Project
Project
Project
At
Khata No. 1540, Survey Nos. 36/2, 36/3,
37, 38, 42/1, 42/3, 43/2, 43/3, 44/1, 44/2,
44/3, 44/4, 45/1, 45/2, 45/3, 45/4, 46, 47/1,
47/2, 49/1, 49/2, 50/2, 51/2, 51/4, 57, 78,
94, 95, 96, 136 & 137 Kundalahalli Village,
Krishnarajapuram Hobli,
Bangalore East Taluk, Bangalore.
Submitted By
M/s. SHYAMARAJU & CO. (INDIA) PVT. LTD.,
“DivyaSree Chambers”,
‘A’ Wing, # 11, O’ Shaugnessy Road,
Bangalore - 560 025.
Submitted to
Ministry of Environment, Forest & Climate Change,
New Delhi – 110 003.
ENVIRONMENTAL CONSULTANTS
M/s. SAMRAKSHAN,
F- 4, I Floor, Swastik Manandi Arcade, S C Road,
Sheshadripuram, Bangalore - 560 020.
Ph. : 080 23460102
Email : info@samrakshan.co.in, samrakshanblr@gmail.com
CONTENTS
2.11.5 E – waste 72
CHAPTER: 8
PROJECT BENEFITS 135 – 136
8.1 Improvements in Physical Infrastructure 135
8.1.1 Employment 135
8.1.2 Environment 135
8.2 Improvements in Social Infrastructure 135
8.3 Other Tangential Benefits 136
CHAPTER: 9
ENVIRONMENTAL COST BENEFIT ANALYSIS 137
9.1 Introduction 137
9.2 Cost Benefit Analysis for the proposed apartment project 137
CHAPTER: 10
ENVIRONMENTAL MANAGEMENT PLAN (EMP) 138 – 155
10.1 Introduction 138
10.2 EMP During Construction Phase 138
10.2.1 Leveling and Site Clearance 139
10.2.2 Transportation of Construction Materials 139
10.2.3 Construction Activities 140
10.2.4 Wastewater Discharge 140
10.2.5 Labor Camps 141
10.2.6 Disposal Of Excavated Earth 141
10.2.7 Personnel Safety system 141
10.3 EMP during Occupancy Phase 142
10.3.1 Air Quality Management 142
10.3.2 Water Quality Management 142
10.3.3 Noise Management 143
10.3.4 Solid Waste Management 144
10.3.5 Storm Water Management 144
10.3.6 Landscape Development 145
10.3.7 Management Of Socio-Economic Issues 145
10.4 EMP Implementation Schedule 146
10.5 Financial allocation/budgetary provisions for environmental 146
management aspects
10.6 Environmental Monitoring Routines 148
10.7 Environment, Health & Safety Policy 153
10.8 Administrative Chart for Environmental Issues 153
10.9 Deploying EHS Process 155
CHAPTER: 11
SUMMARY & CONCLUSION 156 – 157
11.1 Overall Justification For Implementation of the Project 156
11.2 Explanation of how adverse effects have been mitigated 157
CHAPTER: 12
DISCLOSURE OF CONSULTANTS ENGAGED 158 – 160
12.1 The Names of the Consultants Engaged with their Brief Resume & 160
Nature Of Consultancy Rendered
12.2 Architects engaged for the project 160
12.3 Laboratory studies for monitoring 160
TABLES & FIGURES
TABLES
1.0 Land use pattern for the project 8
1.1 Area Statement for the Project 9
1.2 Car Parking Statement 13
1.3 ToRs as per the Letter From State Level Expert Appraisal 14
Committee, Karnataka. No. SEIAA 89 CON 2016 dated 18th
November 2016
1.4 Generic Structure of EIA Document 18
2.1 Land use pattern for the project 29
2.2 Water consumption and Wastewater discharge details 31
2.3 Air pollution sources during construction phase 64
2.4 Quantity of solid waste generated from project 68
2.5 Air Pollution Sources for the Proposed Project 73
2.6 Approximate quantities of construction materials required 74
2.7 IS Standards – material 78
3.1 Meteorological data of Bangalore for the year 2015 87
3.2A Techniques adopted/protocols for ambient air quality monitoring 90
3.2 B Protocol for surface water quality monitoring 90
3.2 C Protocol for ground water quality monitoring 91
3.3 Ambient air Sampling stations 93
3.4A Air Quality Data Analysis during January 2017 94
3.4B Air quality data analysis during February 2017 94
3.4C Air quality data analysis during March 2017 95
3.5 Revised National Ambient Air Quality Standards 96
3.6 Noise level monitoring stations 97
3.7 Summary of noise level 97
3.8 Limits as per Environmental Protection Rules, 1986 97
3.9 Water sampling stations 98
3.10 Surface water quality (SW 1) 99
3.11 Surface water quality (SW 2) 100
3.12 Ground water quality at all locations in the month of March 102
3.13 Soil sampling stations 104
3.14 Physico-chemical characteristics of soil at all locations in the 104
month of March
3.15 Location of sampling stations 105
3.16 Population details 109
3.17 Significant environmental attributes 117
4.1 Impact Matrix 120
6.1 Monitoring schedule for environmental parameters 130
(Construction & occupancy phase)
6.2 Financial allocation/budgetary provisions for monitoring program 131
ANNEXURE
1 Terms of Reference obtained from SEIAA, Karnataka and SEIAA to MoEF & CC transfer letter
2 Traffic impact and management study
3 Project Drawings
“DivyaSree Technopark”
CHAPTER: 1
INTRODUCTION
Preamble:
Ministry of Environment, Forest and Climate Change (MoEF & CC), Government of India has issued
Notification No. S O 1533, dated 14th September 2006 in which Building and Construction projects are
required to obtain Environmental Clearance. Further, as per the Amended EIA Notification No. S O 3999 (E)
dated 09th December 2016, projects with built up area >3,00,000 sq m are classified under A Category in the
Schedule to the Notification and shall obtain Environmental Clearance from Ministry of Environment, Forest
and Climate Change (MoEF & CC), New Delhi.
Keeping above issues under consideration, an Environmental Impact Assessment (EIA) study is conducted
which incorporates into development and planning process, a plan for environmental protection and
conservation. The procedure identifies the possible positive and negative impacts on the environment likely
to emanate as a result of construction and occupancy of a project. The EIA thus, provides for a plan which,
upon implementation, will reduce or offset the negative impacts of a project resulting in a minimum level of
environmental degradation. This minimization may be the result of implementation of project modifications or
environmental protection measures which simply reduces the severity or number or magnitude of negative
impacts. The plan may also result in utilization of positive impacts for enhancement measures which offset
negative impacts. To measure the level of plan implementation and the degree of effectiveness of the above
environmental protection provisions, the EIA provides a monitoring program. This program is so designed
that it identifies the parameters of uncertainty and measures the related impacts. It is necessary that there is
close integration of EIA with various aspects of a project including financial and engineering aspects which
ensures environmental consideration are given due weight in project selection, siting, design and operation.
Analysis of past experiences indicates that it is necessary to examine a number of problem areas in-order to
ensure that environmental concerns can be effectively integrated in the development process. Similar
approach has been adopted while conducting the EIA study for the proposed project.
Therefore, the net impact of any proposed activity could be accessed through a exhaustive study of the
environmental parameters within the study zone prior to the implementation of any proposed project and
presented in the form of ENVIRONMENTAL IMPACT ASSESSMENT (EIA) report which serves as a basis
for the establishment to develop strategies to combat the pollution either at its source of generation or at the
end of the pipe and also to implement measures to reduce the pollution either quantitatively or qualitatively
by resorting to suitable technological up-gradations from time to time.
carried out to assess the consumption of liquid & solid fuel, quantification & characterization of effluents,
solid and hazardous wastes, as applicable.
➢ The third phase includes evaluation of impacts on the environmental setting and assessment of its
effects and delineation of an Environmental Management Plan to mitigate adverse impacts on the quality
of surrounding environment.
The project proponent are required to take Environmental Clearance under the EIA notification 2006 from
MoEF & CC, New Delhi and Consent To Establish (for both air and water Acts) from the SPCB before initiating
any activity.
Projects with Built up area >3,00,000 sq m is classified under A Category in the Schedule to the Notification.
As per this Notification the States have to make necessary amendment in the building bye laws, in the state
laws to make it legally enforceable and this amendment requires to be concurred by the MoEF & CC. This
process is yet to be completed in Karnataka State. As such the present project which is having the built up
area of 8,84,081.62 sq m requires to seek Environmental Clearance from MoEF & CC, New Delhi.
ii) The EIA Notification stipulated that the activities covered under the Schedule to the Notification are
also required to seek Consent to Establish under The Air (Prevention and Control of Pollution) Act,
1981 and The Water (Prevention and Control of Pollution) Act, 1974 from Pollution Control Board.
The State Environment Impact Assessment Authority (SEIAA) in a direction issued under Section (5)
of the EP Act, to the Karnataka State Pollution Control Board vide letter No. SEIAA 2 MEET 2014
dated 01.12.2015 has directed that the Board shall consider issue of CTE only after the activity is
accorded with the EC. Accordingly the project which seek CTE after the grant of EC from MoEF &
CC.
(B) Mandatory acoustic enclosure/acoustic treatment of room for stationary DG sets (5 KVA
and above)
Noise from the DG set should be controlled by providing an acoustic enclosure or by treating the room
acoustically.
The acoustic enclosure/acoustic treatment of the room should be designed for minimum 25 dB(A)
insertion loss or for meeting the ambient noise standards, whichever is on the higher side.
The DG set should also be provided with proper exhaust muffler with Insertion Loss of minimum 25
dB (A) it should be standard make meeting the requirements of Noise as stipulated in the EP Rules.
• The user should make efforts to bring down the noise levels due to the DG set, outside his premises,
within the ambient noise requirements by proper siting and control measures.
• A proper routine and preventive maintenance procedure for the DG set should be set and followed in
consultation with the DG set manufacturer which would help prevent noise levels of the DG set from
deteriorating with use.
With the boom of the IT industry, the company through its flagship DivyaSree forayed into real estate
development in 1997 and is today rated among the top office space solution providers in South India.
Over the last fifteen years DivyaSree has developed more than 7.5 million square feet of world-class office
buildings in Bangalore, Hyderabad and Chennai, the golden triangle for IT Industry in South India. We have
created a strong brand equity with our clients which include leading IT and BPO corporations such as Cisco,
Dell, Oracle, Sun Microsystems, Google, Accenture, IBM, Wells Fargo, Logica, Tesco, Thomson Reuters,
Cognizant, Deloitte, Xerox, UBS amongst others.
Companies SEZ’s in Bangalore and Hyderabad launched during the advent of the SEZ regime, has been
well accepted by our clients above and today over 30,000 people work out of these facilities. We continue to
develop over 3 million sft in these SEZ’s which will cater to the growing IT sector.
In the year 2006, the company forayed into the burgeoning residential sector with the launch of Elan, a high-
end 375 unit complex in a popular suburb of Bangalore. Today, company has over 3 million sft of residential
developments panning a wide spectrum including high end villas, town houses, apartments and plotted
development in Bangalore, Hyderabad and Chennai. Eventually these large gated communities and
townships will house over 10,000 families.
Though the company has grown substantially over the past five years, its has maintained commitment
towards superior client service and adherence to stringent fund management and hence focused on the south
Indian markets of Bangalore, Hyderabad and Chennai. Over the next five years, the company will develop 8
million sft of commercial, residential and retail spaces in South India. The Companies diversification into the
hospitality and education sectors will see further investment and growth over the next few years.
DG sets under Operation (Block A1, A2, A3, B4 & C1) Blocks: 3 X
1010 kVA, 4 X 1250 kVA, 1 X 750 kVA and 11 X 1500 kVA capacity.
DG sets Proposed:
4 X 500 kVA, 7 X 750 kVA, 4 x 1010 kVA, 2 x 1250 KVA and 25 X
1500 kVA capacity DG sets are proposed along with the DG sets
which are under operation.
1.8 BRIEF DESCRIPTION OF NATURE, SIZE, LOCATION OF THE PROJECT AND ITS IMPORTANCE
TO THE COUNTRY, REGION:
3. Proposed Buildings: Block A5, A6, A7, A8, A9, B5 and C3:
3 Activity for which IT park and IT park & residential Blocks A7, A8 & A9 are
EC is obtained residential development added.
development
4 Blocks under 5 Blocks viz., A1, - As per EC proposal
Operation A2, A3, B4 & C1
5 Blocks under 2 Blocks viz., A4 & - As per EC proposal
Construction Residential Block
with Club House
Block
6 Total number of IT 10 Blocks 13 Blocks -
blocks
7 Residential Flats 1332 flats 1,538 flats 206 Flats
Present Scenario:
a) Under Operation: Block A1, A2, A3, B4 & C1
b) Under Construction: Block A4, Residential Block with Club House.
1.9: SCOPE OF THE STUDY – DETAILS OF REGULATORY SCOPING CARRIEDOUT (AS PER TERMS
OF REFERENCE):
The Project Report was submitted to SEIAA, Karnataka on 25th May 2016. The SEAC meeting held on 22nd,
23rd and 24th September 2016 has perused the project report and accorded Terms of Reference (TOR) to
prepare the Environmental Impact Assessment (EIA) Report. The Present Scope of study is carried out duly
considering the ToR issued by SEIAA, Karnataka. The SEIAA, Karnataka has transferred to file to MoEF &
CC, New Delhi vide their letter No. SEIAA 8 MISC2017 dated 14th March 2017 (copy appended) and the
project is required to be appraised at MoEF & CC, New Delhi.
TABLE: - 1.3 TORS AS PER THE LETTER FROM STATE LEVEL ENVIRONMENT IMPACT
ASSESSMENT AUTHORITY (SEIAA), KARNATAKA VIDE LETTER NO. SEIAA 89 CON 2016 DATED
18TH NOVEMBER 2016.
Sl.
Description Details provided in Chapter / Section
No.
1 Examine details of land use as per Master Plan of CDP image of the project site is appended as
the project site. Analysis should be made based Figure – 2.3B. The project is constructed as per
on latest satellite imaginary for land use with raw the bylaws of the planning authority.
images. Check on flood plain of any river.
2 Submit details of environmentally sensitive No environmentally sensitive places are located in
places, land acquisition status, rehabilitation of the surroundings.
communities/ villages and present status of such The project site is converted for Commercial use &
activities. therefore no rehabilitation activities are proposed.
Land description - plot and survey no.s, village,
tehsil, district, state: Section 2.6.1, Chapter 2
Area of the land: Table 2.1, Chapter 2.
3 Examine baseline environmental quality along Baseline environmental quality data is appended
with projected incremental load due to the project. in in Chapter – 3.
4 Environmental data to be considered in relation to Baseline environmental quality data is appended
the project development would be (a) land (b) in in Chapter – 3.
ground water (c) surface water (d) air (e) bio-
diversity (f) noise and vibrations (g) socio
economic and health.
5 Submit a copy of contour plan with slopes, Details appended in Section – 2.2, Chapter – 2.
drainage pattern of the site and surrounding area. Contour plan is appended as Annexure – 3.
Any obstructions of the same by the project.
6 Submit the details of the trees to be felled for the Details appended in Section 2.8, Chapter – 2.
project.
7 Submit the present land use and permission Section 2.3, Chapter - 2;
required for any conversion such as forest,
agriculture etc.
8 Submit Roles and responsibilities of the Chapter - 6.
developer etc., for compliance of environmental
regulations under the provisions of EP Act.
9 Ground water classification as per the Central Section 3.2.4, Chapter 3
Ground Water Authority.
10 Examine the details of Source of water, water Section - 2.7, Chapter – 2.
requirement, use of treated waste water and
prepare a water balance chart.
11 Rain water harvesting proposals should be made Section - 2.10, Chapter – 2.
with due safeguards for ground water quality.
Maximize recycling of water and utilization of rain
water. Examine details.
12 Examine soil characteristics and depth of ground Section - 3.2.6, Chapter – 3.
water table for rainwater harvesting.
15 DG sets are likely to be used during construction Section – 2.12 of Chapter – 2, Section – 11.2 of
and operational phase of the project. Emissions Chapter – 11.
from DG sets must be taken into consideration
while estimating the impacts on air environment.
Examine and submit details.
16 Examine road/ rail connectivity to the project site Figure 3.5, Chapter – 3
and impact on the traffic due to the proposed Traffic survey and management report is
project. Present and future traffic and transport appended.
facilities for the region should be analysed with
measures for preventing traffic congestion and
providing faster trouble-free system to reach
different destinations in the city.
17 A detailed traffic and transportation study should Traffic survey and management report is
be made for existing and projected passenger appended.
and cargo traffic.
18 Examine the details of transport of materials for Chapter – 4 and Section 10.2.2 of Chapter – 10
construction which should include source and
availability.
19 Examine separately the details for construction Environmental Management Plan is appended as
and operation phases both for Environmental Chapter – 10.
Management Plan and Environmental Monitoring Environmental Monitoring Plan with cost and
Plan with cost and parameters. parameters is appended as Chapter – 6.
20 Submit details of a comprehensive Disaster Section 7.2, Chapter 7
Management Plan including emergency
evacuation during natural and man-made
disaster.
21 Details of litigation pending against the project, if None
any, with direct/ order passed by any Court of Law
against the Project should be given.
22 The cost of the Project (capital cost and recurring EMP cost allocation is detailed in Table 10.8 and
cost) as well as the cost towards implementation Table 10.9, Chapter – 10.
of EMP should be clearly spelt out.
CHAPTER 2
PROJECT DESCRIPTION
The proposed project is at a distance of about 25 km from Bangalore City Railway Station, 35 Kms from
Kempegowda International Airport and 10 Km from HAL Airport at Latitude: 12°58” 03.45' N Longitude:
77°43” 29.24' E with 889 m above MSL. The project site is plain land sloping towards South West direction.
The project site is located in commercial zone as per Revised Master Plan 2015 of Bangalore Development
Authority. The project site is surrounded by Software Tech Parks, Commercial Establishments, Residential
Apartments etc., Expected water, power requirement & other utilities are available around the site for the
proposed buildings.
Kundalahalli lake is adjacent to the proposed project and more than 75 mts buffer is left between the lake
and the proposed buildings.
The time schedule for starting and completion of all project works at site including tender event, civil and
structure works with date and time frame is appended as Annexure.
Present Scenario:
a) Under Operation: Block A1, A2, A3, B4 & C1
b) Under Construction: Block A4, Residential Block with Club House.
2.6.3 Land Use Pattern: The project site is located in commercial zone as per Revised Master Plan 2015
of Bangalore Development Authority. The project site is proposed to be developed by giving due
considerations to the amenities & services required by the occupants. The land-use pattern of the project site
is detailed in the following table.
The water requirement in the proposed project is for domestic purpose and firefighting purposes. It includes
the quantity of water required in the houses for drinking, bathing, cooking, washing etc., The quantity of water
required for domestic purposes depends on the habits, social status, climatic conditions and customs of the
people. In India on an average the domestic water consumption under normal conditions is about 135
liters/capita/day as per NBC, the details of domestic consumption are as follows:
The total domestic water demand of the proposed project is worked based on 135 LPCD of domestic water
requirement, 45 LPCD for Commercial development / IT Park the total water requirement details are as under.
Table 2.2: WATER CONSUMPTION AND WASTEWATER DISCHARGE DETAILS: (AFTER EXPANSION
AND MODIFICATION PROPOSAL)
2 Club House:
FAR area of Club house: 4655.91 sq m
Occupancy in the building (Considering 1 person per 10 sq m of FAR Area) = 466 persons
Water requirement at 70 LPCD = 466 X 70 = 32,620 Liters/day
or say 33 KLD ---- (B)
3 Water requirement for the Residential Development: A + B = 1039 + 33
= 1072 KLD
III Water Requirement for Blocks in Modification and Expansion Proposal (IT park and
Residential Development) = 790 + 1155 + 1072
= 3017 KLD
The Sewage from the above A4, A5, A6, A7, A8, A9, B5 & C3 blocks is treated in three STP’s
of 1200 KLD, 450 KLD and 200 KLD capacity
Table 2.2: Water consumption and Waste water generation details (after modification and
expansion proposal)
Description Water required for Wastewater generation
Sl.no. the project (Assuming 90 % of the water
Supplied comes out as wastewater)
1 BLOCKS UNDER 790 KLD = 790 X 0.9
OPERATOIN: A1, A2, A3, B4 & = 638.1 or say 639 KLD
C1
2 Proposed blocks A4, A5, A6, 1155 KLD = 1155 X 0.9
A7, A8, A9, B5 &C3 = 1039.5 KLD or say 1040 KLD
3 Residential Development 1072 KLD = 1072 x 0.9
= 964.8 KLD or say 965 KLD
Total 3017 KLD 2644 KLD
EC is obtained for Sewage Treatment Plant (STP) of 2,400 KLD (2 X 1,000 + 1 X 400 KLD) from MoEF,
Letter No. SEIAA: 148: CON: 2013 dated 3rd October 2013
Presently STP of 1000 KLD + 300 KLD is under Operation, along with these STP’s, the STP of 1200 KLD,
450 KLD & 200 KLD is proposed. Therefore, after completion of construction the project will have STPs of 1
X 1000 KLD, 1 X 300 KLD, 1 X 1200 KLD, 1 X 450 KLD & 1 X 200 KLD capacities.
b. Gardening:
• Treated water used for gardening @ rate of 5 L/sq m/day
• Area available for landscape development is 78,643.55 sq m
= 78,643.55 X 5 = 3,93,217.75 L/day or say 394 KLD
Daily water
Requirement
526KLD
Recycle for Toilet
Flushing Wastewater generated 639 KLD
b) Proposed Modification and Expansion (IT Park): (A4, A5, A6, A7, A8, A9, B5 &
C3):
Daily water
Requirement
820 KLD
Daily water
Requirement
802 KLD
d) Total Project (Scenario after modification and expansion): (A1, A2, A3, A4, A5, A6, A7, A8, A9,
B4, B5, C1, C3 & Residential Block With Club House)
Daily water
Requirement
2148 KLD
Recycle for Toilet
Flushing
Wastewater generated 2644 KLD
Treatment plant for treating sewage in the campus has been proposed for a capacity of 450 cum/day.
➢ MODE OF TREATMENT
It is proposed to setup a treatment plant for treating the domestic waste, kitchen waste adopting Sequencing
Batch Reactor using diffused aeration. The other modes of treatment considered before arriving at activated
sludge process are FAB (Fluidized Aerobic Bio Reactor), ASP (Activated Sludge Process) etc. The
advantages and disadvantages of each scheme, initial investment and maintenance cost etc were compared
and finally arrived at providing a STP using SBR – Sequencing Batch Reactor.
The units proposed for the proposed STP with Sequencing Batch Reactor are:
SL. No. Name of the Unit Purpose
1 Bar Screen Chamber For removing unwanted floating materials.
To even out the flow variations and continuous uniform mixing
2 Equalization Tank
operations with course bubble.
only the supernatant is removed from the reactor and taken up for
tertiary treatment.
4 Pressure Sand Filter To filter out suspended solids if any in the treated water.
5 Activated Carbon Filter To remove color and Odor if any in the filtered water.
To disinfect the treated water to make it safe to come in contact
6 Chlorinator with humans so that the treated water can be used for gardening /
allied uses.
➢ STP
Since the plant is designed @ 450 KLD capacity and the Aeration System is designed per batch with two
SBR reactor tank. The Capacities of the Raw Sewage Pump / Filter Feed Pump are designed to ensure
a minimum optimum time in Decant cycles of the SBR.
Bar Screen
chamber
Equalization Tank
Excess sludge
Disposed in to SBR-01 SBR-02
Filter Press for
Drying
Decant Tank
PSF
ACF
Chlorine Dosage
Provide a chamber of size 1.0 m x 0.60 m to suit sewer gradient to accommodate an inclined bar screen with
opening less than 10 mm. Provide a bar screen of 20 X 6 mm flats with 10mm spacing in between as coarse
bar screen and provide a 1.0 m x 0.60m bar screen with 10mm sq openings as a Fine Bar Screen.
Equalization tank:
The flow from the bar screen chamber is let into the equalization tank. This tank is provided to even out the
flow variation, and to provide a continuous feed into the secondary biological treatment units.
Design flow = 450,000 Lit/day
Average flow = 16Hours
Provide Equalization Tank with a HRT of 6 Hours (holding capacity)
Hence required volume of the tank = 168.75m3
Provide a tank of 169,000 Lit. Capacity.
The tank size would be (67.6 Sq.m x 2.5 m) (Effective volume)
Sequencing Batch Reactor with Diffused Aeration:
Flow = 450 KLD.
BOD after treatment <10 mg/L
Assumption:
F/M ratio = 0.10
MLSS = 8000 mg/L when tank is full
Total BOD load = 157.5 kg/day
No of Reactors = 2 Nos
No of Cycles per reactor = 3 Nos
Decant Fraction of Aeration Tank = 40%
Fill Volume Per Batch = 150 Cumec
Volume of Each Reactor = 188 Cumec
Recommended Volume of Each Reactor = 188 Cumec
Over All volume of SBR = 376 Cumec
Hence provide SBR tank of capacity 376,000 liters capacity.
The aeration tank size required will be of dimension 83.6 Sqm x 4.5m SWD (effective volume).
Chlorination:
The filtered water is further chlorinated through an online automatic chlorination system with electronic dosing
pump for disaffection. Provide one no. 300 Lts capacity automatic Chlorinator with electronic metering pump
to ensure the residual chlorine level to be less than 2 PPM for disinfect ion so that it will not affect the
plantations. The Chlorinator shall be coupled with the filter outlet.
Pumps:
A. Provide 2 Nos. Sewage transfer pumps (one working and one standby)
C. Provide 2 Nos. Filter feed pumps (one working and one standby)
Capacity : 30.0 KLH @ 35 m head
: centrifugal pumps, self-priming
Solid handling size : Up to 5 mm
Duty: To pump the Treated effluent from the Pre-filtration tank through the Pressure Sand Filter and Activated
Carbon Filter.
Treatment plant for treating sewage in the campus has been proposed for a capacity of 200 cum/day.
➢ MODE OF TREATMENT
It is proposed to setup a treatment plant for treating the domestic waste, kitchen waste adopting
Sequencing Batch Reactor using diffused aeration. The other modes of treatment considered before
arriving at activated sludge process are FAB (Fluidized Aerobic Bio Reactor), ASP (Activated Sludge
Process) etc. The advantages and disadvantages of the each scheme, initial investment and
maintenance cost etc were compared and finally arrived at providing a STP using SBR – Sequencing
Batch Reactor.
The units proposed for the proposed STP with Sequencing Batch Reactor are:
SL. No. Name of the Unit Purpose
1 Bar Screen Chamber For removing unwanted floating materials.
To even out the flow variations and continuous uniform mixing
2 Equalization Tank
operations with course bubble.
Activated Sludge Process for developing the bacterial culture, which
stabilizes the waste using submerged aerators. The SBR will also act as
Sequencing Batch
3 Secondary clarifier during the settle process and as a pre-filtration tank
Reactor
during the decant phase. During the decant phase only the supernatant
is removed from the reactor and taken up for tertiary treatment.
4 Pressure Sand Filter To filter out suspended solids if any in the treated water.
5 Activated Carbon Filter To remove color and Odor if any in the filtered water.
To disinfect the treated water to make it safe to come in contact with
6 Chlorinator humans so that the treated water can be used for gardening / allied
uses.
➢ STP
Since the plant is designed @ 200 KLD capacity and the Aeration System is designed for one SBR
reactor tank. The Capacities of the Raw Sewage Pump / Filter Feed Pump are designed to ensure a
minimum optimum time in Decant cycles of the SBR.
Equalization Tank
Excess sludge
Disposed in to
SBR-01 SBR-02
Filter Press for
Drying
Decant Tank
PSF
ACF
Chlorine Dosage
SBR- Sequential Batch
Final Holding Tank Reactor
PSF- Pressure Sand
Filter
To Reuse for Flushing ACF- Activated
/ Gardening purposes Carbon Filter
Equalization tank:
The flow from the bar screen chamber is let into the equalization tank. This tank is provided to even out the
flow variation, and to provide a continuous feed into the secondary biological treatment units.
Design flow = 200,000 Lit/day
Average flow = 16Hours
Provide Equalization Tank with a HRT of 6 Hours (holding capacity)
Hence required volume of the tank = 75.0m3
Provide a tank of 75,000 Lit. Capacity.
The tank size would be (30.0 Sq.m x 2.5 m) (Effective volume)
Chlorination:
The filtered water is further chlorinated through an online automatic chlorination system with electronic dosing
pump for disaffection. Provide one no. 135 Lts capacity automatic Chlorinator with electronic metering pump
to ensure the residual chlorine level to be less than 2 PPM for disinfect ion so that it will not affect the
plantations. The Chlorinator shall be coupled with the filter outlet.
Pumps:
A. Provide 2 Nos. Sewage transfer pumps (one working and one standby)
Capacity : 22.2 KLH @ 15m head
Type : Centrifugal pumps
Solid handling size : Up to 40 mm
Duty: To pump the sewage from the Equalization tank to the SBR Tank.
C. Provide 2 Nos. Filter feed pumps (one working and one standby)
Capacity : 13.3 KLH @ 35 m head
: centrifugal pumps, self-priming
Solid handling size : Up to 5 mm
Duty: To pump the Treated effluent from the Pre-filtration tank through the Pressure Sand Filter and Activated
Carbon Filter.
Treatment plant for treating sewage in the campus has been proposed for a capacity of 1200 cum/day.
MODE OF TREATMENT
It is proposed to setup a treatment plant for treating the domestic waste, kitchen waste adopting Sequencing
Batch Reactor using diffused aeration. The other modes of treatment considered before arriving at activated
sludge process are FAB (Fluidized Aerobic Bio Reactor), ASP (Activated Sludge Process) etc. The
advantages and disadvantages of each scheme, initial investment and maintenance cost etc were compared
and finally arrived at providing a STP using SBR – Sequencing Batch Reactor.
The units proposed for the proposed STP with Sequencing Batch Reactor are:
STP
Since the plant is designed @ 1200 KLD capacity and the Aeration System is designed per batch with two
SBR reactor tank. The Capacities of the Raw Sewage Pump / Filter Feed Pump are designed to ensure a
minimum optimum time in Decant cycles of the SBR.
Bar Screen
chamber
Equalization Tank
Excess sludge
Disposed in to SBR-01 SBR-02
Filter Press for
Drying
Decant Tank
PSF
ACF
Chlorine Dosage
Equalization tank:
The flow from the bar screen chamber is let into the equalization tank. This tank is provided to even out the
flow variation, and to provide a continuous feed into the secondary biological treatment units.
Design flow = 1200,000 Lit/day
Average flow = 16Hours
Provide Equalization Tank with a HRT of 6 Hours (holding capacity)
Hence required volume of the tank = 450.0m3
Provide a tank of 450,000 Lit. Capacity.
The tank size would be (180 Sq.m x 2.5 m) (Effective volume)
Chlorination:
The filtered water is further chlorinated through an online automatic chlorination system with electronic dosing
pump for disaffection. Provide one no. 800 Lts capacity automatic Chlorinator with electronic metering pump
to ensure the residual chlorine level to be less than 2 PPM for disinfect ion so that it will not affect the
plantations. The Chlorinator shall be coupled with the filter outlet.
Pumps:
A. Provide 2 Nos. Sewage transfer pumps (one working and one standby)
Capacity : 66.7 KLH @ 15m head
Type : Centrifugal pumps
Solid handling size : Up to 40 mm
Duty: To pump the sewage from the Equalization tank to the SBR Tank.
C. Provide 2 Nos. Filter feed pumps (one working and one standby)
Capacity : 80.0 KLH @ 35 m head
: centrifugal pumps, self-priming
Solid handling size : Up to 5 mm
Duty: To pump the Treated effluent from the Pre-filtration tank through the Pressure Sand Filter and Activated
Carbon Filter.
Conclusions:
The STP would be able to treat the sewage to the standards prescribed by the PCB with treated BOD levels
less than 10 mg/lit. The treated water is safe to come in contact as the chlorination is done to kill the bacteria
disinfection. The treated water will be consumed in irrigation, flushing toilets as well as washing pavements
and driveways.
Figure 2.7: STP FLOW DIAGRAM
The project site is barren land without any vegetation. In the project 1500 new trees are proposed to be
planted in the site. The landscape of project site has been planned to provide a clean, healthy and beautiful
green environment for the people. Within the proposed project site 74% is open space, and in this about
39.20% of the total space has been designated for landscape development and has been designed to achieve
a blend between modern building and various species of plants, shrubs, to create a clean, healthy and
aesthetic environment that provides a visual retreat and relaxation to the occupants of these buildings. Most
of the plant species proposed to be planted in the project will have better environmental value in terms of
helping soil texture building, less maintenance, help bio diversity by producing nectars, fruits etc., which
attract birds and insects. The proposed Landscape area in the project is proposed with combination of
evergreen trees and ornamental flowering trees and palms.
PROPOSED TREES
No. Botanical Name Common Name
1 Michelia champaca Champaca
2 Thespesia populnea Indian Tulip tree
3 Aegle marmelos Stone apple, Beli fruit, Wood apple
4 Azadirachta indica Margosa tree, Neem
5 Sapindus emarginatus Soapnut tree, Kookatakayi, Soapberry
6 Butea monosperma Parrot tree, Palash, Dhak, Tesu , Bastard Teak
7 Pongamia pinnata Honge, Indian Beech tree
8 Bauhinia purpurea Devakanchan, Purple Butterfly tree
9 Cassia fistula Golden shower tree, Indian Laburnum
10 Saraca asoca Ashoka tree
11 Ixora brachiata Gorbale, Torchwood Ixora, Gurani, Kurati
12 Holarrhena pubescens Indrajao, Bitter Oleander, Easter tree
13 Mangifera indica Mango
14 Phyllanthus emblica Amla, Indian Gooseberry
15 Psidium guajava Guava
15 Grevillea robusta Silver Oak
16 Tectona grandis Teak
17 Cynadon dactylon Bermuda grass
18 Zoysia teunifolia Mexican grass
19 Astytasia Gangetica Chinese violet
20 Dainthus alpinus Alpine pink
21 Dianthus Sunflower
The buildings of the proposed project have Basement Floors and excavation is necessary. The total quantity
of excavated soil is about 2,23,000 cum. About 78,000 cum will be used for landscape development, 69,000
cum will be used for backfilling and 76,000 cum will be used for Road formation and hardscaping activities
within the project site. About 1000 cum of construction debris generated will be used as preparatory for road
formation within the project site.
TEMPORARY STRUCTURES:
Presently about 250 construction workers are engaged for construction activities. (Construction of Block A4
and Residential is under progress). Further, additional 250 workers will be engaged for modification and
expansion proposal. 50 Sheds and 30 Toilets with bathrooms are provided for construction workers and
additional sheds and facilities will be provided for workers once construction of new blocks are started. The
temporary structures are made during the construction phase such as workers sheds; storage yards for
construction materials will be dismantled and re-used for future developmental activities.
Rain Water harvesting potential = Intensity of Rainfall (m) x Roof Area x Impermeability Factor.
The collection efficiency accounts for the fact that all the rain water falling over an area cannot be effectively
harvested due to losses on account of evaporation, spillage or run off etc.,
According to the data available from the Indian Meteorological Department, the Average annual rainfall
around month of September = 194.80 mm
Assuming that about 90 % Rainfall can be effectively harvested.
Number of Rainy Days = 9.3
Therefore the I.R = 194.80/9.3= 20.94 mm/day or 0.02094 m/day
or 0.021 m/day
Quantity of Rain Water that can be harvested from the building is as follows.
Sl. Description Top Floor area Area (Considering 75 Quantity of rainwater
No. (sq m) % of floor area) harvested (*)
1. Blocks under Operation
Block A1 4934.21 3700.65 70
Block A2 1629.25 1221.93 23
Block A3 3341.5 2506.12 47
Block B4 2743.79 2057.84 39
Block C1 4274.83 3206.12 61
Total 240 KLD
2. Proposed blocks (IT Park)
Block A4 3889.82 2917.36 55
Block A5 & 6539.86 4904.89 93
A6
Block A7 610.66 457.99 9
Block A8 2400 1800 34
Block A9 3800 2850 54
Block B5 1678.98 1259.23 24
Block C3 2904.32 2178.24 42
3. Residential Development
Tower R1 1737.39 1303.04 25
Tower R2 1536.63 1152.47 22
Tower R3 1115.19 836.39 16
Tower R4 4376.24 3282.18 62
436 cum/day
Total
The amount of storm water that the landscaped area will produce can be determined by considering
the impermeability factor to be 0.3
Q = 0.021 x 78,643.55sq m x 0.3
= 495.45 cum/day or say 496 cum/day
The Proponents shall also Provide Recharging Pits along the inner periphery of the boundary wall with
recharging pit of size 1.2 m dia x 2.5 m deep spaced at 20 m center to center. These recharging pits are
filled with graded media comprising of Boulder at bottom and with coarse aggregates to facilitate
percolation of harvested rain water to Recharge Ground Water table. The Recharge Pits are interconnected
in such a way that the rain led to the first recharge pit is also led to the next pit. The excess rain water shall
be drained off to the storm water drain.
Per capita generation of refuse from residential establishments: 0.3 to 0.6 kg/capita/day according to the
Manual on Municipal Solid Waste Management (first edition) – Pg. 48, 3.3.6.2.
The solid Wastes generated will be segregated at its point of generation and collected separately in different
color coded Synthetic Bins depending upon the basis of its Bio Degradability at a common designated point.
The collection and disposal of the solid wastes from the Project is done in such a way that it is scientifically
disposed without causing eyesore or any adverse effects to the surrounding environment. Organic solid
waste from the project will be treated in an organic converter and is used as manure for Landscape or used
as fuel. The inorganic solid waste will be sent for recycling.
Fuel pellets needs 2-3 days of sun drying and bio-manure needs 10-15 days of curing time in open space.
The compost formed by this method will have a pH value of 6.5 – 7.5 C: N ratio of 15:1 and organic matter
of 40 – 50%. There will not be any pathogens and the pellets manufactured will have a calorific value of 3500
to 4000 Kcal/kg.
2.11.5 e – waste:
The electronic waste (e-waste) such as radios, televisions, computer and its components, used batteries,
etc. from the project will be segregated, collected and stored at a designated place and will be handed over
to authorized recyclers.
The construction materials are proposed to be obtained from the dealers in the surrounding areas.
LOADS:
A. Dead loads:
Dead load shall include weight of all structural and architectural components. Self-weight of the materials
shall be calculated on the basis of unit weights given in IS: 875.
B. Live loads: Following live loads are considered while designing the structural elements apart from the dead
loads as per codes.
Sl. Particulars Loads considered
No.
1 Lobby 400 kg/ sq m
2 Toilets 400 kg/ sq m
3 Lift machine rooms 1000 kg/ sq m or as per actuals
4 Electrical rooms 750 kg/ sq m or as per actuals
5 UPS rooms 1250 kg/ sq m or as per actuals
6 Server rooms 1200 kg/ sq m or as per actuals
7 Terraces 400 kg/sq m
The parameters for calculation of design wind speed as per IS:875-1987 is as follows
Basic wind speed, Vb 33 m/s
Risk coefficient, K1 1.0
Terrain, height, structure size factor, To suit the height of the structure for terrain category - 1
K2 and class A or appropriate.
Topography factor, K3 1.0
The external and internal pressure co-efficient shall be as per respective clauses of IS: 875
F. Seismic load:
Zone : II
Zone factor : 0.10
Importance factor : 1.00
Response reduction factor : 3.0
Average response acceleration coefficient (sa/g) : As per soil conditions
Infill panels : No infill panels
Detailing as per IS-13920-2002 : Ordinary moment
Resistant frame with wall : Torsional force due to mass and
stiffness irregularities in the
building shall be accounted in
analysis & design appropriately.
MATERIALS:
Materials specified will conform to the latest edition of the relevant Indian Standards or other accepted
standard. Specifications for materials will include for sampling and testing as stipulated in the design
standards.
A. Concrete:
A) All structural concrete shall have cube-crushing strength varying from M25 to M40 N/sq m at 28 days.
B) Plain cement concrete shall have cube crushing strength of 10 N/sq.mm (M10) at 28 days.
B. Reinforcement steel:
All reinforcement shall confirm to IS: 1786 – 1985 having minimum yield strength of 500 N/sq.mm.
C. Structural steel:
All structural steel shall confirm to IS: 2062 with minimum yield strength of 250 N/sq.mm
Reinforcement beams - 40 mm
Slabs - 35 mm
Ribs - 45 mm
Columns - 40 mm
Footings/Foundations - 50 mm
Minimum grade of concrete - mild – M 25
EXPANSION JOINTS:
Expansion gap between two structures shall be sufficient to accommodate temperature and shrinkage
effects, wind and earthquake loads. Expansion joints at suitable locations shall be provided.
A. Underground waterproofing
Underground waterproofing with APP modified membrane with polyester reinforcement. The membrane is
reinforced with a reinforcement layer of non-woven polyester of minimum 180 g/m². The upper surface is
finished with calibrated granules of 1 to 2 mm if required, pressed mechanically into the bitumen. The under
surface is finished with a polyethylene foil of 12-micron thickness. The total membrane thickness is 4 mm
and 4.5 kg/sq m.
B. Roof waterproofing
A flexible waterproof membrane is proposed. The upper coating consists of a mixture of penetration bitumen,
improved with amorphous poly alpha olefins / APP. The under coating consists of a mixture of penetration
bitumen, improved with Styrene-Butadiene-Styrene (SBS) / APP membrane. The membrane is reinforced
with a layer of non-woven polyester of minimum 180 g/sq m. The upper surface is finished with colored slates,
pressed mechanically into the bitumen if required. The under surface is finished with a polyethylene foil. The
membrane thickness is 4.00 mm and has a minimum weight of 4.8 kg.
STRUCTURAL SYSTEM:
General structural system for all floors is a combination of flat slab and waffle slab with columns, core walls
and shear walls.
A. Structural configuration
Flat slab system & waffle slab system:
a) Column grids 10 .5 m x 10.5 m
b) Structural system Waffle slab
c) Waffle 455 mm depth
d) Column drop 450mm depth
e) Peripheral beams 300 mm x 900 mm
f) Core walls 200 mm thick
g) Column size 900 x 900 mm for specified grid
B. Foundation
Foundations are designed based on geo technical investigation report and will dissipate all the vertical and
horizontal loads safely to the soil below. Isolated, combined footings or raft is envisaged depending on the
soil load bearing capacity. Keeping in view the probable perched water table, waterproofing shall be done
as recommended.
C. Design standards
Specific applicable codes and standards will be identified and adopted in the design philosophies as
appropriate to the structural elements. The latest editions of the Codes and Standards will be used in designs.
All design work shall be based on Indian Standards and Codes with latest revision, with amendments if any,
as on date.
D. IS CODES – DESIGNS
IS : 875 Part 1 1987 Code of practice for unit weight of materials.
IS : 875 Part 2 1987 Code of practice for live loads.
IS : 875 Part 3 1987 Code of practice for wind loads.
IS : 1893 - 2002 Code of practice for seismic loads.
IS : 456 - 2000 Code of practice for plain and reinforced concrete
IS : 800 - 1989 Code of practice for steel design
IS : 1080 Code of practice: design and construction of shallow foundations
IS : 1904 COP for structural safety of building foundations
IS : 3370 COP for concrete structures for storage of liquids
SP: 16 Design aid for reinforced concrete to IS: 456
SP: 34(S&T)-1987 Handbook on concrete reinforcement and detailing
IS : 13920-2002 COP for ductility detailing for seismic forces
DESIGN PHILOSOPHY:
A. CONCRETE STRUCTURES
The structure proposed is of cast in-situ concrete construction with columns suitably placed. The core walls
around lifts, stairs and shear walls are of cast in-situ concrete to resist lateral forces.
The structural design of the project is based on Indian Standard Codes and is analyzed for dead, live, wind
and seismic load conditions taking into consideration relevant load combinations recommended by the codes.
The vertical loads including the dead and superimposed loads and the lateral loads due to wind and seismic
forces are transferred to the soil through proposed reinforced concrete core walls/shear walls, columns and
footings. Footings are sized with consideration to the safe bearing capacity of soil at the level of transfer of
load recommended by specialist soil investigation consultants. Geo technical Investigation has been carried
out to assess the soil stability and safe bearing capacity for designing the proposed structure in the project.
The type of footings proposed is either individual, combined or raft depending on the soil investigation report
at specific locations as the soil strata varies considerably over the extent of proposed plot.
Following are the design considerations for the liquid retaining structures.
i. Crack width
ii. Strength
iii. Deflection
They are designed based on the above criteria by limit state method. The limiting crack width shall be 0.2
mm for liquid retaining structure/underground structures and 0.3 mm for super structure.
The proposed project will be provided with adequate fire protection arrangements such as
➢ Fire water tanks for residential development.
➢ Fire pump, wet riser system, hose reel, hose box, fire alarm system, portable fire extinguisher, fire pump,
emergency light etc. are proposed.
➢ Automatic sprinklers shall be installed in the entire building. The portable fire extinguishers shall be
provided at strategic locations.
2.16 Assessment of New & untested technology for the risk of technological failure:
Proposed project is Construction of Software Technology Park project and hence assessment of new and
untested technology for the risk of technological failure is not envisaged.
CHAPTER: 3
DESCRIPTION OF THE ENVIRONMENT
The study of baseline environmental status helps in assessing the existing environmental conditions of the
project area and identifying the critical environmental attributes, which would be monitored after
implementation of the project. This would facilitate the comparison of the resultant environmental conditions
in the post project scenario with the present-day conditions and would help in preserving the environment
without any deterioration.
The study area covers 10 KM radius of the proposed project site. This chapter illustrates the description of
the present environmental status of the study area with reference to the prominent environmental setting to
adjust the baseline conditions which are described with respect to climate, hydro-geological aspects,
atmospheric conditions, water quality, soil quality, ecology, socio-economic profile, land use etc. besides
marine environment. The present report incorporates the primary baseline environmental data related to land,
air, water, soil, noise, ecology and socio-economic status along with secondary data collected from various
Government, Semi-Government and Public-Sector organizations. Secondary data collected from various
scientific studies conducted in the study area by different organization are utilized in the report.
3.1.2 Period:
Baseline study in this Environmental Impact Assessment report was conducted for a period of three months
during January to March 2017.
3.1.3 Components:
Air, Noise, Water & Soil analysis studies were carried out. Survey of the flora & fauna in the surroundings &
demographic pattern of the survey area were also studied.
3.1.4 Methodology:
Baseline environmental studies were conducted to know the status of various environmental attributes viz.,
climatic and atmospheric conditions, air, water, noise, soil, land use pattern, ecological, socio-economic
environment. The studies involved conducting field studies and analyzing various parameters that might be
affected by the project and conducting socio-economic survey among the people. Secondary data was
collected from State/Central Government organizations, Semi-Government & public sector organizations.
State Karnataka
District Bangalore
Tehsil K R Puram Hobli, Bangalore East Taluk
Village Kundalahalli Village
Nature of the Land/Area Project site was barren / vacant land.
Presently construction work is in progress
Project Coordinates
Project Site Co-ordinates Latitude: 12°58” 03.45' N
Longitude: 77°43” 29.24' E
Geological & Meteorological Features
MSL 889 m
Nearby Locations
Nearest Railway Station Bangalore City Railway Station at a distance of about
25 kms
Nearest Air Port Kempegowda International Airport Limited at about 35
Kms and 10 Km from HAL Airport.
Nearest Water body Kundalahalli lake is adjacent to the site on West
direction, Nellurahalli Lake at 1.4 KM (East),
Chinnappanahalli Lake at 1.5 KM (South), Munekolala
Lake at 1.8 KM (South), Varthur Lake at 1.25 KM and
Hoodi Lake at 1.5 KM (North)
National Highway No nearby highways in 10 km radius
Ecologically sensitive zones like Wildlife No Ecologically Sensitive Area is existing within 10 km
Sanctuaries, National Parks or radius.
biosphere
Archeological Monuments No Archeological Monuments within 10 km radius
Socio-economic factors No homestead displacement is proposed at the project
site
The meteorological data reflecting minimum, maximum temperature in 0C, relative humidity in %, rainfall in
mm/hr, wind speed in m/s, mixing height in m, cloud cover in tenths and atmospheric pressure in mb for the
year 2016 obtained from modeling studies carried out using U.S. EPA AERMOD dispersion model, 1996 –
2015 Lakes Environmental Software, Version 7.1.0 has been appended as table 3.1.
1. TEMPERATURE
The mean maximum temperature is observed at (38°C) in the month of April and the mean minimum
temperature at (17°C) is observed in the month of January.
In the summer season, the mean minimum temperature is observed during the month of March (23°C).
During the monsoon, the mean maximum temperature is observed to be 29°C in the month of July with the
mean minimum temperature at 19°C during August. By the end of September with the onset of post monsoon
season (October - November), day temperatures drop slightly with the mean maximum temperature at 30°C
in October and mean minimum temperature is observed at 17°C during November. The values are presented
in table 3.1.
2. RELATIVE HUMIDITY
Minimum and maximum values of relative humidity have been recorded. The minimum humidity is observed
to be at 43% in the month of March and the maximum is 79 % in the month of September. The mean minimum
values of humidity during summer, monsoon, post-monsoon and rainy seasons are 43%, 74%, 69% & 49%
during the months of March, June, October and February respectively. Similarly the maximum values are
56%, 75%, 62% & 69% in the months of May, August, October & January during the summer, monsoon, post
monsoon & winter seasons. The values are presented in table 3.1.
3. RAINFALL
The monsoon in this region usually occurs twice in a year i.e. from June to September and from October to
November. The maximum annual rate of precipitation over this region ranges between 6.3 to 215.01 mm/hr.
4. ATMOSPHERIC PRESSURE
The maximum and the minimum atmospheric pressures are recorded during all seasons. In the summer
season, the mean maximum and minimum pressure values are observed to be 1008 mb in the month of May
and 1007.9 mb in the month of June respectively. During monsoon season, the minimum pressure is 1008.3
mb (July) and maximum 1008.7 (August) mb. The minimum pressure during the post-monsoon season is
observed to be 1010.8 mb in November and maximum pressure is 1013.0 mb in the month of October. During
the winter season the minimum atmospheric pressure is 1013.6 mb in December and the maximum is 1015.1
mb in the month of January. The values are presented in table 3.1.
5. CLOUD COVER
The minimum cover measured in the unit of % is 9 and the maximum observed cloud cover is 59.
6. WIND
The data on wind patterns are pictorially represented by means of wind rose diagrams for the entire year as
figure 3.1.
❖ AIR QUALITY:
PM10 and PM2.5 have been estimated by gravimetric method. Modified West and Gaeke Method (IS: 5182
Part – II, 1969) has been adopted for estimation of SO 2. Jacobs – Hochheiser Method (IS: 5182 Part-VI,
1975) has been adopted for the estimation of NOx. N D I R S (Non-Dispersive Infra-Red Spectroscopic)
Method (IS: 5182 Part-X, 1999) has been adopted for the estimation of CO and Electro chem sensor method
has been adopted for the estimation of Ozone. Spectrophotometric method for ammonia, AAS (Atomic
Absorption Spectrophotometry) method for lead. Summary of the analytical techniques and their references
are appended in table 3.2A
❖ WATER QUALITY:
TABLE: 3.2 B: PROTOCOL FOR SURFACE WATER QUALITY MONITORING
The fluctuations in ambient air quality within the study area of the proposed project are expected to be
governed by the overall regional emissions and micro-meteorology of the study area.
Baseline data for ambient air quality was collected during the months of March to May 2016. The sampling
stations along with their distance and direction from the project site, ambient air quality monitoring stations,
wind rose diagram showing the direction of the blowing wind during the analysis period, ambient air quality
analysis data & National Ambient Air Quality Standards specified by MoEF are detailed subsequently.
To study the existing ambient air quality, monitoring was done by Bangalore Test House, Bangalore, NABL
Accredited lab for the project site & other locations.
The sampling stations along with their distance and direction from the project site is detailed in Table 3.3,
Ambient Air Quality monitoring stations are shown in Fig 3.2, ambient air quality analysis data is shown in
Table 3.4, National Ambient Air Quality Standards (NAAQS) adopted by CPCB is indicated in Table 3.5.
Table 3.5: Revised National Ambient Air Quality Standards – MoEF as per the notification dated 16th
November 2009 for Industrial, Residential & Rural areas
Note:
24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be complied with 98% of the
time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring.
Whenever and wherever monitoring results on two constitutive days of monitoring exceed the limits
specified above for the respective category, it shall be considered adequate reason to institute regular
or continuous monitoring and further investigation.
OBSERVATIONS:
It has been observed that the maximum concentration of SPM, SO2, NOx, Pb & O3 at all the locations are
within the limits specified by MoEF (as per the notification dated 16 th November 2009 for Industrial,
Residential & Rural areas). Marginally high values at Project Site and Pattandur Agrahara are due to the
construction activity at project site, frequent movement of vehicles on the main road close to the sampling
location.
Background noise levels were measured in 5 locations (Table 3.6), monitoring locations depicted in map (Fig
3.2) in human settlements within the study area. A sound level meter was used for measuring the noise level
at one-hour interval continuously for 24 hrs at 1.5 m above ground level, about 3 m from walls, buildings or
other sound reflecting sources.
The measurements were carried out in such a way that the monitoring locations were 1 m away from the
sources and 1 m away from the edge of the roads. The lowest and the highest noise levels are presented in
Table 3.7 and limits as per Environmental Protection Rules, 1986 for the project are presented in Table 3.8
as under.
Table 3.6: Noise level monitoring stations
Sl. Code Name of the Station Direction from Distance from
No. No. site site (km)
1 N 1 Project site - -
2 N 2 Pattandur Agrahara North 2.90
3 N 3 Nallurahalli East 2.1
4 N 4 Kundalahalli West 0.75
5 N 5 Tubarahalli South 1.75
OBSERVATIONS:
The baseline noise levels have been monitored at different locations as indicated in the table above.
Marginally high noise levels at Tubarahalli and Kundalahalli are due to the movement of vehicles.
Geographically the site is located at Latitude: 12°58” 03.45' N Longitude: 77°43” 29.24' E with 889 m above
MSL. Water bodies around the site are Kundalahalli lake is adjacent to the site on West direction, Nellurahalli
Lake at 1.4 KM (East), Chinnappanahalli Lake at 1.5 KM (South), Munekolala Lake at 1.8 KM (South), Varthur
Lake at 1.25 KM and Hoodi Lake at 1.5 KM (North). No nalas are located within or adjacent to the project
site. Required buffer is maintained from the boundary of the lake and the project is designed to comply to the
NGT norms, i.e., 75 mts buffer is left between the lake to nearest proposed building. The ground water in
the area occurs under water table conditions in the weathering mantle of the granite gneisses and in the
joints, cracks and crevices of the basement rock. Ground water is derived mainly from precipitates. Smaller
amounts are derived from infiltration of water from the tanks and the water used for irrigation. Most of the
rainwater is lost through evaporation and run off, only a small percentage reaches the groundwater reservoir.
In order to assess the existing water quality, the water samples were collected from five different locations
within the study area (Fig. 3.2) and analyzed as per the procedure specified in standard methods for
examination of water and wastewater published by American Public Health Association and Bureau of Indian
Standards (APHA/BIS). Name of locations, orientation with respect to the project site are listed in the Table
3.9. The analytical data for surface water quality has been tabulated in Table 3.10, 3.11 & ground water
quality at all locations has been depicted in Table 3.12.
b) Surface Water:
Sl. Code Name of the Station Direction Distance
No. No. from site From site (km)
1 SW 1 Kundalahalli lake Adjacent West
2 SW2 Nallurahalli lake 1.4 East
Note: It is observed during the study period that there is some sewage entry in to the lake on the western
and Northern side of the lake.
The results of the analysis of Nallurahalli lake water sample is appended as Table 3.11.
Class A Drinking water source without conventional treatment but after disinfection
Class B Outdoor bathing (organized)
Class C Drinking water source with conventional treatment followed by disinfection
Class D Propagation of wildlife, fisheries
Class E Irrigation, industrial cooling, controlled waste disposal
Class below E Not meeting A, B, C, D & E criteria
14 Manganese, Mn, mg/L BDL BDL BDL BDL BDL Max. 0.1 Max. 0.3
15 Nitrates, as NO3, mg/L <0.1 <0.1 5.0 <0.1 1.0 Max. 45 No relaxation
16 Fluorides, as F, mg/L <0.1 <0.1 <0.1 <0.1 0.6 Max. 1.0 Max. 1.5
17 Phenolic compounds, as Absent Absent Absent Absent Absent Max. 0.001 Max. 0.002
C6H5OH, mg/L
18 Mercury, as Hg, mg/L BDL BDL BDL BDL BDL Max. 0.001 No relaxation
19 Cadmium, as Cd, mg/L BDL BDL BDL BDL BDL Max. 0.003 No relaxation
20 Selenium, as Se, mg/L BDL BDL BDL BDL BDL Max. 0.01 No relaxation
21 Arsenic, as As, mg/L BDL BDL BDL BDL BDL Max. 0.01 Max. 0.05
22 Cyanide, as CN, mg/L Nil Nil Nil Nil Nil Max. 0.05 No relaxation
23 Lead, as Pb, mg/L BDL BDL BDL BDL BDL Max. 0.01 No relaxation
24 Zinc, as Zn, mg/L <0.1 <0.1 <0.1 <0.1 <0.1 Max. 5 Max. 15
25 Anionic detergents, as MBAS, <0.1 <0.1 <0.1 <0.1 <0.1 Max. 0.20 Max. 1
mg/L
26 Total Chromium, as Cr,mg/L BDL BDL BDL BDL BDL Max. 0.05 No relaxation
27 Residual free chlorine, mg/L <0.1 <1.0 <1.0 <1.0 <0.1 Min. 0.20 Min. 1.0
28 Alkalinity, as CaCO3, mg/L 31 9.0 182.0 8.0 39.0 Max. 200 Max. 600
29 Aluminum, as Al, mg/L BDL BDL BDL BDL BDL Max. 0.03 Max. 0.2
30 Boron, as B, mg/L <0.1 <0.1 <0.4 <0.1 <0.1 Max. 0.50 Max. 1.0
OBSERVATIONS:
The physicochemical quality of the ground water sources at and around the project site has been analyzed,
which indicates that few parameters like total hardness, alkalinity, calcium, total dissolved solids are above
the Acceptable Limits as per IS:10500-2012. However are within Maximum Permissible Limits in the Absence
of Alternate Source as per IS: 10500-2012. The higher values of the said parameters are attributed to
geological conditions of the area. The source of water for the project is from BWSSB Sources.
The results of the analysis show that the nature of the soil is neutral.
3.3 ECOLOGY:
Natural flora and fauna are important features of the environment. They are organized into natural
communities with mutual dependencies among their members and show various responses and sensitivities
to physical innocence. The integrated ecological thinking and planning process is an urgent need in the
context of natural environment's deterioration which has a direct bearing on socio-economic development.
Ecology of the study area includes the flora and fauna studies within the study zone. The investigation
included field observations, discussions with local people, forest officials etc.
3.3.2 FAUNA
The fauna found in the region does not show much diversity, as there is no suitable habitat for the occurrence
of ecologically important fauna. Fauna observed in the region include domestic animals, reptiles and birds.
The composition of fauna in the study area is presented in the table below.
S No. Zoological Name Common Name
Mammals
1 Bos indicus Cow
2 Babulus indicus Buffalo
3 Lepus nigrocollis Indian Hare
4 Pteropus gigantus Bats
5 Equus cabulus Donkey
6 Funambulus ponnanti Squirrel
Avian
7 Pavo cristatus Pea fouls
8 Corvus splendens Common crow
9 Passer domesticus House sparrow
10 Psittacula cupatria Indian parakite
11 Acrodopthesus tristis Indian myna
12 Conturnix coturnix Common quails
Reptiles & Amphibians
13 Rana tigrina Frog
14 Bufo melanosticus Toad
15 Hemidoctylus brookie Common lizard
16 Ptyas mucosus Rat snake
17 Calotes versicolor Garden lizard
The growth of industrial sectors and infrastructure development in and around the agricultural area i.e.,
villages and semi-urban settings and towns is bound to create certain socio-economic impacts on the local
populace. The impacts may be either positive or negative depending on the nature of development. To assess
such impact it is necessary to know the existing socio-economic order of the study area, which will be helpful
in improving the overall quality of life.
The data has been collected for Ward No. 85 of Bruhat Bengaluru Mahanagara Palike Limits of
Mahadevapura Constituency. The ward consists of Munnekolala, Chinnappanahalli, Kundalahalli,
Doddanekkundi, Sonnenahalli and Kundalahalli Village. The population details the year 2011 of the ward is
presented as Table 3.16 below (Source:
http://bbmp.gov.in/documents/10180/460906/BBMPR_ward_master_BBMP+Restructuring+03-08-
2015.pdf/89caf820-58a7-4d73-a785-7082f250d7d7)
The land around the project site indicates a mixed land use pattern with Software Tech Parks, Commercial
Establishments, Residential Apartments, Layouts etc., The project site is located at a distance of about 25
km from Bangalore City Railway Station in the eastern direction.
❖ Transportation: The project site is located off ITPL main road (Kundalahalli road)
❖ Agricultural land: No agricultural lands / agricultural activity is carried out in the surrounding areas of the
site. The site is surrounded by areas like Kundalahalli, Nallurahalli, Whitefield, Tubarahalli, Brookefields,
EPIP and EOIZ Areas, etc.,
❖ Water bodies: Kundalahalli lake is adjacent to the site on West direction, Nellurahalli Lake at 1.4 KM
(East), Chinnappanahalli Lake at 1.5 KM (South), Munekolala Lake at 1.8 KM (South), Varthur Lake at 1.25
KM, Tubarahalli lake at 1.0 KM (South) and Hoodi Lake at 1.5 KM (North)
The proposed project site is in the North Eastern part of Bangalore. The site is located at a Latitude: 12°58”
03.45' N Longitude: 77°43” 29.24' E with 889 m above MSL. The total plot area is 2,02,948.16 sq m (50.15
Acres) and is located at a distance of about 25 km from Bangalore city railway station. The general
topographical features of the area reveal that the proposed project site and its surroundings is generally a
plain land.
FIG 3.6: TOPO MAP COVERING 2 KM DISTANCE FROM THE PROJECT SITE
FIG 3.7: GOOGLE MAP COVERING 1 KM AERIAL DISTANCE FROM THE PROJECT SITE
FIG 3.8: GOOGLE MAP COVERING 5 KM AERIAL DISTANCE FROM THE PROJECT SITE
FIG 3.9: GOOGLE MAP COVERING 10 KM AERIAL DISTANCE FROM THE PROJECT SITE
CHAPTER 4
ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
4.1 Details of Investigated Environmental Impacts due to Project Location, Possible Accidents,
Project Design, Project Construction, Regular Operations, Final Decommissioning or Rehabilitation
of Completed Project
4.1.1 Environmental impacts due to project location, possible accidents, project design
PROJECT LOCATION:
POSSIBLE ACCIDENTS:
The proposed project is Modification and Expansion of Software Technology Park. All precautionary
measures are taken during the construction activities. All civil engineering practices as regard to safety of
workers is being followed in the on going project and the same procedure will be followed for the proposed
expansion. Therefore environmental impacts due to possible accidents are not anticipated. The building
structure is designed duly complying to safety aspects viz., Structural Safety, Fire Hazard, Location of utilities
etc., All related regulatory compliances and clearances will be obtained and complied.
PROJECT DESIGN
The project is designed with utmost consideration to the environment.
a) Green-belt/landscape development is earmarked in the project.
b) Indigenous / native trees species of different species are proposed to be planted.
c) Environmental Infrastructure facilities like Sewage Treatment Plant for treating the wastewater from the
project. Organic Waste Converter for treating the Organic Waste, the product will be used as manure.
d) Rain water harvesting and Ground water recharging is proposed in the project to enhance ground water
potential in the area.
e) Use of alternative source of energy like solar lighting, solar hot water generation will assist in reducing
load on conventional energy sources.
f) Structural safety is ensured following NBC guidelines.
The construction phase impacts are mostly short term, restricted to the plot area and not envisaged on the
larger scale. In the occupancy phase the environmental impacts are due to continuous operation of the
project, hence, the emphasis in the Environment Management Plan (EMP) is to minimize such impacts. The
following mitigation measures are recommended in order to synchronize the economic development of the
project area with the environmental protection of the region.
❖ Procurement and transport of construction materials such as sand, cement, etc., to the construction site;
❖ Operation of construction vehicles and equipments.
The following mitigation measures are proposed to control dust
❖ GI sheets are provided to a height of 5 m all around the project site to control dust;
❖ Water is sprinkled at regular intervals;
❖ SO2 emissions from diesel generators is expected to be low because of usage of low sulfur content
diesel;
❖ Use of efficient machinery and schedule maintenance of the construction vehicles and equipments.
These activities are limited to construction period and are only temporary phenomena. Also, the project site
is surrounded by open areas; hence no major adverse impacts are anticipated. Nonetheless the following
mitigation measures are proposed
• It is proposed to carry out all the noise generating activities during day time;
• Proper planning of the movement of vehicular traffic;
• Proper and periodic upkeep of construction equipments;
• Providing noise reduction gadgets, providing PPE to construction workers to prevent its effect on them.
2. Grit and sediment removal facilities with sediment traps are provided in the storm water drains to prevent
run-off contamination.
3. Top soil is stacked and will be reused for landscape development.
4. The spillage of oil from the machinery or cement residual from concrete mixer plants might contaminate
the soil if not properly collected and disposed off. Collection trays are provided to collect oil dripping from
construction machineries.
Staking of construction materials shall be confined to the project site only and also suitable enclosures shall
be provided, hence no impacts on surrounding land is envisaged. About 1000 cum of construction debris
generated will be used as preparatory for road formation within the project site. Disposal of construction
waste is likely to cause unaesthetic view, unhygienic conditions, choking of nearby drains etc., such impacts
are short term. The severity of such impact will depend upon the magnitude and type of construction waste.
The most susceptible locations for contamination of water during construction are
❖ Waterlogged areas;
❖ Surface and ground water resources close to construction material storage yard, concrete mixer plants
and maintenance sites of construction vehicles;
❖ Surface water bodies close to labor camps.
All the construction activities are strictly confined to the project site. The following measures are undertaken
to prevent water quality degradation during construction phase
❖ Good construction practices are strictly implemented and care is taken to see that no water logging takes
place at the project site;
❖ Remedial measures are immediately undertaken to remediate any accidental spills or other unforeseen
incidents if any;
❖ The domestic sewage from the construction workers camp is treated in existing Sewage Treatment Plant.
❖ The impacts if any are short term and low in magnitude and confined to the construction site and to the
construction period only.
❖ Water requirement of laborers is met by BWSSB sources and also treated water from the occupancy
phase of the project will be used for toilet flushing, landscape development and AC cooling tower
makeup.
The project is modification and expansion of Software Technology Park project and all the construction
related activity will be confined to project site area. Hence no health related impacts are envisaged in the
surroundings during the construction phase.
At the project site about 500 people are engaged in the construction activities. Direct exposure of these
people to dust is likely to cause health related impacts. This is minimized by providing suitable respiratory
Personal Protective Equipments (PPE) such as nose mask with filters etc.,
The construction activities will benefit the local population as it creates employment opportunities.
The proponents have given preference to local people with both direct and indirect employment.
The social impacts during the construction stage could result due to influx of migrant workers and associated
induced development. This will ensure a rise in the consumption of consumer goods in the local area, which
will tend to boost up the local economy. All the activities related to construction work are confined to the
project site only; hence no adverse social impacts are envisaged in the surrounding areas due to the project.
4.7.3 WATER CONSUMPTION AND WASTEWATER TREATMENT AND DISPOSAL DETAILS, WATER
HARVESTING AND RECHARGE:
The water required for the project will be drawn from BWSSB Sources. The wastewater generated from the
project will be treated in Sewage Treatment plant and the treated sewage will be recycled for toilet flushing,
reused for landscape development and AC Cooling tower makeup.
It is proposed to provide shallow recharge pits along the inner periphery of the boundary wall of size 5’ dia x
20’ depth. These recharging pits will be filled with graded media comprising of boulder at bottom and with
coarse aggregates to facilitate percolation of harvested rain water to recharge groundwater table. The
recharge pits are interconnected in such a way that the rain from the first recharge pit is led to the next pit
and so on. The excess rainwater shall be drained off to the storm water drain.
The domestic solid waste generated from the project is being treated in an organic converter and the
inorganic solid waste will be sent for recycling. Additional converters are proposed for the blocks which will
be constructed.
Since the entire project influenced area will be developed as per the Zoning regulations, to cater the demand
of the living population hence no induced development is foreseen due to the proposed project.
Project site is vacant land and no trees are proposed to be felled in the project and no major threat to the
flora & fauna is not envisaged as the project is developed in area located in Commercial Zone of
Comprehensive Development Plan (CDP).
The project is located Kundalahalli Main Road. The traffic studies conducted on the approach roads reveal
that there will not be major impact by addition of traffic / vehicle from the project on the existing traffic scenario.
The occupancy of the project provides value addition to the existing infrastructure facilities such as public
transport, water supply, telecommunications etc.,
4.8.2 EMPLOYMENT:
The occupancy of project and other allied facilities, will improve the employment opportunities. Both direct
and indirect employment is envisaged. The employment will have positive impact on the local economy
thereby increasing the quality of life.
4.8.3 ENVIRONMENT:
▪ An area of 78,643.55 sq m is left for landscape development.
▪ Water conservation measures adopted in the project which reduce burden on water resources.
▪ Use of alternative source of energy like solar lighting, solar hot water generation will assist in reducing
load on conventional energy sources.
▪ Indigenous / native trees of different species are planted / proposed to be planted.
▪ Environmental Infrastructure facilities like Sewage Treatment Plant for treating the wastewater from the
project. Organic Waste Converter for treating the Organic Waste, the product and it will be used as
manure.
▪ Rain water harvesting and Ground water recharging is done / proposed in the project to enhance ground
water potential in the project.
CHAPTER 5
ANALYSIS OF ALTERNATIVES (TECHNOLOGY AND SITE)
The proposed project is Modification and Expansion of Software Technology Park project. Project is proposed
to be developed in Commercial Zone as per the Comprehensive Development Plan (CDP) of Bangalore
Development Authority (BDA). The project is proposed to cater the needs (Office establishment and housing)
of the surrounding areas and hence no alternate site is examined.
b) Corridors – 50 lux
c) Rooms – 200Lux
d) Elec. Room 200 Lux
The construction debris of 1000 cum are expected to be generated from the construction activities and will
be used as preparatory for internal roads, fire drive way, pavements works etc., within the project site and
excess if any will be disposed in designated disposal sites as per the Construction and Demolition Waste
Management Rules, 2016.
Thermal insulation for wall with fenestration and roof pergolas are considered as passive architectural design
building orienting with east to west to meet the ECBC guidelines. (Balconies, Projections, Recessed windows
with orientations etc.)
5.2 Building Orientation to take advantage of solar access, shading & natural lighting:
Passive solar architectural features are considered while designing the buildings in respect of orientation of
building less exposed surface area to east to west directions.
CHAPTER 6
ENVIRONMENTAL MONITORING PROGRAMME
Detailed budgetary provisions for monitoring program are detailed in the following table.
The responsibility of EMP implementation lies with the project promoter for a period of 3 years. Once the
residents' society is established, the EMP responsibility will be properly handed over with clearly defined
procedures and guidelines.
CHAPTER 7
ADDITIONAL STUDIES
Risk analysis follows hazard analysis (Risk = Hazard x Probability of occurrence). It involves identification
and assessment of risks to the personnel and neighboring populations. This requires a thorough knowledge
of failure probability, credible accident scenario, vulnerability of population etc., much of this information is
difficult to procure. Consequently, the risk analysis is confined to maximum credible accident studies. The
subsequent sections shall address the identification of various hazards and risks in the operations, which will
give a broad identification of risks involved.
b. Occupancy phase:
Precautions for risk and disaster management plan:
• Once the likelihood of the disaster is suspected, preventive actions should be undertaken by the project
in-charge.
• Conditional maintenance of equipments, materials and expertise for use during emergency.
• The electrical systems should be provided with automatic circuit breakers activated by over-current.
• Fire extinguishers will be provided at pre-notified locations inside the building.
• Proper escape routes will be planned and displayed in the public domain.
• Selected representatives will be given proper training to guide other inhabitants during fire accidents.
• Periodic awareness program will be conducted for the occupants on their roles during emergency
situations.
Important telephone numbers like police authorities, fire department and hospitals etc. of use during
emergency situations should be made available.
notification, warning procedures and co-ordination among various relief authorities. These are discussed in
following sections.
The building materials should be of appropriate fire resistance standard. Wood shall not be used for any
purpose, excluding artificial wood products, which are flame resistant. The materials which have zero surface
burning characteristics need to be used. The electrical systems shall be provided with automatic circuit
breakers activated by the rise of current and by over-current. The design will include provision for the
following:
All aspects of fire prevention and control will be dealt in close collaboration with the city firefighting authority.
Smoke control will be achieved by the following means
Down stand bulkheads of a minimum depth of 600 mm to provide smoke containment. These will be provided
around openings for escalators, lifts and stairs in underground stations. Adequate firefighting requirement
have been taken into account while designing the distribution system for the area. The LPG supply to the
apartment will be individual and central LPG supply is not proposed.
CHAPTER 8
PROJECT BENEFITS
8.1.1 Employment:
The operation of project and other allied facilities, will improve the employment opportunities. Both direct and
indirect employment is envisaged. The employment will have positive impact on the local economy thereby
increasing the quality of life. The project activities are likely to generate employment opportunities both during
construction (About 500 workers) and the occupancy phase (About 250 workers). The occupational profile of
nearby settlements is such that the locals can be good source of labour during both phases. During the
construction phase, various manual-laboring activities can engulf residents of nearby settlements, like the
labour camp. People from these areas, will also have opportunities during the occupancy of the project.
These include ancillary jobs like housekeeping, cleaners, gardeners, helpers, security staff, etc., the project
will increase the economic activities around the area, creating avenues for direct/indirect employment in the
post project period. There would be a wider economic impact in terms of generating opportunities for
secondary occupation around the project.
Thus the impact on employment due to construction and occupancy of the project can be considered as
“significantly positive”.
8.1.2 Environment:
➢ Total area of 78,643.55 sqm is reserved exclusively for green-belt/landscape development.
➢ Indigenous / native trees species of different species are planted / proposed to be planted.
Environmental Infrastructure facilities like Sewage Treatment Plant for treating the wastewater from the
project. Organic Waste Converter for treating the Organic Waste, the product will be used as manure.
➢ Rain water harvesting and Ground water recharging is done / proposed in the project to enhance ground
water potential. Rain water harvesting, recharging proposed will help in improving water table in the area.
➢ Water conservation measures adopted in the project will reduce burden on water resources.
➢ Use of alternative source of energy like solar lighting, solar hot water generation will assist in reducing
load on conventional energy sources.
The social impacts during the construction stage could result due to influx of migrant workers and associated
induced development. This will ensure a rise in the consumption of consumer goods in the local area, which
will tend to boost up the local economy. All the activities related to construction work are be confined to the
project site only; hence no adverse social impacts are envisaged in the surrounding area due to the project.
CHAPTER 9
ENVIRONMENTAL COST BENEFIT ANALYSIS
9.1 INTRODUCTION:
Cost–benefit analysis (CBA), sometimes called Benefit–Cost Analysis (BCA), is a systematic process for
calculating and comparing benefits and costs of a project for two purposes
• to determine if it is a sound investment (justification/feasibility)
• to see how it compares with alternate projects (ranking/priority assignment)
It involves comparing the total expected cost of each option against the total expected benefits, to see
whether the benefits outweigh the costs, and by how much.
In CBA, benefits and costs are expressed in money terms, and are adjusted for the time value of money, so
that all flows of benefits and flows of project costs over time (which tend to occur at different points in time)
are expressed on a common basis in terms of their "present value."
ENVIRONMENTAL COST-BENEFIT ANALYSIS, refers to the economic appraisal of policies and projects
that have the deliberate aim of improving the provision of environmental services or actions that might affect
(sometimes adversely) the environment as an indirect consequence.
CHAPTER 10
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
10.1 INTRODUCTION
The Environmental Management Plan (EMP) is aimed at mitigating the possible adverse impacts of a project
and ensuring the existing environmental quality. The EMP converses all aspects of planning, construction
and occupancy of the project relevant to environment. It is essential to implement the EMP right from the
planning stage continuing throughout the construction and occupancy stage. Therefore the main purpose of
the Environmental Management Plan (EMP) is to identify the project specific activities that would have to be
considered for significant adverse impacts and the mitigation measures required.
The construction phase impacts are mostly short term, restricted to the plot area and not envisaged on a
larger scale. In the occupancy phase the environmental impacts are due to continuous operation of the
project, hence, the emphasis in the Environment Management Plan (EMP) is to minimize such impacts. The
following mitigation measures are recommended in order to synchronize the economic development of the
project area with the environmental protection of the region.
During construction phase, the activities which need to be monitored and managed from the point of pollution
are detailed in the subsequent sections.
Noise generation:
• Most optimum no. of operation. To reduce noise
Caused due to • Less noise generating equipments are used. levels, only
excavators and • The earth moving equipment are periodically checked and equipments
bulldozers. maintained for noise levels. provided with
• The workers are provided with adequate Personnel Protective noise control
Equipment (PPE) such as ear plugs to reduce impact of high devices will be
noise levels. used.
• All construction activities are carried out during the day time.
Dust generation:• The site cleared is periodically watered to reduce emission of Water supply for
Leveling dust particles. labor camps is
operations results
• Barricades like metal sheets are provided all-round the premises augmented from
in the emission of to avoid fugitive dust emissions into the neighboring area apart BWSSB sources.
dust. from water sprinkling.
• The workers are provided with Personal Protective Equipment
(PPE) such as nose masks and goggles to reduce impact on
health.
• Construction materials are covered with tarpaulin sheet to prevent them from
being air borne.
• The vehicle speed is regulated.
• Workers transporting materials are provided with PPE such as nose mask to
reduce impact of air borne dust on their health
Vehicular • Periodic emission check for vehicles is ensured.
emissions • Clean fuel is being used for vehicles.
expansion proposal. 50 Sheds and 30 Toilets with bathrooms are provided for construction workers and
additional sheds and facilities will be provided for workers once construction of new blocks are started. The
temporary structures are made during the construction phase such as workers sheds; storage yards for
construction materials will be dismantled and re-used for future developmental activities. The sewage
generated from the labor camp during construction phase is treated in STP which are in operation in existing
buildings.
Exhaust from DG sets will be emitted from stacks of adequate heights for dispersion of gaseous pollutants.
The following table presents the EMP for air quality management during occupancy phase.
The sewage generated from the project will be treated in the STP. The treatment scheme for domestic
sewage generated from project is detailed in Chapter 2. Treated water will be reused for flushing, gardening
etc., The following table presents the EMP for water quality.
High noise generating units such as DG sets provided with acoustic enclosures. Green-belt at the project
boundary will further act as noise barrier and help in attenuation of noise. The typical noise levels from these
sources are listed in the following table:
The solid wastes generated during occupancy phase can be categorized as under:
1. Domestic/Residential waste
• Wet garbage: food waste, lawn mowing wastes etc.
• Dry garbage: paper, plastic, bottles, etc.
2. Sludge from Sewage Treatment Plant (STP)
The solid waste generated from the project is estimated to be about 7,484 Kg/day out of which 4,490 kgs/day
(60%) is biodegradable 2,994 kgs/day (40%) is non-biodegradable/recyclable wastes. The sludge generated
from the STP will be used as manure for landscape development after taking it through the filter press.
The various mitigation measures to be adopted during collection and disposal of wastes are as follows:
❖ It is preferable that the container and bins used for collection of waste should be of closed type so that
the waste is not exposed and thus the possibility of spreading of disease through flies and mosquitoes
is minimized.
❖ Adequate number of collection bins, separate for biodegradable and non-biodegradable waste shall be
provided as per The Municipal Solid Waste Rules. Waste from the bins shall be collected separately on
daily basis.
❖ Collection system should be properly supervised so that quick and regular removal of waste from the
dustbin is practiced.
❖ Door to door collection of the solid wastes is being done. The biodegradable wastes is treated in organic
converter and the non-biodegradable wastes-such as plastic materials, glass & metal wastes are handed
over to the waste recyclers.
❖ Litter waste comprising of fallen leaves and other vegetative material will be collected at the secured
location such that it does not hinder the daily activity schedule or be washed away by the surface runoff
causing choking of drains, etc., and such waste will be composted and used as organic manure.
In order to mitigate adverse impacts on water environment due to the surface runoff, wastewater etc.,
provisions for adequate infrastructure facilities such as suitable drainage system, wastewater collection and
conveyance including treatment and reuse has been proposed duly keeping in mind the adjacent Kundalahalli
lake. A buffer of more than 75 m between the lake and the nearest building is maintained and the area
between will be developed as green belt.
As the project location is blessed with fairly good rainfall, it is planned to collect the storm water at different
gradients of the location. There will be rainfall runoff from building roof-tops, roads and pavements and
greenbelt area. Necessary provision will be made to collect rainfall runoff from the rooftop during rainy
season. Rain harvesting pits/recharge pits at every 30 m (center to center) have been envisaged.
The landscape of project site has been planned to provide a clean, healthy and beautiful green environment
for the people. Landscaping has been designed to achieve a blend between modern building and various
species of plants, shrubs, to create a clean, healthy and aesthetic environment that provides a visual retreat
and relaxation to the occupants of these buildings. List of tree species proposed to be planted in the project
is detailed in Chapter 2.
At the project site on an average of 500 people will be engaged, who face direct exposure to dust and noise
generated from the construction activity. This is likely to cause health related affects such as asthma,
bronchitis etc., and hearing impairments respectively.
To minimize these anticipated impacts, suitable actions as listed below will be undertaken
• Use of water sprinklers to prevent dust from being air borne.
• Providing suitable Personal Protective Equipments (PPE) like mouth mask with filters, noise mask, helmets
etc.,
Due to operation of the proposed project, there will be enhancement in public health and safety.
• Regular visit of resident medical officer to take care of the first-aid and primary medication in case of
emergency for occupants and laborers.
• First-aid kit with primary medicines will always be available in the medical centre.
• Display of action plan and preparedness measures during emergency situations.
The responsibility of EMP implementation lies with the project promoter. The responsibility of promoter during
the construction phase of the project is for a period of 3 years. Once the resident’s association / society is
established, the EMP responsibility will be properly handed over with clearly defined procedures and
guidelines.
The financial allocation for EMP during construction phase and occupancy phase of the project is detailed in
Table 10.8 & 10.9 respectively.
Table 10.8: FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS
(CONSTRUCTION ASPECTS)
Sl. Description Financial Provision in
No. Lakhs
Capital Recurring
Cost Cost
1 Environmental Management Plan during construction phase:
Using tertiary treated water for
• Sprinkling to control fugitive dusts
• Construction & curing purposes 2.0 1.0
• Flushing and Package STP 2.0 1.0
10.0 1.0
2 Sewage Treatment Plants for Operation Phase 150.0 -
3 Potable water requirement for the construction workers 2.0 1.0
4 Maintenance of Vehicles and equipments - 1.0
5 Top Soil Conservation 2.0 -
6 Temporary Storm Water Drains 10.0 1.0
7 Personal protection safety gadgets and health care. 2.0 1.0
8 First aid facilities for workers 2.0 1.0
9 Plantation of Saplings 10.0 -
10 Environmental Monitoring Plan (Air, Noise, Water and Solid Waste). - 10
11 TOTAL 192 9.0
Contingency at 10 % 19.2 0.9
TOTAL 211.2 9.9
Table 10.9: FINANCIAL ALLOCATION AND BUDGETARY PROVISION FOR EMP ASPECTS
(OCCUPANCY PHASE)
Sl. Description Financial Provision in
No. Lakh
Capital Recurring
Cost Cost
1 Operation of Sewage Treatment Plant - 6.0
2 Reclaimed Sewage Distribution Network 20.0 2.0
3 Rain water harvesting tanks and its facilities 20.0 3.0
4 Ground water recharging pits & its management 15.0 2.0
5 DG sets acoustic & Maintenance 20.0 3.0
6 Landscaping 50.0 2.0
Apart from the mitigation measures described in above sections, table 10.11 describes the generic measures that need to be undertaken during project
construction and occupancy stage.
Table 10.11: Summary of the potential impacts and mitigation measures during construction and occupancy phases
Sl. Potential Action Parameters for monitoring Timing
No. impact
I. CONSTRUCTION PHASE
1 Air emissions All equipments are operated within specified design parameters. Random checks of equipment logs / Construction
manuals activities
Vehicle trips is minimized to the extent possible. Vehicle logs Site clearance &
construction
Any dry, dusty materials stored in sealed container or prevented Absence of stockpiles or open containers Construction
from blowing. of dusty materials activities
Compaction of soil during various construction activities. Construction logs As per PCC
(Project Civil
Contractor)
requirement.
Ambient air quality within the premises of the project is The ambient air quality will conform to the -
monitored. standards for SPM, SO2 and NOX.
2 Noise List of all noise generating machinery onsite is prepared. Equipment logs, noise reading During
Equipments are maintained in good order. construction phase
Night working is minimized. Working hour records Construction
activities
Generation of vehicular noise. Maintenance records of vehicles Construction
Good working practices is implement (equipment selection and Site working practices records, noise During
siting) to minimize noise and also reduce its impacts on human reading construction phase
health (ear muffs, safe distances, enclosure).
No machinery shall be running when not required.
Acoustic mufflers / enclosures are provided in large engines. Mufflers / enclosures in place Prior to use of
equipment
Noise is monitored in ambient air within the plant premises. Noise reading As per PCC
requirement or
The noise level do not exceed the permissible limit both during quarterly
day and night times. whichever is lesser
All equipment are operated within specified design parameters Random checks of equipment logs Construction
/manuals phase
Vehicle trips is minimized to extent possible. Vehicle logs
3 Wastewater No untreated wastewater discharge to be made to surface water, The wastewater from labor camps is Construction
discharge groundwater or soil. treated in existing STP. phase
The discharge point is selected properly and sampling and Discharge norms for wastewater as per During
analysis is undertaken prior to discharge. standards is followed by project proponent. construction phase
Wastewater generated is treated in package STP to ensure that The wastewater generated is treated in
the soil and groundwater resources are protected. Package STP
4 Soil erosion Minimize ar45 Site boundaries not extended / breached Construction
ea extent of site clearance, by staying within the defined as per plan document. phase
boundaries.
Protect topsoil stockpile where possible at edge of site. Effective cover in place Construction
phase
5 Drainage and Ensure drainage system and specific design measures are Visual inspection of drainage and records During
effluent working effectively. thereof. construction phase
management The design to incorporate existing drainage pattern and avoid
disturbing the same.
6 Waste Implement waste management plan that identifies and Comprehensive Waste Management Plan Prior to site
management characterizes every type of waste generated, associated with in place and available for inspection on- clearance
construction activities and which identifies the procedure for site. Compliance with MSW Rules
collection, handling & disposal of each waste.
7 Non-routine Plan is drawn up, considering likely emergencies and steps Mock drills and records of the same. During
events and required to prevent / limit consequences. construction phase
accidental
releases
8 Environmental The Environmental Management Cell/Unit is set up to ensure A formal letter from the management During
Management implementation and monitoring of environmental safeguards. indicating formation of Environment construction phase
Plan Management Cell.
II. OCCUPANCY PHASE
9 Air emissions Stack emissions from DG set to be optimized, monitored. The ambient air quality shall conform to the During occupancy
standards of Revised NAAQS, 2009. phase
Ambient air quality within the premises of the proposed unit to be The ambient air quality will conform to the During occupancy
monitored. standards for SPM, SO2 and NOx. phase
Exhaust from vehicles to be minimized by use of fuel efficient Vehicle logs to be maintained.
vehicles and well maintained vehicles having PUC certificate.
Vehicle trips to be minimized to the extent possible Vehicle logs During occupancy
10 Noise Noise generated from operation of DG sets to be optimized and Provide acoustic enclosures for DG sets phase
monitored.
DG sets to generate less than 75 dB (A) Leq at 1.0 m from the
source.
DG sets are to be provided at the Stilt floors with acoustic
enclosures with height of chimney as specified by KSPCB.
Generation of vehicular noise Maintain records of vehicles
11 Wastewater No untreated discharge to be made to surface water, The wastewater from the project will be During occupancy
discharge groundwater or soil. treated in a Sewage Treatment Plant. phase
12 Drainage and Ensure drainage system and specific design measures are Visual inspection of drainage and records During occupancy
effluent working effectively. thereof. phase
management Design to incorporate existing drainage pattern and avoid
disturbing the same.
Wastewater to be treated in STP and the treated sewage to be
reused for flushing, landscaping etc.,
The project surrounding areas will be protected and measures The following measures are undertaken During occupancy
for protection to be undertaken. ➢ The storm water drains will be phase
provided with silt traps.
➢ The wastewater generated from the
proposed development will be completely
recycled/re-used within the project
premises.
➢ The solid waste is proposed to be
treated in an organic converter.
13 Energy usage Energy usage for AC & other activities to be minimized. Conduct Findings of energy audit report During occupancy
annual energy audit for the buildings. phase
14 Emergency Fire protection and safety measures will be followed to take care Mock drill records, on site emergency plan, During occupancy
preparedness of fire and explosion hazards, to be assessed and steps taken evacuation plan. phase
(firefighting) for their prevention.
15 Environment The Environment Management Cell / Unit to be set up to ensure A formal letter from the management During occupancy
Management implementation and monitoring of environmental safeguards indicating formation of Environment phase
Cell / Unit Management Cell.
This policy will be applied continually to enhance these standards in all of our operations from initial planning
& design stage through construction, final turnover & start-up & continuous operations.
All the management, supervisors & employees along with our direct contractors / sub-contractors, consultants
& their employees are charged with the responsibility of providing & maintain the highest degree of health &
safety performance & the protection of our environment as well as the safety of others affected by our work.
It is the commitment to excellence that motivates M/s. Shyamaraju & Co (India) Pvt. Ltd., to be diligent in
the placement of supervisors & the selection of contractors & suppliers. Through our established
programmed, as well as relevant training & open communication, we nurture the employees desire to excel
in the areas of environment, Health & Safety performance of the project work.
While complying with the Government Environmental Health & Safety regulatory requirements we will also
meet or exceed recognized standards as an integral part of policy.
Administrative order of the company to deal with the environmental issues is as under
CHAPTER 11
SUMMARY & CONCLUSION
The building structural aspects, eco-friendly features of the project, electrical consumption and the savings
achieved due to the usage of unconventional sources of energy are detailed. The meteorological data and
baseline environmental & ecological features have been evaluated to understand the environmental setting
of the project site.
Traffic studies and its survey have been conducted to ascertain the pattern of traffic along the approach roads
to the project site. The percentage increase in the traffic due to the proposed project reveals that the net
increase in traffic is marginal when compared with the overall traffic.
Based on the above studies an Environmental Impact and mitigation plan has been prepared to ascertain
the possible impacts of the project on the environmental parameters like air, water, land, biological and socio-
economic environment. An impact matrix has also been prepared based on the observations of the impacts
on the environment.
An Environmental Management Plan has been prepared covering the environmental aspect and the
management plan required to be adopted by the management not only during the course of setting up of the
project but also during its occupancy phase.
▪ Mitigation measures are undertaken to prevent adverse impacts on the surrounding environment like air,
water, land and biological.
▪ There shall be economic growth and development at the local and regional level.
To put it in a nut shell the management of M/s. Shyamaraju & Co (India) Pvt. Ltd., strongly believes in the
concept of sustainable development and understands the impacts of the project on the environment from the
Environmental Impact Assessment studies. It is committed to construct and establish the project without
giving room for any adverse impacts on the environment and also lays emphasis on the implementation of
the recommendations of the Environmental Management Plan in true spirits.
CHAPTER 12
DISCLOSURE OF CONSULTANTS ENGAGED
12.1 THE NAMES OF THE CONSULTANTS ENGAGED WITH THEIR BRIEF RESUME & NATURE OF
CONSULTANCY RENDERED
Address: M/s. SAMRAKSHAN,
F – 4, First Floor,
Swastik Manandi Arcade,
S C Road, Sheshadripuram,
Bangalore – 560 020.
Phone No. 080 23460102
E – mail id – info@samrakshan.co.in, samrakshanblr@gmail.com
The Consultants and experts are engaged in Preparation of the EIA report for the proposed Project is
Modification and Expansion of Software Technology Park.
Our philosophy to nurture long-term associations with our esteemed clients has helped us to build strong
association with them. SAMRAKSAN is an organization with a team of specialized, trained and experienced
professionals in varied disciplines viz, Chemical, Environmental Engineering, Civil Engineering, Mechanical
engineering, organic and inorganic chemistry etc.,
No. Description
1 Architects:
Mr. Sanjay P. Bathija,
49, Nanjappa Road,
Shantinagar,
Bangalore – 560 027.
ACCREDITATION
NAME OF LABORATORY SCOPE OF SERVICES
STATUS
Monitoring and Analysis of:
M/s. Vsix Analytical Labs Pvt. Ltd., #771. Ambient Air Quality Monitoring
(502/503), 2nd Floor, 21st D Cross,2. Ground and Surface Water Quality M/s. Vsix Analytical Labs
Muthurayaswamy Layout, Monitoring Pvt. Ltd., is a NABL
Srigandhakaval, Sunkadakatte,3. Noise Level Monitoring and certified laboratory
Bangalore – 560 091. 4. Soil Quality Monitoring
5. Metrological data collection
R ROAD SCENARIO:
A
F SATYA SAI HOSPITAL ROAD:
F ➢The Satya Sai Hospital road is 18.2 m
I ➢ It is proposed to widen this road to 24 m to make it 4 lanes as per CDP.
C
➢ Drain exists on either side of the road.
S
U EXISTING TRAFFIC DETAILS:
R ➢ All types of vehicles move along the road.
V ➢ High traffic flow is observed between 8 to 9 AM (morning) at 5 to 6 PM (evening).
E
Y ➢ Among the vehicles, the speed recorded for four wheelers are more as most of these
vehicles are cabs.
& ➢ Almost negligible number of autos moves, as it is quite far from city.
➢ As compared to ITPL road, the HAL old airport road is near and hence the vehicles can
M use Kundalahalli / Marathahalli road largely as compared to ITPL road.
G
M
.
T TRAFFIC SURVEY ROAD DETAILS 2
R
A
F Traffic Study Conduced on Kundalahalli – ITPL Road
F
I Kundalahalli
C ITPL
S
U
R
V
E
Y
&
Project Site
M
G
M
.
C TRAFFIC PHOTOS 3
O
N
T
D
., Towards Kundalahalli
Towards ITPL
Towards project site
C 4
O
VEHICULAR SPEED DETAILS - ITPL ROAD (KMPH)
N
T
Sl. Towards 2 wh 3 wh 4 wh Buses
D no
., Max Min Max Min Max Min Max Min
1 Kundalahalli 46 22 20 16 54 38 33 21
2 ITPL 37 24 18 13 62 40 36 19
(Satya Sai
Hospital)
Note: The highest peak observed is 506 PCU’s during 5.00- 6.00pm
PCU’s are worked out based on IRC-106:1990.
C 6
O
N EXISTING TRAFFIC FLOW TOWARDS KUNDALAHALLI
T
D Timing 2Wh 3Wh 4Wh Mini Total
., Buses
Note: The highest peak observed is 932 PCU’s during 8.00 to 9.00 am.
PCU’s are worked out based on IRC-106:1990.
C 7
O
N EXISTING TRAFFIC SCENARIO & LOS
T Towards V C Existing V/C LOS
D Ratio
., ITPL 506 2200 0.23 “B”
Kundalahalli 932 2200 0.42 “C”
O DURING CONSTRUCTION
N ➢ Number of trucks proposed to come to the site is 15.
T Day time - 10 no.
D Night time - 05 no.
., ➢ The addition do not make any significant change for traffic movement at any given
time.
➢ Vehicles carrying construction materials are well covered to prevent any spillage.
➢ Vehicles hired for construction material will be in good condition and conforms to
noise and air emission standards.
➢ Vehicles will operate only during non peak hours.
➢ The project site is located at a distance of about 0.5 Km from Kundalahalli – ITPL
road.
➢ Entry and exit is given to the approach road which measures 18.2 m (and is
proposed to be widened to 24 m) and the road leads to Kundalahalli- ITPL road.
➢ It is a two lane road and each lane can take 700 PCU’s/hr as it is a local street (as
per IRC).
➢ The smooth entry and exit of vehicles at the gate is established by providing bell
mouth shape to prevent congestion at the gate without any delay.
➢ The wide entry and exit is adequate for the movement of traffic from in and out.
C 9
O
Towards Existing Modified
N
T V V/C LOS V V/C LOS
D
ITPL Road 506 0.23 “B” 506+ 1648 0.97 “E”
., =2154
Kundalahalli 932 0.42 “C” 932 + 1648 = 1.17 “F”
2580
Towards Modified for 18.2 m road width Modified for 24 m road width