Testing CT
Testing CT
Testing CT
Abel Gonzalez
January 2016
1
What is a CT
A Current Transformer (CT) is an instrument transformer with its
primary winding connected in series with the conductor carrying the
current we want to measure or control.
2
CT use.
3
Metering CT’s
CT’s used for metering have to maintain a high degree of accuracy
over the full range of current levels from ~10% to 100% of the full
load CT rating.
4
Protection CT’s
Protection CT’s serve as inputs for a power system’s fault protection.
They must be accurate under overload and fault conditions.
5
Transformers
6
Construction Types of Current
Transformers
Window Bar
7
Substation Class Circuit Breakers' CTs
8
Current transformers
9
Terms used.
RATIO
EXCITATION:
• CURVE
• VOLTAGE
• CURRENT
• IMPEDANCE
KNEE POINT
EQUIVALENT CIRCUIT/DIAGRAM
POLARITY
BURDEN
CLASSIFICATIONS T AND C
RELAY ACCURACY CLASS
MULTI-TAPS ACCURACY
SATURATION ERROR - RATIO/ANGLE
10
Ratio.
11
Ratio Test – Current Method
A suitable current, below saturation, is applied to the primary
winding, and the secondary current is measured.
12
Ratio Test – Voltage Method
A suitable voltage, below saturation, is applied to the secondary
winding, and the primary voltage is measured.
The turns ratio is approximately equal to the ratio of the secondary
voltage to measured primary voltage.
For metering applications: ±0.1% for ratio and ±0.9mrad (3min) for
phase angle.
For other applications: ±1.2% for ratio and ±1 degree for phase
angle.
13
14
15
16
EXCITATION CURVE
17
Excitation/Saturation Test
The voltage applied to the secondary winding of the CT is varied, and
the current flowing into the winding at each selected value of voltage
is recorded.
Readings near the knee of the excitation curve are especially
important in plotting a comparison curve.
18
Excitation Curve(Measured)
19
Excitation Curves. Multi Tap CT.
20
Excitation Curves. Multi Tap CT. Measured.
21
Knee
22
Knee IEEE 45.
23
Transformers. Equivalent Circuit. Precedent.
24
Equivalent Circuit.
25
Polarity
26
Polarity
http://engineering.richmondcc.edu/Courses/EUS%20110/Notes/Current%20Transformer.pptx
27
Polarity
http://engineering.richmondcc.edu/Courses/EUS%20110/Notes/Current%20Transformer.pptx
28
Polarity Test
Polarity tests prove that the predicted direction of secondary current
flow is correct for a given direction of primary current flow.
Polarity marks designate the relative instantaneous directions of the
currents.
As the primary current is entering the primary terminal, the
corresponding secondary current is simultaneously leaving the
similarly marked secondary terminal.
29
Polarity Test – Voltmeter Method
(IEEE C57.13.1-2006)
When an AC voltage is applied to the primary winding of a CT, the
transformed voltage should appear on the secondary winding, in
phase with the voltage on the primary winding, or lagging within a
few degrees.
The voltmeter connected as shown, should read the difference
between the primary and secondary voltages. If incorrect, the sum of
the two voltages will be ~180º apart.
30
Polarity Test – Phase Angle Method
(IEEE C57.13.1-2006)
An AC test voltage of magnitude less than the CT’s knee-point
voltage can be connected to the secondary winding of the CT as
shown below.
The phase angle between the primary and secondary voltages are
monitored independent of magnitude.
• For correct polarity, the phase angle will be ~0º
• For incorrect polarity, the phase angle will be ~180º.
31
Burden
32
Equivalent Circuit.
33
Burden Test
Verifies that a CT will maintain its specified accuracy under a
specified set of load conditions.
Expressed as either:
• VA and power factor at a specified value of current
• Total impedance with respect to both resistive and reactive
components.
34
Burden Test
35
CT Class.
CLASS T:
CTs that have significant leakage flux within the
transformer core - class T; wound CTs, with one or
more primary-winding turns mechanically encircling
the core. Performance determined by test.
36
CT Class.
CLASS C or K:
37
Classifications.
38
Standard Secondary Voltages and Burden.
39
Equivalent Circuit. Main Source of Error.
Ie = I1’’ – I2
40
41
Metering Class CT’s
42
CT limits of accuracy classes. Metering.
43
CT equivalent parallelogram
44
45
ANGLE
46
Ratio
47
Winding Resistance Test
Measures the CTs winding (DC) resistance from one external
terminal to another.
A test current is injected into the winding and the corresponding
voltage drop across the winding is measured. Resistance is
calculated using Ohm’s law.
A DC test will always cause a residual magnetization of the core
which may affect other test results. IEEE C37.110 recommends that
the CT be demagnetized after this test.
48
Demagnetization
Used to eliminate the effect of residual magnetism.
Achieved by slowly ramping the secondary RMS voltage and taking
the CT to saturation region, then slowly decreasing the voltage back
to zero.
49
Insulation Resistance Test
(IEEE C57.13.1-2006)
Measured resistance values should be compared with those of
similar devices or circuits.
Readings lower than those known to be good should be carefully
investigated.
The generally accepted minimum insulation resistance is 1MΩ.
One of the most common reasons for low insulation resistance
measurements is the presence of moisture.
If insulation resistance readings are low, IEEE recommends that the
equipment be dried out and retested.
50
DFR measurements on CT’s
51
CT Failures
52
Tank Type Current Transformer ABB
1. Gas cushion
2. Oil filling unit
3. Quartz filling
4. Paper-insulated primary conductor
5. Cores/secondary windings
6. Secondary terminal box
7. Capacitive voltage tap
8. Expansion vessel
9. Oil sight glass
10. Primary terminal
11. Ground terminal
53
CT DFR measurement procedure
3 connection points available
• HV terminal
• Capacitive voltage tap (not available on all
CT’s)
• Ground
Measure UST-red (HV to tap), ground=guard
If no tap, measure GST (HV to ground)
• NOTE! GST measurements are much more
sensitive to interference,
humidity/condensation etc
Measure 1000 Hz to 0.1 Hz
Send to MODS for temperature compensation of
measurement data to 20° C reference temperature
Read tan delta @ 1 Hz (20° C)
Classify CT for moisture content using the reference
table
54
CT DFR measurement setup
55
CT moisture analysis reference table
0.5 - 1% 3 - 4%
Suspicious
1 - 2% 4 - 5%
2 - 4% 5 - 6%
Bad
> 4% > 6%
56
Interpretation of moisture content (IEEE 62)
57
CT moisture levels in practice...
2%
4%
? 6%
58
Testing of CT’s
SAFETY FIRST
Protect personnel and equipment close to the Unit Under Test (UUT).
59
Standard CT Tests
Ratio
Polarity & Phase angle
Insulation Resistance
Winding Resistance
Demagnetization
Excitation/Saturation
Burden
60
Traditional Method of Testing
CT
Tester
61
Future Method of Testing
MRCT
62
1. Run all tests, on all taps, simultaneously
63
Conclusion
Current Transformers (CT) play an important role in power systems
for metering and protection applications.
To ensure optimal performance of your CT’s, IEEE recommends a
checklist of tests to be performed and the best way to perform them.
The MRCT helps you achieve the highest CT testing efficiency,
keeping your field crew safe and your assets healthy.
64
Questions?
65