Order-202 of 2020
Order-202 of 2020
Order-202 of 2020
Suo Motu Proceeding in the matter of Grid Failure in the Mumbai Metropolitan Region
on 12 October 2020 at 10.02 Hrs.
Coram
ORDER
Dated: 22 October, 2020
1. In exercise of the powers conferred by clause (zp) of sub-section (2) of Section 181 read
along with Section 86 (1) (h) of the Electricity Act, 2003 (EA), the Commission has
notified the MERC (State Grid Code) Regulations, 2020 (Grid Code). These
Regulations lay down the rules, guidelines and standards to be followed by State Entities
and Users of Intra-State Transmission System (InSTS) to plan, develop, operate and
maintain InSTS as an integrated part of Western Region Grid System and National Grid,
in the most efficient, reliable and economic manner, while facilitating a healthy
competition in the generation and supply of electricity.
2. Regulation 46.1.1 of the Grid Code specifies the reportable events which are
mandatorily required to be reported by the User/Transmission Licensee or SLDC or STU
as the case may be. These events, inter alia, include events such as Blackout/partial
system blackout, System islanding/system split, Grid indiscipline, Loss of major
generating unit, Protection failure on any element of InSTS, Power system instability.
Tripping of any element of the State Grid etc.
3. Further, as per Regulation 46.2.4 of the Grid Code, events affecting the generation
capacity and/or load of more than 1000 MW needs to be reported immediately in writing
within 24 hours from the occurrence to the Commission by MSLDC or Transmission
Licensee or User, as the case may be. The report needs to include brief details of the
event, extent and probable causes of the event.
4. A partial grid disturbance occurred in Mumbai system on 12 October 2020 at 10.02 Hrs
leading to multiple tripping of 400 kV EHV lines and Generating units which affected
the supply to a large part of Mumbai Metropolitan Region (MMR).
5. Maharashtra State Load Dispatch Centre (MSLDC) vide its letter dated 13 October
2020, has submitted the preliminary report of the above partial grid disturbance and
stated that a loss of 3508 MW load and a loss of 1375 MW generation occurred due to
partial grid disturbance in MMR occurred on 12 October 2020 at 10.02 Hrs. Also, the
preliminary reports were filed by Adani Electricity Mumbai Ltd. (AEML) and Tata
Power Company Ltd. (TPC) on 14 October 2020 intimating the event information and
power supply position in their respective areas.
6. Vide its letter dated 14 October 2020, the Commission directed MSETCL to submit the
following information:
i. System conditions prior to the occurrence (pre-fault).
ii. Details of outage management on the infrastructure affected.
400 kV Padghe
400 kV Under emergency Outage from 06:53
Hrs after tripping on OV at 04:33 Hrs
Kalwa Ckt . I on 12.10.2020
379 MW 719 MW
400 kV Kharghar 400 kV T’gaon (PG)
10.5 Status of Islanding facility and the reasons for its failure:
i. Though the islanding scheme operated as envisaged, it was partially successful.
The Mumbai network got separated from MSETCL network but TPC island was
unable to sustain due to continuous drop in frequency and tripping of its generators
(500 MW Unit 5 and 180 MW Unit 7) while AEML-T island was able to sustain
with its generators (2 x 250 MW DTPS) and critical load.
10.6 Generation loss and units tripped during occurrence:
Sr. No. Generation Unit Generation loss (MW)
1 TPC-G Unit 5 454
2 TPC-G Unit – 7A and 7B 180
3 DTPS 242
4 TPC-G Khopoli Hydro 08
5 TPC-G Bhivpuri 70
6 TPC-G Bhira Hydro 120
7 Uran 271
Total 1375
12. Vide its submission dated 14 October and 20 October 2020, TPC reiterated the
events as submitted by MSLDC and stated as under:
12.1 During partial grid failure, when the grid frequency dropped to 47.9 Hz with reverse
power from MMR to MSETCL network, Mumbai Islanding Scheme operated and
isolated MSETCL network from Mumbai Transmission Network. As a part of the
islanding operations, load shedding took place at 10:05 Hrs.
MERC Order in Case No. 202 of 2020 Page 10 of 24
12.2 TPC has carried out the restoration activities as per the Black Start Guidelines of
Western Regional Load dispatch Centre (WRLDC) in consultation with MSLDC .
12.3 TPC-T system elements including protection system worked as per the set process
during the Occurrence and Restoration of Grid.
12.4 In view of 8.5 kM of overhead section converted to EHV cables between Karanjade and
Waghivali on 220 KV Bhira-Dharavi 7 & 8, 110 KV Khopoli-Chembur and 110 KV
Khopoli-Bhokarpada-Mankhurd lines, installation of reactors at Karanjade should be
approved on priority by STU and the Commission to restrict over voltages.
13. Vide its submission dated 20 October 2020, MSEDCL stated as under:
13.1 MSEDCL’s demand and availability in MW at 10:00 hrs and 11:00 hrs i.e before and
after the grid disturbance on 12.10.2020 was as under:
Particulars At 10:00 hrs At 11:00 hrs
Demand (MW) 16132 14015
13.2 MSEDCL has load of about 2025 MW prior to incidence on EHV Substation whose
power supply affected. The grid failure resulted in load loss of MSEDCL load about
1925 MW. The details of the affected load and consumer of MSEDCL is as under:
Demand at Load
Affected
Name of 10:00 hrs on affected
Sr. Area consumers
Circle 12.10.20
No. (Lakhs) (MW)
(MW)
1 Thane Thane Municipal Corporation area,
urban S&T ward area of MCGM (Mulund & 7.7 414 349
Circle Bhandup)
2 Vashi Navi Mumbai Municipal Corporation
Circle area, Panvel Municipal Corporation
Area, Uran Tehsil of Raigad District. 8.81 1056 1056
13.3 MSEDCL has restored the supply step by step in consultation with SLDC and MSETCL.
14. Vide its submission dated 20 October 2020, BEST stated as under:
17.5 Long term measures suggested by Khaparde Committee and action taken are as under:
i. Augmentation in Mumbai generation explicitly or implicitly:
MERC Order in Case No. 202 of 2020 Page 15 of 24
- No Generation is proposed.
ii. 400 KV network connectivity and HVDC interconnection to fill up the gap of implicit
generation addition:
1000 MW HVDC terminal stations at Kudus and Aarey and HVDC cable link lines
between Kudus and Aarey is included in the STU Five Year Plan FY 2019-20 to FY
2024-25 with note as below,
“Two HVDC schemes were part of STU plan 2018-19 to 2023-24 with a note
that consolidated detail study will be carried out considering all Mumbai
related schemes separately. Subsequent STU study indicated that with inclusion
of 400 kV Velgaon, 400 kV Kalwa Switching, 400 kV Kalwa-Padghe M/C line
etc., these HVDC schemes will not be required. However in view of earlier
CEA study in this regard and as HVAC schemes were not referred to CEA, the
STU study including these HVAC schemes has been now referred to CEA for
their comments. Hence 1000 MW Kudus-Aarey HVDC link is included in the
year 2024-25 of this STU five year plan (2019-20 to 2024-25) is subject to
averse comments if any by CEA in the matter may lead to deletion of the
scheme from STU five year plan.”.
The following 400 kV Substations are in STU Five Year Plan:
(1) 400 KV Vikhroli
(2) 400 kV Kalwa-II (Bus Split)
(3) 400 kV Velgaon
Also, 400 kV Navi Mumbai awarded to M/s. Sterlite under Tariff Based Competitive
Bidding (TBCB).
iii. 400 KV Vikhroli and 400 kV Ghodbunder to be taken up immediately:
400 kV Vikhroli is taken up under TBCB and the SPV, Kharghar-Vikhroli
Transmission Pvt. Ltd. (KVTPL) is transferred to Adani Transmission Limited (ATL).
KVTPL has filed Petition for grant of Transmission Licence before the Commission
and 400 kV Vikhroli Substation is targeted for completion in March 2022. 400 kV
Ghodbunder is dropped from earlier STU Plan due to land issue.
iv. Possibility of additional interconnection/LILO of existing 220 / 400 KV lines. Bringing
extra power to Mumbai by any means to cater to the load growth of Mumbai
The following works are completed / Work in Progress/Planned:
Sr. No. Description of the scheme Status
1 220 kV Kharghar – Sonkhar HTLS Conversion Completed
Short Term
Medium Term
1 220 kV Kalwa – Salsette 3rdand 4thCkt TPC-T Completed
2 Commissioning of 220 kV Saki S/S TPC-T Completed
Interconnection of 220 KV Saki (TPC-T) – Saki
3 AEML-T Completed
(AEML-T)
Interconnection of proposed 220 KV Versova
4 Substation (TPC-T) – Versova Substation (AEML- TPC-T Completed
T)
400 KV Navi Mumbai (PGCIL)
5 CTU WIP
17.7 Following schemes are planned for strengthening of Mumbai system to increase
exchange capacity from outside and enhance reliability & security of Mumbai network.
MMR Peak
Sr. Load / Proposed Schemes
Year TTC ATC
No. Embedded
(MW) (MW)
Gen.
(MW)
3907 All Trombay I/C line HTLS + Boisar -
1 2019-20 3092 2592
877 Boisar HTLS + Boisar LILO
4024 220 kV third circuit between MSETCL
2 2020-21 Kalwa and Tata Power Salsette (KS 3212 2712
877
line # 5).
4145
3 2021-22 400 kV Kudus , 400 kV Vikhroli 3605 3105
877
4269 400 kV Padghe - Kalwa MC
4 2022-23 3902 3402
447
Sd/- Sd/-
(Mukesh Khullar) (I.M. Bohari)
Member Member