Start of work August 18, The other activities of the project were given, the
2023 first version of the project statement was
delivered for corrections.
Initial phase of August 27, With the information collected and the feedback,
Github 2023 the registration in Github is made for the creation
of the work repository.
Project September 26, Last meeting to be held during the month while
corrections, 2023 waiting for feedback, to think in more depth
discussions 2 about the entities, relationships and attributes.
DDL planning November 1, The meeting is held to initiate the script, the
2023 basic ideas for the creation of the script are
given.
DDL and November 10, The DDL is started, the queries to be performed
Scripts startup 2023 are started and planned.
Project November 12, On this day, we sought to finish polishing all the
Completion 2023 details of the project and to finalize it in the best
way and with everything necessary.
Results:
An efficient, third normal form database has been built which serves as an