JSA For Materia/equipment Loading Unloading & Shifting Work Jsa

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

JSA NO. Department / Routine/ Non


Job Title: New/ Revised
Activity/ No… Routine

Reference work
Permit no: Supervisor:
Prepared By:
JOB SAFETY
ANALYSIS
Plant Location: UNIT-1
Department: Project FABRIACTION YARD Reviewed By:
TO NIACINAMIDE

Job Description: structural material/equipment unloading, shifting &


lifting by farina/crane or tandem lifting by farana Approved By:

SEQUENCE OF TASK POTENIAL HAZARDS PREVENTIVE MEASURES

 Mobilization of  Unskilled workers,  HSE Induction complete before work start.


Manpower  Person injury  Job Specific Training given for worker before work start.
 Property damage  Daily general Tool Box Talk conducted by Safety representative &
site Eng.
 Only authorized (gate pass) people are allowed to work on
respective jobs.
 Ensure work permit before work start.
 Area shall be barricaded to prevent unauthorized entry.
 Barricading of work  Use of required PPEs as per company rules safety norms- safety
area  Personal injury shoes, safety helmet, safety goggle, reflective jacket.
 No any unauthorized material to be kept inside barricading area.
 10-meter area should be barricaded.
 Improper loading  Follow safe unloading procedure.
 Unloading of  Overloading  Use certified tool and tackles
structural  Unbalance materials  Loaded vehicle should not be more than -
material/equipment  Movement of other  Trained riggers are deployed
vehicle crane/farana  Operator with HMV license deployed.
 Defective lifting  The farana/crane should not exceed 10 km/h speed limit
belt/sling  Use of trained and experienced personnel
 Use of extra leverage  Ensure competence of the personnel involved
for tightening  Capacity of the vehicle should be related to the load to be carried
 Over tightness/
slackness Dimensions of
the load
 Sharp edges

Page 1 of 3
Format No.: EHS-006/F06-00 Effective Date:
Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

 Structural  Inadequate  Operator shall check soil condition and see that outriggers are in
material/equipment farana/crane working position before starting lifting operations
lifting platform (due to  Crane/farana to be operated within SWL
soft/unstable soil,  Certification and color coding of equipment
outrigger not fully  All rigging, singing and lifting to be done by competent person
deployed etc)  Prior to use, all equipment’s to be visually inspected
 Over loading of  All persons to be made aware of danger through tool box talk
farana/crane  Ensure sufficient room for operation
 Damage to lifting  Tag line to be attached to load to prevent swinging
equipment since  The material not to be stacked too high
inspection  Material to be stacked on adequate base
 Personnel having body  Materials to be secured/covered are kept under shelter
part trapped by load  Good housekeeping to be maintained
 Moving crane/load  Material to be adequately segregated
hitting people / assets
 Material stacked too
high
 Inadequate base for
storing materials

 Tandem lifting of  Unbalance of material  All the lifting gears to be third party inspected with valid form-
equipment with 02  Miss communication 10
nos faranha between both operator  Check the driver license with HWV driving license and
 Toppling of the franna. experience of operator.
 slip & trip.  Farana should not use is pulling of materials.
 fall of material  Work permit must be obtained before starting the work.
 Movement of vehicle  Prepare lifting plan for tandem lifting as consider as critical
near tendon lifting/ lifting.
shifting.  Proper PPEs like as Helmet, Goggles, Reflective jacket, shoes,
Hand gloves.
 Overhead power line proper distance must be maintained.
 Root/ground survey shall be done before lifting materials.
 Use tag ropes on each side for avoid over swinging.
 Lifting plan shall be discussed with the operators
 Supervisor/foreman shall monitor the job continuously
 The person who are holding tag ropes shall keep safe distance
from the materials.
 Evacuate the area and rigger shall ensure all the area while
shifting the materials.
 Do not exceed 80% of the rated capacity of the crane for any
loading/ unloading works and or as per manufacturer standards
under any circumstances.
 Only single signalman shall give the signal for the farana/crane
operator.
 Conducted tool box talk prior to start the work.
 Flag man available during shifting reactor

Page 2 of 3
Format No.: EHS-006/F06-00 Effective Date:
Jubilant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

 Shifting of structual  Fall of material  Follow safe shifting procedure


material/equipment  Damage of property  Use of experienced personnel.
 Injury to persons due to  Having adequate area for storage.
fall of load from the  Following proper storing procedures.
vehicle  Proper supervision.
 Slip, trip hazards  Ensure the proper signalman.
 Ensue proper access for materials shifting.
 Ensure moment only 1 fit height for Equipment shifting work
activity.
 Ensure the proper balance for materials.
 Ensure the deviation for Equipment shifting activity.
 Housekeeping  Slip, trip hazards  Ensure entire area shall be cleaned after job is completed.
Remove unwanted material from site after close the job.
 Erection material should be proper stacking.
 In Case of Emergency  Confusion  Emergency assembly point, emergency access should be defined
& always free from any obstructions.
 Emergency contact details to be displayed at prominent locations
of site.
 Emergency vehicle must be available at work locations during all
working hours.
 All workers shall aware / trained about site emergency
procedure.

Day-1 Day-2 Day-3

Permit issuer

Permit acceptor

Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety officer

Approved by HOD

Page 3 of 3