Adama ZLD Preliminary Energy Audit Report
Adama ZLD Preliminary Energy Audit Report
Adama ZLD Preliminary Energy Audit Report
First Draft
May, 2023
Energy Study and Supply Department
I. Executive Summary
Electricity is the major energy source to the plant and the electrical energy consumption
from Tir 2015 to Ginbot 2015 E.C. is 7278.9 MWh and the current minimum production
is 232 m3/day and maximum production is 1,172 m3/day.
The actual plant specific energy consumption of AIP ZLD is average 28 kwh/m3. But by
design the specific energy consumption of the plant is 20.8 kwh/m3.
Increase the production or reduce energy consumption, currently the plant working
capacity is around 10% and all motors and pumps which controlled by DOL and Star Delta
is working under capacity, and it consume more energy for low production. Therefore, we
must maximize the production or reduce energy consumption by using load scheduling
method.
The maximum demand charge is very high, we must reduce this charge by adjusting and
maintaining the plant operation also, we have to discus with EEU about MD charge.
During the site visit, boiler, MEE, and RO is not working. the details are shown in the table
below.
1|P a g e
II. Table of Content
2|P a g e
1.0 Introduction
The full working capacity of the AIP ZLD plant is 11,000m3/day of which 3,000m3/day is for
domestic wastes and 8,000 m3/day is for industries wastes. Therefore, the WWTP is comprised of
Common Effluent Treatment Plant (CETP) and Effluent Treatment Plant (ETP). To operate the
WWTP to its full design capacity, seven oil type transformers (33 KV/0.4 KV) with a capacity of
3000 KVA each are installed. Now this treatment plant is working under its design capacity from
232 m3/day - 1172 m3/day and the specific power consumption is average 28 kwh. The plant has
different facilities like Boiler, ETP, STP, MEE, MBR+RO but MEE and RO are not working
during the assessment period.
We made walkthrough audit and we have seen energy is lost in different section like, steam header,
steam distribution line, different rating of pumps and motors.
The main system of ETP consist of following equipment for treating effluent-
Receiving chamber
Grit screen chamber
Equalization Tank
Primary Clarifier and Dosing System
Aeration System
Secondary Clarifier
Tertiary tank
Clean water tank
Sludge Dewatering
Centrifuge
The main system of STP consist of following equipment for treating sewage-
Receiving tank
Screening and De-gritting
Sequential Batch Reactor
Filter feed tank
Multigrade Filter
Sludge Dewatering
Centrifuge
Sewage treated tank.
3|P a g e
1.1. Objective
The main objective of this audit is to maintain optimum energy utilization and
reducing energy consumption without affecting production and quality. Also analyze
the present use of energy in the plant and to improve the energy performance of the
plant.
1.2. Methodology
First, we made short meetings with plant manager and section head
discussion about energy audit and what we want.
Field visit to each process section of the ZLD plant.
Interviews has been made with plant manager, senior expert,
electricians, operators.
Data were collected such as, energy consumptions and production
of the last 20 months.
4|P a g e
General Energy Audit Methodology
Energy Audit can be classified into the following two types.
i) Preliminary Audit
ii) Detailed Audit
Preliminary Audit
Preliminary energy audit is a relatively quick exercise to:
Establish energy consumption trends in the organization.
Estimate the possible saving opportunity.
Identify the most likely (and the easiest areas for attention) for plausible saving potential.
Identify immediate (especially no-/low-cost) improvements/ savings.
Set a ‘reference point’ for basic energy consumption and production.
Identify areas for more detailed study/measurement.
Collecting Preliminary energy audit existing, or easily obtained data, such us energy bills,
operational hours, energy consumption trends, property of fuels used, types of fuels used,
stoppage and shutdown histories, etc.
This type of audit offers the most accurate estimate of energy savings and cost. It considers the
interactive effects of all projects, accounts for the energy use of all major equipment, and includes
detailed energy cost saving calculations and project costs.
In a comprehensive audit, one of the key elements is the energy balance. This is based on an
inventory of energy using systems, assumptions of current operating conditions and calculations
of energy use. This estimated use is then compared to utility bill charges.
Detailed energy auditing is carried out in three phases: Phase I, II and III.
5|P a g e
Phase I - Pre-Audit Phase
Phase II - Audit Phase
Phase III - Post Audit Phase
Under this project, we have followed these basic and standard steps.
6|P a g e
Step 5 Conduct of detailed Trials/experiments:
trials/experiments for selected 24 hours power monitoring
energy guzzlers (MD, PF, kWh etc)
Load variations trends in pumps,
fan compressors etc
Boiler/Efficiency trials for (4-8
hours)
Furnace Efficiency trials
Equipment’s Performance
experiments etc
Step6 Analysis of energy use Energy and Material balance& energy
loss/waste analysis
Step 7 Identification and development Identification & Consolidation ENCON
of EnergyConservation measures
(ENCON) opportunities Conceive, develop, and refine ideas.
Review the previous ideas suggested by
unit personal.
Review the previous ideas suggested by
energy audit if any.
Use brainstorming and value analysis
techniques.
Contact vendors for new/efficient
technology
Step 8 Cost benefit analysis Assess technical feasibility, economic
viability, and prioritization of ENCON
options for implementation.
Select the most promising projects.
Prioritize by low, medium, long-term
measures
3|P a g e
2.0 Plant overview
ZLD plant at Adama Industrial Park consists of two main parts: Effluent Treatment Plant (ETP)
and Sewage Treatment Plant (STP) and design capacity,
Effluent water treatment Plant is 8 MLD, 8000 m³/day.
Sewage water treatment Plant is 3 MLD 3000 m³/day
Amount of Actual Wastewater Treated
The total productions form Tir 2015 to Ginbote 2014 E.C are as follows:
The major process consequences of the process of Effluent Treatment Plant (ETP) and sewage
treatment plant are shown below figure-
4|P a g e
Color removal Coagulant
PAC
air air
Primary dosing
Aeration
Stilling Fine Grit Equalization Primary
Flash
chamber screen chamber clarifier
mixer
Wet well
Returned sludge
Sludge Secondary
thickener Sludge clarifier
sump1 &2
Coarse bar
screen
Tertiary
ETP receiving chamber Hardness
tank/polishing unit
Sludge removal
Decanter
Sludge DMFs
Indicators: storage UF
4|P a g e
5|P a g e
3.0 Energy Consumption Profile
3.1. Energy Description
Adama ZLD Plant receives electricity from Ethiopian electric utility 33 KVA and step dawn
ETP 3000KVA*2
STP 3000KVA
Total 16.8 MW
7|P a g e
The energy assessment of Adama ZLD plant has been conducted to identify the potential of
energy savings. The plant major energy consumption is electricity. We collect energy data as
8|P a g e
Figure 1 Energy Consumption Trend
50.00
40.00
30.00
20.00
10.00
0.00
9|P a g e
3.2. Production profile
The full working capacity of the Adama ZLD plant is 11,000m3/day of which 3,000m3/day is
for domestic wastes and 8,000 m3/day is for industries wastes but currently or actual production
is under capacity, see below 12 months data.
Months Production in m3
10 | P a g e
Monthly Production
40,000
35,000
30,000
25,000
20,000
15,000
10,000
5,000
-
1,800,000
1,600,000
1,400,000
1,200,000
1,000,000
800,000
600,000
400,000
200,000
-
11 | P a g e
3.4. Energy Baseline and KPIS
The total productions and Energy from Tir 2015 to Ginbot 2014 E.C are as follows:
The electrical energy consumption KPI for the wastewater treatment has been calculated and
presented below:
Production in m3 Baseline (KPI) in (kwh/m3) power cost/unit, ETB
Treated Wastewater
28 33.404
(ETP+STP)
12 | P a g e
4.0 Energy Saving Potential Opportunity
1) Heat loss in steam pipe from boiler to steam header, due to bare of main
steam line.
2) Steam leakage on steam header valve and heat loss in steam pipe.
3) Heat loss in main steam pipe from steam header to MEE#2, due to without
insulation of pipe.
5) Energy loss in equalization transfer pump, the pump is running under load.
13 | P a g e
14 | P a g e
15 | P a g e
4.2. Heat loss analysis of uninsulated steam pipe
Case one: Existing conditions from boiler to steam header.
Electricity cost 1.193 birr/kwh
S=[10+(Ts-Ta)/20*(Ts-Ta)
Ts=145
Ta=28
Modified System:
After insulating with 65 mm of asbestos wool with aluminum cladding, the hot face temperature
will be 65 °C
Ts = 65 °C
Ta = 28 °C
= 480 kcal/hr m2
16 | P a g e
Energy Saving Calculation
Pipe dimension and length = Ø100mm,41 meter
17 | P a g e
Case two: Existing conditions of Steam header
S=[10+(Ts-Ta)/20*(Ts-Ta)
Ts=135
Ta=28
Modified System:
After insulating with 65 mm of asbestos wool with aluminum cladding, the hot face
temperature will be 55 °C
Ts = 55 °C
Ta = 28 °C
Substituting these values:
S = [10 + (55 – 28) / 20] x (55 – 28)
= 306 kcal/hr m2
S2 = S = heat loss after insulation (306 kcal/hr m2)
18 | P a g e
Energy Saving Calculation
Pipe dimension and length = Ø250mm,3.5 meter
19 | P a g e
Case three: Existing conditions
Boiler efficiency 85%
Ts=125
Ta=28
S=[10+(125-28)/20*(125-28)=1440 kca/hr m2
Modified System:
After insulating with 65 mm of asbestos wool with aluminum cladding, the hot face temperature
will be 45 °C
Ts = 45 °C
Ta = 28 °C
Substituting these values:
S = [10 + (45 – 28) / 20] x (45 – 28)
= 185 kcal/hr m2
S2 = S = heat loss after insulation (185 kcal/hr m2)
20 | P a g e
Energy Saving Calculation
Pipe dimension and length = Ø150, 47 meter
kcal/year
21 | P a g e
Case Four: Existing conditions
Electricity cost 1.193birr/kwh
Ts=125
Ta=28
S=[10+(95-28)/20*(95-28)=984kca/hr m2
Modified System:
After insulating with 65 mm of asbestos wool with aluminum cladding, the hot face temperature
will be 45 °C
Ts = 45 °C
Ta = 28 °C
Substituting these values:
S = [10 + (45 – 28) / 20] x (45 – 28)
= 185 kcal/hr m2
S2 = S = heat loss after insulation (185 kcal/hr m2)
22 | P a g e
Energy Saving Calculation
Pipe dimension and length = Ø200, 12meter
23 | P a g e
4.3. Estimated Energy Saving
24 | P a g e
4.4. Implementation Plan
25 | P a g e
5.0 Recommendation and Conclusion
We recommend the following points what we have saw during the site inspection period to save
Increase the production or reduce energy consumption, currently the plant working
capacity is around 10% and all motors and pumps which controlled by DOL and Star Delta
is working under load and consume more energy for low production. Therefore, we have
to maximize the production or reduce energy consumption by off some motors and pumps.
The contractor immediately shields all the bare steam pipeline starting from boiler outlet
to MEE system, condensate recovery system and bypass line with jacketing of steam valves
and flange. unless and otherwise AIP with head quarter maintenance expert insulate steam
line and we can save more than 437.4 MWh energy and 521,830 birr per year.
SCADA System, the SCADA is failed during the audit period. as we know industrial
automation system is increasing the efficiency energy utilization. therefore, we must repair
Motor loading, some of induction motor and pumps is running under loading or idle
running, this cause to consume more energy but the production is very less. For example,
the equalization transfer pump capacity is 180m3/h currently this pump working 30m3/h.
this shows that there is energy loss in the system and this cause avoid by installing VFD
control system for this pump and we can save more than 7884 MWh energy and one million
and above birr per year, but it depends on working hours of pump.
Reduce maximum demand charge, both ZLD Process 7B300000000270 CT-400/1 and
ZLD Boiler 7B300000000193 CT-400/1 energy meter MD charge is very high and reduce
26 | P a g e
Conclusion
During site inspection I have list out the above recommendations and it is a critical point from
energy and process perspectives. Therefore, the plant manager and his team with top management
must be committed to solve the problem. the plant manager establishes energy management team
taskforce to manage energy properly and to increase the energy utilization efficiency. if we
implement the above recommendations, we can save more energy and money.
27 | P a g e