FB Part Bill - 04 of Protik Fine Ceramics Factory Building
FB Part Bill - 04 of Protik Fine Ceramics Factory Building
FB Part Bill - 04 of Protik Fine Ceramics Factory Building
01
BILL OF AMOUNT (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH WIDTH HEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft. ft.
1 EARTH EXCAVATION WORK (UP TO 1.5m DEPTH)
for PILE CAP PC2 2 9.25 5.33 3.91 385.55
for GRADE BEAM GB1 (6500mm.) 4 21.33 3.25 1.5 415.94
for GRADE BEAM GB2 (7118mm.) 2 23.33 3.25 1.5 227.47
for GRADE BEAM GB2 (5103mm.) 1 16.75 3.25 1.5 81.66
for GRADE BEAM GB2 (5068mm.) 2 16.66 3.25 1.5 162.44
for GRADE BEAM GB2 (4983mm.) 3 16.33 3.25 1.5 238.83
for GRADE BEAM GB3 (9950mm.) 2 32.66 3.25 1 212.29
for GRADE BEAM GB3 (7500mm.) 2 24.66 3.25 1 160.29 1884.45 CFT.
SL. NAME OF ITEM ITEM LENGTH WIDTH QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft.
2 LEVELING & DRESSING WORK
for PILE CAP PC2 2 9.25 5.33 98.61
for FLOOR 1 47 99.5 4676.50
1 52 17 884.00
1 41.5 106.5 4419.75
1 52 23.5 1222.00
for MACHINERY STORAGE 1 41.25 41 1691.25
1 83.5 57.5 4801.25
1 68.25 32.5 2218.13 20011.48 SFT.
SL. NAME OF ITEM ITEM LENGTH WIDTH QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft.
3 BRICK FLAT SOLING WORK
for FLOOR 1 47 99.5 4676.50
1 52 17 884.00
1 41.5 106.5 4419.75
1 52 23.5 1222.00
for MACHINERY STORAGE 1 41.25 41 1691.25
1 83.5 57.5 4801.25
1 68.25 32.5 2218.13 19912.88 SFT.
SL. NAME OF ITEM ITEM LENGTH WIDTH QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft.
4 C.C. CASTING WORK
for PILE CAP PC2 2 8.08 3.66 59.15 59.15 SFT.
SL. NAME OF ITEM ITEM LENGTH WIDTH QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft.
5 POLYTHENE LAYING WORK
for PILE CAP PC2 2 9.25 5.33 98.61 98.61 SFT.
PAGE NO. 03
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH WIDTH PC'S. QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft.
6A WOODEN SCAFFOLDING WORK (UP TO 10'-0" HEIGHT)
for COLUMN C1 (6000mm.) 2 7 6 1 84.00
for COLUMN C1 (5400mm.) 4 7 6 1 168.00
for COLUMN C1 (4700mm.) 1 7 6 1 42.00
for COLUMN C1A (5440mm.) 1 7 6 1 42.00
for COLUMN C1A (5400mm.) 3 7 6 1 126.00
for COLUMN C1A (4700mm.) 6 7 6 1 252.00
for COLUMN C2 (6000mm.) 17 7 6 1 714.00
for COLUMN C9 (7000mm.) 4 7 6 1 168.00
for COLUMN C9 (6000mm.) 13 7 6 1 546.00
for TIE BEAM TB3 (7500mm.) 3 24.66 8 1 591.84
additional 9 24.66 8 1 1775.52
for CORBEL CR2 10 9 8 1 720.00
for CORBEL CR3 10 9 8 1 720.00 5949.36 SFT.
6B WOODEN SCAFFOLDING WORK (MORE THAN 10'-0" HEIGHT)
for COLUMN C1 (6000mm.) 2 7 6 1 84.00
2 6 5 1 60.00
for COLUMN C1 (5400mm.) 4 7 6 1 168.00
4 6 5 1 120.00
for COLUMN C1 (4700mm.) 1 6 5 1 30.00
for COLUMN C1A (5440mm.) 1 7 6 1 42.00
1 6 5 1 30.00
for COLUMN C1A (5400mm.) 3 7 6 1 126.00
3 6 5 1 90.00
for COLUMN C1A (4700mm.) 6 6 5 1 180.00
for COLUMN C2 (6000mm.) 17 7 6 1 714.00
17 6 5 1 510.00
for COLUMN C9 (7000mm.) 4 7 6 1 168.00
4 6 5 1 120.00
for COLUMN C9 (6000mm.) 13 7 6 1 546.00
13 6 5 1 390.00
for TIE BEAM TB3 (7500mm.) 3 24.66 9 1 665.82
additional 6 24.66 9 1 1331.64
for CORBEL CR2 10 9 8 1 720.00
for CORBEL CR3 10 9 8 1 720.00 6815.46 SFT.
PAGE NO. 04
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH WIDTH HEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft. ft.
7A RCC CASTING BY MIXER MACHINE (UP TO 10'-0" HEIGHT)
for PILE CAP PC2 2 7.54 3.13 2.16 101.95
for PADESTAL COLUMN C2 3 1.83 1.5 5.25 43.23
for GRADE BEAM GB1 (6500mm.) 4 20 1.16 1.66 154.05
for GRADE BEAM GB2 (7118mm.) 2 22 1 1.66 73.04
for GRADE BEAM GB2 (5103mm.) 1 15.41 1 1.66 25.58
for GRADE BEAM GB2 (5068mm.) 2 15.33 1 1.66 50.90
for GRADE BEAM GB2 (4983mm.) 3 15 1 1.66 74.70
for GRADE BEAM GB3 (9950mm.) 2 31.33 1 1.66 104.02
for GRADE BEAM GB3 (7500mm.) 2 23.33 1 1.66 77.46
for PADESTAL COLUMN C1A (@GB1) 1 1.83 1.5 1.66 4.56
for PADESTAL COLUMN C2 (@GB2) 7 1.83 1.5 1.66 31.90
for PADESTAL COLUMN C3 (@GB1) 3 3 1.83 1.66 27.34
for PADESTAL COLUMN C4 (@GB1) 1 3 1.83 1.66 9.11
for PADESTAL COLUMN C9 (@GB3) 2 1.83 1.5 1.66 9.11
for COLUMN C1 (6000mm.) 2 1.66 1.33 10 44.16
for COLUMN C1 (5400mm.) 4 1.66 1.33 10 88.31
for COLUMN C1 (4700mm.) 1 1.66 1.33 10 22.08
for COLUMN C1A (5440mm.) 1 1.66 1.33 10 22.08
for COLUMN C1A (5400mm.) 3 1.66 1.33 10 66.23
for COLUMN C1A (4700mm.) 6 1.66 1.33 10 132.47
for COLUMN C2 (6000mm.) 17 1.66 1.33 10 375.33
for COLUMN C9 (7000mm.) 4 1.66 1.33 10 88.31
for COLUMN C9 (6000mm.) 13 1.66 1.33 10 287.01 1912.92 CFT.
7B RCC CASTING BY MIXER MACHINE (MORE THAN 10'-0 HEIGHT)
for COLUMN C1 (6000mm.) 2 1.66 1.33 9.66 42.65
for COLUMN C1 (5400mm.) 4 1.66 1.33 7.75 68.44
for COLUMN C1 (4700mm.) 1 1.66 1.33 5.41 11.94
for COLUMN C1A (5440mm.) 1 1.66 1.33 7.83 17.29
for COLUMN C1A (5400mm.) 3 1.66 1.33 7.75 51.33
for COLUMN C1A (4700mm.) 6 1.66 1.33 5.41 71.67
for COLUMN C2 (6000mm.) 17 1.66 1.33 9.66 362.56
for COLUMN C6 (2100mm.) 1 1.66 1.33 6.91 15.26
for COLUMN C9 (7000mm.) 4 1.66 1.33 10 88.31
for COLUMN C9 (6000mm.) 13 1.66 1.33 9.66 277.26
for COLUMN C9 (2100mm.) 2 1.66 1.33 6.91 30.51
for CORBEL CR3 10 3.25 1.5 3.25 158.44 1195.66 CFT.
PAGE NO. 05
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH WIDTH HEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft. ft.
7C RCC CASTING BY MIXER MACHINE (MORE THAN 20'-0 HEIGHT)
for COLUMN C9 (7000mm.) 4 1.66 1.33 3 26.49
for CORBEL CR1 4 11 1.5 3.25 214.50
for CORBEL CR2 10 3.5 1.5 3.25 170.63
for TIE BEAM TB3 (7500mm) 3 23.16 1 1.33 92.41
for VALLEY GURDER side wall 6 26.16 0.41 3 193.06
bottom slab 3 23.83 3.75 0.5 134.04 831.13 CFT.
SL. NAME OF ITEM ITEM LENGTH HEIGHT PC'S. QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft.
8A STEEL SHUTTER INSTALLATION WORK (UP 10'-0" HEIGHT)
for COLUMN C1 (6000mm.) 2 3 10 2 120.00
for COLUMN C1 (5400mm.) 4 3 10 2 240.00
for COLUMN C1 (4700mm.) 1 3 10 2 60.00
for COLUMN C1A (5440mm.) 1 3 10 2 60.00
for COLUMN C1A (5400mm.) 3 3 10 2 180.00
for COLUMN C1A (4700mm.) 6 3 10 2 360.00
for COLUMN C2 (6000mm.) 17 3 10 2 1020.00
for COLUMN C9 (7000mm.) 4 3 10 2 240.00
for COLUMN C9 (6000mm.) 13 3 10 2 780.00 3060.00 SFT.
8B STEEL SHUTTER INSTALLATION WORK (MORE THAN 10'-0" HEIGHT)
for COLUMN C1 (6000mm.) 2 3 9.66 2 115.92
for COLUMN C1 (5400mm.) 4 3 7.75 2 186.00
for COLUMN C1 (4700mm.) 1 3 5.41 2 32.46
for COLUMN C1A (5440mm.) 1 3 7.83 2 46.98
for COLUMN C1A (5400mm.) 3 3 7.75 2 139.50
for COLUMN C1A (4700mm.) 6 3 5.41 2 194.76
for COLUMN C2 (6000mm.) 17 3 9.66 2 985.32
for COLUMN C6 (2100mm.) 1 3 6.91 2 41.46
for COLUMN C9 (7000mm.) 4 3 10 2 240.00
for COLUMN C9 (6000mm.) 13 3 9.66 2 753.48
for COLUMN C9 (2100mm.) 2 3 6.91 2 82.92 2818.80 SFT.
8C STEEL SHUTTER INSTALLATION WORK (MORE THAN 20'-0" HEIGHT)
for COLUMN C9 (7000mm.) 4 3 3 2 72.00 72.00 SFT.
PAGE NO. 06
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH WIDTH HEIGHT PC'S. QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. ft. ft.
9A WOODEN SHUTTERING WORK (UP 10'-0" HEIGHT)
for C.C. SHUTTERING OF PC2 2 11.75 0.25 2 11.75
for PILE CAP PC2 2 10.66 2.16 2 92.10
for PADESTAL COLUMN C2 3 3.33 5.25 2 104.90
for GRADE BEAM GB1 (6500mm.) 4 20 4.5 1 360.00
for GRADE BEAM GB2 (7118mm.) 2 22 4.33 1 190.52
for GRADE BEAM GB2 (5103mm.) 1 15.41 4.33 1 66.73
for GRADE BEAM GB2 (5068mm.) 2 15.33 4.33 1 132.76
for GRADE BEAM GB2 (4983mm.) 3 15 4.33 1 194.85
for GRADE BEAM GB3 (9950mm.) 2 31.33 4.33 1 271.32
for GRADE BEAM GB3 (7500mm.) 2 23.33 4.33 1 202.04
for PADESTAL COLUMN C1A (@GB1) 1 2.33 1.66 2 7.74
for PADESTAL COLUMN C2 (@GB2) 7 2.33 1.66 2 54.15
for PADESTAL COLUMN C3 (@GB1) 3 3.66 1.66 2 36.45
for PADESTAL COLUMN C4 (@GB1) 1 3.66 1.66 2 12.15
for PADESTAL COLUMN C9 (@GB3) 2 2.33 1.66 2 15.47 1752.92 SFT.
9B WOODEN SHUTTERING WORK (MORE THAN 10'-0" HEIGHT)
for CORBEL CR3 side part 10 3.25 3.25 2 211.25
10 1.5 3.25 2 97.50
bottom part 10 3.25 1.5 1 48.75
-10 1.66 1.33 1 -22.08 335.42 SFT.
9C WOODEN SHUTTERING WORK (MORE THAN 20'-0" HEIGHT)
for CORBEL CR1 side part 4 11 3.25 2 286.00
4 1.5 3.25 2 39.00
-4 1 1.33 2 -10.64
-4 3.75 0.5 2 -15.00
bottom part 4 11 1.5 1 66.00
-4 1.66 1.33 1 -8.83
for CORBEL CR2 side part 10 3.5 3.25 2 227.50
10 1.5 3.25 2 97.50
bottom part 10 3.5 1.5 1 52.50
-10 1.66 1.33 1 -22.08
for TIE BEAM TB3 (7500mm) side part 3 23.16 1.16 2 161.19
bottom part 3 23.16 1 1 69.48
for VALLEY GURDER side part 6 26.16 3.25 2 1020.24
bottom part 3 23.83 3.75 1 268.09
-3 23.16 1 1 -69.48 2161.47 SFT.
PAGE NO. 07
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH PC'S. WEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. kg/ft.
10A D-FORMED BAR FABRICATION WORK (UP 10'-0" HEIGHT)
for PILE CAP PC2
bottom bar Ø20mm. 2 9.66 7 0.752 101.70
bottom bar Ø12mm. 2 5.25 15 0.271 42.68
top bar Ø16mm. 2 9.66 7 0.482 65.19
top bar Ø12mm. 2 5.25 15 0.271 42.68
chair Ø12mm. 2 5.66 4 0.271 12.27
tie bar Ø12mm. 2 2.83 6 0.271 9.20
for PADESTAL COLUMN C2 (WITHIN THE PART OF PILE CAP)
main bar Ø20mm. 3 8.5 8 0.752 153.41
stirrup Ø10mm. 3 5 17 0.188 47.94
3 3.91 17 0.188 37.49
for GRADE BEAM GB1 (6500mm.) with lapping length
main bar Ø20mm. 4 23.16 2 0.752 139.33
main bar Ø16mm. 4 22.83 5 0.482 220.08
ex. top Ø20mm. 4 14.66 3 0.752 132.29
stirrup Ø10mm. 4 4.75 41 0.188 146.45
separator Ø20mm. 4 1.08 14 0.752 45.48
for GRADE BEAM GB2 (7118mm.) with lapping length
main bar Ø20mm. 2 25.33 3 0.752 114.29
main bar Ø16mm. 2 25 2 0.482 48.20
ex. top Ø20mm. 2 16 3 0.752 72.19
stirrup Ø10mm. 2 4.41 45 0.188 74.62
for GRADE BEAM GB2 (5103mm.) with lapping length
main bar Ø20mm. 1 18.66 3 0.752 42.10
main bar Ø16mm. 1 18.33 2 0.482 17.67
ex. top Ø20mm. 1 11.58 3 0.752 26.12
stirrup Ø10mm. 1 4.41 32 0.188 26.53
for GRADE BEAM GB2 (5068mm.) with lapping length
main bar Ø20mm. 2 18.58 3 0.752 83.83
main bar Ø16mm. 2 18.25 2 0.482 35.19
ex. top Ø20mm. 2 11.58 3 0.752 52.25
stirrup Ø10mm. 2 4.41 32 0.188 53.06
for GRADE BEAM GB2 (4983mm.) with lapping length
main bar Ø20mm. 3 18.25 3 0.752 123.52
main bar Ø16mm. 3 17.91 2 0.482 51.80
ex. top Ø20mm. 3 11.33 3 0.752 76.68
stirrup Ø10mm. 3 4.41 31 0.188 77.10
PAGE NO. 08
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH PC'S. WEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. kg/ft.
for GRADE BEAM GB3 (9950mm.) with lapping length
main bar Ø20mm. 2 34.58 2 0.752 104.02
main bar Ø16mm. 2 34.25 4 0.482 132.07
ex. top Ø20mm. 2 22.25 3 0.752 100.39
stirrup Ø10mm. 2 4.41 64 0.188 106.12
for GRADE BEAM GB3 (7500mm.) with lapping length
main bar Ø20mm. 2 26.5 2 0.752 79.71
main bar Ø16mm. 2 26.16 4 0.482 100.87
ex. top Ø20mm. 2 16.83 3 0.752 75.94
stirrup Ø10mm. 2 4.41 47 0.188 77.93
for PADESTAL COLUMN C1A (@GB1)
main bar Ø20mm. 1 1.66 20 0.752 24.97
stirrup Ø10mm. 1 5 3 0.188 2.82
1 4 3 0.188 2.26
1 3.83 3 0.188 2.16
for PADESTAL COLUMN C2 (@GB2)
main bar Ø20mm. 7 1.66 8 0.752 69.91
stirrup Ø10mm. 7 5 3 0.188 19.74
7 3.91 3 0.188 15.44
for PADESTAL COLUMN C3 (@GB1)
main bar Ø25mm. 3 1.66 20 1.18 117.53
tie bar Ø16mm. 3 6 8 0.482 69.41
stirrup Ø10mm. 3 5.66 3 0.188 9.58
3 4.66 3 0.188 7.88
3 4.66 3 0.188 7.88
for PADESTAL COLUMN C4 (@GB1)
main bar Ø25mm. 1 1.66 16 1.18 31.34
tie bar Ø16mm. 1 6 8 0.482 23.14
stirrup Ø10mm. 1 5.66 3 0.188 3.19
1 4.66 3 0.188 2.63
1 4.66 3 0.188 2.63
for PADESTAL COLUMN C9 (@GB3)
main bar Ø16mm. 2 1.66 12 0.482 19.20
stirrup Ø10mm. 2 5 3 0.188 5.64
2 4 3 0.188 4.51
2 3.83 3 0.188 4.32
PAGE NO. 09
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH PC'S. WEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. kg/ft.
for COLUMN C1 (6000mm.) with lapping length
main bar Ø20mm. 2 12.75 12 0.752 230.11
main bar Ø16mm. 2 12.25 2 0.482 23.62
stirrup Ø10mm. 2 5 23 0.188 43.24
2 4 23 0.188 34.59
2 3.83 23 0.188 33.12
for COLUMN C1 (5400mm.) with lapping length
main bar Ø20mm. 4 12.75 12 0.752 460.22
main bar Ø16mm. 4 12.25 2 0.482 47.24
stirrup Ø10mm. 4 5 23 0.188 86.48
4 4 23 0.188 69.18
4 3.83 23 0.188 66.24
for COLUMN C1 (4700mm.) with lapping length
main bar Ø20mm. 1 12.75 12 0.752 115.06
main bar Ø16mm. 1 12.25 2 0.482 11.81
stirrup Ø10mm. 1 5 23 0.188 21.62
1 4 23 0.188 17.30
1 3.83 23 0.188 16.56
for COLUMN C1A (5440mm.) with lapping length
main bar Ø20mm. 1 12.75 20 0.752 191.76
stirrup Ø10mm. 1 5 23 0.188 21.62
1 4 23 0.188 17.30
1 3.83 23 0.188 16.56
for COLUMN C1A (5400mm.) with lapping length
main bar Ø20mm. 3 12.75 20 0.752 575.28
stirrup Ø10mm. 3 5 23 0.188 64.86
3 4 23 0.188 51.89
3 3.83 23 0.188 49.68
for COLUMN C1A (4700mm.) with lapping length
main bar Ø20mm. 6 12.75 20 0.752 1150.56
stirrup Ø10mm. 6 5 23 0.188 129.72
6 4 23 0.188 103.78
6 3.83 23 0.188 99.37
for COLUMN C2 (6000mm.) with lapping length
main bar Ø20mm. 17 12.75 8 0.752 1303.97
stirrup Ø10mm. 17 5 23 0.188 367.54
17 3.91 23 0.188 287.42
PAGE NO. 10
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH PC'S. WEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. kg/ft.
for COLUMN C9 (7000mm.) with lapping length
main bar Ø16mm. 4 12.25 12 0.482 283.42
stirrup Ø10mm. 4 5 23 0.188 86.48
4 4 23 0.188 69.18
4 3.83 23 0.188 66.24
for COLUMN C9 (6000mm.) with lapping length
main bar Ø16mm. 13 12.25 12 0.482 921.10
stirrup Ø10mm. 13 5 23 0.188 281.06
13 4 23 0.188 224.85
13 3.83 23 0.188 215.29 11249.88 KG.
10B D-FORMED BAR FABRICATION WORK (MORE THAN 10'-0" HEIGHT)
for COLUMN C1 (6000mm.) with lapping length
main bar Ø20mm. 2 12.41 12 0.752 223.98
main bar Ø16mm. 2 11.91 2 0.482 22.96
stirrup Ø10mm. 2 5 22 0.188 41.36
2 4 22 0.188 33.09
2 3.83 22 0.188 31.68
for COLUMN C1 (5400mm.) with lapping length
main bar Ø20mm. 4 10.5 12 0.752 379.01
main bar Ø16mm. 4 10 2 0.482 38.56
stirrup Ø10mm. 4 5 18 0.188 67.68
4 4 18 0.188 54.14
4 3.83 18 0.188 51.84
for COLUMN C1 (4700mm.) with lapping length
main bar Ø20mm. 1 8.16 12 0.752 73.64
main bar Ø16mm. 1 7.66 2 0.482 7.38
stirrup Ø10mm. 1 5 13 0.188 12.22
1 4 13 0.188 9.78
1 3.83 13 0.188 9.36
for COLUMN C1A (5440mm.) with lapping length
main bar Ø20mm. 1 10.58 20 0.752 159.12
stirrup Ø10mm. 1 5 19 0.188 17.86
1 4 19 0.188 14.29
1 3.83 19 0.188 13.68
for COLUMN C1A (5400mm.) with lapping length
main bar Ø20mm. 3 10.5 20 0.752 473.76
stirrup Ø10mm. 3 5 18 0.188 50.76
3 4 18 0.188 40.61
3 3.83 18 0.188 38.88
PAGE NO. 11
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH PC'S. WEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. kg/ft.
for COLUMN C1A (4700mm.) with lapping length
main bar Ø20mm. 6 8.16 20 0.752 736.36
stirrup Ø10mm. 6 5 13 0.188 73.32
6 4 13 0.188 58.66
6 3.83 13 0.188 56.16
for COLUMN C2 (6000mm.) with lapping length
main bar Ø20mm. 17 12.41 8 0.752 1269.20
stirrup Ø10mm. 17 5 22 0.188 351.56
17 4 22 0.188 281.25
for COLUMN C6 (2100mm.) with lapping length
main bar Ø20mm. 1 9.66 8 0.752 58.11
main bar Ø16mm. 1 9.16 4 0.482 17.66
stirrup Ø10mm. 1 5 16 0.188 15.04
1 4 16 0.188 12.03
1 3.83 16 0.188 11.52
for COLUMN C9 (7000mm.) with lapping length
main bar Ø16mm. 4 12.25 12 0.482 283.42
stirrup Ø10mm. 4 5 23 0.188 86.48
4 4 23 0.188 69.18
4 3.83 23 0.188 66.24
for COLUMN C9 (6000mm.) with lapping length
main bar Ø16mm. 13 11.91 12 0.482 895.54
stirrup Ø10mm. 13 5 22 0.188 268.84
13 4 22 0.188 215.07
13 3.83 22 0.188 205.93
for COLUMN C9 (2100mm.) with lapping length
main bar Ø16mm. 2 9.16 12 0.482 105.96
stirrup Ø10mm. 2 5 16 0.188 30.08
2 4 16 0.188 24.06
2 3.83 16 0.188 23.04
for CORBEL CR3
main bar Ø16mm. 10 8.08 12 0.482 467.35
side bar Ø12mm. 10 3.16 16 0.271 137.02
stirrup Ø12mm. 10 8.66 8 0.271 187.75
10 7.33 8 0.271 158.91 8031.39 KG.
PAGE NO. 12
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM LENGTH PC'S. WEIGHT QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. ft. kg/ft.
10C D-FORMED BAR FABRICATION WORK (MORE THAN 20'-0" HEIGHT)
for COLUMN C9 (7000mm.)
main bar Ø16mm. 4 12.25 3 0.482 70.85
stirrup Ø10mm. 4 5 8 0.188 30.08
4 4 8 0.188 24.06
4 3.83 8 0.188 23.04
for CORBEL CR1
main bar Ø20mm. 4 15.58 12 0.752 562.38
side bar Ø16mm. 4 10.5 16 0.482 323.90
stirrup Ø12mm. 4 8.66 27 0.271 253.46
4 7.33 27 0.271 214.53
for CORBEL CR2
main bar Ø16mm. 10 7.83 12 0.482 452.89
side bar Ø16mm. 10 3 8 0.482 115.68
stirrup Ø12mm. 10 8.66 8 0.271 187.75
10 7.33 8 0.271 158.91
for TIE BEAM TB3 (7500mm.) with lapping length
main bar Ø20mm. 3 26.5 2 0.752 119.57
main bar Ø16mm. 3 26.16 4 0.482 151.31
ex. top Ø20mm. 3 16.83 3 0.752 113.91
stirrup Ø10mm. 3 4.41 47 0.188 116.90
for VALLEY GURDER
main bar Ø10mm. 3 10.5 57 0.188 337.55
3 4 57 0.188 128.59
binder Ø16mm. 3 28 2 0.482 80.98
binder Ø10mm. 3 27.66 26 0.188 405.61 3871.96 KG.
PAGE NO. 13
BILL OF QUANTITY (PART BILL- 04)
SL. NAME OF ITEM ITEM AREA HEIGHT NO'S./ QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. sft. ft. PER ITEM.
12 PILE HEAD BREAKING WORK
for PILE CAP PC2 2 1.77 4 2 28.32 28.32 CFT.
SL. NAME OF ITEM ITEM AREA/ THICKNESS UNIT/ QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. VOLUME ft. PER VOL.
13A CARRYING OF BRICK
for BRICK SOLING WORK 1 19912.88 3 59738.64 59738.64 PCS.
13B CARRYING OF CEMENT
for C.C. WORK 1 59.15 0.25 0.12 1.77
for R.C.C. WORK 1 3939.71 0.21 827.34 829.11 BAG.
13C CARRYING OF SAND
for C.C. WORK 1 59.15 0.25 0.45 6.65
for R.C.C. WORK 1 3939.71 0.41 1615.28 1621.94 CFT.
13D CARRYING OF CHIPS/AGGREGATE
for C.C. WORK 1 59.15 0.25 0.9 13.31
for R.C.C. WORK 1 3939.71 0.82 3230.56 3243.87 CFT.
SL. NAME OF ITEM ITEM CLEANING PERSON QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. LAYER
14A DAILY PURPOSE MASON (FOR REBAR CLEANING WORK)
for PILE CAP PC2 2 1 0.5 1.00
for PADESTAL COLUMN C2 3 1 0.5 1.50
for PADESTAL COLUMN C1A (@GB1) 1 1 0.5 0.50
for PADESTAL COLUMN C2 (@GB2) 7 1 0.5 3.50
for PADESTAL COLUMN C3 (@GB1) 3 1 0.5 1.50
PAGE NO. 14
BILL OF QUANTITY (BOQ)
SL. NAME OF ITEM ITEM CLEANING PERSON QUANTITY TOTAL QUANTITY UNIT
NO. QNTY. LAYER
for PADESTAL COLUMN C4 (@GB1) 1 1 0.5 0.50
for PADESTAL COLUMN C9 (@GB3) 2 1 0.5 1.00
for COLUMN C1 (6000mm.) 2 4 0.5 4.00
for COLUMN C1 (5400mm.) 4 4 0.5 8.00
for COLUMN C1 (4700mm.) 1 3 0.5 1.50
for COLUMN C1A (5440mm.) 1 4 0.5 2.00
for COLUMN C1A (5400mm.) 3 4 0.5 6.00
for COLUMN C1A (4700mm.) 6 3 0.5 9.00
for COLUMN C2 (6000mm.) 17 4 0.5 34.00
for COLUMN C6 (2100mm.) 1 2 0.5 1.00
for COLUMN C9 (7000mm.) 4 4 0.5 8.00
for COLUMN C9 (6000mm.) 13 4 0.5 26.00
for COLUMN C9 (2100mm.) 2 2 0.5 2.00
for CORBEL CR1 4 1 0.5 2.00
for CORBEL CR2 10 1 0.5 5.00
for CORBEL CR3 10 1 0.5 5.00 123.00 PER.
14B DAILY PURPOSE LABOUR (FOR REBAR CLEANING WORK)
for PILE CAP PC2 2 1 0.5 1.00
for PADESTAL COLUMN C2 3 1 0.5 1.50
for PADESTAL COLUMN C1A (@GB1) 1 1 0.5 0.50
for PADESTAL COLUMN C2 (@GB2) 7 1 0.5 3.50
for PADESTAL COLUMN C3 (@GB1) 3 1 0.5 1.50
for PADESTAL COLUMN C4 (@GB1) 1 1 0.5 0.50
for PADESTAL COLUMN C9 (@GB3) 2 1 0.5 1.00
for COLUMN C1 (6000mm.) 2 4 0.5 4.00
for COLUMN C1 (5400mm.) 4 4 0.5 8.00
for COLUMN C1 (4700mm.) 1 3 0.5 1.50
for COLUMN C1A (5440mm.) 1 4 0.5 2.00
for COLUMN C1A (5400mm.) 3 4 0.5 6.00
for COLUMN C1A (4700mm.) 6 3 0.5 9.00
for COLUMN C2 (6000mm.) 17 4 0.5 34.00
for COLUMN C6 (2100mm.) 1 2 0.5 1.00
for COLUMN C9 (7000mm.) 4 4 0.5 8.00
for COLUMN C9 (6000mm.) 13 4 0.5 26.00
for COLUMN C9 (2100mm.) 2 2 0.5 2.00
for CORBEL CR1 4 1 0.5 2.00
for CORBEL CR2 10 1 0.5 5.00
for CORBEL CR3 10 1 0.5 5.00 123.00 PER.