Lifting Procedure of Generator
Lifting Procedure of Generator
Lifting Procedure of Generator
1 of 26
- SDCC : Original
- CNEEC : Copy
- Originator: Copy
ISSUED EFFECTIVE
REV. NO BRIEF OF REVISION
DATE DATE
0 22-10- 2008 22-10- 2008 CHANGE TEMPORARY BEAM AND SPREADER BEAM
1 14-11- 2008 15-11- 2008 REVISION AS COMMENTS
2 27-11- 2008 28-11- 2008 ISSUED FOR APPROVAL
TABLE OF CONTENT
1 Title 1 of 26
2 Scope 3 of 26
3 Objective 3 of 26
4 Reference 3 of 26
5 Description Procedure 3 of 26
5.2 Execution 4 of 26
6 Risk analysis 6 of 26
7 Attachment 7 of 26
DOCUMENT NO. :
LIFTING PROCEDURE OF GENERATOR STATOR P-T3109-RED-005
(TURBINE HOUSE) ISSUED DATE :
27 Nov 2008
7.10. Certificate 21 of 26
1. TITLE
LIFTING PROCEDURE OF GENERATOR STATOR
2. SCOPE
This procedure describes the guidelines and operation step for lifting generator
stator by Jack up system.
The Generator Stator has a shipping weight (approximately) 180 tones and size
of 7690 mm (L) x 3800 mm (W) x 4085 mm (H).
3. OBJECTIVE
4. REFERENCE
1. W – HSE – 001 – Project HSE Management System Plan.
2. W – SAF – 026 Crane & Lifting Procedure.
3. Handbook of Rigging by W.E Rossnagel, P.E (Third Edition).
4. General Catalog, The Crosby group, Inc. ( 2002 Catalog Browser ).
5. Drawing, No : 0EG.340.223S ( Generator Stator )
DOCUMENT NO. :
LIFTING PROCEDURE OF GENERATOR STATOR P-T3109-RED-005
(TURBINE HOUSE) ISSUED DATE :
27 Nov 2008
5. DESCRIPTION PROCEDURE
Safe Working Loads : Each SWL 135 Tones Using 9 Dyform Strand.
each strand taking 15 tonnes
Stroke : 500 mm
5.2. EXECUTION
c) The jack base will be tack welded to the jack supports beams
together with the moving bridge and the fixed anchor blocks
installed inside their fabrications.
d) The jacks and fixed anchor will now be threaded with their
strands comprising the lifting cables.
A. Preparation works
Access way from Generator Storage to inside Turbine Building
house axis 9-10 shall be cleared and compacted wherever required
for the transportation of Generator Stator by Goldhover Trailer.
All rigging tools such as Sling, Shackle, spreader beam and strands
of Over Head Crane ensure that in good condition. On 0 meter
ground located on open space of T/G house, marking by paint the
longitudinal and horizontal centerline, led from generator’s
foundation for unloading generator stator position.
DOCUMENT NO. :
LIFTING PROCEDURE OF GENERATOR STATOR P-T3109-RED-005
(TURBINE HOUSE) ISSUED DATE :
27 Nov 2008
6. Risk Analysis :
7. ATTACHMENT