Hydranautics TAB142 L
Hydranautics TAB142 L
Hydranautics TAB142 L
01
1. INTRODUCTION
The goal of this document is to outline the general procedures for commissioning
HYDRAcap® rack(s). The document should provide sufficient information to aid in the
planning and sequencing of the commissioning process. For specific projects, an
independent check must be carried out as to its suitability. It specifies the various
implementation procedures including installing, cleaning, and testing the system. A
typical P&ID of a HYDRAcap® system can be provided upon request as a guideline for
system configuration and for determining the recommended amount of equipment and
instruments needed for a fully automated HYDRAcap® system. The details of
construction, equipment manufacturers, model numbers, and site specific drawings are
to be provided by the System Supplier.
The procedures discussed within this document are to be read in conjunction with the
System Supplier commissioning procedures. Construction completion activities must be
verified as complete before commissioning can start. Commissioning is carried out by
functionally testing each main process component of the HYDRAcap® plant offline. This
document is designed to be included in the overall commissioning plan for the plant.
TSB142.01 Page 2
2. PRE-COMMISSIONING ACTIVITIES
Immediately following the construction activities, the following items must be checked
prior to commissioning:
All construction should be completed prior to delivering and installing the modules to
prevent foreign matter (i.e. debris, dust, shavings, etc.) from entering the modules. If
there is a pre-treatment system prior to the HYDRAcap® system, it must be
TSB142.01 Page 4
It is important to clear all lines of any particulates that may enter into the module and
cause fiber damage. To do so, dummy modules may be installed or alternatively
flexible hosing or rigid piping can be connected from the feed to both permeate ports
and the concentrate port in place of the modules (see Figure 1). Flushing the system
prior to installation of the modules is critical for several reasons:
To clear tanks and lines of debris and particulates that can get trapped into the
module and cause fiber damage.
To check the performance of the pumps before start up.
To check seals of valves, flanges, and various other connections and
components.
To check the automation and sequences of the different modes of operation
without the risk of damaging the membranes as a result of programming error or
mechanical failure of equipment.
To disinfect the system with the addition of a chemical to the feed, if needed.
TSB142.01 Page 5
Figure 1: Examples of rigid and flexible piping used for commissioning phase 1
If the plant has more than one rack, the flexible hoses and/or pipes must be used for
each rack. It is necessary to place the hoses at both extremities of each rack to ensure
an efficient rinse of the all the lines.
For disinfection, a 10 ppm chlorine solution rinse can be performed (minimum contact
time of six hours, but 24 hours is recommended). This disinfection is intended to
eliminate any bacteria that may have formed after installation of the racks. It is best for
this solution to be prepared in both the feed tank and filtrate/CIP tank. It is
recommended to initially flush the system from the feed side using the feed tank and
then again from the filtrate side with the filtrate/CIP tank. The solution will need to travel
through all the piping, connections, and headers within the system. Once the soaking
time has elapsed, the system should be rinsed.
NOTE: It is important to ensure that valves are opened prior to starting any pump
and pumps are stopped prior to closing any valves. Also, pressurization rates
during any sequence should be slowly ramped up and down at a rate of no more
than 0.25 bar/sec (3.6 psi/sec).
Once the sequences above have been checked and optimized, the sequencing cycles
should be tested. Check the recommended number of filtration and backwash cycles
TSB142.01 Page 7
prior to conducting a CEB1, CEB2, CEB3, and/or CEB1+CEB2 are correct. Any failure
should be noted and addressed immediately.
The following readings should be noted when testing the feed pump: pressure at the
discharge of the feed pump by reading the pressure transmitter value and flow rate
given by the filtrate flow transmitter.
Preliminary samples will be taken to check the following parameters to see if they are in
line with the expected values: temperature, turbidity, total suspended solids, COD,
BOD, TOC, iron, manganese, aluminum, hardness, alkalinity, and pH
A clean water flux profile test is performed when the membranes are new or at any point
to test the permeability or temperature corrected specific flux (TCSF) of the membranes.
Please follow the procedures listed below to perform this test:
1. Supply clean tap water to the HYDRAcap® system. This can be done by filling a
feed tank or making the the proper connections for lines/piping.
2. For new or “long-term” stored membranes, flush the modules with the clean
water to remove the preservatives. The modules should be flushed at a flux rate
of 60 LMH (35 GFD) for 30 min to drain. For systems that cannot supply the
recommended flux rate above, longer flushings may be required. The modules
will need be flushed for 10 mins from feed to concentrate, 10 mins from feed to
filtrate + concentrate, and the last 10 mins from feed to filtrate.
3. Once the modules have been flushed, it is time to begin the clean water flux
profile test. Each rack should be individually tested. Run filtration cycles with the
clean water at 25%, 50%, 75%, and 100% of the design flow rate. Record the
feed pressure, concentrate pressure, filtrate pressure, trans-membrane pressure
(TMP), filtrate flow, and water temperature during each filtration cycle. It is
recommended to take at least four readings at various flow rates, but more can
be conducted if desired.
NOTE: The filtrate may also be sent at this time to the CIP tank to check the
water quality.
4. Calculate the TCSF at 20°C at each data point according to TSB 139. For new,
unused membrane modules, the average TCSF over all data points should be >
385 LMH/bar (15.65 GFD/psi). For used membranes, the average TCSF over all
data points should be > 172 LMH/bar (7 GFD/psi). If the minimum TCSF value is
not reached, the modules may need to be cleaned either with a CEB or CIP as
described in TSB 140 depending on the permeability found. If the module was
used, it is possible that there may have been some irrecoverable fouling that
occurred during operation. If the membranes still do not achieve the required
TSB142.01 Page 9
After completion of the clean water flux profile test, data logging, normalization, and
performance analysis should be performed according toTSB 139.
5. PRECAUTIONS
In addition to other precautions given in the “notes” throughout the document, please
consider the following as well when operating a HYDRAcap® system:
1. Do not use silicone grease for lubrication in areas where it may remain internally
within the pipework, as the grease can irreversibly foul the membranes.
2. The maximum applied pressure rating for a HYDRAcap® module is 5 bar (73
psig).
3. The maximum transmembrane pressure (TMP) is 1.4 bar (20 psig).
4. The maximum instantaneous feed turbidity is 100 NTU.
5. The maximum instantaneous chlorine exposure is 100 ppm.
6. The operating pH range is 4 – 10, while the cleaning pH range is 1.5 – 13.
7. The maximum temperature rating of a HYDRAcap® module is 40°C (104°F). To
avoid thermal shock, temperature increases should be limited to a rate of change
of 1°C per minute.
8. Emulsified oil and grease should be < 2 ppm in the feed, free oil and grease must
be < 0.1 ppm.
9. A ≤120 µm screen filter is required directly ahead of the HYDRAcap® module(s)
regardless of pretreatment for seawater applications; a ≤150 µm screen filter is
required directly upstream of the modules for other applications.
Lenntech
info@lenntech.com
info@lenntech.com Tel.
Tel. +31-152-610-900
+31-152-610-900
www.lenntech.com
www.lenntech.com Fax.
Fax.+31-152-616-289
+31-152-616-289