Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Hydranautics TAB142 L

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Technical Service Bulletin March 2015 TSB142.

01

Commissioning Procedure for HYDRAcap


This Technical Service Bulletin provides information for commissioning of a HYDRAcap
membrane system in a water treatment facility.

1. INTRODUCTION

The goal of this document is to outline the general procedures for commissioning
HYDRAcap® rack(s). The document should provide sufficient information to aid in the
planning and sequencing of the commissioning process. For specific projects, an
independent check must be carried out as to its suitability. It specifies the various
implementation procedures including installing, cleaning, and testing the system. A
typical P&ID of a HYDRAcap® system can be provided upon request as a guideline for
system configuration and for determining the recommended amount of equipment and
instruments needed for a fully automated HYDRAcap® system. The details of
construction, equipment manufacturers, model numbers, and site specific drawings are
to be provided by the System Supplier.

The procedures discussed within this document are to be read in conjunction with the
System Supplier commissioning procedures. Construction completion activities must be
verified as complete before commissioning can start. Commissioning is carried out by
functionally testing each main process component of the HYDRAcap® plant offline. This
document is designed to be included in the overall commissioning plan for the plant.
TSB142.01 Page 2

2. PRE-COMMISSIONING ACTIVITIES

Immediately following the construction activities, the following items must be checked
prior to commissioning:

 Tanks: Construction (i.e. installing connections, tapping, installing tank vents, or


any other related activity) should be completed to all tanks involved in the
membrane system including, but not limited to:
o Feed Tank
o Filtrate Tank
o Backwash Tank
o Clean in Place (CIP) Tank
o Chemical Tank(s)
o Sewage/Neutralization Tank, if required
A visual inspection for internal cleanliness must be made to all the tanks listed
above.
 Power and Electrical Components: Test all pumps, electrical connections, inputs
and outputs of each instrument, level switches, and motor rotation to ensure
proper installation and functionality. This check must be done prior to introducing
water into the system.
 Other Equipment and Instrumentation: Pressure transmitters, flow meters,
pumps, valves, and all measuring devices must be installed. Some systems may
require a ventilation or air conditioning system to keep instrumentation cool.
o With the rack full of water, check timing of valves to both open and close
for all automatic valves. Valves should be optimized to prevent water
hammer and pressure spikes, and to avoid loss of production time while
valves open and close. Each valve should be checked to ensure that they
are properly fastened.
o All instrumentation used for analysis must be calibrated and ranges set.
Instrumentation and equipment test sheets should be completed and
validated by a representative of the System Supplier.
o All flow control valves should be throttled a minimum of 3 times to ensure
reproducibility of the flow set point.
TSB142.01 Page 3

 Sequences of each operating mode (Filtration, Backwash, Chemically Enhanced


Backwash, Clean in Place, Membrane Integrity Test) must be checked before
commissioning and introducing water.
 Alarms modes need to be verified.
 All pipework, couplings, fittings, and other connections must be both visually
checked and leak tested to ensure there are no loose components or leakages.
 All chemical, coagulant, and other dosing systems should be ready for use, as
applicable to the specific system design.
 All piping such as the feed, backwash, chemically enhanced backwash,
membrane integrity, and clean in place must be checked and compared to the
P&ID of the system / plant.
 The compressed air system should be ready for use.
o A minimum pressure of 6 bar (87 psi) is recommended for valve actuation;
however, this pressure should be confirmed with the selected valve
manufacturers requirements.
o The compressed air supply should be checked.
o Hydranautics recommends the receiver be equipped with a low and high
pressure detector. When the pressure in the air receiver is less than 9 bar
(132 psi), the compressor should be started automatically until the
pressure reaches 10 bar (145 psi). Care should be taken to avoid
exceeding 10 bar (145 psi).
o Ensure that the air is oil free.
o The air pressure relief valve for the air integrity line must be calibrated at
1.4 bar (20 psi).
o The pressure regulator for the air integrity line needs to be adjusted to be
between 1.4 bar (20 psi) max.
o To avoid overpressurizing the module, a safety release valve should be
installed to prevent the air pressure from ever exceeding 5 bar.

All construction should be completed prior to delivering and installing the modules to
prevent foreign matter (i.e. debris, dust, shavings, etc.) from entering the modules. If
there is a pre-treatment system prior to the HYDRAcap® system, it must be
TSB142.01 Page 4

commissioned and optimized before the membrane system is commissioned in order to


ensure that the expected feed water quality is provided to the modules.

3. PHASE 1 - FLUSHING AND TESTING THE SYSTEM

It is important to clear all lines of any particulates that may enter into the module and
cause fiber damage. To do so, dummy modules may be installed or alternatively
flexible hosing or rigid piping can be connected from the feed to both permeate ports
and the concentrate port in place of the modules (see Figure 1). Flushing the system
prior to installation of the modules is critical for several reasons:
 To clear tanks and lines of debris and particulates that can get trapped into the
module and cause fiber damage.
 To check the performance of the pumps before start up.
 To check seals of valves, flanges, and various other connections and
components.
 To check the automation and sequences of the different modes of operation
without the risk of damaging the membranes as a result of programming error or
mechanical failure of equipment.
 To disinfect the system with the addition of a chemical to the feed, if needed.
TSB142.01 Page 5

Figure 1: Examples of rigid and flexible piping used for commissioning phase 1

If the plant has more than one rack, the flexible hoses and/or pipes must be used for
each rack. It is necessary to place the hoses at both extremities of each rack to ensure
an efficient rinse of the all the lines.

3.1 Cleaning and Disinfection


Ensure that the tanks are empty by cleaning the inside thoroughly and removing any
large items. Make sure to rinse and fill the feed tanks with clean water (i.e. potable or
city water). This will then be used to flush the pipes and common headers. Rinse/flush
the system for approximately 30 minutes at a feed piping velocity of 2.5 – 3.0 m/s (8.2 –
9.8 ft/s) to remove any debris trapped in the HYDRAcap® system.

For disinfection, a 10 ppm chlorine solution rinse can be performed (minimum contact
time of six hours, but 24 hours is recommended). This disinfection is intended to
eliminate any bacteria that may have formed after installation of the racks. It is best for
this solution to be prepared in both the feed tank and filtrate/CIP tank. It is
recommended to initially flush the system from the feed side using the feed tank and
then again from the filtrate side with the filtrate/CIP tank. The solution will need to travel
through all the piping, connections, and headers within the system. Once the soaking
time has elapsed, the system should be rinsed.

3.2 Testing the automation of the rack


Testing the automation with dummy modules verifies that correct valves and pumps
begin when called upon by the operator or program. It is important to also check pump
speeds, dosing pump rates, etc. at this time. The opening and closing of valves will
need to be physically verified for every sequence. Before beginning any tests, timers
and setpoints need to be set in the PLC. They are specific to the tests done with the
dummy modules. Please contact Hydranautics to determine these values where
necessary. The following sequences should be tested:
 Filtration
o Feed pump settings
o Valve positions
o Flow indicator and transmitter values
TSB142.01 Page 6

o Pressure indicator and transmitter values


 Filtration with concentrate (if applicable)
 Backwash
o Backwash pump settings
o Feed pump settings
o Valve positions
o Flow indicator and transmitter values
o Pressure indicator and transmitter values
 Chemically Enhanced Backwash with chlorine (CEB1)
o Dosing pumps injection settings
o Cleaning pump settings
o Valve positions
 Chemically Enhanced Backwash with caustic soda, if applicable (CEB2) (same
checks as CEB1)
 Chemically Enhanced Backwash with acid, if applicable (CEB3) (same checks as
CEB1)
 CEB1 + CEB2, if applicable (same checks as CEB1)
 Clean in Place with chlorine (CIP1) (same checks as CEB1)
 Clean in Place with caustic soda, if applicable (CIP2) (same checks as CEB1)
 Clean in Place with acid, if applicable (CIP3) (same checks as CEB1)
 Neutralization (if applicable)
 Membrane Integrity Test
o Valves positions
o Pressure and pressure transmitter values

NOTE: It is important to ensure that valves are opened prior to starting any pump
and pumps are stopped prior to closing any valves. Also, pressurization rates
during any sequence should be slowly ramped up and down at a rate of no more
than 0.25 bar/sec (3.6 psi/sec).

Once the sequences above have been checked and optimized, the sequencing cycles
should be tested. Check the recommended number of filtration and backwash cycles
TSB142.01 Page 7

prior to conducting a CEB1, CEB2, CEB3, and/or CEB1+CEB2 are correct. Any failure
should be noted and addressed immediately.

The following readings should be noted when testing the feed pump: pressure at the
discharge of the feed pump by reading the pressure transmitter value and flow rate
given by the filtrate flow transmitter.

4. PHASE 2 – INSTALLATION AND TESTING WITH MODULES

4.1 Analysis of the feed water

Preliminary samples will be taken to check the following parameters to see if they are in
line with the expected values: temperature, turbidity, total suspended solids, COD,
BOD, TOC, iron, manganese, aluminum, hardness, alkalinity, and pH

4.2 Receipt and Installation of Modules


All modules are tested at Hydranautics facility prior to shipping to determine the module
permeability and integrity. Modules are shipped with acceptable permeabilities and free
of integrity defects. Once the modules pass inspection, they are filled with a 0.95%
sodium bisulphite solution and ports are capped to retain the preservative. The
modules are then packed in wooden crates and shipped to site.

After completion of system testing, install modules according to TSB 132.

4.3 Membrane Integrity Testing (MIT)

After installing the modules, perform a MIT according to TSB 133.

4.4 Preserving the modules and/or system

If necessary, racks and/or modules may be stored by following TSB 131.


TSB142.01 Page 8

Clean Water Flux Profile Test

A clean water flux profile test is performed when the membranes are new or at any point
to test the permeability or temperature corrected specific flux (TCSF) of the membranes.
Please follow the procedures listed below to perform this test:
1. Supply clean tap water to the HYDRAcap® system. This can be done by filling a
feed tank or making the the proper connections for lines/piping.
2. For new or “long-term” stored membranes, flush the modules with the clean
water to remove the preservatives. The modules should be flushed at a flux rate
of 60 LMH (35 GFD) for 30 min to drain. For systems that cannot supply the
recommended flux rate above, longer flushings may be required. The modules
will need be flushed for 10 mins from feed to concentrate, 10 mins from feed to
filtrate + concentrate, and the last 10 mins from feed to filtrate.
3. Once the modules have been flushed, it is time to begin the clean water flux
profile test. Each rack should be individually tested. Run filtration cycles with the
clean water at 25%, 50%, 75%, and 100% of the design flow rate. Record the
feed pressure, concentrate pressure, filtrate pressure, trans-membrane pressure
(TMP), filtrate flow, and water temperature during each filtration cycle. It is
recommended to take at least four readings at various flow rates, but more can
be conducted if desired.

NOTE: The filtrate may also be sent at this time to the CIP tank to check the
water quality.

4. Calculate the TCSF at 20°C at each data point according to TSB 139. For new,
unused membrane modules, the average TCSF over all data points should be >
385 LMH/bar (15.65 GFD/psi). For used membranes, the average TCSF over all
data points should be > 172 LMH/bar (7 GFD/psi). If the minimum TCSF value is
not reached, the modules may need to be cleaned either with a CEB or CIP as
described in TSB 140 depending on the permeability found. If the module was
used, it is possible that there may have been some irrecoverable fouling that
occurred during operation. If the membranes still do not achieve the required
TSB142.01 Page 9

TCSF in clean water, pleast contact the Hydranautics Capillary Technology


Group.

After completion of the clean water flux profile test, data logging, normalization, and
performance analysis should be performed according toTSB 139.

5. PRECAUTIONS

In addition to other precautions given in the “notes” throughout the document, please
consider the following as well when operating a HYDRAcap® system:
1. Do not use silicone grease for lubrication in areas where it may remain internally
within the pipework, as the grease can irreversibly foul the membranes.
2. The maximum applied pressure rating for a HYDRAcap® module is 5 bar (73
psig).
3. The maximum transmembrane pressure (TMP) is 1.4 bar (20 psig).
4. The maximum instantaneous feed turbidity is 100 NTU.
5. The maximum instantaneous chlorine exposure is 100 ppm.
6. The operating pH range is 4 – 10, while the cleaning pH range is 1.5 – 13.
7. The maximum temperature rating of a HYDRAcap® module is 40°C (104°F). To
avoid thermal shock, temperature increases should be limited to a rate of change
of 1°C per minute.
8. Emulsified oil and grease should be < 2 ppm in the feed, free oil and grease must
be < 0.1 ppm.
9. A ≤120 µm screen filter is required directly ahead of the HYDRAcap® module(s)
regardless of pretreatment for seawater applications; a ≤150 µm screen filter is
required directly upstream of the modules for other applications.

Lenntech
info@lenntech.com
info@lenntech.com Tel.
Tel. +31-152-610-900
+31-152-610-900
www.lenntech.com
www.lenntech.com Fax.
Fax.+31-152-616-289
+31-152-616-289

You might also like