Quest Ccs Report
Quest Ccs Report
Quest Ccs Report
April 2023
Prepared by:
GHD Limited
Prepared for:
Shell Canada Limited, as Managing Partner and on Behalf of Shell Canada
Energy (an Alberta Partnership)
Version:
Final
RPT-2
Date:
April 27, 2023
Table of Contents
1.0 Summary of Offset Project ..................................................................................... 3
2.0 Introduction ......................................................................................................... 7
2.1 Objective ........................................................................................................... 11
2.2 Scope ................................................................................................................ 11
2.3 Level of Assurance .............................................................................................. 12
2.4 Criteria .............................................................................................................. 12
2.5 Materiality .......................................................................................................... 13
3.0 Methodology ....................................................................................................... 13
3.1 Procedures ......................................................................................................... 13
3.2 Team ................................................................................................................. 29
3.3 Schedule ............................................................................................................ 30
4.0 Results .............................................................................................................. 31
4.1 Assessment of Internal Data Management and Controls ........................................... 31
4.2 Assessment of GHG Data and Information .............................................................. 33
4.3 Assessment against Criteria .................................................................................. 48
4.4 Evaluation of the GHG Assertion............................................................................ 49
4.5 Summary of Findings ........................................................................................... 50
4.6 Opportunity for Improvement ............................................................................... 52
5.0 Closure .............................................................................................................. 52
5.1 Verification Statement ......................................................................................... 52
5.2 Limitation of Liability ........................................................................................... 52
5.3 Confirmations ..................................................................................................... 53
6.0 References ......................................................................................................... 55
Appendix A: Final Verification Plan and Sampling Plan ............................................................ 56
Appendix B: Statement of Qualifications................................................................................ 57
Appendix C: Findings and Issues .......................................................................................... 60
Appendix D: Statement of Verification .................................................................................. 64
Appendix E: Conflict of Interest Checklist .............................................................................. 67
Appendix F: Supplemental Diagrams/Tables/Figure ................................................................ 70
List of Tables
Table 1: Offset Criteria Assessment ...................................................................................... 48
Table 2: Summary of Findings ............................................................................................. 50
Table 3: Detailed Findings and Issues Log ............................................................................. 61
Page 2 of 70
Quest Carbon Capture and Storage Project
April 2023
Item Description
Offset Start Date The offset start date was August 23, 2015.
Offset Crediting Period The credit duration period is 20-years with on-
going five-year extensions as allowed by the
protocol. The initial credit period is therefore
August 23, 2015, to August 22, 2035, with
potential five-year extensions commencing
thereafter
Page 3 of 70
Quest Carbon Capture and Storage Project
April 2023
GHG Assertion (Actual Emission The total emissions offsets for the reporting
Reductions/Sequestration period were 715,416.00 tonnes CO2e
Achieved)
Page 4 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 5 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 6 of 70
Quest Carbon Capture and Storage Project
April 2023
2.0 Introduction
Shell Canada Limited, as Managing Partner and on Behalf of Shell Canada Energy (an Alberta
Partnership) (Shell) retained GHD Limited (GHD) to undertake a verification of the Quest
Carbon Capture and Storage (CCS) Project (Project) for the period of January 1, 2022 to
December 31, 2022 (Offset Project Report or OPR). The Project is registered with the Alberta
Emissions Offset Registry, registration number 7306-8118.
GHD completed the verification in accordance with the requirements of the Technology
Innovation and Emissions Reduction Regulation (Reg. 133/2019, TIER) and any promulgated
amendments, under the Emissions Management and Climate Resilience Act (Government of
Alberta, 2019). The applicable protocol for this Project is the Quantification Protocol for CO2
Capture and Permanent Storage in Deep Saline Aquifers, Version 1.0 (Alberta Environment and
Parks (AEP), June 2015) (Protocol). Shell is responsible for the preparation and fair
presentation of the OPR in accordance with the TIER. Celina Duong is GHD’s contact at Shell for
this verification.
GHD has prepared the Verification Plan and this Verification Report in accordance with the
ISO Standard ISO 14064 Greenhouse gases – Part 3: Specification with guidance for the
validation and verification of greenhouse gas assertions (ISO 14064 3) and with Alberta
Environemnet and Protected Areas (AEPA) Standard for Validation, Verification and Audit
(Alberta Environment and Protected Areas, 2023).
Offset Credit Project Boundaries
The Project consists of two separate components: the CCS capture facility and three injection
sites. The CCS capture facility is located at the Shell Scotford Site, and captures CO2 produced
from the hydrogen manufacturing units (HMUs) of the Scotford Upgrader Facility. CO2 is
absorbed from the raw gas stream through the use of a licensed Shell amine absorption system
(ADIP-X) in a scrubbing tower located at each of the three HMUs. The CO2-amine mixture from
each absorption system is then sent through a regeneration column, separating the CO2 from
amine. The CO2 stream undergoes dehydration (removal of water) and compression, and is
then transported via pipeline to the well pads. There are three injection wells, one per well pad.
Currently, two out of the three injection wells are in operation for sequestering the CO2
approximately two kilometres below ground.
The overall Project consists of emissions associated with the capture of CO2 and operation of
the CCS capture facility and injection wells. The operation of the Scotford Site consists of the
following facilities which, unless otherwise noted, are owned by the AOSP JV or Shell Canada
Limited, and operated by Shell:
Page 7 of 70
Quest Carbon Capture and Storage Project
April 2023
Geographic Boundaries
The Project is located at the following addresses:
CCS Facility
55522 Range Road 214
Fort Saskatchewan, Alberta
Latitude: 53.74047 N, Longitude 113.0231 W
Injection Wells
Well #1: 07 11 59 20 W4
Well #2: 08 19 59 20 W4
Well #3: 05 35 59 21 W4
Description of Project Baseline and Project Conditions
During the baseline condition, CO2 is produced in the hydrogen manufacturing units in the
Scotford Upgrader through the steam-methane reforming reaction, and is then emitted directly
to the atmosphere.
During the product condition, the CO2 produced in the hydrogen manufacturing units is
captured and separated from the raw gas stream by the CCS capture facility, compressed,
transported to the injection wells, and then sequestered underground. Emissions from the
project at the CCS capture facility include the following operations:
Page 8 of 70
Quest Carbon Capture and Storage Project
April 2023
Baseline Condition
B1 – Injected Y NA NA NA NA NA Y
CO2
Project Condition
P3 – Well Y Y Y NA NA NA Y
drilling
reportable
releases
P4 – NA NA NA NA NA NA Y
Production
and delivery
of material
inputs
P5/P6/P7 – Y Y Y NA NA NA Y
Extraction/
processing
and
transportation
of fuel used
for on-Site
and off-Site
heat and
electricity
generation
P8 – Off-Site NA NA NA NA NA NA Y
electricity
generation
P9 – Off-Site Y Y Y NA NA NA Y
heat
generation
P10 – On-Site Y Y Y NA NA NA Y
heat and
electricity
generation
P11 – CCS Y Y Y NA NA NA Y
facility
operation
P18 – Venting Y Y NA NA NA NA Y
of CO2 at
injection well
sites
Page 9 of 70
Quest Carbon Capture and Storage Project
April 2023
P19 – Fugitive Y Y NA NA NA NA Y
emissions at
injection well
sites
P20 – Y Y Y NA NA NA Y
Emissions
from
subsurface to
atmosphere
P21 – Loss, Y Y Y NA NA NA Y
disposal or
recycling of
materials
used in CO2
capture
process
• Ownership of the Athabasca Oil Sands Project Joint Venture (AOSP JV) (including both Quest
and the Shell Upgrader) changed on February 1, 2017. Prior to this date, ownership of the
AOSP JV was split between Shell Canada Energy (60%), Chevron Canada Limited (Chevron)
(20%) and Marathon Oil Canada Corporation (Marathon) (20%). Afterwards, CNUL
purchased Shell Canada Energy’s share of the AOSP JV, and CNUL and Shell jointly
purchased Marathon’s share (creating 1745844 Alberta Ltd.). Therefore, as of February 1,
2017, the ownership split was changed to CNUL (60%), Chevron (20%) and
1745844 Alberta Ltd. (20%), with CNUL and Shell each having 50% ownership of
1745844 Alberta Ltd. Shell remains operator of the Project.
• Starting in early September 2015, the values measured by the CO2 analyzer were found to
drifting lower than expected. This was identified to be the result of three issues:
- A manufacturer’s defect in the switching valve
- Low accuracy due to low volumes of injected gas into analyzer
- High sensitivity in the analyzer to barometric pressure
The above issues were fully resolved by February 3, 2017. Shell submitted and AEP approved a
variance request allowing alternative measurement methodologies be used while the analyzer
was not operational and supporting gas samples be collected of the gas stream. This did not
affect the calculations for the 2022 reporting period, as the analyzer was operational for the
reporting period.
• The initial methodology to quantify waste heat contributions to Quest steam was found to
be not in accordance with the Protocol during an AEP re-verification of the project
Page 10 of 70
Quest Carbon Capture and Storage Project
April 2023
• Project Description – The scope of the verification includes the greenhouse gas (GHG)
offsets resulting from the capture and underground storage of CO2 that would otherwise
have been emitted directly to the atmosphere.
• GHG Types – The claimed offsets result from reductions in CO2 released to the atmosphere
due to the Project. The emissions during the operation of the Project result from:
- The venting and fugitive releases of CO2 and CH4 from the Project.
- Releases CO2, CH4 and N2O due to combustion of fuels for Project operation and heat
and electricity requirements.
- Releases of CO2, CH4 and N2O from the production and/or loss, disposal or recycling of
the various chemical products and fuels required for the Project.
- Emissions from venting releases from drilling or construction
- Emissions due to loss of containment within the storage complex
• Time Period – January 1, 2022 – December 31, 2022
• Use of this Report - This report has been prepared for the use of Shell and AEP.
• Relative Size – The size of the claimed GHG reductions was 715,416.00 tonnes CO2
equivalent (tCO2e).
Page 11 of 70
Quest Carbon Capture and Storage Project
April 2023
• The accuracy of the reported data and calculated emissions, and that all data and emissions
accurately reflected the operation of the Project in the reporting period and are consistent
with the approved Offset Project Plan (OPP).
• The baseline and project conditions during the 2022 Reporting period were consistent with
the requirements of the Protocol and OPP
• The reasonableness of the emission estimation methodologies, assumptions, and results.
• Whether any errors in data, estimations or methodology were adequately managed,
documented, and either corrected or accounted for.
• Whether all measurement devices and sources of data are appropriate, well-maintained and
reading accurately.
• Whether the OPR is clear, well supported, and comprehensive.
• The reporting systems conform to relevant government-mandated or industry-standard
quality assurance procedures.
• The assertion refers to the emissions, from the sources and sinks reported by the Project
• ISO principles such as consistency, conservativeness, transparency, etc. are met by the
Project.
2.3 Level of Assurance
The verification was conducted to a reasonable level of assurance.
Reasonable assurance is a high level of assurance, or positive assurance. Reasonable assurance
is a direct factual statement expressing the opinion of the verifier. If a verification statement
can be provided, it is worded in a manner similar to "Based on our verification, the GHG
emissions statement is, in all material aspects, in accordance with the approved quantification
protocols."
2.4 Criteria
GHD assessed the Project against the following criteria:
• Occur in Alberta
• Result from actions not otherwise required by law and be beyond business as usual and
sector common practice
• Be real, demonstrable, quantifiable, and verifiable
• Result from actions taken on or after January 1, 2002
• Have clearly established ownership
• Be counted once for compliance purposes
• Be implemented according to a Government of Alberta-approved quantification protocol
• Be verified by qualified third-party
GHD has prepared this Verification Report in accordance with the ISO Standard ISO 14064
Greenhouse gases – Part 3: Specification with guidance for the validation and verification of
greenhouse gas assertions (ISO 14064-3) and the VVA Standard.
Page 12 of 70
Quest Carbon Capture and Storage Project
April 2023
For this verification, GHD applied the following ISO and AEP criteria:
• ISO 14064 Greenhouse gases-Part 2: Specification with guidance at the project level for
quantification and reporting of greenhouse gas emissions and removals, ISO, March 2006
(ISO 14064-2)
• ISO 14064 Greenhouse gases-Part 3: Specification with guidance for the validation and
verification of greenhouse gas assertions, ISO, April 2019 (ISO 14064-3)
• Emissions Management and Climate Resilience Act, Technology Innovation and Emissions
Reduction Regulation, Alberta Regulation 133/2019 (TIER) and amendments.
• Standard for Greenhouse Gas Emission Offset Project Developers, Version 3.1, AEP, 2023
• Standard for Validation, Verification and Audit, Version 5.2, AEP, 2023
• Quantification Protocol for CO2 Capture and Permanent Storage in Deep Saline Aquifers,
Version 1.0 (AEP, 2015).
• Carbon Offset Emission Factors Handbook, Version 2.0 (2019)
2.5 Materiality
As the total project offsets are more than 500 ktonnes of CO2e for each full calendar year,
quantitative materiality for this verification is set at absolute 2% of the OPR as per
Section 5.1.1 of the AEPA VVA Standard. In addition, a series of discrete errors, omissions or
misrepresentations or individual or a series of qualitative factors, when aggregated (absolute
values) may be considered material.
3.0 Methodology
The purpose of GHD's verification procedures was to assess the following critical items:
Page 13 of 70
Quest Carbon Capture and Storage Project
April 2023
Document Review:
• Review of data and information to confirm the correctness and completeness of presented
information.
• Cross checks between information provided in the OPP and OPR and information from
independent background investigations.
• Determine sensitivity and magnitude analysis for parameters that May be the largest
sources of error.
Follow-up Interviews:
• On Site
• Via telephone
• Via email
The GHD Project Team interviewed Project personnel to:
• Cross-check information provided by interviewed personnel, i.e., by source check or other
interviews.
• Compare with projects or technologies that have similar or comparable characteristics.
• Test the correctness of critical formulae and calculations.
• Review data management and recording procedures.
Through the document review GHD established to what degree the presented OPR meets the
verification standards and criteria.
The GHD Project Team's document review during the review process comprised an evaluation of
whether or not:
• The documentation is complete and comprehensive and follows the structure and criteria
given in the AEP guidelines and regulations.
• The OPR, and the emissions estimates therein, conform to the program criteria.
• The OPP and OPR are accurate, transparent and complete overview of the Project's GHG
emissions sources
• The methodologies used in the GHG emission inventory are justified and appropriate.
• The assumptions behind the inventory are conservative and appropriate.
• The GHG emission calculations are appropriate and use conservative assumptions for
estimating GHG emissions.
• The GHG information system and its controls are sufficiently robust to minimize the
potential for errors, omissions or misrepresentations.
• The frequency of, and responsibility and authority for, monitoring, measurement, data
recording activities and quality control/quality assurance/management control procedures is
sufficient.
GHD completed data checks from the data source(s) (meter, scale, etc.) through the plant data
management system to the GHG emissions data reports. A sample of raw data was collected for
recalculation. If errors or anomalies were identified that could lead to a material misstatement,
GHD requested further raw data samples to assess the pervasiveness of the errors or
anomalies.
Page 14 of 70
Quest Carbon Capture and Storage Project
April 2023
The specific verification tests conducted by GHD as Part of the audit included the following:
• Review of third-party data and reports
• Tracing of data from output back to the measurement device(s)
• Full recalculations of key GHG supporting data and emissions
• Reasonableness checks of the sources of data and calculation methodologies
The specific documents received by GHD as Part of the verification to conduct the verification
tests outlined above is provided in Appendix F.1.
Verification Steps
GHD adhered to the following schedule for this verification:
Verification Plan
Prior to completion of the site visit, GHD prepared a verification plan, including an overview of
the verification process, a risk assessment, a sampling plan and the site visit agenda. In the
sampling plan, GHD provided a comprehensive list of information and data requests. GHD
utilized a risk-based approach to select a sample size of data and information for each facility.
Site Visit
On February 8, 2023, Ms. Stephaney Davey (Verifier) and Bryan Rubie (Verifier) completed an
in-person site visit of the Project at the Scotford Site/Quest Capture Site. On April 6, 2023,
Mr. Sean Williams (Lead Verifier) and Stephaney Davey (Verifier) of GHD completed a in-person
site visit Site visit of the Project Injection Site. Ms. Celina Duong (Environmental Engineer) and
Mr. Brendan Barski (Site GHG Reporter) of Shell arranged the Site visit, provided an overview
of the Facility operations, answered verification questions, and coordinated data retrievals.
Mr. Barski and Ms. Duong were the primary staff members interviewed by GHD, and are
responsible for the preparation of the OPR. On the first day, Andrea Smitchz (Quest OSE) from
Shell also attended the site visit. Note that the Injection Site visit were conducted concurrently
with the Shell Chem Solar 2022 Offset TIER Report verification site visit. Member of AEPA were
also present for the Injection Site visit.
Page 15 of 70
Quest Carbon Capture and Storage Project
April 2023
GHD also interviewed the following Shell personnel during the two in-person site visits:
• Mark Rogers (Maintenance Tech Support), review of Quest metering and analyzers
• Trevor Pawlik (Operator), Injection Well #3 Operator
• Merisha Bily (Electrical Engineer), Electricity Meter tour
Issues Logs
During the course of the document review and interviews, questions and clarifications were
identified by the Project Team; these were communicated to Shell either verbally, by email, or
in an Issues Log sheet. Shell had an opportunity to respond to identified issues prior to the
completion of GHD's draft and final verification reports.
Page 16 of 70
Quest Carbon Capture and Storage Project
April 2023
Risk Assessment
Based on GHD's review of the Site operations, GHD prepared the following table, which summarizes the potential risk and
magnitude of potential errors, omissions, or misrepresentations:
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
Baseline Emission
B1: Injected 100% Occurrence High – Based on total Low – One meter Low GHD has set the
CO2 CO2 injected. Metering present at each detection risk as low,
points are required to be injection well, and one as GHD reviewed all
located as close to the composition CO2 injected
injection points as measurement system. measurements and
possible. Composition of All meter and analyzer composition data for
CO2 is understood to be data is stored within crediting period.
based on direct gas Shell’s PI system,
analysis; understood to while sampling data is
be additional manual stored in LIMS.
samples historically
collected. Potential
venting/fugitives after
metering point (at
Completeness injection points)
captured in project
condition.
Page 17 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
Project Emissions
P3: Well <1% Occurrence Low – only reportable if Medium – Emissions Medium GHD confirmed if any
Drilling gas is released during estimated based on reportable gas
Reportable Completeness kicks and blowouts of procedures as per AER releases from well
Releases wells as per the Alberta Directive 059. drilling occurred
Accuracy Energy Regulator (AER) during crediting
Directive 059. Emissions period.
during reportable
releases are quantified
using methodologies
defined in the
Directive 059 Reports.
Page 18 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P4: Production <1% Occurrence Medium – multiple Medium – based on Medium GHD reviewed total
and Delivery of materials used in CCS delivery and metered quantification of the
Material Inputs Completeness process. Quantities of quantities of the material inputs as well
each determined based different material as confirm
on delivery and metered inputs. All delivery appropriateness of
quantities. Emission invoices are stored on emission factors.
factors estimated based Shell’s servers, and Based on the size of
primarily on literature meter data is stored in the project emissions
references. Shell’s PI system. from previous
reporting periods,
Accuracy Low – based on delivery significant
and metered quantities discrepancies in
of the different material emissions for this
inputs. category are not
expected to result in
Classification Low – classification of offsets is well defined material error.
within the system.
Page 19 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P5, P6 & P7: 7.1% Occurrence High – Two types of High – Total quantities Low GHD reviewed
Extraction/ fuels used (natural gas of steam measured complete details of
Processing and Completeness and liquid fuels including based on multiple the steam balance
Transportation diesel, gasoline, and steam meters, along and confirmed total
of Fuel Used propane). Total natural with temperature and quantities of natural
for On-Site and gas usage based on pressure meters. gas used, as well as
Off-Site Heat complex steam balance. Liquid fuels determined liquid fuel invoiced
and Electricity Liquid fuels based on based on invoicing. quantities. GHD
Generation default emission factors Steam metering data is confirmed
for each fuel used. stored on Shell’s PI appropriateness of
system. emission factors.
Accuracy High – Complex steam
balance used to quantify
natural gas usage. Liquid
fuels determined based
on invoicing.
Page 20 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P8: Off-Site 20.7% Occurrence High – Multiple Medium – the majority Low GHD reviewed all
Electricity electricity meters and of electricity usage is electricity metering
Generation Completeness invoices (for electricity based on direct quantities. GHD
usage at wellpads) used metering. A confirmed
to quantify electricity small (<1%) quantity appropriateness of
usage by the Project. is estimated. Electricity emission factors.
Standard emission meter data is stored in
factors are used for both Shell’s PI system.
quest and grid-derived Electricity invoices for
electricity. wellpads stored on
Shell’s server.
Accuracy Medium – the majority
of electricity usage is
based on direct
metering. A small (<1%)
quantity is estimated.
Page 21 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P9: Off-Site 72.1% Occurrence High – Total natural gas High – Total quantities Low GHD reviewed
Heat based on steam balance of steam measured complete details of
Generation Completeness and back-calculation of based on multiple the steam balance
equivalent fuel gas steam meters, along and confirmed total
burned. Composition of with temperature and quantities of natural
natural gas based on pressure meters. gas used, as well as
third-party information Steam metering data is the third-party
stored on Shell’s PI composition data.
Accuracy High – Steam balance system.
used to quantify natural
gas usage.
Page 22 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P10: On-Site <1% Occurrence Low – based on total Medium – total fuel Medium GHD confirmed if any
Heat and invoiced propane, consumption based on on-site
Electricity Completeness methanol and metered invoicing (propane) propane/natural
Generation natural gas usage. and metering (natural gas/methanol
Accuracy Default emission factors gas). Invoices are consumption for heat
for propane, while stored on Shell’s or electricity
natural gas emission server. generation occurred in
factors calculated based crediting period.
on gas composition.
P11: Carbon <1% Occurrence Low – based on total Medium – total fuel Medium GHD reviewed total
Capture consumption of diesel, consumption based on quantification of fuel
Storage Facility Completeness gasoline and aviation invoicing. Invoices are usage as well as
Operation fuel, calculated based on stored on Shell’s confirmed
Accuracy direct measurement, server. appropriateness of
invoices or calculated emission factors.
based on kilometers Based on 1st crediting
driven. Default emission period project report,
factors for each fuel type significant
used. discrepancies in
Page 23 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
emissions for this
Classification Low – classification of offsets is well defined
category are not
within the system.
expected to result in
material error.
Transparency Medium - Calculations are completed in “black-
box” calculation model, although inputs and
outputs, along with methodologies are clearly
defined.
P18: Venting of <1% Occurrence Low – multiple vent Medium – multiple Medium GHD reviewed total
CO2 at event categories. Total vent event types can quantification of
Injection Well Completeness gas vented and occur, with different vented quantities and
Sites composition for each quantification methods composition of vented
Accuracy type based on either for each. Calculations gases. Based on 1st
engineering calculations for the vented crediting period
or direct measurements. quantities are project report,
performed on significant
spreadsheets stored on discrepancies in
Shell’s server. emissions for this
category are not
Classification Low – classification of offsets is well defined expected to result in
within the system. material error.
Page 24 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P19: Fugitive <1% Occurrence Low – total fugitive Low – based on known Medium GHD confirmed
Emissions at emissions on fitting equipment counts and equipment counts and
Injection Well Completeness counts and default measured gas gas composition. Based
Sites emission rates from each composition. on 1st crediting period
Accuracy type of fitting. Gas project report,
composition based on significant
measured injected gas discrepancies in
composition. emissions for this
category are not
Classification Low – classification of offsets is well defined within expected to result in
the system. material error.
P20: Emissions <1% Occurrence Low – emissions Medium – Shell’s PI and High GHD reviewed
from calculated only if a leak is LIMS systems are the documentation and
Subsurface to Completeness detected. Methodologies primary data storage methodology used to
Atmosphere to monitor subsurface location; however, some assess leaks from the
Accuracy storage of CO2 and leaks data is stored in subsurface to confirm
performed by Shell using alternative locations, whether leaks occurred
several methodologies at which is then manually during the crediting
multiple levels – each downloaded and period.
methodology is described transferred by Shell
in the Methodology, personnel. All data is
Monitoring and monitoring by Shell.
Verification Plan (MMV).
Page 25 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
P21: Loss, <1% Occurrence Medium – multiple Medium – based on Medium GHD reviewed total
Disposal or materials used in CCS delivery and metered quantification of the
Recycling of Completeness process that can potential quantities of the disposals as well as
Materials Used be disposed. Quantities of different material confirmed
each determined based on inputs. All delivery appropriateness of
disposal and recycling invoices are stored on emission factors. Based
estimates. Emission Shell’s servers, and on first crediting period
factors estimated based meter data is stored in project report,
on material balances. Shell’s PI system. significant
discrepancies in
Accuracy Low – based on delivery emissions for this
and metered quantities of category are not
the different material expected to result in
inputs. material error.
General
Page 26 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
Project NA Occurrence High – if the project quantification methodology Low GHD assessed the
Eligibility and deviates from the Protocol and the validation, it Project against the
Conformance Completeness would result in a non-conformance with the offset criteria to
with Project verification criteria. confirmed project
Plan and Accuracy eligibility.
Protocol
GHD reviewed the
Classification Project Report against
the Project Plan and
Transparency Protocol
Consistency
Page 27 of 70
Quest Carbon Capture and Storage Project
April 2023
Potential Risk Percentage of Attributes Inherent Risk Control Risk Detection Consideration for
Area (Sink and total Risk Design Procedure
Source) Baseline/
Project
Emissions
Use of ICT NA Occurrence Medium –The GHD project Medium – ICT Medium The majority of
team has previous technologies are activities were
Completeness experience in conducting available to both Shell conducted on-Site or
verifications for similar and GHD, when via desktop review, but
Accuracy project types. required. selected interviews
were conducted
Classification virtually. To lower the
detection risk, GHD
Transparency worked with Shell to
arrange meetings at
appropriate times for
Consistency
Shell operators and
staff to be available to
work through the
verification process and
provide sufficient time
to deal with potential
technical limitations.
Data NA Occurrence Medium – Majority of Medium – All data is Low The data management
Management quantities used for managed and tracked systems are present at
Completeness emission reduction are by Shell personnel. the Site. GHD reviewed
real-time data stored on Multiple systems are all data systems and
Accuracy PI or LIMS systems, or via used to track data. the flow of data
third-party invoices. between them.
Classification Some data for subsurface
emissions (P20) are from
Transparency additional data systems.
Consistency
The final sampling plan developed based on the risk assessment is presented in the final Verification Plan, included as Appendix A to this
report.
Page 28 of 70
Quest Carbon Capture and Storage Project
April 2023
3.2 Team
Roles and Responsibilities
Designated Signing Authority – Deacon Liddy – Mr. Liddy will review and sign the
verification report and statement.
Lead Verifier – Sean Williams – Mr. Williams will lead the verification and is responsible for
development of the verification plan. Mr. Williams will review the risk assessment, recalculation
of raw data, data management and draft findings. Mr. Williams will prepare the verification
statement and verification report. Mr. Williams conducted a site visit of the Project.
Verifier – Stepheney Davey –– Ms. Davey will develop and revise the verification plan and
sample plan, develop a risk assessment, recalculate raw data, review management of data
quality and prepare draft findings. Ms. Davey will conduct a site visit of the Project.
Verifier – Bryan Rubie –– Mr. Rubie will develop and revise the verification plan and sample
plan, develop a risk assessment, recalculate raw data, review management of data quality and
prepare draft findings. Mr. Rubie will conduct a site visit of the Project.
Peer Reviewer – Gordon Reusing – Mr. Reusing will conduct a peer review of the risk
verification plan risk assessment and verification report and findings.
Qualifications
Deacon Liddy, P. Eng. – Mr. Liddy is a Principal with GHD and an experienced GHG validator
and verifier, having completed over 100 GHG validation/verifications with 17-years of
experience. Mr. Liddy works with large industrial facilities, Provincial governments, and offset
project developers to complete risk-based verifications. Mr. Liddy has been the lead verifier for
completion of greenhouse gas verifications conducted on behalf of Alberta Environment for
emission offset projects for landfill gas, biomass, tillage, composting and fuel switching for
lumber kilns. Mr. Liddy has completed verifications of greenhouse gas emission intensity
baseline applications and annual compliance reports under the Alberta Specified Gas Emitters
Regulation and British Columbia Mandatory Reporting Regulation. Mr. Liddy is a professional
engineer in BC, Alberta, and Saskatchewan.
Sean Williams, P.Eng. – Mr. Williams is a Project Manager, GHG Lead Verifier and Technical
Expert and with over 10-years of experience in environmental consulting and is a licensed
Professional Engineer in the provinces of Alberta, Saskatchewan and Ontario. Mr. Williams has
experience in completing greenhouse gas verifications, permit applications, air and noise
compliance assessments, completion of annual inventory reports under various voluntary,
provincial and federal regulations across Canada. Mr. Williams is an accredited lead verifier
under the California Air Resources Board and Oregon Department of Environmental Quality.
Mr. Williams has significant air and GHG expertise in a variety of industrial sectors, including oil
sands extraction and upgrading, refineries, chemical plants, mining and mineral production,
power generation facilities, waste management and metals production. Mr. Williams serves as
the Greenhouse Gas Assurances Services (GGAS) Manager for GHD’s ANAB accreditation.
Stepheney Davey, M.Sc., E.I.T. – Ms. Davey is a junior engineer and member of the EHS
Compliance team with GHD. She holds a Master of Science degree in Chemical Engineering
from the University of Alberta. Ms. Davey has been involved with multiple GHG verifications in
various sectors under the Greenhouse Gas Industrial Reporting and Control Act in British
Columbia, The Management and Reduction of Greenhouse Gases in Saskatchewan and the
Technology Innovation and Emissions Reduction regulations in Alberta. She has also been
involved with reporting under the federal Output-Based Pricing System and national reporting
under the National Pollutant Release Inventory. Her experience includes a range of industries
including oil and gas extraction, production and upgrading, power generation, chemical
production, pulp and paper mills, and mining and mineral production facilities.
Page 29 of 70
Quest Carbon Capture and Storage Project
April 2023
Bryan Rubie, P.Eng. – Mr. Rubie has a Bachelor of Environmental Engineering from the
University of Guelph. Mr. Rubie has experience completing permit applications, air and noise
compliance assessments and completion of annual inventory reports for a number of industrial
facilities. Mr. Rubie has experience in greenhouse gas verifications under the Alberta Specified
Gas Emitters Regulation (SGER) and Carbon Competitiveness Incentive Regulation (CCIR) and
has acted as verifier for a number of projects. Mr. Rubie also has experience in completing
greenhouse gas reports for numerous oil and gas facilities as per the US EPA Greenhouse Gas
Reporting Program (GHGRP).
Gordon Reusing, M. Sc., P. Eng. – Mr. Reusing is a greenhouse gas (GHG) Lead Verifier,
Lead Validator, and Peer Reviewer with extensive experience including GHG programmes in
Alberta, British Columbia, Saskatchewan, Ontario, Quebec, Nova Scotia, California, and
programmes operated by the United Nations Framework Convention on Climate Change
(UNFCCC) Clean Development Mechanism (CDM), The Gold Standard, The Climate Registry
(TCR), the Carbon Disclosure Project (CDP), and Verra: Verified Carbon Standard (VCS). He has
completed numerous GHG quantification studies for the oil and gas sector, including upstream,
midstream and downstream facilities. Mr. Reusing has conducted GHG verifications as a Lead
Verifier, Technical Expert and Peer Reviewer in many jurisdictions, including, but not limited to,
British Columbia, Alberta, Ontario, Quebec, and Nova Scotia.
3.3 Schedule
The following presents the final verification schedule:
• Submit Verification Plan to Shell – January 31, 2023
• Shell Verification Plan review period – January 31 – February 2, 2023
• Request, receive, and review documents and raw data from Shell – February 15 –
April 2023
• Site Visit – February 8, 2023 (Capture Site), April 6, 2023 (Injection Site)
• Issues Log provided to Shell – February 16, 2023
• Issue draft Verification Report to Shell – April 24, 2023
• Issue final Verification Report and Statement of Verification – April 28, 2023
Page 30 of 70
Quest Carbon Capture and Storage Project
April 2023
4.0 Results
The verification results are presented in the following five subsections. Subsections 4.1 – 4.3
present the results of the verification procedures for the data integrity (4.1), Quantification
Methodologies and Quantification (4.2), and Boundary Conditions and Activity Data (4.3).
4.1 Assessment of Internal Data Management and Controls
Summary of Data Management and Controls Procedures
The total quantities of emissions from the various baseline and project sources and sinks are
determined based on either direct measurement, third party data, and/or engineering
estimates.
The data management system used by Shell is built upon the existing systems at the Scotford
Site, and is based on a network of Data Focals. The Data Focals consist of various personnel
responsible for the collection and maintenance of data at key measurement points. Each Data
Focal collects the required data for each unit and completes required review and QA/QC on a
monthly basis. Once the data is confirmed, it is supplied to the Shell Environment Department.
Meter and analyzer data is collected from the measurement points by the Distributed Control
System (DCS), and then stored in the Process Information (PI) system. The final meter data is
stored within the PI system. All meters involved have specified standards and practices to
control uncertainty, including calibration and preventative maintenance activities. Data is stored
for at least seven year's past the end of the project reporting period.
At the injection sites, most of the data is integrated with the DCS/PI systems with the exception
of the distributed temperature sensors in the injection wells; this data is stored in separate
storage located on each well during the 2022 reporting period, then transferred for archiving.
Additional data comes from third-party data. These files are received by the relevant personnel
and sent to the Environment Department for storage.
The Data Focal collects all key data and enters this data into the Shell Environmental Reporting
System (SERS), which is the Site’s emissions calculation software. The data and outputs from
the SERS software is reviewed monthly, quarterly and yearly to ensure accuracy.
Findings and Conclusions
Flow of Data
GHD verified that the flow of data from the meters/analyzers through to the SERS system was
appropriate, and could verify that the raw readings from the meters are appropriately
transferred.
GHD noted that the use of the SERS system removes some transparency, as the actual
calculations used can be difficult to review (as opposed to an excel system, which allows for
easy reading of the formulas). The inputs and outputs along with the calculation formulas from
the system can be downloaded, which GHD reviewed and confirmed were appropriate.
Therefore GHD was able to determine that SERS was calculating emissions in accordance with
the Project Plan.
The use of Data Focals to collect and review source-specific data is appropriate. There is some
risk due to the separate responsibilities of these Data Focals. GHD has confirmed that the
Focals interviewed as Part of the verification were knowledgeable in the specific tasks required,
however, there were some issues in transfer of data as a result of the Data Focals, mainly
found while verifying electricity (P8).
Page 31 of 70
Quest Carbon Capture and Storage Project
April 2023
Meter Calibrations
Multiple gas flow, steam and electricity meters are used as Part of the data measurement and
collection for the project (in particular the B1 injection CO2 and P9 heat generation categories).
All meters are subject to Shell’s preventative maintenance (PM) program, and a minimum
calibration frequency of annual has been set for all transmitters identified as “key” for the
purposes of the Quest project.
As Part of the verification, GHD received the following calibration records (some directly used in
the calculation of baseline/project emissions):
FIT-702104 – CO2 injection in Well #1 (July 6, 2022)
FIT-702204 – CO2 injection in Well #2 (July 6, 2022)
FIT-702304 – CO2 injection in Well #3 (July 6, 2022)
FIT-247004 – CO2 injection metered at capture site (February 24, 2022)
FT-246005, FT-246006, FT-246120 – LP steam to Quest (July 27, 2022)
FT-248001 – (August 18, 2021)
FT-248004 – HP steam to Quest (June 29, 2022)
FT-246085– condensate return flow from Quest (August 18, 2021)
FT-251020A – HP steam pressure to Quest (September 30, 2019)
PI-246065 – condensate return from Quest pressure (October 9, 2019)
PT-241062/PT-242062 – HP-IP letdown pressure (November 25, 2019)
PT-247025 (March 8, 2018)
TT-251084 – High Pressure steam to Quest (July 7, 2022)
TI-246050 – condensate return from Quest temperature (September 3, 2021)
TT-247058 (March 2, 2020)
PV-251020A/B – Pressure relief values for HP-MP letdown (July 22, 2022)
PV-251022A – Pressure relief values for LP steam pressure to Quest (September 30, 2019)
FI-246094 – Nitrogen distribution meter (August 18, 2021)
52-15B (Quest Main power) and 52-16B (Compressor power) – Shell has indicated these
meters do not have documentation and do not need to be calibrated.
GHD has reviewed each of the above calibration records, and confirmed that they were
appropriate. There is no specific calibration frequency currently defined for steam meters, this
is not a specific deviation with the protocol, and the impact on emissions is minimal.
The calibrations without documentation have been noted as Item 22-05 in Appendix C.
Conclusion
GHD reviewed available meter calibration records for the meters. Multiple meters were not
calibrated; this will not result in a material misstatement.
Page 32 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 33 of 70
Quest Carbon Capture and Storage Project
April 2023
Continuous measurement of gas flow (defined as The meters record data at a greater than
one measurement every 15-minutes). 15-minute measurement rate. For the
purposes of calculating baseline
emissions, meter data is aggregated on
an hourly basis.
Meter readings May be temperature/pressure As the meters are Coriolis mass flow
compensated to standard temperature and meters, compensation is not required.
pressure.
The flow meters must be placed based on GHD has confirmed the meters were
manufacturer’s specifications installed per manufacturer’s
recommendations.
Must be placed downstream of the input to the GHD has verified that the location of the
gas transport equipment such that they are injection meters are as close to the
downstream of the capture and compression injection wellheads as possible,
equipment to account for fugitives and venting downstream of the gas transport
equipment.
Flow meters should be as close as possible to
injection wellheads to ensure accurate
measurement of injected volumes
Flow meters must be calibrated according to GHD has confirmed that the meters are
manufacturer’s specifications, and must be calibrated on a yearly basis per
check/calibrated at regular intervals according to manufacturer’s specifications. As noted
these specifications and industry standards above, GHD has confirmed the
calibrations were performed properly.
Ownership must be clearly documented for CO2 Not applicable, as both the CCS Capture
transferred (third-party injection activity). and Injection sites are owned/operated by
the AOSP JV/Shell.
Based on GHD’s review, the total quantity of gas injected along with the meters used to
measure these quantities are appropriate and in accordance with the Protocol requirements.
Quantification of Injected Gas Composition – Analyzer Measurements
As defined by Shell in the OPP, the injected gas composition (specifically CO2, methane (CH4),
hydrogen (H2) and water (H2O)) is measured via a continuous online gas analyzer, located at
the Quest CCS Facility (specifically located on the suction side of the seventh stage
compressor). This analyzer measures data on a continuous basis (at a rate greater than once
every 15-minutes), which is then aggregated by Shell on an hourly basis for the purposes of
calculating GHG emissions. This is in accordance with the Protocol.
Issues were identified in the analyzer just after installation, which required updates. While
these issues have been resolved, Shell does conduct additional analysis of the CO2 injected
stream, including grab samples analyzed both on-Site and via a third-party laboratory. These
analysis are in addition to the protocol requirements.GHD has confirmed that the composition is
determined in accordance with the Protocol.
Calculation Methodology for Emissions
The Protocol requires that the Injected CO2 be calculated as per the equation listed in
Section 4.1, Table 6, Part B1. GHD notes that this equation is specifically based on volumetric
Page 34 of 70
Quest Carbon Capture and Storage Project
April 2023
flowrates and compositions for gas injected and CO2 composition. The use of mass flowrates
and composition is not a deviation from the protocol as noted above, and the methodology used
by Shell is functionally equivalent to Protocol equation (just on a mass rather than volume
basis). Therefore GHD has verified that the calculations are completed in accordance with the
Protocol.
Recalculations
Based on the provided information, GHD has recalculated the B1 - Injection CO2 emissions.
These recalculations have yielded a difference of 25.18 tonnes CO2e, <0.01% of total baseline
emissions and <0.01% of total reductions, which is not material. This has been noted as
Issue 22-01.
P3 – Well Drilling and Construction Activities
GHD has confirmed that all well drilling and construction activity venting occurrences are
reported and calculated based on the Protocol and Directive 059 requirements. During the 2022
reporting period, Shell did not report any emissions from well drilling activities. GHD has
confirmed there were no venting events due to well drilling during the 2022 reporting period,
therefore this is appropriate.
P4 – Production of Material Inputs
The following materials are included as Part of the Project:
• Utility/Instrument Air
• Nitrogen
• Methyl diethanol amine (MDEA)
• Antifoam
• Activated Carbon
• Water
• Lubricant
• Refrigerants
• Caustic Soda
• Refridgerants (HFCs)
Consumption of Material Inputs
For MDEA, antifoam, activated carbon, lubricants, refrigerants and caustic soda, emissions are
based on top-ups and purchases of each material, with the purchased quantities equal to the
used amount during the reporting period. GHD notes that the actual consumption amounts may
be different than the shipment amounts; given the low amount of emissions associated with
this source, this will not result in a material discrepancy in the claimed reductions. For the 2022
reporting period, Shell claimed material purchases of 27,100 kg of caustic soda and 8960 kg of
triethylene glycol (TEG), which GHD verified as appropriate.
Shell also reported a three periods of refrigerant (HFC401a) leaks for the 2022 reporting year
which was then added to the Quest site. Shell originally missed these HFC leaks in their original
SERS report. This has been noted in Issue 22-02.
The consumption of nitrogen is estimated with a combination of metered quantities and
engineering estimates. Much of the nitrogen flow is below meter detection thresholds, requiring
engineering calculations to estimate these flowrates. GHD has reviewed the estimation for
nitrogen and confirmed that it is conservative and appropriate. A small quantity of nitrogen is
also used at the wellpads, contained in bottles which are tracked by the field operators based
Page 35 of 70
Quest Carbon Capture and Storage Project
April 2023
on deliveries. The total quantities of nitrogen at the wellpads is estimated based on the
purchased quantities of nitrogen bottles. Shell has omitted the Project’s nitrogen usage for the
month of May in their original SERS report. This Issue has been noted in Issue 22-03.
Utility/instrument air consumption is estimated based on the maximum design flow rate of
instrument air in the Quest project. This estimation method will give a conservative maximum
air usage rate, and therefore a conservative estimation of project emissions. The estimated
amount of instrument air used is 5,594,000 m3.
Water is based on direct metering of the wastewater treated on-Site. It is noted there are no
emissions associated with the production of wastewater (as all water is sourced from local
water bodies).
Emission Factors for Material Inputs
For instrument and utility air, as air is supplied primarily by electric-driven compressors, the
emissions associated with its production are based on the rated power for the compressor and
air supply rate (0.597 MW of power divided by 4,500 sm3/hr = 1.327x10 3 MWh/sm3), which is
then multiplied by the Alberta grid emission factor for increased on-Site grid electricity usage
(0.64 tonnes CO2e/MWh). GHD has confirmed that this calculation is appropriate, and that the
correct grid factor has been used.
For other material inputs, Shell has utilized academic or related data to derive emission factors
for the various materials. For example, the nitrogen emission factor has been derived based on
a nitrogen production factor of 1.093 MWh/tonne N2 published by the US Office of Technology
Assessment, and the Alberta grid factor (since in this specific case, nitrogen is supplied by the
Air Liquide Facility located on the Scotford Site). In some cases, no direct primary or secondary
emissions data is available, so a reasonable analogue has been used; for example, data to
calculate an emission factor for MDEA was not readily available, so a factor for monoethylamine
(MEA) was derived and has been assumed to apply to MDEA (along with any other future amine
solvents). GHD has reviewed the derivation of each material input emission factor, and has
determined that the factors calculated are reasonable and conservative.
Calculation Methodologies for Emissions
The Protocol requires that the emissions be calculated as per the equation listed in Section 4.1,
Table 6, Part 4. GHD has confirmed that this equation is used by Shell.
GHD has confirmed that the Protocol has no specific quantification requirements for the
calculation of material consumptions.
Recalculations
Based on the provided information, GHD has recalculated P4 emissions. GHD identified a
difference of 0.5 tonnes contributing to a total error in project emissions of 0.2%
(underreported) and a total error in reductions of 0.01% (overreported). This difference is likely
due to rounding. This difference is not material. This has been noted as Item 22-01.
P5/P6/P7 – Extraction/Processing of Fossil Fuels for Off/On-Site Electricity/Heat
Generation
Two fossil fuels are combusted for off/on-Site electricity/heat generation; natural gas (used for
both on and off-Site heat generation), and methanol (on-Site only).
Consumption of Fuels
The total consumption of natural gas/methanol and GHD’s findings is documented in the
findings for P9 (off-site heat generation) and P10 (on-site electricity and heat generation).
Page 36 of 70
Quest Carbon Capture and Storage Project
April 2023
• Quest Capture Site: Electrical sources (amine pumps transformers, heat tracer
transformers, etc.) are calculated based on the maximum design ratings for electricity
usage for each equipment. The compressor motor power (52-16B) and one for the main
Quest power (52-15B), however, frequently receive electricity from Cogen as discussed
further later in this section.
1
Greenhouse gas emissions from global shipping, 2013–2015, The International Council on
Clean Transportation, https://www.theicct.org/publications/GHG-emissions-global-shipping-
2013-2015
Page 37 of 70
Quest Carbon Capture and Storage Project
April 2023
• Quest Injection Site: Total electricity at each of the three injection sites is metered based on
third-party utility meters. Electricity invoices is provided to Shell’s accounting department,
who store all invoice data and provide the final monthly values.
In addition, the following two sources of electricity at the Quest Project are assumed by Shell to
be sourced via Upgrader Cogen. However, during periods that GT cannot provide enough
electricity to these sources, electricity is imported from the grid. GHD has confirmed the
method used to calculate the amount imported versus provided by the GT is acceptable.
• Quest Capture Site: The majority of electricity at the Capture Site is measured via two
electrical meters, one for the compressor motor power (52-16B) and one for the main Quest
power (52-15B). The summation of these two meters provides the majority of total Quest
electricity.
• Upgrader Electricity: There is an incremental increase in cooling water circulation in the
Upgrader due to the implementation of the Quest Project; this increase in water increases
the load in the cooling towers, and as a result requires additional electricity generation.
Shell This electricity increase is based on engineering estimates. Electricity usage is
estimated based on the measured usage of the cooling towers, rated fan speed, measured
total cooling water usage rate (on a daily basis) and the rated cooling water requirements of
the Quest Project, as follows:
𝑄𝑄𝑄𝑄𝑄𝑄𝑄𝑄𝑄𝑄𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤
𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐶𝐶𝐶𝐶 = 𝐹𝐹𝐹𝐹𝐹𝐹 𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 ∗ %𝐹𝐹𝐹𝐹𝐹𝐹 𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿 ∗
𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤𝑤
GHD notes that for the unmetered quantities there is some risk that the values are not
necessarily representative of total electricity, as they are based on estimates as opposed to
direct metering.
During GHD’s review of the Cogen electricity, GHD found that Shell accounted for the electricity
from the cooling tower fan twice. Cooling tower electricity is counted as a Part of Cogen
calaculations which was the summation of compressor motor power, main Quest power, and
cooling water tower electricity. Shell also had included cooling tower electricity as a standalone
value in SERS. This has been noted as Issue 22-04. Shell has since remediated this issue.
As Cogen electricity is used to partially power the Quest Project, Shell requested permission to
use an emission factor other than grid-derived electiricty for the portion sourced from the
Cogen. The Alberta Environment and Parks (AEP) provided a re-approval on February 28, 2023,
for a deviation request to use the Technology Innovation and Emissions Reduction (TIER)
Electricity Benchmark of 0.37 tonnes CO2e/MWh for directly connected electricity given all the
protocol requirements are met. The protocol has several conditions which must be met to use
an electricity emissions factor other than grid. The measurement requirements for off-Site
electricity generation are specified in the Protocol, Section 5.1.2, Table 9. These requirements
and Shell conformance with the requirements are summarized below:
Page 38 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 39 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 40 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 41 of 70
Quest Carbon Capture and Storage Project
April 2023
Recalculations
Based on the provided information, GHD has recalculated P10 emissions. These recalculations
have yielded a difference of 0.28 tonnes CO2e, <0.01% of total project emissions
(underreported) and <0.01% of total reductions (overreported). This difference is not
attributable to any specific discrepancy and not material. This has been noted as Item 22-01.
P11 – CCS Facility Operation
There are three main fuels used to operate the CCS Facility; Gasoline/Diesel for vehicle usage,
and Aviation Turbo fuel for light aircraft involved in pipeline inspections.
Consumption of Fuels
The total consumption of diesel, gasoline and aviation turbo fuel are tracked on a monthly basis
by the Shell accounting department. Shell reported no aviation turbo fuel use for this reporting
period. The use of each of these records are appropriate.
Diesel and gasoline usage by the various contractors were estimated based on tracked vehicle
kilometres driven and fuel economy factors from the API Compendium, Table 4-13. The
gasoline usage by the two main Shell employees are tracked via Cardlock and fuel receipts.
GHD has confirmed the above methods for diesel/gasoline are reasonable and conservative.
Emission Factors
The emission factors for diesel and gasoline are taken from the EF Handbook, Table 7, while the
emission factors for aviation turbo fuel are from the most recent Version of the NIR. These
sources are appropriate. There were no other Protocol-specific requirements.
Recalculations
Based on the provided information, GHD has recalculated P11 emissions. These recalculations
have yielded a difference of 0.52 tonnes CO2e, <0.01% of total project emissions
(overreported) and <0.01% of total reductions (underreported). This difference is not
attributable to any specific discrepancy, and is not material. This has been noted as
Item 22-01.
P18 – Venting at Injection Sites
Venting occurring as Part of the Project includes well head blowdowns, surface casing venting
and well workover vents.
Calculation of Gas Vented
For blowdown and workovers, vented quantities are estimated for each venting event and
tracked in the mass balance spreadsheet. No blowdown or workover venting occurred during
the reporting period.
Surface casing venting is estimated based on the results of yearly vent rate measurements for
each well. The Alberta Energy Regulator (AER) requires Shell to test for surface casing vent gas
(SCVG), which is reported under P18, and gas migration at the injection wells on a periodic
basis, and Shell has performed this test in June of every year to date. The most recent test was
completed in June 2022, which was assumed to occur at a constant rate based thereafter.
Assuming a constant venting rate based on the vent rate measurement test is a conservative
estimation method, and is appropriate.
Composition of Vented Gas
The composition of the surface casing vent gas is determined based on the sampling conducted
during the vent rate measurement tests for each well. The sampling of the well surface casing
vent gas is appropriate.
Page 42 of 70
Quest Carbon Capture and Storage Project
April 2023
Calculation Methodologies
The Protocol requires that the emissions be calculated as per the equation listed in Section 4.1,
Table 6, Part P18. No issues were identified.
Recalculations
Based on the provided information, GHD has recalculated P18 emissions. These recalculations
have yielded a difference of 0.43 tonnes CO2e, <0.01% of total project emissions and total
reductions (overreported in Project emissions, underreported in Reductions). This difference is
primarily due to rounding and is immaterial. This has been noted as Item 22-01.
P19 – Fugitive Emissions at Injection Sites
Fugitive emissions include passive venting from fittings (after the CO2 Injection Meters) and gas
migration venting.
Emissions from Fittings
The count of fittings at each well pad were completed at project outset. Emission rates are
based on the published emission factors published in the American Petroleum Institute
“Compendium of Greenhouse Gas Emissions Methodologies for the Oil and Natural Gas
Industry” (API Compendium), Tables 6-4 and 6-12. These emission factors are for total organic
compounds – to convert to CO2, equation 6-10 of the API compendium (multiplying by the
square root of the ratio of the CO2 and CH4 molecular weights) is applied. TetraTech had
previously noted that the API rates are not corrected based on the actual gas composition;
Shell has indicated that this methodology conservatively overestimates emission rates. Since
the fugitive emissions are small relative to total project emissions (<0.01% of project
emissions) and are conservative, GHD has confirmed these are appropriate.
Gas Migration Emissions
The fugitive releases from gas migration are calculated similarly to surface casing venting,
using the surface casing vent gas volumes (measured based on a once/year test done in June
2022) and the composition of the gas migration based on the annual tests. GHD has confirmed
this is appropriate.
Calculation Methodologies
The Protocol requires that the emissions be calculated as per the equation listed in Section 4.1,
Table 6, Part P19. No issues were identified.
Recalculations
Based on the provided information, GHD has recalculated P19 emissions. These recalculations
have yielded a difference of 9.90 tonnes CO2e, <0.01% of total project emissions
(overreported) and <0.01% of total reductions (underreported). This difference is not material.
This has been noted as Item 22-01.
P20 – Emissions from Subsurface
Protocol Monitoring Requirements
The specific Measurement, Monitoring and Verification (MMV) requirements for emissions from
subsurface are outlined in the Protocol, Section 5.1.3. These requirements and Shell’s
conformance to them are listed below:
Page 43 of 70
Quest Carbon Capture and Storage Project
April 2023
The project must have an MMV which is specific Approved MMV is specific to Quest storage
to the storage complex complex
The MMV must be prepared in accordance with
MMV is prepared in accordance with AER
the requirements of the AER, and must
requirements, and lists specific operating
demonstrate the project operates in accordance
license requirements. MMV details when
with the operating license. The MMV must be
updates are required.
updated as required by the AER.
MMV requirements apply to the following four All four project phases are described in MMV,
project phases: with required monitoring and reporting
• Pre-Injection – characterization and outlined.
identification of risks, select monitoring
approach, and acquire baseline data
• Injection – monitoring of activities to manage
containment, and update as needed to ensure
effectiveness
• Closure – monitor to manage containment
risk and demonstrate permanent storage
• Post-Closure – monitoring requirements are
transferred to the Government of Alberta to
ensure storage is behaving in stable and
predictable manner
Page 44 of 70
Quest Carbon Capture and Storage Project
April 2023
• Tier 1 technologies: Address critical risks to loss of containment through direct, continuous
monitoring. These technologies monitor data closest to the Storage Complex or along the
wellbore with immediate action to address any trigger events. These barriers are actively
maintained.
• Tier 2 technologies: Address potential critical risks to loss of containment, though less
directly tied to the Storage Complex. These technologies have a longer sample time or
surveillance frequency, with analysis and longer response time to the trigger event. These
barriers are actively maintained.
• Tier 3 technologies: Contingency based monitoring that can be triggered as a potential
response to Tier 1 or Tier 2 based monitor activities. Discontinuous monitoring or frequency
of analysis may occur, with some technologies requiring re-deployment if triggered.
Comprehensive baseline data (ie InSAR, GW discrete sample profiles) can be utilized for any
trigger events that re-establish utilization of Tier 3 technologies.
Trigger events indicate the need for greater review when they occur. The trigger response plan,
as indicated in the Integrated Response Plan (IRP) is specific to each monitoring technology but
typically involves reviewing the data and data management system to first ensure that the
trigger event is ‘real’. Once confirmed to be a ‘real’ event, other monitoring technologies are
incorporated and reviewed to develop an explanation or set of potential explanations for the
Page 45 of 70
Quest Carbon Capture and Storage Project
April 2023
event. Should the review result in the determination that conformance and containment
performance are not anomalous, routine monitoring may continue. Should an anomalous result
be obtained, a site-specific study may need to be initiated. Measures are then proposed and
evaluated to resolve the Issue through the site-specific study. Any impact to the emission
reduction inventory will be reported through the site-specific study and are the inputs to this
quantification plan.
The results from all monitoring is summarized in quarterly reports. An annual status update
report detailing the yearly monitoring results, status of the MMV plan and future activities is
also prepared.
Monitoring Conducted for 2022 Reporting period and Results
GHD reviewed the P20 (Emissions from Subsurface to Atmosphere) quarterly reports and the
2022 Calendar Year Verification report of the Quest MMV Program and found that the data does
not indicate loss of containment. There were however, two Tier 1 trigger events reported, and
they have been addressed.
As Part of the approved MMV plan, the assessment of trigger events based on a tiered system
are used to help determine if there is a possible loss of containment of CO2 from the Basal
Cambrian Sand Formation.
The first trigger occurred in Q2 and was due to BHP (bottom hole pressure) gauge data,
erroneously reading below 20 Mpa on the Basal Cambrian Sand (BCS) injection well, IW 7-11.
The reason for this was due to a faulty gauge. This has been rectified in July 2022.
Another well, IW 8-19 also began having erroneous BHP Gauge readings in Q2, but they were
not recorded below 20 Mpa. They have been troubleshooting the problem through the end of
the year. As a result, additional alarms on surface pressure have been put in place to ensure no
BHP maximums are not exceeded while working the issue.
The second trigger event occurred in Q4 on the deep monitoring well DMW 8-19 which monitors
the pressure in the above Cooking Lake Formation. The pressure increase was observed after
completing a well intervention, but the pressure continues to fall off towards baseline pressure.
The pressure increase was due to adding fluid during fishing operations.
Thus, no emissions have been identified as a result of these two trigger events
In the Tier 2 level technologies utilized for MMV in 2022, including DTS temperature sensing,
casing inspection logs, packer isolation tests, and MSM microseismic monitoring, there were no
trigger events. Therefore, no emissions have been identified from the subsurface.
GHD Assessment
GHD has been provided the Q1-Q4 2022 quarterly summary reports, along with the current
MMV plan. GHD has reviewed the monitoring activities and results. GHD has confirmed that
Shell has met the requirements of the protocol for monitoring.
Based on GHD’s review, the monitoring program utilized by Shell to monitor the subsurface
emissions of CO2 is very comprehensive and detailed, with multiple levels of monitoring from
the reservoir itself up to the atmosphere. This detailed monitoring allows multiple levels of
redundancy in both the detection and quantification of potential leaks from the subsurface.
With respect to the 2022 reporting period, GHD has confirmed that the requirements of both
the protocol and Shell’s MMV plan have been met, and that the assertion of zero emissions from
the subsurface for the 2022 reporting period is reasonable.
Page 46 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 47 of 70
Quest Carbon Capture and Storage Project
April 2023
The reduction or sequestration must The Quest CCS Facility is located at the Shell
occur in Alberta; Scotford Site, located near Fort Saskatchewan,
Alberta. The injection wells are located 50 to
80-km from the CCS Facility, and are all located
in Alberta.
The reduction or sequestration must The Project start date was August 23, 2015,
(i) result from an action taken on or upon commencement of CO2 injection
after January 1, 2002, and
(ii) occur on or after January 1, 2002;
The reduction or sequestration must be The project sequesters CO2 emissions produced
real and demonstrable; from the hydrogen manufacturing units that
would otherwise have been released to
atmosphere. GHD confirmed that the CCS
Facility and Injection Sites are in place and
operational, and resulting in actual avoidance of
CO2 emissions to atmosphere.
The reduction or sequestration must be As noted in Sections 4.1 and 4.2 above, GHD
quantifiable and measurable, directly or has verified that the baseline and project
by accurate estimation using replicable emissions are quantified based on approved
techniques; protocol methodologies (with the exception of
the approved AEP deviation)
The specified gas emissions that were GHD has verified the specified gas emissions
reduced or the carbon dioxide that was that were reduced or the carbon dioxide that
sequestered must not have had an was sequestered must not have had an effect
effect on the determination of a on the determination of a regulated facility’s
regulated facility’s total regulated total regulated emissions.
emissions under Section 13(3) or (4).
Page 48 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 49 of 70
Quest Carbon Capture and Storage Project
April 2023
Result Type Summary Description of Finding Understatement Tonnes CO2 eq Tonnes CO2 eq
# Source Category or Source/Sink /Overstatement % net % absolute
Page 50 of 70
Quest Carbon Capture and Storage Project
April 2023
Result Type Summary Description of Finding Understatement Tonnes CO2 eq Tonnes CO2 eq
# Source Category or Source/Sink /Overstatement % net % absolute
GHD reviewed all process data used to
develop the baseline/project sources.
None of these discrepancies are
material, and the overall difference is
less than the materiality threshold.
Overall difference is 0.06%, less than
the materiality threshold.
22-02 Quantitative Shell originally missed three HFC leaks Understatement NA – Issue NA – Issue
in their original SERS report. Shell has in project has been has been
since accounted for these leaks in their emissions, addressed. addressed.
Version 5, SERS report. overstatement
in project
reductions
22-03 Quantitative Shell omitted the Project’s nitrogen Understatement NA – Issue NA – Issue
usage for the month of May in their in project has been has been
original SERS report. Shell has since emissions, addressed. addressed.
accounted for this in their Version 5, overstatement
SERS report. in project
reductions
22-04 Quantitative Shell accounting for the electricity from Overstatement NA – Issue NA – Issue
the cooling fan twice, once as a Part of in project has been has been
Total Import Electricity - Cogen emissions, addressed. addressed.
calaculations and once as a standalone understatement
value (Total Import Electricity – Cooling in project
Fans) in SERS. Shell has been made reductions
aware of this issue, and addressed the
error by providing an updated SERS
report without the double-count. This
Issue does not result in a material
misstatement.
Page 51 of 70
Quest Carbon Capture and Storage Project
April 2023
5.0 Closure
5.1 Verification Statement
The verification conclusion is: Positive
GHD has prepared this Verification Report for Shell and AEPA. Shell was responsible for the
preparation and fair presentation of the Offset Project in accordance with TIER with a qualified
third-party verifier to verify the Offset Project Report. Shell’s GHG-related activities are detailed
in Section 4.2.
GHD's objective and responsibility was to provide an opinion regarding whether the Project’s
2022 Offset Project Report was free of material misstatement and that the information reported
is a fair and accurate representation of the operations for the reporting period accurate and
consistent with the requirements of the TIER, and associated criteria. The criteria used by GHD
for the verification of the Offset Project Report is detailed in Section 1.4. GHD completed the
verification of the Offset Project Report in accordance with ISO 14064-3:2019. GHD completed
the verification to a reasonable level of assurance.
Shell reported 715,416 tonnes CO2e as the total emissions reduction the reporting period. This
includes the GHG emissions resulting from operating conditions from January 1, 2022 through
December 31, 2022. The quantitative aggregated magnitude of errors, omissions, and
misstatements is detailed in Section 4.7 and Appendix D.
Based on the verification conducted by GHD, the GHG assertion provided in the 2022 Offset
Project Report for the Quest Carbon Capture and Storage Project was determined to be free of
material misstatements, fairly presented, substantiated by sufficient and appropriate evidence,
and was prepared in accordance with the TIER and relevant criteria.
5.2 Limitation of Liability
Because of the inherent limitations in any internal control structure, it is possible that fraud,
error, or non-compliance with laws and regulations may occur and not be detected. Further, the
verification was not designed to detect all weakness or errors in internal controls so far as they
relate to the requirements set out above as the verification has not been performed
continuously throughout the period and the procedures performed on the relevant internal
controls were on a test basis. Any projection of the evaluation of control procedures to future
periods is subject to the risk that the procedures may become inadequate because of changes
in conditions, or that the degree of compliance with them may deteriorate.
The verification opinion expressed in this report has been formed on the above basis.
GHD's review of the OPR claimed included only the information discussed above. While the
review included observation of the systems used for determination of the claimed OPR, GHD did
not conduct any direct field measurements and has relied on the primary measurement data
and records provided by Shell as being reliable and accurate. No other information was
provided to GHD or incorporated into this review. GHD assumes no responsibility or liability for
the information with which it has been provided by others.
The information and opinions rendered in this report are exclusively for use by Shell. GHD will
not distribute or publish this report without Shell’s consent except as required by law or court
order. The information and opinions expressed in this report are given in response to a limited
assignment and should only be evaluated and implemented in connection with that assignment.
Page 52 of 70
Quest Carbon Capture and Storage Project
April 2023
GHD accepts responsibility for the competent performance of its duties in executing the
assignment and preparing this report in accordance with the normal standards of the
profession, but disclaims any responsibility for consequential damages.
5.3 Confirmations
Verification Findings GHD reviewed the OPP and OPR and found
them to be consistant.
Page 53 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 54 of 70
Quest Carbon Capture and Storage Project
April 2023
6.0 References
Alberta Environment and Parks. January 2023. Standard for Validation, Verification and Audit
(Version 5.2).
Alberta Environment and Parks. January 2023. Standard for Greenhouse Gas Emission Offset
Project Developers (Version 3.2).
Government of Alberta. June 2015. Quantification protocol for CO2 capture and permanent
storage in deep saline aquifers.
Government of Alberta. January 2023. Carbon Offset Emission Factors Handbook (Version 3.1).
Government of Alberta. January 2023. Technology Innovation and Emissions Reduction (TIER)
Regulation, Alberta Regulation 133/2019 and amendments.
International Organization for Standardization. April 2019. ISO 14064 2:2019. Greenhouse
gases –Part 2: Specification with guidance at the project level for quantification and reporting of
greenhouse gas emissions and removals.
International Organization for Standardization. April 2019. ISO 14064 3:2019. Greenhouse
gases –Part 3: Specification with guidance for the validation and verification of greenhouse gas
assertions
Page 55 of 70
Appendix A: Final Verification Plan and Sampling Plan
Page 56 of 70
Verification Plan
Shell Quest Carbon Capture and Storage
Period Jan 01, 2022 to Dec 31, 2022
Shell Canada Ltd.
27 April 2023
Document status
© GHD 2023
This document is and shall remain the property of GHD. The document may only be used for the purpose for which it
was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this
document in any form whatsoever is prohibited.
1. Introduction 1
2. Verification Objective and Level of Assurance 1
3. Verification Standards and Criteria 2
4. Scope 2
4.1 Project Emissions Sink and Source 2
4.2 Geographical and Operational Boundaries 3
4.3 Client contact 3
4.4 Reporting Period 3
4.5 Use of this Report 3
4.6 Use of Information and Communication Technology 3
5. Facility's Data Management System and Controls 3
6. Prior Verification Report and Findings 4
7. Verification Schedule 4
8. Site visit 4
9. Strategic Analysis 5
10. Assessment of Risk and Magnitude of Potential Errors, Omissions, or
Misrepresentations 5
11. Sampling Plan 15
12. Quantitative Testing 17
13. Materiality Level 18
14. Review Team and Peer Reviewer 18
14.1 Roles and Responsibilities 18
14.2 Qualifications 18
15. Verification Procedures 19
16. Closure 20
17. References 22
Table index
Table 1.1 Year-Over-Year Trends 1
Table 9.1 Risk Assessment 6
Table 10.1 Sampling Plan 15
Shell is responsible for the preparation and fair presentation of the Project Report in accordance with TIER.
GHD has prepared this Verification Plan in accordance with the ISO Standard ISO 14064 Greenhouse gases – Part 3:
Specification with guidance for the validation and verification of greenhouse gas assertions (ISO 14064-3:2019) and
with Alberta Environment and Protected Areas (EPA)'s Standard for Validation, Verification and Audit (EPA, 2020).
1
The TIER replaced the Carbon Competitiveness Incentive Regulation, Reg. 255/2017 (CCIR) as of January 1, 2020.
4. Scope
4.1 Project Emissions Sink and Source
During the baseline condition, CO2 is produced in the hydrogen manufacturing units in the Scotford Upgrader through
the steam-methane reforming reaction and is then emitted to the atmosphere.
During the project condition, the CO2 produced in the hydrogen manufacturing units is captured and separated from
the raw gas stream by the CCS capture facility, compressed, transported to the injection wells, and then sequestered
underground.
The baseline emissions source prior to the implementation of the Project includes the following:
– B1: Injected CO2
The project emissions sources include the following:
– P3: Well Drilling Reportable Releases
– P4: Production and Delivery of Material Inputs
– P5, P6 & P7: Extraction/ Processing and Transportation of Fuel Used for On-Site and Off-Site Heat and Electricity
Generation
– P8: Off-Site Electricity Generation
– P9: Off-Site Heat Generation
– P10: On-Site Heat and Electricity Generation
– P11: Carbon Capture Storage Facility Operation
– P18: Venting of Co2 at Injection Well Sites
– P19: Fugitive Emissions at Injection Well Sites
– P20: Emissions from Subsurface to Atmosphere
– P21: Loss, Disposal or Recycling of Materials Used
7. Verification Schedule
The following presents a draft verification schedule:
– Submit Verification Plan to Shell – January 31, 2023
– Shell Verification Plan review period – January 31 – February 2, 2023
– Request, receive and review documents and raw data from Shell – February 15 – April 10, 2023
– Site Visit – February 7, 2023 (Capture Site), TBD (Injection Site)
– Submit Issues Log – early February, 2023
– Independent review by independent peer reviewer – week of April 10, 2023
– Submit draft verification report to Shell – April 12, 2023
– Review draft verification report with Shell – April 12 – 24, 2023
– Issue Final Verification Report and Statement of Verification – April 27, 2023
8. Site Visit
The Site Visit, will generally adhere to the following agenda. Deviations from the proposed agenda may be necessary
to respond to data gaps and or issues identified during the verification process:
– Opening Meeting - Introduction and sign in, safety review, and overview of verification process and expectations
(key personnel need to be present).
– Overview of Facility operations, activities and production processes, including description of key emission
sources.
– Review of monitoring practices, quality control and quality assurance procedures, GHG data and emission
calculations, and any personnel activities that have a potential to impact materiality.
– Review of meter calibration certificates and accuracy specifications for key meters.
– Interviews with key personnel and review of data collection process from meter through distributed control system
or transcription and data entry, as applicable.
– Walkthrough to view Facility boundaries, physical infrastructure, and equipment and measuring devices.
– Closing Meeting – Review issues identified and next steps
Potential Risk Area Percentage of total Site Attributes Inherent Risk Control Risk Detection Consideration for
(Sink and Source) Emissions Risk Design Procedure
Baseline Emission
B1: Injected CO2 100% Occurrence High – Based on Low – One meter Low GHD has set the
total CO2 injected. present at each detection risk as low, as
Metering points are injection well, and GHD will review all CO2
required to be one composition injected measurements
located as close to measurement and composition data for
the injection points system. All meter crediting period.
as possible. and analyzer data
Composition of CO2 is stored within
is understood to be Shell’s PI system,
based on direct gas while sampling data
analysis; is stored in LIMS.
understood to be
additional manual
samples historically
collected. Potential
venting/fugitives
after metering
Completeness point (at injection
points) captured in
project condition.
Accuracy Low – Metering
system present at
each injection well
and composition
based on gas
analysis on injected
CO2 stream.
Classification Low – classification of offsets is well
defined within the system.
Transparency Medium - Calculations are completed in
“black-box” calculation model, although
inputs and outputs, along with
methodologies are clearly defined.
Consistency Low – Understood calculations are
consistent with previous reporting periods
Consistency
Use of ICT* NA Occurrence Medium –. The Medium – ICT Medium To lower the detection
GHD project team technologies are risk, GHD will work with
Completeness has previous available to both Shell to arrange meetings
Accuracy experience in Shell and GHD, at appropriate times for
conducting when required. Shell operators and staff
Classification verifications for to be available to work
similar project types through the verification
Transparency
process and provide
Consistency sufficient time to deal with
potential technical
limitations.
Data Management NA Occurrence Medium – Majority Medium – All data Lowest The data management
of quantities used is managed and systems are present at
Completeness for emission tracked by Shell the Site. GHD will review
Accuracy reduction are real- personnel. Multiple all data systems and the
time data stored on
Classification PI or LIMS
14.2 Qualifications
Deacon Liddy, P. Eng. – Mr. Liddy is a Principal with GHD and an experienced GHG validator and verifier, having
completed over 100 GHG validation/verifications with 17-years of experience. Mr. Liddy works with large industrial
facilities, Provincial governments, and offset project developers to complete risk-based verifications. Mr. Liddy has
been the lead verifier for completion of greenhouse gas verifications conducted on behalf of Alberta Environment for
emission offset projects for landfill gas, biomass, tillage, composting and fuel switching for lumber kilns. Mr. Liddy has
completed verifications of greenhouse gas emission intensity baseline applications and annual compliance reports
under the Alberta Specified Gas Emitters Regulation and British Columbia Mandatory Reporting Regulation. Mr. Liddy
is a professional engineer in BC, Alberta, and Saskatchewan.
Sean Williams, P.Eng. – Mr. Williams is a Project Manager, GHG Lead Verifier and Technical Expert and with over
10-years of experience in environmental consulting and is a licensed Professional Engineer in the provinces of
Alberta, Saskatchewan and Ontario. Mr. Williams has experience in completing greenhouse gas verifications, permit
applications, air and noise compliance assessments, completion of annual inventory reports under various voluntary,
provincial and federal regulations across Canada. Mr. Williams is an accredited lead verifier under the California Air
Resources Board and Oregon Department of Environmental Quality. Mr. Williams has significant air and GHG
expertise in a variety of industrial sectors, including oil sands extraction and upgrading, refineries, chemical plants,
mining and mineral production, power generation facilities, waste management and metals production. Mr. Williams
serves as the Greenhouse Gas Assurances Services (GGAS) Manager for GHD’s ANAB accreditation.
Stepheney Davey, M.Sc., E.I.T. – Ms. Davey is a junior engineer and member of the EHS Compliance team with
GHD. She holds a Master of Science degree in Chemical Engineering from the University of Alberta. Ms. Davey has
been involved with multiple GHG verifications in various sectors under the Greenhouse Gas Industrial Reporting and
16. Closure
The Verification Plan is considered to be a dynamic document that will require modification and adaptation to project
conditions as encountered during the completion of the Verification process. GHD will communicate the changes to
the verification plan with Shell throughout the verification.
Government of Alberta. 2020. Technology Innovation and Emissions Reduction Regulation, Alta Reg. 133/2019 with
amendments.
International Organization for Standardization. 2018. ISO 14064-1:2018. Greenhouse gases – Part 1: Specification
with guidance at the organization level for quantification and reporting of greenhouse gas emissions and
removals.
International Organization for Standardization. 2016. ISO 14064-3:2016. Greenhouse gases – Part 3: Specification
with guidance for the validation and verification of greenhouse gas assertions.
Shell Canada Limited. 2016. Offset Project Plan Carbon Capture and Storage Project.
Page 57 of 70
Statement of Qualifications
Alberta Emission Offset
Project
Emission Offset Project Name Offset Project ID
Quest Carbon Capture and Storage
Project 7306-8118
Emission Offset Project Developer Offset Reporting Period
December 31,
Shell Canada Limited January 1, 2022 2022
from to
Signature of Designated Signing Authority
Lead Verifier
Same as designated signing
☐ authority.
First Name Last Name
Sean Williams
Professional Designation or
Accreditation Org/Number E-mail Address Phone Number
P.Eng Sean.Williams@GHD.com 780-705-7055
Page 58 of 70
Peer Reviewer
First Name Last Name
Gordon Reusing
E-mail Address Phone Number
Gord.Reusing@GHD.com 519-340-4231
Page 59 of 70
Appendix C: Findings and Issues
Page 60 of 70
Table 3: Detailed Findings and Issues Log
22-01 The calculated absolute GHD reviewed all process data Resolved Overall
difference between Shell’s and used to develop the difference is
GHD’s values for the baseline/project sources. 0.06%, less
baseline/project sources and than the
None of these discrepancies are
sinks are the following: materiality
material, and the overall
threshold.
B1 – 25.18 tonnes CO2, difference is less than the
<0.01% of total offsets materiality threshold.
P4 – 0.50 tonnes CO2,
<0.01% of total offsets
P5/P6/P7 – 36.51 tonnes
CO2e, 0.01% of total offsets
P8 – 226.42 tonnes CO2e,
0.03% of total offsets
P9 – 147.10 tonnes CO2e,
0.02% of total offsets
P10 – 0.28 tonnes CO2e,
<0.01% of total offsets
P11 – 0.52 tonnes CO2e,
<0.01% of total offsets
Page 61 of 70
Item (YR-##) Description of the Issues Summary of Information Resolution Conclusion
Investigated During the Exchanged (Resolved or (including %
Verification Unresolved) discrepancy if
applicable)
GHD reviewed all process data
used to develop the
baseline/project sources.
None of these discrepancies
are material, and the overall
difference is less than the
materiality threshold. Overall
difference is 0.06%, less than
the materiality threshold.
22-02 Shell originally missed three GHD reviewed the email Resolved Confirmed to
HFC leaks in their original communication between Shell not result in
SERS report. Shell has since Data Focals and the HFC leaks any material
accounted for these leaks in spreadsheet. discrepancies.
their Version 5, SERS report.
Shell addressed the error by
providing evedience of the HFC
leaks and an updated SERS
report.
22-03 Shell omitted the Project’s GHD reviewed the monthly Resolved Confirmed to
nitrogen usage for the month nitrogen consumption provided not result in
of May in their original SERS in the Mass Balance any material
report. Shell has since spreadsheets and compared the discrepancies.
accounted for this in their consumption to the amounts
Version 5, SERS report. provided in the SERS report.
Shell addressed the error by
providing an updated SERS
report including the nitrogen
consumption for May.
22-04 Shell accounting for the GHD reviewed the raw meter Resolved Confirmed to
electricity from the cooling fan data and the calculations from not result in
twice, once as a Part of Total the Power Monthly spreadsheets any material
Import Electricity - Cogen discrepancies.
calaculations and once as a
Page 62 of 70
Item (YR-##) Description of the Issues Summary of Information Resolution Conclusion
Investigated During the Exchanged (Resolved or (including %
Verification Unresolved) discrepancy if
applicable)
standalone value (Total as well as the SERS outputs for
Import Electricity – Cooling electricity.
Fans) in SERS.
Shell addressed the error by
providing an updated SERS
report without the double-count.
22-05 Shell did not provide GHD reviewed the calibration Resolved GHD has
calibration records for the records provided by Shell. confirmed that
following meters: the lack of
Shell has indicated these meters
calibration
52-15B (Quest Main Power) do not have documentation and
records for
do not need to be calibrated.
52-16B (Compressor Motor these meters
Power) will not result
in a material
misstatement.
Page 63 of 70
Appendix D: Statement of Verification
Page 64 of 70
Quest Carbon Capture and Storage Project
April 2023
Statement of Verification
Alberta Emission Offset Project
Emission Offset Quantification Protocol
Project Title (Date/Version) Project ID #
Quantification protocol
for CO2 capture and
permanent storage in
deep saline aquifers
Quest Carbon Capture and (June 23,
Storage Project 2015/Version 1.0) 7306-8118
December
N/A 31, 2022
Statement of Verification
Value Units
tonnes
Other (I.e. levied)
CO2eq
Page 65 of 70
Quest Carbon Capture and Storage Project
April 2023
Shell is responsible for completing an accurate offset project report and engaging a qualified
third party verifier to conduct a verification of the offset project report form and assertion.
GHD's responsibility was to express a conclusion with respect to the offset project report (2022
reporting period).
Conclusion
Verification
Company Name
Da
Signature of Designated Signing Authority te:
Deacon Liddy
Professional
Designation/Accredit Phone
ation Org & Number E-mail Address Number
Page 66 of 70
Appendix E: Conflict of Interest Checklist
Page 67 of 70
Quest Carbon Capture and Storage Project
April 2023
Emission Offset
Project Title Quantification Protocol (Date/Version)
Quest Carbon Quantification protocol for CO2 capture and
Capture and Storage permanent storage in deep saline aquifers (June 23,
Project 2015/Version 1.0)
Offset Reporting
Project Developer Offset Reporting Period Start Period End
December 31,
Shell Canada Limited January 1, 2022 2022
Checklist
Respond either "True" or "False" to each of the following statements:
The relationship between my firm and this reporting company poses unacceptable
1.
threat to or compromises the impartiality of my firm. False
The personnel my firm has scheduled to participate in the verification may have an
3.
actual or potential conflict of interest. False
My firm will use personnel that have, are, or will be engaged or previously
6.
employed by the reporting company. False
My firm will outsource the Statement of Verification for the associated offset
7.
submission. False
Important: If you have checked "True" to any of the above, you may not fulfill the "independence" requirement for
third party verifiers. Please contact Alberta Environment and Parks for further instruction. If the potential conflict of
interest is a sufficient threat to impartiality (perceived or actual), or cannot be effectively managed, the Verification
Report will not be acceptable to Alberta Environment and Parks.
Page 68 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 69 of 70
Quest Carbon Capture and Storage Project
April 2023
Page 70 of 70
Appendix F.1
List of Documents Received by GHD
Shell Canada Limited
Quest Carbon Capture and Storage (CCS) Project - 6th Reporting Period
Fort Saskatchewan, Alberta
2 Quest Carbon Capture and Storage Project - 2022 OPR.docx Offset Project Report for the 2022 reporting period
ConsumptionValues.xls
EmissionValues.xls
Measurements.xls
3 (Multiple Versions) SERS output
Emissions Drilldown - Quest 2022.xlsx
Quest SERS Protocol Report 2022.xlsx
4 (Multiple Versions) Emissions Summary of SERS output
5 Various Files Calibration records for meters
Enviro Report Verification (Monthly)
6 TransCanada Report-2022 (NOVA Gas Transmission Ltd.) Gas composition data summaries
Contractor Fuel Usage 2022.xlsx
2022 Fuel Consumption Report.xlsx (Monthly)
Fuel Consumption Report - Activity Summary report by
7 Account for Product - (Month) 2022.xlsx Diesel and gasoline usage
8 Analyzer vs Lab data_Quest 2022.xlsx Comparison of lab and analyzer data
Calibration gas and calibration procedures for
9 SCT - GC-023 Quest details.docx laboratory GC
Quest Well Electricity:
10 Quest {Month} 2022.xlsx (Monthly) Monthly injection well site electricity invoices
2022 JV Cogen Billing Model {Month} Final - New Server.xlsx
11 (Monthly) Quest Main Site Electricity
12 Quest Mass Balance - {Month} 2022 Mass Balance spreadsheets
Steam:
13 MM - Monthly Quest {Month} 2022.xlsb.xlsx (Monthly) Steam Spreadsheets
14 MMV Overview through 2022 Presentation overview of MMV Plan updates
Summary of Mass Balance Spreadsheets and Waste
15 2022 Mass Balance Summary.xlsx Water Treatment Volumes Summary
16 Quest_2020_MMV_Plan_Resubmit_Nov20.pdf Most recent MMV Plan
Assessment of MMV plan and emissions for Q1-Q4 in
17 P20_assessment_Q# 2022 (Four files for each Quarter) 2022