MTP132-Daily Report 24 July 2023
MTP132-Daily Report 24 July 2023
MTP132-Daily Report 24 July 2023
Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks
Rebarman 25 23 253
Mason 20 18 198
Carpenter 25 24 264
Fitter 12 8 88
Boilermaker 8 4 44
Pipe Fitter 6 2 22
Indirect * 68 56 598
Planner 1 1 11
Surveyor 3 2 22
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1 1 17
Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100.00% 0.16% 0.12% 24.87% 11.19% 13.69% 88.81% 11.19%
Piping Work Percent 100.00% 0.04% 1.40% 0.52% 0.88% 99.48% 0.52%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Ongoing Swith Room anchor installation Continue Swith Room anchor installation
Ongoing chipping & finishing EMB footing Continue chipping & finishing EMB footing
Ongoing finishing Transformer Bay footing Continue finishing Transformer Bay footing
Dismantle & cutting precasted SF column rebar Continue dismantle & cutting precasted SF column rebar
Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar
B. Structure : B. Structure :
Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 78 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10
Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 10 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10
Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10
Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10
Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 31 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
Ongoing Switch Room anchor installation Transformer bay finishing after concreting
DAILY PHOTOGRAPH
PHOTOGRAPH
Install Switchroom formwork, reinforce support, install anchor Dismantle formwork support
Finishing EMB south footing Install bottom waler Switchroom pedestal support
DAILY PHOTOGRAPH
PHOTOGRAPH
Install Fire water pump slab Buang puing area bekfil emg
Buat kotak untuk penampungan sampah tmf Fabricate waste bin for TMF area
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Bending cakar ayam finis Fabricate waste bin for TMF area
Piping
Joint 09 HDPE pipe dia PSL 160 Joint 08 HDPE pipe dia PSL 160
Continue fitting HDPE pipe Joint 10 HDPE pipe dia PSL 160
Structure
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Continue sort out & pre assembly TFP Continue sort out & pre assembly TFP
Continue sort out & pre assembly TFP Continue sort out & pre assembly TFP
Prepared by : Approved by :
Project Control