Generating System Test Template For Non-Synchronous Generation
Generating System Test Template For Non-Synchronous Generation
AEMO has prepared this document to provide information to assist Generators in their preparation of GPS
compliance assessment and R2 model validation test plans for inverter-based generation technologies, such as wind,
solar and battery, as at the date of publication.
DISCLAIMER
This document or the information in it may be subsequently updated or amended. This document does not constitute
legal or business advice and should not be relied on as a substitute for obtaining detailed advice about the National
Electricity Law, the National Electricity Rules, or any other applicable laws, procedures or policies. AEMO has
made every effort to ensure the quality of the information in this document but cannot guarantee its accuracy or
completeness.
Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants involved
in the preparation of this document:
make no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness
of the information in this document; and
are not liable (whether by reason of negligence or otherwise) for any statements or representations in this
document, or any omissions from it, or for any use or reliance on the information in it.
VERSION CONTROL
Version Release date Changes
2.0 Feb 2020 Revised and updated general requirements , tests and report requirements
Table 1 Typical signals to be measured for asynchronous dynamic reactive support device
control system tests
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 3
Table 2 Typical signals to be measured for generating unit and park dispatch control tests
Table 3 Key stakeholders from each party involved in commissioning and GPS compliance, and
R2 tests
Table 4 Registered plant information
Table 5 Example hold point table for a generating system with 100 MW maximum capacity
(name plate rating 125 MVA) and 45 generating units.
Table 6 Test schedule example
Table 7 Generation profile table example
Table 8 Risk matrix example
Table 9 Risk assessment example – voltage reference step test
Table 10 Risk controls example – voltage reference step test
Table 11 Test conditions example – voltage reference step test
Table 12 File name and time stamp summary example – voltage reference step test
Table 13 Compliance Summary Example
Table 14 Test plan checklist
Table 15 Hold point report checklist
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 4
1. Introduction
1.1 Purpose and scope
Under the National Electricity Rules (NER), Generators are required to:
Prepare commissioning programs for new or replacement equipment (see clause 5.8.4).
Provide a commissioning program to the connecting Network Service Provider (NSP) and AEMO not less than 3
months prior to commencement of commissioning for a connection to a transmission network and not less than 1
month prior to commencement of commissioning for a connection to a distribution network (see clause 5.8.4(b)).
Prepare test plans to demonstrate that their generating systems comply with their performance standards (GPS)
and connection agreements (see clause 5.7.3).
Demonstrate that any system strength remediation scheme provided by their facilities meets the requirements
specified in their connection agreements (see clause 5.7.3A).
Notify AEMO and the NSP of any test to their equipment, or generating units, that requires a change to normal
operation (see clause 5.7.5, or 5.7.6, respectively).
Develop a routine compliance test program for their plant (see clause 4.15(b)).
This document has been prepared to assist Generators to prepare a commissioning program or test plan for inverter-
based generation to meet any of the purposes detailed above for:
New and upgraded plant and equipment.
Inverter-based generation technologies, primarily wind, solar photovoltaic (PV), and battery.
Tests to validate compliance with GPS and connection agreements when carrying out:
– Temporary changes to control system settings; and
– Temporary changes to plant operating modes.
The document does not cover every conceivable variation to generating system design. Minor modifications will be
acceptable when submitting test plans to AEMO and NSP in those circumstances.
This document does not apply to changes to plant protection systems to any detailed test procedure (also known as an
‘Inspection and Test Procedure’ or ‘ITP’) for test engineers for on-site testing.
COMTRADE Common format for Transient Data Exchange for power systems
DI Dispatch Interval
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 5
Term Definition
Generators Generators and those intending to register as Generators following the construction and connection of
new generating plant.
GPS S5.2.X.X The performance standard applicable to the generating system being tested. The reference to
“S5.2.5.X” refers to the clause in Schedule 5.2 of the NER from which the applicable performance
standard is drawn.
GPS Compliance Assessment The plan submitted for the purposes of clause 5.8.4 of the NER.
and R2 Validation Test Plan
HP Hold Point
HV High voltage
Hz hertz
kHz kilohertz
LV Low voltage
MV Medium voltage
MW megawatt
NSP The Network Service Provider who has connected the generating system to the network.
PF Power factor
PSCADTM/EMTDCTM Power Systems Computer Aided Design / Electromagnetic Transient with Direct Current
PU Per unit
PV Photovoltaic
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 6
Term Definition
SI Solar inverter
1.2.2 Interpretation
This document is subject to the principles of interpretation set out in Schedule 2 of the National Electricity Law.
1.3Related documents
Title Location
2. General requirements
2.1 Pre-requisites for GPS Compliance and R2 Model Validation Testing
The following are required before compliance or R2 model validation testing can begin:
Generator’s application for registration as a Generator is approved by AEMO.
GPS are included in the relevant connection agreement and notified to AEMO under clause 5.3.7 of the NER.
SCADA signals of good quality are received by AEMO.
All protection systems are in service.
All trip, runback scheme and other control systems are in service.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 7
The following documents have been submitted to AEMO and the NSP:
– Final connection study reports.
– R1 Power System Design Data Sheets and Power System Setting Data Sheets.
– R1 model package:
○ Generating unit model and aggregation method used.
○ Generating system central dispatch control model.
○ Static and dynamic reactive support devices model (if applicable).
○ System strength remediation scheme facilities model (if applicable).
○ Coordinated generating system control system model (if applicable).
– R1 block diagrams for the above models.
– R1 model source codes.
– R1 model parameters.
– R1 releasable user guide (RUG).
– Model acceptance test report (MAT)
– Final, as-built single line diagrams.
– An agreed GPS Compliance and R2 Validation Test Plan as required by clause 5.8.4 of the NER.
– Voltage control strategy report.
– Trip, runback scheme and other control system reports (if applicable).
– Start-up and shut-down procedure.
– Communication failsafe mechanism (central park controller to generating units and central park controller to
measurement meters) document.
– Physical setting downloads of the controllers.
– Setting summary table comparing physical settings downloaded from controllers on site with the R1
PSS®ETM and PSCADTM/EMTDC™ model settings.
– Valid calibration certificates of measurement equipment.
– Test schedule and generation profiles.
– Pre-test simulation studies - This is particularly necessary when connecting inverter-based generation to weak
networks to ensure that the extent of changes applied to reactive power and voltage at the connection point
would not adversely impact the area in which the generating system is connected.
– Generating system layout, including location of the closest NSP substation, generating unit and generating
system transformers, transmission line/cable arrangement, other static and dynamic reactive support devices
(if available).
– All pre-energisation checks/tests (e.g. protection tests) complete and confirmation that safe to energise.
– Type test, factory acceptance test (FAT) and any relevant off-site test reports.
– Photos of nameplate ratings of major plant installed on site (e.g. transformers, solar inverter (SI)/wind turbine
generator (WTG)) and evidence to confirm any connection assessment and assumptions (e.g. transformer
fixed tap positions).
– Proof of required skills and qualifications of the personnel involved in commissioning and GPS compliance
and R2 validation tests.
– Confirmation of compliance with all workplace health and safety requirements.
– Any other compliance evidence to the agreed GPS.
Operational communication facilities functional.
Bids and intermittent generation section of the Market Management System (MMS) portal complete.
AEMO and the NSP have approved plant to commence commissioning tests.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 8
2.2 Main point of contacts
A commissioning test plan includes contact details of the key personnel involved in commissioning activities. The
Generator must keep the main contact list up to date. Plant operator contacts should be available on a 24-hour basis
for AEMO and NSP control room staff to contact. Refer to Appendix A1.1 for a recommended contact list template.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 9
output to its semi-dispatch cap applying at the end of a semi-dispatch interval, subject to energy availability1.
Any non-conformance to the dispatch target while a semi-dispatch cap applies must be communicated to the
AEMO control room.
Plant monitoring.
– Plant should be monitored constantly. Processes should be in place, and met, to report any non-compliance to
the AEMO/NSP control rooms and commissioning support engineers immediately.
Changes to the commissioning test methodology and procedures.
– The Generator must seek advice from AEMO and the NSP if changes are required to the agreed test
methodology and procedures before proceeding with the commissioning tests.
Update on test progress.
– The Generator test coordinator must update the AEMO and NSP commissioning support engineers on
progress of the commissioning tests on a daily or weekly basis, as required.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 10
HP 2 – At least 60% of plant maximum capacity with all generating units in service.
HP 3 – At least 90% of plant maximum capacity with all generating units in service.
Refer to Appendix A1.3 for a recommended HP table template.
This document assumes that three HPs are required. In practice, AEMO or the NSP can request more than three
based on the location, number of generating units available for tests and size of the generating system.
HPs are based on active power output level assuming that measured responses are stable, and that a reasonable
correlation exists between measured and simulated responses. Additional HPs may be introduced if HP testing show
there is no reasonable correlation between measured and simulated responses.
The minimum generation level and number of generating units online must be agreed with AEMO and the NSP for
each HP in the commissioning test plan.
AEMO and the NSP release HP capacity for commissioning testing only. Plant is not expected to operate for an
extended period without tests being undertaken. If HP tests are not completed or HP reports are not submitted to
AEMO and the NSP within the agreed timeframes, AEMO will constrain generating system output to the previously
approved HP level. If HP tests cannot be completed due to primary energy source availability, interim HPs may be
tested subject to agreement with AEMO and the NSP.
AEMO and the NSP will confirm the following items are complete before final HP approval for unconstrained
operation:
All HP reports have been approved.
All non-compliances during the commissioning period have been resolved.
All control schemes, including system strength remediation schemes, are in operation and agreed parameters
implemented.
Operational communications are functional.
Energy conversion model (ECM) is accurate and all SCADA signals are of good quality.
Bids are updated accurately.
Plant follows dispatch targets from AEMO as in accordance with the Dispatch Procedure SO_OP_3705.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 11
Plant is continuously monitored by the Generator’s control room, and processes are in place to identify and notify
any non-conformance to the AEMO and NSP control rooms.
The Generator’s control room operators have been trained to follow verbal instructions from the AEMO and NSP
control rooms (e.g. switching operation, voltage set point change).
Non-compliance reporting process is in place.
2
It is expected that independent equipment is installed to collect test results separately from the device under test.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 12
Acceptance testing report for measurement equipment.
Valid and up-to-date calibration certificates of measurement equipment.
Signals to be measured at each measurement location.
Where many recorders are to be used, details on how measurement results will be synchronised to GPS clock.
Generating units with high-speed measurement equipment must be in-service for all tests.
Measured voltages and currents must be available in three-phase instantaneous waveforms, three-phase root mean
square (RMS), per-phase RMS.
Measured reference signals (Vref, Qref, Pref, Fref etc), irradiance, wind speed and temperature.
Voltage and frequency thresholds are defined for triggered power system events to trigger, record and save event
data automatically for GPS compliance and R2 validation requirements.
Measurement equipment power is supplied via an uninterruptable power supply (UPS) to ensure continuous
recording during network disturbances.
For example:
Wind Farm X_South section_HP2_VSR_2_B.CSV
refers to a test carried out at Wind Farm X, South section, Hold Point 2, Voltage Step Response (VSR) test, test
number 2.
Note that for generating unit testing, “Section name” is replaced with “Unit number”.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 13
Communication protocol (refer Section 2.4).
HP details (refer Section 2.7 and sample format in Appendix A1.3).
Overview of GPS Compliance Assessment and R2 Model Validation Tests.
Measuring equipment details and location (refer Section 2.8).
Test data file names format (refer Section 2.9).
HP test details (see Section 3).
– Pre-requisites for HP tests commencement.
– Risk assessment for each test (see sample format in Appendix A1.7).
– Purpose, pre-test conditions, methodology and procedure, signals to be measured and plotted, measurement
data file name and format, and acceptance criteria.
– Simulation software for overlays agreed for each test (PSS®ETM or PSCADTM/EMTDCTM).
Single line diagram.
Reactive power capability curve.
Measurement point layout (see Appendix A1.10).
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 14
HP test measured date files consistent with format, resolution and naming convention as detailed under Sections
2.8 and 2.9.
Applicable setting summary table comparing physical settings downloaded from actual controllers on site with
the R1 PSS®ETM and PSCADTM/EMTDC™ model settings as an appendix.
3.1.2 Asynchronous dynamic/static reactive support device (DRD) control system test – HP0
DRD test (if applicable)
Purpose
To assess the response of voltage control system and step response characteristics of voltage and reactive power.
To validate the asynchronous dynamic/static reactive support device control system model parameters including:
– Reactive power capability.
– Switching logic.
– Control model parameters such as control gains, time constants and limits.
To validate transformer, tap changer control logic.
[Note: The asynchronous dynamic reactive support device control system model parameters listed above are
provided for illustrative purposes. The Generator must specify all model parameters being validated].
Pre-test conditions
All generating units are offline.
Generating systems’ connection point is energised.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 15
All other reactive support devices are offline.
Pre-test simulation studies report is submitted by the Generator to AEMO and the NSP to verify the extent of
changes in network voltage and reactive power.
Control system of asynchronous dynamic support device is in service and configured to default control mode.
The generating system transformers are in manual control (fixed tap).
Risk assessment complete.
Communicate and confirm test with the AEMO and NSP control rooms.
Table 1 Typical signals to be measured for asynchronous dynamic reactive support device control system tests
Signals to be measured Signals for model Sampling rate Record time window
overlay
Voltage at T1HV
Voltage at T2HV
Voltage at T1MV
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 16
Signals to be measured Signals for model Sampling rate Record time window
overlay
Voltage at T2MV
Include signals that are plotted and compared against the respective simulated response in the GPS Compliance
Assessment and R2 Model Validation Test Plan.
Acceptance criteria
Reactive power output follows the reference set point correctly.
Reactive power response able to return to stable operation after each step.
Reactive power limits demonstrated in the tests are consistent with those in the submitted Power System Design
Data Sheets and Power System Setting Data Sheets.
The device can generate maximum reactive power (capacitive and inductive) continuously.
Measurement data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 17
Apply a +5% step to Vref.
Apply a -5% step to Vref.
Allow at least 10 seconds pre-triggered recording and at least 60 seconds recording time after the response has
settled at its steady-state value before the next test (step) commences.
View test data file to ensure it has been successfully saved.
Reconfigure the control system to default control mode.
Acceptance criteria
Model overlays of the reactive power responses for the voltage step test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy band is superimposed on the
graphs, including overlays of measured and simulated responses.
Reactive power response able to return to stable operation after each step.
Voltage, active power and reactive power settling time for a 5% step response complies with GPS S5.2.5.13, i.e. a
settling time of five seconds or less for the voltage step response.
Reactive power rise time for a 5% step response complies with GPS S5.2.5.13, i.e. a rise time of two seconds or
less for the voltage step response.
Measurement data is successfully downloaded and confirmed.
Acceptance criteria
Confirm capacitors switching logic threshold, hysteresis, deadband, and delay consistent with voltage control
strategy document.
Measurement signal data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 18
Transformer tap changer logic test (HP0 NDR Test D)
Acceptance criteria
Confirm tap changer logic threshold, hysteresis, deadband, and delay consistent with voltage control strategy
document.
Measurement signal data is successfully downloaded and confirmed.
Purpose
To determine background power quality signature at the connection point before connection of the generating
system.
Pre-test conditions
Confirm measurement systems are ready.
Generating system’s connection point is energised.
All generating units and balance of plant components are disconnected.
Signals to be measured
The typical signals to be measured for the HP0_ WFPQT/HP01_SFPQT test are as follows:
Phase to neutral voltages of each phase.
Fundamental frequency.
Harmonics voltages up to the 50th (including THD).
Flicker levels (including pst and plt levels).
Voltage unbalance levels (positive sequence voltage, negative sequence voltage and negative sequence unbalance
voltage).
Acceptance criteria
Measurement data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 19
3.1.4 Generating unit signal injection tests (HP0_WFSI/HP0_SFSI)
Purpose
To confirm voltage and frequency protection settings of the generating units consistent with GPS S5.2.5.8.
To validate voltage and frequency protection settings implemented in dynamic models of generating units.
Pre-test conditions
Confirm measurement systems are ready.
Confirm all generating unit protection settings consistent with GPS.
All generating unit protection settings uploaded and in service.
Acceptance criteria
Measurement data is successfully downloaded and confirmed.
Confirm generating units trip and delay consistent with the applied settings and GPS.
Purpose
To validate communication delays implemented in dynamic simulation models of generating units.
To confirm functions of communication equipment and feedback signals.
Pre-test conditions
Confirm measurement systems are ready.
All generating unit protection settings uploaded and in service.
Acceptance criteria
Measurement data is successfully downloaded and confirmed.
Confirm measured communication delays consistent with the dynamic simulation models time delays.
Purpose
To partially assess compliance with GPS S5.5.5.2 and GPS S5.2.5.6.
Pre-test conditions
Confirm measurement systems are ready.
Generating system’s connection point is energised.
Generating units and balance of plant components as agreed in the commissioning plan are connected.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 20
Signals to be measured and plotted
Table 2 shows the typical signals to be measured for the HP1_WFPQT/HP1_SFPQT.
Acceptance criteria
Measurement data is successfully downloaded and confirmed.
Assessment is conducted by comparing results obtained from the background measurements
(HP1_WFPQT/HP1_SFPQT) and during the HP 2 testing period.
The quality of the electricity generated (harmonics, flicker and voltage unbalance) is within the agreed limits
under GPS S5.2.5.2.
Purpose
To validate reactive power capability, active power dispatch and reactive power dispatch of the generating units.
To validate generating unit model parameters related to active power and reactive power limits.
Generating unit reactive power capability test (HP1 WTG Test A/ HP1 SI Test A)
Pre-test conditions
Confirm measurement systems are ready.
Monitor and record the ambient temperature before, during and after the test.
Generating units under test are operated with the park dispatch control enabled.
The park dispatch controller is in active power and reactive power control mode.
All reactive support and energy storage devices are offline.
The generating system transformers are in manual control (fixed tap).
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 21
Measurement data file name and format
PlantName_UnitNo_HP1_WTG_RCT.CSV.
Acceptance criteria
Measurement data covers the entire operating range.
The generating units can continuously operate at reactive power boundaries.
Measurement data is successfully downloaded and confirmed.
Generating unit active power dispatch test (HP1_WTG Test B / HP1_SI Test B)
Pre-test conditions
Generating units are operated with the park dispatch control enabled.
Central park controller is configured to local control and is in active power and reactive power control mode.
All reactive support devices are offline.
The generating system transformers are in manual control (fixed tap).
The generating units are operating at above 80% of rated active power output.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 22
Return Pdsp to the pre-test value.
Wait until the response settles.
Confirm the generating units are still generating over 80% of rated output.
Repeat the test with a -50% step.
View test data file to ensure it has been successfully saved.
Acceptance criteria
The active power response follows the reference correctly.
Generating unit active power rate of change (ramp rate) consistent with the configured ramp rate in
the controller.
The generating unit is able to return to stable operation after each step.
Model overlays for the active power dispatch test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
Measurement data is successfully downloaded and confirmed.
Generating unit reactive power dispatch test (HP1 WTG Test C / HP1 SI Test C)
Pre-test conditions
Confirm measurement systems are ready.
Generating units under test are operated with the park dispatch control enabled.
Central park controller is configured to local control and is in active power and reactive power control mode.
All reactive support devices are offline.
Generating system transformers are in manual control (fixed tap).
Generating units are operating at above 80% of rated active power output.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 23
View test data file to ensure it has been successfully saved.
Acceptance criteria
The reactive power response follows the reference correctly.
The generating unit is able to return to stable operation after each step.
Model overlays for the reactive power dispatch test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
Measurement data is successfully downloaded and confirmed.
Table 2 Typical signals to be measured for generating unit and park dispatch control tests
Signals to be measured Signals for model Sampling rate Record time window
overlay
Voltage at T2HV
Voltage at T1MV
Voltage at T2MV
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 24
Signals to be measured Signals for model Sampling rate Record time window
overlay
Voltage reference
Purpose
To assess compliance with GPS S5.2.5.1 with respect to reactive power capability of the generating system.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 of the NER with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Confirm measurement systems are ready.
Communicate and confirm test with NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Monitor and record the ambient temperature before, during and after the test.
Obtain a screenshot of the plant’s HMI demonstrating operational state of the plant before and after testing.
The total output of the generating units is above 80% of HP1 MW level.
The generating units are in park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
The dynamic and static reactive support plant are in service (if applicable).
The generating system transformers are under auto control.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 25
Methodology and procedure
The generating system is operated at a wide range of operating conditions including reactive power generation and
absorption boundaries. Figure 3 shows a typical reactive power capability of inverter-based generating system with
minimum operating points that are required to be captured during an HP1 test.
Pre-test simulation studies report is submitted by the Generator to verify the extent of changes in network voltage
and reactive power at the connection point that would not adversely impact the area to which the generating
system is connected.
Configure the generating system control to local control mode.
Configure the generating system control mode to reactive power control.
Load the generating system to the operating condition specified in Figure 3.
Wait until the response settles.
Allow the generating units to run for 10-15 minutes at each operating point.
While the generating system is continuously running, view test data file to ensure it has been successfully saved
before moving to the next operating condition.
Acceptance criteria
The generating system can continuously run for 10-15 minutes under each reactive boundary operating condition.
Voltage, active power and reactive power at the generating system’s connection point and generating units’
terminals are stable.
Measurement data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 26
Figure 3 Typical inverter-based generating system reactive power capability and measurement conditions for
HP1
Purpose
To assess compliance with GPS S5.2.5.13 with respect to voltage and reactive power control of the generating
system.
To assess compliance with GPS S5.2.5.4 with respect to continuous uninterrupted operation.
To assess response of coordinated voltage control strategy of the generating system and validate associated
simulation models, i.e. between the dynamic reactive support devices and generating units (if applicable).
To validate the dynamic reactive support control system model and parameters (if applicable).
To validate the park dispatch control model and parameters.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Communicate and confirm test with the NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Obtain a screen shot of the plant’s HMI demonstrating operational state of the plant before and after testing.
Maximum generating system output is at the agreed HP1 MW level.
Total output of the generating units is above 80%4 of HP1 MW level.
3
Alternatively, this test may be conducted at other HPs.
4
Specific minimum generation level at each HP must be agreed with AEMO and the NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 27
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode:
– The dynamic reactive support control system is in service.
– The static reactive support devices are in service but in local manual control.
The generating system transformer is under auto control.
Acceptance criteria
Model overlays for the static reactive support device manual switching test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs which include overlays of measured and simulated responses.
Generating system is able to return to stable operation after each switching action.
The settling time of voltage response for the switching action complies with the requirements of GPS S5.2.5.13,
e.g. 5 seconds settling required for a 5% voltage disturbance.
The settling time of reactive power response for the switching action complies with the requirements of GPS
S5.2.5.13, e.g. 5 seconds settling required for a 5% voltage disturbance.
The active power and reactive power response for the switching action complies with the requirements of GPS
S5.2.5.4. e.g. generating system and each of its generating units capable of continuous uninterrupted operation
for a power system disturbance causes voltage at the connection point to vary.
Measurement data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 28
3.2.5 Generating system active power control test
Purpose
To assess compliance with GPS S5.2.5.14 with respect to active power control of the generating system. (e.g.
ability to receive instruction electronically, change active power linearly at a constant rate and limit the active
power level or below the dispatch target).
To confirm the active power dispatch command from the AEMO control room and the generating system local
control.
To validate ramp up and down rates (ramp rate algorithm) to a dispatch command from the AEMO control room
(e.g. linear ramping at the end of the dispatch interval as required under Dispatch Procedure SO_OP_3705).
To validate effective ramp rates with the bid ramp rates.
To confirm the dispatch instruction delivery and processing time delay of the dispatch instruction.
To validate the ramp rate algorithm accuracy.
To validate active power control loop model and parameters of the generating units.
To validate the park dispatch control model and parameters.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Communicate and confirm test with NSP and AEMO control rooms.
Obtain a screenshot of the plant’s HMI demonstrating operational state of the plant before and after testing.
Confirm implemented ramp rates in the controller.
Maximum generating system output is at the agreed HP1 MW level.
Total output of the generating units is above 80%5 of HP1 MW level.
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
– The dynamic reactive support control system is in service.
– The static reactive support devices are in service and in auto control (if applicable).
The generating system transformer is under auto control.
5
Specific minimum generation level at each hold point must be agreed with AEMO and NSP.
6
For generating systems with fast and slow ramp options, testing should be conducted with both ramp rates.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 29
– Return the Pdsp to pre-test level.
– Wait until the response settles.
– Allow at least 10 seconds pre-triggered recording and at least 60 seconds recording time after the response has
settled at its steady-state value before the next test (step) commences.
– Confirm the generating system output is above 80% of HP1 MW level.
– Repeat the test with -50% and -90% steps.
– View test data file to ensure it has been successfully saved.
The second stage of the test will be described in Section 3.4.4.
Acceptance criteria
Model overlays of the generating system active power dispatch test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
The generating system is able to return to stable operation after each step.
The response time of active power dispatch complies with the requirements of GPS S5.2.5.14, e.g. active power
output ramps linearly from one level of dispatch to another.
Ramp up and down rate within the maximum ramp rate.
Measurement data is successfully downloaded and confirmed.
Pre-test conditions
Communicate and confirm test with the NSP and AEMO control rooms.
Obtain a screenshot of the plant’s HMI demonstrating operational state of the plant before and after testing.
Maximum generating system output is at the agreed HP1 MW level.
Total output of the generating units is above 80%7 of HP1 MW level.
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
– The dynamic reactive support control system is in service.
– The static reactive support devices are in service and in auto control (if applicable).
The generating system transformer is under auto control.
AGC tests complete during SCADA tests.
7
Specific minimum generation level at each hold point must be agreed with AEMO and NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 30
Methodology and procedure8
Confirm measurement systems are ready.
This test is initiated by an active power dispatch signal from the AEMO control room and conducted as follows:
– Configure the generating system control to remote control mode.
– The Generator submits 30-minute bids to achieve ramp down to 50%, ramp down to 10%, ramp up to 40%
and ramp up to 80% of HP1 output level.
The dispatch signal from the AEMO control room and subsequent generating system response will be monitored
to confirm end-to-end communication of active power dispatch command from the AEMO control room through
to each generating unit.
Record dispatch instruction delivery and processing time delay.
View test data file to ensure it has been successfully saved.
Acceptance criteria
Model overlays of the generating system active power dispatch test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
The generating system is able to return to stable operation after each step.
The response time of active power dispatch complies with the requirements of GPS S5.2.5.14, e.g. active power
output ramps linearly at a constant rate from one level of dispatch to another at the end of dispatch interval.
The generating system ramp rate algorithm is consistent with the Dispatch Procedure SO_OP_3705 requirements,
e.g. the semi-scheduled generating system is expected to ramp linearly from its initial active power output to its
semi-dispatch cap applying at the end of the dispatch interval, subject to energy availability.
Effective ramp up and down rates consistent with the ramp rate algorithm.
Dispatch instruction delivery delay time and processing time within reasonable limits (typically delivery time
delay up to 10 seconds and processing time up to 30 seconds).
Measurement data is successfully downloaded and confirmed.
Purpose
To assess compliance with GPS S5.2.5.13 with respect to voltage and reactive power control of the generating
system.
To validate reactive power control loop model and parameters of the generating units.
To validate the park dispatch control model and parameters.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Communicate and confirm test with the NSP and AEMO control rooms.
8
For generating systems with fast and slow ramp options, the test should be conducted with both ramp rates.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 31
Risk assessment complete and risk mitigation controls applied.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
Maximum generating system output is the agreed HP1 MW level.
Total output of the generating units is above 80%9 of HP1 MW level.
Generating units are under park dispatch control in active power and reactive power control mode.
All reactive support plants are offline.
The generating system transformer is under auto control.
Acceptance criteria
The reactive power response follows the reactive power reference correctly.
The reactive power control system can regulate the reactive power at the connection point and agreed location
within 2% of the rating (in MVA) of the generating system (expressed in MVAr).
Model overlays of generating system reactive power dispatch test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
Measurement data is successfully downloaded and confirmed.
9
Specific minimum generation level at each hold point must be agreed with AEMO and NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 32
3.2.7 Generating system voltage reference step test (HP1_WFVCT/HP1_SFVCT)
Purpose
To assess compliance with GPS S5.2.5.13 with respect to voltage control capability.
To assess response of coordinated voltage control strategy of the generating system and validate associated
simulation models (if applicable).
To validate static and dynamic reactive support control system model and parameters (if applicable).
To validate the park dispatch voltage control model and parameters.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Communicate and confirm test with the NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
Maximum generating system output is at the agreed HP1 MW level.
Total output of the generating units is above 80%10 of HP1 MW level.
Generating units are under park dispatch control.
The generating system is in voltage control mode.
The generating system transformer is under auto control.
Acceptance criteria
Model overlays of the generating system voltage reference step test are submitted as part of HP reports. The
following responses need to be included:
10
Specific minimum generation level at each hold point must be agreed with AEMO and NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 33
– Connection point.
– Static and dynamic reactive support plant.
– Central park level controller.
– Coordinated voltage control scheme.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
The generating system is able to return to stable operation after each step.
The settling time of active power, reactive power and voltage response for the switching action complies with the
requirements of GPS S5.2.5.13, e.g. five seconds settling time is required for a 5% voltage disturbance.
The reactive power rise time for the switching action complies with the requirements of GPS S5.2.5.13, e.g. 2
seconds reactive power rise time is required for a 5% voltage disturbance.
Measurement data is successfully downloaded and confirmed.
3.2.8 Generating system power factor reference step test (HP1_WFPFT/HP1_SFPFT) (if
applicable)
Purpose
To assess compliance with GPS S5.2.5.13 with respect to power factor control capability.
To assess response of coordinated power factor control strategy of the generating system and validate associated
simulation models (if applicable).
To validate static and dynamic reactive support control system model and parameters (if applicable).
To validate the park dispatch power factor control model and parameters.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 of the NER with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Communicate and confirm test with the NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
Maximum generating system output is at the agreed HP1 MW level.
Total output of the generating units is above 80%11 of HP1 MW level.
Generating units are under park dispatch control.
The generating system is in power factor control mode and the power factor reference (PFref) is set to unity.
The generating system transformer is under auto control.
11
Specific minimum generation level at each hold point must be agreed with AEMO and NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 34
Set PFref to 0.99 inductive.
Set PFref back to unity.
Set PFref to 0.95 (or plant GPS limit) capacitive.
Set PFref back to unity.
Set PFref to 0.95 (or plant GPS limit) inductive.
Set PFref back to unity.
Allow at least 10 seconds pre-triggered recording and at least 60 seconds recording time after the response has
settled at its steady-state value before the next test (step) commences.
View test data file to ensure it has been successfully saved.
Acceptance criteria
Model overlays of the generating system voltage reference step test are submitted as part of HP reports. The
following responses needs to be included:
– Connection point.
– Static and dynamic reactive support plant.
– Central park level controller.
– Coordinated voltage control scheme.
The power factor at the connection point or agreed location follows the power factor reference correctly.
The power factor control system can regulate the power factor at the connection point and agreed location within
2% of the rating (in MVA) of the generating system (expressed in MVAr).
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
The generating system is able to return to stable operation after each step.
Power factor setpoint can be continuously controllable across the reactive power capability range established
under GPS S5.2.5.1.
Measurement data is successfully downloaded and confirmed.
Purpose
To assess compliance with GPS S5.2.5.4 and GPS S5.2.5.13.
To assess response of the generating system and generating units to small voltage disturbances caused by
transformer tap changes.
To validate dynamic model and parameters of the:
– Generating units.
– Transformer tap changer (if applicable).
– Central park level controller.
– Generating system control system.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 35
– Coordinated voltage control scheme (if applicable).
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 of the NER with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Maximum generating system output is at the agreed HP1 MW level.
Total output of the generating units is above 80%12 of HP1 MW level.
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
The generating system transformer is under manual control (fixed tap).
Acceptance criteria
Model overlays of the generating system transformer manual tap position change test are submitted as part of HP
reports. The following responses needs to be included:
– Connection point.
– Static and dynamic reactive support plant.
– Central park level controller.
– Coordinated voltage control scheme.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
The generating system is able to return to stable operation after each step.
Measurement data is successfully downloaded and confirmed.
12
Specific minimum generation level at each HP must be agreed with AEMO and NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 36
3.3 Hold Point 2 Test
3.3.1 Power quality test (HP2_WFPQT/HP2_SFPQT)
Refer to Section 3.2.1 as the same methodology used there is used for this test.
Figure 4 Typical inverter-based generating system reactive power capability and measurement conditions for
HP2
3.3.6 Generating system power factor reference step test (HP2_WFPFT/HP2_SFPFT) (if
applicable)
Refer to Section 3.2.8 as the same methodology used there is used for this test.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 37
3.3.7 Generating system transformer manual tap position change test
(HP2_WFTXT/HP2_SFTXT)
Refer to Section 3.2.9 as the same methodology used there is used for this test.
Purpose
To verify that the response of the generating system to a communication failure does not pose any risk to the
power system security.
To verify the communication failsafe mechanism of the generating system for communication failures between
central park controller and each generating unit and central park level controller and measurement equipment.
To verify local limit calculation while generating units are offline (Test A).
Pre-test conditions
Communication failsafe mechanism document agreed with the NSP and AEMO.
Communicate and confirm test with the NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Obtain a screenshot of the plant’s HMI demonstrating its operational state before and after testing.
Record pre-test local limit (active power).
Maximum generating system output is at the agreed HP2 MW level.
Total output of the generating units is above 80%13 of HP2 MW level.
Generating units are under park dispatch control.
The generating system is in voltage control mode.
The generating system transformer is under auto control.
13
Specific minimum generation level at each hold point must be agreed with AEMO and NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 38
Measurement data file name and format
PlantName_SectionNo_HP2_WFCOMFAIL_A.CSV.
PlantName_SectionNo_HP2_WFCOMFAIL_B.CSV.
PlantName_SectionNo_HP2_WFCOMFAIL_C.CSV.
PlantName_SectionNo_HP2_WFCOMFAIL_D.CSV.
Acceptance criteria
The generating system and each generating unit are able to return to stable operation/standby after each step.
The generating system and each generating unit’s operation consistent with the communication failsafe
mechanism document.
Pre- and post-local limit (active power) calculation accuracy based on generating units in service confirmed.
Measurement data is successfully downloaded and confirmed.
Figure 5 Typical inverter-based generating system reactive power capability and measurement conditions for
HP3
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 39
3.4.3 Static reactive support device manual switching test (HP3_WFCAP/HP3_SFCAP)
Refer to Section 3.2.4 as the same methodology used there is used for this test.
3.4.7 Generating system power factor reference step test (HP3_WFPFT/HP3_SFPFT) (if
applicable)
Refer to Section 3.2.8 as the same methodology used there is used for this test.
Purpose
To assess compliance with GPS S5.2.5.11 with respect to frequency control.
To assess compliance with GPS S5.2.5.8(a)(2) with respect to automatic rapid reduction of generation for a
frequency increase.
To assess the generating system’s ability to provide primary frequency response (PFR)14.
To validate dynamic model and associated parameters of the frequency control function in central park level
controller.
To assess compliance with GPS S5.2.6.1 and clause 4.11.1 of the NER with respect to confirmation of:
– SCADA feedback signals.
– Communication equipment.
Pre-test conditions
Total output of the generating system is above 90% of HP3 MW.
Total output of the generating system is above 90% of HP3 MW level (for over-frequency tests).
Total output of the generating system is above 90% of HP3 MW level but curtailed to 50% of HP3 (for under-
frequency tests).
Generating units are under park dispatch control and configured to frequency control mode.
The generating system is in default control mode, e.g. voltage control mode.
The generating system transformer is under auto control.
14
This requirement anticipates the making of the National Electricity Amendment (Mandatory primary frequency response) Rule 2020, expected to occur on or about
26 March 2020. See https://www.aemc.gov.au/rule-changes/mandatory-primary-frequency-response.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 40
Confirm measurement systems are ready.
Configure the generating system control to local control mode.
Confirm the pre-test conditions.
Set to default deadband and droop settings consistent with GPS S5.2.5.8(a)(2) and GPS S5.2.5.11 requirements.
Inject a frequency step signal into the frequency controller summing junction. Typical step sizes are ±0.1 Hz,
±0.25 Hz, ±1 Hz and ±2.0 Hz15.
Allow at least 10 seconds pre-triggered recording and at least 60 seconds recording time after the response has
settled at its steady-state value before the next test (step) commences.
Repeat tests for different deadbands (range of 0 to ±1.0 Hz) and droop (range of 2% to 10%) combinations.
Typical combinations are (±0.15 Hz, 2%),(±0.15 Hz, 5%),(±0.5 Hz, 2%) and (±1 Hz, 5%).
(Please note AEMO seeks to evaluate the generating system’s ability to adjust generation output automatically to
arrest and stabilise frequency, typically in proportion to measured frequency deviation as required under the primary
frequency response requirements (PFRR)16. The scope of this test should not be altered.)
Repeat the tests for all proposed operating modes such as raise, lower, frequency sensitive mode, limited
frequency sensitive mode, and frequency control ancillary services (FCAS).
Acceptance criteria
Model overlays of the generating system frequency control test are submitted as part of HP reports. The following
responses need to be included:
– Connection point.
– Static and dynamic reactive support plant.
– Central park level controller.
– Coordinated voltage control scheme.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
The generating system is able to return to stable operation after each step.
Measurement data is successfully downloaded and confirmed.
The active power response complies with the requirements of GPS S5.2.5.11, GPS S5.2.5.8(a)(2), and the PFRR.
Purpose
To partially assess compliance with GPS S5.2.5.4, GPS S5.2.5.8 and GPS S5.2.5.13.
To validate dynamic model of generating units, generating system and all associated control systems.
To validate the local limit (active power) calculation based on number of generating units in service.
Pre-test conditions
Confirm the measurement systems are ready.
15
Step sizes for frequency injection signal must be agreed with AEMO and NSP.
16
This requirement anticipates the making of the National Electricity Amendment (Mandatory primary frequency response) Rule 2020, expected to occur on or about
26 March 2020. See https://www.aemc.gov.au/rule-changes/mandatory-primary-frequency-response.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 41
Communicate and confirm test with the NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
Maximum generating system output is at the agreed HP3 MW level.
Total output of the generating system is above 90%17 of HP3 MW level (for over-frequency tests).
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
The generating system transformer is under auto control.
Acceptance criteria
Model overlays of partial generating system trip test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
Generating units not subject to tripping are capable of maintaining continuous uninterrupted operation after
partial tripping concludes.
Pre- and post-local limit (active power) calculation accuracy based on generating units in service confirmed.
Measurement data is successfully downloaded and confirmed.
Purpose
To assess implementation and compliance of trip or runback scheme with GPS S5.2.5.8 and GPS S5.2.5.12.
Pre-test conditions
Confirm the measurement systems are ready.
Communicate and confirm test with NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
17
Specific minimum generation level at each HP must be agreed with AEMO and the NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 42
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
Generating units are under park dispatch control.
Total output of the generating system is above 90% of HP3 MW level.
All generating system protection systems in service with normal settings.
The generating system is in default control mode, e.g. voltage control mode.
The generating system transformer is under auto control.
Acceptance criteria
Model overlays of the generating system trip or runback test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs, which include overlays of measured and simulated responses.
Trip or runback scheme operation comply with the requirements under GPS S5.2.5.8 and GPS S5.2.5.12.
Trip scheme – The generating system is able to return to stable operation and generating units not subject to
tripping are capable of maintaining continuous uninterrupted operation after tripping concludes.
Runback scheme – The generating system is able to return to stable operation after runback.
Measurement data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 43
3.5.1 Network capacitor or reactor switching test (HP3_WFCST/HP3_SFCST)
Purpose
To assess compliance with GPS S5.2.5.13 with respect to voltage and reactive power control of the generating
system.
To assess compliance with GPS S5.2.5.4 with respect to continuous uninterrupted operation of the generating
system.
To assess response of the generating system and generating units to voltage disturbances caused by capacitor or
reactor switching.
To validate dynamic model and parameters of the coordinated voltage control scheme.
Pre-test conditions
Output of the generating units is above 90% of HP MW level.
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
The generating system transformer is under auto control.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
Communicate and confirm test with AEMO and NSP control rooms.
Acceptance criteria
Model overlays for the capacitor or reactor switching test are submitted as part of HP reports.
To assess compliance with the Power System Model Guidelines, ±10% accuracy bands need to be superimposed
on the graphs which include overlays of measured and simulated responses.
Generating system is able to return to stable operation after each switching action.
The settling time of voltage, reactive power and active power response for the switching action complies with the
requirements of GPS S5.2.5.13.
The active power and reactive power response for the switching action complies with the requirements of GPS
S5.2.5.4. e.g. generating system and each of its generating units capable of continuous uninterrupted operation
for a power system disturbance that causes voltage at the connection point to vary.
Measurement data is successfully downloaded and confirmed.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 44
3.5.2 Low irradiance/wind and high irradiance/wind low active power setpoint tests
(HP3_WFLIVCT/HP3_SFLIVCT, HP3_WFAPC_LOC/HP3_SFAPC_LOC)
Purpose
To assess stability of the voltage control system under low irradiance/wind conditions.
Pre-test conditions
Communicate and confirm test with NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
For solar farms: Low irradiance level (closer to sunset, typically below 150 W/m2).
Generating units are under park dispatch control.
The generating system is in voltage control mode.
The generating system transformer is under auto control.
Acceptance criteria
Refer to Section 3.2.7 as the same acceptance criteria are used there.
Purpose
To assess accuracy of temperature dependent local limit calculation to meet GPS S5.2.5.1 and GPS S5.2.5.4.
Pre-test conditions
Local active power limit calculation logic is provided to AEMO and NSP.
Pre assessment complete to verify the local limit calculation accuracy.
– Monitor all inputs to and output from the local limit calculation, trending with 1 second resolution in SCADA.
– Trend inputs and output of local limit calculation for at least 4 hours to allow temperature to vary in a broader
range.
– Calculate the value of the local limit from the inputs (temperature, number of generating units in service etc).
– Compare output of local limit with calculated value of local limit.
Output of the generating units is above 90% of HP MW level.
Generating units are under park dispatch control.
The generating system is in default control mode, e.g. voltage control mode.
The generating system transformer is under auto control.
Obtain a screenshot of the plant’s HMI demonstrating the plant’s operational state before and after testing.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 45
Allow 10 seconds pre-triggered recording and 120 seconds recording time after the response has settled at its
steady-state value.
Apply a bias to the temperature signal at the park controller to synthesise an increase the temperature to 50ºC.
Allow 10 seconds pre-triggered recording and 120 seconds recording time after the response has settled at its
steady-state value.
Apply a bias to the temperature signal at the park controller to synthesise an increase the temperature to 40ºC.
Allow 10 seconds pre-triggered recording and 120 seconds recording time after the response has settled at its
steady-state value.
Configure the park controller in normal mode.
Acceptance criteria
Measurement data is successfully downloaded and confirmed.
Plant responded to the expected derating with the variation in temperature as specified in GPS S5.2.5.1.
Purpose
Under special circumstances, AEMO or the NSP may consider that the fault ride through performance of a
generating system is required to be tested by conducting a fault-throwing test. AEMO and the NSP will evaluate the
risk to power system security and impact on other Network Users during the test.
To validate the generating system response to disturbances following contingency events as required by GPS
S5.2.5.5.
Pre-test conditions
Power system security risk and impact on Network Users evaluated.
Pre-test simulation studies are completed by the NSP and AEMO.
Hardware in the loop (HIL) tests are completed by the Original Equipment Manufacturer (OEM) (AEMO and
NSP to advise).
Communicate and confirm test details with NSP and AEMO control rooms.
The test details communicated to the other relevant Network Users.
The testing methodology and test procedures agreed between the Generator, NSP and AEMO control rooms.
Risk assessment complete and risk mitigation controls applied.
Confirm the primary and secondary measurement systems are ready.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 46
3.5.5 N-1 system outage tests (HP3_WFSOT/HP3_SFSOT)
Purpose
In order to assess its performance during planned network outage conditions (N-1 conditions) the generating system
will be tested during commissioning for the N-1 low system strength configurations identified during connection
assessments. Compliance with the following GPS will be assessed during N-1 system outage tests:
Reactive power capability test (GPS S5.2.5.1).
Voltage reference step test (GPS S5.2.5.13).
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 47
Methodology and procedure
Any power system disturbance captured by continuous monitoring systems during commissioning or post-
commissioning will be used to conduct the GPS compliance assessment and R2 model validation. AEMO and the
NSP will provide information of the power system disturbance, such as fault location, fault clearing time, nature of
the fault, post-fault power system condition, power system model information representing the snapshot of the power
system prior to occurrence of the power system disturbance and relevant system model information and files.
Generating system measurement equipment should be able to trigger, record and save high speed data automatically
for the power system events when voltage or frequency (or both) change outside set thresholds.
The Generator must capture and assess compliance of the generating system with relevant GPS and validate
accuracy of the model with the measured responses. The recorded data must be made available to AEMO and the
NSP.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 48
A1. Appendix
A1.1 Main points of contact
Table 3 Key stakeholders from each party involved in commissioning and GPS compliance, and R2 tests
Description Abbreviation Nominated personnel Land line number Mobile number Email contact Professional
qualifications (e.g.
RPEQ , CPENG and
NER)
Test coordinator TC
Test lead/manager TM
Test engineer TE
Secondary contact
Secondary contact
Secondary contact
Secondary contact
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 49
A1.2 Key plant information
Table 4 Registered plant information
Details Remarks
Nameplate rating
Maximum capacity
Connection Point
Rated voltage
Rated current
HP and maximum active power (MW) Number of generating units in service HP maximum active power (MW) test HP minimum active power (MW) test Maximum and minimum and reactive Reactive plant and/or system strength Harmonic filter bank status (if any)
level* level* power (MVar) * support device status (if any)
18
Notifiable exemption allows maximum combined nameplate rating of all generating units simultaneously connected at the connection point less than 5 MW .
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 50
A1.4 Overview of GPS Compliance Assessment and R2 Validation Tests
est schedule
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 51
Table 6 Test schedule example
Item Day Date Activity Initial Operating Conditions Test Reference GPS Clause Validation MW Initial MW Change MVAr MVAr Start Finish
Initial Change
(Market Time) (Market Time)
1 Hold Point 0
10 HP 0 report 30/09/2019
submission date
12 Hold Point 1
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 52
Item Day Date Activity Initial Operating Conditions Test Reference GPS Clause Validation MW Initial MW Change MVAr MVAr Start Finish
Initial Change
(Market Time) (Market Time)
23 HP 1 report 15/10/2019
submission date
25 Hold Point 2
34 HP 2 report 31/10/2019
submission date
36 Hold Point 3
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 53
Item Day Date Activity Initial Operating Conditions Test Reference GPS Clause Validation MW Initial MW Change MVAr MVAr Start Finish
Initial Change
(Market Time) (Market Time)
50 HP 3 report 20/11/2019
submission date
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 54
A1.6 Generation profile
Figure 6 Generation profile example
Please note: The daily generation profile indicated above, only includes certain selected active power and reactive power tests specified in this test plan and must be amended in-line with the commissioning
schedule.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 55
Table 7 Generation profile table example
06:15 0 0
06:30 0 0
06:45 5 0
07:00 10 0
07:15 20 0
07:30 30 0
07:45 40 0
08:00 50 0
08:15 60 0
08:30 60 25 HP2_SFVCT_LIM
08:45 60 0 HP2_SFVCT_LIM
09:00 60 25 HP2_SFVCT_LIM
09:15 60 0 HP2_SFVCT_LIM
09:45 60 0 HP2_SFVCT_LIM
10:15 60 0
10:30 60 0
10:45 60 0 HP2_SFAPT
11:00 30 0 HP2_SFAPT
11:15 60 0 HP2_SFAPT
11:30 15 0 HP2_SFAPT
11:45 60 0 HP2_SFAPT
12:00 60 0
12:30 60 15 HP2_SFRPT
12:45 60 20 HP2_SFRPT
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 56
Time P (MW) Q (MVAr) Planned HP Test Remark
13:45 60 0
14:00 60 0
14:15 60 0
14:30 60 0
14:45 60 0
15:00 60 0
15:15 60 0
15:30 60 0
15:45 60 0
16:00 60 0
16:15 60 0
16:30 50 0
16:45 40 0
17:00 30 0
17:15 20 0
17:30 10 0
17:45 5 0
18:00 0 0
18:15 0 0
18:30 0 0
18:45 0 0
19:00 0 0
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 57
¹ You may define the probability of occurrence e.g. most likely (more than 80% chance of occurrence).
² You may define the severity of consequence. e.g. insignificant (commissioning program delay less than 1 week, cost overrun
up to 10%, minimum rework to address the issue).
Connection point voltage outside the normal operating level Likely Insignificant Medium
Unexpected protection trip due to incorrect setting or malfunction Unlikely Insignificant Low
3 Confirm all plant quantities are within normal equipment withstand levels
4 Confirm step size and reference change consistency with the test plan
5 Communicate with NSP / AEMO control room to configure network reactive plants, OLTC
etc to allow tests to be conducted as required.
6 Any deviation to the test plan pre-approved and appended to the test plan.
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 58
A1.8 Test conditions, file name and time stamp summary–
voltage reference step test
Table 11 Test conditions example – voltage reference step test
HP2_SFVCT_UPF_POS_3PCT
HP2_SFVCT_UPF_NEG_3PCT
HP2_SFVCT_UPF_POS_5PCT
HP2_SFVCT_UPF_NEG_5PCT
HP2_SFVCT_OER_POS_3PCT
HP2_SFVCT_OER_NEG_3PCT
HP2_SFVCT_OER_POS_5PCT
HP2_SFVCT_OER_NEG_5PCT
HP2_SFVCT_UER_POS_3PCT
HP2_SFVCT_UER_NEG_3PCT
HP2_SFVCT_UER_POS_5PCT
HP2_SFVCT_UER_NEG_5PCT
HP2_SFVCT_OER_LIM_NEG_2P5PCT
HP2_SFVCT_OER_LIM_ POS_5PCT
HP2_SFVCT_UER_LIM_ POS_2P5PCT
HP2_SFVCT_OER_LIM_ NEG_5PCT
Table 12 File name and time stamp summary example – voltage reference step test
HP4_SFVCT_UPF_NEG_3PCT
HP4_SFVCT_UPF_POS_5PCT
HP4_SFVCT_UPF_NEG_5PCT
HP4_SFVCT_OER_POS_3PCT
HP4_SFVCT_OER_NEG_3PCT
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 59
Test Timestamp File names
HP4_SFVCT_OER_POS_5PCT
HP4_SFVCT_OER_NEG_5PCT
HP4_SFVCT_UER_POS_3PCT
HP4_SFVCT_UER_NEG_3PCT
HP4_SFVCT_UER_POS_5PCT
HP4_SFVCT_UER_NEG_5PCT
HP4_SFVCT_OER_LIM_NEG_2P5P
CT
HP4_SFVCT_OER_LIM_
POS_5PCT
HP4_SFVCT_UER_LIM_
POS_2P5PCT
HP4_SFVCT_OER_LIM_
NEG_5PCT
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 60
A1.9 Compliance summary
Table 13 Compliance Summary Example
HP3_SFPQT Harmonics Results within the allocated limits Harmonic allocation in the GPS Yes No
Flicker Results within the threshold Epst Eplt thresholds in the GPS Yes No
Negative phase sequence Results within the limits Negative sequence voltage limits in the GPS Yes No
HP3_SFRCT Reactive power capability Meets the agreed performance standard. 0.395 * rated active power Yes No
HP3_SFRPT Follow reactive power reference within accuracy Results within 2% of the rating 2% of the rating expressed in MVAr. Yes No
limits
Stability Plant response stable and adequately damped Plant response stable and adequately damped Yes No
HP3_SFVCT Voltage error Less than 0.5% Less than 0.5% Yes No
Settling time without limiter action Less than 5 s Less than 5 s Yes No
Settling time with limiter action Less than 5 s Less than 7.5 s Yes No
Stability Plant response stable and adequately damped Plant response stable and adequately damped Yes No
HP3_SFCAP Stability Plant response stable and adequately damped Plant response stable and adequately damped Yes No
Continuous uninterrupted operation (CUO) Plant response meets the CUO requirement Plant capable of CUO Yes No
HP3_SFAPC Constant rate Active power ramps in a constant rate until end of 5 Active power ramps at a constant rate until end of DI Yes No
min DI
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 61
Test Assessment subclause Test Results GPS requirement Compliance
Reach the target Active power ramps reach the target at the end of 5 min Active power ramps reach the target at the end of DI Yes No
DI
Linear ramping Active power ramps linearly Active power ramps linearly until end of DI Yes No
Ramp rate algorithm consistent with System Automatically reducing or increasing its active power automatically reducing or increasing its active power Yes No
Operating Procedure S0_OP_3705 output linearly at the end of the DI linearly. output linearly within 5 minutes at a constant rate.
Follow AGC target Plan can receive and automatically follow targets from Plan can receive and automatically follow target from Yes No
AGC AGC
Adequately damped Active power control adequately damped Active power control adequately damped Yes No
Automatic proportional decrease and increase in Plant can automatically decrease and increase active Plant can automatically decrease and increase active Yes No
frequency control mode power proportionally. power proportionally.
Control system response adequately damped Plant response stable and adequately damped Plant response stable and adequately damped Yes No
Set deadband (0 to ± 1.0 Hz) and droop(2% to Plant response stable and adequately damped in tested Plant can set deadband (0 to ± 1.0 Hz) and droop( 2% to Yes No
10% ). deadband and droop settings 10% ).
Active power reduction for over frequency (GPS Active power reduction within GPS S5.2.5.8(a)(2) Reduce at least by half above or reaching frequency Yes No
S5.2.5.8(a)(2)) requirements. limit
HP3_SFLLCAL Temperature dependent local controls Active power ramps linearly based on temperature. Active power ramps linearly based on temperature. Yes No
Accuracy of local limit calculation Local limit algorithm accurate with the design algorithm accuracy for unit/ plant outages Yes No
HP2_SFCOMFAIL Communication failure failsafe mechanism Plant response consistent with agreed failsafe N/A Yes No
mechanism logic
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 62
Test Assessment subclause Test Results GPS requirement Compliance
(Additional tests as … … … …
necessary)
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 63
A1.10Measurement point layout example
Figure 7 Measurement point layout
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 64
A1.11Test Plan checklist
Table 14 Test plan checklist
5 Main point of contacts See Section 2.2 and Appendix A1.11 Yes No
6 Key plant information See Section 2.3 and Appendix A1.2 Yes No
8 Risk assessment included for each test See Section 2.5 and Appendix A1.7 Yes No
10 Simulation software for overlays agreed for each test PSS®E and/or PSCADTM/EMTDCTM Yes No
11 Test data file name format details See section 2.9 Yes No
14 Hold point details See Section 2.7 and Appendix A1.3 Yes No
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 65
Table 15 Hold point report checklist
HMI screenshots.
Yes No
Plots and overlays as agreed in the Test plan.
Yes No
Summary of test results for each test.
Conclusion and compliance with acceptance
criteria. Yes No
Yes No
18 Test data file name format consistent with the test See section 2.9 Yes No
plan requirements
© AEMO 2020 | GPS Compliance Assessment and R2 Model Validation Test Plan Template 66