Design and Construction of LNG Regasific
Design and Construction of LNG Regasific
Design and Construction of LNG Regasific
GASTECH 2005
March 14 – 17, 2005
Bilbao, Spain
© Gastech 2005
Design and Construction of LNG Regasification Vessel
Hochung Kim, JungHan Lee, Daewoo Shipbuilding & Marine Engineering Co. Ltd.
Abstract
With the expansion of the LNG consumption around the world, many LNG receiving terminals are under various
planning and engineering stages. Though the concepts and ideas on the offshore floating LNG terminal have been
studied and widely spread for many years, actual projects could not be materialized mainly due to technical risks
involved in the offshore operation as well as the commercial justif ication. Considering land-based or offshore LNG
receiving terminal projects usually take 5-7 years from feasibility study, authority permission clearance, engineering,
and actual construction, the f irst physical appearance of the LNG Regasif ication Vessel (LNG RV) in the commercial
market would be an important achievement in the offshore LNG technology. The typical LNG storage and regasif ication
(regas) capacity of the LNG RV is 138,000 M3 and 500 mmscfd respectively. The LNG RV had successfully completed
the submerged buoy connection test and the regas operation test with actual LNG during the sea and regas trials
before the delivery of the vessel, and she will start the f irst commercial regas operation at the Gulf of Mexico later
March 2005. This paper covers introduction of the LNG RV process, design and construction of the regas system, regas
process simulator, and offshore buoy mating system. The experiences gained from the f irst LNG RV implementation
could be a step-stone for the future offshore LNG terminal technologies, and contribute to the safe and stable supply of
the clean energy.
General
The LNG RV is based on the conventional LNG carrier design with onboard LNG regasif ication (regas) facilities and
internal turret for the sub-sea pipe connection. The LNG RV can take the role of the conventional LNG carrier during the
voyage, and at the same time it is used for an offshore regas terminal when connected to a submerged buoy. The
regas process is mainly composed of the LNG feeding pumps, HP (high pressure) pumps, vaporizers, and send-out
equipment, which is similar to that of a land-based LNG receiving terminal. The heating medium of the vaporization is
sea water. The LNG cargo tanks are based on the conventional membrane type (GTT No. 96) containment system. But
the strengthened insulation boxes have been used in sides, hoppers and top of the tanks. Therefore, there is no tank
level restriction in the regas operation.
I n LNG RV, 6 sets of HP pumps and vaporizers are installed in the forward part of the vessel (3 units in port, 3 units in
starboard) The normal regasif ication capacity is 500 mmscfd (each vaporizer : 100 mmscfd, million standard cubic feet
per day), and the maximum capacity can be 690 mmscfd. Therefore, the onboard 138,000 cubic meters LNG can be
converted to the HP NG (natural gas) within 5-6 days. LNG RV process is briefly shown in Figure 1. The HP NG also can
be delivered through either mid port or starboard HP manifold.
The LNG RV concept, which is also known as the “Energy Bridge”, had been introduced initially in Ref. 2, and more
details of project backgrounds, applications, and operations will be introduced in Ref. 3 and Ref. 4. Therefore,
duplicated parts of the contents will not be reiterated in detail in this paper. The builder, owner, and charterer of the
f irst LNG RV are Daewoo Shipbuilding and Marine Engineering (DSME), Exmar, and Excelerate Energy. The 3 parties
have worked very closely for the LNG RV project from the early concept development to the detail engineering stages.
The LNG RV, the f irst offshore LNG facility, has completed the construction, sea, gas, and regas trials, and delivered to
Exmar on January this year. Excelerate will start the f irst LNG regasif ication business (based on Deepwater Port Act,
USA) in March 2005, at Gulf of Mexico (West Cameron Block 603).
LNG RV is based on the collection of many proven technologies in the LNG industry including LNG carriers and land
base LNG receiving terminals. From the proven operation records and a series construction of the LNG carriers, the LNG
containment system and the cargo handling system technologies have become very mature. I n parallel, the
accumulated technologies from the land base LNG receiving terminal designs and operations especially in Japan and
Korea could bring suff icient references in the similar operation. Equipment vendors in LNG carriers and LNG receiving
terminals have enhanced their equipment reliabilities and performances these past years. I n Korea, the environment for
the LNG RV technology development were favorable as shipyards had many experiences in LNG carrier construction and
LNG receiving terminal industry had references for the basic design and operation. The maturity of offshore mooring
and off-loading technology in oil and gas FPSO’s and the crude shuttle tankers from West Africa, and North Sea could
bring conf idence in the safe operation of a vessel in a harsh offshore environment.
Some of the characteristics of the regasif ication (regas) and turret equipment are introduced here to have overview of
the LNG RV operation. HP (high pressure) pumps, vaporizers, metering, and turret system have been supplied by
Nikkiso, CPP, and APL respectively.
2.3 Vaporizer
Shell and tube type LNG vaporizers have been adopted considering equipment size, ship motion effects, and references.
The vaporizers have been designed to cope with the high thermal shrinkage due to the cold LNG and corrosion against
sea water. Due to the high pressure, it was not practical to adopt opening flanges for tube bundle maintenance. I nstead,
very careful quality control program from the component manufacturing to the f inal assembly in the factory has been
maintained. The piping systems connected to the inlet and outlet of the vaporizer have been designed to have
suff icient flexibilities so that excessive nozzle forces are not exerted to the vaporizers. The vaporizers have been
designed to operate in the supercritical pressure of the natural gas. Therefore the regas system has been designed to
operate above the LNG critical pressure regardless of the downstream network pressure. Any pressure down is required,
it can be done in the main send out control valve of the LNG RV.
3. Design Features
As stated previously, the LNG RV design adopts many proven technologies from LNG carrier, receiving terminals, and
offshore mooring and offloading. However, the system integration and the unique application in the offshore
environment required special attentions and technology developments. Some of the design features are introduced in
the followings.
3.1 Arrangement
The LNG RV design started from the concept that the vessel will not be much different from the conventional LNG
vessel to utilize the proven design and to reduce the overall project schedule. Most of the conventional LNG carrier
systems have not been changed. The regas system was assigned to the slanted part of the No. 1 cargo tank. 3 HP
pumps and 3 vaporizers have been arranged in each of the port and starboard sides. The turret has been located in the
forward part of the No. 1 cofferdam. The heating water pump room and the regas switchboard room have been
assigned to the beneath of the forecastle deck. The eff icient arrangement of the regas, turret, heating water, and
electric system in the compact areas was one of the diff icult tasks of the LNG RV engineering. The HP LNG liquid
© Gastech 2005 Kim & Lee 4
handling areas have been properly protected against liquid spillage.
3.2 Thrusters
LNG RV requires an accurate positioning and maneuvering capability for the mating of the submerged buoy. For the
purpose, LNG RV is equipped with 2 bow thrusters, and 1 stern thruster in addition to a rudder and a main turbine
driven propeller. Whereas most of the shuttle tankers adopt the CPP (controllable pitch propeller) system for better
positioning performance, LNG RV adopted the f ixed pitch propeller considering the normal voyage operation and the
characteristics of the steam turbine. Shipyard developed a dedicated system for the unique positioning requirements.
The system was named as “maneuvering aids and positioning system, MAPS”. The MAPS collects the status and
environment information, and allocates the thruster forces to each of the thrusters and main propeller.
Onboard turret system is composed of swivel, swivel handling, flexible riser, rope guide, rope guide handling, hydraulic,
traction winch, and control systems. As the functions, equipment, and utility system arrangements were quite different
and not familiar with shipyard, there were some diff iculties in the construction of the turret system. The mating cone
© Gastech 2005 Kim & Lee 5
was machined by the outdoor portable machining tool. The turret system has a PLC based standalone control system.
But all the turret related parameters are linked to the shipboard central control system by a serial communication.
I mportant parameters and those signals required for the LNG RV overall control and shutdown have been hardwired
and controlled by the central control system.
through the detail process analysis, heat dissipation, pressure drop, and stress calculations. Especially the pipe stress
analysis for the HP LNG and HP NG lines in regas area needed a lot of efforts. During the pressure and cold tests of the
piping system, actual stress measurement by stain gauges have been made and compared with the theoretical values.
As the HP cryogenic lines between HP pumps and vaporizers do not allow hydro test with fresh water due to the
possibility of water remains during actual operation, pneumatic test with HP nitrogen (201 bar) has been used for the
test. Suff icient loops for the regas piping system have been given to reduce the piping stress due to the cold
temperature shrinkage.
Thanks to the thorough check in the previous stage, there have been few changes in the actual operation of the regas
trial. I ndependent ESD (emergency shut down) system has been provided in the LNG RV. The ESD system adopted the
same hardware as the conventional LNG carrier. However, the ESD system has a hardwire switch to distinguish between
the conventional LNG mode and the regas mode. The control and ESD system can monitor and control for the turret
and sub-sea part as well. Therefore consistent integrated control and safety functions for the LNG RV, submerged buoy,
and the sub-sea PLEM (Pipe Line End Manifold) can be achieved.
The regas send out pressure and flow should be controlled carefully to meet the downstream pressure and flow
demand, which are critical to the overall performance and daily throughput of the LNG RV. At the same time the
onboard regas system pressure should maintain predef ined minimum value to secure the stable performance of the
vaporizer. The effective BOG (boil off gas) handling during normal operation, cool down, and depressurization are made
by the suction drum inlet and outlet control valves, and control loop programs for the specif ic operations.
3.10 MAPS
An approaching and positing keeping system for the mating with the submerged buoy had to be developed as there
were no similar systems for the application. Though the steam turbine system also had some limitations in the
continuous operation in the low RPM, the control characteristics was better than that of slow speed diesel engine. For
the improvement of the existing steam turbine from the limitations, a series of discussion with turbine vendor had been
made.
I n the submerged buoy, 6 acoustic transponders are prepared, so that the acoustic transceiver installed in the LNG RV
can detect the exact location of the buoy center. Onboard acoustic transceiver is installed in the bottom of No. 2
cofferdam and extruded approximately 2.8 meters from the hull bottom when the vessel is approaching to the mating
site. DGPS (Differential Global Positioning System) usually gives quite accurate position information, typically 2-3 meters.
Hence the DGPS itself can provide reliable location information. However, to verify the actual location of the submerged
buoy with a self-dependent device, the APR (acoustic positioning reference) system should be used in parallel.
The MAPS development required advanced ship hydrodynamics and control backgrounds. But as the required
technologies and the model tests data were readily available, the hardware and software development have been
smooth. To f ind more detail characteristics of thrusters for the MAPS, additional model test have been carried out.
For the training and familiarization of the MAPS, MAPS simulator has been developed. The simulator depicts LNG RV
motion characteristics. Hence, it could be used effectively before the deployment of the main system. Whereas some of
the operations cannot be learned from actual system such as operations in the extreme weather or in one of the
thrusters fail mode conditions, the simulator does not have any limitations in the dangerous operations.
by using a specially prepared floating fender. The same procedure of the turret mating, opening the mating cone cover,
dropping the messenger line, connecting the submerged buoy, rope guide handling, hoisting the submerged buoy with
an onboard traction winch, swivel connection, buoy disconnection, and buoy dropping, was carried out. During the
dummy buoy test, the performance of MAPS and the APR (acoustic positioning reference) system have also been
checked.
120
100
Pressure (bar g)
80
60
40
20
0
0 20 40 60 80 100 120 140
Time(min)
Not only for the capacity test, detail control functions have been carried out with the actual situation as far as
practicable. Therefore most of the loop and cascade controls have been demonstrated during the regas trial.
The regas operation in the shipyard stage may have a special meaning though the regas amount was not so much. The
operation would be the f irst offshore LNG regas record.
5. Conclusion
The LNG RV has been successfully constructed and delivered to her owner after proving the regas functionalities in the
regas trial. The LNG RV is the f irst offshore LNG facility, and its success would accelerate subsequent offshore LNG
projects and technology developments.
6. Acknow ledgements
Authors and our colleagues sincerely appreciate those who initiated the LNG RV concept from the scratches. And
equally, we appreciate those unknown persons in unknown places who have worked for the development of the
offshore LNG technology in various f ields regardless of their successes or fails of the concepts and technologies. We
heartily respect their challenging attitudes and dedications. We believe we have been fortunate that we could utilize
© Gastech 2005 Kim & Lee 11
and materialize the long accumulated outputs from those people and organizations around the world.
References
1. Hans Y.S. Han, JungHan Lee, and YongSoo Kim, “Design Development of FSRU from LNG Carrier and FPSO
Construction Experiences”, OTC 14098, Offshore Technology Conference, 2002
2. Jonathan Cook, “EP Energy Bridge – Offshore LNG Delivery Solution” Gastech 2002
3. Jonathan Cook, “Technical & Commercial Prove Up Of Energy Bridge” Gastech 2005
4. Patrick Janssens, “Energy Bridge TM - The World's First LNG Offshore Solution”, Gastech 2005