GSW NG01017640 GEN LA7880 00003 - Technical Specifications For Barred Tee - D01
GSW NG01017640 GEN LA7880 00003 - Technical Specifications For Barred Tee - D01
GSW NG01017640 GEN LA7880 00003 - Technical Specifications For Barred Tee - D01
Proprietary Information: This document contains proprietary information and may not be partly or wholly
reproduced without prior written permission from Shell Petroleum Development Company.
Revision Philosophy
All revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03,
etc as required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.
Narrative sections revised from previous approved issues are to be noted in the table
below and/or highlighted in the RH margin (using the appropriate revision status) thus: |
A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding'
the affected areas and the use of a triangle containing the revision status.
Revision History
Page 1 of 27
CONTENTS
1 INTRODUCTION 4
2 GENERAL 7
4 ORDER OF PRECEDENCE 14
5.1 General 15
6 DESIGN REQUIREMENTS 16
6.1 General 16
6.2 Dimensions 16
Page 2 of 27
8 MATERIAL REQUIREMENTS 18
8.1 Manufacture 18
9 WELDING 19
9.1 General 19
10.1 General 20
10.3 Re-Tests 20
11.1 Identification 21
12 QUALITY ASSURANCE 22
12.1 General 22
13 CERTIFICATION 22
Page 3 of 27
1 INTRODUCTION
1.1 Project Description
The Gbaran-026 Hook-up and F1B/ F22B Gas Development opportunity is part of SPDC’s Single
Wells opportunities portfolio for quick win delivery of gas to fill the gap in Shell JV export gas
value stream (NLNG T1 -T6) from 2020 at competitive CAPEX. The opportunity entails
developing 284.9 Bscf of gas and 11.7 MMstb of condensate from the Gbaran F1000B and F2200B
reservoirs. The GBAR-026 well, drilled in 2015, is part of SPDC’s campaign to explore and develop
High Pressure High Temperature (HPHT) reservoirs around the Gbaran Area in a bid to increase
its hydrocarbon resource volumes and increase the robustness of gas supply to NLNG by early
hook-up to production through the Gbaran CPF. The drilling of Gbaran-026 confirmed the
presence of hydrocarbon in the F2200B reservoir and was also used to appraise the already proven
F1000B reservoir. It is proposed to drill a second NAG well (Gbaran-F1F22) from the Gbaran
23/25/26 well cluster to carry out a 6-month Extended Well Test (EWT) of the F2200B reservoir
through the Gbaran CPF. Data gathered during the EWT will be used to develop and secure
approval for the F2200B RDP. Subsequently, the F2200B reservoir will be fully developed by
producing through the Gbaran CPF. Once F2200B is depleted, the Gbaran-F1F22 well will be re-
completed to target the crestal volumes on F1000B.
The Gbaran-026 Hook-up and F1B/ F22B Gas Development opportunity involves the following:
Drilling of GBAR-F1F22 NAG well from the GBAR-23/25/26 well cluster and initial
completion on F2200B to develop 49 Bscf of gas and 1.6 MMstb of condensate. When
F2200 is depleted, the well will be re-completed on the shallower F1000B reservoir to
develop 160 Bscf of gas and 5 MMstb of condensate.
Completion of GBAR-026 on the F1000B reservoir to develop 79.5 Bscf of gas and 2.7
MMstb of condensate.
Laying of 10” x 5km bulk line from the Gbaran well cluster to Gbaran CPF and tie-in of
the 2 wells (GBAR-026 and BGAR-F1F22) to the bulk line via standardized HPHT well
hook-up system for production through the CPF.
Laying of 48core FO cable from CPF to Gbaran NAG FAR and from the FAR to the
Hook-up skids
Page 4 of 27
Page 5 of 27
Page 6 of 27
Page 7 of 27
Page 8 of 27
Page 9 of 27
Page 10 of 27
Page 11 of 27
Page 12 of 27
Page 13 of 27
4 ORDER OF PRECEDENCE
All materials to be supplied under this specification shall conform to the requirements specified
herein. In the event of any conflict between specification, data sheets, codes and standards, then
the following precedence shall apply.
This Specification
Other Relevant Project Specification
International Code and Standards.
National/ Local Codes and Standards
Nigerian Government Legislation
Project Scope of Work
Shell DEPs and Standards
Page 14 of 27
Page 15 of 27
6 DESIGN REQUIREMENTS
6.1 General
Tees shall be designed to meet the requirements of ASME B31.8. Tees shall be designed to code
to withstand the forces and moments equivalent to the base pipe.
All tees shall be barred design, suitable for pigging in either direction through the run of the tee.
Reference shall be made to APPENDIX 1 & 2, – Barred Tee Design Requirements.
The bars shall be of the same material type and grade as the tee itself and shall be welded into the
branch of the tee via a carrier ring that is seal welded. Bars shall be full penetration welded into the
outlet branch after fabrication of the tee.
The design of the bars and their attaching welds shall be such that they can sustain a bi-directional
uniformly distributed load equivalent to the full test pressure of the tee multiplied by the internal
cross sectional area of the branch piping. (This load is equivalent to that which would be seen if a
pig were to become trapped in the branch of the tee with full test pressure on one side and no
pressure on the other).
Where required, the bars shall be recessed into the branch of the tee to sufficient depth to prevent
their hindering the passage of a pig but at the same time, at not such a depth as to allow a pig to
rotate and become trapped in the tee.
6.2 Dimensions
Dimensions and tolerances shall be in accordance with ASME B16.9, unless modified by the data
sheet. The diameters and wall thicknesses of the tee at each weld end shall be as shown on the data
sheet.
The tolerance on the nominal internal diameter, defined as the nominal external diameter minus
twice the nominal wall thickness, shall meet the requirements of ASME B16.9. Out of roundness
shall be assessed using an internal ring gauge of diameter 5mm less than the nominal internal
diameter and of length equal to 1.5 times its diameter shall be assumed.
Page 16 of 27
Page 17 of 27
8 MATERIAL REQUIREMENTS
8.1 Manufacture
Forged tees shall be manufactured by a hot forging process in accordance with ASTM A815 UNS
S31803 and shall be suitable for welding to line pipe manufactured in accordance with API 5LC.
Tees shall be forged into shape such that finishing of the forgings may be achieved with the
minimum of machining.
Unless otherwise agreed by the COMPANY, all tees shall be from the same heat (cast) of steel and
the same heat treatment batch.
Materials used in the manufacture of the tees may be forged or seamless carbon steel pipe material.
Steels shall be made from a basic oxygen process or electrical arc furnace method. Only fully killed
fine grain steels shall be used. The steel shall be of carbon or carbon manganese based composition.
The mechanical testing schedule and specimen location shall be as agreed by the COMPANY. The
mechanical properties of the material shall be as follows:
Yield Strength 448N/mm2 (minimum)
Tensile Strength 620N/mm2 (minimum)
Elongation % of 50mm specimen 25% (minimum)
The testing procedure shall be in accordance with ASTM A370.
The impact toughness of the tees shall be determined by Charpy V-notch (CVN) impact testing in
accordance with ASTM A370, using full-size specimens where possible. Three Charpy specimens
shall be taken from the parent metal at locations agreed by the COMPANY.
The impact test temperature shall be lower than or equal to the minimum design temperature, as
specified in the data sheet.
For approval testing, specimen location and orientation shall be longitudinal.
For production quality control testing, specimens may be taken from forging prolongations. The
specimen orientation shall be tangential.
The Charpy energy acceptance criterion shown is for full size 10mm x 10mm specimens. Where
sub-size specimens are used, the energy acceptance criteria may be adjusted proportionally.
Page 18 of 27
9 WELDING
9.1 General
Welds, including welding of guide bars in tees, shall be made according to procedures qualified to
the requirements of ASME IX.
All welds on barred tees for guide bars and attaching guide bars to the branch of the tee shall be
full penetration and continuous around the guide bars.
Page 19 of 27
10.3 Re-Tests
If any of the results does not conform to the specified requirements, the SUPPLIER may heat-
treat the batch forgings again provided they have COMPANY acceptance. The material shall then
be tested in accordance with this Specification.
Page 20 of 27
Page 21 of 27
12 QUALITY ASSURANCE
12.1 General
All certification, test results, reports, and any other documentation submitted to the COMPANY
relative to the inspection system and results of inspections shall be in English language.
The CONTRACTOR shall establish and maintain a fully documented Quality System in
accordance with ISO 9001.
13 CERTIFICATION
A certification to BS EN 10204 3.2 is required, containing, as a minimum:
Purchaser Order Number
Purchase Order Item Number/Sub-item Number
SUPPLIER Identification
Nominal Size
Material Designation and Specification Number
Heat or Melt Number
Steel Making Process
Heat Treatment
Results of all Specified Tests and Examinations
Welding Procedures
Page 22 of 27
Page 23 of 27
Page 24 of 27
Page 25 of 27
Page 26 of 27
Page 27 of 27