ICE Report 01 - AR - DBD Access Bridge - Submitted
ICE Report 01 - AR - DBD Access Bridge - Submitted
ICE Report 01 - AR - DBD Access Bridge - Submitted
Report Date Written Date submitted to Date reviewed by SCE/DE Date of Quarterly
No. SCE/DE Interview
Page | 1
Continuation Sheet No. 2
This report covers work done on the permanent access bridge for Diamir Bahsha while employed as a Project
Engineer and BIM specialist from September 2020 to August 2021. The bridge is a 312m-long balanced cantilever
box girder design spanning the Indus River in the mountainous region of Bahsha, Pakistan. The primary purpose
of the bridge was to provide access for dam works and transport its turbines across the river. Zeeruk was awarded
the conceptual, detailed and construction supervision contract.
2. Synopsis
This project allowed me to conduct research, analyse site data, deliver presentations, communicate with
stakeholders, and assist team members. Additionally, some of key accomplishments I have achieved are increasing
project efficiency, improving data accuracy, and contributing to successful project outcomes.
Core
Report Attributes
Fulfilled
Diamer Bahsha Dam (DBD) is one of the 4 new dams being built along the Indus River in
Pakistan. These dams are of national significance since they help provide water security and
resilience against flooding in Pakistan.
The access bridge for DBD is a 312m span box-culvert bridge designed for transporting the
dam’s turbine and other infrastructure equipment. I worked with the design team from the
conceptual to detailed design stage as a project coordinator and BIM specialist.
During this project I conducted a range of tasks through the various stages of the project.
Project Tendering
At the tendering stage for the assignment, I prepared a BIM execution plan (BEP) in response
to the Employers Information requirement (EIR.) As this was one of the first BIM enabled
infrastructure projects with contractual BIM deliverables, I had to liaise with external
technology providers (Autodesk) to provide adequate understanding of the software packages
proposed in the BEP to both the client and company management. I proposed in the BEP that I
would train to become an Autodesk Certified Professional (ACP) and deliver presentations to 6(K & E)
stakeholders on BIM execution on the project 6(K & E). The ACP certification reflects 400 hours
of learning and experience and is awarded through a proctored test. I also trained in-house
resources (2-Cad draftsmen) to execute the 3D modelling of concrete, rebar, and post-
tensioning tendons. This work during the tendering stage directly had a positive impact in our 7(K)
firm winning the assignment. 7(K)
Ahson Reza
Development Report No. 01 Page | 2
Continuation Sheet No. 3
One of the bridge’s piers was subject to submersion during flooding season and hence a coffer
dam for construction was proposed. I created the 3D geometry for this and extracted quantity
estimates that were used within the specifications for the sub-contractor’s tender. 1(K & E)
Superstructure 4(K)
I used CSI bridge software to model the construction sequence for the cast in-place box girder
superstructure. The sequencing of the gantry movement, post-tensioning and concrete pouring 1(E)
was challenging for me, and I had to read literature about how the software treated these
various stages and loading to ensure the construction loadings and the resulting camber and
sagging was accurate. I proposed that precast construction for the superstructure be
considered for its health, safety (H&S), and welfare benefits. However, this was deemed
unfeasible due to the high upfront cost of the casting yard and the lack of experience on the
contractor’s end. 4(K) 2(K)
I also modelled the reinforcement and the post-tension tendons for this bridge using a
combination of Revit, AutoCAD and various plugins 1(E). A Revit model with LOD 350 was a
Ahson Reza
Development Report No. 01 Page | 3
Continuation Sheet No. 4
contractual requirement but it was not time efficient to model rebar and tendons using built-
in Revit tools. I assessed various Revit plugins to identify CADS RC3D as a more efficient
modelling tool. There were 40 unique tendon geometries that curved in the X and Y planes.
After some experimentation this too was not efficient to model within Revit so AutoCAD was
used. I federated the model in Navisworks and managed drawing production to ensure the
design was clash-free 2(K).
Ahson Reza
Development Report No. 01 Page | 4
Continuation Sheet No. 5
Core
Report Attributes
Fulfilled
I recorded a total of 56 CPD hours during the period spanning October 2022 to May
2023 (7 months). The detailed records are attached in the appendix of this report
(Appendix D). There was a good variety in the type of CPD recorded. The following
is a brief overview:
• ICE early careers networking event 6(K)
• London Build Expo 2022 for Seminars on BIM and networking. (Met BSI
person here) 6(K)
• Numerous in-house presentations on sustainability, commercial and legal
aspects, and technical presentations.
• STEM promotion event as Bushey Meads school. 7(K & E)
• Online courses on Tekla Structures. 1(K)
• Online webinars covering bridge design workflows using various software. 1(K)
• CSCS preparation and test. 4(K)
• Sustainable Development - Design, Construction And Maintenance – ICE 5(K)
Course
• Construction contracts – ICE 5-week course 3(K)
Ahson Reza
Development Report No. 01 Page | 5
Continuation Sheet No. 6
This should be a brief summary of an industry news topic that you have read and found interesting.
During a recent full-day workshop on sustainability in the civil engineering profession; delivered by
ICE for Rendel graduates, I enquired about the efficacy of “green steel.” Much is known about
reducing the carbon footprint of concrete via substituting its constituents with greener alternatives
than virgin materials. The mechanical and chemical impacts of replacing cement with fly ash, and
aggregates with recycled concrete, amongst various other materials are well documented and
literature on the subject has been in development since atleast the 1980s1.
Reinforcement steel makes up between 10-30% of the cardon footprint of reinforced concrete. The
wide range illustrates how the carbon footprint can vary due to a range of reasons; mining methods,
refining, transport, and project type to name a few. A Life Cycle Analysis (LCA) is usually undertaken
to establish a more specific number. However, until very recently, reinforcement steel with a low
carbon content has not been available owing to various supply and demand side issues. A 2022
report by McKinsey2 titled “Net-zero steel in building and construction” outlines both these
categories. Supply side issues cover technological and logistical challenges. Hydrogen and electric
based furnaces are in development and the McKinsey report claims these technologies could be on-
line by 2030. For supply chain issues, green steel manufacturing has not achieved the scale of
production to allow for competitive cost to conventional steel.
On the demand side of the equation, when comparing carbon reduction investments, a common
approach to comparing various carbon reduction strategies is using a marginal abatement cost
curve. This essentially gives the cost per kg of C02 reduced by a given strategy. For green steel,
this number indicates that substitution with alternative materials, such as basalt reinforcement, yields
the highest marginal CO2 savings.
The discussion thus far assumes that ceteris paribus, demand for reinforcement steel is purely
governed by cost. We know this is not true in the contemporary realm of publicly procured projects.
Green initiatives by public funding bodies, both locally in the UK and internationally, are increasingly
stipulating green targets on their projects via CO2 targets imposed on the Lifecyle of the project they
are procuring. High Speed 2 (HS2) stipulated net zero carbon targets for all construction by 2030.
The contractor was able to optimise design, construction methodology and reduction of material to
bring about a 28.4% reduction in the carbon footprint3. “Green steel,” as discussed in this discussion,
was not used.
In conclusion, “green steel” is a promising material, that will see wide-scale commercial use once
the technical and economical challenges are overcome. This is expected to take place by 2030 and
I am excited to see what opportunities this would give civil engineers in designing our built
environment of the future.
Ahson Reza
Development Report No. 01 Page | 6
Continuation Sheet No. 7
Looking forward should detail any areas of development required to fulfil specific Attributes, and specific
experience required on projects to assist in obtaining these Attributes.
A Development Action Plan (DAP) has been created and attached in appendix E of this report. I look
forward to undertaking training, gaining experience, and achieving higher levels in the various
attributes in line with DAP. Areas of development I particularly look forward to are attribute 2 and 3,
namely management and leadership, and commercial ability. I have been recently seconded to the
HS2 ALIGN site as a designer’s site representative and hope to use this experience to make
progress on these attributes.
In conclusion, I believe documenting my experience and planning for growth via the methods used
in this report is a robust way for professional and personal growth within the profession. I look forward
to continuing this practice.
Ahson Reza
Development Report No. 01 Page | 7
Continuation Sheet No. 8
Ahson Reza
Development Report No. 01 Page | 8
Continuation Sheet No. 9
E Experience Have achieved the attribute in different situations, working under supervision
A Ability Have achieved the attribute in different situations, assisting others and working
without supervision
This section highlights to your Delegated Engineer when you are claiming a new level of achievement for Attributes
(making it easier for them review).
Ahson Reza
Development Report No. 01 Page | 9
Continuation Sheet No. 10
Ahson Reza
Development Report No. 01 Page | 10
Continuation Sheet No. 11
Ahson Reza
Development Report No. 01 Page | 11
Continuation Sheet No. 12
Appendix C – Bibliography
Malhotra, E. E. (1980). Fly Ash for Use in Concrete - A Critical Review. International Concrete
Abstracts Portal, 59-73. doi:10.14359/6991
Ravina, D., & Mehta, P. (1988). Compressive strength of low cement/high fly ash concrete. Cement
and Concrete Research, 18(4), 571-583. Retrieved 5 15, 2023, from
https://sciencedirect.com/science/article/pii/0008884688900506
Ahson Reza
Development Report No. 01 Page | 12
Appendix D - CPD Summary
CPD SUMMARY 19 May 2023
Name: Ahson Haider Reza ICE Member No. 90035303
Job role and responsibilities: Graduate Engineer
ATTRIBUTES OF MEMBER CHARTERED CIVIL ENGINEER (CEng MICE) 2022 2023 2024 2025 Total to date
5. Sustainable Development 0 8 8
7. Professional Commitment 0 9 9
TOTALS 4 52.5 56.5
7. Professional Commitment
16% 1. Understanding and Practical
Application of Engineering
21%
3.Commercial Ability
13%
5. Sustainable Development
14%
Sustainable Development -
Design, Construction And 10 May 2023 8
Maintenance
knowledge
also need to learn efficient I will read some literature on the that are inline with
I will need time to attend
I will also be achieving ICE Attribute 1 : modelling workflows so the model subject. project requirements
webinar on the subject.
Understanding and Practical can be reiterated for various Reinforced Concrete Design to (design of culvert)
Application of Engineering at level 1 geometries and conditions. Eurocode 2[B.Mosley-J.Bungey-
R.Hulse,2007]
welfare to have CSCS cards using the app for this and will sit card. cost of app and test.
the test on the 3rd of Feb.
Knowledge of sustainable
Sustainable Sustainable development is an ICE Attend 1 day sustainability in Attend course and engage in the course was arranged development and the
Apr-23 May-23
5
Development attribute for CEng construction course run by ICE discussions during training. by Rendel role of civil engineers
within it
Feedback from my DE on
Write my ICE attribute acheiivement attribute achievement
Improve my report and letter Succesful sign-off of the
report and gain feed back from DE. form.
Interpersonal Skills Interpersonal Skills and Management writing skills. attributes covered in first
Feb-23 Make and present HS2 lessons learned Time from company to Mar-23
6
and Management is an ICE attribute for CEng Imrpove my presentation skills to ICE attribute
presentation to University event and in- travel to University for 1
address various types of audience acheivement form.
house day and give
presentation.