MTP132-Daily Report 21 July 2023
MTP132-Daily Report 21 July 2023
MTP132-Daily Report 21 July 2023
Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks
Rebarman 25 22 242
Mason 20 17 187
Carpenter 25 24 264
Fitter 12 8 88
Boilermaker 8 4 44
Pipe Fitter 6 2 22
Indirect * 68 53 556
Planner 1 1 11
Surveyor 3 2 22
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1 1 11
Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100.00% 0.18% 0.04% 24.37% 10.88% 13.49% 89.12% 10.88%
Piping Work Percent 100.00% 0.03% 0.001% 1.27% 0.52% 0.75% 99.48% 0.52%
Structural Percent 100.00% 0.02% 0.13% 2.80% 0.74% 2.06% 99.26% 0.74%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Complete fabricate Swith Room pedestal formwork Start install Switch Room anchor
Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar
B. Structure : B. Structure :
Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 77 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø 160 PN10 Joint 76 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10
Joint pipe HDPE Field Piping Ø 90 PN10 Joint 75 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10
Joint pipe HDPE Field Piping Ø 63 PN10 Joint 70 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10
Joint pipe HDPE Field Piping Ø 355 PN16 Joint 31 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
DAILY PHOTOGRAPH
PHOTOGRAPH
DAILY PHOTOGRAPH
PHOTOGRAPH
Transfer Switchroom anchor bolt to TMF Marking & cutting EMB wall
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint 29 HDPE pipe dia 355 PN16 Joint 31 HDPE pipe dia 355 PN16
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint 77 HDPE pipe dia 400 PN10 T joint to HDPE pipe dia 110 PN10
Structure
Project Control