Estimated Cost of Septic Tank

S.No. Description Nos. L (Ft) B (Ft) H (Ft) Qty. Unit Factor Qty. Unit Brick Cement Sand Grit steel Cost in Rs.
1 Bottom Brick Soling 1 13.083 7.583 99.215 Sqft 10.764 9.217 Sqm 368.7
2 Bottom RCC M:20 1 12.417 6.917 0.5 42.941 Cft 35.315 1.216 M3 9.728 24.319 36.479
3 RCC Beam in 1st Compartment 1 4 0.75 0.75 2.25 Cft 35.315 0.064 M3 0.51 1.274 1.911
4 RCC M : 20 Top Cover 1 11 5.5 0.5 30.25 Cft 35.315 0.857 M3 6.853 17.132 25.698
5 Outer Brick Wall Bottom 14" 1 30 1.167 1.5 52.5 Cft 35.315 1.487 M3 683.85 2.765 13.826
6 Outer Brick Wall 9" 1 30 5.5 0.75 123.75 Cft 35.315 3.504 M3 1611.94 6.518 32.589
7 Mid Wall 1st compartment 1 4 0.75 4.75 14.25 Cft 35.315 0.404 M3 185.62 0.751 3.753
8 Mid Wall 2nd compartment 1 4 0.75 5.833 17.5 Cft 35.315 0.496 M3 227.95 0.922 4.609
9 Tor Steel Bottom Beam Dia 10 mm 6 4 24 Ft 0.3048 7.315 Mtr 4.5078
10 Tor Steel Bottom Beam Dia 8 mm 8 3.113 24.9 Ft 0.3048 7.59 Mtr 2.9932
11 Tor Steel Bottom Beam Dia 12 mm 23 5.5 126.5 Ft 0.3048 38.557 Mtr 23.7599
12 Tor Steel Bottom Beam Dia 10 mm 12 11 132 Ft 0.3048 40.234 Mtr 24.793
13 Total qty. 3078.05 28.05 97.5 64.09 56.05
14 Rate 8 450 112 100 65
15 Amount 24624.42 12620.35 10920.13 6408.75 3643.5 58217.14