A Maerials 64,078,113
B Labour 19,813,635
83.892 Million
Abstract of Cost
4 Brick work for plinth with (1:1:6) composite motor cft 805.00 5,325,089 cft 6,615
5 Plastering work plinth with (1:1:6) composite motor (1/2" tk) sft 596.00 454,854 sft 763
6 (1:2:4) cement concrete work up to plinth cft 570.72 5,120,109 cft 8,971
8 4'' tk (1:3:6) Lean concrete work cft 293.33 2,481,469 cft 8,460
9 1 1\2" tk (1:2:4) Cement concrete work for floor topping sft 110.00 139,167 sft 1,265
10 (1:2:4) Cement concrete work for superstructure cft 1829.28 15,743,893 cft 8,607
11 1st Class brick work with (1:1:6) cement motor for superstructure (4 1/2'' tk) cft 1270.31 8,395,134 cft 6,609
12 1/2'' tk plastering work with (1:1:6) composite motor for superstructure sft 7836.00 5,979,686 sft 763
13 1 1/2'' tk (1:2:4) cement concrete work for floor topping sft 2449.50 3,096,672 sft 1,264
14 Scaffolding work ( for two Layer) sft 4092.00 1,931,920 sft 472
A Maerials
9 8' x 4' Plywood (3 times used) sheet 36.01 18,000 sheet 648,146
20 Seperators No 1502.95 No -
64,078,113
Bill of Quantity
B Labour
19,813,635
Total 83,891,748
83.892 million
Builder's Estimate
595,400
3,428,533
2,435,404
4 Brick work for plinth with (1:1:6) composite motor Cft 805
5,325,089
Sft 596 -
454,854
Builder's Estimate
5,120,109
144,345
2,481,469
sft 110
139,167
15,743,893
11 1st Class brick work with (1:1:6) cement motor for superstructure (4 1/2'' tk)
Cft 1270.31
8,395,134
Sft 7836
5,979,686
sft 2449.50
3,096,672
1,931,920
Builder's Estimate
8' x 4' Plywood (3 times used) sheet 36.01 18,000 sft 648,146
Seperators No 1502.95 - No -
5,460,903
16 Reinforcing Work
For Sub-structure
Footing
Column
Beam
Slab
For Superstructure
Column
Beam
Slab
22,493,896
Builder's Estimate
665,275
Total 83,891,748
83.892 million
Details of Measurements
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
Retaining wall (long wall) 3 40' 0'' 2' 6'' 2' 6'' 750
Retaining wall (Short wall) 5 22' 0'' 2' 6'' 2' 6'' 687.5
2 Hardcore Filling
Retaining wall (long wall) 3 40' 0'' 2' 6'' 0' 9'' 225
Retaining wall (Short wall) 5 22' 0'' 2' 6'' 0' 9'' 206.25
Retaining wall (long wall) 3 40' 0'' 2' 6'' 0' 3'' 75
Retaining wall (Short wall) 5 22' 0'' 2' 6'' 0' 3'' 68.75
Retaining wall (long wall) 3 40' 0'' 0' 9'' 4' 8'' 420
Retaining wall (short wall) 5 22' 0'' 0' 9'' 4' 8'' 385
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
Column
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
FB1
For 12' span 3 11' 0'' 0' 10'' 0' 14'' 32.1
For 11' span 5 10' 0'' 0' 10'' 0' 14'' 48.6
For 9' span 3 8' 0'' 0' 10'' 0' 14'' 23.3
For 8' span 2 7' 0'' 0' 10'' 0' 14'' 13.6
FB2
FB1
For 12' span 3 11' 0'' 0' 10'' 0' 14'' 32.1
For 11' span 5 10' 0'' 0' 10'' 0' 14'' 48.6
For 9' span 3 8' 0'' 0' 10'' 0' 14'' 23.3
For 8' span 2 7' 0'' 0' 10'' 0' 14'' 13.6
FB2
FB1
For 12' span 3 11' 0'' 0' 10'' 0' 14'' 32.1
For 11' span 3 10' 0'' 0' 10'' 0' 14'' 29.2
For 10' span 3 9' 0'' 0' 10'' 0' 14'' 26.25
For 8' span 3 7' 0'' 0' 10'' 0' 14'' 20.4
FB2
Slab
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
11 1st Class brick work with (1:1:6) cement motor for superstructure (4 1/2'' tk)
Ground floor
For 12' span 3 11' 0'' 0' 4.5'' 10' 0'' 123.8
For 10' span 5 9' 0'' 0' 4.5'' 10' 0'' 168.8
For 8' span 2 7' 0'' 0' 4.5'' 10' 0'' 52.5
532.5 cft
Doors and windows deduction
MD 1 5' 0'' 0' 4.5'' 9' 0'' 16.9
108.5 cft
First Floor
For 12' span 3 11' 0'' 0' 4.5'' 10' 0'' 123.8
For 11' span 3 10' 0'' 0' 4.5'' 10' 0'' 112.5
For 10' span 8 9' 0'' 0' 4.5'' 10' 0'' 270
For 8' span 2 7' 0'' 0' 4.5'' 10' 0'' 52.5
671.3 cft
157.3 cft
Details of Measurements
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
Second Floor
For 12' span 2 11' 0'' 0' 4.5'' 10' 0'' 82.5
For 11' span 3 10' 0'' 0' 4.5'' 10' 0'' 112.5
For 10' span 3 9' 0'' 0' 4.5'' 10' 0'' 101.25
For 8' span 2 7' 0'' 0' 4.5'' 10' 0'' 52.5
440.25 cft
107.9 cft
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
Second Floor
15 Carpentary work
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
Roof beam
Measurements
No. Particles No. Contents Dedu; Total Remark
L B H
Slab
17 Chowket work(6''x3'')
1 Footing
F1 4.0' 5 8 40 160.00
4.0' 5 8 40 160.00
F2 4.0' 2 8 16 64.00
4.0' 2 8 16 64.00
F3 6.0' 6 12 72 432.00
3.0' 6 6 36 108.00
F4 7.0' 2 14 28 196.00
4.0' 2 8 16 64.00
1248.00
1301.66 Lbs
2 Column
1560.00
1627.08 Lbs
3 Beam
GB 22.0' 5 6 30 660.00
40.0' 3 6 18 720.00
1380.00
1439.34 Lbs
9.0' 1 13 13 117.00
243.00
91.37 Lbs
Rebar Work
Superstructure
6 Column
Gf to 1st 11.0' 15 8 120 1320.00
C1
1st to 2nd 11.0' 15 8 120 1320.00
C1
2nd to roof 11.0' 9 8 72 792.00
3432.00
3579.58 Lbs
7 Beam
1st floor
FB1 222.0' 1 6 6 1332.00
FB2 39.0' 1 6 6 234.00
2nd floor
FB1 222.0' 1 6 6 1332.00
FB2 39.0' 1 6 6 234.00
roof floor
FB1 126.0' 1 6 6 756.00
FB2 37.0' 1 6 6 222.00
4110.00
4286.73 Lbs
Rebar Work
8 Slab
1st + 2nd floor 44.5' 4 67 268 11926.00
22.0' 4 33 132 2904.00
Roof floor 22.0' 2 33 66 1452.00
25.5' 2 39 78 1989.00
18271.00
7900.38 Lbs
9 Stirrup & Tie
C1 4.5' 39 22 858 3861.00
FB1 4.5' 1 1140 1140 5130.00
FB2 4.0' 1 230 230 920.00
9911.00
2586.77 Lbs