the extra cost, if any,
shall be borne by the contractor. However, when this clause is invoked, penalty will not be applicable
other than on account of delayed completion.
The value of the work taken away shall be calculated for the items and quantities taken away at the
agreement rates including price variation as applicable on the date, when notice in writing for taking
away part work was issued to the contractor. The contractor, from whom part work is being taken
out, shall not be allowed to participate in the tendering process if any.
If the expenses incurred by the department is less than the amount payable to the contractor at his
agreement rates, the difference shall not be payable to the contractor.
In the event of above course being adopted by the Engineer-in-Charge, the contractor shall have no
claim to compensation for any loss sustained by him by reasons of his having purchased or procured
any materials or entered into any engagements or made any advance on any account or with a view
to the execution of the work or the performance of the contract.
Except in cases where the contract provides for "Performance Test" before issue of Defect Liability
certificate, in which case the issue of Defect Liability certificate shall be in accordance with the
procedure specified therein, the contractor shall give notice of completion of work, as soon as the
work is completed, to the Engineer-in-Charge. The Engineer-in-Charge and or any other Officer,
nominated for the purpose by the company, shall within 30 (thirty) days from the receipt thereof,
inspect the work and ascertain the defects/deficiencies, if any, to be rectified by the contractor as
also the items, if any, for which payment shall be made at reduced rate.
If the defects, according to the Engineer-in-Charge are of a major nature and the rectification of
which is necessary for the satisfactory performance of the contract, he shall intimate in writing the
defects and instruct the contractor to rectify the defects/remove deficiencies within the period and
in the manner to be specified therein. In such cases Defect Liability Certificate will be issued by the
EIC after the above rectifications are carried out/ deficiencies are removed by the contractor to the
satisfaction of EIC.
65
CONDITIONS OF CONTRACT
In the event there are no defects or the defects/ deficiencies are of a minor nature and the Engineer-
in-Charge is satisfied that the contractor has already made arrangements for rectification, or in the
event of contractor's failure to rectify the defects for any reason whatsoever, the defects can be
rectified by the company departmentally or by other means and the 50% of the security deposit of
the contractor shall be sufficient to cover the cost thereof, he shall issue the Defect Liability
Certificate ( Taking Over Certificate with list of defects )indicating the date of completion of the work,
defects to be rectified, if any, and the items, if any, for which payment shall be made at reduced rate
indicating reasons there for and with necessary instructions to the contractor to clear the site/place
of work or all debris/ waste materials, scaffoldings, sheds, surplus materials etc. making it clean.
12.1 In cases where separate period of completion for certain items or groups of items are specified
in the contract, separate Defect Liability certificate for such items or groups of items may be issued
by the Engineer-in-Charge after completion of such items on receipt of notice from the contractor
only in the event the work is completed satisfactorily in every respect.
Refund of security deposit and payment of final bill shall, however, be made on completion of the
entire contract work, but not on completion of such items of work.
12.2 Before the date fixed for completion of work, the work as well as the site of work are to be
made clean after removal of rubbish, scaffolding, surplus materials, temporary structures etc.
12.3 In case of contractor's failure to clear the site, the EIC shall have right to get the work done. The
cost thereof shall be recovered from the final bill of the contractor.
i) The company reserves the rights to let other contractors also work in connection with the Project
and the contractor/contractors shall co-operate in the works for the introduction and stores and
materials and execution of his/their works.
ii) The contractor/contractors shall keep on the work site during the progress a competent and
experienced Resident Engineer exclusively for the work and necessary assistants who shall represent
the contractor(s). The contractor shall employ, on the site in connection with the execution and
maintenance of the work, technical and managerial staff as mentioned below.
The contractor shall intimate the Engineer-in-Charge in writing the names, qualifications, experience
and full postal address of each and every technical personnel employed at site by him.
The contractor(s) shall not be allowed to execute the work unless he/they engage the required
technical staff as assessed by Engineer-in-charge or as specifically mentioned in the bid. The delay on
this account, if any, shall be the contractor's responsibility.
66
CONDITIONS OF CONTRACT
iii) The contractor / contractors shall employ only competent, skilful and orderly men to do the work.
The Engineer-in-Charge shall have the right to ask the contractor/ contractors to remove from the
work site any men of the contractor/contractors who in his opinion is undesirable and the
contractor/contractors will have to remove him within 3 (three) hours of such orders.
The contractor shall employ apprentices in the execution of the contract work as required under
Apprentices Act.
The contractor shall further be responsible for making arrangements at his own cost, or
accommodation and social needs of the staff and workers under his employment.
iv) Precautions shall be exercised at all times by the contractor(s) for the protection of persons
(including employees) and property. The safety required or recommended by all applicable laws,
codes, statutes and regulations shall be observed by the contractor(s). In case of accidents, the
contractor(s) shall be responsible for compliance with all the requirements imposed by the
Workmen's Compensation Act or any other similar laws in force and the contractor shall indemnify
the company against any claim on this account.
All scaffoldings, ladders and such other structures which the workmen are likely to use shall be
examined by the Engineer-in-Charge or his authorized representative whenever they want and the
structure must be strong, durable, and safe and of such design as required by Engineer-in-Charge.
The contractor / contractors shall at all times exercises reasonable precautions for the safety of
employees in the performance of his/their contract and shall comply with all applicable provisions of
the safety laws drawn up by the State Govt. or Central Govt. or Municipalities and other authorities
in India. The contractor/contractors shall comply with the provision of the safety hand book as
approved and amended from time to time by the Government of India.
v) The contractor / contractors shall familiarize themselves with and be governed by all laws and
rules of India and Local statutes and orders and regulations applicable to his/ their work.
vi) The contractor shall maintain all records as per the provision made in the various statutes
including Contract Labour (Regulation & Abolition) Act, 1970 and the Contract Labour (Regulation &
Abolition) Central Rules,1971, Minimum Wages Act, Workmen Compensation Act etc. and latest
amendment thereof. Such records maintained by the contractor shall be opened for inspection by
the Engineer-in-Charge or by the nominated representative of the Principal Employer.
vii) The contractor/ contractors shall provide facilities for the sanitary necessities of all persons
employed on the work shall be constructed and maintained in the number, manner and place
approved or ordered by the Engineer-in-Charge. The contractor/ contractors shall vigorously prohibit
committing of nuisance at any other place. Cost of all works under this item shall be covered by the
contractor/contractor's tendered rates.
67
CONDITIONS OF CONTRACT
viii) The contractor/contractors shall furnish to the Engineer-in-Charge or his authorized
representative with work reports from time to time regarding the contractor / contractors
organization and the progress made by him / them in the execution of the work as per the contract.
ix) All duties, taxes (excluding Goods and Services Tax (GST) & GST Compensation Cess (if applica-
ble) only) and other levies, royalty, building and construction workers cess (as applicable in States)
payable by the bidder/Contractor under the Contract, or for any other cause as applicable on the
last date of submission of Bid, shall be included in the rates, prices and the total Bid Price submit-
ted by the Bidder. Applicable GST, if any, either payable by bidder or by company under reverse
change mechanism shall be computed by system in BOQ sheet as per predefined logic.
All investments, operating expenses, incidentals, overheads, leads, lifts, carriages, tools and plants
etc. as may be attendant upon execution and completion of works shall also be included in the
rates, prices and total Bid price submitted by the bidder.
However, such duties, taxes, levies etc. which is notified after the last date of submission of Bid
and/or any increase over the rate existing on the last date of submission of Bid shall be reimbursed
by the company on production of documentary evidence in support of payment actually made to
the concerned authorities.
Similarly, if there is any decrease in such duties, taxes and levies the same shall become recovera-
ble from the contractor. The details of such duties, taxes and other levies along with rates shall be
declared by the bidder.
The item wise rate quoted by bidder shall be inclusive of all taxes, duties & levies but excluding
GST & GST Compensation Cess, if applicable. The payment of GST and GST Compensation Cess by
service availer (i.e. CIL/Subsidiary) to bidder/contractor (if GST payable by bidder/contractor)
would be made only on the latter submitting a Bill/invoice in accordance with the provision of rel-
evant GST Act and the rules made there under and after online filing of valid return on GST portal.
Payment of GST & GST Compensation Cess is responsibility of the service provider/contractor.
Further, any GST credit note required to be issued by the bidder / contractor under the GST
provisions should be issued within the time limit prescribed under the GST law.
CONDITIONS OF CONTRACT
Further, where any damages or compensation becomes payable by either the Company or the
bidder / contractor pursuant to any provision of this Agreement, appropriate GST wherever
applicable as per the GST provisions in force shall also apply in addition to such damages or
compensation.
Note: During the execution of the contract if the GST status of the bidder changes, then the payment
of GST, if any, to the contractor will be made as per the GST status declared by the bidder during
tender stage based on which cost to company has been ascertained or at actuals, whichever is lower.
x) The contractor / contractors shall make his / their own arrangement for all materials, tools, staff
and labourer required for the contract, which shall include cost of lead, lift, loading, unloading,
railway freight, recruiting expenses and any other charges for the completion of the work to entire
satisfaction of the company.
xi) The contractor / contractors shall make their own arrangement for carriage of all materials to the
work site at his/their own cost.
xii) The work shall not be sublet to any other party, unless approved by Engineer-in-Charge, in
writing. Prior permission is required to be taken from the owner for engagement of sub-contractor in
part work/piece rated work.
xiii) a) No fruit trees or valuable plants or trees with trunk diameter exceeding 150mm shall be
pulled, destroyed or damaged by the contractor/contractors or any of his/their employees without
the prior permission of the company, failing which the cost of such trees or plants shall be deducted
from the contractor/contractors dues at the rate to be decided by the company. The rates quoted
are supposed to include clearance of shrubs and jungles and removal of such trees up to 150 mm
dia., as will be permitted by the Engineer-in-Charge in writing.
b) Anything of historical or other interest or of significant value unexpectedly discovered on the site
is the property of the employer. The Contractor is to notify the Nodal Officer or his nominee of such
discoveries and carry out the Nodal Officer or his nominee’s instructions for dealing with him.
xiv) The contractor / contractors shall not pay less than the minimum wages to the labourer engaged
by him/them as per Minimum Wages Act or such other legislation or award of the minimum wage
fixed by the respective State Govt. or Central Govt. as may be in force. The contractor / contractors
shall make necessary payments of the provident fund for the workmen employed by him for the
work as per the laws prevailing under provisions of CMPF and allied scheme and Miscellaneous
Provisions Act, 1948 or Employees Provident Fund and Miscellaneous Provisions Act 1952 as the case
may be.
xv) All accounts shall be maintained properly and the company shall have the right of access and
inspection of all such books of accounts etc., relating to payment of labourer in online mode
including payment of provident fund considered necessary.
xvi) The contractor shall in additions to any indemnity provided by the relevant clauses of the
agreement or by law, indemnify and keep indemnified for the following:
a) The company or any agent or employee of the company against any action, claim or proceeding
relating to infringement or use of any patent or design right and shall pay any royalties or other
charges which may be payable in respect of any article or material included in the contract.
However, the amount so paid shall be reimbursed by the company in the event such infringement
has taken place in complying with the specific directions issued by the company or the use of such
article or material was the result of any drawing and/or specifications issued by the company after
submission of tender by the contractor. The contractor must notify immediately after any claim being
made or any action brought against the company, or any agent or employee of company in respect of
69
CONDITIONS OF CONTRACT
any such matter.
b) The company against all claims, damages or compensation under the provisions of payment of
Wages Act, 1938, Minimum Wages Act, 1948, Employer's Liability Act, 1938, The Workmen's
Compensation Act, 1923, Industrial Dispute Act, 1947, Mines Act as applicable, Employees State
Insurance Act 1948 and Maternity Benefit Act, 1961, Acts regulating P.F. or any modification thereof
or any other law relating thereto and rules made there under from time to time, as may be
applicable to the contract which may arise out of or in consequence of the construction or
maintenance or performance of the work under the contract and also against costs, charges and
expenses of any suit, action or proceedings arising out of any accident or injury.
c) The company against all losses and claims for injuries or damages to any third party or to any
property belonging to any third party which may arise out of or in consequence of the construction
or maintenance or performance of the work under the contract and against all claims/demands
proceedings/damages, cost charges and expenses whatsoever in respect of or in relation thereto.
xvii)The contractor is under obligation to hand over to the company the vacant possession of the
completed building structures failing which the Engineer-in-Charge can impose a levy upon the
contractor up to 5% of the total contract value for the delay in handing over the vacant possession of
the completed works after giving a 15 (fifteen) days’ notice to the contractor.
xviii) Insurance – The contractor shall take full responsibility to take all precautions to prevent loss or
damage to the works or part thereof for any reasons whatsoever (except for reasons which are
beyond control of the contractor or act of God, e.g. flood, riots, war, earthquake, etc.) and shall at his
own cost repair and make good the loss/damage to the work so that on completion, the work shall
be in good order and condition and in conformity with the requirements of the contract and
instructions of the Engineer-in-charge.
The contractor/contractors shall take following insurance policies during the full contract period at
his own cost:
a). In the case of construction works, without limiting the obligations and responsibilities under the
contract, the contractor shall take insurance policy for the works and for all materials at site so that
the value of the works executed and the materials at site up to date are sufficiently covered against
risk of loss/damage to the extent as permissible under the law of insurance. The contractor shall
arrange insurance in joint names of the company and the contractor. All premiums and other
insurance charges of the said insurance policy shall be borne by the contractor.
The terms of the insurance policy shall be such that all insurance claims and compensations payable
by the insurers, shall be paid to the Employer and the same shall be released to the contractor in
instalments as may be certified by the Engineer-in-charge for the purpose of rebuilding or
replacement or repair of the works and/or goods destroyed or damaged for which payment was
received from the insurers. Policies and certificates for insurance shall be delivered by the contractor
to the EIC for his approval before the starting date. Alterations to the terms of insurance shall not be
made without the approval of EIC.
b). Where any company building or part thereof is used, rented or leased by the contractor for the
purpose of storing or using materials of combustible nature, the contractor shall take separate
insurance policy for the entire building and the policy shall be deposited with the company.
c) The contractor shall at all times during the tenure of the contract indemnify the company against
all claims, damages or compensation under the provision of the Workmen's Compensation Act and
shall take insurance policy covering all risk, claims, damages, or compensation payable under the
Workmen's Compensation Act or under any other law relating thereto.
70
CONDITIONS OF CONTRACT
d) The contractor shall ensure that the insurance policy/ policies is/are kept alive till full expiry of the
contract by timely payment of premiums and it/they shall not be cancelled without the approval of
the company and a provision is made to this effect in all policies, and similar insurance policies are
also taken by his sub-contractors if any. The cost of premium shall be borne by the contractor and it
shall be deemed to have been included in the tendered rate.
e) In the event of contractor’s failure to effect or to keep in force the insurance referred to above or
any other insurance which the contractor is required to effect under the terms of the contract, the
company may effect and keep in force any such insurance and pay such premium/premiums as may
be necessary for that purpose from time to time and recover the amount thus paid from any moneys
due to the contractor.
THE CLAUSE 13(xviii) SHALL BE APPLICABLE FOR WORKS OF ESTIMATED VALUE OF OVER Rs. 50
LAKHS.
xix) Setting Out: The contractor shall be responsible for the contract and proper setting out of the
works and correctness of the position, reduced levels, dimensions and alignment of all parts of the
work including marking out the correct lay out in reference to the permanent bench mark and
reference points. Only one permanent bench mark and basic reference lines shall be marked and
shown to the contractor as basic data.
The contractor shall have all necessary instruments, appliances and labour in connection therewith.
If at any time during the progress of work any error is detected in respect of the position, levels,
dimensions or alignment of any part of the work, the contractor on being required to do so by the
Engineer-in-Charge or his representative shall at the expenses of the contractor rectify such errors to
the satisfaction of Engineer-in-Charge unless such error is due to incorrect data supplied by the
Engineer-in-Charge.
xx) On receipt of Letter of Acceptance of Tender / Work Order the contractor shall forthwith Register
and obtain License from the competent authority under the Contract Labour (Regulation & Abolition)
Act 1970, the Contract Labour (Regulation & Abolition) Central Rules, 1971 and submit certified
copies of the same to the Engineer-in-Charge and the Principal Employer.
xxi) Deleted.
xxii) The contractor shall, in connection with works, provide and maintain, at his own cost, all lights,
security guards, fencing when and where necessary as required by the Engineer-in-Charge for the
purpose of protection of the works, materials at site, safety of workmen and convenience of the
public.
xxiii) All materials (e.g. stone, moorum and other materials) obtained in the course of execution of
the work during excavation and dismantling etc. shall be the property of the company and the same
may be issued to the contractors, if required for use in the works at the rates to be fixed by the
Engineer-in-Charge.
xxiv)Unless otherwise specifically provided for, dewatering of excavation pits, working areas etc. shall
be the contractor's responsibility and is to be carried out at his own cost as per instructions of EIC.
The rates quoted by the contractor shall be deemed to include the dewatering costs.
xxv) Approval by the Nodal Officer/Engineer-in-Charge or his nominee: The contractor shall submit
specifications and drawings showing the proposed temporary work to the Nodal Officer/Engineer-in-
Charge or his nominee, who is to approve them if they comply with the specifications and drawings.
The Nodal Officer/Engineer-in-charge or his nominee’s approval shall not alter the contractor’s
71
CONDITIONS OF CONTRACT
responsibility for design of the Temporary Works.
xxvi) The contractor shall directly pay the ex-gratia amount of Rs.15.00 (Fifteen) lakhs to the eligible
dependent family members of the deceased contractor’s worker, who died in mine accident as
certified by DGMS, to whom the statutory benefits under Employee Compensation Act, Provident
Fund etc. have been paid, as per the terms of contract or through Insurance Company by availing
Group Personal Accident Insurance Policy for all its workers before commencement of the contract,
which shall be renewed periodically to cover the entire duration of the contract. No reimbursement
shall be made on this account by CIL/Subsidiary.
In order to comply with the above provisions, contractor shall immediately on receipt of letter of
acceptance/work order shall obtain group personal accident insurance in respect of all the workmen
engaged in mining activities for payment of Rs.15.00(fifteen) lakhs in case of death in mine accident.
A proof to such effect shall be produced to the satisfaction of the management before
commencement of the work. However, the responsibility of payment of special relief/ex-gratia
amount shall lie exclusively with the Contractor.
If the contractor fails to disburse the special Relief/Ex-gratia within the due date, the subsidiary
concerned may make payment to the eligible dependent as mentioned herein above. However, such
amount shall be recovered from the Contractor from his dues either in the same and/or other
subsidiaries of CIL”.
In addition to the defect/s to be rectified by the contractor as per terms of the contract/ work order,
the contractor shall be responsible to make good and remedy at his own expense the defect/s
mentioned hereunder within such period as may be stipulated by the Engineer-in-Charge in writing:
a) Any defect/defects in the work detected by the Engineer-in-Charge within a period of 6 (six)
months from the date of issue of Defect Liability certificate / completion certificate.
b) In the case of building works or other works of similar nature any defect in the work detected by
the Engineer-in-Charge within a period of 6 (six) months from the date of issue of Defect Liability
certificate/ completion certificate or before the expiry of one full monsoon period i.e. June to
September whichever is later in point of time.
14.1 A programme shall be drawn by the contractor and the Engineer-in-Charge for carrying out the
defects by the contractor detected within the defect liability period and if the contractor fails to
adhere to this programme, the Engineer-in-Charge shall be at liberty to procure proper materials
and carry out the rectifications in any manner considered advisable under the circumstances and the
cost of such procurement of materials and rectification work shall be chargeable to the contractor
and recoverable from any of the pending dues of the contractors.
The defect liability period can be extended by the company on getting request from the contractor
only for valid reasons.
There will be no defect liability period for works like Grass Cutting, Jungle Cutting, Surface Dressing &
any other work of similar nature to be decided by the Engineer-in-Charge.
If “as built” drawings and/or Operating and Maintenance Manual are required the contractor shall
supply them by the dates as per instruction of the Engineer-in-charge.
If the contractor does not supply the drawings and/or Manual by the dates as stated above, or they
do not receive the Nodal Officer or his nominee’s approval, the Nodal Officer or his nominee shall
withhold the amount as stated in the agreement.
72
CONDITIONS OF CONTRACT
16. Settlement of Disputes.
It is incumbent upon the contractor to avoid litigation and disputes during the course of execution.
However, if such disputes take place between the contractor and the department, effort shall be
made first to settle the disputes at the company level.
The contractor should make request in writing to the Engineer-in-charge for settlement of such
disputes/claims within 30 (thirty) days of arising of the cause of dispute/ claim failing which no
disputes/ claims of the contractor shall be entertained by the company.
If differences still persist, the settlement of the dispute shall be resolved in the following manner:
Disputes relating to the commercial contracts with Central Public Sector Enterprises / Govt.
Departments (except Railways, Income Tax, Customs & excise duties)/ State Public Sector Enterprises
shall be referred by either party for Arbitration to the PMA (Permanent Machinery of Arbitration) in
the department of Public Enterprises.
In case of parties other than Govt. Agencies, the redressal of the dispute may be sought through
Arbitration (THE ARBITRATION AND CONCILIATION ACT, 1996 as amended by AMENDMENT ACT of
2015).
If the parties fail to resolve the disputes/differences by in house mechanism, then, depending on the
position of the case, either the employer/owner or the contractor shall give notice to other party to
refer the matter to arbitration instead of directly approaching Court. The contractor shall, however,
be entitled to invoke arbitration clause only after exhausting the remedy available under the clause
16.
In case of parties other than Govt. agencies, the redressal of disputes/differences shall be sought
through Sole Arbitration as under.
Sole Arbitration:
In the event of any question, dispute or difference arising under these terms & conditions or any
condition contained in this contract or interpretation of the terms of, or in connection with this
Contract (except as to any matter the decision of which is specially provided for by these conditions),
the same shall be referred to the sole arbitration of a person, appointed to be the arbitrator by the
Competent Authority of CIL / CMD of Subsidiary Company (as the case may be). The award of the
arbitrator shall be final and binding on the parties of this Contract.
(a) In the event of the Arbitrator dying, neglecting or refusing to act or resigning or being unable to
act for any reason, or his/her award being set aside by the court for any reason, it shall be lawful for
the Competent Authority of CIL / CMD of Subsidiary Company (as the case may be) to appoint
another arbitrator in place of the outgoing arbitrator in the manner aforesaid.
(b) It is further a term of this contract that no person other than the person appointed by the
Competent Authority of CIL / CMD of Subsidiary Company (as the case may be) as aforesaid should
act as arbitrator and that, if for any reason that is not possible, the matter is not to be referred to
Arbitration at all.
Subject as aforesaid, Arbitration and Conciliation Act, 1996 as amended by Amendment Act of 2015,
and the rules thereunder and any statutory modification thereof for the time being in force shall be
deemed to apply to the Arbitration proceedings under this clause.
The venue of arbitration shall be the place from which the contract is issued.
73
CONDITIONS OF CONTRACT
Applicable Law: The contracts shall be interpreted in accordance with the laws of the Union of India.
Contracts with Partnership firm/ Joint Venture:
The Partnership firm /Joint Venture is required to submit written consent of all the partners to above
arbitration clause at the time of submission of bid.
The e-way bill required in connection with supply of goods or services, if any, shall be arranged by
the supplier/vendor. However, the e-way bill will be arranged by CIL/Subsidiary if the
supplier/vendor is unregistered one or if provisions of the relevant Act and the rules made there
under specifically states that the e-way bill is required to be issued by recipient of goods.
18. In the event of recovery of any claim towards LD charges, penalty, fee, fine or any other charges
(Except EMD) from the supplier/vendor, the same will be recovered with the applicable GST and
the amount shall be adjusted with the payment to be made to the supplier/vendor against their
bill/invoice or any other dues.
CIL and its Subsidiary Companies shall follow the following guidelines for effecting ‘Banning of
Business’ with a contracting entity in respect of Works and Services Contracts.
1. Observance of Principle of Natural Justice before banning the business dealings with any
contracting entity.
2. The contracting entity may be banned in the following circumstances :-
i) If bidder backs out after notification of opening of price bid and if that bidder is found to be L-
1.
ii) If L-1 bidder fails to submit PSD and APSD, if any and/or fails to execute the contract within
stipulated period.
iii) If L-1 bidder fails to start the work on scheduled time.
iv) In case of failure to execute the work as per mutually agreed work schedule.
v) Continued and repeated failure to meet contractual Obligations:
a. In case of partial failure on performance, agency shall be banned from future
participation in tenders keeping his present contract alive.
b. On termination of contract.
vi) Willful suppression of facts or furnishing or wrong information or manipulated or forged doc-
uments by the Agency or using any other illegal/unfair means.
vii) Formation of price cartels with other contractors with a view to artificially hiking the price.
viii) The contractor fails to maintain/repair/redo the work up to the expiry of performance guaran-
tee period, when it is specifically brought to his notice.
ix) Contractor fails to use Mobilisation advance given to him for the purpose it was intended.
x) Contractor fails to renew the securities deposited to the department.
xi) The contractor fails to rectify any lapse(s) in quality of the work done within defect liability pe-
riod.
xii) Transgression of any clause(s) relating to Contractor’s obligation defined in the Integrity Pact
wherever such Pact exists.
xiii) Any other breach of Contract or misdeed which may cause financial loss or commercial dis-
advantage to the Company.
3. Such ‘Banning of Business’, if and when effected, shall be with prospective effect only. The ef-
fect of ‘Banning of Business’ shall be for future tenders from the date of issue of such Order.
However, if any contracting entity is banned after online notification of opening of Price Bid,
such a ban will not be effective for that work.
4. The banning shall be for a minimum period of one year and shall be effective for the concerned
74
CONDITIONS OF CONTRACT
Subsidiary for the tenders invited at Subsidiary level. Similarly, in case of tenders of CIL HQ,
banning shall be for CIL HQ. However, if such ‘Banning of Business’ has to be made effective for
entire CIL and its Subsidiaries then approval of Chairman, CIL shall be required.
5. Once a contracting entity is banned, it shall be extended to the constituents of that entity, all
partners in case of Joint Venture, all the partners in case of Partnership Firm, own-
er/proprietor in case of Proprietorship Firm and all the Directors in case of Limited Company. If
such banned owner/Proprietor/ Partner/Director make/form different Firms/entity and at-
tempts to participate in tenders, the same will not be entertained during the currency of such
banning.
6. The above ‘Banning of Business’ shall be in addition to other penal provisions of NIT/Contract
document.
7. Approving Authority: The ‘Banning of Business’ of a contracting entity shall be done with the
approval of the Competent Authority as per the details below:
a) In case the Accepting Authority of the work is Board or Empowered Committee or FDs or CMD
of CIL/Subsidiary Company, then the Competent Authority for banning shall be CMD of
CIL/Subsidiary Company.
b) In case the Accepting Authority of the work is up to the level of Director of CIL/Subsidiary
Company, then the Competent Authority for banning shall be Director of CIL/Subsidiary Com-
pany.
8. Appellate Authority shall be one Rank higher than the Competent Authority meant for ‘Ban-
ning of Business’. In case the banning is done with the approval of CMD of the Subsidiary
Company then Chairman, CIL shall be the Appellate authorly.
9. Any change on the above may be done with approval of FDs of CIL.
10. All the orders of banning or orders passed in appeal shall be marked to GM(CMC) / Civil / con-
cerned HODs of CIL/Subsidiary Company. Further, all such orders will be uploaded in Coal India
site as well website of the Subsidiary Company.
11. Efforts shall be made by the concerned Department so that such order is linked to e-tender
portal of Coal India Limited.
20. The contractor shall submit valid electrical license either in his name or of his authorized
representative/supervisor [under whose supervision electrification work (internal and/or external)
will be executed] issued by Electrical Licensing Board / Authority of the Indian State / UT, in
accordance with Indian Electricity Rule before execution of electrical works, if any.
@@@@@
75
76
The following additional terms and conditions are also acceptable to the company. The tenderers are
requested not to quote any further additional conditions in the tender.
1. Mobilization Advance
i) No mobilization advance is payable for works whose estimated value is less than
Rs.100.00 lakhs.
ii) In the case of turnkey work whose estimated value is more than Rs.100 lakhs a maxi-
mum of 10 % of the total contract value of work will be paid as mobilization advance
subject to submission of Bank Guarantee equal to 110% of the advance amount. The
mobilization advance shall be paid in two instalments.
iii) In case of other civil works valued more than Rs.100 lakhs mobilization advance will be
paid upto 5% of the contract value subject to submission of Bank Guarantee equal to
110% of the advance amount. The mobilization advance shall be paid in two instalments.
iv) Interest on mobilisation advance will be charged at the rate of CIL’s borrowing rate under
cash credit arrangement as on date of disbursement and to be compounded quarterly.
v) The mobilization advance shall be recovered from the bills of the contractor from the 2nd
running account bill onwards @ 20% of the advance amount paid. However, the full
amount of mobilization advance with interest will be recovered maximum within sched-
uled date of completion as per agreement.
vi) The value of Bank Guarantee may be reduced to the extent such advance is recovered
by the company subject to the conditions that the value of Bank Guarantee amount at
any time is more than the recoverable outstanding advance. Bank Guarantee shall be ir-
revocable and from a Scheduled- Bank acceptable to the Company.
vii) Part Bank Guarantee” (BGs) against the Mobilization Advance shall be taken in as many
numbers as the proposed recovery instalments and shall be equivalent to 110% of the
amount of each instalment.
viii) In case of “Machinery and Equipment advance”, insurance and hypothecation to the em-
ployer shall be ensured.
ix) Mobilization advance will be given in instalments and subsequent instalments will be re-
leased after getting satisfactory utilization Certificate from the contractor for the earlier
instalments.
If the prices of materials (not being the materials supplied at fixed issue rates by the company)
and wages of labour required for execution of the work increase or decrease, the contractor
shall be compensated for such increase or recoveries will be made from the bills for such
decrease as per provisions detailed hereafter:
a) The amount of the contract shall accordingly be varied subject to the condition that such
compensation for escalation/ de-escalation in price shall be available only for the work
done during the stipulated period of the contract including such period for which the con-
77
tract is validly extended under the provisions of the contract without any penal action. The
Price Variation Clause shall not be applicable for works for which stipulated period of com-
pletion is six months or less.
b) The base date for working out such escalation/de-escalation shall be the last date on
which the bids (inclusive of price part) or revised price bids (inclusive of revised offer)
were stipulated to be received.
c) The compensation for escalation or recoveries to be made shall be worked out at quar-
terly intervals and shall be with respect to the cost of work done during the previous
three months. The first such payment will be made at the end of three months after the
month (excluding) in which the tender was accepted and thereafter at three months' in-
terval.
d) Job specific modification in the formulae of price variation given in the following para(s)
can be done with the approval of the CMD of the company
2.1 Escalation/ De-escalation for Labour: The amount paid to the contractor for the work done
shall be adjusted for increase or decrease in the cost of labour and the cost shall be calculated
quarterly in accordance with the following formula :
VL = W
Where :
W= Value of work done during the period under reckoning to which the escalation/de-
escalation relates as indicated in clause-2.4 of the Additional Terms & Conditions of
the contract.
Lo = Minimum wages for unskilled workers payable as per the Minimum Wages Act /
Rules of the State or Central Govt., whichever is more, applicable to the place of work
as on the last date stipulated for receipt of the bids (inclusive of price part) or revised
price bids whichever is later.
2.2 Escalation /De-escalation on Materials: The amount to be paid to the contractor for the work
done will be adjusted for increase or decrease in the cost of materials and the cost shall be cal-
culated quarterly in accordance with the following formula :
Vm = W
Where :
Vm = Variation in the material cost i.e. increase or decrease in the amount in rupees to be
paid or recovered.
78
W= Cost of work done during the period under reckoning to which the escalation / de-
escalation relates as indicated in clause-2.4 of the Additional Terms & Conditions of
the contract.
B = Component of material expressed as percentage of the total value of the work adopted
from the Table -1.
M = Average All India Wholesale Price Index for all commodities for the period to which esca-
lation/de-escalation relates as published by the RBI Bulletin, Ministry of Industry &
Commerce, Govt. of India.
Mo = All India Wholesale Price Index for all commodities as published by the RBI Bulletin,
Ministry of Industry & Commerce, Govt. of India, relating to the last date on which the
bids (inclusive of price part) or revised price bids whichever is later were stipulated to
be received.
2.3 Escalation/ De-escalation on POL : The amount to be paid to the contractor for the work
done shall be adjusted for the increase or decrease in the cost of POL and the cost shall be cal-
culated quarterly in accordance with the formula given below :
Vf = W
Where :
Vf = Variation in the cost of fuel, oil and lubricants i ncrease or decrease in the rupees to be
paid or recovered.
W= Value of work done during the period under reckoning to which the escalation/ de-
escalation relates as indicated in clause 2.4 of the Additional terms & Conditions of the
contract.
C = Component of POL expressed as percentage of the total cost of the work taken from Table
-1.
F = Average Index Number for wholesale price for the group of `Fuel, Power, Light & Lubri-
cants' as published by the Economic Adviser, Ministry of Industry, Govt. of India for the
period to which the escalation/de-escalation relates.
Fo = Index number of wholesale price for the group, Fuel, Power, light & lubricants as pub-
lished by the Economic Adviser, Ministry of Industry, Govt. of India prevalent on the last
date of receipt of bids (inclusive of Price Part) or revised price bids whichever is later.
2.4 While calculating the value of "W" the following may be noted : The cost on which the esca-
lation will be payable shall be reckoned as 85 % of the cost of work as per the bills to which es-
calation relates, and from this amount the value of materials supplied or services rendered at
the prescribed charges under the relevant provisions of the contract, and proposed to be re-
covered in the particular bill, shall be deducted before the amount of compensation for escala-
tion or de-escalation is worked out. In the case of materials brought to site for which any se-
cured advance is included in the bill, the full value of such materials as assessed by the Engi-
neer-in-Charge (and not the reduced amount for which secured advance has been paid) shall
be included in the cost of work done for operation of this clause. Similarly, when such materials
are incorporated in the work and the secured advance is deducted from the bill, the full as-
sessed value of the materials originally considered for operation of this clause should be de-
79
ducted from the cost of the work shown in the bill, running or final. Further the cost of work
shall not include any work for which payment is made at prevailing market rates.
2.5 In the event the price of materials and/ or wages of labour required for execution of the work
decreases, there shall be downward adjustment of the cost of work so that such price of mate-
rials and/or wages of labour shall be deductible from the cost of work under this contract and
in this regard the formulae herein before stated under this clause shall mutatis/mutandis apply.
No such adjustment for the increase / decrease in material price and/ or wages of labour be-
fore mentioned would be made in case of contracts in which the stipulated period of comple-
tion of the work is six (6) months or less.
The Price Variation Clause as stated above will be applied for extended time frame of a con-
tract by following the principle stated as under:
i) Normally, if and when it is understood that a contract is not going to be completed within
the scheduled time period, the contract is kept operative by extending the time of com-
pletion provisionally. During this provisional extended period the operation of the Price
Variation Clause will remain suspended.
ii) If and when it is decided at the end of the successful completion of the work that the de-
lay was due to causes not attributable to the contractor, then the Price Variation Clause
will be revived and applied as if the scheduled date of completion has been shifted to the
approved extended date.
iii) If it is decided at the end of successful completion of the work that the delay was due to
the fault of the contractor then the Price Variation Clause will not be revived for the pur-
pose of escalation but shall be revived and applied for the purpose of de-escalation and
no further payment will be made to the contractor on account of any escalation during
this period but recovery shall be made for de-escalation, if any. Additionally, the Clause
related to Compensation for delay will be applied.
iv) If it is decided at the end of successful completion of work, the delay was partly due to
the fault of the contractor and partly due to the fault of the employer and thereby Liqui-
dated Damages (LD)/compensation due to delay is imposed then price variation clause
for the purpose of escalation shall not be revived for this extended period, but shall be
revived and applied for the purpose of de-escalation.
Table – 1
Value of A, B & C in the escalation formula in the additional terms & conditions for Civil Works :
The Scope of the Work would essentially cover, but not limited to visiting the sites and survey of Roof
Tops of the identified sites, Design, Engineering, Manufacture, Supply, Storage, Civil Works, Erection,
Testing, Commissioning , ensuring net metering as per the concerned State/ UT Policies, Quality Con-
trol of the total 1415 kWp Grid Connected Solar PV Rooftop Project at 10 different areas of ECL consist-
ing 26 different sites as below including Operation and Maintenance (O & M) of the Project for a peri-
od of 05 (Five) years.
Office Building 10
Dist- Paschim
1 Sripur Area (W.B.) Guest House Building 30 Burdwan, WB
(WBSEDCL)
Auditorium 15
Area Office 70
Project Office 10 Dist- Paschim
Sonepur Bazari Pro-
2 Burdwan, WB
ject (W.B.) Hostel 20 (WBSEDCL)
Guest House 10
Khottadihi Agent Office 20
Pandaveswar Area Office 20 Dist- Paschim
Pandaveswar Area
3 Burdwan, WB
(W.B.) Pant Nagar Hospital 150 (WBSEDCL)
Vivekananda Hostel 10
Dist- Paschim
4 Jhanjra Area (W.B.) Chinese Hostel 60 Burdwan, WB
(WBSEDCL)
5 Area Hospital 300 Dist- Paschim
Bankola Area (W.B.)
Burdwan, WB
Area School 30 (WBSEDCL)
Dist- Paschim
6 Kajora Area (W.B.) Kajora Area Hospital 225 Burdwan, WB
(WBSEDCL)
Dist- Dhanbad, Jhar-
Mugma Area (Jhar-
7 Office Building 20 khand
khand)
(JBVNL)
Urja Nagar Hospital 70
Rajmahal House 55
Dist- Godda, Jhar-
Rajmahal Area
8 Area Office 15 khand
(Jharkhand)
(JBVNL)
Pit Office 50
CHP GM Office 15
82
(3) All component of Roof Top Solar Project shall be Indigenous only.
The Project cost shall include all the costs related to above Scope of Work. Bidder shall quote for the
entire facilities on a “single responsibility” basis such that the total Bid Price covers all the obligations
mentioned in the Bidding Documents in respect of Design, Supply, Erection, Testing and Commission-
ing including Warranty, Operation & Maintenance (for a period of 5 years), GST, goods and services
including spares required if any during O&M period. The Bidder has to take all permits, approvals and
licenses, Insurance etc., provide training and such other items and services required to complete the
scope of work mentioned above. The fixed project cost should be quoted while accounting for the cost
of grid-connectivity and net metering application/ security deposit etc. All costs associated with net-
metering will have to be borne by the successful bidder.
The Project cost shall remain firm and fixed and shall be binding on the Successful Bidder till comple-
tion of work. No escalation will be granted on any reason whatsoever. The bidder shall not be entitled
to claim any additional charges, even though it may be necessary to extend the completion period for
any reasons whatsoever.
The Project cost shall be inclusive of all duties and taxes, insurance etc. The prices quoted by the firm
shall be complete in all respect and no price variation/ adjustment shall be payable by ECL. However,
statutory variation of taxes and duties may be paid by ECL is found applicable.
The Operation & Maintenance of Solar Photovoltaic Power Plant would include wear, tear, overhaul-
ing, machine breakdown, insurance, and replacement of defective modules, invertors/ Power Condi-
tioning Unit (PCU), spares, consumables & other parts for a period of 5 years.
(8) Insurance:
The Bidder shall be responsible and take an Insurance Policy for transit-cum-storage-cumerection for
all the materials to cover all risks and liabilities for supply of materials on site basis, storage of materi-
83
als at site, erection, testing and commissioning. The bidder shall also take appropriate insurance in-
cluding watch and ward during O&M period.
The Bidder shall also take insurance for Third Party Liability covering loss of human life, engineers and
workmen and also covering the risks of damage to the third party/material/equipment/properties dur-
ing execution of the Contract. Before commencement of the work, the Bidder will ensure that all its
employees and representatives are covered by suitable insurance against any damage, loss, injury or
death arising out of the execution of the work or in carrying out the Contract. Liquidation, Death,
Bankruptcy etc., shall be the responsibility of bidder.
The Bidder shall warrant that the goods supplied under this contract are new, unused, of the most re-
cent or latest technology and incorporate all recent improvements in design and materials. The bidder
shall provide warrantee covering the rectification of any and all defects in the design of equipment,
materials and workmanship including spare parts for a period of 5 years from the date of commission-
ing. The successful bidder has to transfer all the Guarantees/ Warrantees of the different components
to ECL. The responsibility of operation of Warrantee and Guarantee clauses and Claims/ Settlement of
issues arising out of said clauses shall be joint responsibility of the Successful bidder and the owner of
the project and ECL will not be responsible in any way for any claims whatsoever on account of the
above.
The design, engineering, manufacture, supply, installation, testing and performance of the equipment
shall be in accordance with latest appropriate IEC/ Indian Standards as detailed in Technical Specifica-
tion Part. Where appropriate Indian Standards and Codes are not available, other suitable standards
and codes as approved by the MNRE shall be used.
The specifications of the components should meet the technical specifications mentioned in Technical
Specification Part.
Any supplies which have not been specifically mentioned in this Contract but which are necessary for
the design, engineering, manufacture, supply & performance or completeness of the project shall be
provided by the Bidder without any extra cost and within the time schedule for efficient and smooth
operation and maintenance of the SPV plant.
The bidder shall be responsible for all the required activities for successful operation and maintenance
of the Rooftop Solar PV system for a period of 5 years from the date of commissioning of the plant.
For system sizes above 25 kWp, below mentioned guidelines, shall be followed in addition:
O&M of Solar Power Plant shall be compliant with grid requirements to achieve committed energy
generation.
Deputation of qualified and experienced engineer/ technicians till the O&M period at project site.
Periodic cleaning of solar modules. The modules shall be cleaned with a periodic interval of 15 days
or as and when required as per actual site conditions. It’s the responsibility of the bidder to get the
modules cleaned during O & M Period. Roof Top Owner is responsible for such obligation of bidder so
as to achieve guaranteed CUF.
84
Periodic checks of the Modules, PCUs and BoS shall be carried out as a part of routine preventive
and breakdown maintenance.
Immediate replacement of defective Modules, Invertors/PCUs and other equipment as and when
required.
Supply of all spares, consumables and fixtures as required. Such stock shall be maintained for all
associated equipments and materials as per manufacturer’s / supplier’s recommendations.
All the testing instruments required for Testing, Commissioning and O&M for the healthy operation
of the Plant shall be maintained by the Bidder. The testing equipment must be calibrated once in a
year from NABL accredited labs and the certificate of calibration must be kept for reference as re-
quired.
If negligence/ mal-operation on part of the Bidder's operator results in failure of equipment, such
equipment should be repaired/ replaced by the Bidder free of cost.
Co-ordination with ECL/ DISCOM / CEIG as per the requirement for Joint Metering Report (JMR).
The person in charge present at site from bidder’s side shall take a joint meter reading in the presence
of representative of ECL on a monthly basis.
Online Performance Monitoring, controlling, troubleshooting, maintaining of logs & records. A
maintenance record register is to be maintained by the operator with effect from Commissioning to
record the daily generation, regular maintenance work carried out as well as any preventive and
breakdown maintenance along with the date of maintenance, reasons for the breakdown, duration of
the breakdown, steps taken to attend the breakdown, etc.
If any jobs covered in O&M Scope are not carried out by the contractor/ Bidders during the O&M
period, the Engineer-In-Charge shall take appropriate action as deemed fit. Failure to adhere to above
guidelines will result in penal action including debarring from participation in next tender.
Metering and grid connectivity of the roof top solar PV system under this scheme would be the re-
sponsibility of the Bidder in accordance with the prevailing guidelines of the WBSEDCL / or CEA (if
available by the time of implementation). ECL shall facilitate connectivity; however, the entire respon-
sibility lies with bidder only.
The successful bidder shall be required to meet minimum guaranteed generation with Performance
Ratio (PR) at the time of commissioning and related Capacity Utilization Factor (CUF) as per the GHI
levels of the location during the O&M period. PR should be shown minimum of 75% at the time of in-
spection for initial commissioning acceptance. Minimum CUF of 15% should be maintained for a period
of 5 years for fulfilling one of the condition for release of PBG for the O&M part. The bidder should
send the periodic plant output details to ECL for ensuring the CUF. The PR will be measured at Inverter
output level during good radiation conditions.
PAYMENT TERMS
PBG shall be 5% of the total awarded value (including GST) and must be deposited within 21 days from
issue of LOA as per clause 4.2 of Condition of Contract.
Total Project cost shall be divided in two part as follows:
(A) 95% of the Awarded Value shall be considered as cost for Supply, Installation, commissioning and
Testing and payment shall be made on supply, installation, commissioning and testing of individual
roof top solar plant (location wise) after acceptance by concerned AE (E&M) of Area/ Agent of Work
Shop (who shall be the acceptance authority) after recovery of 5% of award value as retention money.
(Total award value divided by 1415 shall be consi9dered as the awarded rate. Accordingly, the capacity
85
of individual project, finally implemented, shall be considered as awarded value for each individual
project.
(B) Balance 5% of the Awarded Value shall be treated as O&M Cost. For this:
The Successful Bidder shall have to furnish a Bank Guarantee equal to 5% of the Awarded Value
(including GST) on or before the completion of installation and commissioning which shall be
valid for 5 years thereafter.
ECL shall release the O&M cost on yearly basis (equal part for each year) on successful comple-
tion of O&M of each year by the successful bidder.
ECL shall release the BG of O&M part (5% of project cost) after completion of entire O&M peri-
od of 5 years if completed by the Successful Bidder.
Release of PBG and Retention Money shall be governed by clause 4.3 and 4.5 of Condition of
Contract.
ECL shall be liable to encash the BG due to any non-performance of any obligation of the CON-
TRACTOR as mentioned in this NIT and Tender Document.
“Capacity Utilization Factor” (CUF) means the ratio of the actual output from a solar plant over the
year (kWh) to the maximum possible output from it for a year (kWh) under ideal conditions.
CUF = Actual Plant Output in kWh over the year/ (Installed Plant Capacity in kW* x 365 x 24)
Monthly CUF: Monthly Plant output in kWh/ (Installed Plant Capacity in kW* x number
of days in a month x 24)
“Performance Ratio” (PR) means the ratio of plant output versus installed plant capacity at any in-
stance with respect to the radiation measured.
Availability of ITC:
Dist- Paschim
Jhanjra Area
7 Chinese Hostel 60 Burdwan, WB
(W.B.)
(WBSEDCL)
8 Bankola Area Area Hospital 300 Dist- Paschim
(W.B.) Burdwan, WB
9 Area School 30
(WBSEDCL)
Dist- Paschim
10 Kajora Area (W.B.) Kajora Area Hospital 225 Burdwan, WB
(WBSEDCL)
11 Urja Nagar Hospital 70 Dist- Godda, Jhar-
Rajmahal Area
khand
12 (Jharkhand) Rajmahal House 55 (JBVNL)
Dist- Deoghar,
13 S P Mines Area Hospital 10 Jharkhand
(JBVNL)
TOTAL : 13 locations 985
SAFETY CODE
1. Suitable scaffolds should be provided for workmen for all works that cannot safely be done from
the ground, or from solid construction except such short period work as can be done safely from
ladders. When a ladder is used, an extra mazdoor shall be engaged for holding the ladder and if the
ladder is used for carrying materials as well suitable footholds and hand-hold shall be provided on
the ladder and the ladder shall be given an inclination not steeper that ¼ to 1 ( ¼ horizontal and 1
vertical).
2. Scaffolding of staging more than 3.6 m (12ft). above the ground or floor, swung or suspended from
an overhead support or erected with stationary support shall have a guard rail properly attached or
bolted, braced and otherwise secured at least 90 cm (3ft) high above the floor or platform of such
scaffolding or staging and extending along the entire length of the outside and ends thereof with
only such opening as may be necessary for the delivery of materials. Such scaffolding or staging
shall be so fastened as to prevent it from swaying from the building or structure.
3. Working platforms, gangways and stairways should be so constructed that they should not sag
unduly or unequally, and if the height of the platform or the gangway or the stairway is more than
3.6 m (12ft) above ground level, they should be closely boarded, should have adequate width and
should be suitably fastened as described in (2) above.
4. Every opening in the floor of a building or in a working platform shall be provided with suitable
means to prevent the fall of person or materials by providing suitable fencing or railing whose
minimum height shall be 90 cm (3ft).
5. Safety means of access shall be provided to all working platforms and other working places. Every
ladder shall be securely fixed. No portable single ladder shall be over 9 m (30ft) in length while the
width between side rails in rung ladder shall in no case be less than 20 cm (11 ½”) for ladder upto
and including 3 m (10ft) in length. For longer ladders, this width should be increased at least ¼” for
additional 30 cm (1ft.) of length. Uniform step spacing of not more than 30 cm shall be kept.
Adequate precautions shall be taken to prevent danger from electrical equipment. No materials on
any of the sites or work shall be so stacked or placed as to cause danger or inconvenience to any
person or the public. The contractor shall provide all necessary fencing and lights to protect the
public from accident and shall be bound to bear the expenses of defence of every suit, action or
other proceedings at law that may be brought by any person for injury sustained owing to neglect
of the above precautions and to pay any damages and cost which may be awarded in any such suit;
action or proceedings to any such person or which may, with the consent of the contractor, be paid
to compensate any claim by any such person.
6. Excavation and Trenching: All trenches 1.2 m (4ft) or more in depth, shall at all times be supplied
with at least one ladder for each 30 m. (100 ft.) in length or fraction thereof. Ladder shall extend
from bottom of the trench to at least 90 cm (3ft) above the surface of the ground. The side of the
trenches which are 1.5 m (5ft) or more in depth shall be stepped back to give suitable slope or
securely held by timber bracing, so as to avoid the danger of sides collapsing. The excavated
materials shall not be placed within 1.5 m (5ft) of the edges of the trench or half of the depth of
the trench whichever is more. Cutting shall be done from top to bottom. Under no circumstances,
undermining or undercutting shall be done.
7. Demolition: before any demolition work is commenced and also during the progress of the work,
a) All roads and open areas adjacent to the work site shall either be closed or suitably protected.
88
8. All necessary personal safety equipment as considered adequate by the Engineer-in-Charge should
be kept available for the use of the person employed on the site and maintained in a condition
suitable for immediate use, and the contractor should take adequate steps to ensure proper use of
equipment by those concerned: - The following safety equipment shall invariably be provided.
i) Workers employed on mixing asphaltic materials, cement and lime mortars shall be provided
with protective footwear and protective goggles.
ii) Those engaged in white washing and mixing or stacking of cement bags or any material which is
injurious to the eyes, shall be provided with protective goggles.
iii) Those engaged in welding works shall be provided with welder’s protective eye-shields.
iv) Stone breaker shall be provided with protective goggles and protective clothing and seated at
sufficiently safe intervals.
v) When workers are employed in sewers and manholes, which are in active use, the contractors
shall ensure that the manhole covers are opened and ventilated at least for an hour before the
workers are allowed to get into the manholes, and the manholes so opened shall be cordoned
off with suitable railing and provided with warming signals or boards to prevent accident to the
public. In addition, the contractor shall ensure that the following safety measures are adhered
to: -
a) Entry for workers into the line shall not be allowed except under supervision of the
Engineering Assistant or any other higher officer.
b) At least 5 to 6 manholes upstream and downstream should be kept open for at least 2 to 3
hours before any man is allowed to enter into the manhole for working inside.
c) Before entry, presence of Toxic gases should be tested by inserting wet lead acetate paper
which changes colour in the presence of such gases and gives indication of their presence.
d) Presence of Oxygen should be verified by lowering a detector lamp into the manhole. In
case, no Oxygen is found inside the sewer line, workers should be sent only with Oxygen kit.
e) Safety belt with rope should be provided to the workers. While working inside the manholes,
such rope should be handled by two men standing outside to enable him to be pulled out
during emergency.
f) The area should be barricaded or condoned of by suitable means to avoid mishaps of any
kind. Proper warming signs should be displayed for the safety of the public whenever
cleaning works are undertaken during night or day.
g) No smoking or open flames shall be allowed near the blocked manhole being cleaned.
h) The malba obtained on account of cleaning of blocked manholes and sewer lines should be
immediately removed to avoid accidents on account of slippery nature of the malba.
89
i) Workers should not be allowed to work inside the manhole continuously. He should be
given rest intermittently. The Engineer-in-Charge may decide the time up to which a worker
may be allowed to work continuously inside the manhole.
j) Gas masks with Oxygen Cylinder should be kept at site for use in emergency.
k) Air-blowers should be used for flow of fresh air through the manholes. Whenever called for,
portable air blowers are recommended for ventilating the manholes. The Motors for these
shall be vapour proof and of totally enclosed type. Non-sparking gas engines also could be
used but they should be placed at least 2 meters away from the opening and on the leeward
side protected from wind so that they will not be a source of friction on any inflammable
gas that might be present.
l) The workers engaged for cleaning the manholes / sewers should be properly trained before
allowing to work in the manhole.
m) The workers shall be provided with Gumboots or non-sparking shoes bump helmets and
gloves non-sparking tools safety lights and gas masks and portable air blowers (when
necessary). They must be supplied with barrier cream for anointing the limbs before
working inside the sewer lines.
n) Workmen descending a manhole shall try each ladder stop or rung carefully before putting
his full weight on it to guard against insecure fastening due to corrosion of the rung fixed to
manhole well.
o) If a man has received a physical injury, he should be brought out of the sewer immediately
and adequate medical aid should be provided to him.
p) The extents to which these precautions are to be taken depend on individual situation but
the decision of the Engineer-in-Charge regarding the steps to be taken in this regard in an
individual case will be final.
vi) The Contractor shall not employ men and women below the age of 18 years on the work of
painting with products containing lead in any form. Wherever men above the age of 18 are
employed on the work of lead painting, the following precaution should be taken: -
a) No paint containing lead or lead products shall be used except in the form of paste or
readymade paint.
b) Suitable face masks should be supplied for use by the workers when paint is applied in the
form of spray or a surface having lead paint is dry rubbed and scrapped.
c) Overalls shall be supplied by the contractors to the workmen and adequate facilities shall be
provided to enable the working painters to wash during and on the cessation of work.
d) Measures shall be taken, wherever practicable, to prevent danger arising out of from dust
caused by dry rubbing down and scraping.
e) Adequate facilities shall be provided to enable working painters to wash during and on
cessation of work.
f) Overall shall be worn by working painters during the whole of working period.
90
g) Suitable arrangement shall be made to prevent clothing put off during working hours being
spoiled by painting materials.
9. When the work is done near any place where there is risk of drowning, all necessary equipment
should be provided and kept ready for use and all necessary steps taken for prompt rescue of any
person in danger and adequate provision, should be made for prompt first aid treatment of all
injuries likely to be obtained during the course of the work.
10. Use of hoisting machines and tackle including their attachments, anchorage and supports shall
conform to the following standards or conditions: -
i) (a) These shall be of good mechanical construction, sound materials and adequate strength and
free from patent defects and shall be kept repaired and in good working order.
(b) Every rope used in hoisting or lowering materials or as a means of suspension shall be of
durable quality and adequate strength, and free from patent defects.
ii) Every crane driver or hoisting appliance operator, shall be properly qualified and no person
under the age of 21 years should be in charge of any hoisting machine including any scaffolding
winch or give signals to operator.
iii) In case of every hoisting machine and of every chain ring hook, shackle swivel and pulley block
used in hoisting or as means of suspension, the safe working load shall be ascertained by
adequate means. Every hoisting machine and all gear referred to above shall be plainly marked
with the safe working load. In case of a hoisting machine having a variable safe working load
each safe working load and the condition under which it is applicable shall be clearly indicated.
No part of any machine or any gear referred to above in this paragraph shall be loaded beyond
the safe working load except for the purpose of testing.
iv) In case of departmental machines, the safe working load shall be notified by the Electrical
Engineer-in-Charge. As regards contractor’s machines the contractors shall notify the safe
working load of the machine to the Engineer-in-Charge whenever he brings any machinery to
site of work and get it verified by the Electrical Engineer concerned.
12. Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting appliances
should be provided with efficient safeguards. Hoisting appliances should be provided with such
means as will reduce to the minimum the risk of accidental descent of the load. Adequate
precautions should be taken to reduce to the minimum the risk of any part of a suspended load
becoming accidentally displaced. When workers are employed on electrical installations which are
already energized, insulating mats, wearing apparel, such as gloves, sleeves and boots as may be
necessary should be provided. The worker should not wear any rings, watches and carry keys or
other materials which are good conductors of electricity.
13. All scaffolds, ladders and other safety devices mentioned or described herein shall be maintained in
safe condition and no scaffold, ladder or equipment shall be altered or removed while it is in use.
Adequate washing facilities should be provided at or near places of work.
14. These safety provisions should be brought to the notice of all concerned by display on a notice
board at a prominent place at work spot. The person responsible for compliance of the safety code
shall be named therein by the contractor.
15. To ensure effective enforcement of the rules and regulations relating to safety precautions the
arrangements made by the contractor shall be open to inspection by the Labour Officer or
Engineer-in-Charge of the department or their representatives.
91
16. Notwithstanding the above clauses from (1) to (15), there is nothing in these to exempt the
contractor from the operations of any other Act or Rule in force in the Republic of India.
17.
92
TECHNICAL SPECIFICATIONS
Latest CPWD specification shall be adopted. Presently CPWD specifications 2019 Vol. I & II is in vogue
which may be followed. These specifications cover all type of Building Works. The specifications are
available as a printed document issued by CPWD and also in soft copy PDF format in CPWD website.
Latest CPWD specification shall be adopted. Presently the following are in vogue:
I Internal 2013
The proposed projects shall be commissioned as per the technical specifications given below. Any
shortcomings will lead to cancelation of award of work and forfeiture of EMD and PBG or as decided by
the TIA. Domestic Modules are to be used failing which it will be assumed that system is not matching
the requirement of the scheme and bidder’s PBG shall be forfeited. Competent Authority’s decision
will be final and binding on the bidder.
A Grid Tied Solar Rooftop Photo Voltaic (SPV) power plant consists of SPV array, Module, Mounting
Structure, Power Conditioning Unit (PCU) consisting of Maximum Power Point Tracker (MPPT), Invert-
er, and Controls & Protections, interconnect cables, Junction boxes, Distribution boxes and switches.
PV Array is mounted on a suitable structure. Grid tied SPV system is without battery and should be de-
signed with necessary features to supplement the grid power during day time. Components and parts
used in the SPV power plants including the PV modules, metallic structures, cables, junction box,
switches, PCUs etc., should conform to the BIS or IEC or international specifications, wherever such
specifications are available and applicable. Solar PV system shall consist of following equi-
ments/components.
(a) Solar PV modules consisting of required number of Crystalline PV cells.
(b) Grid interactive Power Conditioning Unit with Remote Monitoring System
(c) Mounting structures
(d) Junction Boxes.
(e) Earthing and lightening protections.
(f) IR/UV protected PVC Cables, pipes and accessories
93
Modules deployed must use a RF identification tag. The following information must be mentioned in
the RFID used on each modules. This should be inside the laminate only.
a) Name of the manufacturer of the PV module
b) Name of the manufacturer of Solar Cells.
c) Month & year of the manufacture (separate for solar cells and modules)
d) Country of origin (separately for solar cells and module)
e) I-V curve for the module Wattage, Im, Vm and FF for the module
f) Unique Serial No and Model No of the module
g) Date and year of obtaining IEC PV module qualification certificate.
h) Name of the test lab issuing IEC certificate.
i) Other relevant information on traceability of solar cells and module as per ISO 9001 and
ISO 14001
Warranties:
a) Material Warranty:
i. Material Warranty is defined as: The manufacturer should warrant the Solar Module(s) to be free
from the defects and/or failures specified below for a period not less than five (05) years from the date
of sale to the original customer ("Customer")
ii. Defects and/or failures due to manufacturing
iii. Defects and/or failures due to quality of materials
iv. Non conformity to specifications due to faulty manufacturing and/or inspection processes.
If the solar Module(s) fails to conform to this warranty, the manufacturer will repair or replace the so-
lar module(s), at the Owners sole option.
94
b) Performance Warranty:
i. The predicted electrical degradation of power generated not exceeding 20% of the minimum rated
power over the 25 year period and not more than 10% after ten years period of the full rated original
output.
ARRAY STRUCTURE
a) Hot dip galvanized MS mounting structures may be used for mounting the modules/ panels/arrays.
Each structure should have angle of inclination as per the site conditions to take maximum insolation.
However, to accommodate more capacity the angle inclination may be reduced until the plant meets
the specified performance ratio requirements.
b) The Mounting structure shall be so designed to withstand the speed for the wind zone of the loca-
tion where a PV system is proposed to be installed (like Delhi-wind speed of 150 kM/hour). It may be
ensured that the design has been certified by a recognized Lab/ Institution in this regard. Suitable fas-
tening arrangement such as grouting and calming should be provided to secure the installation against
the specific wind speed.
c) The mounting structure steel shall be as per latest IS 2062: 1992 and galvanization of the mounting
structure shall be in compliance of latest IS 4759.
d) Structural material shall be corrosion resistant and electrolytically compatible with the materials
used in the module frame, its fasteners, nuts and bolts. Aluminium structures also can be used which
can withstand the wind speed of respective wind zone. Protection towards rusting need to be provided
either by coating or anodization.
e) The fasteners used should be made up of stainless steel. The structures shall be designed to allow
easy replacement of any module. The array structure shall be so designed that it will occupy minimum
space without sacrificing the output from the SPV panels.
f) Regarding civil structures the bidder need to take care of the load bearing capacity of the roof and
need arrange suitable structures based on the quality of roof.
g) The minimum clearance of the structure from the roof level should be 300 mm, for RCC type roof,
h) Ballast type structures can be used only for plants for capacity more than 40 kWp.
b) Copper bus bars/terminal blocks housed in the junction box with suitable termination threads Con-
forming to IP65 standard and IEC 62208 Hinged door with EPDM rubber gasket to prevent water entry.
Single / double compression cable glands. Provision of earthings. It should be placed at 5 feet height or
above for ease of accessibility.
c) Each Junction Box shall have High quality Suitable capacity Metal Oxide Varistors (MOVs)/ SPDs,
suitable Reverse Blocking Diodes. The Junction Boxes shall have suitable arrangement monitoring and
disconnection for each of the groups.
d) Suitable markings shall be provided on the bus bar for easy identification and the cable ferrules
must be fitted at the cable termination points for identification.
e) All fuses shall have DIN rail mountable fuse holders and shall be housed in thermoplastic IP 65 en-
closures with transparent covers.
DC DISTRIBUTION BOARD:
a) DC Distribution panel to receive the DC output from the array field.
95
b) DC DPBs shall have sheet from enclosure of dust & vermin proof conform to IP 65 protection. The
bus bars are made of copper of desired size. Suitable capacity MCBs/MCCB shall be provided for con-
trolling the DC power output to the PCU along with necessary surge arrestors.
PCU/ Inverter:
As SPV array produce direct current electricity, it is necessary to convert this direct current into alter-
nating current and adjust the voltage levels to match the grid voltage. Conversion shall be achieved
using an electronic Inverter and the associated control and protection devices. All these components
of the system are termed the “Power Conditioning Unit (PCU)”. In addition, the PCU shall also house
MPPT (Maximum Power Point Tracker), an interface between Solar PV array & the Inverter, to the
power conditioning unit/inverter should also be DG set interactive. If necessary. Inverter output should
be compatible with the grid frequency. Typical technical features of the inverter shall be as follows:
a) Three phase PCU/ inverter shall be used with each power plant system (10kW and/or above) but in
case of less than 10kW single phase inverter can be used.
b) PCU/inverter shall be capable of complete automatic operation including wake-up, synchronization
& shutdown.
c) The output of power factor of PCU inverter is suitable for all voltage ranges or sink of reactive pow-
er, inverter should have internal protection arrangement against any sustainable fault in feeder line
and against the lightning on feeder.
d) Built-in meter and data logger to monitor plant performance through external computer shall be
provided.
e) Anti-islanding (Protection against Islanding of grid): The PCU shall have anti islanding protection in
conformity to IEEE 1547/UL 1741/ IEC 62116 or equivalent BIS standard.
f) Successful Bidders shall be responsible for limiting dc injection into the grid and load as per the
CEA/state regulations.
g) The PCU/ inverter generated harmonics, flicker, DC injection limits, Voltage Range, Frequency Range
and Anti-Islanding measures at the point of connection to the utility services should follow the latest
CEA (Technical Standards for Connectivity Distribution Generation Resources) Guidelines.
h) The power conditioning units / inverters should comply with applicable IEC/ equivalent BIS standard
for efficiency measurements and environmental tests as per standard codes IEC 61683/IS 61683 and
IEC 60068-2 (1,2,14,30)/ Equivalent BIS Std.
i) The MPPT units environmental testing should qualify IEC 60068-2 (1, 2, 14, 30)/ Equivalent BIS std.
The junction boxes/ enclosures should be IP 65 (for outdoor)/ IP 54 (indoor) and as per IEC 529 specifi-
cations.
j) The PCU/ inverters should be tested from the MNRE approved test centres/ NABL/ BIS/ IEC accredit-
ed testing- calibration laboratories. In case of imported power conditioning units, these should be ap-
proved by international test houses.
The output power from SPV would be fed to the inverters which converts DC produced by SPV array to
AC and feeds it into the main electricity grid after synchronization. In case of grid failure, or low or high
voltage, solar PV system shall be out of synchronization and shall be disconnected from the grid. Once
the DG set comes into service, PV system shall again be synchronized with DG supply and load re-
quirement would be met to the extent of availability of power. 4 pole isolation of inverter output with
respect to the grid/ DG power connection need to be provided.
iii. Solar Irradiance: An integrating Pyranometer / Solar cell based irradiation sensor (along with cali-
bration certificate) provided, with the sensor mounted in the plane of the array. Readout integrated
with data logging system.
iv. Temperature: Temperature probes for recording the Solar panel temperature and/or ambient tem-
perature to be provided complete with readouts integrated with the data logging system
v. The following parameters are accessible via the operating interface display in real time separately
for solar power plant:
a. AC Voltage.
b. AC Output current.
c. Output Power
d. Power factor.
e. DC Input Voltage.
f. DC Input Current.
g. Time Active.
h. Time disabled.
i. Time Idle.
j. Power produced
k. Protective function limits (Viz-AC Over voltage, AC Under voltage, Over frequency, Under frequency
ground fault, PV starting voltage, PV stopping voltage.
vi. All major parameters available on the digital bus and logging facility for energy auditing through the
internal microprocessor and read on the digital front panel at any time) and logging facility (the current
values, previous values for up to a month and the average values) should be made available for energy
auditing through the internal microprocessor and should be read on the digital front panel.
vii. PV array energy production: Digital Tri Vector Energy Meters to log the actual value of AC/ DC volt-
age, Current & Energy generated by the PV system provided. TVM Energy meter along with CT/PT
should be of 0.5 accuracy class.
viii. Computerized DC String/Array monitoring and AC output monitoring shall be provided as part of
the inverter and/or string/array combiner box or separately.
ix. String and array DC Voltage, Current and Power, Inverter AC output voltage and current (All 3 phas-
es and lines), AC power (Active, Reactive and Apparent), Power Factor and AC energy (All 3 phases and
cumulative) and frequency shall be monitored.
x. Computerized AC energy monitoring shall be in addition to the digital AC energy meter.
xi. The data shall be recorded in a common work sheet chronologically date wise. The data file shall be
MS Excel compatible. The data shall be represented in both tabular and graphical form.
xii. All instantaneous data shall be shown on the computer screen.
xiii. Software shall be provided for USB download and analysis of DC and AC parametric data for indi-
vidual plant.
xiv. Provision for instantaneous Internet monitoring and download of historical data shall be also in-
corporated.
xv. Remote Server and Software for centralized Internet monitoring system shall be also provided for
download and analysis of cumulative data of all the plants and the data of the solar radiation and tem-
perature monitoring system.
xvi. Ambient / Solar PV module back surface temperature shall be also monitored on continuous basis.
xvii. Simultaneous monitoring of DC and AC electrical voltage, current, power, energy and other data of
the plant for correlation with solar and environment data shall be provided.
xviii. The bidders shall be obligated to push real-time plant monitoring data on a specified interval (say
15 minute) through open protocol at receiver location (cloud server) in XML/JSON format, preferably.
Suitable provision in this regard will be intimated to the bidders.
b) The bidirectional electronic energy meter (0.5 S class) shall be installed for the measurement of im-
port/Export of energy.
c) The bidder must take approval/NOC from the Concerned DISCOM for the connectivity, technical fea-
sibility, and synchronization of SPV plant with distribution network and submit the same to ECL before
commissioning of SPV plant.
d) Reverse power relay shall be provided by bidder (if necessary), as per the local DISCOM require-
ment.
5. POWER CONSUMPTION
Internal Consumption of ECL. Net Metering shall be done.
6 PROTECTIONS
The system should be provided with all necessary protections like earthing, Lightning, and grid island-
ing as follows:
Cables of appropriate size to be used in the system shall have the following characteristics:
i. Shall meet IEC 60227/IS 694, IEC 60502/IS1554 standards
ii. Temp. Range: –10oC to +80oC
iii. Voltage rating 660/1000V
99
8 CONNECTIVITY
The maximum capacity for interconnection with the grid at a specific voltage level shall be as specified
in the Distribution Code/Supply Code of the State and amended from time to time. Following criteria
have been suggested for selection of voltage level in the distribution system for ready reference of the
solar suppliers.
a) Utilities may have voltage levels other than above, DISCOMS may be consulted before finalization of
the voltage level and specification be made accordingly.
b) For large PV system (Above 100 kW) for commercial installation having large load, the solar power
can be generated at low voltage levels and stepped up to 11 kV level through the step up transformer.
The transformers and associated switchgear would require to be provided by the SPV bidders.
11 FIRE EXTINGUISHERS:
The firefighting system for the proposed power plant for fire protection shall be consisting of:
a) Portable fire extinguishers in the control room for fire caused by electrical short circuits
b) Sand buckets in the control room
c) The installation of Fire Extinguishers should confirm to TAC regulations and BIS standards. The fire
extinguishers shall be provided in the control room housing PCUs as well as on the Roof or site where
the PV arrays have been installed.
a) The bidder should carry out Shadow Analysis at the site and accordingly design strings & arrays lay-
out considering optimal usage of space, material and labour. The bidder should submit the array layout
drawings along with Shadow Analysis Report to ECL for approval.
b) ECL reserves the right to modify the landscaping design, Layout and specification of sub-systems and
components at any stage as per local site conditions/requirements.
c) The bidder shall submit preliminary drawing for approval & based on any modification or recom-
mendation, if any. The bidder submit three sets and soft copy in CD of final drawing for formal approv-
al to proceed with construction work.
15 SOLAR PV SYSTEM ON THE ROOFTOP FOR MEETING THE ANNUAL ENERGY REQUIREMENT
The Solar PV system on the rooftop of the selected buildings will be installed for meeting upto 90% of
the annual energy requirements depending upon the area of rooftop available and the remaining en-
ergy requirement of the office buildings will be met by drawing power from grid at commercial tariff of
DISCOMs.
16 SAFETY MEASURES:
The bidder shall take entire responsibility for electrical safety of the installation(s) including connectivi-
ty with the grid and follow all the safety rules & regulations applicable as per Electricity Act, 2003 and
CEA guidelines etc.
17 DISPLAY BOARD
The bidder has to display a board at the project site (above 25 kWp) mentioning the following:
a. Plant Name, Capacity, Location, Date of commissioning, estimated Power generation.
b. The size and type of board and display shall be approved by Engineer-in-charge before site inspec-
tion.
102
In order to create a user account and use the eTender portal you must read and accept this eTender
portal User Agreement.
A. UNDERTAKINGS TO BE FURNISHED ONLINE BY THE BIDDER
I DO HEREBY UNDERTAKE
1. That all the information being submitted by me/us is genuine, authentic, true and valid on the date
of submission of tender and if any information is found to be false at any stage of tendering or
contract period, I/We will be liable to the following penal actions apart from other penal actions
prescribed elsewhere in the tender document.
2. That I/we accept all terms and condition of NIT, including General Terms and Condition and
Special/Additional Terms and Condition as stated there in the tender document as available on the
website.
3. That I/we accept the Integrity Pact as given in the tender document (if applicable).
4. That I/we, am/are giving my/our consent for e-payment and submitting/ shall submit the mandate
form for e-Payment in the format as prescribed in the document in case, the work is awarded to us.
5. That I/we do authorize CIL/Subsidiary for seeking information/clarification from my Bankers having
reference in this bid.
6. That I/we will upload original/certified photo/scanned of all the relevant documents as prescribed
in the tender document in support of the information and data furnished by me/us online.
7. I/We confirm that I/We have not been banned or de-listed by any Govt. or Quasi Govt. agencies or
PSUs. In case We are banned or delisted this information shall be specifically informed to the
tender issuing authority.
8. That I/We accept all the undertakings as specified elsewhere in the tender document.
9. That this online agreement will be a part of my bid and if the work is awarded to me/us, this will be
a part of our agreement with CIL/Subsidiary Company.
COPYRIGHT NOTICE : Copyright©2013, Coal India Limited, India. All rights reserved.
YOU MAY NOT MODIFY, COPY, REPRODUCE, REPUBLISH, UPLOAD, POST, TRANSMIT, OR DISTRIBUTE, IN
ANY MANNER, THE MATERIALON THE SITE, INCLUDING TEXT, GRAPHICS, CODE AND/OR SOFTWARE.
You may print and download portions of material from the different areas of the website solely for
your own non-commercial use provided that you agree that you shall not change or delete any
copyright or proprietary materials from the site.
www.coalindiatenders.nic.in is an e-procurement portal of Coal India Limited/its Subsidiary.
103
THIS E-TENDER PORTAL AND RELATED SERVICES SUBJECT TO YOUR COMPLIANCE WITH THE USER'S
TERMS AND CONDITIONS SET FORTH BELOW:
PLEASE READ THE FOLLOWING INFORMATION CAREFULLY. YOU MAY NOT COMPLETE YOUR
REGISTRATION AND USE THE E-TENDER PORTAL WITHOUT AGREEING TO COMPLY WITH ALL OFTHE
TERMS AND CONDITIONS SET FORTH BELOW.
BY REGISTERING THE USER NAME AND PASSWORD, YOU AGREE TO ABIDE BY ALL THE TERMS AND
CONDITIONS SET FORTH BELOW:
Upon successful completion of Registration online, User ID and Password will be registered. You can
login, only by giving valid User ID and Password and then signing with your valid Digital Signature
Certificate.
The Online registration/enrolment of bidder on the portal should be done in the name of the bidder.
The person whose DSC is attached to the Registered Bidder should be either the bidder himself Or,
duly authorized by the Bidder.
User ID and password are strictly personal to each Authorised User and non-transferable. The User
shall ensure that its Authorised Users do not divulge or disclose their user ID or password to third
parties. In the event that the Authorised User comes to know that the User ID/Password has been/
might have been divulged, disclosed or discovered by any third party, user or its authorized user shall
immediately modify the password using "Change Password" option. CIL/subsidiary will have no
responsibility or obligation in this regard.
At the time of enrolment in the e-Tendering portal of CIL/its Subsidiaries, the Bidders should ensure
that the status of DSC is active on this site. The activation of newly issued DSC may take 24 hrs or
more. Hence Bidders who are obtaining new DSC should register at least 24 hrs before the submission
of Bid.
By registering in this portal, you forthwith assume the responsibility for maintaining the confidentiality
of the Password and account, and for all activities that occur under your Password or Account. You
also agree to (a). immediately notify by e-mail to Application Administrator/Nodal officer, of any
unauthorized use of your Password or Account or any other breach of security, and (b) ensure that you
log-out from your account at the end of each session. CIL/its Subsidiaries shall not be liable for any
loss or damage caused to you due to your failure to comply with the foregoing.
Registered user can modify or update some of the information in their profile as and when required at
their own discretion. However, some information such as "User ID" are protected against changes by
Bidder after enrolment and some other information such as "Bidder Name" etc. are protected against
changes by Bidder after bid submission.
Modification of software:
With consent of Project Advisory Committee, e-procurement of CIL, the Administrator of e-Tender
portal, reserves the right to modify, add, delete and/or change the contents, classification and
presentation of the information on the market place at any time as it may in its absolute discretion
find to be expedient and without giving any notice. It is the users responsibility to refer to the terms
and/or any change or addition to the same while accessing the site.
Coal India Limited reserves right to interrupt/suspend the availability of the e-Tender system without
104
System Requirements:
It is the user’s responsibility to comply with the system requirements: hardware, software, Internet
connectivity at user premises to access the eTender portal as mentioned in the home page in the link
"Resources Required".
Under any circumstances, CIL shall not be liable to the Users for any direct/indirect loss incurred by
them or damages caused to them arising out of the following:
(b). Internet Connectivity failures in respect of the equipment used by the Users or by the Internet
Service Providers, or;
(c). Inability of the Bidder to submit their bid due to any DSC related problems, hardware, software or
any other factor which are personal/ special/local to the Bidder.
Tenders shall be published by the authorized Tender Inviting Authorities of the respective Tendering
entities of CIL/subsidiary. In case of any clarifications arising out of the tenders, the users have to
contact the respective Tender Inviting Authority.
The User should complete all the processes and steps required for Bid submission. The successful Bid
submission can be ascertained once acknowledgement is given by the system through Bid Submission
number i.e. Bid ID, after completion of all the processes and steps. Coal India Limited is not
responsible for incomplete bid submission by users. Users may also note that the incomplete bids will
not be saved by the system and so the same will not be available to the Tender Inviting Authority for
processing.
The acknowledgment is the only confirmation of submission of bid, which the bidder can show as a
proof of participating in the tender. Other than this acknowledgement, no proof will be considered as
a confirmation to the submission of a bid. If the bidder fails to produce this acknowledgement
required for verification in case of dispute, his claim for submission of bid may not be considered.
Upload files:
The bidders have to ensure that the files being uploaded by them are free from all kinds of viruses and
contain only the relevant information as stated by the Tender Inviting Authorities for the particular
tender. It is not obligatory on the part of CIL/subsidiary to read each and every document uploaded by
the Bidder. If any bidder/Company has uploaded/attached irrelevant data, bogus or fabricated
certificates towards his qualification requirements to the respective tender then their User account
will be liable for termination permanently or temporarily by CIL/subsidiary without any prior notice.
User Conduct:
You agree that all information, data, text, software, photographs, graphics, messages or other
materials ("Content"), whether publicly posted or privately transmitted, are the sole responsibility of
the person from which such Content is originated. This means that you are entirely responsible for all
Content that you upload, post, email or otherwise transmit via the eTender portal.
105
CIL/subsidiary does not control the Content posted via the e-Tender portal and, as such, does not
guarantee the accuracy, integrity or quality of such Content. Hence under no circumstances,
CIL/subsidiary is liable in any manner for any Content, including, but not limited to, for any errors or
omissions in any Content, or for any loss or damage of any kind incurred as a result of the use of any
Content posted, e-mailed or otherwise transmitted via the Site.
You agree that the CIL/ Subsidiary companies reserves the right to re-tender /cancel a tender or
extend the closing date or amend the details of tender at any time by publishing corrigendum as
applicable.
Recognizing the global nature of the Internet, you agree to comply with all local rules regarding online
content and acceptable Content. Specifically, you agree to comply with all applicable laws regarding
the transmission of technical data to and from India or the country in which you reside.
Links:
The Site may provide, links to other World Wide Web sites or resources. Because CIL/subsidiary has no
control over such sites and resources, you acknowledge and agree that the CIL/Subsidiary is not
responsible for the availability of such external sites or resources, and does not endorse and is not
responsible or liable for any Content, advertising, products, or other materials on or available from
such sites or resources.
You further acknowledge and agree that the CIL/subsidiary shall not be responsible or liable, directly
or indirectly, for any damage or loss caused or alleged to be caused by or in connection with use of or
reliance on any such Content, Goods or Services available on or through any such site or resources.
Miscellaneous:
This Agreement shall all be governed and construed in accordance with the laws of India & applicable
to agreements made and to be performed in India. The e-Tender portal's failure to insist upon or
enforce strict performance of any provision of this Agreement shall not be construed as a waiver of
any provision or right. Neither the course of conduct between the parties nor trade practice shall act
to modify any provision of this Agreement. CIL/subsidiary may assign its rights and duties under this
Agreement to any party at any time without notice to you. Any rights not expressly granted herein are
reserved.
Governing Law:
Terms shall be governed by, and construed in accordance with, Indian law. The parties agree that the
principal civil court of the place where the registered office of Coal India/Subsidiary Company is
situated shall have non-exclusive jurisdiction to entertain any dispute with Coal India/Subsidiary
company. In case of dispute being with a regional Institute of CMPDIL, the principal Civil Court where
the said regional Institute is situated shall be place of suing.
CIL/subsidiary reserves the right to initiate any legal action against those bidders violating all or any of
the above-mentioned terms & conditions of e-Tender services agreement.
CIL/its Subsidiaries reserves the right to add to or change/modify the terms of this Agreement.
Changes could be made by us after the first posting to the Site and you will be deemed to have
accepted any change if you continue to access the Site after that time. CIL/its Subsidiaries reserves the
right to modify, suspend/cancel, or discontinue any or all services/ make modifications and alterations
in any or all of the content, at any time without prior notice.
General Policy:
CIL/its Subsidiaries is committed to protecting the privacy of our e-Tender site visitors. CIL/subsidiary
does not collect any personal or business information unless you provide it to us voluntarily when
conducting an online enrolment, bid submission etc. or any other transaction on the Site.
Information Collected:
When you choose to provide personal or business information to us to conduct an online transaction,
we use it only for the purpose of conducting the specific online transaction that you requested. The
information is also used for the purpose of vendor searches. For each online transaction, we require
only a minimum amount of personal and business information required to process your transaction.
When you visit our portal to browse, read pages, or download information, we automatically collect
and store only the following information:
The Internet domain and IP address from which you access our portal;
This information would help us to make our site more useful to visitors and to learn about the number
of visitors to our site and the types of technology our visitors use.
We do not give, share, sell or transfer any personal information to a third party unless required to do
so by law. If you do not want any personal or business information to be collected, please do not
submit it to us; however, without this required information we will be unable to process your online
bid submission or any other online transaction. Review, update and correction of any personal or
business information can be done directly on the Site.
Use of Cookies:
When you choose to enter into an online transaction, we use cookies to save the information that you
input while progressing through the transaction. A cookie is a very small amount of data that is sent
from our server to your computer’s hard drive. By enabling this feature, the cookie will remember the
data entered by you and next time when you visit this site, the data stored in the cookie will be
available in future.
Security:
The Site has security measures in place to protect against the loss, misuse and alteration of
information under our control.
The GePNIC eProcurement Server has functionality of automatically sending eMail / SMS alerts at
various events as per the bidders preference. There is no manual intervention while sending these
pre-defined eMail / SMS alerts. All events for which eMails / SMS being sent is also available to users
on the Dash Board / the user login of the Bidder. Although all efforts will be made to ensure timely
delivery of eMail / SMS, due to dependency in various other external factors, the delivery of eMail /
SMS may not be assured and bidders are requested to check the portal on a periodic basis for any such
events. Non receipt of eMail / SMS cannot be quoted as a reason for failure of service as this is an
added facility being provided to users.
108
ANNEXURES
Annexure-I
(To be uploaded by the Bidder on his Letter Head during submission of bid online)
To,
The Tender Committee
CIL/ Subsidiary
Tender Id No:…………………….
Dear Sir,
This has reference to above referred bid. I/we have read and examined the conditions of
contract, Scope of Work, technical specifications, BOQ and other documents carefully.
I /We am/are pleased to submit our bid for the above work. I/We hereby unconditionally accept
the bid conditions and bid documents in its entirety for the above work and agree to abide by and
fulfil all terms and conditions and specifications as contained in the bid document.
I/we here by submit all the documents as required to meet the eligibility criteria as per provision
of the bid notice/document.
I/We hereby confirm that this bid complies with the Bid validity, Bid security and other documents
as required by the Bidding documents.
If any information furnished by me/us towards eligibility criteria of this bid is found to be incorrect
at any time, penal action as deemed fit may be taken against me/us for which I/We shall have no
claim against CIL/Subsidiary.
Until a formal agreement is prepared and executed, this bid and your subsequent Letter of
Acceptance/Work Order shall constitute a binding contract between us and CIL/ Subsidiary.
Should this bid be accepted, we agree to furnish Performance Security within stipulated date and
commence the work within stipulated date. In case of our failure to abide by the said provision,
CIL/ Subsidiary shall, without prejudice to any other right or remedy, be at liberty to cancel the
letter of acceptance/ work order /award and to forfeit the Earnest Money and also debar us from
participating in future tenders for a minimum period of 12(twelve) months.
109
Annexure-II
(To be uploaded by the Bidder on his Letter Head during submission of bid online)
4. All copy of documents, credentials and documents submitted along with this Bid are genuine,
authentic, true and valid.
6. We hereby undertake that we shall register and obtain license from the competent authority
under the contract labour (Regulation & Abolition Act) as relevant, if applicable.
7. *I/We hereby confirm that we have registration with CMPF / EPF Authorities. We shall make
necessary payments as required under law.
Or
*I/We hereby undertake that we shall take appropriate steps for registration as relevant under
CMPF / EPF authorities, if applicable. We shall make necessary payments as required under law.
8. ** I/We have not been banned or delisted by any Govt., or Quasi Govt. Agencies or PSUs.
Or
**I / We ………………..have been banned by the organization named “_____________” for a period
of………………… year/s, effective from ………………. to……………………..…..
9. I/We have not been debarred by any procuring entity for violation of Preference to Make in India
(as applicable) vide Order No. P-45021/2/2017-PP (BE-II) dated 04.06.2020, issued by Govt. of India
as amended from time to time (not applicable for works with estimated value put to tender less
than 5 lakh).
10. If any information and document submitted is found to be false/ incorrect at any time,
department may cancel my/our Bid and action as deemed fit may be taken against me/us,
including termination of the contract, forfeiture of all dues including Earnest Money and banning
of our firm and all partners of the firm etc.
110
Annexure-III
………………………………………………………………….
E-mail Id ………………………………………………………
I hereby declare that the particulars given above are correct and complete. If any transaction is
delayed or not effected for reasons of incomplete or incorrect information. I shall not hold Company
responsible. I also undertake to advise any change in the particulars of my account to facilitate
updation of records for purpose of credit of amount through SBI Net / RTGS transfer/NEFT. I agree to
discharge responsibility expected of me as a participant under the scheme. Any bank charges levied by
the bank for such e-transfer shall be borne by us.
Place :
Date :
Signature of the Party / Authorised Signatory
------------------------------------------------------------------------------------------------------------------------
Certified that particulars furnished above are correct as per our records.
Banker’s Stamp
Date :
Signature of the Authorised official from the Bank)
111
Annexure-IV
REGISITERED POST/A.D.
No. date…...
To
M/S…………………………………..
……………………………………….
Dear Sir(s),
1) The…………………… (Name of the Company) considers that the items of work (specified in the
statement appended herewith) relating to the work of ……………………… undertaken by you in terms of
the above agreement have not been executed in accordance with the prescribed specifications and/ or
in a workman like manner and, therefore, cannot be accepted in terms of the above said agreement for
payment at the rates specified in the agreement.
2) The …………………… (Name of the Company) is willing to consider acceptance of the same should you
agree to receive payment at rates suitably reduced taking in consideration of substandard nature of the
said items of work. The Area Engineer of this work will determine as to what suitable reductions in the
rates should be made from the agreed rates for the said items. His decision shall be final. Pending such
decision of the Area Engineer, however, the payment for the said items of work will be made at the
provisional rates indicated against each item.
3) If you agree to the aforesaid conditions for acceptance of payment for the said items of work, you
may please return the enclosed form duly executed by you.
4) If no reply is received from you within three weeks of the date of issue of the letter, it shall be
presumed that the offer is not acceptable to you. In the said event, the offer shall stand withdrawn
without prejudice to the rights and remedies of the ………. (Name of the Company) in terms of the
contract.
Engineer-in-Charge
For and on behalf of
(Name of the Company)
112
Annexure - V
No. Date:
To
………………………………..
………………………………..
Sir,
I/We have carefully read the terms and conditions offered in your letter dated……………..and they are
acceptable to me/us.
Pending the decision of the Area Engineer of the final rates of payment against the items of work
specified in the statement attached to your above letter which will be final and binding,. I/We agree to
the same being paid at the provisional rates indicated against each of the said item of work for the
above work as mentioned in your statement.
Yours faithfully,
Contractor(s).
113
Annexure- VI
PROFORMA OF BANK GUARANTEE INLIEU OF
BID SECURITY/EARNEST MONEY
N.A.
114
Annexure- VII
WHEREAS
………….. (Name and address of the Contractor) (herein after called “the Contractor”) has
entered into a contract made as per letter of acceptance………………..dated.……..(herein after called the
said contract) with ………… (name of the Company) (hereinafter called “the Company”) to
execute …………. (name of the contract and brief description of work) on the terms and conditions
contained in the said contract.
It has been agreed that the Contractor shall furnish a Performance Security in the shape of
Bank Guarantee from a Schedule bank for a sum of Rs………….. as security for due compliance and
performance of the terms and conditions of the said contract.
We……… (name of the Bank) having its branch/Office at……..….. have, at the request of the
Contractor, agreed to furnish this bank Guarantee by way of performance Security.
NOW, THEREFORE, we the……………… Bank (herein after called The Bank) hereby, unconditionally and
irrevocably, guarantees and affirms as follows:
The Bank do hereby irrevocably guarantees and unconditionally agree with the Company that if
the contractor shall in any way fail to observe or perform the terms and conditions of the said contract
or shall commit any breach of its obligation there under, the Bank shall on its mere first written
demand, and without any objection, demur and without any reference to the contractor, pay to the
company the said sum of …………… or such portion as shall then remain due with interest without
requiring the Company to have recourse to any legal remedy that may be available to it to compel the
Bank to pay the sum, or failing on the company to compel such payment by the contractor.
Any such demand shall be conclusive as regards the liability of the Contractor to the company
and as regards the amount payable by the Bank under this Guarantee. The Bank shall not be entitled to
withhold payment on the ground that the Contractor has disputed its liability to pay or has disputed
the quantum of the amount or that any arbitration proceeding or legal proceeding is pending between
the company and the Contractor regarding the claim.
The Bank further agree that the Guarantee shall come into force from the date hereof and shall
remain in force and effect till the period that will be taken for the performance of the said Contract
which is likely to be …………. day of ………….. but if the period of Contract is extended either pursuant to
the provisions in the said contract or by mutual agreement between the contractor and the company,
the Bank shall renew the period of the Bank Guarantee failing which it shall pay to the company the
said sum of ………….…. or such lesser amount of the said sum of …………… as may be due to the company
and as the company may demand.
This Guarantee shall remain in force until the dues of the company in respect of the said sum
of ……………….and interest are fully satisfied and the Company certifies that the Contract has been fully
carried out by the Contractor and discharged the guarantee.
The Bank further agrees with the company that the company shall have the fullest liberty
without consent of the Bank and without affecting in any way the obligations hereunder to vary any of
the terms and conditions of the said contract or to extend time for performance of the said contract
from time to time or to postpone for any time or from time to time any of the powers exercisable by
the Company against the contractor and to forebear to enforce any of the terms and conditions relating
115
to the said Contract and the Bank shall not be relieved from its liability by reason of such failure or
extension being granted to the Contractor or to any forbearance, act or omissions on the part of the
company or any indulgence by the Company to the Contractor or any other matter or thing whatsoever
which under the law relating to sureties would but for this provision have the effect or relieving or
discharging the Guarantor.
The Bank further agrees that in case this Guarantee is required for a longer period and it is not
extended by the Bank beyond the period specified above, the Bank shall pay to the company the said
sum of ……….….. or such lesser sum as may then be deemed to the Company and as the Company may
require.
Notwithstanding anything contained herein the liability of the Bank under this Guarantee is
restricted to Rs………..……. The guarantee shall remain in force till the day ……*…….. of ……*..……. and
unless the guarantee is renewed or claim is preferred against the bank on or before the said date all
rights of the Company under this guarantee shall cease and the Bank shall be relieved and discharged
from all liabilities hereunder except as provided in the preceding Clause.
* The date of guarantee shall cover a period of minimum one year or 90 days beyond the date of
completion whichever is more.
Any notice by way of request, demand or otherwise hereunder maybe sent by post/e-mail/Fax
addressed to the bank branch/operative branch, which shall be deemed to be a sufficient demand
notice. Bank shall effect payment thereof forthwith.
This guarantee will not be discharged due to the change in the constitution of the Bank or the
Contractor.
The Bank has under its constitution power to give this Guarantee and Sri……………………. who has
signed it on behalf of the Bank has authority to do so.
(Signature)
(Name)
(Designation)
(Code number)
(address)
“The Bank Guarantee as referred above shall be operative at our branch at…….. payable
at………………………….
(NIT shall specify town/city of the operative Branch. Bank Guarantee shall specify name of the branch
with address of the specified town/city)”
NOTE:- The department shall ensure extension of guarantee period in case of extension of time.
116
Annexure- VIII
4) The Company shall have the fullest liberty without affecting in any way the liability of the Bank un-
der this guarantee or indemnity from time to time vary any of the terms and conditions of the said
contract or to extend the time of performance by the said contractor or to postpone any time and
from time to time any of the powers exercisable by it against the said contractor and either to enforce
or to forbear from enforcing any of the terms and conditions governing the said contract or securities
117
available to the company and the said Bank shall not be released from its liability under these pre-
sents.
5. Notwithstanding anything contained herein the liability of the said Bank under this Guarantee is re-
stricted to Rs………….. and this Guarantee shall come into force from the date hereof and shall remain
in full force and effect till ………………… unless the written demand or claim under this Guarantee is
made by the Company with us on or before ………………. all rights of the Company under this Guarantee
shall cease to have any effect and we shall be relieved and discharged our liabilities hereunder.
6. We, the said Bank lastly undertake not to revoke this Guarantee during its currency except with the
previous consent of the company in writing and agree that any change in the constitution of the said
contractor or the said Bank shall not discharge our liability hereunder.
7. This guarantee issued by Sri………….. who is authorized by the Bank.
Under jurisdiction of …………………………… court only.
118
Annexure-IX
(On Non-Judicial Stamp paper of appropriate value as per provision of the Stamp Act applicable in the
concerned state)
This Joint Venture agreement is made on this ……………………..day of…………………………………..
AMONGST/BETWEEN
M/s………………………………………, having its registered Office at ………………………...
Represented by Shri…………………………….(Name and Designation) of M/s………………...Who has power of
Attorney to enter into Joint Venture with…………………………………...andSign all documents/ agreements
on behalf of M/s……………… (hereinafter referred to as”……………….”)
AND
M/s………………………………………, having its registered Office at ………………………...
Represented by Shri…………………………….(Name and Designation) of M/s………………...who has power of
Attorney to enter into Joint Venture with…………………………………...andSign all documents/agreements
on behalf of M/s……………… (hereinafter referred to as”……………….”).
AND
M/s………………………………………, having its registered Office at ………………………...
Represented by Shri…………………………….(Name and Designation) of M/s………………...who has power of
Attorney to enter into Joint Venture with…………………………………...andSign all documents/agreements
on behalf of M/s……………… (hereinafter referred to as”……………….”).
The expressions M/s …………………..and M/s…………………and M/s ………..shall, wherever the context ad-
mits, mean and include their respective legal representatives, successors-in-interest and assigns and
shall collectively be referred to as “Joint Venture /Parties” and individually as “Joint Venture Part-
ner/Party”.
WHEREAS M/s……………….and M/s………………agreed to form a Joint Venture in order to join their forces
to obtain best results from the combinations of their individual resources of technical and manage-
ment skill, finance and equipment for the benefit of the project and in order to submit the Bid for the
work of “………………………………….............................................
……………………………………………………………………………………………………………………………….. (Hereinafter re-
ferred to as “Project”) under……………………..(Name of Company(hereinafter referred to as “the principle
Employer”).
The Parties hereby enter into this Joint Venture Agreement (hereinafter referred to as “Joint Venture
agreement”) to jointly prepare and submit the Bid for the Project and in the event of securing the Pro-
ject from the Employer, to execute the Project in accordance with the Contract terms and conditions,
to the satisfaction of the Principal Employer.
NOW THEREFORE, the parties, in consideration of the mutual premises contained herein, agree as fol-
lows:
1) FORMATION AND TERMINATION OF THE JOINT VENTURE.
The parties under this Agreement have decided to form a Joint Venture to submit the Bid for the
above Project and execute the Contract with the Principal Employer for the Project, if qualified and
awarded.
a) The name and style of the Joint Venture shall be “………………………………..”
(hereinafter called the “Joint Venture ”)
b) The Head Office of the Joint Venture shall be located at………………………. and the site office will
be located at the site of the Project. All communication regarding the project will be made
to…………………… Telephone Nos…………………………..
119
c) Neither of the parties of the Joint Venture shall be allowed to sign, pledge, sell or otherwise
dispose all or part of its respective interests in the Joint Venture to any party including the ex-
isting partner of the Joint Venture.
d) The terms of the Joint Venture shall begin as on the date first set forth above and shall termi-
nate on the earliest of the following dates.
2) LEAD PARTNER.
M/s…………………………. shall be the Lead Partner of the Joint Venture and is In-charge for perform-
ing the contract management. M/s…………………. shall be attorney of the parties duly authorized to
incur liabilities and receive instructions for and on behalf of any and all partners in the Joint Ven-
ture and also all the partners of the Joint Venture shall be jointly and severally liable during the
bidding process and for the execution of the contract as per contract terms with the employer in
accordance with the power of attorney annexed.All Joint Venture partners M/s…………………..;
M/s…………….& M/s………………………….. nominate and authorize Shri………………. ( name and designa-
tion) of M/s……………………………… to sign all letters, correspondence, papers & certificates and to
submit the Pre-qualification Application / Bid documents for and on behalf of the Joint Venture.
3) REPRESENTATIVE OF THE PARTNERS OF THE JOINT VENTURE.
Each constituent party of the Joint Venture appoints the following personnel as the representative
of the relevant party with full power of attorney from the Board of Directors of the concerned
company, or from the partners of the entity, or from the proprietor.
JV Partner Name Position in the respective Company
4.1 The parties agree that their respective participation share (hereinafter called ‘Participation
Share’) in the Joint Venture shall be as follows:
M/s………………………………….. : ……..…..% (…………..per cent)
M/s………………………………….. : ……..…..% (…………..per cent) and
M/s………………………………….. : ……..…..% (…………..per cent)
4.2 The Parties shall share the rights and obligations, risk, cost and expenses, working capitals,
profits or losses or others arising out of or in relation to execution of the Project in proportion to
their share of participation in the Joint Venture except as otherwise agreed.
4.3 The parties shall jointly execute the works under the Project as an integrated entity and allo-
cate responsibilities as regards division of work between themselves by organizing the adequate
resources for successful completion of the Project. However all parties shall remain jointly and
severally responsible for the satisfactory execution of the Project in accordance with the Contract
terms and conditions.
5) JOINT AND SEVERAL LIABILITIES.
All partner of Joint Venture shall be liable jointly and severally during the Pre-qualification and
Bidding process; and in the event the contract is awarded, during the execution of the Contract, in
accordance with Contract terms.
120
6) WORKING CAPITAL
Each party shall contribute working capital for equipment, labour and material or any expenses in-
curred for execution of the Project or any other investment required in connection with the execu-
tion of the project proportionate to the participation ratio.
7) BID SECURITY:
Bid Security, Performance Security and other securities shall be paid by the Joint Venture except as
otherwise agreed.
8) PERSONNEL & EQUIPMENT
Team of Managers / Engineers of all the partners of the Joint Venture will form part of the core
management structure and assist in execution of the project. The list of Personnel and equipment
proposed to be engaged for the project by each Party will be decided by the management
committee.
a) As between themselves, each Party shall be fully responsible for the fulfillment of all obliga-
tions arising out of its scope of the work for the Project to be clarified subject to the Agree-
ment between the Parties and shall hold harmless and indemnified against any damage arising
from its default or non-fulfillment of such obligations.
b) If any Party fails to perform its obligations described in this Agreement during the execution of
the Project and to cure such breach within the period designated by the non-defaulting party,
then the other party shall have the right to take up work, the interest and responsibilities of the
defaulting party at the cost of the defaulting party.
c) Stepping into the shoes of the existing partner of Joint Venture with all the liabilities of the ex-
isting partner from the beginning of the contract with the prior approval on Northern Company.
e) In case bid being accepted by Company, the payments under the contract shall only be made to
the Joint Venture and not to the individual partners.
Separate Bank A/c. shall be opened in the name of the Joint Venture in a scheduled or Nationalized
Bank in India asper mutual Agreement and all payments due to the Joint Venture shall be received
only in that account, which shall be operated jointly by the representative of the Parties hereto.
The financial obligations of the Joint Venture shall be discharged through the said Joint Venture
Bank Account only and also all the payments received or paid by company to the Joint Venture
shall be through that account alone.
11) LIMIT OF JOINT VENTURE ACTIVITIES.
The Joint Venture activities are limited to the bidding and in case of award, to the performance of
the Contract for the Project according to the conditions of the Contract with the Employer.
12) TAXES.
121
Each Party shall be responsible for its own taxes, duties and other levies to be imposed on each
party in connection with the Project. The taxes, duties and other levies imposed on the Joint Ven-
ture in connection with the Project shall be paid from the account of the Joint Venture.
13) EXCLUSIVITY
The Parties hereto agree and undertake that they shall not directly or indirectly either individually
or with other party or parties take part in the Bid for the said Project. Each Party further guarantee
to the other party hereto that this undertaking shall also apply to its subsidiaries and companies
under its direct or indirect control.
14) MISCELLANEOUS:
a. Neither party of the Joint Venture shall assign, pledge, sell or otherwise dispose all or part of its
respective interests in the Joint Venture to all third party without the Agreement of the other party
in writing.
b. Subject to the above clause, the terms and conditions of this agreement shall be binding upon
the parties, the Directors, Officers, Employees, Successors, Assigns and Representatives.
15) APPLICABLE LAW
IN WITNESS Whereof the Parties hereto have hereunder set their respective hands and seals the day,
month, year first above written.
Witness Witness
Signature …………………………….. Signature …………………………
Annexure-X
General
This pre-bid pre-contract Agreement (hereinafter called the Integrity Pact) is made on…………….day of
the month of ………….20…, between, on one hand, Coal India Limited/Subsidiary Cos. acting through
Shri …………………….., Designation of the officer, (hereinafter called the “BUYER / Principal”, which ex-
pression shall mean and include, unless the context otherwise requires, his successors in office and
assigns) of the First Part and M/s. …………………………..represented by Shri………………, Chief Executive Of-
ficer (hereinafter called the “BIDDER/Seller/Contractor” which expression shall mean and include, un-
less the context otherwise requires, his successors and permitted assigns) of the Second Part.
NOW, THEREFORE,
To avoid all forms of corruption by following a system that is fair, transparent and free from any influ-
ence/prejudiced dealings prior to, during and subsequent to the currency of the contract to be entered
into with a view to :-
Enabling the BUYER to obtain the desired said stores/equipment at a competitive price in conformity
with the defined specifications by avoiding the high cost and the distortionary impact of corruption on
public procurement, and
Enabling BIDDERs to abstain from bribing or indulging in any corrupt practice in order to secure the
contract by providing assurance to them that their competitors will also abstain from bribing and other
corrupt practices and the BUYER will commit to prevent corruption, in any form, by its officials by fol-
lowing transparent procedures.
The parties hereto hereby agree to enter into this Integrity Pact and agree as follows:
(1) The Principal commits itself to take all measures necessary to prevent corruption and to observe
the following principles:-
a. No employee of the Principal, personally or through family members, will in connection with the
tender for , or the execution of a contract, demand ; take a promise for or accept, for self or third per-
son, any material or immaterial benefit which the person is not legally entitled to.
b. The Principal will, during the tender process treat all Bidder(s) with equity and reason. The Principal
will in particular, before and during the tender process, provide to all Bidder(s) the same information
and will not provide to any Bidder(s) confidential / additional information through which the Bidder(s)
could obtain an advantage in relation to the tender process or the contract execution.
123
c. Principal will exclude from the process all known prejudiced persons.
(2) If the Principal obtains information on the conduct of any of its employees which is a criminal of-
fence under the IPC/ PC Act, or if there be a substantive suspicion in this regard, the Principal will in-
form the Chief Vigilance Officer and in addition can initiate disciplinary actions.
(1) The Bidder(s) / Contractor(s) commit themselves to take all measures necessary to prevent corrup-
tion. The Bidder(s) / Contractor(s) commit themselves to observe the following principles during partic-
ipation in the tender process and during the contract execution.
a. The Bidder(s) / Contractor(s) will not, directly or through any other person or firm, offer, promise or
give to any of the Principal's employees involved in the tender process or the execution of the contract
or to any third person any material or other benefit which he/ she is not legally entitled to, in order to
obtain in exchange any advantage of any kind whatsoever during the tender process or during the exe-
cution of the contract.
b. The Bidder(s) / Contractor(s) will not enter with other Bidders info any undisclosed agreement or
understanding, whether formal or informal. This applies in particular to prices, specifications, certifica-
tions, subsidiary contracts, submission or non- submission of bids or any other actions to restrict com-
petitiveness or to introduce cartelisation in the bidding process.
c. The Bidder(s) / Contractor(s) will not commit any offence under the relevant IPC/ PC Act; further the
Bidder(s) / Contractor(s) will not use improperly, for purposes of competition or personal gain, or pass
on to others, any information or document provided by the Principal as part of the business relation-
ship, regarding plans, technical proposals and business details, including information contained or
transmitted electronically.
d. The Bidder(s) / Contractors(s) of foreign origin shall disclose the name and address of the
Agents/ representatives in India , if any, Similarly the Bidder(s) /Contractors(s) of Indian Nationality
shall furnish the name and address of the foreign principals, if any. Further details as mentioned in the
"Guidelines on Indian Agents of Foreign Suppliers" shall be disclosed by the Bidder(s) / Contrac-
tor(s).Further, as mentioned in the Guidelines all the payments made to the Indian agent/ representa-
tive have to be in Indian Rupees only.
e. The Bidder(s) / Contractor(s) will, when presenting their bid, disclose any and all payments made, is
committed to or intends to make to agents, brokers or any other intermediaries in connection with the
award of the contract.
f. Bidder(s) / Contractor(s) who have signed the Integrity Pact shall not approach the Courts while rep-
resenting the matter to IEMs and shall wait for their decision in the matter.
(2) The Bidder(s) / Contractor(s) will not instigate third persons to commit offences outlined above or
be an accessory to such offences.
Section 3 - Disqualification from tender process and exclusion from future contracts
If the Bidder, before contract award, has committed a transgression through a violation of Section 2 or
in any other form such as to put his reliability or credibility as Bidder into question, the Principal is enti-
tled to disqualify the Bidder from the tender process or to terminate the contract, if already signed, for
such reason.
124
(1) If the Bidder / Contractor / Supplier has committed a transgression through a violation of Section 2
such as to put his reliability or credibility into question, the Principal is also entitled to exclude the Bid-
der / Contractor / Supplier from future contract award processes. The imposition and duration of the
exclusion will be determined by the severity of the transgression. The severity will be determined by
the circumstances of the case. In particular the number of transgressions, the position of the trans-
gressors within the company hierarchy of the Bidder and the amount of the damage. The exclusion will
be imposed for a minimum of 6 months and maximum of 3 years.
(2) A transgression is considered to have occurred if the Principal, after due consideration of available
facts and evidences within his / her knowledge concludes that there is a reasonable ground to suspect
violation of any commitment listed under Section 2 i.e “ Commitments of Bidder(s) / Contractor(s).
(3) The Bidder accepts and undertakes to respect and uphold the Principal’s absolute right to resort to
and impose such exclusion and further accepts and undertakes not to challenge or question such ex-
clusion on any ground, including the lack of any hearing before the decision to resort to such exclusion
is taken. This undertaking is given freely and after obtaining independent legal advice.
(4) If the Bidder / Contractor / Supplier can prove that he has restored / recouped the damage caused
by him and has installed a suitable corruption prevention system, the Principal may revoke the exclu-
sion prematurely.”
(1) If the Principal has disqualified the Bidder(s) from the tender process prior to the award according
to Section 3, the Principal is entitled to demand and recover the damages equivalent to Earnest Money
Deposit/ Bid Security.
(2) If the Principal has terminated the contract according to Section 3, or if the Principal is entitled to
terminate the contract according to Section 3, the Principal shall be entitled to demand and recover
from the Contractor liquidated damages of the Contract value or the amount equivalent to Perfor-
mance Bank Guarantee.
(1) The Bidder declares that no previous transgressions occurred in the last three years with any other
Company in any country conforming to the anti-corruption approach or with any Public Sector Enter-
prise in India that could justify his exclusion from the tender process.
(2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the tender pro-
cess or action can be taken as per the procedure mentioned in "Guidelines on Banning of business".
(1) In case of Sub-contracting, the Principal Contractor shall take the responsibility of the adoption of
Integrity Pact by the Sub-contractor.
(2) The Principal will enter into agreements with identical conditions as this one with all Bidders and
Contractors.
(3) The Principal will disqualify from the tender process all bidders who do not sign this Pact or violate
its provisions.
(1) The Principal appoints competent and credible Independent External Monitor for this Pact after
approval by Central Vigilance Commission. The task of the Monitor is to review independently and ob-
jectively, whether and to what extent the parties comply with the obligations under this agreement.
(2) The Monitor is not subject to instructions by the representatives of the parties and performs his/
her functions neutrally and independently. The Monitor would have access to all Contract documents,
whenever required. It will be obligatory for him / her to treat the information and documents of the
Bidders/Contractors as confidential.
He/ she reports to the Chairman, Coal India Limited / CMD, Subsidiary Companies
(3) The Bidder(s) / Contractor(s) accepts that the Monitor has the right to access without restriction to
all Project documentation of the Principal including that provided by the Contractor. The Contractor
will also grant the Monitor, upon his/ her request and demonstration of a valid interest, unrestricted
and unconditional access to their project documentation. The same is applicable to Sub-contractors.
(4) The Monitor is under contractual obligation to treat the information and documents of the Bid-
der(s) / Contractor(s) / Sub-contractor(s) with confidentiality. The Monitor has also signed declarations
on 'Non-Disclosure of Confidential Information ' and of 'Absence of Conflict of Interest'. In case of any
conflict of interest arising at a later date, the IEM shall inform Chairman, Coal India Limited / CMD,
Subsidiary Companies and recuse himself / herself from that case.
(5) The Principal will provide to the Monitor sufficient information about all meetings among the par-
ties related to the Project provided such meetings could have an impact on the contractual relations
between the Principal and the Contractor. The parties offer to the Monitor the option to participate in
such meetings.
(6) As soon as the Monitor notices, or believes to notice, a violation of this agreement, he/ she will so
inform the Management of the Principal and request the Management to discontinue or take correc-
tive action, or to take other relevant action. The monitor can in this regard submit non-binding rec-
ommendations. Beyond this, the Monitor has no right to demand from the parties that they act in a
specific manner, refrain from action or tolerate action.
(7) The Monitor will submit a written report to the Chairman, Coal India Limited / CMD, Subsidiary
Companies within 8 to 10 weeks from the date of reference or intimation to him by the Principal and,
should the occasion arise, submit proposals for correcting problematic situations.
(8) If the Monitor has reported to the Chairman, Coal India Limited / CMD, Subsidiary Companies, a
substantiated suspicion of an offence under relevant IPC/ PC Act, and the Chairman, Coal India Limited
/ CMD, Subsidiary Companies has not, within the reasonable time taken visible action to proceed
against such offence or reported it to the Chief Vigilance Officer, the Monitor may also transmit this
information directly to the Central Vigilance Commissioner.
(9) The word 'Monitor' would include both singular and plural.
This Pact begins when both parties have legally signed it. It expires for the Contractor 12 months after
the last payment under the contract, and for all other Bidders 6 months after the contract has been
awarded. Any violation of the same would entail disqualification of the bidders and exclusion from fu-
ture business dealings.
If any claim is made / lodged during this time, the same shall be binding and continue to be valid de-
spite the lapse of this pact as specified above, unless it is discharged / determined by Chairman Coal
India Limited / CMD, Subsidiary Companies.
(1) Changes and supplements as well as termination notices need to be made in writing. Side agree-
ments have not been made.
(2) If the Contractor is a partnership or a Joint Venture, this agreement must be signed by all partners
or JV members.
(3) Should one or several provisions of this agreement turn out to be invalid, the remainder of this
agreement remains valid. In this case, the parties will strive to come to an agreement to their original
intentions.
(4)Issues like Warranty / Guarantee etc. shall be outside the purview of IEMs.
(5) In the event of any contradiction between the Integrity Pact and its Annexure, the Clause in the In-
tegrity Pact will prevail.
In case of any allegation of violation of any provisions of this Pact or payment of commission, the BUY-
ER or its agencies shall be entitled to examine all the documents including the Books of Accounts of the
BIDDER and the BIDDER shall provide necessary information and documents in English and shall extend
all possible help for the purpose of such examination.
This Pact is subject to Indian Law. The place of performance and jurisdiction is the seat of the BUYER.
The actions stipulated in this Integrity Pact are without prejudice to any other legal action that may
follow in accordance with the provisions of the extant law in force relating to any civil or criminal pro-
ceedings.
(For & On behalf of the Principal) (For & On behalf of Bidder/ Contractor)
Place --------------
Date ------------
127
Witness 1:
(Name & Address)
Witness 2:
(Name & Address)
128
Annexure-XI
STAMP PAPER
(of appropriate value as per Stamp Act)
This agreement is made on ………………. day of …………….. between ( Name of Company ) having
its registered office at ……………………………………………… (hereinafter called the ‘COMPANY’ which
expression shall, unless repugnant to the subject or context, include its successors and assignees) of the
one part and ( Name of the Contractor ) carrying on business as a ( partnership/ proprietorship/ Ltd. Co.
etc. ) firm under the name and style ………………………………………………… (hereinafter called the ‘said
Contractor’ which expression shall, unless the context requires otherwise include them and their
respective heirs, executors, administrators and legal representatives) of the other part.
1) In this agreement words and expressions shall have the same meaning as are respectively assigned
to them in the tender papers hereinafter referred to.
2) The following documents which are annexed to this agreement should be deemed to form and be
read and construed as part of this agreement viz.
3) In consideration for the payment of the sum of Rs……………( W/O Value; both in words and figures )
or such other sum as may be arrived at under the clause of the specification relating to Payment by
items measurements at unit prices by the Company, the said Contractor shall, subject to the terms &
condition contained herein execute and complete the work as described and to the extent of probable
quantities as indicated in Schedule B with such variations by way of alteration, addition to or reduction
from the said works.
129
4) The company has received a sum of Rs............ towards Performance Security Deposit (1st part of
Security Deposit) in the form of Demand Draft / Certified Cheque/ B.G./ other form (details to be
furnished) .
5) The said contractor hereby covenants with the company that the company shall deduct at 5% of R/A
Bills as Retention Money (2ndpart of security deposit) as per the terms & condition of the tender/
contract.
IN WITNESS WHEREOF THE parties herein have set their hands and seals the date and year above
written.
1 Partner. Signature
2 Partner Signature
On behalf of M/S………………………………..
The Contractor, as one of the constituted attorney,
In the presence of –
Address :
Occupation :
a) Name : Signature
b) Address: .
130
Annexure-XII
To be submitted by Bidder on Non-Judicial Stamp Paper of Rs. 10/- duly attested by Notary
Public.
GUARANTEE TO BE EXECUTED BY CONTRACTOR FOR REMOVAL OF DEFECTS AFTER COMPLETION IN
RESPECT OF WTER PROOFING WORKS.
The agreement made this ……………….…..……… day of ………………Two thousand and …………………….………..
between…………………… (Hereinafter called Guarantor of the one part) and ……………… Limited
(hereinafter called the Owner of the other part).
AND WHEREAS the Guarantor agreed to give a guarantee to the effect that the said structures will
remain water and leak proof for five years from the date of giving water proofing treatment.
NOW THE GUARNTOR hereby guarantees that water proofing treatment given by him will render the
structures completely leak proof and the minimum life of such water proofing treatment shall be five
years to be reckoned from the date after the maintenance period prescribed in the contract.
Provided that the Guarantor will not be responsible for leakage caused by earthquake or structural
defects or misuse of roof or alteration and for such purpose.
a) Misuse of roof shall mean any operation, which will damage proofing treatment, like chopping of
fire wood and things of the same nature which might cause damage to the roof.
b) Alternation shall mean construction of an additional storey or a part of the roof or construction
adjoining to existing roof whereby proofing treatment is removed in parts.
c) The decision of the Engineer-in-Charge with regard to cause of leakage shall be final.
During this period of guarantee, the Guarantor shall make good all defects and in case of any defect
being found render the building water proof to the satisfaction of the Engineer-in-Charge at his cost
and shall commence the work for such rectification within seven days from the date of issue of notice
from the Engineer-in-Charge calling upon him to rectify the defects failing which the work shall be got
done by ……………………….. Coalfields by some other Contractor at the guarantor’s cost and risk. The
decision of the Engineer-in-Charge as to the cost, payable by the Guarantor shall be final and binding.
That if the Guarantor fails to execute the water proofing or commits breach thereunder, then the
Guarantor will indemnify the principal and his successors against all loss, damage, cost, expense or
otherwise which may be incurred by him by reason of any default on the part of the GUARANTOR in
performance and observance of this supplementary agreement. As to the amount of loss and / or
damage and / or cost incurred by ……………….. Coalfields, the decision of the Engineer-in-Charge will
final and binding on the parties.
IN WITNESS WHEREOF these presents have been executed by the Guarantor……….. and by …………………
and for and on behalf of ……………………….. Limited on the day, month and year first above written.
In presence of:
1.
2.
132
Annexure-XIII
We,………………………………………………………………………………………………………………..(Name of Partners of
Partnership Firm/Joint Venture), partners of …………………………………………………………………..(Name of
Partnership Firm/Joint Venture) hereby consent to abide by the provisions of Clause 16 and 16A of
General Terms and Conditions pertaining to arbitration.