Post Tensioning
Post Tensioning
Post Tensioning
Objectives:
1. To know the brief history of posttensioning. 2. To understand the basic principles of post-tensioning. 3. To identify the components of posttensioning. 4. To know the applications of posttensioning
History
The first patent for prestressed concrete was
issued to P.H. Jackson of San Francisco in 1886. He obtained a US patent for tightening steel tie rods in artificial stones (concrete blocks) and concrete arches used for slabs and roofs.
Shortly thereafter, in 1888, C.E.W. Doehring from Germany also obtained a patent for prestressing concrete slabs with metal wires. However, modern development of prestressed concrete is usually attributed to Eugene Freyssinet of France. In 1928, Freyssinet begun to use high-strength steel wire for prestressing concrete.
In 1940, Professor Gustav Magnel of Belgium developed a system of curve, multi-wire tendons in flexible rectangular ducts.
The first use of post-tensioning in the US was on the Walnut Lane Bridge in Philadelphia in 1949. This landmark bridge had precast girders post-tensioned with the Magnel system.
Tie-Back Anchorage
Tie-Down Anchorage
Over the years, there have been a number of significant technological developments that have helped advance the state-of-the-art of post tensioning and have contributed to its continued growth. These developments include:
1. Introduction of strand system 2. Development of ductile iron castings for single strand tendons 3. Introduction of the load-balancing design method 4. Introduction of banded tendon layout for 2-way slab system 5. Segmental bridge construction 6. Use of computers for analysis and design 7. Formation of the Post-Tensioning Institute 8. Improvements in corrosion resistance
system used high-strength stress-relieved steel wires, bars, or strand. The button-headed tendon system used inch wire bundled together, greased, and wrapped with Kraft paper as sheathing. The wires ran through a stressing head and were button headed to anchor them. Machinery was used to cold-upset the ends of the wires to create the button-head anchors. The post-tensioning elongation was held with shims or a threaded nut.
ended up on the outside edges of the constructed slab, they have to be covered with second concrete pour.
Corporation- used inch sever-wire prestressing strand and an anchorage assembly manufactured of coiled wire and a plate and anchored with two half wedge chucks. The strand was also greased and wrapped with Kraft paper.
has continued to grow at a rapid pace, averaging 8.5% annual growth as shown.
to be a multibillion-dollar industry in North America and is used in many different construction applications. Figure shows the relative usage of posttensioning by market value.
Prestressing
Principles:
General: Pre-stressing is a method of reinforcing concrete. Externally applied loads induce internal stresses (forces) in concrete during the construction and services phases of a member. The concrete is pre-stressed to counteract these anticipated stresses during the service life of the member.
One is called pre-tensioning. The prefix pre means that the prestressing steel is stressed before the concrete is cast. This method consists of first stressing high- strength steel strands or wires between buttresses, and then casting the concrete around the steel. Once the concrete has reached a certain specified strength, the steel is cut between the ends of the member and the buttresses to transfer the pre-stressing force to the concrete. This process typically takes place at a precast plant and requires the complete pre-tensioned concrete member to be trucked out to the job site and then assembled.
post-tensioning. The prefix post means that the prestressing steel is stressed after the concrete is cast. Instead of stressing the high-strength steel between buttresses at a precast plant. The steel is simply installed on the job site after the contractor forms up the member. The high-strength steel is housed in a sheathing or duct that prevents it from bonding to the concrete. The steel is attached to the concrete at the ends of the member by especially design anchorage devices. Once the concrete has cured (hardened), the steel is stressed to induce forces in the concrete. Posttensioning has all of the advantages of pre-stressed concrete while allowing the builder the freedom to construct the member in any location, including its final position in the structure (cast-in-place).
tendons are embedded in the concrete before the concrete is cast. These internally post-tensioned systems can be either bonded or unbonded. In some bridge and retrofit applications, the post-tensioning tendons are mounted outside the structural members. These are referred to as external post-tensioning systems.
single-strand that coated with corrosion-inhibiting coating and protected by extruded plastic sheathing. This allows the strand to move inside the plastic sheathing and prevent the ingress of water. The strands are anchored to the concrete using ductile iron anchors and hardened steel wedges. The tendon is supported by chairs and bolsters along its length to maintain the desired profile. Figure shows the typical components and construction sequence for an unbonded system.
system, it can be classified as a standard or encapsulated system. Encapsulated systems are required for aggressive environment where there is a possibility of tendon exposure to chlorides or other deleterious substances. Encapsulated tendons are designed to prevent any ingress of water during and after construction. Figure shows an example of a standard and encapsulated tendon.
Bonded Post-Tensioning System: Bonded post-tensioning systems consist of tendons with multi
strands or bars. The strands or bars are placed in corrugated galvanized steel, high density polyethylene (HDPE) or polypropylene (PP) ducts. Depending on the site conditions and system used, the strands may be installed before the concrete is placed or the ducts may be installed without the strands. The strands are then pulled or pushed through the ducts. Once the concrete has hardened, the tendons are stressed and ducts filled with grout. Inlets and outlets are provided at high/low points to ensure that the grout fills the ducts completely. Figure shows the components of a typical multi strand grouted system. The grout provides an alkaline environment and protect the pre-stressing strands from corrosion. It also bonds the strands to the surrounding concrete.
Illustrations:
compression. The tensile strength of concrete is about 10% of its compressive strength. As a result, plain concrete members are likely to crack when loaded.
As the load increases, the beam deflects slight and then falls abruptly. Under load, the stresses in the beam will be compressive in the top, but tensile in the bottom. We can expect the beam to crack at the bottom and break, even with a relatively small load, because of concretes low tensile strength. In order to resist tensile stresses or counter the low tensile strength which plain concrete cannot resist, it can be reinforced in two ways by using steel reinforcing bars or by pre-stressing.
concrete cannot be used efficiently, certain forces may be applied to the beams that result in a member in which all the concrete can resist the bending stresses.
tensile zones of the concrete members to offset anticipated tensile stresses will reduce or eliminate cracking and will produce a more durable concrete member. By pre-compressing a concrete element, so that when flexing under applied load, it will still remain in compression and achieving a more efficient design of the structure.
tensile strength of its own and, provided that the tensile stresses do not exceed the precompression stresses, cracking cannot occur in the bottom of the beam.
cancel the compression induced by the posttensioning before it can crack the concrete. The pre-compression stresses can also be designed to overcome the diagonal stresses. The normal procedure is to design to eliminate cracking at working loads.
involved. There is also shear. Vertical and horizontal shear forces are set up within a beam and these will cause diagonal tension and diagonal compression stresses of equal intensity. As concrete is weak in tension, cracks in a reinforced concrete beam will occur where the diagonal tension stresses are high, usually near the support. In pre-stressed concrete, the compression stresses can also be design to overcome these tension stresses.
prestressed concrete used this illustration and simply explained to his students using stack of books.
Illustration #2:
simple-span beam and a fixed cantilever beam cracked under applied load.
prestressing forces applied by stressing high strength tendons. By placing the prestressing low in the simple-span beam and high in the cantilever beam, compression is induced in the tension zones; creating upward camber.
after loads have been applied. The loads cause both the simple-span beam and cantilever beam to deflect down, creating tensile stresses in the bottom of the simple-span beam and top of the cantilever beam.
Fig. 1.4
Fig. 1.5
Fig. 1.6
masonry wall, is that they are subjected to forces that cause them to flex and bend. Examples of this includes slabs on ground where the edges of the slabs are forced upward by swelling soil, elevated concrete slabs where gravity and other applied loads pull down on the slab in between supports, and walls that might be subjected to lateral forces from wind or seismic activity. This bending creates high tensile forces that can cause the concrete and masonry to crack. This is where the use of reinforcing is applied.
Illustration #3:
tensile forces, it can be embedded in the concrete at the tension zones (the area that tensile failures could occur) allowing the tensile forces to be handled by the reinforcing steel. Adding post-tensioned reinforcing combines the action of reinforcing the tension zones with the advantages of compressing the concrete or masonry structure.
tensioned reinforcing is installed in a draped profile instead of running in a straight line. A typical draped profile in an elevated concrete slab would route the post-tensioned reinforcing through a high point over the slabs supports, and through a low point in between those supports. Now, optimum efficiency is obtained in the tension zones, the concrete is being compressed, and the post-tensioned reinforcing is creating an uplift force in the middle of the spans where it is needed the most.
applied to the section and the corresponding bending moment diagram applied to this alone.
The stress distribution from the flexure of the beam is calculated from M/Z, where M is the bending moment and Z is the section modulus. By
considering the deflected shape of the beam, it can be seen that the bottom surface will be in tension. The corresponding stress diagram can be drawn.
compression but not in tension. Only small tensile stresses can be applied before cracks that limit the effectiveness of the section will occur. By combining the stress distribution from the applied pre-compression and the applied loading, it can be seen that there is no longer any tension.
tool. In this, forces exerted by the prestressing tendons are modeled as equivalent upward forces on the beam or slab. These forces are then proportioned to balance the applied downward forces. By balancing a chosen percentage of applied loading, it is possible to control deflections and also to make the most efficient use of the beam or slab depth.
pre-stressing tendons must be set to follow profiles that reflect the bending moment envelop from applied loadings. Generally, parabolic profiles are used.
usually in a factory and being done between heavy end anchorage, bulkheads or abutments.
members due to an eccentrically applied prestressing force. Camber is divided into two categories i.e., initial camber and long-term camber. Initial camber is induced at transfer of the prestressing force at the time of release. It is the net upward deflection calculated by algebraically summing the smaller downward deflection caused by the beam self-weight (beam) and the larger upward deflection (ps) caused by the prestressing force applied at an eccentricity e below the center of gravity of the section.
structures are exposed to direct or indirect application of deicing chemicals, seawater, brackish water, or spray from these water sources; and salt-laden air as occurs in the vicinity of seacosts. Aggressive environment also include structures where stressing pockets are wetted or are directly in contact with soils which contain chloride levels considered y the geotechnical engineer to be harmful to metals.
components required to anchor the prestressing steel and permanently transfer the post-tensioning force from the prestressing steel to the concrete.
which the concentrated prestressing force is transferred to the concrete and distributed more uniformly across the section. Its extent is equal the largest dimension of the cross section. For anchorage devices located away from the end of the member, the anchorage zone includes the disturbed regions ahead of and behind the anchorage.
into the anchorage during the transfer of the prestressing force to the anchorage device. This is that set which was assumed to occur in the design calculation of post-tensioning forces immediately after load transfer
breaking strength obtained in tests on a single representative strand or bar, breaking outside the anchorage. For multi-strand or bar tendons, AUTS equals the AUTS of a single tendon elements (strand, bar) times the number of such elements in the tendon. Representative samples must be from same coil of strands or the same bar from which strands or bars are cut and used in connection efficiency tests.
slabs placed together in a narrow strip, usually along the column line.
wedges and normally used with a bearing plate to transfer the prestressing force to the concrete.
the perimeter of a structure and at open edges of ramps to prevent automobiles and pedestrians from falling over the open sides.
concrete meeting the analytical design requirements. Covered by this definition are square, rectangular, or round plates, sheared or torch cut from readily available steel plates, normally ASTM A36.
concrete and is part of an overall anchorage system. A steel hardware that transfers the tendon force into a structure.
application of prestressing force. Camber is intentionally built in a structural element or form to improve appearance or to nullify the deflection of the element under the effect of loads, shrinkage, and creep.
Chair Hardware used to support or hold posttensioning tendons or reinforcing. Bars in their proper position to prevent displacement before and during concrete placement.
reinforcement in the local zone. Confinement reinforcement in the concrete ahead of tendon anchorage is limited to the local zone. Confinement reinforcement consists of spirals, orthogonal reinforcing bars, or a combination of both.
that are uniformly distributed, usually perpendicular to the bonded tendons and spaced at a maximum of eight times the slab thickness or 5 feet (1.5 M).
prevents the ingress of water into the tendon during all stages of construction, and isolates the strand and anchorage from contact with concrete.
resulting from friction created between the strands and sheathing due to curvature and wobble during stressing.
prestressing force spreads out to a more linear stress distribution over the cross section of the structural member (Saint Venant Region). It includes the local zone. The general zone extends from the anchorage along the axis of the member for a distance equal to the overall depth of the member. The height of the general zone equal to the overall depth of the member.
tensile strength of the material that can be assured by the Manufacturer. GUTS should not be confused with fpu the specified ultimate tensile strength (AASHTO LRFD). (The term GUTS has been replaced by two definitions, MUTS and AUTS by the Post-Tensioning Institute.)
Inlet The opening used to inject grout into the duct. Intermediate Anchorage An anchorage located at any
point along the tendon length, which can be used to stress a given length of tendon without the need to cut the tendon. Normally used at concrete pour breaks.
Live End Stressing End. Local Zone The local anchorage zone is the volume of
concrete surrounding and immediately ahead of the anchorage device where the concrete compressive stresses exceed acceptable values for unconfined concrete (concrete without confinement reinforcement). The local zone is defined as a rectangular prism of concrete surrounding the bearing plate and any integral confinement reinforcement. The transverse dimension of the prism are equal to those of the bearing plate, including any integral confinement, plus the suppliers specified minimum edge covers. The length of the local zone extends over the distance from loaded concrete surface to the bottom of each bearing surface of the anchorage device plus maximum dimension of the bearing surface.
that confirms that the quality of material supplied meets all project requirements.
Monostrand One single-strand. Multistrand More than one single-strand in a tendon. MUTS Minimum Ultimate Tensile Strength: When
measured as a force, for a single strand or bar breaking outside of the anchorage or the multiple of those single strand or bar forces for multi-strand or bar tendons; MUTS is the force equal to the nominal cross-sectional area of strand , or bar, times their nominal ultimate tensile stress.
Outlet Opening to allow the escape of air, water, grout P/T Coating material used to protect against corrosion
and reduce friction between prestressing steel and sheathing. For unbonded application P/T coating should meet or exceed the performance criteria outlined in the PTI Specifications for Unbonded Strand Tendons.
behind the anchoring wedges during load transfer from the jack to the permanent anchorage.
prevent bonding of the prestressing steel with the surrounding concrete, provide corrosion protection, and contain post-tensiong coating.
tendon anchor forces into the concrete but does not meet analytical design requirements. Covered by this definition are devices having single or multiple plane bearing surfaces, and devices combining bearing and wedge plate in one piece. They normally require confinement reinforcement.
strand with respect to wedges during force transfer. See seating loss.
Stressing Force See jacking force. Stressing Pocket The void created by the pocket former
between the stressing anchor and the edge of the concrete to allow access for stressing equipment. After stressing, this void is filled in with an approved grout to provide protection for the tendon end.
chairs, bolsters, and other accessories required to maintain the tendon profile. Tendon Tail The excess strand beyong the stressing-end anchor.
complete assembly consisting of anchorages, prestressing steel, and sheathing with post-tensioning coating for unbonded applications or ducts with grout for bonded applications. A single or group of prestressing elements and their anchorage assemblies, which impart a compressive force to a structural member. Also included are ducts, grouting attachment and grout. The main stressing element is usually a high strength steel member made up of a number of strands, wires or bars.
stiffen in a short time while at rest, but to acquire a lower viscosity when mechanically agitated. The process is reversible.
states to define a qualified professional engineer who inspects structures of certain defined parameters, and who also inspects the post-tensioning tendons.
prevented from bonding to concrete and is free to move relative to concrete. The prestressing force is permanently transferred to concrete at the tendon ends by the anchorages only.
increases the slump of freshly mixed grout without increasing the water content or maintains the slump with reduced amount of water due to factors other than air entrainment.
which bite into the prestressing steel (strand) during transfer of the prestressing force.
Wedge Set See seating loss. Wobble friction The friction caused by the
unintended deviation of the tendon.
Anchor assembly
Barrel Anchor
Banded Tendons
General zone
Local Zone
Prestressing Steel:
material in not only North America is a 7-wire carbon steel strand. Seven-wire has a center wire enclosed tightly by six helically wound outer wires. Strand conforming to ASTM A416 Grade 270 has a minimum ultimate strength of 279 ksi (1860MPa). Grade 250 is also available (with an ultimate strength of 250 ksi) for use, for barrier cable applications. ASTM A416 also sets forth other requirements for strands, such as strand size, tolerances, workability, bending, fatigue, stress corrosion and hydrogen embrittlement, and bond. For each grade, there are two types of steel: low relaxation and stress relieved (normal relaxation).
relaxation steel. Up until 1970s, stress-relieved strands were common; however they are rarely used today. Relaxation is defined as the reduction in force over time in a highly stressed tendon at a given elongation. Low relaxation strand must conform to the Supplement I requirements of ASTM A416, which limit relaxation loss after 1000 hours of testing to 2.5% at 70% of minimum ultimate tensile strength (MUTS) or 3.5% at 80% of MUTS.
loss limit under ASTM A416. Relaxation losses for such tendons typically run at 4.5%, 8%, and 12% of the initial stress in the free tendon (i.e., strand is not associated with a concrete element) for an initial stress equal to 0.6, 0.7, and 0.8 of MUTS, respectively.
environment, the designer may elect to specify a corrosion protective coating for the strand such as epoxy coating or hot dip galvanizing. Epoxycoated strands shall conform to ASTM A882, Standards Specification for Epoxy-Coated SevenWire Strand. Galvanized strand shall conform to ASTM A475-98, Standard Specification for ZincCoated Steel Wire strand. Neither epoxy-coated or galvanized strand are widely used in general post-tensioning applications in the United States. The designer should evaluate the local availability of these materials before specifying.
are cold-stressed to not more than 80% MUTS and then stress relieved to produce the desired mechanical properties. They have a minimum ultimate tensile strength of 150 ksi (1036 MPa). Prestressing bars are rolled from properly heat ingot or strand-cast steel. They can be manufactured as a smooth round (Type I) or with deformations similar to a common reinforcing bar (Type II). Deformed prestressing bars have deformations that are arranged in a thread pattern permitting the use of screwon couplers and nuts. Plain round bars must be threaded before they can be used with nut/bearing plate anchoring system. Bars used in post-tensioned structures Bars for Prestressed Concrete, including must meet the requirements of ASTM A722, Specifications for Unbonded High-Strength Supplementary Requirements S1 and S2. These requirements include chemical composition, dimension, and tensile properties.
conform to ASTM A421, Uncoated Stress-Relieved Wire for Prestressed Concrete. Rods are used to manufacture wires by open hearth or elastic furnace process. Heat treatment is then used to stressed relieve the wires so that the desired mechanical properties are achieved. Wires are manufactures with various cross-sectional shapes and surface conditions: round versus oval, smooth versus indented, ribbed or crimped. ASTM A421 also has a supplement for low-relaxation wires. Wires are rarely used for post-tensioning applications in the United States; however, they are still used to a greater degree in other parts of the world.
properties of prestressing steel must be known to properly design a post-tensioned structure. ASTM specifications identify requirements for: MUTS fpu; yield limit fpy, modulus of elasticity Ep; and the total elongation under load. In most cases, the design strength of unbonded tendon fps will substantially less than the yield limit fpy. For bonded construction, the designstrength will be greater than or equal to fpy. Typically mechanical properties for low-relaxation strands, wires, and bars are shown in the table below.
Prestressing Steel
fpu
ksi (MPa)
fpy
ksi (MPa)
Ep
ksi (MPa)
Relaxation
Low-Relaxation 7-Wire strand Grade 270 per ASTM A416/416M Stress-Relieved Wire per ASTM A421/421M Low-Relaxation Wire per ASTM A421/421M Prestressed Bars Grade 150 per ASTM A722
270 (1860)
0.90 fpu
28,500 (196,50 0)
0.85 fpu
4 [10 in (250 mm)] 4 [10 in (250 mm)] [2.5% @ 70% MUTS] or [3.5% @ 80% MUTS]
0.90 fpu
150 (1035)
used for design purposes; however, the actual material properties for the prestressing steel supplied to the project may vary and may exceed specification minimums.
during inspection and future rehabilitation. For example, when evaluating out-of-tolerance elongations during stressing, the design engineer should compare the actual values (e.g. the modulus of elasticity) as given on the supplierprovided mill certificates and the value assumed in design. In many instances, the difference may explain the observed elongation.
of a prestressing material. Standard specifications prescribe ductility requirements, which are usually expressed as a minimum percent elongation in the gauge length under total load. For ASTM A416 prestressing strand, the minimum elongation is specified as 3.5% using gauge length of not less than 24 inches (610mm). For ASTM A722 prestressing bars, the minimum percent elongation after rapture is 4% and 7% for type I and type II prestressing bars, respectively.
prestressed concrete structures and ground anchors normally do not experience stress cycling significant enough to cause fatigue problems. For those applications where fatigue is a concern, such as post-tensioned bridge and cable-stayed bridges, fatigue resistance can be increase by proper material selection and anchorage design. Tendon fatigue will depend on the type of structure and whether the tendon is bonded or unbonded. The strand-wedge connection is the most sensitive part of a tendon in regards to fatigue resistance.
engineer should confirm that the intended posttensioning system has been dramatically tested and qualified in accordance with the PTI Acceptance Standards for Post-Tensioning Systems for bonded tendons and in accordance with the post-tensioning project specifications for unbonded tendons. For unbonded systems on bridges, AASHTO requires that a representative anchorage and coupler specimen, as well as tendon, be dynamically tested without failure, 500,000 cycles from 60 to 66 percent of MUTS, and 50 cycles from 40 to 80 percent MUTS.
Application of Post-tensioning Today, post-tensioning is used for a wide range of applications including:
Prepared by: Danny M. Francisco. C.E., G.E. Tel. 6770359 (Office) Mobile: 0557124793 Email: danilo.francisco@aramco.com