Module 2 Field Joint Coatings
Module 2 Field Joint Coatings
Module 2 Field Joint Coatings
ON CORROSION MANAGEMENT
& CATHODIC PROTECTION OF
CGD NETWORKS
SMART LEARNING DIGITAL PLATFORM
▪ Each pipe is 11 to 12
meters long and as such for
every 1 Km of pipe there are
83 to 85 Joints / km.
WHY ARE FIELD JOINT COATINGS IMPORTANT
▪Wrong selection of the field joint coating (Material, Operating Temperature Mechanical
Strength, Resistance to soil stresses, Compatibility with the main line coating)
▪Application in environment not conductive to coating (dew point, high humidity / dust / rain
fall etc )
Cutback
120+/-10mm
150+/20mm
Weld bead
Manual
Semi Auotomatic
Automatic
If there is no bevel, then at the transition area of 3LPE to Steel (step down of 2-3mm
there will be air entrapment leading to possible corrosion at the 3LPE to steel interface
FIELD JOINTS – WELD BEAD HEIGHT/PROFILE
Coating cutback
• Ease of application
FIELD JOINT COATING – TYPE
-PERFORMANCE SAME AS 3LPE / -PERFORMANCE SAME AS 3LPE / 3LPP Surface preparation required St3
3LPP COATING COATING
1. Remove Loose and Soluble 2. Pipe Temperature Above 3. Remove Mill Scale and
Surface Contaminants Dew Point other Insoluble Solids
40μ 60 μ 100μ
Chloride contamination<5 ug/cm2
SURFACE PREPARATION STANDARDS
NACE SSPC Swedish British ISO 8501
#1 White Metal SP5 White Metal Sa3 First Quality Sa3
40μ 60 μ 100μ
SALT CONTAMINATION METER
PIPELINE COATINGS & FIELD JOINT COATING
3 LAYER POLYETHYLENE COATING STORAGE OF LINE PIPE
&
FIELD JOINT COATING
MATERIAL
SURFACE PREPERATION
•Using copper slag blast only the bare steel part of the girth weld area to SA 2½ and a roughness profile
(anchor pattern) between 50 to 100 microns.
• The air compressor shall be checked for delivering air without any oil contamination
•Sweep blast adjacent PE line coating to create a rough surface for a distance minimum
100 mm from the edge of the 3LPE coating.
APPLICATION PROCESS-FIELD JOINT COATING
FBE TOE
APPLICATION PROCESS-FIELD JOINT COATING
APPLICATION PROCESS-FIELD JOINT COATING
Surface profile measurement using Testex tape & Micrometer
•Using copper slag blast only the bare steel part of the girth weld area to SA 2½ and a roughness profile
(anchor pattern) between 50 to 100 microns.
• The air compressor shall be checked for delivering air without any oil contamination
•Sweep blast adjacent PE line coating to create a rough surface for a distance minimum
100 mm from the edge of the 3LPE coating.
APPLICATION PROCESS
Pre heating of the surface Temperature measurement
•Preheat the steel surface 70-80ºC and the adjacent PE line coating to 70 - 80ºC.
• This is very important to create a bond properly to the PE line coating.
APPLICATION PROCESS
Dispensing of epoxy with the help of pumps
•Apply S1301M/S1201M two pack epoxy primer over the girth weld seam first and then on the body
to a wet film thickness of > 200 microns.
APAPPLICATION PROCESS PLICATION PROCESS
APPLICATION PROCESS
SLEEVE INSTALLATION & POST HEATING
APAPPLICATION PROCESS PLICATION PROCESS
APPLICATION PROCESS
SLEEVE INSTALLATION & POST HEATING
INSPECTION OF INSTALLED HEAT SHRINK SLEEVE
Property Test Method Frequency Acceptance Criteria
No.
Wet Film
1 Epoxy primer wet Every Joint (1 reading / quadrant) Min. 200 microns
Gauge
film thickness
Free of defects, air voids and pinholes.
2 Visual Inspection Visual Every Joint Hot melt adhesive flow evident from
both sides.
Every Joint (Three location each quadrant on
Installed Minimum Thickness Min. 3 mm on steel body body Min 2.5
3 steel body) Total 12 readings. Four readings
Thickness of HSS Gauge mm on weld bead
on the weld seam.
Holiday Detection
Brush 5 kV+5 kV/mm
4 (on complete Every Joint
detector (25 kV max)
system)
Peel Force @230C EN-12068 One per 50 joints or one days production 3.5N/mm
5 /
Or Ambient temp. ISO21809 on steel and adjacent line 3LPE coating
EN-12068 One per 50 joints or one days production 0.5 N/mm
6 Peel Force @ 600C /
ISO 21809 on steel and adjacent line 3LPE coating
VISUAL INSPECTION
The inspection of the joint shall be done after the cooling down of the
sleeve and the substrate to ambient temperature.
The sleeve shall be visually inspected for the following points.
✓The weld bead profile contour shall be visible through the sleeve.
✓The ends of the sleeve shall be firmly bonded to the mill coating.
✓There shall be no upstanding edges.
✓Adhesive flow shall be evident at both edges of sleeve around entire
circumference of pipe / sleeve.
▪ No damage to the field joint when the pipe is pulled over the rollers.
▪ As the field joint coating has a step down, the leading edge of the field joint coating
should be designed with a special wear cone so that in case of direct shear forces acting
at the “step down”, only the wear cone should be damaged and not the main field joint
coating.
HDD – FIELD JOINT COATINGS
• Split resistant
• Fiber glass reinforced backing
HOLIDAY DETECTION
A PAPPLICATION PROCESS
PLICATION PROCESS
AP APPLICATION PROCESS PLICATION
PROCESS
AP APPLICATION PROCESS
PLICATION PROCESS
AP
APPLICATION PROCESS
PLICATION PROCESS
DIRAX SLEEVE INSTALLED
THANK YOU