Professional Documents
Culture Documents
Work Method Statement
Work Method Statement
Prepared for :
NEW CONN
INDEX
1) SCOPE
2) PURPOSE
3) REERENCES
4) RESPONSIBILITIES
- Project Manger
- Project Control Engineer:
, Page 1 of 7
- Procurement Engineer
- Construction Engineer / Site Supervisor
- Electrical & Instrumentation Engineer
- QA/QC Engineer
- HSSE Supervisor
5) EQUIPMENT / MATERIALS
6) MANPOWER CATEGORY
7) QUALITY CONTROL AND ASSURANCE
8) SAFETY INSTRUCTIONS AND PRECAUTIONS
9) METHOD OF EXECUTION
1. Scope:
The scope of works under this WMS applies to connection line between test separator and close drain
on the platform.
2. Purpose:
The purpose of this WMS for connection line between test separator and close drain is to ensure that
the work activities such as material handling, equipment installation and test & inspection shall be
carried out safely, efficiently and in accordance with the project requirements.
3. References :
Client specifications and applicable standards .
4. Responsibilities:
Project Manager:
The project Manager will be responsible for the overall project coordination and be the principal focal
point of Contract for CONTRACTOR on a day-to-day basis with COMPANY. Key tasks and
responsibilities throughout the project will include:
, Page 2 of 7
Initiate the Project Processes:
Contract Review / Negotiations / Signature
Project Charter Development
Stakeholders Identification
Manage the Project Planning Process:
Issue the Project Management Plan
Issue the Scope Management Plan
Procurement Engineer:
The Procurement Engineer will be responsible for the management of all procurement activities, and
this includes:
Procurement Management Plan Application
Managing and Controlling Tendering Process
Managing Procurement Negotiations and Contracts
Manage Freight Forwarding and Customs Clearing
QA/QC Engineer :
, Page 3 of 7
The QA/QC Engineer will manage the implementation of the Quality Control procedures related to
the construction work, and will assure the coordination with the Construction team in matters related
to Quality Control, Inspection, and Testing at site.
The QA/QC Engineer will be responsible for the management of the Quality Control Records and the
Project Quality Book compilation at the end of the Execution Phase of the Project.
HSSE Supervisor:
The HSSE Supervisor will establish the Health, Safety, Security and Environment (HSSE) Plan and
Procedures for the Project based on CONTRACTOR’s HSSE manual, Legal Obligations and
COMPANY’s requirements in terms of HSSE.
The HSSE Supervisor will be responsible for the HSSE Communication, Monitoring, Control and
Reporting all the way through the Project Execution.
5. Equipment / Materials :
Generator, diesel driven 150 KVA
Electrical welding machine (TIG AND ARC) including welding leads
Air compressor elect
Air compressor disel
Pipe fitter tool box
Welder tool box
Tool case ELECTRICIAN
Megohmmeter
megger insulation tester
Electrical Panels
Angle Grinder
Power drill
Pneumatic drill
Electric Pipe Threading Machine
manual Pipe Threading Machine
Cold cutters
Scaffolding
Hydro test pump
Oxygen/acetylene set including torch, hoses and gauges, hose shall be with an anti -flame return
device
, Page 4 of 7
6. Manpower Category:
Foreman
Mechanical/pipefitter
Welder
Helper
Scaffolder
Rigger
Permit Receiver and other involved Manpower
9. Method of Execution:
9.1 Project Initiation:
Site survey to verify and to endorse the deliverables of the engineering package.
Gather all project requirements and specifications.
Assemble project team, including engineers, technicians, and project managers.
9.3 Procurement:
, Page 5 of 7
The necessary materials and components for the piping Supports.
Providing all necessary fittings, supports, and mounting accessories for the field connections.
Supplying SS pneumatic tubes for Connection of instrument air.
Coordinate with suppliers and manage the procurement process.
9.7 Pre-Installation
– Cleaning of piping materials
– Review construction drawings by identifying the following requirements:
Arrangement of lifting, hoisting and construction equipment during lift.
– Once the foundation preparation has been completed, equipment installation commences. Ensure
that lifting and rigging shall be done with job specification and approved Method Statement
respectively.
, Page 6 of 7
– Removal of test blinds and major field welds are completed, as pressure test blinds and field welds
can result in changes in piping-to-machinery alignment.
– Check and verify that the inlet and outlet piping is properly constructed in accordance with the
latest drawing. Verification shall include gasket size and material, size and length of flange, bolts,
studs and nuts.
• Upon completion of inspection and acceptance by Company, conduct housekeeping properly.
, Page 7 of 7