Oq RFCC MM 02

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

BG-FR-051 Minutes of Meeting

Format Issue date: 28.06.2021


Rev. no: 01

Topic : QO_TANK 6102 / Roof Structure Dismantling, Fabrication and Erection

Location : BG Conference Room, Phase #7 Sohar

Date : 23 Aug 2023 Start Time: 04:00 PM Finish Time: 05:30 PM

Participants in

# Name Designation Signature

1 Mr. Alexander Paneer BG / General Manager

2 Mr. Bibin Raveendran BG / Operation Manager

3 Mr. Vasantha Kumar BG / Project Manager

4 Mr. Siva Raj BG / Construction Manager

5 Mr. Muthu Mani BG / Project Coordinator

6 Mr. Pritham METCO

7 Mr. Jaffar METCO

8 Mr. Samuel METCO

9 Mr. Atul Dubey METCO

Document No: BG-FR-0111 Page 1 of 2


BG-FR-051 Minutes of Meeting

Format Issue date: 28.06.2021


Rev. no: 01

# Description Action By Date Remarks


METCO has requested BG to deploy the following
technicians for Roof installation activities at site :
1) Welder – 04 Nos
2) Gas cutter – 02 Nos
1 BG / METs
3) Rigger – 02 Nos
Time Sheet will be shared on a daily basis to Metco site
team and the same will be certified by METs representative.
Detection will be applicable from METs
METCO agreed Mr. Samuel will be present at site from
2 morning TBT to until the end of the day to manage site team METs
properly
Mr. Nayak (METCO), Welding Foreman need to do OQ
3 medical and Submit Gate pass documents immediately to METs
guarantee his presence at site for welding
Mr. Atul (METCO), Needs to update his lifting supervisor
certification, as two cranes will be used at the site and he will
4 METs
be responsible for supervising the lifting operations and
granting permits for the second crane
BG Ordered Required Welding Electrodes for this project
5 and the same will be provided to METs. Detection will be BG / METs
applicable from METs
Phase 2 beams Fabrication will be since BG carried out as
6 per Metco mail request the weight age will be deducted their BG / METs
accounts
Metco agreed the Roof Fabrication will be completed as per
7 METs
the schedule dated 5th of September
Metco should ensure site PPE as well as frequent
8 absenteeism at site Half day show off duty should be METs
controlled
Currently working in Site Metco deployed riggers card
existing third party not approved by OQ since the incident is
9 METs
happened they have concern in competency , Hence re
validation to be done OQ approved third party agency

Document No: BG-FR-0111 Page 2 of 2