Geotechnical Engineering Final Report
Geotechnical Engineering Final Report
TECNHNOLOGY
COLLEGE OF ENGINEERING
8146419
ABSTRACT
This report contains geotechnical engineering designs based on information obtained from
laboratory and field tests performed since the site investigation was conducted on the 24th of March
2023 up to the 7th of April 2023.
Among the field tests performed were 2 trial pit tests, one each at the proposed section of roadway
and the other at the proposed section of the car pack for the engineering laboratory. Moisture
content test, compaction test, Atterberg limits test, laboratory CBR test and SPT were also
conducted. However, the results from DCP, CBR test and SPT, Atterberg limit test indicate that
the in-situ soil up to at least a meter deep is generally poor and of low strength and as such would
not be able to support the expected traffic or structural loads without any improvements or
replacements. SPT and trial pit test results also indicate the presence of a high-water table.
The foundation design involves using pile groups consisting of four 300mm diameter piles spaced
at 800mm center to center.
Materials and aggregates to be used for the concrete to be used for general construction works will
be sourced from a borrow pit in Bonwire.
At the end of this document is an environmental impact assessment of all geotechnical activities
that have already taken and are to take place for the construction of the road, car park and
laboratory building.
i
TABLE OF CONTENTS
ii
5.0 SOIL IMPROVEMENTS ........................................................................................ 16
11.0 APPENDIX................................................................................................................ 31
Appendix D ......................................................................................................................... 35
iii
TABLE OF FIGURES
Figure 1: Satellite Image of Site for Development ................................................................... 3
Figure 2: Topology of Development Site ................................................................................. 4
Figure 3: Image of in-situ vegetation cover .............................................................................. 6
Figure 4: Elevation profile of land from engineering labs to IRAI building ............................ 7
Figure 5: Image of erosion gullies on site ................................................................................. 7
Figure 6: Image of water accumulating in ponds...................................................................... 8
Figure 7: SPT N value versus Borehole depth ........................................................................ 11
Figure 8: Stratigraph for soil underlying roadway .................................................................. 13
Figure 9: PSD of borrow material ........................................................................................... 22
Figure 10: Test results for borrow material ............................................................................ 23
Figure 11: Grading Curve for 20mm Chippings ..................................................................... 35
Figure 12: Grading Curve for 14mm Chippings ..................................................................... 35
Figure 13: Grading curve for 10mm chippings....................................................................... 36
LIST OF TABLES
iv
Table 15: Negative impacts of geotechnical activities ........................................................... 29
Table 16: Positive Impacts of geotechnical activities ............................................................. 29
LIST OF ABBREVIATIONS
i. TBD ~ To be determined
ii. OMC ~ Optimum Moisture Content
iii. MDD ~ Maximum Dry Density
iv. DCPT ~ Dynamic Cone Penetration Test
v. SPT ~ Standard Penetration Test
vi. IRAI ~ Integrated Rural Arts and Industry
vii. PSD ~ Particle Size Distribution
viii. USCS ~ Unified Soil Classification System
v
1.0 INTRODUCTION
The Kwame Nkrumah University of Science and Technology, KNUST, Kumasi in an effort to
support the industrial and socio-economic development of Ghana is undertaking redevelopment of
its facilities; this includes the expansion of existing facilities. The site for the expansion is to the
south of the existing facilities for which a master plan has been developed. The objective of the
project is to develop the required infrastructure to support the Master Plan and develop a new Civil
Engineering laboratory to replace the existing facility built some 50 years ago. The development
will be done in two phases where phase one involves several acres of land where the full
infrastructure would be developed and phase two is anticipated to commence in the next 10 years.
Complete infrastructural services, including drainage, water supply and waste management, are
required for the entire master plan but implementation will be limited to phase one works.
The development office of KNUST, the client has commissioned a planning and architectural
consulting firm to undertake the general planning and design of the architectural aspects of the
scheme. The client has completed and approved the planning proposals and architectural designs
of the laboratory. However, the design of site layout has been partly completed as the planners are
awaiting the engineers’ advice, especially regarding the road layout and other supplementary
infrastructure. It is now required to propose conceptual engineering designs and undertake the
design of civil engineering infrastructure works for the proposed development scheme.
To this end, the client has commissioned M/s EDCIV 2023 civil groups to design the civil
engineering infrastructure works for the entire project site, emphasizing the development of phase
one works for the university in Kumasi.
To develop the required infrastructure to support the required infrastructure to support the Master
Plan and develop a new Civil Engineering laboratory to replace the existing facility built some 50
years ago. The components of the infrastructure works to be designed include:
1
❖ Road Network, Vehicular Parking
❖ Drainage, Water Supply and Distribution Networks;
❖ Solid and Liquid Waste Management System (Sewerage networks)
❖ Any supplementary facilities
i. Carry out the appropriate geotechnical investigation to support the safe and economic
design of the foundation of the Laboratory Building.
ii. Carry out the foundation design of the Laboratory Building.
iii. Provide the necessary information about the sources and quality of construction
materials of geologic origin
i. Carry out the appropriate investigation to support the safe and economic design of the
pavement of the road network and parking areas.
ii. Provide the necessary information about the sources and quality of construction
materials of geologic origin required
2
2.0 DESK STUDY
The site ranges from the old engineering laboratories past the Bibini stream to the disability center
and is bordered on the east and west by P.V. Obeng Avenue and the walls between KNUST campus
and Kotei.
DCP tests were performed along the sections where the new roads will be constructed and also at
the car park.
Boreholes were drilled at five locations within the area where the new engineering laboratory will
be constructed
Two trial pit tests were conducted, one at the proposed location for the roadway and the other at
the proposed section of the car park.
3
2.2 Topology of study area
The proposed site for the development of the new engineering laboratory is located in a valley that
is oriented east to west. The lowest point is 243m above sea level. The old engineering laboratories
which are about 100m north of the river are at an elevation from 247m to 257m and the Faculty of
ARTS building about 250m south is at an elevation of about 261m above sea level.
4
2.3 Tests carried out
❖ Dynamic cone penetration test (DCPT) to determine the in-situ subgrade strength for the
road pavement.
❖ Trial pitting to observe the changes in strata, the extent of weathering and the existence of
any shear planes. Samples from trial pit will be collected for laboratory testing.
❖ Standard penetration test (SPT) to determine various characteristics of the sub surface
layers (i.e., bearing capacity at various depths, clays), the height of water table
5
3.0 FIELD RECONNAISANCE
The reconnaissance survey of the site for the proposed lab project was conducted on the 24 th of
February, 2023.
❖ Most of the land area is used for farming and is covered in various crops and other forms of
vegetation. Crops like lettuce and cassava are grown in the area; the other vegetation on the
land is mostly grasses and shallow rooted trees like plantain and a few deep-rooted trees.
❖ The area is low lying and forms a valley between the old engineering laboratories and the
Industrial rural arts building
6
Figure 4: Elevation profile of land from engineering labs to IRAI building
❖ There were sightings of massive gullies formed from erosion by water exposing underground
pipes
7
❖ Accumulation of water in ponds, which may indicate high water table
8
4.0 TESTS PERFORMED
This section contains a summary of geotechnical information obtained from performing the
following tests on site and in the lab:
{ 4. Compaction test
The following were conducted on site and are more reflective of actual in-situ properties of the
soil.
Two trial pits were dug where pit 1 was dug at the proposed location of the roadway and pit 2 was
dug at the proposed location of the car park for the engineering laboratory. In both pits, the walls
of excavation were crumbling. Although no groundwater was encountered in trial pit two, the soil
in the bottommost layer was wet which indicates that the groundwater level may be dynamic.
9
Table 1: Soil description from trial pit tests
10
4.1.2 SPT for Laboratory building
SPT N-value
0 20 40 60 80
0
1
2
3
4
5
6
7
Depth (m)
8
9 BH1
10 BH2
11 BH3
12
Average n-value
13
Refusal
14
BH4
15
BH5
16
The graph above illustrates how the strength of the existing soil varies from 1m below the surface
to 15m below the surface. Higher N-Value indicates higher strength. Refusal for SPT was 50
blows. The highest level of Groundwater recorded static and dynamic combined was at 2m below
the surface. We can infer from the graph that up 10m below the surface, the soils are weak since
the all have N-values less than 20
11
4.1.3 DCPT for roadway section
The 8 DCP tests were conducted along the stretch of the proposed road. The lowest CBR
determined for the first layer of soil was 3% and the highest was 8%. For the next layer, the
minimum was 2% and maximum 5% and for the 3rd underlying layer which did not reveal itself at
all points had its lowest CBR to be 4% and highest to be 8%.
Layer
DCP Layer
Thickness D - Value CBR
Point ID
[mm]
1 500 80.12 3
1
2 400 50.00 5
1 300 41.38 6
2 2 300 100.00 2
3 300 50.00 5
1 400 64.66 4
3
2 500 38.39 6
1 200 32.14 8
4 2 500 41.99 6
3 200 32.14 8
1 400 43.23 6
5 2 300 100.00 2
3 200 64.29 4
1 400 65.69 4
6 2 300 100.00 2
3 200 50.00 5
1 400 35.00 7
7 2 300 100.00 2
3 200 64.29 4
1 400 72 3
8 2 300 51.08 5
3 200 54.29 4
12
4.1.4 Strati-graph
The following graph represents the organization and thicknesses of the different soil layer
encountered during DCP test
Chainage
1 2 3 4 5 6 7 8
0
100
Depth below surface in mm
200
300
400
500
600
700
800
900
Lower Bound of Layer Surface
13
4.2 Laboratory test results
The following moisture contents represent the existing moisture contents of the soils as they
were on site.
This is a modified proctor compaction test, with a hammer weight of 6.782Kg falling through
470mm.
The soil in trial Layer 2 of trial pit 1 has plasticity index of 13 and that of layer 3 from the same
pit is 17, These soils would be regarded as highly expansive since PI > 12.
14
4.1.3.1 Soil classification according to USCS
This test was performed in accordance with BS 1377, with a loading speed of 1.0 mm/min.
Proving ring constant is 0.02.
1.92KN
2.00
Force in KN
1.50 1.32KN
1.00
0.50
15
5.0 SOIL IMPROVEMENTS
It can be observed from lab and field tests that the soil is not adequate in-situ is not adequate for
the construction of the roadways and the building. The soil be replaced by a higher quality soil up
to 3m deep for the laboratory building.
The material will be sourced from a borrow pit located at Bonwire. It is located at 60 48’06” N, 1
0 27’47” W, which is about 23km form the project site about 40min drive.
16
6.0 FOUNDATION DESIGN
The ultimate bearing capacity of the pad footing was determine using Terzaghi’s bearing
capacity equation.
The maximum expected load from the laboratory building columns as provided by the structural
consultant is 2.0MN. The smallest pad footing will therefore be designed to be able to support this
maximum load. A factor of safety of 2 will be applied to ultimate bearing capacity to obtain the
allowable bearing capacity.
Table 7: SPT N-values and bearing capacity factors for existing soil
Table 8: Table showing variation of Bearing capacity with footing size at 5.5m depth
B qu in kN qa in kN
0.5 3305.68 1652.84
1 3679.54 1839.77
1.5 4053.40 2026.70
2 4427.27 2213.63
2.5 4801.13 2400.56
3 5174.99 2587.50
17
Table 9: Variation of Bearing capacity with footing size at 5.5m depth
2700.00
2500.00
Allowable bearing capacity
2300.00
2100.00
1900.00
1700.00
1500.00
0 0.5 1 1.5 2 2.5 3 3.5
Footing size
In order to determine the ultimate load capacity of a single pile, the following formula derived
from Terzaghi’s bearing capacity formula was employed
Where Pbu is the ultimate base capacity of the single pile, Psu is the ultimate shaft capacity of the
pile and W is the weight of concrete pile.
The pile group will consist of four 300mm diameter, 6m long concrete piles spaced at 800mm
center to center. They will form two rows and two columns or piles from plan
Up to 1m of soil from the surface will be replaced with the soil from the quarry but the soil below
that will be retained and the piles will be driven through 6m of soil in total.
18
6.3.1 Pile Specifications
The ultimate Base Capacity of a single pile is determined by the relation below:
Assuming the soil is cohesionless, 𝑐 = 0, for the first 1m of imported soil, the values of the
parameters need to determine the base capacity of the pile are
For the remaining 5m of in-situ soil, the values of the parameters need to determine the base
capacity of the pile are
Substituting all the appropriate values into equation (2), we get ultimate base capacity of pile,
𝑃𝑏𝑢 = 3322.76𝑘𝑁 = 𝟑. 𝟑𝟐𝑴𝑵
19
1 5
𝑃𝑠𝑢 = ∑ 𝐶 [∫ 𝛼𝐶𝑢 + ∫ 𝛼𝐶𝑢 ] − − − (3)
0 1
Assuming the soil is cohesionless, 𝑐 = 0, for the first 1m of imported soil, the values of the
parameters need to determine the base capacity of the pile are
For the remaining 5m of in-situ soil, the values of the parameters need to determine the base
capacity of the pile are
Substituting all the appropriate values into equation (3), we get ultimate shaft resistance of pile,
𝑃𝑠𝑢 = 161.08𝑘𝑁 = 𝟎. 𝟏𝟔𝑴𝑵
Substituting the values of ultimate base capacity and shaft resistance and weight of a single pile
into equation 1, we get an ultimate load capacity, 𝑃𝑢 = 3473.85𝑘𝑁 = 𝟑. 𝟒𝟕𝑴𝑵
Applying a factor of safety of 3 to the ultimate load capacity to obtain the allowable load
𝑃𝑢
capacity, 𝑃𝑎 = = 1157.95𝑘𝑁 = 𝟏. 𝟏𝟔𝑴𝑵
3
𝐷
Diameter, D Spacing, s 𝜃 = tan−1( ) m n Efficiency, ε
𝑠
20
0.3 .8 20.56 2 2 0.77
The efficiency of the pile group has been estimated to be 0.77, thus we can determine the
allowable load capacity of the pile, Pg to be
𝑃𝑔 = 𝜀 × 𝑚 × 𝑛 × 𝑃𝑎 − − − (4)
Substituting all relevant values into equation 4, we get 𝑃𝑔 = 3573.89𝑘𝑁 = 3.57𝑀𝑁 ≈ 𝟑. 𝟔𝑴𝑵
In order for the pile to be considered adequate enough to support the maximum column load, the
condition must be satisfied, 𝑃𝑔 ≥ 𝑀𝑎𝑥𝑖𝑚𝑢𝑚 𝑐𝑜𝑙𝑢𝑚𝑛 𝑙𝑜𝑎𝑑
Since 𝑃𝑔 (3.6𝑀𝑁) = 𝑀𝑎𝑥 𝐶𝑜𝑙. 𝑙𝑜𝑎𝑑(3.5𝑀𝑁), the pile is adequate. Factor of safety has been
applied to ensure that pile is far from the brink of failure.
21
7.0 SOURCE OF CONSTRUCTION MATERIALS
Information about borrow pit locations around the project site was acquired from the Ghana
Highway Authority (GHA). A borrow pit located at Bonwire was selected due to its closeness to
the project site. It is located at 60 48’06” N, 1 0 27’47” W, which is about 23km from the project
site. Results of lab tests conducted on samples from the borrow by the GHA was obtained. The
results indicated that it met the required standards for Material class G60 as stated in Table 12.1,
Section 12, Natural Material Subbase and Base from the Standard Specification for Road and
Bridge Work.
USCS classification
22
Figure 10: Test results for borrow material
23
7.1 Aggregates for Pavement Sealing Works
A. Kanin Quarry, located near Bonwire, which is about 23km away from the site was selected.
Due to time constraints, results from lab tests conducted on samples from the quarry site was
obtained from GHA for assessment. The results shows that the materials meet the stated
specifications. Summary of the results obtained are tabulated below
Table 11: Test results for 14mm chippings from Borrow pit
Aggregate
24.90% Max 25% BS 812 PART 110
Crushing Value
Los Angeles
34.1 Max 40% ASTM C131
Abrasion Value
24
Table 12: Test results on 10mm chippings from borrow pit
Aggregate
Impact Value 22.30% Max 25% BS 812 - PART 112
Aggregate
22.60% Max 25% BS 812 PART 110
Crushing Value
Water
2.1 2.5 ASTM C 127
Absorption
Los Angeles
21.8 Max 40% ASTM C131
Abrasion Value
25
7.2 Aggregates for Concrete mix
Chippings
Chippings for concrete mix will be sourced from A. Kanin Quarry. Summary of laboratory
results is tabulated below;
Aggregate
25.91% Max 25% BS 812 PART 110
Crushing Value
26
Los Angeles
8.4 Max 40% ASTM C131
Abrasion Value
Sand pits were located at areas around the project site. It was ensured that the location where
sand will be burrowed for the concrete mixes didn’t interfere with the project layout plan.
Samples were taken for lab tests and the results indicated that they meet the required
specifications. Quarry dust will be sourced from the A. Kanin Quarry. A summary of the
laboratory test results is tabulated below.
Table 14: Test results for fine aggregates from borrow pit
Glass
Organic impurities ≤ glass
Standard
GSSRB Standard AASHTO T21
Colour
Colour no. 3
No.1
Fineness
Modulus 3.70 BS 882 BS 812 - PART 112
27
Test On Fine Aggregates
Description: Aggregate For Concrete Works
Glass ≤ Glass
Organic
Standard GSSRB Standard AASHTO T21
Impurities
Colour No.1 Colour No. 3
Fineness BS 812 -
3.70 BS 882
Modulus PART 112
Loose Bulk
1.748g/cm3 BS EN 1097 - 3
Density
28
8.0 ENVIRONMENTAL IMPACT ASSESSMENT
The effects of the various geotechnical activities mentioned in this report on the environment are
highlighted in this chapter as well as measures to mitigate some of the adverse effects.
29
9.0 CONCLUSION and RECOMMENDATION
From the preliminary site investigation, it was quickly realized that the soil was weak and there
would need to be improvement. From Atterberg limit tests, the liquid limit of the soil in trial pit 1
between 0.18m to 0.84m was determined to be 26.61%, and for trial pit 2, liquid limits were
determined to be 22.4% and 23.08 % for 0m to 0.49m and 0.49m to 1m below the soil surface
respectively which are fairly low water contents for the soil to start behaving like a liquid. Also,
we can infer from the DCP tests although incomplete that the soil has low strength with CBR of
the first layer between 2% and 8% and that of the second layer being between 2% and 6%.
Based on this realization, soil form Consar Quarry has been selected to be used for to replace the
first 1m of soil on site where the road and laboratory building will be. This will provide additional
strength for the subgrade however, it is not enough to support the structural loads. As a result, pile
foundations will be constructed to a total depth of 9m below the surface where per my analysis
will be adequate enough to support the maximum column load of 3.5MN. The piles will also help
to resist uplift and overturning forces that may be induced by water pressure underground.
The borrow pit at Bonwire will serve as the main source of materials for construction of roads and
mixing of concrete for buildings.
I recommend that piles are cast in-situ rather than driven to prevent excess noise and also to
minimize disturbance to the soil.
Due to the high-water table, I recommend the use of geotextiles at the maximum height of water
to prevent seepage of water to the surface.
30
11.0 APPENDIX
Appendix A – Formulas
𝐷
❖ Coefficient of uniformity, 𝐶𝑢 = 𝐷60
10
(𝐷30 )2
❖ Coefficient of gradation, 𝐶𝑐 = 𝐷
60 ×𝐷10
31
Appendix B – SPT Borehole results
BH1
Overburden
Depth (m) SPT n-values Cn Ce Cb Cs Cr Ncor
Pressure in kN/m2
1 9 18.00 2.0000 0.6 1.05 1.2 0.95 13
2 2 36.00 1.6313 0.6 1.05 1 0.95 2
3 3 42.19 1.5069 0.6 1.05 1 0.95 3
5.12 12 57.88 1.2865 0.6 1.05 1.2 0.95 11
6 8 64.76 1.2163 0.6 1.05 1 0.95 6
7.5 9 77.05 1.1151 0.6 1.05 1 0.95 6
BH2
Overburden
Depth (m) SPT n-values Cn Ce Cb Cs Cr Ncor
Pressure in kN/m2
1 12 18.00 2.0000 0.6 1.05 1 0.95 14
2 3 26.19 1.9126 0.6 1.05 1 0.95 3
3 4 28.67 1.8280 0.6 1.05 1.2 0.95 5
4.5 5 37.95 1.5888 0.6 1.05 1.2 0.95 6
6 11 44.24 1.4716 0.6 1.05 1.2 0.95 12
7.5 7 56.52 1.3019 0.6 1.05 1.2 0.95 7
BH3
Overburden
Depth (m) SPT n-values Cn Ce Cb Cs Cr Ncor
Pressure in kN/m2
1 12 18.00 2.0000 0.6 1.05 1 0.95 14
2 3 36.00 1.6313 0.6 1.05 1 0.95 3
3 4 54.00 1.3319 0.6 1.05 1.2 0.95 4
4.5 5 63.29 1.2303 0.6 1.05 1 0.95 4
6 11 72.57 1.1490 0.6 1.05 1.2 0.95 9
7.5 7 81.86 1.0818 0.6 1.05 1.2 0.95 5
32
BH4
Overburden
Depth (m) SPT n-values Cn Ce Cb Cs Cr Ncor
Pressure in kN/m2
1 12 18.00 2.0000 0.6 1.05 1.2 0.95 17
2 3 36.00 1.6313 0.6 1.05 1 0.95 3
3 4 53.60 1.3369 0.6 1.05 1.2 0.95 4
4.5 5 62.89 1.2342 0.6 1.05 1 0.95 4
6 11 78.67 1.1035 0.6 1.05 1.2 0.95 9
7.5 7 95.46 1.0018 0.6 1.05 1.2 0.95 5
BH5
Overburden
Depth (m) SPT n-values Cn Ce Cb Cs Cr Ncor
Pressure in kN/m2
33
Appendix C – Compaction Curves
Pit 1 Layer 2
1.000
0.900
2198Kg/m3
0.800
0.700
0.600
0.500
0.400
0.300
0.200
0.100
0.000 8.78%
0 1 2 3 4 5 6
Pit 1 Layer 3
1.000
0.900 2095Kg/m3
0.800
0.700
0.600
0.500
0.400
0.300
0.200
0.100
0.000 9.85%
0 1 2 3 4 5 6
34
Appendix D
35
Figure 13: Grading curve for 10mm chippings
36