Switching Operators Manual Distribution
Switching Operators Manual Distribution
Distribution Switching
CS10#5011675 Page 2 of 3
RECORD OF REVISIONS
CS10#5011675 Page 3 of 3
SECTION ONE
Introduction: Distribution
Switching
Table of Contents
1. Introduction: Distribution Switching ...................................................... 1-1
1.1 Purpose .............................................................................................. 1-1
1.2 Content .............................................................................................. 1-1
1.2.1 Manual One .................................................................................... 1-1
1.2.2 Manual Two .................................................................................... 1-3
1.3 Switching Operator Authorisation Levels ............................................ 1-3
i
Switching Operator's Manual One
List of Figures
No table of figures entries found.
List of Tables
No table of figures entries found.
ii
1. Introduction: Distribution
Switching
1.1 Purpose
Manual One provides the switching operator with information on the distribution
network configuration, apparatus and switching operations. The manual covers
the Horizon Power distribution networks associated with the microgrid and Pilbara
Grid systems.
Manual Two provides the switching operator with information on the transmission
network configuration, apparatus and switching operations. This manual covers
the transmission network associated with the Pilbara Grid.
Both manuals are intended to be used as a resource for all switching operators
and also a major resource for the training modules in Switching Operations.
1.2 Content
1.2.1 Manual One
Manual One covers the network and switching associated with the distribution
high voltage (HV) and low voltage (LV) network, which is common to both
microgrid and Pilbara Grid systems. The LV distribution network connects
electrical power to the majority of the Horizon Power’s customers, and the HV
distribution network supplies HV power to the distribution transformers which is
stepped down in voltage to supply the LV network.
Section 1
Section One (this section) provides a brief overview of the contents of the manuals
and a more detailed overview of the sections related to the distribution HV and LV
networks.
Section 2
1-1
Switching Operator's Manual One
Section 3
Section 4
Section 5
Section 6
Section Six describes in detail the substations which provide the source of supply
for the HV distribution network. It includes a description of the substation
configurations and the associated primary and ancillary apparatus.
Section 7
Section Seven describes the protection systems used on both the HV and LV
distribution systems. It includes descriptions of the grading introduced to ensure
only the faulted section of the distribution system is disconnected.
Section Eight describes the critical matters relating to safe switching operations, it
is applicable to both distribution and transmission switching. The section includes
a description of the switching related documentation and the roles and
responsibilities. Also detailed are the principles and practice of isolation and
earthing, permits and barriers, locking and tagging. Details are provided on
common switching operation tasks, the practical checks before and after switching
apparatus and switching related hazards.
Section Nine describes the roles and responsibilities, tools and procedures
associated with the creation and running of switching programs which are
applicable to both distribution and transmission switching. Also included in the
section are the program writing considerations which must be reflected on and
included if appropriate to create a successful switching program.
1-2
Section One – Introduction: Distribution Switching
Section 10
Level Description
1-3
SECTION TWO
Table of Contents
2. Horizon Power’s Power Systems ........................................................... 2-1
i
Switching Operator's Manual One
List of Figures
Figure 2-1 Horizon Power's microgrid and interconnected systems ................... 2-2
Figure 2-2 Components of a microgrid system ................................................... 2-3
Figure 2-3 Components of an interconnected system ........................................ 2-5
Figure 2-4 Interconnected system: The interconnection of components ............. 2-6
Figure 2-5 Typical gas turbine generator............................................................ 2-8
Figure 2-6 Typical diesel fuel-fired power station ............................................... 2-8
Figure 2-7 Horizon Power’s Pilbara Grid transmission system ........................... 2-9
Figure 2-8 South Hedland Terminal Station ..................................................... 2-11
Figure 2-9 Hedland Terminal Station ............................................................... 2-12
Figure 2-10 Anderson Street Zone Substation ................................................. 2-14
Figure 2-11 Wedgefield Zone Substation 66kV single busbar .......................... 2-15
Figure 2-12 Typical distribution feeders ........................................................... 2-17
List of Tables
Table 2-1 Responsibility for components ......................................................... 2-18
Table 2-2 System advantages and disadvantages ........................................... 2-19
ii
2. Horizon Power’s Power
Systems
2.1 Introduction
Horizon Power generates, distributes and retails electricity through its range of
power systems in regional Western Australia. The components and structure of
Horizon Power's power systems are described in this section.
The type of system used is determined by local conditions such as the number of
customers, customers load, and the distance to the power supply source.
Horizon Power’s microgrid systems are designed to suit load centres in regional
and remote areas. Figure 2-1 shows the location of the microgrid systems and the
fuel type used for generation. (Note that all locations outside the Pilbara Grid
network are microgrids, although there is an interconnection between Kununurra
and Wyndham in the Kimberley region.) Because of their remote location, each
microgrid system operates independently and does not connect to other microgrid
systems.
Figure 2-2 shows the basic components of a microgrid system. The system can be
divided into generation, HV distribution and LV distribution.
2-1
Switching Operator's Manual One
Step up transformers are used to increase the voltage to 11, 22 or 33kV. The HV
distribution feeders supply distribution transformers with electrical energy which is
further stepped down to the LV distribution voltages (480/415/240V), to supply the
customers via overhead and underground LV networks.
2-2
Section Two – Horizon Power’s Power Systems
Generating
plant
Generation
Output
415V – 11kV
Step-up
transformer
HV Distribution
Distribution feeders
33kV – 22kV – 11kV
Distribution
transformer
LV Distribution
LV Distribution
415V – three-phase
480V – split-phase
240V – single-phase
Consumer
2-3
Switching Operator's Manual One
Horizon Power’s Pilbara Grid is of the interconnected system type and is designed
to accommodate large load centres and use several generating stations connected
together with a transmission network. Figure 2-1 shows the location of the Pilbara
Grid system supplying the Karratha and Port Hedland areas. The fuel used for
generation is predominantly natural gas, with diesel fired generation being available
for shortages in natural gas supply.
Figure 2-3 shows the basic components of a typical interconnected system. The
system can be divided into generation, transmission, HV distribution and LV
distribution.
The generating stations produce electrical energy using large gas turbines.
Generator step up transformers increase the voltage to higher transmission
voltages of 66, 132 or 220kV to reduce the electrical system losses. The HV
transmission lines transport the electrical energy to the terminal stations which are
the bulk supply points for the zone substations.
The zone substations connect the transmission network to the distribution network
using step down transformers to reduce transmission voltages (66 or 132kV) down
to HV distribution voltages (11, 22 or 33kV). The distribution feeders supply
distribution transformers with electrical energy which is further stepped down to the
LV distribution (415/240V), to supply the customers via overhead and underground
LV networks (see Figure 2-4 below).
Figure 2-4 shows a simplified representation of the Pilbara Grid, where the
Karratha and Port Hedland systems are connected together with a long 220kV
transmission line. It can be seen the terminal stations connect the generation
stations together and supply the zone substations. For increased supply security
most zone substations have more than one source of high voltage transmission
supply.
2-4
Section Two – Horizon Power’s Power Systems
Generators
Generation
11kV
Transmission line
220kV – 132kV – 66kV
Terminal station
220kV – 132kV – 66kV
Step-down transformer
Transmission
Transmission line
132kV – 66kV
Zone substation
Step-down transformer
HV Distribution
Distribution feeders
33kV – 22kV – 11kV
Distribution transformer
LV Distribution
LV Distribution
415V – three-phase
240V – single-phase
Consumer
2-5
2-6
Generation Generation Generation Generation
Generation
220 kV
Switching Operator's Manual One
132 kV 66 kV
Transmission
Zone substation Zone substation Zone substation Zone substation
U/G to O/H
connection Industrial or
U/G HV commercial
Feeder customer
HV
O/H HV
Feeder
U/G HV Feeder
Distribution
415 / 240 V Kiosk Universal
Pole top substation Pillar
Distribution
transformer O/H service Distribution feeders
line and
LV
11, 22, or 33 kV U/G customer
415 / 240 V service
Residential Distribution line 415 / 240 V network
415 / 240 V network customer
Distribution
Section Two – Horizon Power’s Power Systems
The interconnected system is much larger and has a transmission system which
requires the additional components of transmission lines, terminal stations and
zone substations
Microgrid towns can be supplied from a range of generation which can include
combinations of the following (dependent on the specific installation):
wind turbines
The size of generating units is dependent on the load to be supplied from the
kilowatt range to many megawatts. The smaller generating units will generate at
low voltage 415V, whilst the larger units will generate around 11kV with step up
transformers to match the voltage of the network to which they connect.
In the Pilbara Grid to increase efficiency, because of the large amounts of power
required and long distances involved, the voltage may be stepped up to 132 or
220kV. In microgrids the generator or step up transformer voltage will match the
local distribution voltage.
Generating stations usually have multiple generating units to allow for multiple units
to run at high load and also make individual units available for maintenance.
2-7
Switching Operator's Manual One
Exhaust with
Air inlet
silencer
duct
Generator
Step-up
Transformer
Exhaust
Generator
Exciter
Water
cooling
Diesel engine
Step-up
Transformer
2-8
2.3.2
KTP KRP
HDS = Hope Downs BUL = Bulgarra SHT = South Hedland Terminal AST = Anderson Street
LEGEND DBS = Dampier Bulk Supply SS KTP = Karatha Temporary Power CBS = Cape Lambert Bulk supply HDT = Hedland Terminal HPS = Hedland Power Stn
WAS
YPS = Yurrali Maya PS DMP = Dampier substation KTS = Karatha Temporary Substation CLB = Cape Lambert SWC = South West Creek FIH = Finucane Island
BKN = Brockman MSM = Millstream KRT = Karatha Terminal PSN = Point Sampson UTP = Utah Point MDR = Murdoch Drive
Figure 2-7 shows the network and voltages used in the Pilbara Grid.
TPE = Tom Price PBO = Paraburdoo PCK = Pegs Creek ROE = Roebourne TIG = Tiger substation BPS = Boondarie PS
WAS = West Angelas PWA = Pannawonica SHL = Stove Hill Terminal SHP = South Hedland Power Stn MNM = Mount Newman GW = Goldsworthy
These lines transmit power over long distances using very high voltages. This
reduces power losses. However, the cost and availability of equipment (step up
transformers, insulators, circuit breakers, towers etc.) limit the degree to which the
Section Two – Horizon Power’s Power Systems
2-9
Switching Operator's Manual One
Voltage of 66kV, 132kV or 220kV are used in terminal stations. These voltages
may be stepped up for further transmission to other terminal stations or stepped
down for transmission to lower levels of transmission at zone substations.
Transmission to zone substations is carried out at voltages of 66kV or 132kV.
2-10
Section Two – Horizon Power’s Power Systems
2-11
Switching Operator's Manual One
2-12
Section Two – Horizon Power’s Power Systems
Zone substations are used as the final stage of transmission and the first level of
distribution networks. Zone substations are fed mainly from 66kV or 132kV
transmission lines and are usually connected in a ring network to other zone
substations and terminal stations. The ring network is used to maintain continuity of
supply during faults and planned outages.
double bus.
The double bus configuration has better flexibility of supply than the single bus
configuration.
There are also two types of switchgear used for distribution from the zone
substation:
indoor
outdoor.
Zone substations can have distribution voltages of 11, 22 or 33kV. This depends on
local conditions and design factors.
2-13
Switching Operator's Manual One
2-14
Section Two – Horizon Power’s Power Systems
2-15
Switching Operator's Manual One
Feeders are three-phase circuits and can be overhead line networks, underground
cable networks or a combination of both.
The distribution high voltages used are 11kV, 22kV and 33kV. The choice of
voltage is determined by the load and location.
Long rural feeders are often supplied at 33kV to reduce line losses.
In some remote areas the rural feeders extend from the substation as three-phase
overhead lines and branch into single-phase spurs. These spurs combine with a
running earth to feed several small distribution transformers. These single-phase
spurs can be overhead or be installed in an underground system, referred to as a
single-phase underground distribution system (SPUDS).
Each distribution transformer steps down the feeder high voltage to supply the
distribution low voltage circuits. Depending on the circuit arrangements, the
distribution low voltage circuit provides customers with a range of voltages:
415V three-phase
240V single-phase
The low voltage circuit may feed a single rural customer, a large commercial
customer or several streets in a residential area.
Low voltage circuits are designed to allow the transformers to be run as near as
possible to their rated values. Various sizes of conductors maintain set voltage
limits around the circuit.
2-16
Section Two – Horizon Power’s Power Systems
Substation
F1 F2 F3
Legend
Circuit breaker closed Recloser
Distribution transformer
PTS or RMU SWDC NOP OH to UG cable head non-interconnectable
2-17
Switching Operator's Manual One
Responsibilities for the components of the Horizon Power microgrid and Pilbara
Grid systems are shown below. Horizon Power Control Centre (HPCC) located in
the Perth suburb of Bentley is the control authority.
2-18
Section Two – Horizon Power’s Power Systems
Recall also that the Horizon Power Pilbara Grid (an interconnected system)
consists of all the components already presented. These components connect
many generating sources to customers through various levels of transmission and
distribution.
The relative advantages and disadvantages of the microgrid and Pilbara Grid
systems are shown in Table 2-2. The most appropriate system is set up according
to the particular conditions of the location. However, wherever possible, an
interconnected type of system is preferred.
Microgrid systems
Advantages Disadvantages
Pilbara Grid
Advantages Disadvantages
Horizon Power Control Centre (HPCC) is the operating authority for Horizon
Power’s networks. HPCC has a Supervisory Control and Data Acquisition (SCADA)
system which monitors switchyard apparatus and enables remote switching of
specific apparatus in the networks.
After successful training and assessment, personnel are authorised with level-
specific switching authorities which allow operators to undertake switching duties in
a particular part of the network.
These switching operators are based in the regional depots. Switching operators
are required to write switching programs and undertake manual switching to
provide safe access for the maintenance, construction and testing as required on
the network.
2-19
SECTION THREE
LV Distribution System
Table of Contents
3. LV Distribution System ........................................................................... 3-1
i
Switching Operator's Manual One
List of Figures
Figure 3-1 LV distribution system ....................................................................... 3-1
Figure 3-2 Circuit of pole mounted transformers................................................. 3-3
Figure 3-3 Typical schematic circuit of ground mounted transformers ................ 3-3
Figure 3-4 Distribution transformer ..................................................................... 3-4
Figure 3-5 Single-phase transformer circuits ...................................................... 3-5
Figure 3-6 Typical peak loads for 24-hour period ............................................... 3-7
Figure 3-7 LV overhead distribution connected in mesh ..................................... 3-8
Figure 3-8 LV underslung pole mounted disconnector........................................ 3-9
Figure 3-9 Pfisterer (l) and Krone (r) ganged fuse units ................................... 3-10
Figure 3-10 Distribution board disconnector ..................................................... 3-11
Figure 3-11 Two types of HRC fuse ................................................................. 3-12
Figure 3-12 Current limiting HRC fuse .............................................................. 3-12
Figure 3-13 HRC fuse system (underground system) ....................................... 3-13
Figure 3-14 Distribution board mounted disconnectors (extractable) ................ 3-14
Figure 3-15 Distribution board mounted disconnectors (hinged) ....................... 3-15
Figure 3-16 ABB SLBM 400 fuse and BSL 1600 disconnector ......................... 3-15
Figure 3-17: ABB Single Switch-Fuse / Isolator ................................................ 3-16
Figure 3-18: Double Switch-Fuse / Isolator ....................................................... 3-17
Figure 3-19 Testing busbar and cable side. ...................................................... 3-17
Figure 3-20 Type 1.1 Kiosk rated at 630A/415V ............................................... 3-18
Figure 3-21 Type 2 Kiosk rated at 1400A/415V ................................................ 3-18
Figure 3-22 Type 3.1 Kiosk rated at 2800A/415V ............................................. 3-18
Figure 3-23 Three core LV XLPE Cable (Wavecon) ......................................... 3-19
Figure 3-24 LV underground radial connections ............................................... 3-21
Figure 3-25 Mini pillar ....................................................................................... 3-22
Figure 3-26 Universal pillar............................................................................... 3-22
Figure 3-27 Universal pillar rear view ............................................................... 3-23
Figure 3-28 Feeder pillar .................................................................................. 3-24
Figure 3-29 Underground LV distribution system .............................................. 3-25
Figure 3-30 Overhead LV distribution system ................................................... 3-28
Figure 3-31 Examples of barriers for disconnectors.......................................... 3-31
Figure 3-32 Danger of misaligning universal pillar contacts .............................. 3-33
ii
Section Three – LV Distribution System
List of Tables
Table 3-1 Voltage ranges at customer level meter position ................................ 3-2
Table 3-2 Transformer five stage variation on input voltage ............................... 3-5
Table 3-3 Advantages of HRC fuses ................................................................ 3-11
Table 3-4 Commonly-used LV underground cables ......................................... 3-20
Table 3-5 Transformer and LV circuit fault – switching operator response ....... 3-32
iii
Switching Operator's Manual One
iv
3. LV Distribution System
3.1 Introduction
This section is designed for the switching operator to refer to before and during
switching. It aims to promote safe switching practice and ensure continuity of
supply within the LV distribution system.
The low voltage distribution system extends from the distribution system
transformer to the customer's point of supply (see Figure 3-1). It is the point where
the majority of customers receive their supply.
Distribution
transformer
LV
Distribution
415 V 3Ø
480 V 2Ø
240 V 1Ø
Customer
Horizon Power is required to maintain its supply within 6% (either side) of the
nominated voltage (240V phase to neutral, 415V phase to phase). Where the
power quality tests verify it is found to be outside these limits, modification to the
network is required.
3-1
Switching Operator's Manual One
Nominal
Voltage Lower limit Upper limit
(V) (V) (V)
Those used by Horizon Power are either pole mounted or ground mounted,
depending on size.
3-2
Section Three – LV Distribution System
Pole mounted
(bare LV or ABC)
transformer
HV feeder
LV mains
HV drop-out fuse LV disconnector
(or fuses)
For safety reasons, the distance between a three-phase transformer and the drop-
out fuse is normally as short as possible.
Ground Circuit
mounted fuses
transformer
overhead
LV
HV
LV circuits
Drop-out
fuse disconnector
transformer
LV
HV
LV circuits
Switch
fuse
disconnector
Circuit
Ring main unit fuses
Padmount
3-3
Switching Operator's Manual One
• 63kVA
• 160 kVA
• 315 kVA
• 630 kVA
• 1000 kVA.
Purpose
LV Star Phase-to-phase
HV Delta Iron core
415 V
240 V
3-phase HV
• 11 kV Neutral
• 22 kV
• 33 kV Phase-to-neutral
The rural system is an exception, for the high voltage supplying the transformer
may be single-phase. Rural transformers supply single-phase (240V) or split-
phase (480V). See Figure 3-5.
Each transformer has a tap changer to provide a constant LV voltage with variable
HV levels. Table 3-2 shows the five-stage variation with 2.5% steps for a
22kV/415V transformer.
3-4
Section Three – LV Distribution System
Earth Phase-to-earth
Iron core
1Ø
240 V
22 kV 480 V
240 V
1Ø
Phase-to-phase
HV
Nameplate Percentage LV Voltage
Tap
Voltage (%) (Φ to N)
(volts)
1 23 100 -5 415/240
2 22 550 -2.5 415/240
3 22 000 415/240
4 21 450 +2.5 415/240
5 20 900 +5 415/240
Switching operators should find out what localised tap requirements are necessary
to obtain the correct voltages for all types of transformers in each locality.
3-5
Switching Operator's Manual One
When a fault occurs on the LV distribution system, the current flowing from the
transformer into the fault will be very large. The higher the rating of the
transformer, the larger the fault current or short circuit current.
The tap changer is a no-load tap changer, requiring the de-energisation of the
transformer before the tap is changed. See Table 3-2 for tap settings. The tap
selector handle is required to be locked or otherwise secured after a required tap
is selected.
Pole Mounted.
Ground Mounted.
Ratings
The switching operator must understand the transformer capacities used in the
switching program. Check the ratings and loads that are required when planning
interconnection for feeding up of the load.
3-6
Section Three – LV Distribution System
Transformers operate within a range that is influenced by temperature and the type
of load being supplied. Both a cyclic rating and a nameplate rating are allocated to
each transformer.
Cyclic rating is higher than nameplate rating because the transformer takes
approximately 4 hours to heat to maximum temperature. The transformer may be
run higher than its nameplate rating for the 2 to 4 hour period of daily peaks.
During this time, the oil will not rise to a temperature where insulation breakdown
could occur, or the flashpoint of the oil is reached. Figure 3-6 shows there are two
peak loads for each 24-hour period.
Transformer load
Cyclic
rating
(130%)
Name-
plate
rating
(100%)
0 2 4 6 8 10 12 14 16 18 20 22 24
Time (hours)
Note: These peak load times may vary depending on weather conditions and
location.
Aerial conductors making up overhead distribution vary in size and type (copper,
aluminium, aluminium alloy).
Horizon Power typically uses the following conductors for open aerial mains:
3-7
Switching Operator's Manual One
For details of overhead bare LV conductors see the Distribution Design Rules.
Aerial bundled cable (ABC) has been introduced to replace bare conductors on
the LV distribution network. There are only two sizes:
• 95 mm²
For details of ABC conductors and accessories, see the Distribution Design Rules.
Each type of conductor has a summer and winter rating. The switching operator
must know these capacities to note the rating for the switching process. The rating
changes because of a higher average temperature during summer. This reduces
the current carrying capacity of the conductors.
More than one type and size of conductor is commonly fed from one transformer.
When interconnecting two or more transformers, there may be even more sizes
and types involved.
Configuration
Volt drop depends on the conductor size, the load current and the length of
conductor. Connecting the circuit in mesh has historically been the most efficient
way of ensuring maximum voltage at every point of the supply.
3-8
Section Three – LV Distribution System
Note: LV aerial bundled cable circuits are not connected in mesh, but as radial
feeds.
These disconnectors are rated at either 400 or 600 amps operating current (see
Figure 3-8).
They may be used to make or break this load. Commonly, these disconnectors:
3-9
Switching Operator's Manual One
LV disconnectors are mounted under the crossarm and may be operated from
below. An insulated HV operating stick is used to pull the blade out, making the
operation reasonably fast and uncomplicated.
Figure 3-9 Pfisterer (l) and Krone (r) ganged fuse units
3-10
Section Three – LV Distribution System
Solid disconnector
Moulded case carrier
The HRC (high rupturing capacity) fuses are used to protect LV cable circuits. The
fuses fit into a range of carriers including mounted case carriers (see Figure 3-10)
and ABB SLBM carriers (see Figure 3-16). Table 3-3 lists the advantages of HRC
fuses.
Operates silently
Has a tamper-proof fuse element
The HRC fuses (see Figure 3-11) used in Horizon Power's LV distribution system
include meter board, pole and LV distribution board fuses.
3-11
Switching Operator's Manual One
The HRC fuses shown below are two of the types of fuses used by Horizon
Power. All fuses have one or more parallel silver fuse elements, each with multiple
narrow sections. When fault current exists, the fuse element narrow sections will
melt and arc simultaneously, ensuring the arc is rapidly extinguished. High current
rating fuses use multiple silver elements in parallel.
Function
HRC fuses are more effective than rewirable fuses because they limit fault current
or overcurrent to less than a dangerous level.
Figure 3-12 shows the point at which the HRC fuse interrupts power during the
first quarter of the phase cycle.
Current
B
Prospective fault current
A
HRC fuse
actual Rewireable fuses and air circuit breakers
current extinguish arc at or beyond this point
Time
3-12
Section Three – LV Distribution System
In Figure 3-12, point B is the peak fault current. This may be thousands of amps
causing excessive damage to equipment. Point A shows the point where the HRC
fuse has blown. In this case, the fault current is interrupted in less than 5
milliseconds (ms), that is, 0.005 seconds.
Note: The HRC fuse is designed to give a specific characteristic under fault
conditions. If the fuse is tampered with, it will not operate correctly.
Rating
The amperage rating is marked on the end cap of HRC fuses and is easily seen
when replacing the cartridge.
Horizon Power fuses in the LV supply range in size from 32 to 400 amps. (See
Figure 3-13).
Figure 3-13 shows how the fuses are used to protect the underground LV
distribution system. A fuse is also installed on the consumer switchboard.
There are various types of board mounted disconnectors and fuses. The
disconnectors are used for isolation or interconnection and fuses are used for
isolation.
3-13
Switching Operator's Manual One
3-14
Section Three – LV Distribution System
LV circuit
LV distribution breaker
board
Figure 3-16 ABB SLBM 400 fuse and BSL 1600 disconnector
To operate the disconnector, the switching operator grasps the handle at the top
and pulls briskly outward to open. To close, the operator engages the bottom
pivots, then moves the cover toward the closed position, and while holding a safe
distance away, checks alignment and then briskly closes by pushing forward.
3-15
Switching Operator's Manual One
When used as an isolation point, the fuses/disconnectors inside the cover must be
removed and the cover replaced and Danger–Do Not Operate (D–DNO) tagged. An
alternative is to fit a D–DNO tagged replacement cover with the fuses/disconnectors
removed.
Where large capacity transformers are installed, a circuit breaker (see Figure 3-15)
or moulded air break switches can be installed between the transformer and the LV
board. This replaces the transformer disconnectors which are used on smaller
capacity transformers.
A new type of low voltage distribution board is available to Horizon Power as a result
of ABB switch gear becoming obsolete as from 2020.
The new gear using the Weber South Pacific type is frame mounted LV distribution
switchgear. Standard components, such as fuse switch strips, isolators, circuit
breakers and load break switches, are assembled together to make switchgear
configurations.
Vertical fuse switches and isolators are a core product of Weber South Pacific
switchgear design. They are ideally suited to power distribution in electricity
networks because of the efficient shape of the switch and busbar mounting.
3-16
Section Three – LV Distribution System
Applications
3-17
Switching Operator's Manual One
3-18
Section Three – LV Distribution System
There are several types and sizes of cables that are used in the underground
system. Initially, lead or lead alloy sheathed underground cables were used. Now,
all new underground cable is XLPE (cross-linked polyethylene) insulated.
Termite
protection layer
Butyl mastic
moisture barrier
XLPE insulation
phase colouring
Outer sheath
3-19
Switching Operator's Manual One
Details and sizes of all Horizon Power underground cables can be found in the
Horizon Power Distribution Design Rules.
Apart from the physical location, underground cables differ from the overhead
system because:
3-20
Section Three – LV Distribution System
3 x 3-phase
circuits
Disconnector
solid link
Transformer
Outgoing
circuit
fuses
Normally open
3.2.5 Pillars
• mini
• universal
Mini Pillars
These are usually located inside a customer's property. The pillar becomes the
connection point for the property's consumer main. It may also service the
property next door. They also supply street light circuits and unmetered supply
pillars and pits.
Figure 3-19 shows a mini pillar. Customer service connections are unfused, while
street light and unmetered supplies are fused in the pillar.
Isolation of street light circuits and unmetered supplies requires load-side tail to be
removed from the fuse holder. This practice is required because the holder can
become conductive because of water condensation in the pillar.
3-21
Switching Operator's Manual One
Mini pillar
Housing properties
Mini Mini
pillar pillar
LV U/G circuit
Universal Pillars
These are used in the LV circuit as open points and/or switching points, and to
supply customers with larger load requirements of up to 315A, e.g. commercial or
industrial lots.
Figure 3-20 shows that the universal pillar normally has no fuses, only removable
disconnectors. These disconnectors can be removed or installed, as required for
interconnection, load distribution or isolation
Sometimes, universal pillars are used for connection points for only one large
customer. As fuses may be installed, fuse grading must be observed.
The maximum load at which a universal pillar can run is 400 amps. The load
depends on the cable sizes being used.
Universal pillar
Housing properties
Universal
Mini pillar Mini
pillar pillar
LV U/G circuit
3-22
Section Three – LV Distribution System
For large demand LV customers a universal pillar with fuses is used to connect
the customer rather than a mini-pillar.
Figure 3-21 shows the rear view of the universal pillar, the customer service
connection blocks and a HRC fuse for a street light or unmetered supply.
Customer
connections
(R-W-B)
Feeder pillars are used in high-density underground areas and are generally
located on the cable alignment or in a distribution substation compound. They
allow isolation of underground cables, interconnection and load distribution.
Feeder pillars (or LV kiosks) provide Horizon Power with a convenient place to
marshal its underground LV circuits and provide switching flexibility. They can also
be used to provide a customer's point of supply.
3-23
Switching Operator's Manual One
3.3 Design
LV distribution consists of two systems; underground and overhead. Each system
is different in design but both serve the same purpose.
Both the underground and overhead systems are described in the following
sections.
3.3.1 Underground
The underground system consists of high voltage feeders which supply ground
mount transformers required to step the voltage down to LV (415V). The
transformer LV then supplies the underground LV cable circuits running down
each street to connect the houses via their service connections. Each transformer
will have multiple separately-fused LV circuits.
3-24
Section Three – LV Distribution System
1
2
5 9
8
6 4
1 Coolajacka Transformer 1
2 Coolajacka Transformer 1 LV circuits (orange)
3 Coolajacka Transformer 2
4 Coolajacka Transformer 2 LV circuits (green)
5 Coorbeeli Transformer
6 Coorbeeli Transformer LV circuits (red)
7 LV Normally open point (NOP) between Coolajacka Transformer 1 and Coorbeeli Transformer circuits
8 LV Normally open point (NOP) between Coolajacka Transformer 2 and Coorbeeli Transformer circuits
9 LV Normally open point (NOP) between Coolajacka Transformer 2 and Coorbeeli Transformer circuits
3-25
Switching Operator's Manual One
Low voltage circuits are not normally run in parallel, however there are occasions
when interconnection may be required. If these circuits are left permanently
interconnected, the problems that may occur are:
• one fault on either circuit may blow both fuses and totally cut power
• a minor fault on the cable may result in neither set of fuses blowing but
cause overload on each circuit.
Different size ratings can be used according to the size of the cable required:
• 400 amp fuses are normally used for 240 mm² XLPE cables
• 315 amp fuses are normally used for 185 mm² XLPE cables.
Note: Because of the grading problems between 400 amp LV HRC fuses and
some HV HRC fuses, sometimes it is necessary to reduce the rating of the LV
fuse, usually to 315 amp.
To prevent grading problems, no additional fuses are usually installed along the
cable feed. Instead, disconnector links are used for all additional connection or
interconnection. This is an advantage if a customer loses supply, because there is
only one location to be checked for blown LV fuses. However, this also means all
customers connected to the cable will lose supply and depending on the fault
current the fuses at the source may not blow.
3.3.2 Overhead
The overhead system consists of high voltage feeders which supply transformers
required to step the voltage down to LV (415V). The transformer LV then supplies
3-26
Section Three – LV Distribution System
the overhead LV circuits (LV mains) running down each street to connect the
houses via their service connections.
The NOPs between LV different circuits are installed to allow flexibility for
interconnection, which can be used to maintain supply during transformer
outages.
The overhead system has the advantage of being visible for inspection and
quickly accessible for maintenance and repair.
3-27
Switching Operator's Manual One
1
3
8 5
2
6
7
NELSON
• interconnection
• isolation
• fault location.
3-28
Section Three – LV Distribution System
3.4.1 Interconnection
Before Interconnection
1. Check the load on both the transformer to be taken out and the transformers
being used to feed up. (This helps the operator to decide whether there is
enough capacity available to feed up from the other sources.)
Note: When two transformers are interconnected, they tend to share the load
between them. If transformers of different sizes are interconnected for a long time,
the load should be checked at each transformer. This will show if either
transformer is overloaded.
2. Check for small conductor size and long route length. These may cause volt
drop or overload problems. Where possible, use the largest conductors
available and the shortest possible route length.
4. The switching operator should check to see if they are parallelling two
substation feeders together via the LV circuits. (If one of the feeders trips off
completely, the other feeder will try to pick up all that feeder's load through the
interconnected LV system. This will cause major damage to transformers and
conductors.)
If a feeder is tripped momentarily and restored by auto reclose, the
transformers feeding up the interconnected area may blow a drop-out fuse.
Interconnecting two feeders through the LV network should be avoided, it is
often possible to reconfigure the HV feeders by switching to place all
3-29
Switching Operator's Manual One
After Interconnection
6. The switching operator should check whether they are within the statutory
voltage limits at all points of supply. Do not forget to check the voltage at the
furthest point from the transformer! (See Table 3-1).
Restoration
7. Check all closed normally open point disconnectors have been opened. If
transformers are left interconnected, load sharing will continue. When a fault
occurs, both transformers will share the fault current.
3.4.2 Isolation
When isolating any equipment on the LV distribution system, the isolation points
must be prevented from inadvertent closure which can result in re-energisation.
This is achieved by using a form of physical barrier or where locking facilities are
available they are to be used. A Danger–Do Not Operate tag is also to be fitted.
Actions for consideration when performing isolations include the following points.
3-30
Section Three – LV Distribution System
• For underground cables, use a voltmeter to prove the cable is isolated. The
operator should D-DNO tag isolation points. Where it is suspected that there
may be an HV cable in the same area, signal injection may be required to
prove LV cable identification.
• ABC fuse box inserts when used as an isolation point must be removed with
a Danger–Do Not Operate tag attached.
Overhead
Overhead circuits are reasonably short in length and faults are usually easy to
find. Most faults can be found by patrolling the circuit.
3-31
Switching Operator's Manual One
SECTION FOUR
HV Distribution – Overhead
Table of Contents
4. HV Distribution – Overhead .................................................................... 4-1
4.1 Introduction......................................................................................... 4-1
4.2 Components ....................................................................................... 4-3
4.2.1 Conductors .................................................................................... 4-3
4.2.2 Fuses ............................................................................................ 4-3
4.2.3 Pole Top Switch Disconnectors (PTS) ........................................... 4-7
4.2.4 Disconnectors (Isolators) ............................................................... 4-9
4.2.5 Surge Diverters and Arresters ..................................................... 4-12
4.2.6 Reclosers .................................................................................... 4-13
4.2.7 Single-phase Sectionalisers ........................................................ 4-19
4.2.8 Fusesaver ................................................................................... 4-21
4.2.9 Load break switches .................................................................... 4-25
4.2.10 Line Voltage Regulating Transformers ........................................ 4-26
4.2.11 Fault Indicators ............................................................................ 4-30
4.2.12 Transformers ............................................................................... 4-31
4.2.13 Reactors ...................................................................................... 4-31
4.3 Interconnection of Feeders ............................................................... 4-31
4.4 Common Distribution Faults ............................................................. 4-37
4.4.1 Vehicles Hitting Poles .................................................................. 4-37
4.4.2 Trees Touching or Falling on Mains ............................................. 4-37
4.4.3 Pollution Failures ......................................................................... 4-38
4.4.4 Pole Top Fires ............................................................................. 4-38
4.4.5 Animals ....................................................................................... 4-38
4.4.6 Transient Faults........................................................................... 4-38
4.4.7 Single-phasing Faults (Loss of one HV phase) ............................ 4-39
4.4.8 Feeder Faults – Drop Out Fuses Failing to Clear......................... 4-40
4.5 Fault Finding Process ....................................................................... 4-40
4.5.1 Single-phase Spur Faults ............................................................ 4-40
4.5.2 Three-phase Feeder Faults ......................................................... 4-42
4.5.3 Distribution Transformer Faults ................................................... 4-44
i
List of Figures
Figure 4-1 HV overhead distribution system ...................................................... 4-1
Figure 4-2 Typical microgrid network ................................................................. 4-2
Figure 4-3 Single shot drop-out expulsion fuse .................................................. 4-4
Figure 4-4 Sparkless fuse element..................................................................... 4-6
Figure 4-5 Typical wear rod – expulsion drop-out fuse ....................................... 4-7
Figure 4-6 Pole top switch ................................................................................. 4-9
Figure 4-7 Single HV disconnector (isolator) .................................................... 4-10
Figure 4-8 Opening disconnectors under load.................................................. 4-12
Figure 4-9 Surge diverter ................................................................................. 4-13
Figure 4-10 Nu-lec N-series recloser installation in the field ............................. 4-15
Figure 4-11 Nu-Lec operator control panel....................................................... 4-16
Figure 4-12 Kyle E hydraulic single-phase recloser (top left)............................ 4-17
Figure 4-13 Nu-Lec W-type single-phase recloser ........................................... 4-18
Figure 4-14 Sectionaliser operations on detection of a fault ............................. 4-20
Figure 4-15 Haycolec sectionaliser .................................................................. 4-21
Figure 4-16 Typical Fusesaver™ installation ................................................... 4-21
Figure 4-17 Installation of RTU & Fusesaver ................................................... 4-22
Figure 4-18 Remote Control Unit ..................................................................... 4-23
Figure 4-19 Remote Control Unit ..................................................................... 4-24
Figure 4-20 Remote Control Unit Display ......................................................... 4-25
Figure 4-21 RL series load break switch/sectionaliser...................................... 4-26
Figure 4-22 Load break switch/sectionaliser in the field ................................... 4-26
Figure 4-23 Horizon Power’s VR-32 voltage regulator ..................................... 4-27
Figure 4-24 Windings ....................................................................................... 4-27
Figure 4-25 Circuits of line voltage regulator .................................................... 4-28
Figure 4-26 Tap position indicator .................................................................... 4-28
Figure 4-27 Typical Horizon Power fault indicator ............................................ 4-30
Figure 4-28 Fault indicator operation ............................................................... 4-30
Figure 4-29 Types of feeder interconnection .................................................... 4-32
Figure 4-30 Circulating current......................................................................... 4-34
Section Four – HV Distribution – Overhead
List of Tables
Table 4-1 HV and LV fuse ratings ...................................................................... 4-5
Table 4-2 Types of reclosers used on Horizon Power networks ....................... 4-14
Table 4-3 Interconnection switching table ........................................................ 4-35
iii
Switching Operator's Manual One
iv
4. HV Distribution – Overhead
4.1 Introduction
This section examines components of the overhead HV distribution system, its
design principles and switching procedures. It is designed to give the switching
operator a working knowledge of HV overhead supply in the Horizon Power
distribution system.
This section is written to reflect current standards and may not include many of the
legacy installations and apparatus.
The overhead high voltage distribution system extends from the zone or microgrid
substation to the distribution transformers (see Figure 4-1).
Overhead HV circuits are connected radially, most having open points which permit
the interconnection of other feeders (see Figure 4-2). However, some feeders
cannot be interconnected with any other feeders. This causes a problem when
isolating sections of these feeders. If interconnection is not available, the power to
the isolated sections is interrupted for the duration of the isolation.
Pole top
switch
3-phase
transformer
Main feeder
1-phase
spur line
1-phase
transformer From
substation
4-1
Switching Operator's Manual One
Substation
F1 F2 F3
Legend
OH to UG cable head
Circuit breaker closed
Recloser
Pole top switch
or RMU switch disconnector closed
4-2
Section Four – HV Distribution – Overhead
4.2 Components
The main components of this system are conductors, fuses, pole top switches,
disconnectors, surge diverters, reclosers, regulators, sectionalisors, fault indicators,
transformers, distribution line reactors and capacitors.
4.2.1 Conductors
• AAAC - All Aluminium Alloy Conductor – sizes include 7/2.50 and 7/4.75
Only AAC, AAAC, SC/GZ (for repairs only) and SC/AC are now purchased as
standard bare overhead conductors. ACSR/AZ is also used for special applications.
However, the following conductor types may also be found in Horizon Power
networks:
• Hendrix-configured conductors.
4.2.2 Fuses
This fuse is designed to operate when current flow exceeds the fuse element
rating. Although the expulsion fuse is mainly a protective device, it may be used as
an isolation point, by removing the barrels from their frames and tying the barrels to
the pole with a Danger–Do Not Operate (D–DNO) tag.
4-3
Switching Operator's Manual One
• single vent – this is the most-commonly used type. Single vent DOFs do not
permit venting through the top.
• double vent – has a vent cap fitted allowing venting through the top should
the barrel be blocked (for example, a mud wasp nest), or the fault current be
too high.
Many brands of fuses are available but the design is basically the same.
The single shot drop-out fuse is most common (see Figure 4-3). It is used in the
three-phase system to protect distribution transformers (one fuse per phase). It is
also used in rural areas to protect the single-phase spurs which feed many
transformers.
Contact Terminal
assembly
Mounting
Operating
bracket
ring
Fuse barrel
in open position
Terminal
Safety hinge
4-4
Section Four – HV Distribution – Overhead
Fuses
Phase
kVA 11kV 22kV 33kV LV
The correct fuse element must be used to replace the fuse that
has been blown. This ensures appropriate grading is
! maintained. In emergencies, this may not be possible.
When replacing a fuse, the barrel must not be slammed with excessive force but
closed firmly and sharply. Care must be taken to check that the barrel has made
good contact and is seated correctly.
Insulated HV operating sticks are used to replace a fuse barrel into the mechanism.
The operator must wear appropriate PPE when operating these devices.
Horizon Power uses sparkless fuse elements to reduce the risk of ground fires. The
construction of a sparkless fuse is shown in Figure 4-4. The nylon tubing contains a
fuse element of lower melting point than the older types of fuse. A carbon-doped
Terylene cord is used to take the strain of the installed fuse.
4-5
Switching Operator's Manual One
Inner
Nylon tube Teflon heat
Tube crimp insulating tube
Tube crimp
Brass terminal
Tin fuse wire
Outer Nylon tube
Carbon doped
Brass terminal
Terylene cord
When the fuse element operates, arcing inside the barrel causes the internal barrel
lining (typically horne fibre) to produce a gas which vents through the bottom of the
barrel. This venting gas blows the arc outside the barrel where it extinguishes.
The fuse barrel then drops to release the top catch and then the barrel drops fully
away. This physically separates the circuit, preventing the arc from restriking and
providing visual indication the fuse element has blown.
Care must be taken when replacing a fuse element. The switching Operator must
check:
The switching operator should use an expulsion fuse wear rod to check the internal
diameter of the fuse barrels, as they have a limited life span. The wear rod is used
to determine whether the barrel is serviceable. The smaller diameter end of the
wear rod must be able to pass freely through the centre of the barrel, indicating
there are no obstructions.
If there is insufficient clearance inside the barrel, the fuse element may not clear
and the barrel may not drop away, causing extensive damage to the fuse barrel.
A flashover may result, shorting out the adjacent phases and tripping the feeder.
4-6
Section Four – HV Distribution – Overhead
The fuse wear rod larger diameter must not be able to enter the barrel, to ensure
there is an adequate amount of gas producing material lining (typically horne fibre)
the inside of the barrel. This gas producing material is required to extinguish the arc
inside the barrel.
The notch on the end of the wear rod is used to check the shrinkage of the gas
producing material inner tube. The shrinkage of the gas producing material should
not exceed this distance.
The fuse barrel must be replaced if any of these tests cannot be correctly
performed. A typical expulsion fuse wear rod is shown in Figure 4-5.
600 mm
500 mm
10 mm Ø 5 mm
13.5 mm Ø
This information is also provided in Field Instruction – Expulsion Drop Out Fuse
Barrel Inspection and Fuse Rating Requirements.
Pole top switch disconnectors are usually called pole top switches and are three-
phase air break switches used to provide:
• flexibility of supply
Pole top switches used for 11kV and 22kV systems are rated to 22kV. 33kV
systems use a larger pole top switch than the 22kV switch because they require
higher levels of insulation. 33kV-36kV-rated pole top switches are sometimes used
on the 22kV system in areas of high pollution.
4-7
Switching Operator's Manual One
Pole top switches are normally rated at 400 amps continuous load current and a
limited load breaking rating of 200kVA.
When operating pole top switches, the operator should remember the following.
1. Confirm the location of the pole top switch is correct against its asset label
and as identified on the switching program.
2. Before switching, check the pole top switch to see if it is in the expected
operational position.
(For example, if the switching program directs the switching operator to open
a pole top switch, before opening first check that the switch is closed. If the
switch is not closed, something is wrong with the program or the operator is
at the wrong switch.)
3. Before operating, check the mechanism for defects. Check earthing of the
switch handle and connections to the earthing mat. Also check that the flexi
tail is bent in the correct direction.
5. Ensure the correct PPE for switching is being used. Refer to the Field
Instruction Manual for the PPE appropriate to the switching operation.
6. When operating the switch, the switching operator should stand with feet
together on the earth mat to avoid any effects of step potential.
7. When opening or closing, make sure that the operation of the switch handle
is smooth and complete. A brisk speed of the operation should be used and
the operation must not be interrupted.
8. After the operation, visually check again to make sure both the main switch
contacts and the arc suppression contacts have been properly made or
broken.
9. All pole top switches have locking facilities that must be used at all times
(unless the switch is actually being operated). If the pole top switch is being
used as an isolation point, D–DNO tags are locked onto the operating handle.
4-8
Section Four – HV Distribution – Overhead
Arcing
suppression
PTS contact
Flexi tail PTS
Open Closed (On)
(Off)
Contact
in closed
position
Main contact
Pipe bracket
leading to
Operating
Handle
On Pivot
point
Operating
Off Handle
OFF ON
HV disconnectors have a lower rating than a pole top switch, 100 amps being
typical. Normally, they are used to open or close on no load, or to open and close
on limited interconnection loads.
4-9
Switching Operator's Manual One
Clip
Pull
down
here
Bolted
to
crossarm
Blade
4-10
Section Four – HV Distribution – Overhead
1. Confirm the location of the HV disconnector is correct against its asset label
and as identified on the switching program.
(For example, if the switching program directs the switching operator to open
HV disconnector, before opening first check that the disconnector is closed.
If the switch is not closed, something is wrong with the program or the
operator is at the wrong disconnector.)
4. Ensure the correct PPE for switching is being used. Refer to the Field
Instruction Manual for the PPE appropriate to the switching operation.
6. When opening or closing, make sure that the operation of the blade is smooth
and complete. A brisk speed of the operation should be used and the
operation must not be interrupted.
When closing, the blade must not be slammed shut with undue force. This
action must be firm.
7. After closing, the operator must check the blade is fully shut and correctly
aligned between the contact points.
8. After the operation, visually check again to make sure both the main blade
contacts and, where fitted, the arc suppression contacts have been properly
made or broken.
4-11
Switching Operator's Manual One
Crossarm
2 1 3
HV disconnectors
Pole
Note: The operation should be carried out in the sequence 1–2–3 to give
maximum clearance to the second operation (as it produces the largest arc).
Note: The internal failure of a surge diverter may result in a permanent phase to
earth fault.
4-12
Section Four – HV Distribution – Overhead
Phase
connection
End fitting
Silicone housing
Fibre reinforced
plastic rods
4.2.6 Reclosers
The recloser is a pole mounted circuit breaker connected in-line (series) in a feeder
or spur. It is used to interrupt fault current, automatically restoring power after a
transient outage. Recloser protection is required to grade with distribution feeder
circuit breaker protection for correct protection operation.
• clear the fault and restore service with the minimum delay
Reclosers are set to trip and restore power multiple times before locking out. The
time lapse between trips may also be changed to suit different circumstances.
4-13
Switching Operator's Manual One
Types of reclosers
Reclosers are available in many different forms as shown in the table below:
Characteristics
Number of phases
Three-phase and single-phase reclosers are used to match the distribution system
where they are installed.
Operation
Both electronic and hydraulic control reclosers are currently in use. Electronic
controls panels are used with the Nu-Lec reclosers, and the Kyle E recloser is a
lever-operated hydraulic recloser.
4-14
Section Four – HV Distribution – Overhead
Three-phase recloser
The three-phase recloser used on HV lines is the Nu-Lec N-series. Figure 4-10
shows a typical Nu-Lec recloser and electronic control box installation.
Disconnectors
to isolate
the recloser
Single-phase
Disconnectors
transformer
to isolate
drop out fuse
the recloser
Surge diverters
on both sides
Single-phase Nu-lec
transformers for N-series recloser
240V supply
ON – OFF
indicator
Recloser
control box
Bypass pole
top switch
operating handle
• the electronic control panel is mounted in a box at the bottom of the structure
or pole. Figure 4-11 shows the operator controls and indication.
4-15
Switching Operator's Manual One
• a separate power supply is required for the control panel. This can be
provided by a nearby LV supply or where this is not available, a single-phase
HV fused transformer is mounted on the recloser pole (see Figure 4-10) or a
nearby pole.
• a bypass pole top switch and three disconnectors on each side of the
recloser are installed to enable continuity of supply and isolation of the
recloser for maintenance work. At some locations, such as Leonora, the
disconnectors have not been installed.
Single-phase Reclosers
These reclosers are used on single-phase HV spurs. The main types used by
Horizon Power are:
• Nu-Lec W type
4-16
Section Four – HV Distribution – Overhead
• hydraulic operating mechanism with operating lever and a ‘single shot’ non-
reclosing lever which are operated with an insulated HV operating stick. The
switching operator should recognise the operating positions of the recloser
levers shown in Figure 4-12 (on/off/single shot).
Cyclometer
Closed
Open
Non-reclosing
4-17
Switching Operator's Manual One
Manual
lever
Status
indicator
• manual lever – UP position allows for normal operation, and in the DOWN
position the recloser is tripped and both mechanically and electronically
locked open.
The recloser connections should not be earthed until both sides are isolated.
4-18
Section Four – HV Distribution – Overhead
• the location of the control box, making them targets for vandalism.
Normally, sectionalisers have a bypass drop-out fuse mounted on the same pole.
When sectionalisers are removed for any reason, the fuse barrel may be installed
to protect the line and maintain supply for the period of removal.
When a fault F1 occurs down the line from the sectionaliser S1 (in its normal zone
of protection), the fault current is sensed by both the recloser R1 and the
sectionaliser S1. The recloser R1 trips and de-energises the line. The sectionaliser
S1 count is one, due to the fault current.
4-19
Switching Operator's Manual One
Substation
S2
R1
S1
F1
The recloser R1 recloses again and fault current is sensed by R1 and S1. R1 trips
again and S1 has now reached its count of 2; it opens, disconnecting the fault F1
whilst the recloser is open. The recloser R1 again recloses and the feeder is
restored with the exception of the faulted line section after S1.
In another scenario, the recloser R1 and sectionaliser S1 have the same settings
as above. However, this time F1 is a transient fault (the first reclose attempt is
successful).
On seeing the fault, recloser R1 and sectionaliser S1 sense the fault current.
Recloser R1 opens and the sectionaliser S1 count is one. The recloser R1
recloses, this time successfully as the fault has cleared. Sectionaliser S1 has not
reached its count and remains closed. The complete feeder is restored. Both the
recloser R1 and sectionaliser S1 fault counts are reset back to zero after a set time
delay.
Sectionalisers may be used in series. Where this occurs, the sectionaliser further
down the line will be set for fewer counts. (Normally, they are set for either two or
three shots.)
Before the line tap is removed, the load current must be broken with the
sectionaliser.
4-20
Section Four – HV Distribution – Overhead
This electronic unit counts the times fault current passes through the link and
activates the latch mechanism, allowing the link to open by swinging down on the
bottom hinge point when its set count is reached. The desired count is set with
switches on the link.
Operating
ring
Electronic
sectionaliser
link
Electronic
sectionaliser
link fitted to holder
Hinge point
When used as an isolation point, the sectionaliser link must be fully removed from
the holder and tied to the pole with a D–DNO tag.
4.2.8 Fusesaver
Fuse savers are used on single-phase spurs and connected in series with the
associated drop out fuse. Figure 4-16 shows a Fusesaver.
To
To line
drop out
fuse
4-21
Switching Operator's Manual One
When a fault occurs the Fusesaver vacuum interrupter opens, disconnecting the
line before the associated drop out fuse element can melt. The Fusesaver remains
open for a period of one to 30 seconds dependent on the setting, giving time for a
transient fault to clear. The Fusesaver vacuum interrupter then closes. Therefore,
for a transient fault the power is fully restored. However, for a permanent fault the
associated drop out fuse blows, resulting in a loss of power.
The Fusesaver has the capability to improve system reliability, because a transient
fault does not cause the drop out fuses to blow.
Fusesavers have the ability to be incorporated into a SCADA system via a Remote
Control Unit (RCU). The RCU works in partnership with a Fusesaver to increase
network automation by allowing the Utility Control Centre to be able to remotely
monitor and control Fusesavers.
Additionally, the RCU can be equipped with a local control panel to enable a local
Switching Operator control of the Fusesaver. Remote Control Units are outdoor
installed devices that are normally pole mounted close to a single or ganged set of
Fusesavers.
4-22
Section Four – HV Distribution – Overhead
4-23
Switching Operator's Manual One
The electronic housing contains the micro-processor, battery, power terminals, data
connection points and the user interface for the RCU. The RCU has a simple user
interface for operations and maintenance purposes. The panel makes use of LED
indicators, which are not illuminated when the door to the panel is closed to save
power.
4-24
Section Four – HV Distribution – Overhead
The purpose of SCADA connecting through the RCU is to allow remote operation of
the devices it controls as well as to review event data.
2). Issue trip and close commands to the Fusesaver via the RCU. The RCU must
have the Remote Control Switch set to “ON” for this to be possible.
3). Change protection settings in the Fusesaver via the RCU. The RCU must have
the Remote Control Switch set to ON for this to be possible.
The LBS can be operated from the local electronic control panel attached to the
pole, or manually operated using an insulated HV operating stick in the operating
lever rings. The electronic control panel requires an external power supply and
when fitted with a communications system will provide remote operation.
The LBS provides a mechanical indicator for the switching operator to verify the
switch status. The LBS lockout lever is provided to mechanically lock the switch
4-25
Switching Operator's Manual One
contact mechanism in the open position. This is part of the requirement to use the
LBS as an isolation point. Further details are provided in Field Instruction – Nu-Lec
RL (SF6) load break switch as an isolation point.
Operating SF6
lever contact tank
4-26
Section Four – HV Distribution – Overhead
MOV-type
series arrestor
Bushings
Tap position
indicator
Tap changer
motor capacitor
Control
Tap position
indicator
Iron core
Primary winding
Secondary winding
a. Connected magnetically
Winding
Auto transformer
b. Connected electrically
4-27
Switching Operator's Manual One
Bypass disconnect
A B
Unregulated
Regulated
Line Load
Main
winding
The regulator on-load tap changer has 32 tap positions (see Figure 4-22). This
allows the regulated load voltage to range from 90-110% of the unregulated line
voltage. The tap changer is controlled by automatic voltage regulating relays with
line drop compensation.
4-28
Section Four – HV Distribution – Overhead
Note: When closing the bypass disconnector, the tap changer must be in the
neutral position so the unregulated line and regulated load voltages are the same.
If the tapping mechanism is in any position but neutral, closing the bypass switch
short-circuits the tapped winding coils and results in heavy circulating current flows.
2. Using the push button control, adjust the regulator to the neutral tap position.
Check all indicators.
(A light may indicate when the mechanism is on the neutral tap. The
switching operator must check the mechanical tap indicator and nameplate
for the neutral tap setting.)
3. Close the bypass switch. (This may have a mechanical or electrical interlock.)
4. Open the disconnectors on the line and load sides of the regulator.
1. Check the regulator is on manual control and in the neutral tap position.
2. Close the disconnectors on the line and load sides of the regulator and
remove any D–DNO tags.
To avoid errors, the switching operator must check each step and work
methodically.
4-29
Switching Operator's Manual One
Fault indicators are used to assist in locating faults by indicating the path fault
current has flowed. A range of fault indicators are used in Horizon Power; a
common example is the SEL AR360 AutoRANGER® fault indicator (shown in
Figure 4-23). This fault indicator is clipped onto the overhead line conductor using
an insulated HV operating stick.
Use an
insulating HV operating stick
to install the fault indicator
Fault indicators detect the presence of a fault by the sudden increase in current
flow, caused by the fault current which is followed by the loss of voltage as the
protective device operates to disconnect the fault.
A successful auto reclose would indicate a temporary fault and the fault indicator
flashes amber. However, an unsuccessful auto reclose resulting in permanent loss
of supply would cause the fault indicator to flash alternately red-amber.
Fault detectors
Three-phase
feeder
A B C
Fault current flow
Substation
F1
In Figure 4-24, a line fault F1 is located between fault indicators B and C. Fault
indicators A and B operate as the fault current has passed through them, however
fault indicator C does not operate as the fault current did not pass through C.
4-30
Section Four – HV Distribution – Overhead
Most fault indicators will self-reset after a set time period. Others must be reset
manually after the fault is found.
Note: The manual fault indicator must be reset as soon as possible. In the event
of a further fault before resetting, the operator will not be able to tell whether the
fault current passed the indicator point. The indicator would still show the previous
fault.
4.2.12 Transformers
• pole top
• padmount
4.2.13 Reactors
Reactors are used mainly on 33kV distribution lines. Normally, they are protected
by drop out fuses.
4-31
Switching Operator's Manual One
Substation 1 Substation 2
T1 T2 T1
F1 F2 F3 F4
NOP
B
NOP NOP
A C
Figure 4-25 shows two substations S1 and S2 and four feeders F1, F2, F3 and F4
with normally open points A, B and C. There are two basic types of feeder
interconnection:
• to transfer load
4-32
Section Four – HV Distribution – Overhead
• the selection of the best location for interconnection (for example, for circuit
breaker isolation, interconnection should be close to the substation)
• the need for two or more connection points, where required by the load
• the type of switchgear used for interconnection (for example, pole top
switches or disconnectors)
Figure 4-26 shows circulating current. T1 and T2 are set at different taps, therefore,
the secondary busbars will be at different voltages.
If the bus coupler A is closed under this condition, a current will be driven around
the transformers, as shown. This is called circulating current and may be several
hundred amps for large tap differences. The smaller the tap difference, the less
circulating current will occur.
The same principle applies when bus coupler A is left open and two feeders F2 and
F3 on opposite bars are interconnected with a pole top switch or ring main unit
outside the substation. To minimise the circulating current through the feeders,
transformer T1 and T2 taps need to be set reducing the voltage difference. Failure
to reduce the circulating current may result in the interconnected feeders tripping
on overcurrent.
The circulating current will lessen the further the pole top switch or ring main unit is
from the substation because of the increased line impedance. For example, the
circulating current through NOP C will be less than NOP B. The circulating current
is negligible over two kilometres from the substation, unless most of the feeder is
underground cable.
4-33
Switching Operator's Manual One
Circulating
T1 current T2
Tap 6 Tap 8
NOP
Bus
coupler A
F1 F2 F3
NOP B
Close in NOP
NOP C
Distant NOP
4-34
Section Four – HV Distribution – Overhead
Note 1 Transformers must be set to manual and the taps must be matched if the length of the feeder route is
more than 50% cable.
Note 2 Transformers need only to be set to manual when the feeder length route is more than 50% cable.
Note 3 This applies to reclosers installed in feeders as well as substation feeder breakers.
Note 4 This applies only for outdoor substations with a disconnector type bus coupler.
Note 5 Sensitive Earth Fault – Flag 14.
Note 6 Taps may need to be adjusted if separate substations have extreme voltage differences.
Note 7 If the switching operator is concerned that there may be a flashover or fault on the switching apparatus
they are operating, they must set the feeders/reclosers to manual to prevent multiple automatic reclose
operations when paralleling feeders.
Adjust Taps
Adjusting transformers to the same tap or voltage is carried out when switching
inside two kilometres of the substation. Circulating current result if switching inside
two kilometres, while on different taps. The current may trip the feeder or cause
excessive arcing on the interconnecting apparatus.
4-35
Switching Operator's Manual One
When switching with pole top switches, 'feeder earth fault out' is not necessary.
(However, it is necessary when switching a three-phase set of single-phase
disconnectors. If this is not done, the feeder may trip. This is due to the out-of-
balance load as the first disconnector is operated during interconnection.)
Always switch with a ganged three-phase device rather than a single-phase device,
where ever possible.
Note: When carrying out three-phase isolation of a rural feeder connected with
single-phase spurs, earth fault protection may operate due to out-of-balance
current.
Nu-Lec Reclosers
The bus coupler may need to be closed when interconnection is carried out:
The bus coupler (circuit breaker or switch) is closed, because it has a higher rating
than field equipment. It may also be fault rated.
4-36
Section Four – HV Distribution – Overhead
The reverse is true when reinstating the bus coupler to normal. The switching
operator should first open the interconnection point in the field and then open the
bus coupler.
The switching operator must remember to adjust the taps before operating the bus
coupler.
In outdoor substations, the bus coupler is normally a switch, not a circuit breaker.
When interconnecting with the bus coupler, with the substation capacitor banks in
service, there is a danger of flashover.
If the bus coupler has to be operated at a zone substation, all capacitor banks may
need to be taken out of service, according to local conditions. The operation of
capacitor banks may cause unwanted transient spikes through the system. (Local
rulings determine when capacitor banks should be operated.)
When interconnecting feeders, the sensitive earth fault must be made inoperative.
This is because the slightest out-of-balance load may be detected and trip the
feeder. The out-of-balance may be caused by something as simple as poor contact
on a pole top switch.
Note: Not all overhead feeders have sensitive earth fault protection activated.
Underground feeders will not have sensitive earth fault protection enabled.
When a vehicle hits a pole, a power failure may occur due to the conductors
clashing or shorting to earth. At times, the feeder successfully recloses.
Foliage and wet limbs of trees touching the mains can conduct electricity and cause
short circuits between conductors. This may result in a circuit breaker tripping or a
high voltage fuse blowing. Falling or swaying trees, and their limbs, may also
damage or break conductors, resulting in live wires falling or hanging dangerously.
4-37
Switching Operator's Manual One
The pollution from industrial areas and exposed coastal areas may result in
flashovers, pole top fires or radio interference.
Pole top fires normally occur on those structures that have loose connections or are
poorly bonded. Pollution, lightning damage and rain also contribute. Fires are more
frequent with the first light rains following a long dry summer and also occur with
high humidity at the end of summer. The fires are caused by leakage from, or
damage to, the insulator. As a result, the current may track down the insulator to
earth, or flow between the conductors. The tracking current through the wooden
pole and wooden crossarm will heat the wood and may eventually, set them on fire.
4.4.5 Animals
Both domestic animals and wild life may interfere with mains by short-circuiting the
phases. Cats, birds and flying foxes may create problems.
Faults with no known cause may trip a feeder that then successfully recloses.
These are called transient faults. On the other hand, a feeder may trip and lock out.
Switching operators will then be called upon to patrol and then sectionalise the line
to determine the position of the fault.
For recurrent transient faults, the relevant part of the feeder or spur must be
patrolled.
• High winds cause tree limbs to come into contact with mains. This problem
may be observed by the burning ends of branches and dead leaves. (The
switching operator should find, cut and remove the problem limbs of trees
using suitable safety procedures.)
• High winds and slack bays of mains may result in conductors swinging
together and clashing. (When patrolling lines, the switching operator should
look for burn marks or pitting on the conductors.)
• Hot weather may cause excessive sag in long bays. Lines may touch trees in
the heat of the day but be quite clear early in the morning or at night. (When
patrolling, the switching operator should carefully examine the height of trees
near the middle of long bays.)
4-38
Section Four – HV Distribution – Overhead
• Vehicles hitting poles may stretch street light circuits, customer services,
stays and mains. Lines may become so taut that they break, whip up into the
HV mains, cause a short circuit and then fall clear. These accidents may also
break conductor ties or split crossarms. (Close checking of pole tops is
required here.)
• Faults near water and grain storage areas may be caused by birds that fly
into exposed lines, especially at dusk or sunrise. (The switching operator
should look for signs of dead wildlife or feathers when patrolling the line.)
• Insulation failures may be transient. Surge diverters may be faulty but look
perfectly normal. Pin insulators may puncture beneath the conductor and trip
the line when moisture fills the puncture. (These faults are extremely difficult
to find.)
The open circuiting of one HV phase will not operate feeder circuit breaker
protection, because of the balanced current on the healthy two phases.
• a tap may burn off at a pole top switch, a corner tapping pole, or a
termination.
• the contacts on a pole top switch may overheat and burn so badly that the
contacts become highly resistive. They may also melt away from each other
resulting in an open circuit.
4-39
Switching Operator's Manual One
After the repair and restoration of a permanent phase to phase or earth fault, or the
successful reclose after a transient fault, complaints about dim lights or partial
supplies may be received. Such complaints may indicate the fault current from the
previous fault has also caused an open circuit HV conductor or a blown HV fuse.
Sometimes faults occur on fused spurs or circuits that feed transformers. A whole
feeder may trip for the following reasons:
• The fuse operates too slowly, because it may be incorrectly sized or have
been hard wired.
• The expulsion tube (in which the arc extinguishes) fails to function correctly.
A flashover then results, causing the feeder to trip instead of the drop out
fuse (DOF).
The fault finding process requires a close review of any protection or fault indicator
operation and a systematic approach to the trial restoration process.
Note: Line patrols for faults are mandatory for overhead HV circuits within town
boundaries and overhead LV circuits.
Risk assessment and line patrol requirements for feeder and auto-recloser lockout
and sectionaliser operation are similar to those for fuses.
Examples of the approach typically used for fault finding specific types of faults are
given below.
Single-phase HV spurs are often protected by single and multiple drop out fuses.
They may have disconnection points (live line taps) at several points throughout the
4-40
Section Four – HV Distribution – Overhead
spur.
HPCC manages HV fault switching and will guide the switching operator to ensure
compliance with Field Instruction – Replacing fuses on the HV/LV underground and
overhead network after a fault has occurred for line patrol requirements. HPCC will
then the request the operator at the appropriate time to perform the following steps:
• If the fault was transient, the fuse will hold. A full line patrol is required
at the earliest practical time, if not already carried out.
• If the fuse blows when it is replaced the fault is permanent , the line will
then need to be sectionalised and reenergised until the fault is located:
o Once the faulted section is found, the healthy sections of the line
may be reinstated.
o The line fault can then be rectified and the line may be returned to
normal.
Note: The fault may cause arcing and sparks every time the fuse is replaced. (Dry
conditions present a real danger of fire in this case.)
The fault may be a conductor close to the ground. (This places people and stock at
great risk.)
The fault may be in a transformer and not visible. (In this case, each transformer or
group of transformers must be disconnected in order to locate the fault.)
For two and three shot fuses, the fault finding process is the same as for single
shot drop out fuses.
Fault finding for recloser and sectionaliser operation is described in Section 4.2.
The switching operator should consider the following.
• To locate a fault when fault switching, the reclosers must be set to 'manual'
(single shot or non-reclosing). The recloser is fully rated for fault switching.
4-41
Switching Operator's Manual One
• The sectionaliser must not be used for fault switching. The sectionaliser
bypass fuse should be used, where available. If it is not available, use the
recloser.
Note: Regular records of the number of reclose attempts are kept. This assists
district staff to identify any spur that has a high percentage of transient faults. Such
spurs can be patrolled and the problems identified.
Records should also be kept for three-phase reclosers protecting the whole feeder
or parts of the feeder.
HPCC manages three-phase fault switching and the manual reclosing of feeders
and will direct the switching operator on the actions required. Details of the typical
actions are provide below.
Transient Faults
Transient faults on feeders are reinstated by auto reclose of the circuit breakers at
the substations or line reclosers. Where the number of reclose attempts is high in
normal conditions, the line will be requested by HPCC to be patrolled to locate and
rectify the transient fault.
Manual Reclose
At times, the complete feeder trips and, following the required number of reclose
attempts, the circuit breaker locks out at the substation. HPCC will request field
staff to investigate the fault with a line patrol. If called to attend a substation, the
switching operator must record all flagging in the logbook before resetting the flags.
For short feeder lengths, the line is patrolled from the substation. If required the
patrolled sections can be progressively reinstated.
For long 22kV and 33kV feeders it may be necessary to patrol, sectionalise and
attempt trial reclose operations to locate the fault. Therefore, the feeder should be
opened at an appropriate point of the feeder, approximately half way. After manual
reclose, if the first half of the feeder stays in, the remaining half of the feeder should
be opened at its half way point.
4-42
Section Four – HV Distribution – Overhead
The feeder may then be tripped at the substation and the first open pole top switch
should be closed. If the pole top switch is fault-rated, the feeder does not need to
be tripped. If the reinstated feeder stays in, the fault must be contained in the last
quarter of the feeder. The feeder may be broken again or patrolled, depending on
the length of the remaining feeder.
During fault switching, after location and isolation of the fault, further faults may be
found as the feeder is restored. This is because the high fault current travelling to
the fault may cause more damage to other parts of the feeder. The following
problems may occur under these circumstances:
• drop out fuse flashover causing the original trip – once the feeder is
reinstated, the drop out fuse still needs to be replaced
• a burnt off tap – during the transient fault, the fault current has been
sufficiently large to burn off a connection. If the live side falls clear of all
other apparatus when it is energised after a reclose, the feeder will hold
in. However, dim supplies will occur past the burnt off connection.
• blown drop out fuses – a drop in voltage may cause the operation of
deteriorated fuses or fuses with a very small rating.
• HPCC manage all unplanned outages and will request the required line
patrols.
• HPCC must be advised of all flags recorded at the substation (if attendance is
required).
• Pole top switches are designed to make fault current, but not break fault
current.
4-43
Switching Operator's Manual One
• The auto reclose device must be taken out of service when fault switching at
zone substations and/or feeder reclosers which are installed along the line.
• While the faulted section is being located and repaired, the unfaulted line
sections may reinstated. For example, unfaulted line sections may be fed
from the zone substation or be interconnected using another feeder.
• The same fault finding principles, as those for a feeder from a zone
substation, apply to fault finding beyond a recloser.
Note: If the stated rating is not exceeded when closing on a fault, the pole top
switch may be used instead of the circuit breaker.
See Section 3.4.3 for a description of overhead transformer faults and the
associated procedures required.
4-44
SECTION FIVE
HV Distribution – Underground
Table of Contents
5. HV Distribution – Underground .............................................................. 5-2
5.1 Introduction ........................................................................................ 5-2
5.2 System Components .......................................................................... 5-2
5.2.1 Cables ........................................................................................... 5-2
5.2.2 High Voltage Cable Terminations .................................................. 5-4
5.2.3 Ring Main Units ............................................................................. 5-6
5.2.4 HV Metering ................................................................................ 5-20
5.2.5 Ground Mounted Distribution Transformers ................................. 5-20
5.3 Design Principles.............................................................................. 5-21
5.3.1 Method 1 – Standard RMU single transformer............................. 5-21
5.3.2 Method 2 – Single RMU with multiple transformers ..................... 5-22
5.3.3 Method 3 – Overhead supply to transformer................................ 5-22
5.3.4 Method 4 – Piggy-back transformers ........................................... 5-23
5.3.5 Method 5 – Single-phase underground distribution system ......... 5-25
5.3.6 Combination of Methods ............................................................. 5-25
5.4 Switching Procedures ....................................................................... 5-27
5.4.1 Planned Switching ....................................................................... 5-27
5.4.2 Fault Indicators............................................................................ 5-32
5.4.3 Fault Switching ............................................................................ 5-33
5.5 Ferroresonance ................................................................................ 5-34
5.6 Traps ................................................................................................ 5-37
5.6.1 Isolating Both Ends of Cable before Earthing .............................. 5-37
5.6.2 Switchgear Interlocks .................................................................. 5-37
5.6.3 Switchgear Testing Facilities ....................................................... 5-38
5.6.4 Not having a Mental Picture of the Circuit.................................... 5-38
5.6.5 Ferroresonance ........................................................................... 5-38
5.6.6 Maps and Diagrams not Up-to-Date ............................................ 5-38
5.6.7 Not Using Meters or Indicators .................................................... 5-38
5.6.8 Lack of Local Knowledge............................................................. 5-39
5.6.9 Equipment Labelling .................................................................... 5-39
i
Switching Operator's Manual One
ii
Section Five – HV Distribution – Underground
List of Figures
iii
List of Tables
Table 5-1 Cable applications .............................................................................. 5-3
Table 5-2 Typical makes and types of ring main units ........................................ 5-6
Table 5-3 Ring main HRC fuse ratings ............................................................... 5-8
Table 5-4 Operational positions and their electrical status ............................... 5-13
Table 5-5 Mechanical interlock status in relation to operational positions ......... 5-14
Table 5-6 DOF sizes for piggy backed transformers ........................................ 5-25
Table 5-7 Critical cable length for ferroresonance – XLPE cable ...................... 5-36
Table 5-8 Critical cable length for ferroresonance – PILCSWA cable ............... 5-36
5-1
Switching Operator's Manual One
5. HV Distribution –
Underground
5.1 Introduction
This section deals with the operations of HV (11kV to 33kV) underground
distribution systems. These systems may be combined within an overhead system
or used solely from the zone substation to the distribution transformers.
The fundamental principles of the underground HV system are the same as those
of the overhead system. However, certain areas require different designs for
operation procedures.
This section is written to reflect current standards and may not include many of the
legacy installations and apparatus.
5.2.1 Cables
Horizon Power uses cables in a variety of sizes and voltages, depending on the
need. The main cables are shown in Table 5-1.
In addition to those listed, many older sizes and types of cables are found in
Horizon Power's system.
5-2
Section Five – HV Distribution – Underground
Distribution 35 Al
22
transformer 50 Al
33 50 Al
XLPE Cables
Cross-linked polyethylene (XLPE) cables are the standard cable. Polyethylene has
the following advantages over previous insulants:
• low cost
• low capacitance
• ease of extrusion
Termite Conductor
protection layer Metallic
screen
shield
LV
Concentric
round
HV
Compacted
conductor
Conductor
Outer sheath
Insulation Insulation
screen
5-3
Switching Operator's Manual One
PILCSWA Cables
PILCSWA cables are paper insulated with lead sheathing and steel wire armour.
The cable has a conductive screen of metal tape around each core that aids the
detection of any earth leakage current from an individual core. The lead sheath
prevents moisture from entering the cable while the wire armours provide
mechanical protection around the cable.
Where the cable is terminated, the screening, the lead sheath and the steel wire
armours are each connected to the earth system of the zone or distribution
substation.
This means that there is a fully screened system bonded to earth, except for the
small area where the screening does not meet the cable box bushings at the
terminations. Therefore, nearly all cable faults will be detected and cleared by
earth fault relays.
Although no longer installed, these PILCSWA type cables will be found in older
systems.
High voltage cable terminations are used to connect high voltage cables to Horizon
Power’s indoor and outdoor switchgear and pole mounted terminations. The
integrity of the connection is paramount to ensure terminations are able to
withstand peak load requirements and not fail during fault events.
5-4
Section Five – HV Distribution – Underground
Apparatus Use
Horizon Power's cable terminations are not rated as switching devices. Any
removal or modification will need to be done under an Electrical Access Permit
(EAP). Before switching and where possible, a visual inspection should be
performed to check integrity, including baling assemblies and terminations for
tracking or other defects.
5-5
Switching Operator's Manual One
Many styles and designs of ring main units are used by Horizon Power (for details
see Table 5-2). They are mainly non-withdrawable units with a few remaining
withdrawable units.
Make Type
Areva/Alstom FBA
Ring main switch and fuse switch contacts have a ganged three-phase operation.
The insulating materials used in the switch contact chamber to extinguish arcing
during operation are:
A typical ring main unit is shown Figure 5-4 below. The ring main unit has a fuse
switch in centre position with a switch on either side.
5-6
Section Five – HV Distribution – Underground
These switches are used on distribution underground systems for the same
purpose as pole top switches on overhead systems.
Ring main switches are connected between the internal bus bar and the cable as
shown in Figure 5-7 and incorporate either an internal earth function or facilities for
external earthing. The earth function works on the cable side and not the busbar
side of the ring main switch.
The normal configuration of a ring main unit is two ring main switches and a
number of switch fuses, although other configurations may be installed where
required.
Typically, the maximum full load rating of a ring main switch is 630 amps.
Particular details for each type of ring main unit can be found on the nameplate.
Fuse switches are used on distribution underground systems for the same purpose
as drop out fuses on overhead systems.
Switch fuses are used extensively in ring main systems, as an economical means
of protecting distribution transformers. They are similar to ring main switches in
construction, but include a HV HRC fuse to provide fault interruption and an
associated automatic three-phase trip as shown in Figure 5-6.
5-7
Switching Operator's Manual One
• quick isolation of the fault, minimising the risks of injury and damage to
equipment
Switch fuses typically have a maximum full load rating of 200 amps.
The size of the fuse to be used depends on the size of the transformer to be
protected. For example, an 11kV 500kVA transformer is protected by 63 amp HRC
fuses. The fuse sizes range from 6.3 amps to 80 amps (see Table 5-3).
160 25 10 6.3
315 31.5 16 16
Three-
500 40 25 -
phase
630 50 31.5 20
750 63 40 -
1000 80 40 40
Note: 33kV ground mounted distribution transformers are mainly fed via overhead
drop out fuses.
HV HRC fuses consist of a porcelain cylinder with end caps and an internal fuse
element and striker pin. The fuses are located in a dry air insulated chamber
attached to the switch tank.
5-8
Section Five – HV Distribution – Underground
Seal
End cap
Ceramic spider
Silica powder
Fusible elements
Porcelain tube
Porcelain beads
End cap
Seal
When the fuse blows, the striker pin in the cartridge is released. This protrudes
outside the cartridge, striking the trip bar device on the fuse switch. The switch
then trips to the 'off' position. An indicator on the face of the fuse cabinet may be
provided to show the fuse has blown.
Because fuse striker pins are fitted at one end only, the striker pin must be
correctly located adjacent to the trip bar mechanism. Note the arrow on the fuse
body in Figure 5-5, indicating the correct direction of the striker pin.
Access to a fuse is not possible unless it is isolated, that is, the switch fuse is
switched 'off'. Where switches have an internal earth function, the switch must be
put to the 'earth' position before access to the fuse chamber is possible. Where
switch fuses are withdrawable, they must be switched 'off' and racked out for
access to the fuses.
• the internal bus bar section of the ring main unit is normally energised, and
• the fuse must be fitted with the striker pin towards the trip mechanism.
5-9
Switching Operator's Manual One
The ring main units consist of the required number of switches and fuse switches
to match their application in the network. Figure 5-6 shows a ring main unit with
two switches and two fuse switches. This arrangement is commonly referred to as
a 2+2 unit. Figure 5-7 shows a unit with only four switches (4+0 unit).
Switch
Trip Trip
signal signal
Earth switches
operate
together
Fuse
Cables
Figure 5-6 Schneider RM6 two ring main switch and two switch fuse
Earth
switch
Switch
Cables
Extendable units provide the capability to build the required configuration by joining
together the required number of switch and fuse switch modules. Each module is
5-10
Section Five – HV Distribution – Underground
joined to the next with air-insulated connection joints. Where the switch and fuse
switch modules are SF6 -insulated, each module has a separate SF6 chamber and
associated pressure gauge.
Removable joints
Extendable
if required
Transformer
One tank
Transformer
5-11
Switching Operator's Manual One
Shown in Figure 5-9 below is the principle of withdrawable ring main units with a
withdrawable truck unit for both a ring main switch and a switch fuse. The figure
shows the truck C may be moved in or out of the housing D. When the ring main
switch is inserted into its correct position, it plugs into the HV cable spouts A and
the busbar spouts B. When physically withdrawn the switch separates from the
busbar and cable connections as shown for the ring main switch in the right image
of Figure 5-9.
In its correctly plugged-in position, the interlock of the ring main switch may be set
to the 'service' position. The switch can then be operated to 'on' or 'off', as
required, usually by means of a spring charged device.
The interlock prevents the switch from being withdrawn while it is in the 'on'
position. It also prevents the switch being racked in if the truck is in the 'on'
position.
The withdrawable switch fuse is constructed and operated in the same way as a
ring main switch but contains three fuses (see Figure 5-9 left). It must be switched
'off' and racked out into the withdrawn position out before the fuses can be
replaced.
C C C
B B B
A A A
Figure 5-9 Ring main switch in the service and withdrawn positions
Note the ring main fuse switch on the left is also a withdrawable unit.
It can be seen that underground and overhead systems are almost identical in
operation but there are important differences.
• Ring main units have a cable earthing facility. This may be a switch or manual
plug-in device that is used instead of portable overhead earth sets.
5-12
Section Five – HV Distribution – Underground
• Ring main units are designed so that the transformer's switch fuse opens if a
fuse blows. This produces a three-phase trip if any fuse blows. (Drop out fuses
only trip one phase).
• The switch contacts are inside the chamber and are not visible. The switching
operator must prove the circuit is de-energised before the earths are applied.
(Some units have neon indicators while others have external testing devices.)
Operation of Switches
Ring main switches and fuse switches have three operational positions – ON, OFF
and EARTH. A description of the electrical status for each position is shown in
Table 5-4 below.
Operational
Electrical status
position
Most ring main switches and fuse switches have separate switch operating
mechanisms or earth switch operating mechanisms, whereby a handle is inserted
to operate the switch or earth switch. Switching is restricted to one operation at a
time to ensure each operation is separate and deliberate.
Mechanical interlocks between the switch and earth switch mechanisms restrict
the allowable combination of the switch and earth switch position to those shown in
Table 5-5 below.
5-13
Switching Operator's Manual One
Earth
Operational Switch
Electrical status switch
position position
position
One exception to this arrangement is the Brown Boveri ring main unit, which has a
plug-in portable earth rather than an earth switch.
Figure 5-10 shows an example of the mechanisms and indicators on the front
panel of a ring main unit.
Earth switch
operating handle
socket
Switch operating
handle socket
Mechanical
indicator
5-14
Section Five – HV Distribution – Underground
Ring main switches and earth switches typically have some form of spring
assistance in the operating mechanism to ensure the switch contacts move at the
rate required to achieve the nominated switching current ratings.
As the handle of the switch is operated, it charges a spring that takes over the
switching action. This release of stored energy quickly transfers the switch to the
selected position, giving a consistent operation every time.
On closing a fuse switch, a stored charge is first made to enable the fuse switch to
trip if the HRC fuse blows and operates the striker pin. To trip a fuse switch, the
switching operator is required to either press a button or move the handle in the
opposite direction.
Earth switches are spring-assisted on closing to ensure rapid earthing of the circuit
but in some cases are not assisted on opening.
Certain types of Schneider switches and breakers make use of a DC drive motor to
charge the closing spring. This feature is used when remote switching operations
are required on apparatus using a RTU via SCADA.
The design of some apparatus does however not include a standard feature to
isolate the DC supply to the spring charge motor. This is a problem when the
switch needs to be isolated for the issue of an EAP.
5-15
Switching Operator's Manual One
Remote control functionality of some ring main units via SCADA is achieved by
means of a T300 Remote Terminal Unit (RTU).
A single T300 Remote Control Unit is designed to allow remote operation (close,
open) of the switches it controls at a particular location.
To inhibit remote operation of the RTU and the associated switches it controls, a
selection to “local control” must be made on the unit. When the unit is selected to
“local control”, a LED is illuminated to indicate this.
The T300 remote terminal unit is housed in a weather proof lockable enclosure. To
prevent the T300 unit from being accessed and inadvertently selected to “remote
control” after being selected to “local control”, it must be locked.
5-16
Section Five – HV Distribution – Underground
Voltage indicators are provided on the ring main unit front panel to show the
electrical status of the associated cable. Earth switches must not be closed unless
the indicators on each phase show the cable is de-energised.
An example of voltage indicators is shown in Figure 5-11 below. The markings L1,
L2 and L3 represent the R, W and B phases respectively. The neon indicators
glow to show the presence of voltage on each phase of the cable
It is good switching practice to observe the three voltage indicators are operational
prior to de-energising a circuit. As an alternative method of proving de-energised,
three sockets are often provided near the indicators to allow the use of a voltmeter.
Some ring main units have removable voltage indicators. This facilitates proving
the indicators are working on live circuits before and after switching to de-energise
a cable.
SF6 ring main units require adequate gas pressure at the operating temperature to
achieve the rated switching current. An energised switch must not be operated
with low gas pressure. The switching operator must check the gas gauge to ensure
adequate pressure before operating a switch.
5-17
Switching Operator's Manual One
An example of a gas pressure gauge is shown in Figure 5-12. The gas pressure is
indicated by the black needle. As pressure varies with temperature, the gauge has
a number of concentric circles indicating temperature between the range of –25°C
to +40°C. The green and red areas are used to show adequate or low gas
pressure respectively.
One method of reading the gauge is to look if the needle crosses anywhere into
the red area. If so, the temperature of where the needle crosses from the green
into the red area is estimated using the concentric temperature circles. If the actual
switchgear temperature (usually ambient temperature) is above this temperature
read from the gauge then the gas pressure is low and switching is not to proceed.
For example, in Figure 5-12 the left-hand image shows the needle in the green
area over the entire temperature range; therefore the gas pressure is adequate.
The right-hand image shows the needle crossing into the red area at an estimate
5°C from the concentric circles. This is interpreted as the gas pressure is low if the
actual temperature of the switchgear (usually ambient temperature) is above 5°C
(that is, a temperature in the red area). Therefore if the actual temperature of the
switchgear at the time of switching is above 5°C this switchgear must not be
operated.
5-18
Section Five – HV Distribution – Underground
Withdrawable ring main units are not fitted with an integral earthing switch.
Earthing of the cable circuits must be done manually.
An example of a withdrawable ring main unit is the Brown Boveri unit (shown in
Figure 5-13). Proving de-energised and earthing is performed through the cable
access cover. The portable earths are applied with the insulated earthing handle.
Because of interlocking arrangements this earthing access cover can only be
opened when the switch/fuse switch is in the withdrawn position.
Cable access
cover
Withdrawable
fuse switch
3 x withdrawable
switches
Portable earth
insulated handle
Portable earth
leads
5-19
Switching Operator's Manual One
Fuse switches are used to supply distribution transformers. To change the fuses
in the fuse switch the following conditions are required:
• The fuse switch earth switch must be ON – this earths both side of the fuses
and enables access to remove covers and change the fuses.
• The fuse must be inserted with the fuse striker pin facing toward the trip bar.
5.2.4 HV Metering
Where customers require a sole use distribution substation (usually over 2 MVA),
HV metering can be installed instead of LV metering. This allows customers to run
HV supplies within their own installations and have different rates for power
consumption. Depending on the ring main switchgear type the metering may be
installed as part of the ring main unit or as a separate unit.
In this type of installation, the HV distribution system has one, two or three
incoming feeds entering a common busbar. From here, the power passes through
the HV metering tank, where current and voltage transformers measure power
consumption. The common busbar then feeds a series of customer owned switch
fuses or circuit breakers.
If this is not done, incorrect readings will result during the tests.
The principles of both overhead and ground mounted transformers are the same.
However, enclosed HV and LV cable boxes are normally fitted to ground mounted
transformers, in contrast with the open HV and LV bushings used on pole mounted
transformers.
5-20
Section Five – HV Distribution – Underground
The switch fuse replaces the drop out fuse. The ring main switch replaces the pole
top switch.
The most common method for supplying padmount transformers in the network is
via ring main switchgear with at least two ring main switches and a switch fuse
(see Figure 5-14). This method enables flexibility of feeder loads and continuity of
supply during minor outages.
5-21
Switching Operator's Manual One
Transformer
Main feeder Main feeder
cable cable
In this method, a remote transformer is supplied from a ring main substation (see
Figure 5-15).
There may be problems when the ring main unit has to be isolated. Both the
substation’s transformer and the remote transformer must be fed up on LV circuits
to avoid customer outage.
Ring main
substation
Satellite substation
remote location from
ring main substation Main feeder cables
5-22
Section Five – HV Distribution – Underground
Cable termination
a. Construction
Overhead
main feeder
Cable to
ground mounted
transformer
b. Circuit
Insulators
Drop out fuses
Feeder
conductors
Cable head
5-23
Switching Operator's Manual One
200 ECS
elbow cable seal
The last transformer in the HV feed is obviously not looped out, and must have its
vacant or unused bushing of each phase covered by a dead-end receptacle
insulated connector when energised. This is illustrated in Figure 5-19 below.
Dead end
plug
Dead end
receptacle
The Table 5-6 below should be used for piggy-backed transformers supplied with
drop out fuses (DOF). These fuse sizes are required to ensure non-operation of
DOFs for transformer energisation.
5-24
Section Five – HV Distribution – Underground
2 x 500kVA 40A
2 x 315kVA 25A
The system is based on servicing semi-rural residential lots using several 25kVA
single-phase padmount transformers, each servicing up to six customers. Each
transformer is internally fused to protect the system from internal transformer
faults.
5-25
Switching Operator's Manual One
A B
F1
* F2
F1
Typical substation
F1 F2 ring main board
F2
Overhead
Drop out line
fuse
To zone or regional
substation
transformer F2
Circuit breakers
to main feeders
F3
F3 F2 F2
Zone or regional Drop out fuse
substation C D Substation 7
distribution busbar
* *
*F1 Normally
Feeder 1
open point
Remote
Substation 5 transformer
F2 Feeder 2
F3 Feeder 3
Substation 6
In Figure 5-20 substation 1 is being fed via feeder F1, which also feeds through to
open point A at substation 2. Feeder F2 feeds substations 2, 3, and 7, and through
to the open points at ring main switches C and D at substation 5. Feeder F3 feeds
substation 5 and its remote transformer at substation 6. The diagram shows that it
is the open points on feeders that enable flexibility of supply and adjustment of
loads on distribution feeders.
Note: The particular types of ring main units are not shown in Figure 5-20. The
switching operator must have local knowledge of the type of ring main unit
and its characteristics when choosing open points and switching
arrangements.
5-26
Section Five – HV Distribution – Underground
• up-to-date plans
• local knowledge.
Standard procedures must be adopted for the safety of the switching operator and
work crews, as well as for the security of the system.
Ring main switching can be complicated and more technically demanding than
overhead switching because of the inherent layout and concealed nature
underground distribution networks. A switching operator is required to keep
continuous contact with HPCC.
• Ring main switchgear is operated at close quarters. The operator must use all
correct PPE. The second operator must stand outside the substation, holding
the door open while switching is being carried out.
• The operator must know how to operate the switch and its interlocks.
Interlocks on switch fuses are similar to ring main switches, but extra
precautions must be taken when changing fuses.
5-27
Switching Operator's Manual One
• Operations on ring main units are carried out without any visual confirmation
of the circuit route. Only the labels on switchgear and schematic plans are
available. The switching operator must be satisfied that they are operating the
correct switch.
Do not rely solely on the program. If the program is faulty, the careless
operator may follow the program blindly, thus operating incorrect items.
Figure 5-21 shows two feeders supplying four ring main units.
Feeder 2
Substation 1
Substation 2
A
Cable
to be
isolated
B
Substation 3
C * Substation 4
5-28
Section Five – HV Distribution – Underground
To isolate a cable within the ring main system, the switching operator must be sure
that work can be carried out with safety and system security. Loads must be within
acceptable limits.
The standard way of isolating a cable, and a brief description of what happens in
each operation, are given in the following procedure.
1. In Figure 5-21 when the normally open point C is closed, both feeders are
interconnected. (At this point the fault level will be at its highest.) If a fault on
either feeder occurs at this time, both feeders will trip.
2. Ring main switch B is opened and D–DNO tagged to create the first isolation
point which separates the interconnected feeders and transfers substation 3
from feeder F2 to feeder F1.
3. Ring main switch A can then be opened and D–DNO tagged to create the
second isolation point which de-energises the cable. This arrangement gives
a cable isolated at both ends whilst maintaining supply to all ring main units
and distribution transformers.
If access to the cable is required, earth switches at both ends of the cable must be
applied after proving de-energised.
Normally, restoration follows the reverse of the procedure above, although phasing
out or other testing may be necessary depending on the nature of the work
performed.
With reference to Figure 5-22, to access substation 3 ring main unit for
maintenance or replacement, all HV feeder cables and transformer cables
connected to this ring main unit must be isolated at their remote ends. The feeder
cables are isolated and earthed at the remote end ring main units. The transformer
cable is isolated on the transformer LV side.
5-29
Switching Operator's Manual One
Substation 3
Substation 2
* Substation 4
B D
Substation 6
Substation 1
Substation 7
*Substation 5
F1 F2 F3
*M HV
Normally open point
metered customer
5-30
Section Five – HV Distribution – Underground
To isolate distribution substation 3 ring main unit shown in Figure 5-22, the
following isolation points are required:
1. Start by interconnecting to transfer load then isolate the LV supply from the
transformer at substation 3.
2. Open and D–DNO tag the isolation point D at substation 4. (This breaks the
interconnection from F1 to F3 and moves the load of substation 4 and
substation 5 onto F3.)
3. Open and D–DNO tag the isolation point C at substation 6. (This de-
energises the cable between substation 6 and substation 3.)
4. Open and D–DNO tag the isolation point B at substation 2. (This de-
energises all incoming supplies to substation 3 including its distribution
transformer.)
5-31
Switching Operator's Manual One
6. The switching operator may then prove de-energise and earth each cable at
B, C and D.
7. At substation 3 the switching operator should open the closed ring main
switches (switches to substation 2 and substation 4), then prove de-
energised and close the earth switches on the three switches and the fuse
switch. (This indicates to the work crew that each possible incoming supply
to substation 3 is isolated and earthed.
It must be remembered that this action isolates, but does not earth, the
busbar of the ring main unit.
Shown below in Figure 5-23 is a typical ring main switchgear fault indicator which
is fitted on the switch circuits. The L1 (R), L2 (W) and L3 (B) phase flags will drop
to indicate the presence of fault current exceeding the operating current setting.
When pressed, the test button will drop the flags down and when pressed again
the flags will reset. The flags will automatically reset after the period indicated on
the automatic reset time setting (that is, two or four hours).
Operating
current
setting
Phase fault
indicator
Test button
Automatic reset
time setting
Fault indicators are installed on the front panel of most ring main unit switches.
These fault indicators have a current measuring device (current transformer)
around the termination bushing of each phase of the ring main switch cables.
Secondary wiring connects the current measuring devices to the front panel
indicator as shown above in Figure 5-23. Normal load current does not operate the
fault indicator, however when fault current flows the corresponding fault phase
indicator will operate.
To determine the fault location the switching operator visits the substations,
inspecting fault indicators to determine passage of the fault current. In the example
in Figure 5-23, all fault indicators up to and including ring main unit 4 have
operated and all fault indicators from ring main unit 5 to the end of the feeder have
5-32
Section Five – HV Distribution – Underground
not operated. This would indicate fault is located in the cable connected between
ring main units 4 and 5.
Feeder
OCB
1 2 3 4 5 6 7
Fault
indicator
Fault
Once fault switching or the fault indicators locate the faulted section, the exact
location of the damage must be identified. In most cases, fault location is obvious,
for example, digging or fencing along the cable route. If damage is not visible,
specialist personnel must be called to locate the exact location of the fault.
Fault switching refers to the isolation and feed up of distribution systems under
fault conditions. This may involve closing switches onto faulted sections of the
system.
Feeders with over 50% cable have their auto reclose relay
taken out of service, due to the risk of further damage to the
cable.
! The switching operator must never attempt a trial reclose if the
auto recloser facility of a feeder is already out of service.
Fault indicators are used to locate the faulted section of the cable. Once the
faulted section is isolated, healthy parts of the feeders can be fed up from other
sources.
Where fault indicators are not operating correctly, the switching operator is
confronted with a difficult situation. The fault must be located by fault switching on
a ring main switch or the feeder circuit breaker. To fault switch on a ring main
switch, the switching operator must first establish that the switchgear is fit for that
purpose.
Horizon Power has designed the network to ensure ring main unit switchgear
ratings exceed the expected fault level, however this assumes the switchgear is in
good working order and operates correctly. To minimise any risk, the switching
operator must conduct pre-operation switchgear visual checks and other available
5-33
Switching Operator's Manual One
checks (such as checking the SF6 gas pressure) or use the alternative method
described below.
Where the switching operator is concerned about closing a particular switch during
fault switching, an alternative method is described below:
1. HPCC open the feeder circuit breaker feeding up to the open point (the
feeder which is going to be used to feed up to the potentially faulted area).
2. The switching operator closes the suspect open point switch under the de-
energised condition.
3. HPCC reinstate the feeder circuit breaker. This means that the circuit
breaker is being used to close onto the fault rather than the suspect ring
main switch. This ensures maximum safety for the switching operator and
reduces possible damage to Horizon Power apparatus.
This procedure may have to be done a number of times along the feeder.
However, the number of operations onto faulted circuits should be kept to a
minimum as high fault currents can cause further damage along the feeder.
When fault switching, the switching operator must remember the following:
• Before performing each switching operation, consider the affect that step will
have on the network.
5.5 Ferroresonance
Ferroresonance may occur in three-phase underground distribution systems when
an unloaded delta/star distribution transformer becomes energised or de-energised
by single-phase switching. Ferroresonance is a problem only when the length of
cable exceeds the critical length for a given transformer.
5-34
Section Five – HV Distribution – Underground
Tests have shown that excessive phase to earth voltages, 3.3 times the normal
voltage, may be developed in distribution circuits conducive to ferroresonance.
Once developed, they have a steady value that persists for the duration of the
switching operation.
This sustained overvoltage will shorten the insulation life of distribution equipment,
by accelerating its deterioration. Surge diverters, reclosers and distribution
transformers all are prone to the effects of ferroresonance.
Table 5-7 and Table 5-8 show broad guidelines for areas where ferroresonance is
likely to be a problem, that is, where cable lengths longer than those specified are
used.
63 17 12 9 8 7
160 43 30 24 21 17
315 84 59 46 41 33
500 133 93 74 64 52
63 4 3 2 2 2
160 11 7 6 5 4
315 21 15 12 10 8
500 33 23 18 16 13
630 42 29 23 20 16
1000 67 46 37 32 26
63 2 – 1 – –
160 4 – 3 – –
5-35
Switching Operator's Manual One
315 8 – 7 – –
500 13 – 11 – –
630 16 – 13 – –
1000 26 – 21 – –
160 18 11 10 8
315 36 23 20 15
500 57 36 33 24
630 72 45 41 30
1000 114 72 65 47
Note: The low voltage side of the transformer should be disconnected before
switching the high voltage.
5-36
Section Five – HV Distribution – Underground
5.6 Traps
The switching of underground systems is complex, therefore a high level of
competency is required. The switching operator must be aware of likely traps with
the following tasks and equipment:
Interlocks are available on ring main units to stop a switching operator earthing a
unit before the switch is opened. However, it is possible to earth a cable which is
energised from the remote end.
To avoid this, the switching operator must make sure that the ring main switches at
both ends of the cable are isolated (off and D–DNO tagged) and the neon
indicators used to prove the circuit de-energised before the earth switch is closed.
A variety of interlocking systems are used in different ring main units, some having
more complex interlocks than others. The switching operator must know the
function of each type of interlock before conducting any operation.
The switching operator will find standard operational padlocks on ring main
switches and different earth padlocks on earth switches. Before operation, the
operator must verify the correct padlock is on the appropriate switch. If this is not
done, it is possible to think that they are operating a ring main switch when it is
actually an earth switch that is being operated.
5-37
Switching Operator's Manual One
Testing facilities on all Horizon Power ring main switchgear are provided to allow
access to and testing of cables. Specialised equipment must be used on some
switchgear to allow testing to be carried out.
The switching operator must keep a clear mental picture and understand how each
operation affects the total configuration of the circuits being switched.
5.6.5 Ferroresonance
As computer systems are used to write planned and fault switching programs it is
essential the computer single line schematic accurately reflects the actual system.
This requires all changes made to the system are accurately recorded and
incorporated into these schematics.
If the switching operator is faced with a situation where the switching program and
the physical system appear to be in conflict, no operations should be carried out
until the conflict is resolved.
The condition of the switchgear must also be checked before switching; this
includes checking SF6 gas pressure.
5-38
Section Five – HV Distribution – Underground
Where apparatus is not labelled to the required Horizon Power standard, the
switching operator must be satisfied that the label on the apparatus in question is
accurate and correct for the switching operation. If there are any doubts about the
labelling of apparatus, the switching program is to stop until clarification has been
made.
When performing multiple steps on a single ring main unit, only the padlock on the
switch or earth switch to be operated is to be unlocked. After the switching
operation is complete, the padlock must be replaced and locked before proceeding
to the next switching operation. This action ensures that access to only one switch
is possible at any time.
The switching operator must not identify the switch and earth switch by the type of
lock fitted. Always carefully inspect the front panel to identify the switch and earth
switch. It has been known for the locks to be reversed as a result of taking multiple
locks off and replacing them incorrectly.
Ring main unit voltage indicators must be proven to work before and after (where
possible) switching to prove a cable de-energised.
5-39
SECTION SIX
Substation
Distribution Feeders
Table of Contents
6. Substation Distribution Feeders ............................................................ 6-1
i
Switching Operator's Manual One
ii
Section Six – Substation Distribution Feeders
List of Figures
Figure 6-1 Outdoor single distribution bus ......................................................... 6-2
Figure 6-2 Outdoor single with transfer busbar .................................................. 6-4
Figure 6-3 Indoor single busbar configuration .................................................... 6-5
Figure 6-4 Minimum oil circuit breaker ............................................................... 6-8
Figure 6-5 Puffer-type SF6 circuit breaker .......................................................... 6-9
Figure 6-6 Indoor Yorkshire SF6 Circuit Breaker.............................................. 6-10
Figure 6-7 Vacuum circuit breaker interrupter .................................................. 6-10
Figure 6-8 Outdoor vacuum circuit breaker ...................................................... 6-11
Figure 6-9 Indoor switchboard with vacuum circuit breakers installed .............. 6-11
Figure 6-10 Indoor vacuum circuit breaker ....................................................... 6-12
Figure 6-11 Cross-sectional view of a typical indoor switchboard .................... 6-12
Figure 6-12 Circuit breaker mechanism box showing closing springs .............. 6-13
6-13 Typical positioning of DC Isolator on Control Panel. ................................ 6-15
6-14 Schneider RM6 ........................................................................................ 6-16
6-15 Schneider Flusarc. ................................................................................... 6-16
Figure 6-16 The typical SCADA system (simplified) ......................................... 6-18
Figure 6-17 Typical substation human machine interface ................................ 6-19
Figure 6-18 Outdoor feeder panel controls....................................................... 6-20
Figure 6-19 Indoor switchgear feeder control panel ......................................... 6-22
Figure 6-20 Typical outdoor circuit breaker mechanism box ............................ 6-22
Figure 6-21 Feeder circuit disconnector ........................................................... 6-24
Figure 6-22 Shutters inside circuit breaker cubicle ........................................... 6-26
Figure 6-23 Typical voltage indicator ............................................................... 6-26
Figure 6-24 415V AC local supply changeover boards .................................... 6-27
Figure 6-25 Typical substation transformer ...................................................... 6-28
Figure 6-26 Single line circuit ........................................................................... 6-30
Figure 6-27 Typical battery chargers and banks .............................................. 6-31
Figure 6-28 Typical substation battery paralleling panel................................... 6-33
Figure 6-29 Circuit showing the principle of automatic voltage regulation ........ 6-34
Figure 6-30 Substation transformer showing tap changer mechanism box ...... 6-35
Figure 6-31 Tap changer mechanism box showing controls ............................ 6-36
Figure 6-32 Automatic voltage regulator / tap change panel ............................ 6-37
Figure 6-33 Typical AVR relay ......................................................................... 6-38
Figure 6-34 Transformer interconnections ....................................................... 6-40
iii
Figure 6-35 Transformers with different tap settings ......................................... 6-41
Figure 6-36 Two ways of interconnecting transformers .................................... 6-45
iv
Section Six – Substation Distribution Feeders
List of Tables
Table 6-1 Circuit breaker control locations ....................................................... 6-17
Table 6-2 Implications of losing substation local supply ................................... 6-29
v
6. Substation Distribution
Feeders
6.1 Introduction
The zone substation transforms high voltage transmission power to lower voltages
for local distribution. Typically, the substation's high voltage input is either 66kV or
132kV, while the lower voltage output varies between 11kV and 33kV.
This section examines only those components associated with the operation of
distribution feeders. This includes outdoor and indoor busbar configurations, circuit
breakers, local and battery power supplies, alarm panels, voltage control
mechanisms and under frequency load shedding.
6-1
Switching Operator's Manual One
The single bus configuration is the simplest form of substation. Single bus outdoor
substations supply feeders from one common busbar (see Figure 6-1 below). One,
two or three transformers are used, depending upon the load and required level of
system security. The single busbar is broken into sections with busbar
disconnectors. This allows several transformers to feed different parts of the busbar
separately, or one transformer to feed the whole busbar.
Outdoor single
distribution busbar
Busbar
disconnector 5xx.4
Circuit
breaker 5xx.0
Circuit
disconnector 5xx.5
Each feeder circuit breaker has disconnectors on each side to provide a visual
break for isolation of circuit breakers and feeders. Some substations provide only
one disconnector on the busbar side of the circuit breaker.
6-2
Section Six – Substation Distribution Feeders
The single bus with transfer bus substation is most commonly used in rural areas.
The same principle as the single bus configuration applies. The only difference is
that a second busbar or transfer bus is added to the outgoing side of the feeder
circuits. The transfer bus is used to interconnect feeder circuits within the
substation, making it unnecessary to interconnect feeders on the distribution
overhead circuits.
The use of the transfer bus is clearly shown in Figure 6-2. Where WFD 506.8 and
WFD 508.8 are closed, and WFD 506.0 is opened, the Bailey feeder is effectively
transferred to the Hamilton Rd feeder via the transfer bus.
The breaker WFD 506.0 may be taken out of service with further isolation (open
WFD 506.5 and WFD 506.4). This does not require major interconnection of the
distribution system. The method is flexible, saves time and makes the operation
quite simple.
Note: Before attempting to transfer one feeder onto another, the switching
operator must determine the combined loads. Check that the circuit breaker setting
is capable of carrying the extra current.
6-3
Switching Operator's Manual One
single busbar
Indoor
Outdoor single busbar
with transfer busbar
Hamilt on
Road
Bayley
Transfer
busbar
Outdoor
busbar
main
6-4
Section Six – Substation Distribution Feeders
Earth Voltage
switches transformers T4 incomer
T5 incomer
In indoor single busbar configurations all circuit breakers are attached to one
busbar (see Figure 6-3). There may be bus section circuit breakers along the
busbar's length, to split the bus as required (see PCK 512.0 and PCK 517.0 in
Figure 6-3, top and bottom respectively). This differs from outdoor substations that
use disconnectors for this purpose.
If the bus section breakers are closed, all feeder circuit breakers can be fed from
the one transformer. If the load is too high for one transformer, the second
transformer can be turned 'on' and a bus section circuit breakers can be opened.
The load is then split between two or more transformers.
6-5
Switching Operator's Manual One
Earth switches
Earth switch are provided on the cable side of each circuit (e.g. PCK 503.7 in
Figure 6-3 top).
The earth switch closing is spring assisted to ensure rapid earth switch operation
regardless of the speed of operating handle movement.
All circuit breakers are designed to create an arc, control it and then destroy it at
the most convenient time. The current flowing through the arc depends upon the
voltage between its ends.
At the instant the contacts separate in a circuit breaker, the electrons (which make
up the current) attempt to flow through the very small gap of the contact. They
collide with the atoms of the insulation medium and cause the atoms to rapidly
break up as more electrons and energy are released. This raises the temperature
of the contact gap.
This process continues as the contacts open. As the length of the arc increases,
more and more energy is required to sustain it. When the arc lengthens and cools,
it will break quite easily.
In Horizon Power's 50Hz alternating current (AC) system, the current falls to zero at
every half cycle or every 10 milliseconds (ms). This means that, for a brief time,
there will be no electron movement to sustain the arc.
Immediately after zero, the voltage across the contacts attempts to re-establish the
current. If the conducting path of the arc is still present, the current will be re-
established. However, the current will not be re-established when:
6-6
Section Six – Substation Distribution Feeders
In the case of vacuum circuit breakers the contacts separate in a vacuum and
therefore absence of atoms in the vacuum assists in interrupting the arc as the
contact separate.
SF6 and vacuum circuit breakers are used in new substations, as it is cost effective
and provides an acceptable level of operation with reduced maintenance
requirements.
This type of oil circuit breaker is common in older substations. The circuit breaker
contacts are immersed in a small quantity of insulating oil.
The minimum oil circuit breaker is manufactured to cater for a wide variety of
voltages and breaking capacities this varies the amount of oil required.
A three-phase minimum oil circuit breaker consists of three identical units which are
operated by a common linkage from the single mechanism box. The cross section
of a typical minimum oil circuit breaker is shown in Figure 6-4 below.
The circuit breaker is made up of two sections mounted one above the other. The
upper section is the switching chamber, while the lower section houses some of the
mechanical linkages and insulation to the ground.
The operating cam drives the insulated operating rod and moving contact up to
close and down to open the moving contact and fixed contact.
On opening, the fixed and moving contacts rapidly separate drawing an arc inside
the arc extinguishing chamber which is filled with insulating oil. The action of the
arc extinguishing chamber is to divide the arc into several sections and force it into
cool oil. The result of rapidly lengthening, dividing and cooling the arc extinguishes
the arc.
Closing is a less onerous operation for a circuit breaker because the arc will only
strike at the point where the oil insulation breaks down. As the moving contact is
rapidly moving towards the fixed contact the arc length is continually shortened until
the contacts meet at which time the arcing stops.
6-7
Switching Operator's Manual One
Primary
connection
Oil level
glass gauge
Fixed
contact Moving
contact
Arc
extinguishing
chamber Primary
Moving connection
contact
rollers
Moving
contact
Insulated Operating
operating rod cam
Gas vents with filters are fitted to all circuit breakers to allow free passage of gas
and prevent oil from being thrown out during operations. They are constructed to
prevent moisture entering and contaminating the oil.
The level of oil is most important, as this affects the degree of turbulence caused by
the arc. The oil level glass gauges must be inspected regularly.
The switching operator must report all low oil levels, especially
if one phase is lower than the other two phases.
The SF6 circuit breaker is a modern type, which is used indoor and outdoor
substations. Shown below in Figure 6-5 is the puffer type circuit breaker in the
6-8
Section Six – Substation Distribution Feeders
closed position (top view A.) and during opening (bottom view B.). When the circuit
breaker is opening SF6 gas is forced through the separating contact to extinguish
the arc.
Arc
B.
SF6 gas
Moving cylinder
compressed
Its arc quenching function is similar to the minimum oil circuit breaker, but much
more efficient. SF6 gas (sulphur hexafluoride) has better insulating properties than
mineral oil and does not break down under arcing.
The gas is held inside the arc chamber under pressure. If a leak occurs, the switch
will lose part of its switching capabilities. For this reason, Horizon Power's SF6
breakers have a low gas alarm and lockout function built into their operation.
Figure 6-6 shows the indoor Yorkshire SF6 switchboard with a circuit breaker
picture inset. Gas pressure gauges are typically fitted to these circuit breakers.
Where possible, SF6 pressure gauges should be checked before carrying out
switching operations.
6-9
Switching Operator's Manual One
Feeder circuit
control panel
Gas pressure
gauge
Circuit breaker
inside cubicle
The vacuum circuit breaker is a modern type, which is commonly used in indoor
substation switchboards. Figure 6-7 below shows the circuit breaker interrupter in
the open position. When the circuit breaker is opening, the fixed and moving
contacts separate rapidly causing the arc to lengthen whilst passing through a
vacuum. Because the arc cannot sustain itself within the vacuum, it rapidly
extinguishes.
End flange
Enclosure
Metallic
End shield bellow
6-10
Section Six – Substation Distribution Feeders
Vacuum
interrupter
Feeder cable
Current
transformer
Mechanism
(mech) box
Feeder circuit
control panel
Feeder circuit
circuit breaker
inside cubicle
Feeder circuit
cable and earth
switch inside
cubicle
6-11
Switching Operator's Manual One
Explosion duct
for evacuation
of the gases produced
if an arc should occur
Control panel
Busbars
Rackable
circuit breaker Current
transformer
Front
of Earth switches
switchboard (operation arrowed)
Cables
Voltage
transformer
(if fitted)
6-12
Section Six – Substation Distribution Feeders
• The circuit breaker must close cleanly and quickly, with no hesitation at the
'contact touch'. (This means that the moving contacts are in the 'fully home'
position that firmly latches the circuit breaker closed).
• The holding toggles or latch must be released as the tripping (opening)
device operates, allowing the circuit breaker to open.
Correct opening and closing are most important, for example, when the circuit
breaker is being closed onto a fault where the fault current will be high. The moving
contacts must reach a position which provides ample pressure between the
contacts to prevent 'chatter' and possibly 'welding in'.
The mechanism must be trip-free at all times. It should not be possible for a circuit
breaker to be held closed against an opening operation. For example, when closing
a circuit breaker onto a fault, it will need to trip very quickly.
For distribution circuit breakers the common method of storing energy for opening
and closing the circuit breakers is springs.
Spring Method
There are single-spring and multi-spring closing mechanisms that are charged by
hand or an electric motor.
Manual spring
charging handle
in storage location
Spring charge
handle motor
Manual spring
charging mechanism
Closing springs
6-13
Switching Operator's Manual One
Single Spring
The fully charged closing springs store sufficient energy for one operation. Upon
closing, the spring discharges fully, in turn charging the tripping springs to allow a
trip function. This allows automatic reclose or manual reclose, despite loss of the
auxiliary supply. Spring charging by hand may be carried out if the electric motor
fails to charge the spring.
In most cases, the stored energy of the spring is released by a small electric
solenoid. Spring mechanisms are normally recharged automatically immediately
after a close function.
Multi Spring
When in operation, all spring operated mechanisms for distribution feeders have
pre-charged springs. These are designed to perform a trip-close-trip sequence,
when auxiliary power to the circuit breaker is lost. Although a breaker has no
auxiliary power to charge the spring after locking out, the breaker may be closed to
restore power to a feeder while the supply problem is investigated and rectified.
The circuit breaker also has a trip function in reserve, which is essential when a
circuit is in the faulted condition.
Sometimes, the breaker motor may charge the spring partially or not at all. When
this occurs, the spring must be charged by hand. A typical procedure follows:
1. remove and check the fuse feeding the circuit breaker motor, or switch the
motor 'off'
4. the spring is fully charged when the crank handle runs free or reaches a stop
and a click is heard
5. the motor fuse of the circuit breaker must then be replaced or its switch
turned 'on'
There are two major advantages of power operated spring close mechanisms:
• Once the closing operation has been initiated, it may be completed without
any further action by the operator. (This is because its power supply is
independent of the operator. It does not rely on manual force for its
operation).
• The trip-close-trip function allows back up of breaker operation after a trip.
6-14
Section Six – Substation Distribution Feeders
Certain types of Schneider circuit breakers and switches make use of a DC drive
motor to charge the closing spring. This feature is used when remote switching
operations are required using a RTU via SCADA.
The design of the RM6 and Flusarc apparatus does however not include a standard
feature to isolate the DC supply to the drive motor. This is a problem when the
breaker or switch needs to be isolated for the issue of an EAP.
The position of the DC isolator in the circuit not only isolates the drive motor, but
also effectively isolates the electrical supply for remote control functioning of the
apparatus.
6-15
Switching Operator's Manual One
6-16
Section Six – Substation Distribution Feeders
Circuit breakers may be controlled from several locations as indicated in Table 6-1
below. The table shows the location, mode, description, control system and
switching preference for each switching position.
Switching
Site Mode Description Control system
preference
If possible, all switching should be carried out in the remote location, SCADA
switching is the preferred location.
SCADA Control
The SCADA system provides remote monitoring and control facilities for a range of
apparatus in the network. In zone substations the controllable apparatus includes
circuit breakers and transformer tap changers.
This is the preferred operating location for all SCADA controllable apparatus.
Shown below in Figure 6-13 is a simplified SCADA system. The control room client
computers are connected to master station computer when then communicates to
the remote terminal units (RTUs) located at each substation. The RTUs are hard-
wired to the relay racks which can then control and obtain data from the associated
substation apparatus.
6-17
Switching Operator's Manual One
Various communication
systems
Remote terminal
unit
In Figure 6-13, the red arrows show the path of the control signals to the substation
apparatus. The blue arrows show the path of the data from the substation such as
voltage, current, transformer tap position, circuit breaker status ON/OFF and
equipment alarms. The orange arrows represent the hard wiring in the substation
between the RTU, relay panel and substation apparatus.
6-18
Section Six – Substation Distribution Feeders
The substation operations must still be performed via HPCC except where authority
has been given by HPCC for local operation. Switching operators must make
themselves familiar with the operation of the screen, where these have been
installed in their area.
6-19
Switching Operator's Manual One
Outdoor feeders circuit breakers may be operated remotely from the feeder control
panel.
Shown below in Figure 6-15 are the instruments that are most likely to be on a
feeder relay panel. They include TRIP-CLOSE control switch, ON-OFF indicators,
load current ammeter, sensitive earth fault control, auto-reclose control, protection
relay, control fuses and protection links.
Note: Interchangeable terms are used in descriptions, labels and circuit breaker
indicator and controls - 'Off/On', 'Open/Close' and 'Trip/Close'.
'Off', 'open' and 'trip' mean the circuit breaker contacts are open.
Circuit breaker
TRIP – CLOSE
control switch
Circuit breaker
Circuit breaker ON indicator
OFF indicator
Ammeter
Protection
relay
The following procedures should be observed for operating outdoor circuit breakers
from remote relay panels and operating indoor circuit breakers from their control
panel:
6-20
Section Six – Substation Distribution Feeders
• Before operating the circuit breaker, the feeder auto-reclose function (if fitted)
must be disabled (or placed in “manual”). (Where applicable the auto reclose
function must be re-enabled when the circuit breaker is return to service at
the end of switching.
Note: Some feeders have auto reclose permanently disabled because greater
than 50% of the feeder is cable.
• The circuit breaker control switch marked 'trip/close'. The switching operator
turns the knob to the left ('trip') or right ('close'), according to the operation
required. (When released, the switch always returns to a central position).
• Before and after operating the circuit breaker, the ammeter should be
checked. (This ensures that the required operation is complete. For example,
if the breaker is switched 'off', the load drop to zero is shown on the ammeter.
Switching operators should also check other ammeters in the substation that
may provide more information on changes of substation status such as
transfer or load to interconnected feeder).
• Circuit breaker indicator lamps are red and green, according to the state of
the breaker:
• red glowing = 'on' (OCB closed)
• green glowing - 'off' (OCB open).
• Controls (and indicators) are provided to disable and enable the sensitive
earth fault and auto-reclose functions.
• Protection relays, links and control fuses are also mounted on the feeder
panel. They provide isolation and protection for the secondary control circuits.
Note: The ON–OFF indicator lamps can fail at any time, and the associated
indication circuit relies on circuit breaker mechanism box auxiliary switches which
can occasionally lose correct adjustment.
The switching operator must not rely on the first look at the lamps, and check all
available indicators such as ammeters and mechanical indicators.
The circuit breaker mechanism mechanical indicators are the most reliable
indicators of the circuit breaker status and should be used by the switching operator
to confirm the circuit breaker status.
The indoor switchgear control panel shown below in Figure 6-16. This circuit
breaker is currently in the ‘off’ position as indicated by the green light glowing.
6-21
Switching Operator's Manual One
The local panel is intended for maintenance purposes and is not used in normal
switching.
To locally operate the breaker, the local /remote switch is to be set to local. This will
prevents operation from a remote position. There may also be mechanical ON and
OFF buttons or control switch; this interacts directly with the mechanical operating
mechanism. Electrical ON and OFF buttons or a control switch use the control
close/trip solenoids to activate the operating mechanism. (see Figure 6-17 below).
Local / remote
switch
Mechanical status
indicator
Mechanical ON and OFF Green O = OPEN (OFF)
buttons
I = CLOSE (ON)
O = OPEN (ON)
I = CLOSE (ON)
Spring charge
status indicator
Spring charge
hand crank socket
6-22
Section Six – Substation Distribution Feeders
The switching operator should use the circuit breaker mechanical indicator to
confirm the status is “off” prior to operating an outdoor circuit breakers associated
disconnector or racking an indoor breaker. The electrical lamp indicators that are
also available use the circuit breaker’s auxiliary switches and are not considered as
reliable at the mechanical indicators. An example of the mechanical status
indicators is shown in Figure 6-17 above. In some cases the mechanical status
indicator is located on the outdoor circuit breaker poles.
• isolation points
• bus section switches, and
• transfer busbar switches.
Disconnectors are air break switches and have limited current switching capability,
therefore they are not to be used to make or break load current because of the risk
of a flashover.
Disconnectors have a manual operating handle and therefore the speed of contact
movement is linked to the speed of the operating handle movement. To reduce the
risk of flashover during opening and closing operations the movement of the handle
must be brisk and continuous.
The pre and post checks conducted by the switching operator when operating a
disconnector are similar to the requirements for pole top switches.
In a switchyard the connection of the operating handle to the earth mat and the
connection to the main earth can be visually inspected by the switching operator
before operation, therefore the installation of a portable operator mat is not
required.
6-23
Switching Operator's Manual One
Feeder cable
Current
transformers
Disconnector
operating handle
• switchgear interlocks
• busbar and circuit shutters, and
• circuit voltage indicators.
Switchgear Interlocks
• the circuit breaker can only be racked out when the circuit breaker is OFF
• the circuit breaker can only be racked in when the circuit breaker is OFF and
cubicle door is closed and secured
6-24
Section Six – Substation Distribution Feeders
• the circuit breaker cubicle door can only be open when the circuit breaker is
racked out
• the earth switch cannot be closed unless the associated circuit breaker is
OFF and racked out
• the circuit breaker cannot be racked in if the earth switch is ON, and
• the cable cubicle door cannot be opened unless the earth switch is ON. The
means a VT (where fitted) cannot be racked out unless the earth switch is ON
• On some indoor switchboards with capacitor bank CB’s the umbilical cords
need to remain connected to maintain a supply for the Castell key or Sentry
key interlock system timer to operate.
Shown below in Figure 6-19 is the inside of the circuit breaker cubicle with the
busbar and circuit shutters. The busbar and circuit shutters move to cover the
busbar and circuit contacts as the circuit breaker is racked out.
When the circuit breaker is removed from the cubicle, inadvertent access to live
busbar and circuit contacts is prevented by locking and D–DNO tagging the busbar
and circuit shutters in the closed position.
In some cases it’s not always possible to lock and D DNO-tag the shutters to create
an isolation point, when this occurs the CB cubicle door needs to become the
isolation point with the cubicle door locked and D DNO-tag attached. E.g. if a CB
trolley is unavailable and more than one CB needs to be racked.
6-25
Switching Operator's Manual One
Shutter
covering
busbar contacts
Shutter
covering
circuit contacts
Shutter
mechanism locking
Each circuit is provided with voltage indicators which are connected on the circuit
(cable side of the circuit breaker). These indicators are to be used to confirm the
cable is de-energised before the earth switch is closed.
Test sockets
Voltage indicators
Test sockets are also provided so a multimeter can be used to confirm de-
energisation. After testing to verify the test sockets secondary wiring is internally
connected to correct phase the sockets can use used to phase out using a
voltmeter.
6-26
Section Six – Substation Distribution Feeders
For reliability, it is standard practice to have two incoming 415V AC supplies to the
main control panel which has automatic changeover relays. If the supply currently
supplying the substation fails, the change-over contactors swap the substation load
to the alternate healthy supply (see Figure 6-21).
415V 415V
incoming incoming
supply no.1 supply no.2
Changeover Changeover
contactor contactor
Changeover
415V control 415V
incoming fuses incoming
supply no.1 supply no.2
Changeover Changeover
contactor Changeover contactor
relay
Changeover
control
fuses
6-27
Switching Operator's Manual One
A range of sources is available to provide the 415V local supplies. These include:
The range of substation ancillary equipment using the 415V AC local supply and
the impact is dependent on a number of factors as indicated in Table 6-2 below.
6-28
Section Six – Substation Distribution Feeders
Relay room air conditioning Impact probably delayed to keep electronic apparatus (protection, SCADA,
etc.) within operating temperature range.
Hydraulic charge closing – loss of pressure will result in the circuit breaker
not being able to be closed.
Panel status indicator lamps Immediate impact where indicator lamps supply is derived from the 240VAC
supply.
(ON-OFF indicators)
Note: Spring charged and hydraulic operated switchgear have stored energy for a
trip-close-trip sequence, that is, the next close operation is stored within the
switchgear mechanism.
6-29
Switching Operator's Manual One
Battery Banks
Shown in Figure 6-23 below is the battery charging arrangement. The 415V AC
local supply provides the energy for the battery chargers to charge the battery
banks. The protection, alarm and SCADA systems are connected to the batteries
via DC distribution panels.
Because the protection, alarm, and SCADA systems are connected to the battery
banks they will continue to operate regards of the state of the 415V AC local
supplies.
The length of time the batteries can continue to supply their load without being
charged, depends upon the standing load and rating of the battery bank. Normally,
these banks are designed for a six- to eight-hour load without being charged.
Typically this enables most faults affecting battery charging to be investigated and
appropriate action taken before any battery voltage problems occur.
Different battery voltages are used for different purposes within a substation. The
voltages used may also differ with the age of a substation or the type of equipment
installed.
Newer substations are designed with more elaborate and secure protection
systems. Two 110V battery banks are used for the transmission system and
distribution system (in some case only one battery bank is used for distribution).
50V battery banks are used for alarm systems and SCADA apparatus. (see Figure
6-24.)
Microgrid substations and older substations typically use lower voltage battery
banks for most functions.
Because substation design has changed, switching operators now find different
combinations of battery banks in different substations. Field staff should familiarise
themselves with the types of battery systems used within their local area.
Note: Battery systems are the most important component within a substation. The
battery banks must be kept in good working order to ensure protection systems will
detect fault, and trip the associated circuit breakers under all conditions.
6-30
Section Six – Substation Distribution Feeders
Problems
The main problems experienced with battery systems are low DC voltage output,
battery earth faults, and loss of AC supply. Any of these problems may cause a
fleeting (intermittent) alarm.
This occurs for a number of reasons, mainly when the AC supply is removed
from the battery charger, or one or more battery cell fails.
Gases are produced and emitted from the chemical reaction within batteries.
If these gases dry and crystallise, leakage current from the battery may track
along the path formed.
If the batteries have been insulated from the earth system of the battery
bank, meters can be installed to measure the leakage current. When the
leakage reaches a certain level, an alarm is triggered.
6-31
Switching Operator's Manual One
• Loss of AC supply
Note: Do not leave a battery charger off for any length of time. If faults are
detected in any battery system, immediate steps must be taken to return the
system to full operation.
Testing
Most battery chargers have a built in test facility. This is usually a switch or push
button that is wired for two functions. When operated, it first removes the AC supply
to the charger and then places a load across the battery bank. This load normally is
a resistive element.
When the switch is put in the test position, the operator should check the voltage
across the battery bank. This can be done by inspecting the voltmeter on the front
of the charger or by placing a DC voltmeter across the battery bank. If the voltage
drops below the battery charger's rating, further investigation must be carried out.
Note: Test facilities on chargers must not be held 'on' for more than 15 seconds at
one time. If held on for longer periods, the load resistors may fail due to overload.
Because test switches remove the AC supply from the charger, an alarm may be
operated. Before any tests are carried out on battery systems, the HPCC should be
notified.
6-32
Section Six – Substation Distribution Feeders
110V DC Battery
parallelling switch
110V DC Battery 1 110V DC Battery 2
Voltmeter Voltmeter
Parallelling
instructions
In many cases the alarms presented to HPCC are grouped or general in description
and a switching operator or other maintenance or protection personnel are required
to attend the substation to determine the specific source of the alarm.
Also the feeder voltage drop is caused by the feeder load and the length which
affects the line resistance and reactance. For a heavy load current, the voltage
drop over the feeder is large. For example, a 22kV feeder may have a voltage of
only 21kV after it has travelled 5km from the substation.
6-33
Switching Operator's Manual One
The voltage control method used has a voltage transformer (VT) connected to the
secondary side of the transformer which supplies a proportional voltage (around
110V) to the Automatic Voltage Regulating (AVR) relay. The AVR measures this
voltage against a reference set point and if required will activate the tap changer
mechanism to raise or lower the tap position to adjust the secondary voltage.
Primary
132kV – 66 kV
Raise Lower
Automatic
Voltage
VT Regulating
22kV/110V Relay (AVR)
110V
Secondary
22kV
Usually, tapping takes place on the higher voltage winding because this is the low
current side compared to the higher current on the low voltage side of the
transformer.
6-34
Section Six – Substation Distribution Feeders
The off-load transformer must be disconnected from all sources of supply before
the tap change is made. The tap change is usually done by some operating device,
such as a wheel or handle which is external to the unit.
On-load tap changing transformer circuits are designed to be operated at full load
without interruption to the supply as the tap change occurs. To achieve this, a
special high speed change-over switch is used to move from one tap the next
without interrupting the flow of current.
Shown below in Figure 6-27 is a zone substation transformer with an on-load tap
changer built into the tank. The tap changer mechanism box contains a 415V three-
phase AC motor which can turn in either direction to tap up or down.
Overhead conductors
connected through
bushings to transformer
primary side
Tap changer
mechanism box
– has mechanical
tap position
indicator
This means that some form of compensation is necessary for variations in both the
substation voltage and line voltage.
6-35
Switching Operator's Manual One
Voltage regulating relays may be used in conjunction with line drop compensation,
to give automatic control for on-load tap changing transformers (and distribution
line regulators). Electric control of the tap changer is normally used, however
manual operation of the tap changing mechanisms is also possible, by using a
manually-controlled electric motor or hand-cranked lever. A tap changing
mechanism box with its main component parts is shown in Figure 6-28.
Crank handle
socket
Manual crank
Mechanical tap handle
position indicator
(blank pointer) with
maximum and minimum
tap position indicators (red)
Raise / Lower
switch
Local / Remote
switch
Note: When hand cranking, the switching operator must check the motor is
isolated. Before any operation is carried out, the operator must remove the fuses or
turn the motor switch 'off’.
• the master / slave / independent / lockout switch, for selecting the operating
mode of the tap changer
• the raise / lower switch, to manually adjust the tap position, and
• the automatic / manual mode switch is used to select the control from the
AVR relay or the manual raise / lower switches.
6-36
Section Six – Substation Distribution Feeders
Out Of Step
indicator
Auto / Manual
switch
The AVR relay compares the actual distribution system voltage against the
reference set point which has been stored in the relay. The relay also has a voltage
band setting which allows small changes in the actual voltage either side of the
reference setting without initiating a tap change.
When the voltage moves outside the band the relay starts a timer. If the voltage
remains outside the band for the timer setting (typically around 60 seconds) one or
more tap changes are initiated. This will return the voltage to within the band
around the reference set point. The purpose of the band setting and the timer
reduce unnecessary tap changer operations.
These relays also have line drop compensation and metering and event recording.
6-37
Switching Operator's Manual One
Line drop compensation settings representing the resistance and reactance of the
feeder line are applied to the AVR relay settings. This ensures the line voltage drop
with respect to current is correctly modelled.
For example, as the feeder line voltage drop increases with increasing load, the
LDC function will proportionally reduce the voltage seen by the AVR voltage
sensing circuit. This will cause the AVR to see low voltage, causing the tap changer
to tap up, boosting the substation voltage to compensate for the line voltage drop.
6-38
Section Six – Substation Distribution Feeders
The UFLS function is typically incorporated into the electronic feeder protection
relays. The relay settings specify the frequency at which the feeder trips. UFLS
occurs in stages such that additional feeders will trip as the frequency drops lower.
HPCC dispatches generation to cater for the expected load and, in unusual
circumstances where a shortage of generation will occur, feeders can be shed by
HPCC to maintain stable system operation. It is normal practice to rotate the
feeders which are off at regular intervals to minimise customer inconvenience
where the generation shortage continues for an expended time.
HPCC must be aware of the substation local supply arrangements to ensure the
local supply is not affected by the load shedding.
Following an UFLS event, HPCC will manage the feeder restoration to match the
available generation.
HPCC will manage the paralleling of zone substation transformers with the
switching operator carrying out any field switching activities which cannot be
performer remotely from HPCC, e.g. air break bus section switch. The following
material is provided as additional information and explanation.
6.10.1 Principles
Horizon Power transformers vary in size, tap selection and impedance. These
factors, together with feeder loads and capacitor banks, must be considered when
paralleling transformers. This is necessary in order to determine what current will
flow through the interconnecting switch.
6-39
Switching Operator's Manual One
HPCC will manage the paralleling of transformers including setting the taps,
however switching operators must be aware of the issues associated with the
paralleling of transformers.
When transformers are interconnected at a zone substation, the current flow will
change on each circuit, according to transformer impedance and secondary
voltage. When two transformers of equal impedance and voltage are paralleled,
their loads will balance (see Figure 6-31). Each transformer will feed half the total
load of the combined circuit. (The current flowing through the bus coupler is also
shown).
100A
a. Unbalanced b. Balanced
The previous principle holds only if both transformers have the same output
voltage. If the voltage is different, it is more difficult to calculate the load that each
transformer will supply. Circulating current will develop between the transformers
and increase with voltage difference. It also alters the current through the
interconnecting switch.
The circulating current's power factor is very different from the load current. This
means that operations on transformers with voltage differences must be limited.
6-40
Section Six – Substation Distribution Feeders
Figure 6-32 shows two transformers connected together with different tap settings
(voltage outputs).
Circulating
current
22kV 23kV
Tap 5 Tap 6
300A 400A
See Note
For 22kV zone substations, where transformers are one tap out of step,
approximately 50 amps circulating current flows between the transformers when
paralleled.
Therefore, if the transformer is three taps out of step, the circulating current will be
approximately 150 amps.
For 11kV zone substations, each tap difference results in approximately 100 amps,
when transformers are paralleled.
Case 1
Some zone substation transformers may have different tap change mechanisms or
different tap step ratios. (This may be due to different makes).
6-41
Switching Operator's Manual One
Case 2
Zone substations are normally designed to have two or three transformers of the
same size, for example, two 20/27 MVA or two 10/13 MVA units.
Where two transformers of different sizes are installed at the same substation,
transformer loads will not balance if they are paralleled. Depending upon feeder
loads, the imbalance may cause high currents to flow through the interconnecting
switch.
This imbalance may be calculated using the following mathematical formula. (MVA
and impedance values are indicated on each transformer's nameplate).
MVA1
Tx 1 impedance
Tx 1 load = Total load by
MVA1 MVA 2
+
Tx 1 impedance Tx 2 impedance
Example
Tx1 = 20MVA
Tx2 = 10MVA
Tx1 and Tx2 = 10% impedance
Substation Total Load (load between transformers being interconnected)
= 800 Amps
20
Tx load = 800 by 10 = 533.3 Amps
20 10
+
10 10
Therefore,
Note: If three transformers are in service, the given substation total load refers
only to the load of the two transformers being interconnected.
Case 3
6-42
Section Six – Substation Distribution Feeders
Example
Tx1 and Tx2 = 20 MVA
Tx1 = 8% impedance
Tx2 = 12% impedance
Total Substation Load = 800A
20
8
Tx 1 load = 800 A by = 480 A
20 20
+
8 12
Therefore,
Tx2 load = Total load – Tx1 load
= 800A – 480A
= 320 amps
This example shows the load expected on each transformer, given ideal conditions
of the same size and tap ratio for each transformer. However, this condition may
not occur as there may be out of step tap changers.
Note: Cases 1, 2 and 3 demonstrate that transformers may not evenly share load
when paralleled. This may cause higher than normal currents to pass through the
interconnecting switch.
Capacitor Banks
Where paralleling is being carried out on an outdoor 22kV air break bus section
switch, the switching operator may have to remove the capacitor from service
before commencing any switching operation. This is necessary only when the load
on the section of transformer bus (with the capacitor installed) is less than 8 MVA
(209 amps at 22kV).
This action must be carried out to make sure that the power factor of the bus
section load with the capacitor does not differ significantly from the other section.
6-43
Switching Operator's Manual One
The exception to this is when feeders which are 50% or more cable are being used
for interconnection. Tap changers at both substations must be put in manual.
Voltage checks should be made to determine whether both feeds have
approximately equal voltages.
If interconnection is carried out in areas more than two kilometres out on each
feeder, the previous principle still applies.
Shown in Figure 6-33 are two ways of interconnecting transformers at the same
substation:
6-44
Section Six – Substation Distribution Feeders
300A 300A
Bus coupler
1
Bus section switch
Because of the problems already identified, there are limitations on how a pole top
switch can be used within two kilometres of a substation. However, if the following
three circumstances apply, pole top switches may be used:
• Both zone substation transformers are put on 'manual' and set to equivalent
tap or voltage output. (Transformer nameplates should be checked if the
switching operator is unsure of voltage outputs. This ensures the same
voltage output when transformers are paralleled).
• Both zone substation transformers have approximately the same load.
• Any out-of-balance transformer load can be easily picked up on the
interconnecting feeders with no overloading occurring.
If the above circumstances do not apply, the bus coupler/bus section switch must
be used to interconnect and break interconnection during operations.
This means that any circulating current, or high out-of-balance current, will flow
through the busbar and not a feeder circuit. The following procedure should then be
adopted:
6-45
Switching Operator's Manual One
When manually setting taps, switching operators should remember that the
substation output voltage changes with changing tap position. It may be necessary
for the operator to reduce the taps on one transformer and increase the taps on the
other, to be able to parallel successfully. This action changes the voltage on the
outgoing feeders.
Note: When adjusting taps, switching operators should not change the tap setting
by more than two taps either way.
Circulating current occurs if the taps are not exactly equal. To limit this,
transformers should not be paralleled, if their final tap selection is more than two
taps out for 22kV or one tap for 11kV. This, together with the tap limit above, results
in the following overall guide.
Note: If transformers are six taps out of step for 22kV, or five taps out for 11kV,
the switching operator should not interconnect until alterations to the system are
completed.
Taps can be brought closer together by either altering the load on the transformers
(load movement) or by switching out capacitor banks. In most circumstances, it is
better to move the load.
• faults in a feeder
• recharging a spring assisted circuit breaker
• faulty operation of a circuit breaker.
If switching operators are concerned about any operations on feeder switchgear for
any reason (fear of flashover, etc.), the operation should not be attempted. The
feeder circuit breaker should be tripped and the switchgear should be operated in a
6-46
Section Six – Substation Distribution Feeders
de-energised condition. (Switchgear includes pole top switches, ring main units,
etc.).
Because most of Horizon Power switchgear is rated for fault switching (to
sectionalise and test for fault location), it should not normally be necessary to trip
feeders under these conditions.
If a transient fault is suspected, a trial reclose may be carried out. The procedure
for this is given in Section 4.5.2
Spring charged circuit breakers have a trip-close-trip function. If the circuit breaker
trips on fault, it still has close and trip functions in reserve before its springs need
recharging.
If the trip-close-trip function has been used, and no LV supply is available, the
operator must recharge the springs manually. Normally, a crank handle is inserted
into the appropriate socket and winding (in the direction indicated on the gear
wheel), until the handle runs free or the spring latches. The circuit breaker may
then be operated normally.
The switching operator should consult the Switchgear Instruction Manual (SIM) as
required if this hand charging is required.
Note: Spring charging can be carried out with the busbar or circuit energised.
After the springs are fully charged the circuit breaker can be operated normally
from a remote location.
If the breaker fails to operate, the following checklist may be used to solve the
problem.
6-47
Switching Operator's Manual One
1. If the breaker does not operate, check the auto reclose switch is on 'manual'.
2. Check whether the springs are charged within the breaker drive box. If
discharged, check the AC motor fuses. Manual charging may be needed.
3. If the operation still does not work, check the control supply fuses.
4. If the circuit breaker fires through (does not latch closed and trips) during the
close operation, check the relay panel for flags which have not been reset or
relays which may not reset themselves.
1. Complete all checks for the outdoor spring charged circuit breakers.
2. Check the interlocks on the circuit breakers, to make sure they are fully home
in the correct position.
3. Check that the breaker is racked up into the correct position and the auxiliary
contacts are connected .
6-48
Switching Operator's Manual One
The switching operator must check whether the cable circuit labels conform
to the drawings. Before proceeding with switching, the operator must know
exactly what is being interconnected or isolated.
Corroded connections
Fuses continuity
Interconnected LV circuits
Installing more than one set of fuses along the LV underground circuit
Shorting busbars
3-32
SECTION SEVEN
Distribution Protection
Table of Contents
7. Distribution Protection ............................................................................ 7-1
7.1 Introduction ........................................................................................ 7-1
7.2 Protection Zones ................................................................................ 7-1
7.3 Distribution System Protection Equipment .......................................... 7-2
7.3.1 Fuses ............................................................................................ 7-3
7.3.2 Current and Voltage Transformers ................................................ 7-5
7.3.3 Relays ........................................................................................... 7-7
7.3.4 Principles of Time/Current Protection .......................................... 7-17
7.3.5 Reclosers .................................................................................... 7-18
7.3.6 Sectionalisers .............................................................................. 7-20
7.3.7 Operation of the Recloser Sectionaliser Combination .................. 7-20
7.4 Protection of Typical Distribution Feeders ........................................ 7-20
7.4.1 Fault on Single-phase Fuse Protected Spur Line ........................ 7-21
7.4.2 Fault on Section of Main Feeder Past Recloser........................... 7-22
7.4.3 Fault on Single-phase Recloser Protected Spur .......................... 7-22
i
Switching Operator’s Manual One
List of Figures
Figure 7-1 Zones of protection ........................................................................... 7-2
Figure 7-2 Location of protection equipment in distribution system..................... 7-3
Figure 7-3 Minimum operating current ................................................................ 7-4
Figure 7-4 Location of current transformer in feeder ........................................... 7-5
Figure 7-5 Current transformer ........................................................................... 7-6
Figure 7-6 Voltage transformer ........................................................................... 7-6
Figure 7-7 Relay single line diagram .................................................................. 7-7
Figure 7-8 Operation circuit for protection relay .................................................. 7-7
Figure 7-9 Digital relay – with multiple elements................................................. 7-9
Figure 7-10 Inverse time/current curve ............................................................. 7-10
Figure 7-11 Distribution feeder protection ......................................................... 7-11
Figure 7-12 Out-of-balance earth fault tripping ................................................. 7-12
Figure 7-13 Example of parallelling feeders ..................................................... 7-13
Figure 7-14 SEL351 relay................................................................................. 7-14
Figure 7-15 SEL351 protection indication ......................................................... 7-16
Figure 7-16 Correct discrimination.................................................................... 7-17
Figure 7-17 Inverse time/current operating characteristic grading .................... 7-18
Figure 7-18 Typical overcurrent curves for a recloser ....................................... 7-19
Figure 7-19 Protection of typical distribution feeder .......................................... 7-21
Figure 7-20 Time/current characteristics of a circuit breaker ............................ 7-22
List of Tables
Table 7-1 Typical minimum tripping currents ...................................................... 7-9
Table 7-2 SEL351 LED indicator interpretation and reporting ........................... 7-15
ii
7. Distribution Protection
7.1 Introduction
This section describes the principles and operation of distribution feeder protection.
The phase conductors are insulated (normally done by insulators on poles) from
the ground and from each other. If the insulation fails, the power will not flow to the
load but will flow as an uncontrolled short circuit to earth or other phases. These
faults may cause damage to plant, interruption of power to customers and loss of
revenue.
Protection equipment is added to the system to limit the effects of these faults.
Various devices are designed to:
protect personnel
detect all faults quickly, so they can be disconnected from the system
Protection zones enable the protection equipment to disconnect only the faulted
zone. Any fault occurring within a zone will cause circuit breakers, reclosers or
fuses in that zone to operate and trip. When this happens, protection equipment in
other zones should not operate.
Zones of protection are shown in Figure 7-1. Earth fault protection for a zone
substation may extend through several zones.
7-1
Switching Operator’s Manual One
Busbar
protection
Feeder protection
Feeder circuit
Transformer
protection
Zone substation
Feeder spur
protection
Pole top
transformer
protection
Pole or pillar
fuse protection
(if fitted)
Meter fuse
Customer
protection
The protection devices for feeders detect the existence of a fault, generally by
measuring overcurrent. (Overcurrent is a higher-than-normal current which is above
a preset value). Each device's operating time is determined by its operating
characteristic and the amount of fault current.
7-2
Section Seven – Distribution Protection
Protection equipment for the distribution system includes current and voltage
transformers, circuit breakers, reclosers, sectionalisers, fuses and relays. Figure
7-2 shows the location of protection equipment in a distribution system.
415V Customer
main board
22kV
Substation
busbar
Current
Ring main
transformer
substation
Circuit Sectionaliser
breaker S
Recloser
DOF
Pole top
transformer
Open
Trip
O/C
timer
Counter Meter
O/C
O/C and 415V
E/F relay Trip fuse
and
and
E/F Trip close
relay relay
Customer
Counter Lock
out
7.3.1 Fuses
a fusible element
a suitable enclosure.
The fuse operating time decreases as the overload or fault current increases. This
is called the inverse time/current characteristic (see Figure 7-3).
7-3
Switching Operator’s Manual One
Time
T2
I1 I2 Current
For current I1, the operating time is very high. This value is usually called the
minimum operating current.
For current I2, the corresponding fuse operating time is T2. This is the time taken
for the fuse element to clear the fault. The larger the current flowing through the
fuse, the faster the fuse operates.
Horizon Power uses different types of fuses, the most common being HV drop-out,
HV HRC fuses and LV HRC fuses.
This is the most common type of fuse found in Horizon Power's high voltage
overhead distribution system.
Fault current will cause the fuse element to melt and the barrel assembly to swing
down.
HV high rupturing capacity (HRC) fuses are used in the fuse switch of ring main
switchgear for transformer protection.
It is a porcelain tube containing a fuse element. The tube is filled with silica powder
and sealed.
When the operating current causes the fuse element to blow and the silica powder
surrounding it to melt, a glass shield forms around the element. The striker pin is
7-4
Section Seven – Distribution Protection
released through the end cap. This is designed to trip the three-phase switch in the
fuse switch.
This fuse is also silica powder-filled but does not have a striker pin. Usually, its fuse
element is made from pure silver wire or strip.
HRC fuses are designed to operate very quickly and under extreme short circuit
conditions.
Horizon power’s high voltage system voltages range from 11kV to 220kV. Currents
extend up into hundreds of amps under normal conditions and thousands of amps
under fault conditions.
It is not possible to connect the small, delicate relays into these high voltage/high
current circuits. The currents and voltages must be reduced to manageable levels
before connection is possible. Current transformers reduce current. Voltage
transformers reduce voltage to acceptable levels.
Current transformers are inserted in series with the circuit. They develop a
secondary current that is a small fraction of the line current. (Under normal
conditions this secondary current is a few amps, but under fault conditions it will be
much higher – up to 100A).
The location current transformers on outdoor feeders is shown in Figure 7-4 and
the CT primary and secondary circuits in Figure 7-5.
Current Circuit
transformer breaker Disconnector
Busbar
Feeder
cable
CT secondary
wiring
7-5
Switching Operator’s Manual One
Voltage transformers are connected between phases or from phase to earth. They
reduce the phase to phase voltage to 110V (phase to earth 63.5V) .
Primary 22kV
circuit
Current
transformer
Secondary
circuit wiring
Primary circuit
connections
Voltage
transformer
Secondary
circuit wiring
Fig 7-4 –– VT
7-6
Section Seven – Distribution Protection
7.3.3 Relays
The relay operates contacts when the input reaches a preset level or condition. The
circuit breaker is then directly tripped by the output contact or may be indirectly
tripped via the trip relay.
The electrical power required to trip the circuit breaker (or operate trip relays) and
alarms is supplied by a substation battery system.
Input Output
Battery
Voltage or current
being monitored
Alarm or
trip circuit
Coil Output
contact
Figure 7-8 shows how the relay output contacts are wired to the circuit breaker trip
coil. Relay output contacts can also be used to activate alarms.
Substation
Circuit Current
breaker transformer
Feeder
Trip
coil
Overcurrent
relay
Battey
Trip circuit
7-7
Switching Operator’s Manual One
the time-delay overcurrent element starts to operate with currents above the
level of the relay setting. The time delay has an inverse relationship with the
current magnitude (called inverse time relationship), this means the higher
the current the shorter the tripping time.
the instantaneous (hiset) element operates without any introduced delay to
trip the circuit breaker when the current reached the level of the relay setting.
This is used to rapidly clear high current faults very close to the substation.
Overcurrent protection is used on each feeder phase and must be set above the
normal feeder load to avoid tripping under full load conditions. Typical setting are
shown in Table 7-1.
The sensitive earth fault (SEF) is designed to detect low earth fault currents which
are not detected by the standard earth fault protection (e.g. HV conductors falling
across a dry bitumen road). The SEF has a very low current setting of several
amps and therefore is very sensitive to earth fault current, however it has a long
time delay of several seconds to allow the normal overcurrent and earth fault
operation for normal faults.
When the overcurrent or earth fault elements in a digital relay operate, a visual
indication is provided on the face of the relay, using LEDs or text on a display. The
relay shown in Figure 7-9 has LED indicators showing the instantaneous, phase
overcurrent, earth fault (GND/NEUTRAL OVERCURRENT) as well LEDs for other
elements.
The older electro-mechanical relays have numbered flags drop to indicate relay
operation.
7-8
Section Seven – Distribution Protection
Indicator
LEDs
Sensitive
Overcurrent Earth Fault Earth Fault
Amps (A) Amps (A) Amps (A)
Town Feeders
Rural Feeders
Note: Town feeders are generally fitted with sensitive earth fault relays to trip the
feeder for low current faults, such as a conductor on the ground.
These relays cannot be fitted to rural feeders because the single-phase spurs
unbalance the line.
7-9
Switching Operator’s Manual One
Figure 7-10 shows the curve for the inverse relationship between operating time
and current for a typical overcurrent relay element. The relay overcurrent element
settings allow the curve to be moved in both the horizontal direction (changing the
current) and the vertical direction (changing the time).
The minimum pick up current shown in Figure 7-10 is the current below which the
relay element will not operate. A temporary overcurrent may go above the minimum
pick-up level and then return to levels below the pickup level for durations less than
the tripping time shown on the curve without the tripping the circuit breaker. If
however, the temporary overcurrent time duration reaches the tripping time the
circuit breaker will trip.
In summary, the inverse curve shows the higher the fault current the shorter the
tripping time.
Time setting
Time adjustment
(seconds)
Current setting
adjustment
3
1 Time setting 2
Time setting 1
0 1 2 3
Pick-up Current (amperes)
current
Overload Fault
region region
Figure 7-11 shows typical distribution feeder overcurrent and earth fault protection
at a substation. The operation of the protection for an overcurrent (F1) and earth
fault (F2) is shown.
7-10
Section Seven – Distribution Protection
Substation
busbar
(three phases shown)
R W B
Circuit Current
breakers transformers Distribution feeder
F1
F1 F1 F1
F1
F1
SEF Direction of
F1 fault current
E A B C F1
A
Overcurrent
Overcurrent fault (F1) B relays
C
Substation E Earth fault
busbar relay
(three phases shown) SEF Sensitive earth
fault relay
R W B
Circuit Current
breakers transformers Distribution feeder
F2
SEF F2 F2
E F2 A B C Direction of
F2
fault current
In Figure 7-11 (bottom), the phase-to-earth fault F2 (red phase) primary fault
current flows through the R CTs which produces equivalent fault level secondary
current to flow in elements A, E and SEF. In this case the E element will have the
shortest operating time tripping the circuit breaker. Notice the R phase current flows
back to the substation through the ground and not on the other phases creating an
out-of-balance on the phase conductors.
If the earth fault F2 was a low level fault and the current too low to be detected by
the E or A after of several seconds the SEF element will operate tripping the feeder
circuit breaker.
7-11
Switching Operator’s Manual One
As stated before, earth fault protection is sensitive and detects an out balance on
the phase conductors. When two feeders are parallelled on single-phase
disconnectors, there is a significant risk of out-of-balance being detected and
operating the earth fault protection.
To eliminate this tripping risk, the earth fault protection must be disable before the
feeders are interconnected and returned to service after the feeders are separated.
Interconnection of three-phase feeders should be performed on three-phase
switchgear (e.g. pole top switch) wherever possible to avoid the necessity of
disabling earth fault protection.
Figure 7-12 shows the first phase of a set of single-phase disconnectors closing on
a feeder near a substation. This creates an out-of-balance load on the feeder.
The secondary current flows through both the overcurrent and the earth fault relay.
As the earth fault relay is set to be more sensitive, it will often operate under these
conditions. This differs from balanced loads, where the three phases cancel each
other out at the earth fault relay and prevent the relay from operating.
Substation
busbar
(three phases shown)
R W B
Circuit Current Distribution feeder
breakers transformers
I I load
Interconnection
point
E I A B C I
A
Overcurrent
B relays
E Earth fault
relay
Trip relay
It can be seen that different relays pick up and operate for different types of faults.
To prevent too many relays firing into the trip coil of the protected circuit breaker, a
trip relay is used. This collects all relay operations and gives one signal to the
breaker.
7-12
Section Seven – Distribution Protection
The relay works immediately. As soon as one input gives an operation signal, the
output is closed. This is necessary, for the timing of the complete operation from
fault to tripping should be determined by the protection relay characteristics, not
those of the trip relay.
As described before, sensitive earth fault (SEF) relays are installed on overhead
distribution feeders to detect low current earth faults (high resistance faults) which
may do not produce enough fault current to operate the standard earth fault and
overcurrent relays.
Similar to standard earth fault protection, SEF detects the out-of-balance current in
the three-phase HV system That is, at all instants in time the current flowing out on
a phase must be balanced by currents returning on the other two phases. Where
current flows out on a phase but does not return on the other phases of that feeder,
this indicates an out-of-balance current and is seen by the protection as an earth
fault.
Shown in Figure 7-13 is a basic example with two HV feeders and their respective
loads before and after switching a pole top switch to parallel the feeders.
Slight differences
in the Red phases impedances
Before switching does not cause any problems.
R = 100A R = 200A
W = 100A W = 200A
Feeder 1 Feeder 2
B = 100A B = 200A
SEF = 0A SEF = 0A
FEEDERS HEALTHY
R = 160A R = 140A
W = 150A W = 150A
Feeder 1 Feeder 2
B = 150A B = 150A
SEF = 10A TRIP SEF = 10A TRIP
Assume the SEF settings are an operating current of 8A with a delay of 9 seconds.
7-13
Switching Operator’s Manual One
Before the Feeders 1 and 2 are parallelled it can be seen the out-of-balance in the
SEF on both feeders is zero. After the feeders are parallelled, a slight imbalance in
the R phase line impedances causes Feeder 1 R current to increase by 10 amps
with respect to the W and B phases, and conversely the R phase current on Feeder
2 is reduced by 10 A with respect to W and B. The SEF relay element on both
Feeder 1 and 2 see the 10A out-of-balance. If the SEF setting are 8A then after the
time delay of 9 seconds one or both feeders will trip on SEF.
The above is also applicable to reclosers with SEF protection. The basic rule is all
SEF protection devices inside a feeder loop created by switching must be disabled.
Substations with outdoor feeders usually have protection relays with the auto
reclosing function enabled to improve system performance for transient faults.
If the feeder is cable for more than half its length, auto reclosing is not used. (The
auto reclose function is either not installed or it is taken out of service). Cable faults
are usually permanent, and reclosing of the feeder will not restore the feeder but
further adds to any fault damage.
Indicator
LEDs
7-14
Section Seven – Distribution Protection
The LEDs illuminated on the front panel provides detail of the relay elements which
operated. This information which consists of a combination of LEDs illuminated can
be equated to the flag numbering system shown in Table 7-2.
The LEDs marked EN, INST, COM, SOTF, RS, CY, and LO do not impact on the
flag number and can be ignored.
7-15
Switching Operator’s Manual One
Example 4 – UFLS
7-16
Section Seven – Distribution Protection
It is most important that all flags are accurately recorded before the relays are
reset. Do not reset the relays and then record the flags from memory.
The flag operation information may be checked at a later date to establish whether
the protection has operated according to its design specifications.)
Figure 7-16 shows circuit breaker A and recloser B and fault at location F1. Fault
F1 causes the fault current to flow through the circuit breaker A and recloser B. If
recloser B can be made to open before circuit breaker A, the fault would be de-
energised and circuit breaker A would remain closed.
The operation of the closest protective device to the fault operating first is called
correct discrimination. The customers from the circuit breaker A to the recloser B
remain energised and the customers in the faulted section downstream from
recloser B lose the supply.
Substation
busbar
Distribution
feeder
Circuit Recloser B
breaker A
F1
The circuit breaker A and recloser B have their individual protection relays. The
setting on these relays are shown in Figure 7-17 as the time/current curves relay A
and relay B.
The fault current is shown by the vertical dotted line. Relay B operates in time T1
for the value of fault current shown. If the fault current is not cleared, relay A would
operate in time T2. Usually, a margin of 0.3 seconds is allowed, to give the recloser
B time to operate and clear the fault. If the margin is too short, the fault current may
not cease before relay A operates and trips the entire feeder.
7-17
Switching Operator’s Manual One
10
Relay A
Time
(seconds)
Relay B
1
t2
Margin
0.3 secs
t1
0.1
Fault current F1
Current (amperes)
7.3.5 Reclosers
The recloser is a self-contained device that senses and interrupts distribution fault
currents. If the fault is temporary, it automatically reclose will be successful. If the
fault is permanent, the recloser locks out after two, three or four preset trip
operations (dependent on the setting applied). If the fault clears before lockout, the
recloser after a period of time will reset the count for another full cycle of reclose
operations.
The time interval the recloser remains closed before tripping can be set selecting
the appropriate fast or slow curve. See Figure 7-18.
The basic principle of recloser operation is that fast operations will clear temporary
faults before spur line fuses can blow. (However, this is not always possible. The
small spur fuses may operate to clear the fault before the recloser operates.)
Delayed openings allow time for fuses to clear so that a permanent fault can be
confined to smaller sections of the line. See Figure 7-18.
Figure 7-18 shows typical slow and fast time overcurrent curves for a recloser. The
options for slow close is ‘B’ and ‘C’ or ‘D’ and ‘E’.
7-18
Section Seven – Distribution Protection
For a recloser set to four shots the range of possible combinations is:
4 fast reclose attempts
3 fast and 1 slow reclose attempts
2 fast and 2 slow reclose attempts
1 fast and 3 slow reclose attempts
4 slow reclose attempts.
The typical sequence is 2 fast and 2 slow reclose attempts.
60 3600
50 3000
40 2400
30 1800
20 1200
10 600
8 480
6 360
5 300
4 240
3 180
2 120
0.3 18
0.2 12
0.1 C 6.0
0.08 B 4.8
E
0.06 3.6
D
0.05 A 3.0
0.04 2.4
0.03 1.8
0.02 1.2
0.01 0.6
50
60
80
100
200
300
400
500
600
800
2000
3000
1000
4000
5000
6000
8000
10000
20000
30000
40000
50000
7-19
Switching Operator’s Manual One
7.3.6 Sectionalisers
A description of the operation of a recloser set for three shots and sectionaliser set
for two shots is given below.
When a fault occurs, the recloser opens the circuit. Simultaneously, both the
recloser and the sectionaliser register one fault. The recloser then closes and
restores supply. If the fault has cleared, the recloser and sectionaliser reset
automatically after a period of time reset the counts to zero. However, if the fault
still persists, the recloser trips again the recloser and sectionaliser increment their
counter to two.
At this point, a sectionaliser set to two shots automatically opens disconnecting the
faulted section of line. The recloser then closes a third time, restoring supply up to
the sectionaliser but not beyond.
The recloser shot setting must always be one or more greater than the sectionaliser
shot setting to ensure the recloser will reclose after the sectionaliser has opened
disconnecting the fault.
Each feeder has a main circuit breaker at the substation. The feeder circuit breaker
protects main feeder backbone up to the next downstream protective devices. A
fault in this backbone section will result in the entire loss of the feeder and all
customers.
7-20
Section Seven – Distribution Protection
Substation busbar
Circuit
breaker
Fault current
Recloser R1
(3-phase)
Sectionaliser
Recloser R1 S
Single phase
S
Sectionaliser
F2
F3
F1
In Figure 7-19 fault F1 causes fault current to flow from the substation, through the
feeder circuit breaker, the three-phase recloser R1 and fuse A, to the fault.
Fuse A must detect the fault and operate in a time that limits the faults damage to
the feeder. The recloser and feeder circuit breaker's protection also “see” the fault.
However, what is finally required is the operation of fuse A only.
Figure 7-20 shows the time/current characteristics of the circuit breaker, recloser
and fuse. At fault current F1, the lower fast trip curve of the recloser is below the
fuse curve. Therefore, the recloser will perform a fast trip and reclose. If the fault is
temporary, then the system may be fully restored without fuse A even operating.
7-21
Switching Operator’s Manual One
For a permanent fault, the recloser trips and closes again until the delayed trip
allows enough fault current to operate fuse A. The recloser then closes and
restores the rest of the line.
If however, the recloser fast curve is located above the curve A then fuse A will
operate before the recloser, even for a temporary fault.
Fuse at A
Time
Slow curve
Recloser
R1
Fast curve
Fault Current
F1
For temporary fault F3 in Figure 7-19, the single-phase recloser R2 trips and closes
successfully. For a permanent fault the single-phase recloser trips and closes up to
four times. The sectionaliser opens after the third trip of the recloser, if it is a three
shot sectionaliser. The recloser closes for the fourth time and stays closed, as fault
F3 is isolated beyond the sectionaliser.
7-22
SECTION EIGHT
Table of Contents
8. Switching For Safety ............................................................................... 8-1
i
Switching Operator's Manual One
ii
Section Eight – Switching For Safety
List of Figures
Figure 8-1 Distribution safe work area ............................................................. 8-13
Figure 8-2 Transmission safe work area .......................................................... 8-14
Figure 8-3 Transition from live to earthed network state for EAP ..................... 8-14
Figure 8-4 Flowchart of planning process ........................................................ 8-16
Figure 8-5 Distribution isolation and earthing ................................................... 8-17
Figure 8-6 Earthing of rural distribution system with spurs ............................... 8-18
Figure 8-7 Single-phase spur earthing ............................................................. 8-19
Figure 8-8 Distribution system earthing ............................................................ 8-20
Figure 8-9 Distribution system earthing ............................................................ 8-21
Figure 8-10 Example of safe work area ........................................................... 8-22
Figure 8-11 Electrical Access Permit – Front ................................................... 8-25
Figure 8-12 Electrical Access Permit – Back.................................................... 8-26
Figure 8-13 Sanction To Test – Front .............................................................. 8-28
Figure 8-14 Sanction To Test – Back ............................................................... 8-29
Figure 8-15 Vicinity Authority ........................................................................... 8-31
Figure 8-16 Operating Agreement ................................................................... 8-33
Figure 8-17 Handover Certificate ..................................................................... 8-34
Figure 8-18 Danger–Do Not Operate tag ......................................................... 8-35
Figure 8-19 Caution–Vicinity Work in Progress warning tag ............................. 8-36
Figure 8-20 Danger–Restricted Use tag ........................................................... 8-37
Figure 8-21 Warning–Out of Service tag .......................................................... 8-37
Figure 8-22 Isolation locks used to isolate apparatus ....................................... 8-38
Figure 8-23 Touch potential ............................................................................. 8-43
Figure 8-24 Step potential................................................................................ 8-44
Figure 8-25 Indoor switchboard arc flash and arc blast .................................... 8-45
iii
Switching Operator's Manual One
List of Tables
Table 8-1 Western Australian and Horizon Power authorities ............................. 8-3
Table 8-2 Apparatus electrical state ................................................................... 8-7
Table 8-3 Switchgear isolation requirements ...................................................... 8-9
Table 8-4 Work stages and responsibilities ...................................................... 8-24
Table 8-5 Pre-switching visual checks .............................................................. 8-41
iv
8. Switching For Safety
8.1 Introduction
This section describes the safety requirements the switching operator must comply
with when undertaking switching, and providing access for others required to work
on the network.
The switching operator is required to comply with Horizon Power’s standards and
work practices and must document and notify their supervisor if a procedure is not
followed. Notification is required to initiate procedure review and adjustments if
required.
Under these regulations, provisions exist for fines for non-compliance by Horizon
Power or the switching operator.
8-1
Switching Operator's Manual One
Horizon Power’s Electrical Safety Standards (ESS) provide the basic safety
principles applicable to employees and contractors working on or in the vicinity of
electrical apparatus controlled by Horizon Power.
prevent damage to Horizon Power assets and public and private property,
and
think SAFETY.
No employee should allow or request any personnel to perform any work that is
known to be unsafe or which may expose the person to a hazard.
8-2
Section Eight – Switching For Safety
Field Instructions
8.3 Authorities
Several Western Australian authorities are involved with safe switching procedures
in Horizon Power. The requirements of these authorities must be met when
switching. The table below summarises the role of each authority.
Authority Responsibility
WorkSafe WA Regulations to cover the occupational health, safety and welfare
in the workplace. This does not include electrical safety.
EnergySafety WA All aspects of electrical safety including investigation
of electrical incidents.
Horizon Power Control Controlling authority for all transmission and HV distribution switching
Centre (HPCC) on the Pilbara Grid and HV microgrids.
Construction or The group in control of electrical assets
commissioning authority before the authority is transferred to HPCC.
Regional depots The operating authority for the LV network within their area
of responsibility. The Works Delivery Coordinator
in these depots delegates responsibility for initiating programs
and all LV network switching to distribution workers.
Switching operators Conduct switching in accordance with procedures and instructions
8-3
Switching Operator's Manual One
Switching Operator
the flagging and barricading of safe working areas inside switchyards, and
8-4
Section Eight – Switching For Safety
Planned Switching
Planned switching is the usual switching mode for all work that is scheduled in
advance. In this mode a switching program is written and checked by switching
operators and approved by HPCC in advance of the switching occurring. The
program is executed under the control of HPCC.
Unplanned Switching
8-5
Switching Operator's Manual One
Example
An excavator damages a feeder cable between two RMUs. The feeder circuit
breaker has tripped and the faulted cable is required to be isolated to enable power
restoration.
Emergency Switching
It is preferred HPCC is notified prior to the action to remove the immediate threat
where possible. However, where this is not possible, HPCC is to be notified
immediately after the necessary action to remove the threat has been completed.
Where the emergency threat has been removed, further switching is to follow the
unplanned switching requirements.
Example
Overview
This section details the isolation and earthing requirements to create a safe work
area surrounding the work site on the electrical apparatus.
8-6
Section Eight – Switching For Safety
Fundamental Principles
The apparatus to be worked on is called the work site. Depending on the nature of
the work, the work site could be a single point or a wide area covering the
outermost points of the network where work will be performed.
Earths must be installed between the work site and all sources of HV electrical
supply into the work site. These earths are called program earths. The area of the
network inside the program earths is called the safe work area.
For overhead networks, where any program earth is not visible from the work site, a
working earth which is visible from the work site must be added by the RIC
between the work site and that program earth. The work site is limited to the area
inside the visible earths.
The principles outlined above are described in more detail in the sections which
follow
To understand the creation of isolation points and safe work areas it is necessary to
comprehend the different electrical states of switchgear.
Switchgear can have a number of unique electrical states as described in Table 8-2
below.
Electrical
State Description
OFF Switchgear has its primary contacts open which electrically separates
each side of the switchgear.
ISOLATED Switchgear is securely OFF and requiring a deliberate physical act
to turn back ON. This state is not available on all switchgear.
8-7
Switching Operator's Manual One
Each of the above electrical states have unique requirements, therefore terms such
as OFF and ISOLATED are not interchangeable. The switching operator must
understand the meaning of these terms and use the correct terms when describing
the electrical state of apparatus.
De-energised Area
Isolation Points
Isolation points are switchgear in the network which can provide a safe and secure
disconnection from an electrical source.
Some apparatus, whilst in the isolated state, may require further fitting of barriers or
other methods to prevent access to live parts.
The above requirements are general in nature and due to the large range of
switchgear types the actual implementation of these requirements will vary. Table
8-3 below describes the specific requirements for common types of switchgear to
be used as an isolation point. The switching operators must be able to correctly
create an isolation point for all switchgear they are required to switch .
8-8
Section Eight – Switching For Safety
Isolation requirements
PoA
Apparatus code Condition Locking requirements
Pole top switch PTSD Off and attach D DNO Isolation lock applied
HV three-phase ISOL Off and attach D DNO Isolation lock applied
disconnector
Approved load break LBS Off and attach D DNO See FI – NULEC RL
switch (SF6) Load Break Switch
as an isolation point
RMU switch / fuse SWDC / Off and attach D DNO Isolation lock applied
switch FSSW
Temporary
TEMP Off – and attach D DNO Cannot be locked
disconnector
8-9
Switching Operator's Manual One
reclosers
Work Site
Isolated Area
Earthing
limit the rise in potential difference in the work area and trigger the protection
equipment to disconnect the supply, if supply is inadvertently restored
Each earth will short circuit all three-phase conductors together and connect them
to ground. Earthing may be in the form of switchgear earth switches or portable
earths.
8-10
Section Eight – Switching For Safety
There are two types of earths, program earths and working earths and each has a
specific purpose.
Program earths are applied for the purpose of protecting against inadvertent
energisation into the work area through any isolation point. If an isolation point is
inadvertently energised, program earths will immediately cause the supply
protection device to operate, de-energising that supply. Program earths are applied
and removed as steps in the switching program by the switching operator. These
earths are required to be applied before the work permit is issued and removed
after the work permit is cancelled. The application and removal of program earths
must be noted on the EAP or STT. Depending on the location of program earths,
one program earth may cover more than one isolation point.
As switchgear earths are rated switchgear, where available they are preferred for
program earths over portable earths.
Working earths are additional earths fitted and removed within the safe work area
as required for the work being undertaken. The purpose of these earths is to:
provide visible earths at the work site where the program earths cannot be
seen
to manage induction
These earths are managed by the Recipient in Charge or Tester in Charge and are
fitted after the work permit is accepted and removed before the work permit is
relinquished. The application and removal of working earths must be noted on the
EAP or STT.
Portable Earths
For substations with overhead apparatus where portable earths are required the
earths must be connected to the main earth grid via the earth studs placed on the
structures at convenient intervals around the area.
8-11
Switching Operator's Manual One
All portable earth connections must be firmly attached to ensure good electrical
contact and also to ensure that the earth will remain effective if subjected to
inadvertent energisation.
Earth Switches
Indoor switchboard circuit breakers typically have built in earth switches associated
with each circuit breaker. Similarly ring main units have a built in earth switch
associated with each switch and fuse switch. Due to the large range of switchgear
types the actual operations required for applying earths will vary. The switching
operator is required to be able to correctly apply earthing on each type of
switchgear.
Ring main unit interlocks require the ring main switch/fuse switch to be OFF
before the earth can be applied. Similarly, the ring main switch/fuse switch
cannot be turned ON if the earth switch is ON.
The earth switch on each circuit is connected on the cable side of the circuit
breaker or ring main switch or fuse switch.
An earth switch when used as a program earth must be ON, locked and a Danger–
Do Not Operate tag attached.
Because earth switches are rated switchgear they are normally applied before
portable earths.
8-12
Section Eight – Switching For Safety
A safe work area is the area within the isolated area and inside the program earths.
Therefore a safe work area has two electrical safety measures employed. The first
safety measure is all sources of electrical supply into the work area have been
securely disconnected at the isolation points and the second safety measure is the
program earths are applied to ensure the work area cannot be inadvertently
energised through the isolation points. The safe work area is commonly referred to
as being ‘boxed in’ by isolation points and program earths.
Figure 8-1 shows part of the distribution network, where a section of HV overhead
line connects to an underground cable at the cable termination pole. The work site
is cable termination pole. The two isolation points (IP1 and IP2) create the isolated
area and the earthing requires two program earths (Portable Earth PE1 and RMES
PE2) creating the safe work area. Inside the safe work area is the work location
(cable termination pole) and an EAP is issued for work on the cable termination.
Figure 8-3 shows a transmission line connecting two substations. The transmission
line is the work site. There are isolation points IP1 and IP2 at each end of the line
creating an isolated area. The earthing requires program earths PE1 and PE2 at
each end of the line. This creates the safe work area as shown.
However, as the work party is required to work between visible earths, working
earths WE1 and WE2 (both portable earths) must be installed on each side of the
work site. If the work site progresses along the line, the working earths must be
moved by the work party, so they remain visible from the work site. If working near
one end of the line and program earth PE1 or PE2 is visible then only one working
earth will be required on the side of the worksite where the program earth is not
visible.
8-13
Switching Operator's Manual One
Figure 8-3 below shows the stages network apparatus progresses through from an
energised state to an isolated and then earthed state for the issue of an EAP. The
terms live, de-energised, isolated and earthed must be correctly used to describe
the specific state of the network.
Figure 8-3 Transition from live to earthed network state for EAP
8-14
Section Eight – Switching For Safety
In each case if a LV back-feed does occur, the transformer will step the LV voltage
up and become a HV source of supply onto the HV feeder. Each transformer must
be appropriately isolated on the LV side and earthed on the HV depending on the
transformer type and location relative to the work site.
Below is a set of rules to assist in planning the creation of a safe work area on a HV
feeder. The first part covers the HV feeder isolation and earthing rules and the
second part deals with the transformer isolation and earthing rules for the
transformers connected between the HV feeder isolation points.
1.1. All main feeder HV sources of supply into the work site must be isolated.
1.2. Program earth(s) must be fitted between step 1.1 isolation point(s) and
the work site AND as close as possible to the work site.
2. Rules for all transformers inside the isolated area defined by step 1:
2.2. for each transformer, there must be a program earth between the
transformer and the work site AND as close as possible to the work site.
2.3. Note: the placement of the program earths fitted in step 1.2 determines
the earthing needed for transformers in step 2.2.
The planning process for distribution feeder and associated transformer isolation
and earthing is shown in the flowchart below (Figure 8-4).
Note: Remember, when writing the switching program all HV feeder and
transformer isolations must be completed before the program earthing is
commenced.
8-15
Switching Operator's Manual One
4. Are
there any
transformers 5. No further isolation
between the No or earthing required.
isolation
points?
Yes
6. Isolate 7. Is it an
Yes
the LV side interconnectable
of the transformer. transformer?
No
8. No further
isolation needed –
May still need earthing!
10. Is there
Yes a program earth
9. No further
between each transformer
earthing required.
and the work site?
No
Yes
14. Return to Step 2 15. Is the work site Yes 16. Continue
to check each isolation inside the safe with permit to work
and earth point. No procedure.
work area?
To illustrate the application of isolation and earthing principles and rules to create
safe work areas on the distribution network consider Figure 8-5.
8-16
Section Eight – Switching For Safety
IP 3 IP 4
A PE 3
C
Work site
IP 1 IP 2
Safe work area
PE 1 PE 4 PE 2
B D
Figure 8-5 shows the work site on the main feeder which includes the HV
connections to transformer A and B. The two sources of feeder supply must be
isolated at IP1 and IP2. These sources of supply must have program earths PE1
and PE2 placed between these isolation points and the work site. Program earths
must be placed as close to the work site as practicable.
The safe work area is between the program earths and surrounds the work site.
The switching program can now be written, remembering all isolations must occur
before program earthing is commenced.
Example 1
Figure 8-6 shows a three-phase overhead network, the work site, a three-phase
transformer X, and a number of single-phase spurs each with multiple transformers.
8-17
Switching Operator's Manual One
Single-phase Single-phase
spur 1 spur 2
Three-phase
main line
Safe work area
IP 1 Work site IP 2
PE 1 PE 2
X
PE 3
Single-phase
spur 3
In Figure 8-6, the work site on the main feeder requires isolation points IP1 and
IP2. These sources of supply must have program earths PE1 and PE2 placed
between these isolation points and the work site. Program earths must be placed
as close to the work site as practicable.
The safe work area is between the program earths and surrounds the work site.
The switching program can now be written, remembering all isolations must occur
before program earthing is commenced.
8-18
Section Eight – Switching For Safety
Example 2
IP 1
Single-phase spur
PE 1
Work site
Safe work area
PE 2
The work site requires isolation from the feeder at isolation point IP1. This source of
supply must have program earth PE1 fitted between this isolation point and the
work site. Program earth must be placed as close to the work site as practicable.
The safe work area is between the program earths and surrounds the work site.
The switching program can now be written, remembering all isolations must occur
before program earthing is commenced.
8-19
Switching Operator's Manual One
Example 3
Figure 8-8 shows a diagram of the work site on a three-phase overhead network
with three transformers.
X Safe work
area
PE 1 PE 2
IP 1 IP 3
PE 3
Work
site
Y Z
IP 2
IP 4 IP 5
In Figure 8-8, the work site on the main feeder requires isolation points IP1, IP2
and IP3. These sources of supply must have program earths PE1 and PE2 placed
between the isolation points and the work site. Program earths must be placed as
close to the work site as practicable.
Each transformer between IP1, IP2 and IP3 must now be managed :
The safe work area is between the program earths and surrounds the work site.
The switching program can now be written, remembering all isolations must occur
before program earthing is commenced.
8-20
Section Eight – Switching For Safety
Example 4
Figure 8-9 shows an HV overhead feeder with a cable head pole and cable
connecting to a ring main switch. The work site is at the cable head pole and
requires isolation and earthing on all three sources of HV supply. There is one
isolation point IP1 on the ring main switch and two overhead isolation points IP2
and IP3. Program earth PE1 is the ring main earth switch and program earths PE2
and PE3 are applied to the overhead line on each side of the work site.
The safe work area is between the program earths and surrounds the work site.
The switching program can now be written, remembering all isolations must occur
before program earthing is commenced.
PE 2 PE 3
Work site
IP 2 IP 3
Safe
work
area
PE 1
IP 1
8-21
Switching Operator's Manual One
Refer to ESS for specific clearance zones and safe working distances.
Isolation Isolation
point Substation fence point
Safe
work
area
Access
to work site
8-22
Section Eight – Switching For Safety
The Network Permit to Work Training Manual describes the following topics relating
to work permits and procedures:
work permits
tags
locks
The switching operator is required to fully understand the Network Permit to Work
procedures.
Work Permits
Access on or near the network to carry out work requires the issue of a work
permit. Work permits provide a written record of the safety information transferred
between the switching operator and the work party.
Three work permits are provided to cover the range of access requirements and
types of work to be undertaken. The three work permits are:
8-23
Switching Operator's Manual One
All work permits progress through several stages involving the switching operator,
Recipient in Charge or Tester in Charge and the Recipients. The table below
provides a description of the activities, the responsible role and the name of the
work permit stage.
Responsible
Description Stage
role
An Electrical Access Permit (EAP) is a work permit required for work which involves
direct access to network apparatus.
The EAP document is shown in Figure 8-11 and Figure 8-12 below. The diagram
has annotations to show the stage and the responsible role for completing the
written details.
8-24
Section Eight – Switching For Safety
Details
completed
by
switching
operator
Issue
of
Details
work entered
permit by RIC
as working
earths are
applied and
removed
Details
completed
by
switching
operator
Details
Acceptance completed
by RIC
8-25
Switching Operator's Manual One
Transfer Details
completed
of permit by RICs
between changing
RICs responsibility
Managing Recipients
sign on before
Recipients starting work –
Sign on – sign off when
sign off finished their work
RIC checks
all conditions
Relinquish- are complete
ment by RIC then relinquishes
work permit
Cancellation
by switching
operator
8-26
Section Eight – Switching For Safety
Sanction To Test
This variable nature of the apparatus electrical state allows a wide range of test
types, and includes apparatus which is initially isolated and earthed or isolated and
not earthed, de-energised or in the energised state. Typically for distribution testing
(such as VLF testing) the initial state is isolated and earthed, this allows the
connection of test equipment. The earths are removed for the testing and then
reapplied for removal of test equipment. Transmission testing work involves a wider
range of test types and therefore STT may be required to be issued in one of the
several states described above.
Note: The STT is shown in Figure 8-13 and Figure 8-14 below.
The diagram has annotations to show the stage and the responsible role for
completing the written details.
An EAP and STT cannot be issued at the same time, on the same apparatus, due
to the conflicting requirements of the EAP to have a safe work area which is
isolated and earthed and the STT to apply test voltages to apparatus.
8-27
Switching Operator's Manual One
Details
Issue completed
of by
work switching
operator
permit
Accepted
Acceptance
by TIC
8-28
Section Eight – Switching For Safety
Transfer Details
of permit completed
between by TICs
changing
TICs
responsibility
Managing
Recipients
Recipients sign on before
Sign on – starting work –
sign off sign off when
finished their work
TIC checks
all conditions
Relinquish- are complete
ment by TIC then relinquishes
work permit
Cancellation
by switching
operator
8-29
Switching Operator's Manual One
Vicinity Authority
A Vicinity Authority (VA) is the work permit required to perform work near energised
electrical apparatus. The safe approach distance which must be maintained at all
times from the apparatus is specified in Field Instruction Safe Approach Distances.
Where the required safe approach distance cannot be maintained during the work,
the apparatus must have a safe work area created by being isolated and earthed
and an EAP issued.
An EAP and VA can be issued on the same apparatus at the same time, as the
EAP requires the apparatus to be isolated and earthed, whilst the VA requires the
same apparatus to be treated as alive and the required safe approach distance
maintained at all times.
8-30
Section Eight – Switching For Safety
Issue Details
of completed
by
work switching
permit operator
Accepted
Acceptance
by RIC
Managing Recipients
Recipients sign on before
starting work –
Sign on – sign off when
sign off finished their work
Relinquish-
ment by RIC
Cancellation
by switching
operator
8-31
Switching Operator's Manual One
Two additional documents which do not give authority to undertake any work on the
network are used to formalise agreements made between different authorities.
Operating Agreements
Handover Certificates
Operating Agreement
An OA is used when:
An OA is not a work permit, and does not authorise any work to be undertaken. The
appropriate work permit must be issued to allow work to take place. The conditions
stated on the work permit must reference the OA in place. An OA is issued by a
switching operator or Issuing Officer.
8-32
Section Eight – Switching For Safety
Details
of apparatus
Issue and conditions
of of Agreement
document
Acceptance
Relinquish-
ment by
authorised
person
Cancellation
by authorised
person
Handover Certificate
Handover Certificates are used where the responsibility for electrical apparatus is
transferred from one authority to another. An example of this is where network
apparatus is constructed and then transferred from the construction authority to the
Operating Authority, who subsequently energises and is responsible for the
apparatus operation. Any future access to this apparatus will require a work permit
provided by the Operating Authority.
8-33
Switching Operator's Manual One
It is a requirement all persons working in the construction phase sign the Handover
Certificate to acknowledge they will treat the apparatus as energised and will need
a work permit for future access to the apparatus.
Details of
apparatus
and conditions
Acknowledge-
ment by parties
of apparatus
and conditions
8-34
Section Eight – Switching For Safety
Note: The formal term used by Horizon Power is tag, however the term label is
interchangeable and often used.
Danger–Do Not Operate tags shall only be used in conjunction with switching
programs and electrical apparatus access requirements.
8-35
Switching Operator's Manual One
Danger–Restricted Use
The Danger–Restricted Use tag can be used with the STT permit. It is attached by
the switching operator to the apparatus in a prominent position and listed on the
STT permit. This apparatus may be operated in a restricted capacity by the RIC or
TIC under the work permit.
8-36
Section Eight – Switching For Safety
Warning–Out of Service
Where a Warning–Out of Service tag and Danger–Do Not Operate tag is attached
to the same electrical apparatus, the Warning–Out of Service tag shall be removed
before the Danger–Do Not Operate tag is removed. The Warning–Out of Service
tag shall not be removed until that apparatus is ready for service.
The only exception to this is under emergency switching conditions where the
appropriate authority permits the Danger–Do Not Operate tag to be removed while
the Warning–Out of Service tag is still attached.
8-37
Switching Operator's Manual One
the date tag is fitted and the telephone number of the person attaching the
tag.
Locks
Horizon Power uses a Lock Out Tag Out (LOTO) procedure which includes
tagging when isolating HV electrical apparatus. The lock out process includes
dedicated isolation locks incorporated with control and individual personal locks to
create a safe and secure working environment.
When isolating a part of the electrical network all network security locks are
replaced with isolation locks and the isolation lock keys are placed in a lockout
station. The lockout station is locked with a control lock and all members of the
work party fit their personal lock to the lockout station.
8-38
Section Eight – Switching For Safety
When the switching operator undertakes a single step task it is important the
actions are performed in a systematic and sequential manner to correctly achieve
the required outcome. The following sections elaborate on the actions and
sequence required to complete some of the common single step tasks.
Proving De-energised
2. Test instrument is used to prove each phase of the circuit under test is de-
energised.
This ensures the test is valid and must be performed at each location where earths
are to be applied.
Applying Earths
Portable Earths
1. Inspect the portable earth leads and connections to ensure they are in good
working order and appropriately rated.
2. Layout the portable earths on the ground at the location where the earths are
to be applied.
a. inside substations use the earth studs on the structures which are
connected the main earth grid
8-39
Switching Operator's Manual One
5. Remain clear of the earth leads and apply to each phase earth with a positive
action. Ensure the phase connections are firmly made and the clamps are
tight.
Earth Switches
2. Confirm the earth switch is in the ON state, lock and apply danger tag.
Phasing Out
The procedure for LV and HV phasing out has been described in Section 10.
Racking out and racking in of indoor switchgear requires a full understanding of the
operation of the interlocks. The typical range of interlocks and their features is
provided in Section 6.5 – Indoor Switchgear Safety Features – Switchgear
Interlocks.
Pre-switching Checks
The look, listen and smell checks which can be performed before a switching
operation is undertaken are given below.
8-40
Section Eight – Switching For Safety
LOOK
The switching operator should look and visually check the mechanical and
electrical condition of the switchgear which is to be operated. This is to confirm as
far as practically possible that the switchgear is fit for switching and is in the
expected electrical state. The actual switchgear type will determine which of the
visual checks listed in Table 8-5 can actually be performed.
Status indicators Check ON and OFF mechanical and Outdoor circuit breaker electrical
– mechanical electrical indicators confirm the indicator driven from the mech box
and electrical expected electrical state. auxiliary switches may show OFF
whilst mechanical indicator shows
ON due to a broken drive shaft.
Instrumentation Voltmeter and ammeter instruments Voltmeter and ammeter indications
show expected electrical state concur do not agree with status.
with the status indicators.
Insulation SF6 gas pressure checks. Switchgear leaking insulation
medium material depending on the amount
condition Oil level checks. may prevent the switchgear being
operated.
LISTEN
The switching operator should listen for the abnormal sound of arcing. It should be
noted that dependent on the humidity and level of insulator pollution, outdoor
transmission HV switchyards can have a low sound level which is not considered
abnormal.
8-41
Switching Operator's Manual One
SMELL
The switching operator should be aware if the smell of insulation burning or the
pungent smell of ozone is detected, it is an indication of abnormal electrical arcing
or tracking. Consideration must be given to de-energising the switchgear, pending
further investigation.
Post-switching Checks
After performing the required switching operation the switching operator should
undertake a subset of the look, listen and smell checks as described in the pre-
switching checks. In Table 8-5 the operating mechanism, insulators, contacts,
status indicators and instrumentation checks are applicable. Listening for arcing
after switching is also appropriate, however the smell check may not be effective
because it can take time for the smell to accumulate.
Electric Shock
Due to the proximity of live exposed apparatus the switching operator must always
be aware of the risk of electric shock and ensure that safe approach distances are
maintained. Details of safe approach distances is given in Field Instruction Safe
Approach Distances.
Switchgear Explosion
Touch Potential
When switchgear fails resulting in fault current flowing into the ground via the
earthing system, this will create a risk of touch potential to the switching operator.
This fault current and related touch potential risk will be removed when the
associated protective device operates.
8-42
Section Eight – Switching For Safety
Touch potential is the voltage difference between the switching device earthing and
the surrounding earth (ground). This voltage is graded and decreases as the
distance from the switch increases as shown below.
12.7 kV
Touch potential
12.7 kV – 10 kV =
Electric shock of 2.7 kV
12.7 kV
10 kV
8 kV Both feet
in the 10 kV zone
6 kV
To mitigate the risk of touch potential the switching operator must wear switching
gloves and insulated footwear. Where the installed earth mat may not be effective
(such as a pole top switch) an equipotential mat is placed at the foot of a switch
and connected to the earthing conductor of the switch. This places the operator’s
hands and feet at the same potential.
Step Potential
When switchgear fails resulting in fault current flowing into the ground via the
earthing system this will create a risk of step potential to the switching operator.
This fault current and related step potential risk will be removed when the
associated protective device operates.
Step potential is an electric shock hazard that occurs when a person’s feet are
exposed to voltage differential created by the fault current flowing in the ground.
To mitigate the risk of step potential the switching operator must wear insulated
footwear. Where the installed earth mat may not be effective (such as a pole top
switch) an equipotential mat is placed at the foot of a switch and connected to the
earthing conductor of the switch. Provided the switching operator remains with both
feet on the equipotential mat during the switching operation the risk of step
potential is removed as both feet will be at the same potential.
For this reason the switching operator must inspect the switch prior to approaching
the site for loose or broken switch connection, conductors or insulators.
8-43
Switching Operator's Manual One
12.7 kV
Step potential
8 kV – 6 kV =
Electric shock of 2 kV
12.7 kV
10 kV
8 kV Left foot
in the 6 kV zone
6 kV
Right foot
in the 8 kV zone
Substances that may emit toxic fumes when heated or burning are:
PILCSWA cable
insulating oil
SF6 gas.
8-44
Section Eight – Switching For Safety
Arc Flash
An arc flash is the heat and light energy released when an arc occurs and current
flows through a normally nonconductive medium such as air. An arc flash can
happen in less than one millisecond (1/1000 of a second).
The flash produced because of this breakdown is similar to the light radiation
emitted by a commercial electrical arc welder. The heat that is released from an arc
flash can be in excess of 20,000°C. Such temperatures will vaporise any known
material on earth. Obviously, any unprotected flesh or eyes of a switching operator
may be severely burned if exposed to an arc flash.
Arc Blast
The arc flash produces an arc blast which is an explosion where the massive
amount of energy rapidly vaporises metal conductors, blasting molten metal and
superheated material (plasma) outward with extreme force.
This violent event can cause the destruction of switchgear and nearby equipment.
The high velocities of molten metal particles can cause severe and possibly fatal
burns, or blindness, internal organ damage or death through inhalation of the
superheated air or fumes.
8-45
Switching Operator's Manual One
The switching operator must always wear the PPE appropriate to the switching task
as detailed in Field Instruction Worksite Clothing / Personal Protective Equipment
Requirements.
Switchroom Egress
Before switching begins in switchroom buildings and other confined spaces, the
switching operator must ensure all available exits are functioning and unobstructed
to allow rapid egress if required.
All persons not required to be present during switching operations should vacate
the switchroom building.
Due to the risk of damaged earthing which will not be discovered by visual
inspection the switching operator is to fit an equipotential mat when switching pole
top switches. Together with appropriate PPE this will minimise the risk of touch and
step potential. Full details of the requirements and procedures for the use of
equipotential mats are provided in Field Instruction Use of Portable Equipotential
Mat for Switching.
The switching operator must ensure switching tools and test equipment are
appropriately rated for the task intended to be performed.
Before use by the switching operator, all switching tools and test equipment must
be checked to ensure they are in good working order and up-to-date if a routine test
date is applicable. Where provided, built-in or self-test accessories are to be used
by the switching operator to prove the test equipment is functional.
For example, the HV insulated operating stick (also known as ‘hot sticks’ or HV live
line sticks) may be used for HV and LV switching. Six monthly HV insulation tests
are required and the sticks marked to show the expiry date. Where the date has
expired, re-testing must be completed before the sticks can be used for HV
switching.
Refer to Field Instruction Testing and Use of High Voltage Insulated Equipment for
further information.
8-46
Section Eight – Switching For Safety
Switchgear operation can involve many individual sequenced steps which are
specific to the switchgear make and type. Therefore, a switching operator must only
operate switchgear they have previously operated and are competent in its
operation.
8-47
SECTION NINE
Distribution Switching
Programs
Table of Contents
9. Distribution Switching Programs ........................................................... 9-1
i
Switching Operator's Manual One
ii
Section Nine – Distribution Switching Programs
List of Figures
Figure 9-1 PoA virtual client and mobile tablet .................................................. 9-3
Figure 9-3 PoA Switching Program Header ...................................................... 9-9
Figure 9-4 The fields in the PoA switching program ........................................ 9-10
Figure 9-5 Sample of a PoA switching program .............................................. 9-12
Figure 9-6 Network diagram before commencing the switching program ........ 9-13
Figure 9-7 Network diagram showing worksite isolated................................... 9-13
Figure 9-8 Network diagram showing worksite ................................................ 9-14
iii
Switching Operator's Manual One
List of Tables
Table 9-1 Recommended switching program notification period for work permits 9-
4
Table 9-2 Typical EAP switching program outline .............................................. 9-7
iv
9. Distribution Switching
Programs
9.1 Introduction
The switching program is one of the most important parts of safe and successful
switching on the Horizon Power network. It is a list of switching operations that are
placed in a logical sequence to ensure the operation of electrical apparatus is
carried out safely, and includes:
9-1
Switching Operator's Manual One
The program writer is the person who initiates and prepares the switching program.
This person must be authorised and hold the appropriate switching operator’s
authority for the task involved.
The program writer must have a clear understanding of what is required when they
prepare a program. They must be aware of the scope of work to be undertaken and
the switching operations required to safely allow the work to be completed.
The program checker is the person who reviews the switching program for errors
and to verify that it is fit for purpose. They must be authorised and hold the
appropriate switching operator’s authority for the task involved.
The program checker must have a clear understanding of what is required when
they check a program. They must be aware of the scope of work to be undertaken
and the switching operations required to safely allow the work to be completed.
The HPCC controller is the final authority to review a switching program. They must
be authorised at the appropriate switching authorisation level.
In the event of unplanned network conditions (e.g. a fault or overload), the HPCC
controller will prepare a program in collaboration with the on-site switching
operator. In these situations the HPCC controller will be the program writer and the
program checker will be the on-site switching operator.
9-2
Section Nine – Distribution Switching Programs
The PoA system includes Geo Viewer (a geocentric distribution database) and
Trouble Call System (TCS) which models the network diagram with real time
accurate information as switching and network outages occur.
9-3
Switching Operator's Manual One
9.4.1 Purpose
Network changes that require the creation of a “patch” in PowerOn will need to be
sent to HPCC 10 days in advance of the planned work start date.
Recommended
notification
Type of work permit period
or document (days)
Planned work 3
System Change 10
9-4
Section Nine – Distribution Switching Programs
Direct access to network apparatus for construction, maintenance and repair work
requires an Electrical Access Permit (EAP). The switching program must create a
safe work area by establishing isolation points and applying program earths on
each possible source of supply into the work area.
Sanction to Test
For example, when VLF insulation testing is required, the switching program will
provide the apparatus with established and unchangeable isolation points, however
the earths which were initially applied for access to the cable connections, may be
operated as required by the test procedure.
Vicinity Authority
A Vicinity Authority (VA) authorises work near live network apparatus whilst
remaining outside the safe approach distance for the voltage concerned. The
switching program will include steps to disable any installed auto-reclose on the
protection apparatus on the supply side of the work area.
Switching programs are also required for switching which does not involve the
issue of a work permit. An example of this is where distribution feeders require load
balancing by a permanent change in the location of a network normally open point.
9-5
Switching Operator's Manual One
Communication Steps
Communication steps occur between the HPCC controller and the switching
operator at the commencement and completion of both the isolation and restoration
stages. Work permit issue and cancellation is also communicated as part of
isolation and restoration stages.
Switching Steps
Switching operator steps are also included for work permit issue and cancellation.
An outline of the typical distribution switching program steps for the creation of a
safe work area and issue of an EAP is provided in the left hand column in Table 9-2
the other columns indicate the program step type.
Isolation
Switching operator – Contact HPCC and request
permission to proceed
9-6
Section Nine – Distribution Switching Programs
To write a switching program in PoA the program writer populates the fields in the
switching program by selecting on-screen apparatus and selecting the appropriate
operation options from drop down menus.
Writing a PoA switching program requires the completion of the header page and
the switching steps to provide:
restoration steps.
9-7
Switching Operator's Manual One
The header provides a summary of the purpose of the switching program and
allows the HPCC controller a quick reference when conducting compatibility
checks between programs and during fault activity.
Switching programs are stored as individually numbered jobs in the Work Package
Manager module in PoA.
9-8
Section Nine – Distribution Switching Programs
Request No.37015
Job No.J17-3836-v
Job Status Running
View detailed version (not suitable for printed programs)
Requested By
Comments/Notes
9-9
Switching Operator's Manual One
In this area of the switching program the program writer must include the steps for
communication, HPCC and switching operator switching, and permit management.
Program writers should attempt to keep the size of the isolated area to a minimum.
However, there may be instances where the isolated area will need to be expanded
to accommodate larger clearances, e.g. for cranes and other work site vehicles.
Figure 9-3 shows the fields in a PoA switching program for the switching steps and
their purpose. These fields are required to uniquely identify who, where and what
needs to be done.
Item Operator Location Component (Volt, Type, ID) Action System Date / Time
The Operator field The Component field The System Date / Time
identifies the role identifies the voltage, type, field provides space
responsible and identification for the time of the completion
for performing the Item. of the component of the Item.
(apparatus)
to be operated.
A typical PoA switching program is shown below and the series of figures
which follow illustrate the network diagram at particular stages of running the
switching program.
Note: The formal term used by Horizon Power is tag, however the term label is
interchangeable and often used.
9-10
Section Nine – Distribution Switching Programs
1 Schedule
13 BENNIER,COREY- BRAZIER ST,7 E CNR 11kV PTSD 2085 Off & Attach DL
0419812050(1to6) RANDELL
ST,CHADWICK
9-11
Switching Operator's Manual One
9-12
Section Nine – Distribution Switching Programs
9-13
Switching Operator's Manual One
9.6.1 Load
Switching programs may require load to be moved or reduced in order that the job
may be done.
if capacity is available
if there are any other limiting factors, e.g. a section of undersized overhead
conductor or cable.
9-14
Section Nine – Distribution Switching Programs
ensure notifications are provided for all customers who will have their supply
interrupted
The program writer should determine whether any voltage checks are required.
confirm that supply has been maintained within satisfactory limits at the point
of isolation
Due to the hazards encountered when removing taps live line, there are conditions
that apply, depending on the connection types.
Single-phase Spur
9-15
Switching Operator's Manual One
A switching operator may at any time request HPCC to disable the auto reclose
should they feel it necessary due to safety concerns.
A Switching Job Risk Assessment (JRA) shall be carried out by the Switching
Operator.
The length of the spur being disconnected shall be kept as short as possible to limit
capacitive charging as far as practically possible.
Maximum unloaded spur lengths.
a). 11kV / 12.7kV rated line - 15km
b). 19.1kV /22kV rated line - 4km
c). 33kV rated line - 1.5km
The respective upstream protective device with respect to the line tap removal i.e.
re-closer shall be disabled and reflected on the program.
The removal of the line tap itself must be reflected as an isolation step and point in
the program.
Removal of the line tap shall be carried out by a Competent Person. Note: The
Switching Operator and Competent Person may be the same person in some
instances.
9-16
Section Nine – Distribution Switching Programs
An Observer must be posted when the line tap is disconnected and reconnected.
The removed line tap shall be tagged as an isolation point with a Do Not Operate
Tag for the later Electrical Access Permit (EAP).
The removed tap and section of conductor must be mechanically secured to the
running earth conductor and not be left dangling.
These being:
A Switching Job Risk Assessment (JRA) shall be carried out by the Switching
Operator.
The length of the spur being disconnected shall be kept as short as possible in
order to limit any capacitive charging as far as practically possible.
Maximum unloaded spur lengths.
a). 11kV / 12.7kV rated line - 15km
b). 19.1 kV / 22kV rated line - 4km
c). 33kV rated line - 1.5km
The respective upstream protective device with respect to the line tap removal i.e.
re-closer shall be disabled and reflected on the program.
A specific comprehensive Job Risk Assessment shall be carried out for the removal
and replacement of the line taps.
Removal of the line tap shall be carried out by a Competent Person. Note: The
Switching Operator and Competent Person may be the same person in some
instances.
The removal of the line tap itself must be reflected as an isolation step and point in
the program required for the later Electrical Access Permit (EAP).
As a critical step in the process, an Observer must be posted when the line taps are
disconnected and reconnected.
The removed line taps shall be tagged as isolation points with a Do Not Operate
Tag for the later issue of the EAP.
The removed taps and sections of conductor must be mechanically secured and
not be left dangling.
These being:
9-17
Switching Operator's Manual One
A Switching Job Risk Assessment (JRA) shall be carried out by the Switching
Operator.
The length of the spur being disconnected shall be kept as short as possible in
order to limit any capacitive charging as far as practically possible.
Maximum unloaded spur lengths.
a). 11kV / 12.7kVrated line - 15km
b). 19.1kV /22kV rated line - 4km
c). 33kV rated line - 1.5km
The respective upstream protective device for the clamp disconnection i.e. re-closer
shall be disabled and reflected on the switching program.
The issue and cancellation of Vicinity Access Permit (VA) for the disconnection of
the clamps shall be reflected in the switching program.
The removed line tap shall be tagged as an isolation point with a Do Not Operate
Tag for the issue of the later Electrical Access permit (EAP).
The removed tap and section of conductor must be mechanically secured to the
running earth conductor and not be left dangling.
The removal of the line tap itself must be reflected as an isolation step and point in
the program required for the later EAP.
A Vicinity Access Permit (VA) shall be used for the reconnection of the clamps once
the later EAP has been cancelled.
The following risk mitigation measures shall apply when disconnecting a three phase
parallel groove tap by means of glove and barrier methods for the purposes of creating an
isolation point.
These being:
A Switching Job Risk Assessment (JRA) shall be carried out by the Switching
Operator.
The length of the spur being disconnected shall be kept as short as possible in
order to limit any capacitive charging as far as practically possible.
Maximum unloaded spur lengths.
a). 11kV / 12.7 kV rated line - 15km
b). 19.1 kV / 22kV rated line - 4km
c). 33kV rated line - 1.5km
The respective upstream protective device with respect to the line tap removal i.e.
re-closer shall be disabled and reflected on the program.
The removal of the line tap itself must be reflected as an isolation step and point in
the program required for the later EAP.
A comprehensive Job Risk Assessment shall be carried out in conjunction with the
issue of a Vicinity Access permit (VA) for the removal of the line taps.
Glove and Barrier methods for disconnecting the line taps shall be followed.
As a critical step in the process, an Observer must be posted when the line taps are
disconnected and reconnected.
The removed line taps shall be tagged as isolation points with a Do Not Operate
Tag for the later issue of the EAP.
The removed taps and sections of conductor must be mechanically secured and
not be left dangling.
9-18
Section Nine – Distribution Switching Programs
A Vicinity Access Permit (VA) shall be used for the reconnection of the clamps
once the EAP has been cancelled.
11kV = 15 km
22kV = 4 km
33kV = 1.5 km
The program writer must be aware the fault level (fault current) is increased at
times when supplies are paralleled (interconnected).
9-19
Switching Operator's Manual One
1. interconnect onto the same feeder (frequently this not possible due to
network configuration)
The program writer should first determine whether phasing out is necessary and, if
so, where it should be done.
9-20
Section Nine – Distribution Switching Programs
9.6.9 Ferroresonance
The program writer must understand how ferroresonance occurs and where it may
be encountered during a switching program.
When multiple distribution transformers are interconnected on the LV, but supplied
from different HV feeders, there is a risk if one feeder trips on fault the healthy
feeder will supply the tripped feeder load and fault via the interconnected LV. This
can possibly result in severe overload and permanent damage to the LV
interconnection.
To avoid the above problem, LV fused jumpers are used for interconnection where:
overhead transformers without LV fuses, are on the same feeder, but have a
recloser or sectionaliser between the LV interconnected transformers.
An important consideration when writing a switching program is the rating and load
breaking capacity of the electrical apparatus being switched.
9-21
Switching Operator's Manual One
Many items of electrical apparatus while able to carry significant load current have
limited ability to break load current without damage to the contacts or drawing a
substantial arc.
It is therefore important to check the ratings of each item to be switched and adjust
the program where necessary to avoid breaching their capacities.
impact on life support (LS) customers and general customers and the
associated notification requirements
Where possible, the switching program sequence should minimise the travelling
time and distances required by the switching operator. For example, where several
isolation points are required to be created, and there is no technical reason for this
to be performed in a particular sequence, the sequence which minimises the
travelling time and distances should be selected.
Where the work performed results in a change to the network, the system change
documentation must be completed by the program writer prior to execution of the
switching program.
9-22
Section Nine – Distribution Switching Programs
Switching operators must not commence switching until they are specifically
instructed by the HPCC. This is normally included as a “Contact HPCC, request
permission to commence “ step in the switching program.
Unless otherwise stated in the switching program, all switching operations will be
carried out in the consecutive sequence of step numbers in the switching program.
Where the program requires minor changes, HPCC and the switching operator will
agree on the changes required to enable the program to proceed. HPCC will
amend the program and ensure that all operators at the locations involved in the
switching program are informed of and note the program changes. The amended
switching program will then proceed.
Where the switching program requires major change, a new program will be written
by the switching operator.
The backup process will make use of a paper copy of the checked
and approved switching schedule.
HPSC and the SWOP will enter the backup process once all reasonable
steps have failed to restore switching operations via the tablet in the field.
Should the backup process be initiated during the tablet switching process
for whatever reason, the Switching Operator and the HPSC shall review the
current paper copy of the switching schedule and check which steps were
last confirmed by tablet before proceeding with the next step of switching.
9-23
Switching Operator's Manual One
If this is not possible, then the Switching Operator must go back go to the
last location of the last known step and check the status of the switched
device is correct, before proceeding with any further switching actions.
Any other additional switching steps which were added when using the
tablet must also be discussed and added to the paper copy of the program
as required at this time. This can be done manually by the Switching
Operator in the field or if possible it should be reprinted.
Once the decision is made to use a backup paper switching schedule the following
will apply or be in place:
All communication between the SWOP and HPSC will be concise and clear.
Instructed steps issued to the SWOP shall be “repeated back” to the HPSC
to ensure that each instruction has been understood.
The word “Instruction” shall be used in context when the HPSC issues an
instruction to the Switching Operator.
Every time a new call is made to HPCC, the Switching Operator shall state
his name, location and program number.
When a HPSC receives a call, he shall identify himself by name and the
control centre (HPCC).
If at any time the SWOP or the HPSC are unable to give full attention to the
operation of the schedule, the schedule should be halted until such time as
it can carry on without interruption.
9-24
Section Nine – Distribution Switching Programs
The SWOP has checked against the switching schedule that he is at the
correct location.
He has confirmed that the state of the apparatus is in the expected position.
He has noted any alarms or unusual situations that could potentially affect
safe operation of the apparatus in question.
Hatching and Cross Hatching shall be used to ensure that the SWOP does not lose
his place on the paper copy of the switching schedule.
The Switching Operator must confirm he has the correct authorised version
of the switching schedule in his possession.
Once the instruction has been executed by the SWOP, another line must be
made through this line to form an ( X ). Steps instructed but not yet
executed will clearly be visible etc. No step must be executed without a
diagonal line ( / ) adjacent to it.
9-25
Switching Operator's Manual One
Steps that do not require an action from the Switching Operator that have
been communicated by the HPSC as complete, for example tele steps,
must be indicated with a tick ( √ ) adjacent to that step in the program.
Times when the switching instruction has been completed; must be recorded by the
Switching Operator adjacent to the switching step on the paper copy in the
“Confirmed Date / Time” section.
This shall be done by using standard 24 hour clock times to record when the
switching operation was completed e.g. 12h36.
If at any time an error is made when writing information on the paper copy of the
program, for example the date / time of an operation, a single line shall be drawn
through the incorrect information and the correct information rewritten.
9-26
SECTION TEN
i
Switching Operator's Manual One
List of Figures
Figure 10-1 Typical LV Voltmeter ..................................................................... 10-3
Figure 10-2 Amplifier type voltage tester (the Modiewark®) .............................. 10-4
Figure 10-3 The Modielive® EMF generator (right) ........................................... 10-4
Figure 10-4 Ring main unit Neon indicator ....................................................... 10-5
Figure 10-5 Capacitive bushing and neon circuit.............................................. 10-6
Figure 10-6 Phasing LV disconnectors ............................................................ 10-6
Figure 10-7 LV phasing out diagram ................................................................ 10-7
Figure 10-8 Proving de-energised and phasing out .......................................... 10-8
Figure 10-9 HV overhead wireless phasing out equipment .............................. 10-9
Figure 10-10 High voltage test sticks ............................................................... 10-9
Figure 10-11 Typical 5kV HV Megger testing unit .......................................... 10-10
Figure 10-12 Horizon Power's standard VLF tester – the HVA60 VLF Tester 10-11
Figure 10-13 Method 1: Fall of potential test .................................................. 10-12
Figure 10-14 Method 2: Stakeless hand held test .......................................... 10-13
Figure 10-15 Method 3: Stakeless test ........................................................... 10-13
Figure 10-16 Typical phase rotation meter ..................................................... 10-14
Figure 10-17 The phase to neutral voltages ................................................... 10-14
Figure 10-18 Signal injector for cable identification ........................................ 10-16
Figure 10-19 Typical HV spiking tools ............................................................ 10-17
Figure 10-20 Commissioning ring main unit ................................................... 10-20
List of Tables
Table 10-1 LV phasing out tests and readings ................................................. 10-7
ii
10. Distribution Testing and
Commissioning
10.1 Introduction
This section is designed to give the switching operator an overview of the
equipment and the procedures required for the testing and commissioning of
equipment on Horizon Power's distribution networks.
Horizon Power has detailed documentation available for distribution testing and
commissioning, note this information will not be repeated here.
10.2 Documentation
Switching operators required to carry out testing and commissioning must ensure
they are knowledgeable of the requirements specified in the related Horizon Power
documentation.
10-1
Switching Operator's Manual One
The range of testing and commissioning tasks the switching operator may need to
carry out include voltage tests, phasing out tests, cable identification, insulation
resistance tests and earth resistance tests. The test equipment used to conduct
these tasks is briefly described below.
insulation testing
Voltage test equipment includes voltmeters, neon testers and amplifier type testers
(e.g. a Modiewark® device).
10-2
Section Ten – Distribution Testing and Commissioning
Voltmeters
Voltmeters may be used on the LV system to measure voltage and phasing out
tests. A hand held voltmeter is shown in Figure 10-1.
This instrument has an electronic amplifier which is used to detect the electric field
near an energised conductor. This instrument has internal batteries.
Direct contact with the conductor under test is not required, however close
proximity is preferred for correct indication.
When testing for high voltage, this tester must not be hand
held. Approved HV insulated operating sticks must be used.
10-3
Switching Operator's Manual One
A neon light and buzzer indicate if the conductor/busbar is energised when the
Modiewark is set to its prescribed voltage setting and placed adjacent to the
conductor/busbar. The following test methods must be used to prove the
Modiewark for testing.
Head
On-Off
Voltage selection
switch
Handle
with universal
sunrise fitting
Audio (buzzer)
indicator
Visual LED
indicator
Before and after testing a de-energised circuit, the preferred method of proving that
the Modiewark is operational is by testing a similar voltage on an adjacent
energised line.
The Modielive® EMF generator is an accessory device used with the Modiewark
voltage tester. The Modielive produces an electromagnetic field (EMF) which can
be detected by the Modiewark to prove the Modiewark is working correctly.
10-4
Section Ten – Distribution Testing and Commissioning
Note: The Modiewark will not be damaged by placing it against a high voltage
conductor, even when selected to ‘Test/240V’.
Horizon Power’s high voltage switchgear such as indoor switchboards and ring
main units frequently have built-in neon indicators. (see Figure 10-4).
A capacitive bushing is used on each phase to provide the neon with a reduced
voltage which is proportional to the primary conductor voltage (see Figure 10-5).
The screen develops a voltage somewhere between the primary conductor voltage
and earth (0 volts), dependent on its physical location between the primary
conductor and earth. The screen is typically located to provide voltages around
100-200V, but this can vary between bushings.
10-5
Switching Operator's Manual One
LV Phasing out
LV phasing out requires the use of a voltmeter as shown in Figure 10-6 below.
Figure 10-7 shows two LV supplies at a normally open point. As this open point is
interconnecting the two supplies, it is necessary to ensure the two supplies phase
out. Table 10-1 shows the series of tests to be performed and the expected results
for correct phasing out. An open point which does not phase out must not be
closed.
10-6
Section Ten – Distribution Testing and Commissioning
R R1 R2 R
LV W W1 W2 W LV
Suppy 1 B1 B2 Suppy 2
B B
N N
Phasing out
location
Voltmeter
Test connections Voltage reading
Volts (V)
Test supply 1 – Each phase to neutral Phase to neutral voltage Approx. 240
Test supply 2 – Each phase to neutral Phase to neutral voltage Approx. 240
Note: Because last test was ‘no significant voltage’, test the instrument is still working using any phase to phase
or phase to neutral voltage reading.
10-7
Switching Operator's Manual One
R1
R2
W1
W2
B1
B2
The switching operator should measure the incoming cable voltages between
each phase and neutral (R2 to N, W2 to N and B2 to N) to check if the cable
is de-energised. If the voltage records zero, the cable is de-energised.
Where the incoming cable is energised, if voltages higher than 30V are
measured from R1 to R2, W1 to W2 and B1 to B2 , the phasing out is not
10-8
Section Ten – Distribution Testing and Commissioning
Shown in Figure 10-9 below is the typical phasing out test equipment used on the
HV overhead.
This instrument consists of two parts; grey (transmitter) and blue (receiver). The
transmitter and receiver are connected, using insulated HV operating sticks to each
side of the apparatus to be phased out (e.g. pole top switch).
The test sequence is similar to the LV phasing out in Table 10-1, except the
transmitter unit alone is used to prove the presence of voltage on supply 1 and 2,
and then the transmitter and receiver combination is used between phases on
supply 1 and 2 to phase out. An audible signal is issued when both parts of the
instrument are connected to the same phase.
Indoor switchgear can be phased out using specialised HV test instruments such
as shown in Figure 10-10. This instrument functions as a high voltage volt meter.
10-9
Switching Operator's Manual One
An alternative method is to phase out with a voltmeter, using the voltage indicators
(neon indicators) sockets on the front panel of the switchgear. This requires the
neon sockets have been proven to be connected to the correct HV phases before
being used to phase out.
The voltage indicators (neon indicators) sockets on the front panel of the
switchgear and a hand-held voltmeter can be used to phase out HV supplies. This
requires the neons sockets have been previously commissioned and proven to be
connected to the correct HV phases before being used to phase out.
The main types of insulation test equipment used by Horizon Power include the
insulation resistance meter (Megger®) and the high voltage paper insulated cable
tester (hipot).
This device is used to measure the insulation resistance value of the apparatus by
applying a voltage (usually 1kV to 5kV) from phase to phase or phase to neutral (or
earth for HV).
VLF Testing
Very low frequency (VLF) cable testing is a technique used for testing of high
voltage cables.
10-10
Section Ten – Distribution Testing and Commissioning
The cable being tested must withstand a VLF AC voltage for a specified testing
time without flashover. This method yields a ‘Pass/ Fail’ result. Frequency ranges
used are within the range of 0.01 Hz to 0.1 Hz, with 0.1 Hz being the Horizon
Power standard.
Figure 10-12 Horizon Power's standard VLF tester – the HVA60 VLF Tester
Note: XLPE cables must not be tested with a High Voltage DC Cable Tester
(Hipot) because it may shorten the life of the cable.
Principle of Operation
Horizon Power uses multiple techniques to test and record the resistance of its
earthing systems. As there are a range of test instruments used the specific manual
must be consulted to ensure correct test setup and measurement technique.
A range of test instruments and associated test methods are used. The most
common test methods include:
10-11
Switching Operator's Manual One
Figure 10-13 shows the fall of potential test method used to measure the
effectiveness of the earth electrode under test. This method requires a known test
current to be passed between the electrode under test and the test stake (current).
The voltage is measured at the test stake (voltage) in positions 1, 2 and 3 and the
average voltage value is calculated. Using Ohm’s Law R = V/I = (average voltage
value) / (test current) is used to determine the resistance of the electrode under test
resistance.
Position Position
Position 3 2 1
Earth
Figure 10-14 shows the instrument applied to the electrode under test whilst it
remains connected in the earth system. The clamp-on head has two internal cores,
the first core induces a constant AC voltage into the earth rod under test and the
second core measures the induced current which flows.
Because the induced voltage is constant, the current flowing is proportional to the
electrode under test resistance. This method requires multiple earth electrodes to
provide the loop current required for measurement.
The greater the number of additional electrodes, the greater the accuracy of the
measurement. The instrument-induced voltage is at a very high frequency to
ensure the measurement is not affected by any 50Hz current which may be flowing
in the electrode under test.
10-12
Section Ten – Distribution Testing and Commissioning
Other earthing
system electrodes
Electrode
under test
Earth
This method is similar to Method 2, except the voltage inducing and current
measurement cores are separately attached to the electrode under test. See Figure
10-15.
Other earthing
system electrodes
> 10 cm
Electrode
under test Earth
10-13
Switching Operator's Manual One
Other specialised equipment includes phase rotation meters and cable location
meters.
The phase rotation meter is a device used to test for correct phase rotation (see
Figure 10-16). The phase to neutral voltages in Figure 10-17 show the correct
sequence R > W > B as each phase reaches its peak value. Phase rotation
determines the direction three-phase electric motors will spin. The swapping of any
two phases will cause the motor to spin backwards.
It is most important that phase rotation meters are not used for phasing out, as
different phasing can give the same phase rotation.
Phase rotation meters may be used for checking supplies that cannot be
interconnected or for the rotation of kilowatt-hour meters.
Phase-neutral Voltages
400
200
-200
-400
inst R V inst W V inst B V
10-14
Section Ten – Distribution Testing and Commissioning
signal injection.
The measurement of magnetic field (due to the load current in the cable) is used to
establish whether a cable is in the vicinity (including its alignment and depth). This
knowledge is necessary, for example, when excavation is occurring near buried
cables.
Note: The cable detector uses the measurement of magnetic field to locate
cables. It will not detect an energised cable that is unloaded.
One of the problems of the magnetic field cable detector is that it is difficult to
distinguish a specific de-energised cable from surrounding cables.
It is standard procedure to work on live LV cable. This means there is the danger of
an HV cable being worked on live, because it has been incorrectly identified as a
LV cable.
For this reason, it is necessary to use signal injection for cable detection when
several similar cables are run in the same alignment and positive identification of
only one cable is necessary.
Where it is not possible to positively identify an LV cable, the required cable must
be made dead and spiked using a HV cable spiking gun. The width of the blade
should be across the cable to ensure contact is make with all three phases.
10-15
Switching Operator's Manual One
Note: Before removing the spike from the cable, the point of LV supply must
first be checked for blown fuses or any HV protection operation.
To accurately identify the location of cables, a signal is injected into the cable at a
convenient point. The cable detector is then able to follow the route of the particular
cable. However, there may be difficulties in avoiding the injected signal flowing into
other cable neutrals. This makes the method unsatisfactory for the identification of
LV cables.
Signal injection is accurate for HV cables, because the signal may be isolated from
earth. This is achieved by short circuiting the cable between two phases at the
remote end and injecting a signal between the two phases at the signal point. The
signal is then picked up by the signal detection instrument current at any point
along the cable route.
In general, HV apparatus must be tested and earthed at the work site, if the
program earthing points cannot be seen. Because this is impractical for HV cables,
the method of proving the cable de-energised requires a spiking tool to penetrate
all cable phases at the work site. Once this has been done, the cable can be
worked on with no visual earths.
For further information refer to the Field Instruction Identifying and Proving of HV
Cables.
10-16
Section Ten – Distribution Testing and Commissioning
The switching operator must also ensure that the auto reclose function
is disabled on the cable to be spiked and on all cables in the vicinity.
During the spiking action, contact must be made with HPCC to verify
that the spiking action has not affected the network by tripping other
feeders.
10-17
Switching Operator's Manual One
ensure correct operation of the apparatus and suitability for integration into
the network.
Distribution Commissioning Test Sheets describe the required tests and provide
space for the recording of test results for electrical apparatus.
Note: Where testing has been carried out by other competent persons, the
associated test sheets and handover sheets must be provided to the
switching operator for review before equipment energisation can occur.
Distribution Commissioning Test Sheets are available for the following apparatus:
10-18
Section Ten – Distribution Testing and Commissioning
Customer-owned installations
Distribution substations
Private parallel generators
Distribution substations
Reclosers
Fault indicators
Testing requirements
10-19
Switching Operator's Manual One
Substation Substation
B A
SWDC SWDC SWDC SWDC FSSW FSSW
4 3 1 2 1 2
Existing LV
Live LV
board
Transformer 2
Substation
C
Feeder 1 SWDC SWDC
6 5
Existing LV
Live LV
board
Transformer 1
SWDC = RMU switch disconnector
FSSW = RMU fuse switch
= Existing installation
= New installation
Phasing Out and Proving of Labels on a New 2+2 Ring Main Unit
The following steps are required to be carried out, to prove the switchgear
operation on potential, HV and LV phasing out and circuit label designations on a
new 2 + 2 ring main unit (RMU) as shown in Figure 10-20.
This is an example of the switching sequence that can be used for commissioning
Substation A RMU, however there are other switching sequence variations which
could alternatively be used to achieve satisfactory commissioning.
Initial conditions are that Substations B and C are energised via RMU SWDC 4 and
RMU SWDC 6 respectively. All other switches are OFF and all earth switches are
OFF.
2. At Substation A check that all HV switches are OFF and earth switches are
OFF.
10-20
Section Ten – Distribution Testing and Commissioning
10. Switch RMU SWDC 1 OFF at Substation A. This proves the operation of the
switch while energised.
Note: Transformer 1 has been supplied from the two HV supplies (Substation
B then Substation C) and phased out both times using the LV side of
Transformer 1 to an existing LV system – this proves both HV supplies must
phase out.
14. Switch RMU FSSW 1 OFF at Substation A. This proves the operation of RMU
FSSW 1 while energised.
15. Switch RMU SWDC 2 OFF at Substation A. This proves the operation of
RMU SWDC 2 while energised.
19. Switch RMU SWDC 5 ON at Substation C. (Steps 17, 18 and 19 allow RMU
FSSW 2 and the Transformer 2 to be energised remotely.)
20. Check the no load volts at the Transformer 2. If the transformer is energised,
this proves that the correct labels are fitted to RMU FSSW 2 and the
Transformer 2.
10-21
Switching Operator's Manual One
22. Switch RMU FSSW 2 OFF at Substation A. This proves the operation of RMU
FSSW 2 while energised.
23. Switch RMU SWDC 1 ON at Substation A. This proves that the new HV
circuits parallel successfully.
The switching may then be completed to the required final circuit arrangement and
the normal open points set to the designated positions.
All phasing out and switching operations shall be written as part of the switching
program.
It would also be possible to use the voltage indicators (neon indicators) sockets
with a voltmeter to phase out the two HV supplies (from RMU SWDC 3 and RMU
SWDC 5). This requires the neons sockets have already been proven to be
connected to the correct HV phases inside the switchgear.
An example of the switching sequence required to prove the neons sockets is:
1. With RMU SWDC 3, RMU SWDC 5, RMU FSSW 1 and RMU FSSW 2
all OFF
4. Phase out on the neon sockets on RMU SWDC 1 and RMU SWDC 2.
As both RMU SWDC 1 and RMU SWDC 2 cables are supplied from a single HV
source (RMU SWDC 3), the correct phasing out proves the neon sockets
connections inside the switchgear are correct.
These neon sockets can now be used to phase out the two separate HV supplies to
Substation A from RMU SWDC 3 and RMU SWDC 5.
10-22
SECTION ELEVEN
To Be Confirmed