ESC1
ESC1
ESC1
METHODS OF ESTIMATION
ESTIMATION
Estimation is the scientific way of working out
the approximate cost of an engineering
project before execution of the work.
2) SPECIFICATIONS
a) General Specifications:
This gives the nature, quality of work and materials in general
terms to be used in various parts of wok. It helps to form a
general idea of building.
b) Detailed Specifications:
This gives the detailed description of the various items of work
laying down the Quantities and qualities of materials, their
proportions, the method of preparation workmanship and
execution of work.
Department of Civil
Engineering
3) RATES
For preparing the estimate the unit rates of each item of
work are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the
construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of masons,
carpenters, Amador, etc.,
LUMPSUM:
While preparing an estimate, it is not possible to work out in
detail in case of petty items. Items other than civil
engineering such items are called lump sum items or simply
L.S.Items.
Department of Civil
Engineering
Factors to be considered for estimation
Department of Civil
Engineering
Factors to be considered for estimation (-ctd-)
Department of Civil
Engineering
Rough (or) approximate estimate
Preliminary or approximate estimate is required for studies of
various aspects of work of project and for its administrative
approval.
It can decide, in case of commercial projects, whether the net
income earned justifies the amount invested or not. The
approximate estimate is prepared from the practical knowledge
and cost of similar works.
The following are the methods used for preparation of
approximate estimates.
1) Plinth area method
2) Cubical contents methods
3) Unit base method.
Department of Civil
Engineering
1) Plinth area method
cost of construction = Plinth area x plinth area rate.
2) Cubical Contents Method
It is more accurate that the other two methods viz., plinth area
method and unit base method.
cost of construction = Total cubical contents x Local Cubic Rate.
3) Unit Base Method
. For public buildings, cost. Per person (cost per capita) is used.
For example,
Students hostel - cost per student
Hospital - Cost per bed
Hotel - Cost per Guest
Department of Civil
Engineering
EXAMPLE 1
Prepare a Rough-cost Estimate of a residential building project with
a total plinth area of all building of 1500 sq.m. given that:
Plinth Area Rate = Rs: 950.00 / sq. ft.
Extra for special architectural treatment = 1.5 % of the buiding
cost.
Extra for water supply and sanitary installations = 5 % of the
building cost.
Extra for internal installations = 14 % of the buiding cost
Extra for Electric & Sui gas services = 16 % of buiding cost
Contigencies 3 % overall
Supervision charges = 8 % overall
Design charges = 2 % overall
Department of Civil
Engineering
EXAMPLE 2
Prepare a Rough-cost Estimate based on unit costs of per
unit plinth area basis of a four storeyed office building
having a carpet area of 2000 sq.m. for obtaining the
administrative approval of the Government. It may be
assumed that 30 % of the built up area will be taken by the
corridors, verandas, lavatories, staircase, etc. and 10 % of
built up area will be occupied by walls. The following data is
given:
Department of Civil
Engineering
DETAILED ESTIMATE
• Detailed estimates are prepared by carefully and
separately calculating the costs of various item of the
work that constitute the whole project from the
detailed working drawings after the design has been
finalized.
Department of Civil
Engineering
DETAILED ESTIMATE
Department of Civil
Engineering
PRICED BILL OF QUANTITIES
Department of Civil
Engineering
DETAILED ESTIMATE
Each item of the work is then multiplied by its estimated
current rate calculated by a fixed procedure to find out
cost of the item.
Department of Civil
Engineering
DETAILED ESTIMATE
Besides drawings and details of measurements and
calculation of quantities (Bill of Quantities), the following
documents are also usually submitted with the detailed
estimate for obtaining Technical Sanction:
Department of Civil
Engineering
METHODS OF DETAILED ESTIMATE
The dimensions, length, breadth and height or depth
are to be taken out from the working drawings (plan,
elevation and section).
Department of Civil
Engineering
LONG WALL & SHORT WALL METHOD
Department of Civil
Engineering
CENTER LINE METHOD
Department of Civil
Engineering
Department of Civil
Engineering
Estimation of Quantity of
Concrete in Foundation
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
Length of Long wall = 5.3+0.9 = 6.2 m Length of Short wall = 4.3-0.9 = 3.4 m
Quantity of concrete in foundation = 2 x (6.2+3.4) x 0.9 x 0.3 cu.m
Department of Civil
Engineering
Estimation of Quantity of
Brickwork in 1st step Foundation
Department of Civil
Engineering
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
width of foundation = 0.6 m
Total quantity of brickwork in 1st step foundation = 19.2 x 0.9 x 0.3 cu.m
Department of Civil
Engineering
Long Wall & Short Wall method:
Length of Long wall = 5.3+0.6 = 5.9 m Length of Short wall = 4.3-0.6 = 3.7 m
Quantity of brickwork in 1st step foundation = 2 x (5.9+3.7) x 0.6 x 0.3 cu.m
Department of Civil
Engineering
Estimation of Quantity of
Brickwork in super structure
Department of Civil
Engineering
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
width of wall = 0.3 m Total quantity of brickwork in wall = 19.2 x 3.5 x 0.3 cu.m
Department of Civil
Engineering
Long Wall & Short Wall method:
Length of Long wall = 5.3+0.3 = 5.6 m Length of Short wall = 4.3-0.3 = 4.0 m
Quantity of brickwork in wall = 2 x (5.6+4.0) x 0.3 x 3.5 cu.m
Department of Civil
Engineering
Problem-2
Estimate in detail the quantities of following items of work for a
given plan and section as shown in Fig.2 using Centre line method
and Long wall & short wall method.
Concrete in foundation
Brickwork in 1st step in foundation
First class brickwork in super structures
Department of Civil
Engineering
Department of Civil
Engineering
Estimation of Quantity of
Concrete in Foundation
Center Line method:
Total Length of Center Line = (4 x 5.3) +(3 x 4.3) = 34.1 – 0.9 = 33.2 m
width of foundation = 0.9 m
Total quantity of concrete in foundation =33.2 x 0.9 x 0.3 cu.m
Department of Civil
Engineering
Long Wall & Short Wall method:
Length of Long wall = 5.3+5.3+0.9 = 11.5 m Length of Short wall = 4.3-0.9 = 3.4 m
Quantity of concrete in foundation= [ (2x11.5) + (3X3.4) ] x 0.9 x 0.3 cu.m
Department of Civil
Engineering
References:
https://www.wikipedia.org/
https://nptel.ac.in/course.php
https://www.vidyarthiplus.com/studymaterials.php