HIRAC
HIRAC
HIRAC
IDENTIFICATION
AND RISK
ASSESSMENT &
RISK CONTROL
ISO 45001: 2018 - Clause: 6.1.2
Prepared By:
Business Excellence
Agenda
Hazard identification
Types of Hazards
Risk assessment
Hierarchy of Controls
Review Mechanism
Hazard, Risk & Accident
❖ HAZARD:
• Anything (a situation, a substance or a condition)
that has the potential or ability to cause harm.
We must always be seeking to identify hazards in
the workplace and once identified, prevent those
hazards from causing us harm.
❖ RISK:
• The chance or likelihood that a HAZARD will cause
you a problem or injury & how severe the harm
will be. When faced with a HAZARD.
• Will help assess what action is required to
prevent an accident from occurring that could
result in injury.
❖ ACCIDENTS:
• Unplanned events that result in injuries or
property damage.
Hazard Vs Risk
Hazard Identification
❖ Hazard identification information sources:
Incident injury
illness Report
Health &
Accident
Environment
investigation
monitoring
Employees/
Team Associate
Consultant complainants &
observation
Hazard
Workplace identification
Safety Audits
inspections information
sources
Hazard Identification
Electrical
Ergonomic Mechanical
Types of
Hazards
Biological Physical
Chemical
Types of Hazards
HIRAC Format
Arcelor Mittal Nippon Steel India Limited (AMNSIL)
Plant Name :
Ref No. AMNSIL/Dept/16.7/HIRAC
Rev No. 0
Competency's required
Nature of Risk Severity
Measure
Who may get affected
or exposed due to the
material)/ Source, or
Yes/No
Risk priotization
How Likely? (L)
Category of Hazard
RPN (L x S)
RPN (L x S)
Severity (S)
Severity (S)
may go wrong
energy or haz
Gaps, if any
(OH / S)
hazard
Existing
R/NR
D/I
Risk Assessment Criteria
If almost no gap exists in control of the identified OHS hazard as technology, operational control,
Highly Unlikely (1)
competence, measurement monitoring in place
Unlikely (2) If there is any minor gap / weakness in control of the identified OHS hazard
There are unreasonable gaps in control of the identified OHS hazard with respect to adoption of
Likely(3)
technology, operational control, measurement monitoring and competence
There are unreasonable major gaps in control of the identified OHS hazard with respect to adoption of
Very Likely (4)
technology, operational control, measurement monitoring and competence
There are almost no controls in place in controlling the identified OHS hazard and have occurred in the
Certain(5)
past but ignored.
Hierarchy of Controls
Hierarchy of Controls
Risk Assessment Criteria
DETERMINING RISK SEVERITY DESCRIPTION– GUIDANCE CRITERIA
Category S-1 S-2 S-3 S-4 S-5
Frequently >OEL for CMRS; >10 Frequently >10 times OEL CMRS;
>10% but <50% OEL for CMRS; >50% but
times the OEL for irritants; sensitization; hearing loss; permanent
<100% OEL for irritants. Frequent noise Threshold shifts; >50% but <OEL for CMRS;
Health Exposure < 10% OEL; <80 dBA for noise. muscle strain/sprain with lost health effects; severe but routinely
exposure >80 dBA but <85 dBA.(CMR - >OEL for irritants; muscle strain/sprain
time; exposure event; BBP treatable BPP/infectious disease diagnosis
Carcinogenic, Mutagenic, Reprotoxic)
exposure event (not including seasonal flu, common cold)
Minor release of
materials within the Major release makes
Release with effect to outside plant
Environment Minor Impact within the unit plant boundary but no impact to Massive impact to
boundary environment
environmental Impact to environment & media coverage
outside
> 8 hour, >1 day > 10 days,
Business Interruption < 8 hour > 30 days
but < 1 day but < 10 days but < 30days
Property Damage 0 (No damage) < 10 Lakhs (Minor damage) 10 lakhs-2 Cr (Moderate damage) 2 Cr - 20 Cr (Severe damages) > 20 Cr (Critical damage)
For less than a year which impairs For about a year which impairs For long run (over a year) which impairs
Regulator caution letter Warning
Company's operations Company's operations Company's operations
Adverse local media - Concerns on -Adverse global media coverage
Intra industry knowledge of incident -Adverse National media
Brand / Reputation Minimal Impact on reputation performance by financial analysts or - Major loss of shareholder support
without media attention coverage
shareholders - Major boycott campaign
Unable to fully satisfy all customer
requirements
Near 100% satisfaction of customer
(Quantity/Quality/Delivery). Customer will Shortfall in satisfying critical Significant Shortfall in satisfying critical
requirements expected, negligible impact
Customer, Quality & Energy objective No Impact experience limited impact. Marginal non customer requirements. customer requirements.
on companies objective w.r.t. quality &
compliance to company objective w.r.t (Quantity/Quality/Delivery). (Quantity/Quality/Delivery).
objective
quality & energy- may be achieve with
additional resources.
Low Energy Consumption i.e. (<30%) of the High Energy Consumption i.e.
Very low Energy Consumption i.e. (<15%) entire department / Medium Energy Consumption i.e. (<60% to (<80% to >60%) of the entire High Energy Consumption i.e. (>80%) of the
Energy Consumption/ Energy Efficiency of the entire department / >30%) of the entire department / department / entire department /
Medium effect on Energy Efficiency (60-
High effect on Energy Efficiency (>80%) Less effect on Energy Efficiency (30-60 %) Very less effect on Energy Low effect on Energy Efficiency (<30%)
80%)
Efficiency (<60% to >3%0)
Risk Assessment Criteria
HIGHLY UNLIKELY (1) TOLERABLE (1) TOLERABLE (2) TOLERABLE (3) TOLERABLE (4) MODERATE (5)
UNLIKELY (2) TOLERABLE (2) TOLERABLE (4) MODERATE (6) MODERATE (8) SUBSTANTIAL (10)
LIKELY (3) TOLERABLE (3) MODERATE (6) MODERATE (9) SUBSTANTIAL (12) SUBSTANTIAL (15)
VERY LIKELY (4) TOLERABLE (4) MODERATE (8) SUBSTANTIAL (12) SUBSTANTIAL (16) INTOLERABLE (20)
CERTAIN (5) MODERATE (5) SUBSTANTIAL (10) SUBSTANTIAL (15) INTOLERABLE (20) INTOLERABLE (25)
Efforts should be made to reduce the risk, but the cost of prevention should be carefully measured and limited.
MODERATE ALARP
Risk reduction measures should be implemented.
UN ACCEPTABLE
Work should not be started until the impact / risk has been reduced. Considerable resources may have to be
SUBSTANTIAL
allocated to reduce the impact / risk where the risk involves work in progress, urgent action should be taken.
Urgent action should be taken. Work should not be started or continued until the impact / risk has been
INTOLERABLE
reduced.
HIRAC
HIRAC Format
Review Mechanism
✓ If any changes done in processes / activities which have / can have impact on health and safety
✓ Amendments / addition in legal and corporate requirements
✓ Change in process or products handled
✓ Internal and external audit results, including Corporate and Specialized Audits
✓ Occurrence of accident, emergency, 'near misses'
✓ while initiating any corrective and preventive action
✓ while purchasing and erecting any new equipment / machinery / building
✓ major changes in facilities, equipment consuming energy, systems, or processes.
✓ Planned or new developments; new or modified activities, products or services