Assignment7-Project Management (CO5)

Subject: Operation Research (3151910) Semester: 5th

Year : 2022-23

1. Whatisthemeaningfloatinprojectmanagement?Statethevarious typesfloat
2. WhatisCPMandPERT.? Discusssignificanceof usingCPMandPERT.
3. Define event, activity, precede activity, successor activity, dummy activity with respect to
CPM/PERT
4. What are the 3 time estimates? How are the expected duration of a project, and its
standard deviation calculated?
5. A project consists of 10 activities for which the relevant data are given below:
Activity PrecedingActivity Duration(Hours)
A -- 0.5
B A 1
C B 1.5
D B 1.4
E D 1.2
F B 0.8
G F 1.0
H C,E,G 0.4
I H 1.4
J I 0.5

a. Draw the network and find the project completion time.


b. Calculate Total float for each of the activities.
6. The data for a network is given below.

Activity TimesinDays Directcost


Normal Crash Normal Crash
1-2 10 4 2300 3100
1-3 12 3 1700 2600
2-4 20 10 2400 4400
3-5 10 9 1100 1500
4-5 6 6 800 800

Considering indirect cost as Rs.1000 per/day.


(i) Find the normal duration of project completion and corresponding cost.
(ii)What can be minimum compression of project and corresponding total time?
(iii)Find the optimal duration of project completion and related cost

7. A construction company is preparing a PERT network for laying the foundation of a new
artmuseum.Giventhefollowingsetofactivities,theirpredecessorrequirementsandthreetimeesti
matesofcompletiontime:
Activity Predecessors TimesinWeeks
Optimistic Pessimistik Most Likely
A None 2 4 3
B None 8 8 8
C A 7 11 9
D B 6 6 6
E C 9 11 10
F C 10 18 14
G C, D 11 11 11
H F,G 6 14 10
I E 4 6 5
J I 3 5 4
K H 1 1 1
(a) Draw the PERT network.
(b) What is the expected time of the duration of the project?

8. A small project involves 7 activities, and their time estimates are listed in the following table.
EstimatedDuration(Weeks)
Activity Optimistic Mostlikely Pessimistic
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15

(a) Draw the network diagram of the activities in the project.


(b) Find the expected duration and variance for each activity.What is the expected project
length?
(c) What is the probability that the project will be completed at least 4 weeks earlier than
expected time?

9. Tasks A to I constitutes a project in which the precedence relationships are A< D; A<E; B
<F; D< F; C< G; C<H, F< I; G< I.
Time in day for each task is as follows:
Task A B C D E F G H I
Time 8 10 8 10 16 17 18 14 9
Draw the network to represent the project and find out total float of each activity and identify
critical path
10. The details of activity and duration are shown below:
Activity A B C D E F G
Dependson - A A A B,C C,D E,F
Time,Days 10 5 4 7 6 4 7
Find:
1. Draw a network diagram
2. Find the critical path
3. Project duration

11. Draw the network diagram for given relationship of activities

Activity A B C D E F G H
Predecessor - - A B B C D E,F,G