MTP132-Daily Report 21 July 2023

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Friday, 21 July 2023

DAILY PROGRESS REPORT


0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks

Direct Labor * 141 108 1430

Skilled Worker (Source : Jakarta) 110 83 1188

Rebarman 25 22 242

Mason 20 17 187

Carpenter 25 24 264

Fitter 12 8 88

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) : Helper 31 22 242

Unskilled Worker (Source : Local) : Watchmen 3 3 33

Indirect * 68 53 556

Construction Manager 1 Total Hours :

Site Manager 1 1 11 Note :

Planner 1 1 11

Surveyor 3 2 22

Field Engineer/Project Engineer 1 1 11

HR Staff/Administration 2 1 11

HR/Administration 1 1 11

GA & Supporting 1 1 11

Administration 1 1 11

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 1 11

Civil Superintendent 1 Roughter Crane 50 Ton 1

QC Staff 2 2 22 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 Mixer Truck 03 1

Scaffolder 7 7 77 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 4 44 Tractor Head 6X6 1

Logistic and Warehouse 2 3 30 LV 01 (Pajero) 1

Rigger 3 3 33 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1

Assistant CM 1 1 11 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 1 11 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 1 11 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Friday, 21 July 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2

TOTAL 206 161 1744

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirect)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100.00% 0.18% 0.04% 24.37% 10.88% 13.49% 89.12% 10.88%

Mechanical Work Percent 100.00% 0.00% 1.52% 1.52% 100.00%

Piping Work Percent 100.00% 0.03% 0.001% 1.27% 0.52% 0.75% 99.48% 0.52%

Structural Percent 100.00% 0.02% 0.13% 2.80% 0.74% 2.06% 99.26% 0.74%

Plate Works Percent 100.00% 0.31% 0.31% 100.00%

Erected Tanks Percent 100.00% 0.02% 0.02% 0.02% 100.00%

Electrical Percent 100.00% 0.25% 0.94% 0.94% 100.00%

Testing and Punch list Percent 100.00% 100.00%

Pre-commisioning Percent 100.00% 100.00%

Total Percent 0.50% 0.17% 31.23% 12.14% 19.09% 12.14%

2. MAJOR HIGHLIGHT

Friday, 21 July 2023 Saturday, 22 July 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Complete fabricate Swith Room pedestal formwork Start install Switch Room anchor

Complete remove EMB footing formwork Finishing EMB footing concrete

Remove Transformer Bay formwork Curing slab rebar Transformer Bay

Dismantle precasted SF column rebar Continue dismantle precasted SF column rebar

Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar

B. Structure : B. Structure :

Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 77 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø 160 PN10 Joint 76 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10

Joint pipe HDPE Field Piping Ø 90 PN10 Joint 75 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10

Joint pipe HDPE Field Piping Ø 63 PN10 Joint 70 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10

Joint pipe HDPE Field Piping Ø 355 PN16 Joint 31 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Install PERI UP footing GL 1-5 Continue install PERI UP footing GL 1-5

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -19.09% Base on updated Schedule R

Need Civil to give way to SMP team

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Friday, 21 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting TBM at recyn


CIVIL

Fabricate shelter furniture Cleaning EMB

Chipping South side EMB wall Formwork maintenance

Formwork maintenance Setting Switchroom pedestal formwork


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Friday, 21 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Fabricate Switch Room anchor template Finishing EMB footing

Fabricate shelter furniture Cutting rebar dia 8 for anchor bracing

Dismantle precasted column Install EMB corner rebar

Install Fire Water Pump slab rebar Fabricate rebar spacer


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Friday, 21 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Fabricate rebar spacer Fabricate rebar spacer

Transfer Switchroom anchor bolt to TMF Marking & cutting EMB wall

Install Switchroom Bowplank Fabricate Switch Room anchor template

Formwork cleaning & maintenance Switch Room anchor inspection


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Friday, 21 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Cutting rebar dia 8 mm for bracing Dewatering Filtration footing

Dewatering Filtration footing Install safety handrail for EMB

Install safety handrail for EMB Finishing Switchroom footing


Piping

Joint 29 HDPE pipe dia 355 PN16 Joint 31 HDPE pipe dia 355 PN16
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Friday, 21 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint 77 HDPE pipe dia 400 PN10 T joint to HDPE pipe dia 110 PN10
Structure

Sort out TFP material Preassembly TFP material

Sort out TFP material Sort out TFP material