Sabp J 900
Sabp J 900
Sabp J 900
Contents
1 Introduction ...................................................... 2
2 Conflicts with Mandatory Standards ................ 2
3 References ...................................................... 2
4 Definitions ........................................................ 3
5 Background ..................................................... 3
6 FF Segment Components................................ 4
7 Recommendations ........................................... 6
Revision Summary ................................................ 9
1 Introduction
1.1 Purpose
The objective is to establish best practices and guidelines for commissioning the
physical layer components of a FOUNDATION™ fieldbus (FF) Segment.
1.2 Scope
This best practice provides information and guidelines for the proper
commissioning of Foundation fieldbus physical layers in Process Automation
Systems. For the purpose of this SABP, a FOUNDATION™ fieldbus physical
layer includes the following: Fieldbus devices, (i.e., transmitters, transducers,
etc.), wiringblock, terminators, bulk power supply (24 V DC), FF power supply,
and H1 FF interface cards.
1.3 Disclaimer
This SABP is not intended to detail all aspects of the configuration and does not
include adequate information to enable it to be used as an instruction or user
manual.
In the event of a conflict between this Best Practice and other Mandatory Saudi Aramco
Engineering Requirements, the Mandatory Saudi Aramco Engineering Requirements
shall govern.
3 References
Specific sections of the following documents are referenced within the body of the
document. Material or equipment supplied to this best practice, shall comply with the
referenced sections of the latest edition of these specifications. Where specific sections
are not referenced, the system shall comply with the entire referenced document.
Page 2 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
4 Definitions
This section contains definitions for acronyms, abbreviations, words, and terms as they
are used in this document.
BPS Bulk Power Supply (24 V DC)
DCS Distributed Control System
FF FOUNDATION™ fieldbus
FFPS FOUNDATION™ fieldbus Power Supply
H1 FOUNDATION™ fieldbus Interface Card
HSE High Speed Ethernet
I.S. Intrinsically Safe
P&CSD Process & Control Systems Department
PELV A protective extra low voltage system which is not electrically separated
from earth but which otherwise satisfies the requirements for SELV.
SELV A safety extra low voltage system (i.e., normally not exceeding 50 V AC and
120 V ripple free DC) electrically separated from earth and other systems in
such a way that a single fault cannot give a rise to an electrical shock.
Segment A single network consisting of fieldbus devices, BPS, FFPS, Terminators,
WB, and H1 Interface Cards.
WB Wiringblock (Megablock, or Segment Protector)
5 Background
Saudi Aramco has been installing Foundation fieldbus (FF) systems since 2001, and
experience shows higher reliability is associated with proper physical layer
Page 3 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
6 FF Segment Components
6.1.2 Field device shield conductor shall be cut and insulated with heat shrink
sleeve at the field instrument per SAES-J-902.
6.1.3 FF Motor Operated Valves (MOVs) and other non-I.S. devices shall be
grouped together in a field junction box and shall not be mixed with
other two-wire FF devices. Live-workability is not allowed.
Page 4 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
6.3 FF Cables
6.3.1 FF spur cables shall be Type A per SAES-J-904. The outer jacket color
shall be light blue to indicate intrinsic safety as opposed to previous
orange color in non-incendive installations.
6.3.2 Spur cables shall be mechanically protected. They are typically armored
and placed on a secondary cable tray (i.e., Channel Type).
6.3.3 Spur cable voltage resistance test shall be conducted to ensure insulation
resilience at either 300 V ac for PLTC/ITC type cables or 600 V ac for
TC type cables.
6.3.4 Trunk cable outer jacket color shall be orange and maybe armored
suitable for direct burial.
6.3.6 The total length of any segment shall not exceed 1900 meters. Each spur
shall not exceed 120 meters.
6.3.7 Home-run cable trays should be covered all the time to protect cables
from sunlight. Sunlight could potentially cause signal degradation.
Page 5 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
6.4.1 FF power supplies shall have voltage limitation (i.e., embedded zener
diode) to limit the voltage to meet the intrinsic safety requirements.
6.4.2 They shall be rated for 24 V DC and shall carry the FF logo.
6.5.2 They shall not be encapsulated inside an HSE card casing. H1 cards run
at 31.25 Kb/sec, whereas HSE could run at either 10 or 100 Mb/sec.
6.5.3 The connection from H1 cards to the DCS controller shall be through the
baseplate and shall not go through any network switches.
7 Recommendations
Per the relevant clause in IEC60079-14 (Section 14), IS type ‘ic’ may be utilized
while maintaining the nL architecture. This installation can be allowed
providing that proper entity parameters calculations between associated
apparatus (i.e., spur block or wiringblock) and field apparatus (field devices) are
done and matched. The safety parameters calculations shall consist of voltage,
current, capacitance, and inductance as follows:-
Page 6 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
7.3.1 The segment commissioning form shall be used and saved for each
segment before powering up that segment. This test will reveal any pre-
commissioning issues such as cable insulation damage, grounding
problems, or inferior cable qualities. The use of FBT-6 or P&F handheld
tester is recommended as it would reveal wiring problems as well as
signal quality. The recorded figures should be saved for future
comparisons. During turn-arounds, it is advisable to check signal quality
and compare with previous values. If the signal quality has deteriorated
Page 7 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
7.3.2 Typical commissioning forms and physical layer measurement report are
attached below for reference only.
Page 8 of 9
Document Responsibility: Instrumentation Standards Committee SABP-J-900
Issue Date: 30 May 2016
Next Planned Update: TBD FOUNDATION™ fieldbus (FF) Physical Layer Commisioning
Revision Summary
30 May 2016 New Saudi Aramco Best Practice that provide guidelines for the proper commissioning of the
FOUNDATION™ fieldbus (FF) physical layers in Process Automation Systems.
Page 9 of 9