2022 Buildblock Pocket Install Guide
2022 Buildblock Pocket Install Guide
2022 Buildblock Pocket Install Guide
4”
432 mm
9”
1219 mm
48”
.178097 m3
.097206 yd3
RECOMMENDED TOOLS AND MATERIALS Is adequate labor prepared for pouring?
N/A
102 mm 229 mm 1219 mm .074318 m3
TOOLS LIST • Alignment & Bracing System
NOTE: Recommended minimum pouring temperature is 15°F
6” 48” .130128 yd3 • Foam Guns, Low Expansion
152 mm
N/A
1219 mm
N/A
.099489 m3 • Hand Saw (-9°C). Properly handled, specially formulated concrete can be
Foam Adhesive, Foam
• Power Saw poured at temperatures as low as -15°F (-26°C). Consult your
8” 48” 5.33 ft2 .163050 yd3 Cleaner
203 mm
N/A
1219 mm
N/A
.4951 m2 .124660 m3 • Keyhole Saw ready mix company. At temperatures below freezing, you
• Work Gloves
• Table Saw (Optional, For must cover all exposed concrete with insulating material.
10”
N/A
48”
N/A
.195972 yd3 • Sunscreen
254 mm 1219 mm .149831 m3 Convenience)
Double Taper Top • Broom And Floor Scraper
• Hammer Drill / Cordless Drill
12”
N/A
48”
N/A
.261816 yd3
This guide is intended for a contractor or installer of BuildBlock
305 mm 1219 mm .175002 m3
• Rebar Tie Tool MATERIAL LIST Insulating Concrete Forms. It is intended to supplement the basic
4” 9”
N/A
3.125 ft2
N/A • Hot Knife, Router • Reinforcing as required construction knowledge of a professional.
102 mm 228 mm PIECE LENGTH .2903 m2
52”/1321 mm • Hammer plus accessories, (rebar ties,
6”
152 mm
11”
279 mm
N/A
3.82 ft2
.3550 m2
N/A
• Framing Square For the latest version of this publication and our complete
NOMINAL LENGTH
stirrups) Installation & Technical Manual visit BuildBlock.com
BuildBuck
8” 13” 48”/1219 mm
N/A
4.51 ft2
N/A • Concrete Tools • Screws (1-5/8”, 2-1/2”,
203 mm 330 mm .4190 m2
• Level, Laser Level BUILDBLOCK BUILDING SYSTEMS LLC
#10 Course thread),
OUTER PANEL • Mason’s Line And Chalk Line 866-222-2575 | 831-597-0792 Fax | buildblock.com
48”/1219 cm 18“/6” 5.33 ft2 .056296 yd³ Concrete screws 1-3/4”
INNER PANEL 457 mm/152 mm .4951 m2 .043041 m3 • Rebar Bender And Cutter • BuildBuck window & door
BuildRadius 2 ft
30.75”/ 781 cm
• Scaffold Planks bucking material
• Internal Concrete Pencil • Sleeves for mechanical, BUILDBLOCK REPRESENTATIVE:
OUTER PANEL
Vibrator (Max 1” Head) electrical, plumbing.
POCKET
60”/1524 mm 12”/0 6.67 ft2 .105645 yd³
INNER PANEL 305 mm/0 .6197 m2 .080771 m3
6” 11” 42.75”/1086 mm
INSTALLATION
BuildRadius 4 ft 152 mm 279 mm
INNER PANEL .045099 yd3 RECOMMENDED CONCRETE MIX
19.75”/502 mm .03448 m3 (See our buildblock.com for mix designs and more information.)
INNER PANEL .04642 yd3 • 3000 psi: Higher psi can be used but lower psi is not recommended. In Canada,
GUIDE
OUTER PANEL 21.125”/ 537 mm 2.67 ft2 .035490 m3
minimum 20 mpa.
24”/610 mm INNER PANEL .2480 m2 .04715 yd3
21.8175”/554 mm .036048 m3 • Aggregate: 3/8” (10mm) rock chip or river rock is highly recommended. 1/2”
BuildRadius (12mm) aggregate can be used but will require more vibration.
8 ft,12 ft,16 ft,20 ft INNER PANEL .047606 yd3
22.25”/565 mm .036397 m3 • Slump: 5” - 6” (Keep in mind as the concrete is being pumped under pressure, it TECHNICAL SUPPORT
MORE INFORMATION AVAILABLE AT BUILDBLOCK.COM loses approximately 1/2-inch of slump.)
ITEM# BBM-2100 PSALMS 118:22-24 REV 02/22
technical@buildblock.com | (405) 212-3138
STEP 1: FOOTING OR SLAB 3. Try cutting blocks on vertical lines (center between two interlocks)
in a manner that will not jeopardize the blocks functioning
5. Refer to engineering for all header/lintel steel placement and
stirrup requirements.
1. Footing or slab must be level for best results (within 1/4” in all interlock. If it is not possible to adjust wall dimensions, a
directions). “stacked joint” will be created which should be placed under a STEP 5: SUCCESSIVE COURSES
2. Establish wall locations on footing or slab with chalk line. window or at center of door to minimize its effect. If possible try
to keep this cut four to six feet from a corner. 1. Start second course by reversing direction of each corner
3. Place packaged forms inside perimeter of footing. form, creating a stagger of the vertical joints. Proceed around
4. Note that horizontal rebar must be placed as the BuildBlock perimeter in the same manner as the first course. Make sure
4. When pouring footing or slab, place reinforcing dowels as per
forms are stacked, per engineering requirements or design. (See blocks are pressed together completely.
Project Engineer and/or local building code requirements. The
following dowel spacing instructions will prevent dowels from
Step 4.) Complete first course.
2. Once the first three courses have been set, string walls and shim.
STEP 7: CONCRETE PLACEMENT
interfering with webs: 1. Use Prior to Pour checklist (see back).
5. 6” 90° Corner: Place first dowel 5-1/2” in from one outside
STEP 3: DOOR & WINDOW OPENINGS 3. For out-of-level footings or slabs, use wood door shims to level
low areas and trim bottom of block for high areas. 2. Order/use proper concrete mix (see back).
edge and 8-1/2” in from the other outside edge as shown in 1. BuildBuck is the perfect ICF bucking
material to create and insulate 4. Set additional courses the same way as the first two courses, 3. When ordering Pump Truck, make sure they have an “S” bend,
Diagram A. Reverse those measurements to place Dowel #2.
all window and door openings. reversing corners each course. Cut forms at window openings ram’s horn, or reducer before end of hose. If possible, final size
Space remaining dowels on 6” increments according to your
Dimensional lumber should be used and place reinforcement as required. of hose should be reduced to 3”.
engineering requirements (i.e. 6, 12, 18, or 24” apart.)
only on overhead garage doors. 5. Spot glue the bottom of each block on the final (top) course 6” 4. Begin pouring 4’ to 5’ from a corner; direct concrete flow
6. 8” 90° Corner: Place first dowel 6-1/2” in from one outside
2. Determine openings for doors and from the end of each block. This will lock the blocks into place. towards the corner, then move along the wall. Never pour
edge and 10-1/2” in from the other outside edge as shown in
windows: Mark footing or slab at Do not glue the entire length of the block to prevent lift and directly down a corner.
Diagram B. Reverse those measurements to place Dowel #2. BuildBuck window properly braced and
these locations. glued before a pour. interlock issues. 5. When filling around window and door bucks alternate pour
Then space remaining dowels on 6” increments as described
above. Note: Optimum location of steel is centered between 3. Determine window and door locations, and sizes. If needed, cut 6. Identify all building service penetrations and install appropriate from side to side so buck is not moved sideways by concrete
DOWEL PLACEMENT
webs. blocks horizontally for setting bucks between block courses. Be size pipes. pressure.
8 1/2” careful when cutting through block webs. Additional bracing of
DIAGRAM A: BB-690 6” FORM 7. Once wall is completely stacked, pop string line at desired wall 6. As the pour continues, make sure that the space below the
blocks may be required. height and trim top of wall level. Note: ICF walls may compress bottom of any window opening or pipe sleeve is filled entirely
up to 1/16” per course during the pour as the weight of the and vibrated.
51/2”