SO146
SO146
SO146
NEW DELHI
...Petitioner
Vs
1. Director (Grid operation)
Transmission Corporation of Andhra Pradesh Limited
Vidyut Soudha,
Hyderabad
2.
Director (Thermal)
Andhra Pradesh Generation Corporation Limited
Vidyut Soudha,
Hyderabad- 500082 (AP)
3.
SLDC, APTRANSCO
-----------------------------------------------------------------------------------------------------------------------------------Order in Petition No 146/MP/2013 with I.A. 36/2013
Page 1 of 38
Vidyut Soudha,
Hyderabad- 500082 (AP)
4.
Karnataka Power Corp. Limited
Shakti Bhawan,82, Race Course Road,
Bangalore-560001
5.
Karnataka Power Transmission Corporation Limited
Cauvery Bhavan,
Bangalore-560009
6.
SLDC, Karnataka Power Transmission Corporation Limited
Race Course cross road,
Bangalore
7.
Kerala State Electricity Board
Vaidyuthi Bhavanam Pattom,
Trivandrum- 695004
8.
SLDC, Kerala State Electricity Board
Kalamassery,
Ernakulam Dist.
9.
TANGEDCO
Anna Salai,
Chennai, 600002
10.
SLDC, TANTRANSCO
Chennai
11.
Superintendent Engineer- I
Electricity Dept,
Puducherry
12.
Executive Director
Power Grid Corporation of India Limited
SRTS-I,
Hyderabad
13.
Executive Director
Power Grid Corporation of India Limited,
SRTS-II,
Bangalore
14.
Executive Director
NTPC, SR HQ,
Hyderabad.
15.
General Manager
NTPC Talcher Stage-II,
Talcher
..Respondents
ORDER
This petition has been filed by the petitioner, Southern Regional Load Despatch
Centre with the following prayers, namely:
"(a) Ensure Adequacy and healthiness of protection system in compliance with
regulation 3 (e) of the CEA (Grid Standards) in terms of IEGC regulation 5.2 (e);
(b)
Form their own expert group in protection audit for periodic protection
audit of the entire substation of 220 kV and above on continuous basis and
discuss such protection audit reports in the Protection Co-ordination subcommittee of SR;
(c) Ensure different type (Principle of operation) and make of relays for Main-I
and Main-II protection as well as different input for different protection schemes
in a time bound manner on priority;
(d)
Ensure proper and periodical preventive maintenance of transmission
lines including RoW clearance, bush/jungle cutting etc., particularly in forest area
adopting best O&M Practices;
-----------------------------------------------------------------------------------------------------------------------------------Order in Petition No 146/MP/2013 with I.A. 36/2013
Page 3 of 38
(e) Ensure dual source of supply for all the auxiliaries in substation;
(f)
Ensure availability of bus sectionaliser scheme in all the 200kV/230kV
substation that may lead to Grid disturbance of category GD-I and above;
(g)
Ensure strict compliance of IEGC provision under clause 5.2 (r) in
furnishing the detailed tripping report along with DR & EL printouts within 24 hrs
of the occurrence of the event; and
(h)
Pass such further Order as this Hon'ble Commission may deem just and
proper in the circumstances of the case."
2.
The petitioner has submitted that from January, 2013, at least 16 times Grid
disturbance of Category GD-I were occurred in Southern Region (SR) due to delayed
operation or failure to operate of concerned protection relays/scheme, i.e. improper
functioning of Protection Schemes.
3.
protection audit in SR was carried out and all constituents were agreed in principle for
implementation of the recommendations. However, the status review reveals that many
recommended items are yet to be implemented. In addition,
Disturbance (GD-I) instances due to not complying with the best O and M practices by
the concerned utilities. The
4.
under
Event
Multiple tripping of
220
kV
transmission lines
at
Madakathara
sub-stations
of
KSEB
Multiple tripping of
400
kV
transmission lines
at Hassan substation
due
to
failure of CT of
POWERGRID
Simultaneous
forced outage of
multiple
transmission lines,
interconnecting
transformers
and
generating units in
SR.
Time
02.01.2013
at 13:58 hrs
10.03.2013
at
15:04:23hrs
29.03.2013
at 13:48 hrs
Description
Resulted in complete
outage of 220 kV this
sub-stations
and
thereby
loss
of
supply to parts of
North Kerala.
Led to outage of
multiple
elements
connected to 400/220
kV
Hassan
substation.
Reason
Default Fault Clearance in
Madakatathara-Areacode 220 kV
line breaker on (Y-B phase fault).
Also there was no provision like
bus sectionaliser in Madakathara
sub-station
There were two faults and during
both
instances,
there
was
delayed clearance of fault i.e., in
240 ms and 320 ms against 100
milli seconds
Total
outage
Sharavati 220
sub-station.
Total
outage
5.
Sharavati 220
sub-stations
kV
Total
outage
of
Sharavati 220 kV
sub-station.
All
running
units
at
Sharavati
hydro
station also tripped.
The petitioner has submitted that the following measures have been taken by
Third party protection audit has been carried out at Sharavati Hydro
(c)
have been
observed in the reports and some even lead to non-conformity of CEA Grid
Standards.
(d)
(Indian Electricity Grid Code) Regulations, 2010 (Grid Code), all the regional
entities
Disturbance Recorder (DR) and Event Logger (EL) printouts within 24 hours of
the event. However, there is significant delay in receiving detailed tripping report
along with DR and EL print outs from SRLDC and SRPC. Till the completion of
analysis and implementation of recommendations of SRLDC/SRPC, the system
operator is exposed with the risk of operating the system without knowing the
danger associated with those elements that caused the Grid disturbance. The
delay
in
reporting
also
adds
delay
in
implementation
of
required
corrective/preventive measures.
(e)
reported which are affecting the security, economy and efficiency of the entire
power system in Southern Region and needs to addressed quickly:
6.
(i)
(ii)
(iii)
(iv)
seeking
directions to respondents to comply with the Grid Code. The petitioner has submitted as
under:
(a)
Station of Power Grid along with generation loss of 260 MW had occurred at
(c)
400/220kV
Mamedapalli
(Hyderabad)
sub-station
of
APTRANSCO.
The
(d)
On 2.9.013 at 11:41 hrs, all connected 220 kV lines, 400kV Kaiga-II and
ICT-I and II tripped at Guttur sub-station. The synchrophasor data indicates that
there was a fault in B-phase and there was a delayed clearance of fault.
(e)
Date
of Time
tripping
tripping
10-09-2013
2:46
10-09-2013
3:04
10-09-2013
3:04
10-09-2013
3:04
10-09-2013
3:04
10-09-2013
3:04
10-09-2013
3:04
of
stage-1
protection.
The
400
kV
bus
voltage
(figure-1)
from
(f)
SRPC and SRLDC have taken all possible efforts to identify the slackness
It may be evident from the details of all the above incidents, that there is
Replies to the petition as well as IA have been filed by the Karnataka Power
Karnataka Power Corporation Ltd. (KPCL) in its reply dated 28.9.2013 has
submitted as under:
(a)
Sharavati units
1,2,3,4,5,6,7,8,9 and
10
tripped due to which generation loss of 690 MW and frequency came down from
50.05 Hz to 49.49 Hz. KPCL has submitted that it was reported on 8.1.2013 at
8:37 hrs, generator voltage reduced from 11 kV to zero causing station blackout.
The reason for this might be failure of control supply of Governor and AVR, which
in turn indicates that the root cause as 250V station battery bank, which is
unusual to its nature. However, immediately after the station blackout, DG was
started and the station was normalized and units brought on bar after 45mins.
(b)
In SGS, there are two battery banks of 1000 AH and 500 AH. Standard
O&M practices are being carried out in the corporation for regular maintenance of
batteries as under:
(i) Pilot cell readings of the battery banks are noted down daily;
(iii) Monthly topping up of distilled water for maintaining the electrolyte level
and boost charging of the battery bank if required.
(c)
(d)
Earth Fault protection at 28.1.2013 at 23.21 hrs, Chief Engineer, Sharavati, KPC
on 29.1.2013 have furnished the detailed report pertaining to system disturbance
on 28.1.2013 to SRLDC which was discussed and recorded in minutes of 17th
meeting of Protection Coordination Sub Committee held on 26.2.2013 at SRPC,
Bangalore. On 28.1.2013, it was reported that, Sharavati-Talaguppa (St-1) line
was taken on bus coupler breaker to review the settings of Main-I and Main-II
relays of ST-1 line.
(e)
At 23:20 hrs, ST-1 and ST-2 lines tripped at Talaguppa end only. ST-2 line
tripped on backup zone-3 fault at Talaguppa and ST-1 tripped on back-up earth
fault at Talaguppa end and ST-1 tripped on backup earth fault at Talaguppa end
only. Rest of line breakers hand tripped after the station bus became dead.
(f)
and ST-2 tripped at their end only on earth fault during the event. At 1:42 hrs,
ST-2 line taken into service and at 02:00 hrs, ST-1 line, which was on bus
coupler breaker was changed over to regular breaker. At 02:07 hrs, St-1 again
tripped on distance fault (Zone-1) when tried to take into service. After line
patrolling TLM staff of KPTCL informed that de-capping/flashover of R-phase line
insulator at location no. 8 has occurred and caused the disturbance for which
distance relays may not detect on zonal fault, whereas backup relays should
operate to these type of faults. However, the bus coupler breaker (taken on St-1)
at SGS end did not trip on Back-up E/F.
(g)
KPTCL, Shimoga tested the bus coupler relays and informed that the relay is
operating for distance zonal settings whereas the configured output relay for
backup E/F settings is not operating for Main-I and II relays. The output relay
was reconfigured, tested and normalized.
(h)
On the issue of Sharavati-Sirsi line:(i) On 13.6.2013, it was reported that SS-1 line tripped on distance
protection at both the ends. Subsequently, units on bar 1,2,3,6,7 and 8
tripped resulting in station shutdown. Rest of the lines were hand
tripped. Auxiliary supply resumed through DG set and subsequently,
units started from 14:40 hrs.
(ii) It was informed by KPTCL TLM staff that a bamboo branch had
fallen on SharavatiSirsi line-1, SharavatiSirsi line-2 causing phase to
-----------------------------------------------------------------------------------------------------------------------------------Order in Petition No 146/MP/2013 with I.A. 36/2013
Page 13 of 38
ground faults and R-Y phase fault, which was cleared. Thereafter, and
lines were restored at 16:20 hrs.
(iii) SS-1 line tripped on fault at both ends. SS-2 line tripped at Sirsi
end on distance protection. However, relays of SS-2 line at SS end
(ABB make REL511) found not operated. Since SS-2 line did not trip
on fault, all the running generators tripped on back-up earth fault and
remaining lines tripped at other end occurred on 13.6.2013 to SLDC
and SRPC.
(i)
taken for 220 kV Kodasalli-Nagjhari line-2 on 16.6.2013 at 12:05 hrs, during the
testing, the local breaker back-up relay of 220 kV Kodasalli-Nagjhari line-2 maloperated unexpectedly which in turn led to tripping of 220 kV bus at Kodasalli
Hydro Station.
Remedial Solution: The relay was serviced and tested and found satisfactorily.
(j)
Since SS-1 line tripped and cleared the fault in 40ms, the operation of the
SS-1 distance relay is consistent as per requirement and CEA norms and fault
on SS-2 line persisted.
(k)
Sharavati-Sirsi line-2 failed operation, it is clarified that the relays were calibrated
by KPTCL staff on 4.3.2013. However, the relays did not respond. On thorough
checking of the relays by firms, it was found that the terminal configuration of the
relays was not properly downloaded earlier and suspected files were missing.
The problem was rectified and relays were tested and found to be in order.
(l)
With regard to only 1 CVT is there for all the feeder protection, KPCL has
submitted that as per normal practice, one or two CVTs output was usually used
for feeder protection. However, as desired by SRPC, the matter of providing
CVTs for all the 3 phases of lines has been deliberated at higher levels and
included in DPR for Renovation and Up gradation of Control and Protection
system for 220/400 kV Switchyards of KPCL Generating Stations, which has
been furnished to SRPC.
(m)
With respect to same CT core being used for both Main-I and Main-II,
KPCL has submitted that as per earlier practice there was only Main-1 distance
protection for 220 kV lines. Due to interaction, pursuance for implementing Main2 protection by SRPC to 220 kV feeders also, Main-2 protection was provided at
the same core. This has not caused any grid events from past decades. As per
guidelines of CEA, Main-1 and Main-2 are required for 400 kV lines and Main1 is required for 220 kV lines and Main-2 is optional i.e. yes/no (shown in CEA`s
gazette Page No. 121 schedule-V). However, as desired by SRPC, the issue of
replacement of CTs by 5 core Cts has been deliberated at high levels and finally
approval sought for including in the DPR furnished to SRPC.
(n)
With regards to carrier protection not available for many feeders, it has
been submitted that carrier protection is provided for all the feeders. (SS-1 and
SS-2 feeder wave trap was not available during audit. The same was normalized
by KPTCL later).
(o)
With regard to very old breakers (1964 make) in poor condition, KPCL
has submitted that this in context to Sectionaliser Breaker referred by the Audit
team. As sectionaliser breakers are of BOCB type with built in CTs and also due
to space constraint in the switchyard, BOCBs of sectionaliser breaker could not
be replaced by SF6 breakers (as CTs
and
(q)
Regarding dual battery source with dual rectifier KPCL has submitted that
(r)
The work was already awarded to M/s GE India Ind. Pvt. Ltd. Bangalore on
22.3.2007. Supply of the new numerical bus-bar protection panels with relays
completed. While supplying the cables, the contractor had delivered cable short
length which was not suitable to works. The problem has been rectified
and
work is in progress.
(t)
Regarding different energisation source for breaker trip coil and tec.,
KPCL has submitted that dual battery source is already commissioned (1000AH16.1.2013 and 500AH-24.6.2013)
9.
Centre, Karnataka vide their joint reply dated 20.11.2013 have submitted as under:
(a)
system the protection system adopted for 220 kV and 400 kV networks
and the setting adopted for these protection relays are based on CBIP
guidelines and the directions of SRPC.
(b)
SRPC has formulated a third party protection audit group which audited
KPTCL from 11.10.2012 to 22.12.2012. The observations of the audit
team were discussed in SRPC meeting and minor observations were
attended. However, regarding major observations, DPR is already
prepared which is under execution.
(c)
head of the circle and 14 RT divisions for effective periodical testing and
up keeping of protection system. Further, based on the fault level and
system conditions, relay coordination is carried out during precommissioning only.
(d)
On the issue of ensuring different type and make of relays for Main-
(e)
10.
TANTRANSCO in its reply dated 6.11.2013 has submitted that adequacy and
11.
NTPC vide its reply dated 14.11.2013 has submitted that it is complying with all
directions of the petitioner and SRPC. NTPC has further submitted that directions in
respect of Ramagundam STPS and Simhadri STPS have been complied with.
12.
Kerala State Electricity Board (KSEB) in its reply dated 6.11.2013 has submitted
that all necessary steps are being taken for implementation of the recommendations
of the enquiry committee report. Protection audit has already been completed in all 23
Nos 220 kV and one No. 400 kV sub-station and on 15.6.2013 DPR prepared based
on the protection audit was submitted to SRPC . KSEB has submitted that since the
work associated with protection audit has to be executed through various departmental
procedures, four months time is not sufficient to
implement recommendation of
protection audit. KSEB has submitted that on 2.1.2013 at 13.59 hrs, MDAR tipped on
distance protection zone I, B and C phase, LBB, reclosed and A/R lock out 315 MVA
transformer Bank I (220 kV side) 200 MVA transformer bank II (220 side) SHMD,
MDPK and LMPD II 200 kV feeders tripped on LBB, which is a mal-operation. Tripping
of MDAR feeder on distance protection (zone I, B and C phases) was normal. Available
records or data did not reveal for LBB tripping. However, circuit breaker and relays were
tested and proper functioning has been ensured .KSEB has submitted that DR and EL
in major sub-stations and generating station. However, routine tests are being done to
confirm proper functionality of various protection schemes and non-occurrence of mal-
operation.
13.
submitted as under:
(a)
On 3.8.2013 at 5.26 hrs, all concerned lines and ICTS tripped at 400/220
(e)
APTRANSCO
is adopting
frequency stability by providing the load relief through under frequency relays
and F+df/dt relays methods and their periodical testing
14.
TANTRANSCO vide its affidavit dated 1.2.2014 has submitted that all the Special
months.
15.
The petitioner
filed rejoinders
to
It is to be noted that:
(i)
battery bank;
(ii)
Sharavati end;
(iii)
(iv)
Though all the above GD- 1 type grid disturbances are due to either failure
/miss-operation of sub-station equipment, protection relays and switching
elements, the respondents claim that the maintenance activities / testing /
calibration was done as per the industry standard is not justifiable.
(b)
KPCL has also linked number items with funding modality through DPR
make
OCV
Bus
sectionaliser
breaker,
replacement
of
sectionaliser breaker of BOCB type with modern Hybrid breakers etc. have been
linked to the DPR or the funding modality. It is pertinent to mention that
respondent is aware of the replacement required in its system even before the
protection audit. Instead of attending the same on priority, the respondent links
with funding modality thereby deliberately exposing the system to security threat
-----------------------------------------------------------------------------------------------------------------------------------Order in Petition No 146/MP/2013 with I.A. 36/2013
Page 23 of 38
(c)
stations, the action plan indicated by KPCL for rectification / replacement does
not match the urgency as it is required. From the time schedule mentioned by
KPCL, it appears that the procurement action is being taken as applicable for a
routine item without any due urgency on the criticality of protection system. For
some of the items, even time schedule for implementation is not mentioned.
Accordingly, the grid is exposed to security threat for longer duration / till the
implementation of identified rectification / replacement. For example in reply to
the Petition, for the replacement of old electro-mechanical relays with numerical
relays, the work is said to be in progress. In the reply to the Interim Application,
for installation of DC earth fault relay, 4 months, commissioning of numerical bus
bar protection system 6 months, is sought and for procurement of unique
Disturbance Recorder for the whole facility, procurement of GPS facility, no
timeline is provided. From the above, it is evident that KPCL adopts normal
procurement procedure even for highly critical protection items. This nature
adopting routine approach, poses severe threat to grid security for the integrated
operation of SR with NEW grid. The impact of the problems in Karantaka system
on the inter regional inter connector is very high as at present SR grid is
connected through only one 765 kV ISTS line emanating from Karnataka system.
16.
(a)
KPTCL has submitted that it has provided two different protections for
Main and back-up. However, the concern of the petitioner is that in many
locations the relays are of same make though they are configured on different
logic / principle. Under this situation, in case of any defect in configuration/
software of the relays of same make, the effect will be the same on both Main as
well as backup protection. The right approach to mitigate such a failure is to have
relays of different make for Main-I and Main-II protection respectively. This
aspect was deliberated in PCC meetings and special meetings in which the
constituents including KPTCL endorsed the requirement. Accordingly, necessary
action needs to be ensured by KPTCL.
(b)
the area. The maintenance activities in hardship terrain and forest area are the
matter of concern which makes such locations as fault prone.
(c)
properly, number of the instances enumerated in the petition could have been
averted. Probably deployment of expert team with adequate number of members
for rigorous and periodic checking by the respective constituents is essential for
this activity.
17.
(a)
TANTRANSCO has stated that the fault clearance time by the main
protection for all equipments is well within 100 m sec. However, the experience
of incident at Kayathar on 7.6.2013 confirms that the time taken for fault
clearance was about 1.5 seconds while the Central Electricity Authority (Grid
Standards) Regulations, 2010 prescribes 160 milliseconds as maximum fault
clearance time for 230 kV system.
(b)
It is reiterated that the loss of wind generation led to heavy drawl from grid
by Tamil Nadu which in turn resulted in sudden dip in Southern regional grid
frequency from 50.05 to 48.83 Hz. The Commission in its order dated 21.8.2009
in Petition No. 106/2009 had directed
(c)
(d)
It has been pointed out in the Protection Audit that for Phase I, at 230 kV
Kayathar sub-station, earth resistance had to be measured and recorded, and for
Phase II renovation of control room needs to be done and proper fire fighting and
oil drain pit to be provided for transformers. However, no response has been
received on this front of the steps taken.
18.
The petitioner, in response to NTPC reply, has submitted that as per the
19.
in the present petition, it has raised concerned on a grid disturbance of type GD-I
occurred on 3.8.2013 with regard to
However, such
instances could have been averted provided APTRANSCO regularly analyzed the
past incidents and revised the protection settings time to time in line with the changes
in the transmission network configuration. With regard to rectifications, the petitioner
has submitted that APTRANSCO attended items that generally does not involve
financial implications. However, number of other critical items were kept pending linking
funding modality. The petitioner has further submitted that the purpose of Islanding,
SPS and AUFR are different from system protection and no one type can substitute the
function of other. Accordingly, the requirement of effective and efficient system
protection cannot be deferred with complacent that other mechanisms are in service.
According the petitioner, since APTRANSCO confirms that some of the major stations
are not equipped with Disturbance Recorders and Event Loggers, it will not possible for
SRLDC and APTRANSCO to analyze the grid incidents/grid disturbances and make
good the defects noticed. Therefore, situation amounts to non-compliance of Regulation
4.6.3 of the Grid Code.
20.
The petitioner
that
considering the present status of Southern Regional Grid, it is very much essential to
have perfect protection system in place and pro-active and proper maintenance in place
of planning to attend the defect as and when it surfaces. The petitioner has further
submitted as under:
(a)
occurrence of multiple tripping leading to total black-out of 400kV / 220kV substations due to mal-operation of the protection system at many locations.
(b)
(c)
(d)
(e)
At times features such as auto re-closure, relay reach etc., were not
tested/ ensured properly. Such lapses also pose threat with multiple tripping
(f)
Constituents are not furnishing the trip report within 24 hours in terms of
(g)
Number of
continue to operate as single main and transfer bus configuration without any bus
sectionaliser breaker posing threat of total outage of the sub-station in case of
operation of bus-bar protection for any reason. The bus coupler breaker at
Gummidipundi, Sharawathi, Madakathara, Guttur etc are non-functional.
(h)
The situation is not limited to any one constituent though the degree of
issue varies. Some of the sub-stations at following locations are identified with
critical lapses:
(i)
(i)
(ii)
(iii)
(iv)
Jungle clearance) in tough terrain / forest area are not planned properly by the
constituents and thereby leading to persistent fault condition.
21.
The petitioner has further submitted that all the above facts as well as number of
lapses existing in the Southern Regional grid were brought out clearly in the Protection
Audit Report with suitable action required to be done by the constituents. All the
constituents endorsed the lapses and agreed in-principle for attending the same.
However, the progress of implementation is insignificant. The matter has been regularly
taken-up with Protection co-ordination Committee (PCC) meetings, OCC meetings, and
Special meetings of SRPC. The seriousness of the issue has been brought to the senior
management of the constituents through TCC and SRPC Board meetings. Since the
constituents still rely upon the implementation with funding from PSDF, the
implementation is getting delayed.
22.
During the course of hearing on 19.12.2013, the Commission took serious note
of the deficiencies pointed out by the petitioner and observed that the matter assumes
added importance as NEW Grid is to be shortly synchronized with the Southern Grid.
The Commission directed the petitioner to analyze as to whether Southern Grid can be
connected synchronously with NEW Grid under such deficiencies. The petitioner was
directed to file a list of detailed deficiencies in the systems of respondents and
the
respondents were directed to file an affidavit stating the deadline for attending to the
deficiencies.
The Commission also noted that the petitioner raised issue of non-
compliance of the Regulation 5.2 (r) of the Grid Code which mandated all users to
report the disturbance/fault to RLDCs within 24 hours of occurrence. The Commission
directed the petitioner to submit the instances of non-compliance by SLDC/users.
23.
In response, the petitioner vide its affidavit dated 8.1.2014 has submitted as
under:
(a)
(b)
(c)
There are many tripping instances for which the tripping report, DR and EL
print outs are yet to be received or received in a delayed manner. In the absence
of timely receipt of such details/data, it may not be possible for the petitioner to
analyse the incident immediately and come out with suggestions to avert such
instances in future. Not maintaining DR and EL in proper working condition, nonavailability of qualified / adequate personal etc., could have been some of the
reasons for non-furnishing of tripping details/ report on time. The petitioner has
filed the list of delayed receipt or non-receipt of tripping details / data as on date
with its reply.
that grid security and operation within the prescribed parameters is of prime importance
and no compromise will be allowed in this regard. The Commission considers it to be of
paramount importance in view of the fact that two major grid disturbances occurred on
30/31.7.2012. Further, grid security assumes added importance as NEW Grid has been
synchronously connected with SR Grid and there is one synchronous grid in the country
with conventional generation of about 200 GW.
25.
In the Central Electricity Authority (Grid Standards) Regulations, 2010 (CEA Grid
26.
The petitioner, after analyzing the system conditions, has submitted that any grid
27.
28.
In terms of Regulation 5.2 (r), all the users, STU/SLDC and CTU are required to
29.
The petitioner has submitted that number of respondents are not complying with
the
Commission.
the
directions of the
measures permissible under the Act and the Grid Code to provide data /information to
RLDC and RPC for maintaining reliability and security of the grid. We also make it clear
that failure in this regard will amount to non-compliance of the directions of this
Commission and render the constituent liable for proceedings under Section 142 of the
Electricity Act, 2003 and other relevant provisions. We also direct the petitioner and
SRPC to coordinate and monitor the progress and compliance of Commission's
directions and ensure compliance of Regulations 5.2 (r) of the Grid Code and report
instances of non-compliance to the Commission.
30.
The petitioner has submitted that the respondents have not fully implemented the
31.
The petitioner has further raised issue of non-compliance of Regulation 3 (1) (e)
of the CEA Grid Standards and Regulation 5.2(e) of the Grid Code. Regulation 3 (1) (e)
of the CEA Grid Standards provides as under:
3. Standards for Operation and Maintenance of Transmission Lines.
(1) All Entities, Appropriate Load Despatch Centres and Regional Power Committees, for
the purpose of maintaining the Grid Standards for operation and maintenance of
transmission lines, shall,
(e) Provide standard protection systems having the reliability, selectivity, speed and
sensitivity to isolate the faulty equipment and protect all components from any type of
faults, within the specified fault clearance time and shall provide protection coordination as
specified by the Regional Power Committee.
Explanation: For the purpose of this regulation fault clearance time means the maximum
fault clearance time are as specified in Table below-
S. No.
1
2
Time
(in
Provided that in the event of fault by a circuit breaker within the time limit
specified in Table 4, the breaker fail protection shall initiate tripping of all the
breakers in the concerned bus section to clear the fault in the next 200
milliseconds."
32.
33.
The petitioner has submitted that there have been instances where fault clearance
time has been more than the prescribed limit due to old equipment in the sub-stations.
In this regard, the petitioner should take immediate steps. We direct the respondents to
strictly comply with the provisions of Regulation 5.2(e) of the Grid Code and CEA Grid
Standards. The petitioner is directed to monitor the progress and compliance of the
Commission's directions and ensure compliance of provision of regulations. In case of
non-compliance for action plan finalized by RPC, the petitioner is at liberty to approach
the Commission with specific instances of non-compliance against defaulting entities for
necessary directions in accordance with law.
34.
35.
The petitioner has raised another issue of Jungle Clearance and non-monitoring
36.
petitioner is directed to discuss and try to resolve the issues in the Protection Coordination Committee and in case of non-resolution of the issues in RPC forum, the
petitioner is at liberty to approach the Commission for direction/decision in accordance
with law.
The issues regarding non-compliance with the provisions of the Act and
Regulations should be brought before the Commission and the implementation issues
shall be handled at RPC level. Further, RPCs shall direct constituents to implement its
recommendations in a time bound manner.
37.
The petition No. 146/MP/2013 along with IA is disposed of with the above.
Sd/-
(A.K.Singhal)
Member
sd/
(M Deena Dayalan)
Member
sd/-
(V.S.Verma)
Member
sd/-
(Gireesh B.Pradhan)
Chairperson