Sr.

Particulars SIZE Area Unit Rate Amount


No
CIVIL WORK
Breaking, Tiling, Plaster
Precession Breaking of partial kitchen wall to covert into open Kitchen &
1 8.83 2.2 19 Sq.Ft 1,250 24283
internal tiling @ 1200/- per Sq.ft
2 New White quartz material platform 10 3.5 35 2 1070 74900
3 Kitchen entry gate & framing 1 1 1 15000 15000
Plastering for all room @ total areas of 1800-2000 sqft
(Breaking Old gypsum coat, New Cement plaster, POP on walls)
4 (Breaking Coat - 35 psqft 215 8.50 1800 Sq.Ft 185 338088
Plaster - 120 psqft
POP wall - 40 psqft
5 Shifting of Bathroom wall 7 4.00 28 Sq.Ft 1000 28000
6 Tilling work for Bedroom 1 internal walls 17.00 8.5 145 715 103318
7 Tilling work for Bedroom 2 internal walls 20.00 8.5 170 715 121550
Breaking of Bathroom wall to bring Washbasin out of bathroom near
8 7.30 5.4 39 Sq.Ft 1,200 47304
dining area@ 1200/- per Sq.ft
New washbasin work including platform, electrical, plumbing & piping &
9 1 1 1 25000 25000
Faucets
10 American Standard Washbasin 1 1 1 28000 28000
11 Marble frames for all doors 1 4 4 11500 46000

TOTAL AMOUNT 851442


NOTES
Above measurement are for referance purpose only final measurement may vary afte the completion 1 of site and the same may
be considered for hnal bill purpose.
All the Tiles and Granite rates are calullated with base price which has been mention any increase in 2 Tiles and Granite cost the
difference rate will be born by client.
3 Above rate are Excluding GST .