This document provides an estimate for the construction of a residential building in Oothukadu Village, Kancheepuram. It includes 10 items: [1] earthwork excavation, [2] sand filling, [3] plain cement concrete, [4] flooring concrete, [5] reinforcement cement concrete, [5A] centering and shuttering, [5B] supplying and laying reinforcement, [6] brickwork, [7] ceiling plastering, [8] wall plastering, [9] teak wood doors and windows, [10] granite flooring, and [11] white washing. The total area estimated for construction is 3,000 square feet across a ground floor and
This document provides an estimate for the construction of a residential building in Oothukadu Village, Kancheepuram. It includes 10 items: [1] earthwork excavation, [2] sand filling, [3] plain cement concrete, [4] flooring concrete, [5] reinforcement cement concrete, [5A] centering and shuttering, [5B] supplying and laying reinforcement, [6] brickwork, [7] ceiling plastering, [8] wall plastering, [9] teak wood doors and windows, [10] granite flooring, and [11] white washing. The total area estimated for construction is 3,000 square feet across a ground floor and
This document provides an estimate for the construction of a residential building in Oothukadu Village, Kancheepuram. It includes 10 items: [1] earthwork excavation, [2] sand filling, [3] plain cement concrete, [4] flooring concrete, [5] reinforcement cement concrete, [5A] centering and shuttering, [5B] supplying and laying reinforcement, [6] brickwork, [7] ceiling plastering, [8] wall plastering, [9] teak wood doors and windows, [10] granite flooring, and [11] white washing. The total area estimated for construction is 3,000 square feet across a ground floor and
This document provides an estimate for the construction of a residential building in Oothukadu Village, Kancheepuram. It includes 10 items: [1] earthwork excavation, [2] sand filling, [3] plain cement concrete, [4] flooring concrete, [5] reinforcement cement concrete, [5A] centering and shuttering, [5B] supplying and laying reinforcement, [6] brickwork, [7] ceiling plastering, [8] wall plastering, [9] teak wood doors and windows, [10] granite flooring, and [11] white washing. The total area estimated for construction is 3,000 square feet across a ground floor and
ESTIMATE FOR THE PROPOSED CONSTRUCTION OF A RESIDENTIAL BUILDING IN
SURVEY.NO: OOTHUKADU VILLAGE WALAJABATH, KANCHEEPURAM
NAME OF APPLICANT: Mr. MOORTHI
DETAILED ESTMATE
S.NO DESCRIPTION NOS. LENGTH BREATH DEPTH QTY PER
GROUND FLOOR
Earth Worik excavation for foundation
1 in ordinary soils including lead and lift etc.. Columns 8.00 6.00 6.00 6.00 1728.00
1728.00 Cft
Collection and supply of sand flling for
foundation and basement in layers of 2 15cm thick including all labour charges etc.. Columns 8.00 6.00 6.00 0.50 144.00 144.00 Cft
Plain cement concrete 1:5:10 mix using
3 size HBBG including cost of all materials and all labour charges etc. Columns 8.00 6.00 6.00 0.50 144.00 All Walls 1.00 165.00 1.50 0.38 92.81 236.81 Cft
Flooring concrete 1:4:8 mix using size
4 HBBG including cost of all materials and all labour charges etc. Columns 8.00 6.00 6.00 0.38 109.44 109.44 Cft
Renforcement cement concrete 1:2:4
mix using 20 mm ISS Gauge HBBG metal 5 including cost of all materials and all labour charges etc. Column - Footing 8.00 6.00 6.00 2.00 576.00 Column - G.f.,FF,SF 24.00 1.50 0.75 12.00 324.00 All round & Cross walls - Plinth Beam 1.00 80.00 0.75 1.25 75.00 Lintel beam - G.F 2.00 80.00 0.75 0.50 60.00 Roof beam - G.f. 3.00 80.00 0.75 0.88 157.50 Roof Slab - G.f 3.00 15.00 30.00 0.38 506.25 Staircase 3.00 8.50 3.00 0.38 28.69 Landing slab 2.00 3.00 6.00 0.38 13.50 waist slab 2.00 8.50 3.00 0.38 19.13 Door 1.00 5.00 2.00 0.25 2.50 Door 1.00 4.50 2.00 0.25 2.25 Door 2.00 4.00 2.00 0.25 4.00 Window 5.00 5.50 2.00 0.25 13.75 Ventilator 2.00 3.50 2.00 0.25 3.50 1786.06 Cft
Centering and Shutterng arrengements
5A for R.C.C. works including cost of all materials and all labour charges etc. Column - Footing 8.00 6.00 6.00 288.00 Column - G.f.,FF,SF 8.00 1.50 0.75 9.00 All round & Cross walls - Plinth Beam 1.00 80.00 0.75 60.00 Lintel beam - G.F 2.00 80.00 0.75 120.00 Roof beam - G.f. 2.00 80.00 0.75 120.00 Roof Slab - G.f 2.00 15.00 30.00 900.00 Staircase 2.00 8.50 3.00 51.00 Landing slab 2.00 3.00 6.00 36.00 waist slab 2.00 8.50 3.00 51.00 Door 1.00 5.00 2.00 10.00 Door 1.00 4.50 2.00 9.00 Door 2.00 4.00 2.00 16.00 Window 5.00 5.50 2.00 55.00 Ventilator 2.00 3.50 2.00 14.00 1739.00 Sft
Supplying, cutting,bending,& lying in
position RTS & MS rods including cost 5B of all materials and all labour charges etc. Column - Footing 8.00 6.00 6.00 288.00 Column - G.f.,FF,SF 8.00 1.50 0.75 9.00 All round & Cross walls - Plinth Beam 1.00 80.00 0.75 60.00 Lintel beam - G.F 1.00 80.00 0.75 60.00 Roof beam - G.f. 2.00 80.00 0.75 120.00 Roof Slab - G.f 3.00 20.00 35.00 2100.00 Staircase 2.00 8.50 3.00 51.00 Landing slab 2.00 3.00 6.00 36.00 waist slab 2.00 8.50 3.00 51.00 Door 1.00 5.00 2.00 10.00 Door 1.00 4.50 2.00 9.00 Door 2.00 4.00 2.00 16.00 Window 5.00 5.50 2.00 55.00 Ventilator 2.00 3.50 2.00 14.00 2865.00 Sft Brick work in CM 1:6 mix using best country bricks of size 8.75"x4.25"x3" 6 including cost of all materials and all labour charges etc. Basement Level 1.00 80.00 0.75 3.00 180.00 Upto Basement Level 1.00 80.00 0.75 10.00 600.00 Upto FF & SF 1.00 80.00 0.75 10.00 600.00 Steps 20.00 3.00 0.81 0.58 28.19 Patapet wall 1.00 80.00 0.75 4.00 240.00 DEDUCTION: Door -1.00 5.00 - 7.00 -35.00 Door -3.00 3.00 - 7.00 -63.00 Door -3.00 2.50 - 7.00 -52.50 Window -5.00 4.00 - 4.00 -80.00 Ventilator -2.00 2.00 - 2.00 -8.00 1409.69 Cft
Ceiling Plastering in C.m. 1:3 mix
7 including cost of all materials and all labour charges etc. Stilt, FF, SF 3.00 15.00 30.00 1350.00 Bed Rm-1 1.00 10.00 9.50 95.00 Toilet 1.00 7.00 4.00 28.00 Bed Rm-2 1.00 11.00 10.00 110.00 Common Toilet 1.00 3.25 7.00 22.75 Kitchen 1.00 10.00 10.50 105.00 Stair 1.00 6.00 8.00 48.00 1758.75 Sft
Wall Plastering in C.m. 1:5 mix ( inner
8 and outer) including cost of all materials and all labour charges etc. Basement Level 1.00 80.00 - 3.00 240.00 above Basement Level FF , SF 4.00 80.00 - 12.00 3840.00 Steps 19.00 3.00 - 0.58 33.06 DEDUCTION: Door -1.00 5.00 - 7.00 -35.00 Door -3.00 3.00 - 7.00 -63.00 Door -3.00 2.50 - 7.00 -52.50 Window -5.00 4.00 - 4.00 -80.00 Ventilator -2.00 2.00 - 2.00 -8.00 3874.56 Sft
Provision made for teak wood doors
and windows using 5"x4" frame 9 including cost of all materials and all labour charges etc. Door 1.00 5.00 - 7.00 35.00 Door 3.00 3.00 - 7.00 63.00 Door 3.00 2.50 - 7.00 52.50 Window 12.00 4.00 - 4.00 192.00 Ventilator 3.00 2.00 - 2.00 12.00 354.50 Sft
Flooring with 19MM thick polished
granite in c.m. 1:3 mix including laying 10 and polishing and cost of all materials and all labour charges etc. Stilt, FF SF 3.00 15.00 30.00 1350.00 Stair 1.00 6.00 8.00 48.00 1398.00 Sft
White washing two coats with best shell
11 lime including cost of all materials and all labour charges etc. Upto Basement Level 3.00 80.00 - 10.00 2400.00 2400.00 Sft
Asian premium emulsion two coats with
12 putty fnishng including cost of all materials and all labour charges etc. Basement Level 1.00 80.00 - 3.00 240.00 Upto Basement Level 1.00 80.00 - 10.00 800.00 Steps 19.00 3.00 - 0.58 33.06 DEDUCTION: Door -1.00 5.00 - 7.00 -35.00 Door -3.00 3.00 - 7.00 -63.00 Door -3.00 2.50 - 7.00 -52.50 Window -5.00 4.00 - 4.00 -80.00 Ventilator -2.00 2.00 - 2.00 -8.00 834.56 Sft
Asian wheather shield - two coats
13 including cost of all materials and all labour charges etc. Basement Level 1.00 80.00 - 3.00 240.00 Upto Basement Level 3.00 80.00 - 10.00 2400.00 Steps 19.00 3.00 - 0.58 33.06 DEDUCTION: Door -1.00 5.00 - 7.00 -35.00 Door -3.00 3.00 - 7.00 -63.00 Door -3.00 2.50 - 7.00 -52.50 Window -5.00 4.00 - 4.00 -80.00 Ventilator -2.00 2.00 - 2.00 -8.00 2434.56 Sft