Commissioning DPR - 28-07-2014 Lanco, Koradi - PF1261

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 4

DAILY PROGRESS REPORT

DATE :- 7/28/2014

PROJECT :- FM BOILER, M/s Lanco A/c Mahagenco, Koradi, Nagpur


JOB NO. :- PF 1261

DAY PROGRESS:

Inputs
Sr. No. Activity planned
FROM
FROM Customer
Thermax

Manpower/
1 Trial of MSSV valve from Local Engineer
Engineer/Tools

PLC Software Activation & Graphics Manpower/


2 Engineer
interlink with BMS, BCS system. Engineer/Tools

Manpower/
3 Trails of the FD fan to be completed. Engineer
Engineer/Tools

Allignment of BFW Pump to be Manpower/


4 Engineer
completed. Engineer/Tools

Manpower/
5 Hot loop check to be started. Engineer
Engineer/Tools

NEXT DAY’S PLAN:

Sr. No. Activity planned Inputs


FROM
FROM Customer
Thermax

Skilled Manpower
1 Hot loop check to be done. Manpower/Engineer Engineer
/Tools.

Manpower/
2 Trails of the FD-2 fan to be completed. Engineer
Engineer/Tools
Skilled
Manpower/Engineer
Allignment of BFW-B Pump to be
3 /Commissioning Engineer
completed.
Tools/UPS Power
supply/Walky Talky

Trails of the BFW Pump to be Manpower/


4 Engineer
completed. Engineer/Tools

Skilled
Manpower/Engineer
5 Trial of MSSV valve from Local. Engineer
/Commissioning
Tools/Power Supply

Next milestone activity- Burner Light Up Trials


EPORT

LEGENDS:
· C – Completed
· NC – Not completed
· PC – Partially Complete

Activity
Status
Remarks / Reason for activity not completed
C / NC / PC

Power Cable is not terminated. However, Power


NC
supply is yet to be made available.

Switch gear remote selection f/b fluctuation


problem from Lanco. Interlock simulation
NC
checking Pending.FD fan trial is planned on 29-
07-2014

PC Under Progress.

NC No manpower available for Loop Check.

Remarks