Safety Manual
Safety Manual
Safety Manual
BOOK
2.0 Purpose 1
10.0 PPE 10
10.1 Specification for PPE & Safety Devices 10
10.2 PPE matrix 15
This Plan sets out the approach to safety management across K RAHEJA CORP. In particular
it defines the overall project safety standard and control arrangements to be employed. This
Plan will be maintained as a living document. Specific revisions and cumulative additions will
be issued at different stages.
2. PURPOSE
K Raheja Corp (KRC) has developed the safety management system to update its
operational safety standard and meet its customer expectations by adhering to higher
standard of safety at every stage of construction. The Safety Management Manual is being
introduced at sites to have adequate control at site related to safety.
This Manual consists of planned actions undertaken by KRC for execution of the project both
residential and commercial. The plan shall define the operations to be performed, the
systematic and sequential progression of operations, the persons responsible for each
activity and the measures employed to assure the specific requirement of safety. Thus, it is
essential to ensure that activities are monitored, inspected, checked and actions taken at all
stages from commencement of work towards various safety standards.
Project head shall establish a project HSE committee comprising of at least one
representative from each trade of work. All committee members will be committed towards
implementation and control of HSE aspects of work to be performed. A typical structure of
project HSE committee is given below.
1|Page
Project Safety Manager (site) shall have dual reporting structure. For day to day functioning
he shall take instruction from and report administrative matters to project head. Project
Safety Manager shall functionally report, safety performance (Refer Appendix I) to Corporate
Safety Head and shall take relevant direction / guidance from him in addition to report all
deviation / escalations to him.
Provide leadership and facilitate the team achieve the Safety objectives.
Conduct review meeting for Safety aspects.
Provide resources as required by the Safety team for implementing safety plans.
Decide corrective and preventive actions for NC’s.
Lead the project team as an auditee during Safety audits.
Release employees for attending Training programmes [Safety related]
2|Page
3.5 Responsibilities of the Project Safety In charge:
3|Page
4. JOB SAFETY ANALYSIS
A job safety analysis (JSA) is a procedure which helps integrate accepted safety and health
principles and practices into a particular task or job operation. In a JSA, each basic step of
the job is to identify potential hazards and to recommend the safest way to do the job.
Identify hazardous activities / job which has a potential of serious injury and
repetitive in nature.
The JSA shall be completed by management of contractor and submitted to M/s K-Raheja
for review and approval before commencement of the task. The JSA shall be used by the
foreman / site supervisor in developing the Pre-Task Plan (PTP) / tool box talk prior to shift
start and whenever a new task is initiated.
1. Hot work
4. Painting work
5. Scaffolding
7. De-shuttering
8. Backfilling, Earthwork
4|Page
5. PERMIT TO WORK SYSTEM
Permit to work (PTW) systems are formal procedures used to control activities that are
considered high-risk. Permits only allow authorised personnel to perform those activities at
specified times and in a way set out in the permit and other referenced documents. Permit
to work systems do not in themselves make activities safer, this is only possible through the
implementation of the correct procedures.
Work at Height, HOT Work permit, Temporary Site Electrification permit will be issued by
KRC site representative to the contractor performing the work after proper verification and
assessment of site condition. Same work permit will be endorsed by safety representative
during daily site inspection of workplace (Refer Appendix B). Once work is completed for
that particular location, permit to be surrendered to safety In charge.
Based on the criticality of the project, following permit to work systems are developed
1. Work at Height Permit: - This permit applies to Work at heights as defined below,
This permit has 3 day validity, for 2nd and 3rd day reinspection to be done and signed on
same permit.
2. HOT Work Permit: - Hot work is any work that involves burning, welding, using fire- or
spark-producing tools, or that produces a source of ignition. This permit has 3 day validity,
for 2nd and 3rd day reinspection to be done and signed on same permit.
3. Temporary Site Electrification Permit: - For any temporary connection from main electrical
distribution system at site, this permit will be issued after adequate inspection of site
premises as per safety standard. This permit is valid for total work duration, if all the
connection remains same.
4. Excavation Work Permit: - This permit to be issued before starting excavation work and
approval from concerned parties to be taken if applicable.
5. General Work Permit: - This permit can be used for any of the hazardous / high risk
activity (as identified by safety In charge in coordination with building manager) to be
performed at site.
6. Driver Operator Permit & Electrician Permits to be issued by safety Incharge to the
authorized persons after preliminary inspection of all required documents, experience.
5|Page
6. PERIODICAL HSE INSPECTION
K Raheja Corp. project HSE team shall continually monitor the project site. Periodical HSE
inspections shall be carried out and recorded as described (Refer Appendix C). All the
findings during periodical inspection will be communicated to concerned person for
necessary action.
6|Page
* Scaffolding should be inspected before the first use after initial erection is completed. After
the inspection, a safety tag shall be posted on the scaffold indicating if they are safe to use
or not safe. Sample safety tag is given below for reference:
7|Page
7. FIELD OBSERVATION REPORT
Preventive Action:
The Safety In-charge shall review and analyse all “FOR” recorded during the month at site
and identify common threads running through these. These will be used to develop
effective “preventive actions” to reduce recurrence of same observations.
8|Page
8. ACCIDENT / INCIDENT REPORTING SYSTEM
This section defines the system to report, investigate and analyze incidents in order to find
out as many direct and contributory causes as relevant and suggest corrective measures to
avoid recurrence.
Procedure:
Sl. Procedure Responsibility Record
No.
Project Level
1 Motivate all personnel in the project to report PM -
incident cases with a view to prevent recurrence.
2 Submit preliminary HSE report to corporate head Site Engineer / Appendix E.1
within 12 hours of incident occurrence. Verbal Supervisor
information shall be immediate.
3 Conduct on-spot investigation at the earliest after HSEO Appendix
receiving preliminary incident report or informal E.2,
information to that effect Appendix E.3
4 Form a team for detailed investigation of incident, HSEO Appendix
which shall include PM, building manager, Site E.2,
engineer, subcontractor and workmen. Appendix E.3
5 Refer checklist Annexure 9 for guidance and find Investigation Appendix
out as many direct and contributory causes as Team E.2,
relevant. Appendix E.3
6 Suggest Precautionary measures to prevent similar HSEO Appendix
occurrence in the investigation report. E.2,
Appendix E.3
7 Prepare the investigation report and circulate to HSEO Appendix
PM, Corporate HSEM and other concerned E.2,
departments of the projects within 48 hours of Appendix E.3
occurrence of receipt information.
Corporate Level
8 Communicate the results of incident investigation HOD-HSE Incident
to all HSEO’s and other concerned to enable them Cause
to take necessary preventive action in their projects Studies
in future.
9|Page
Reporting / Communication Tree
Submit Preliminary
KRC Corporate Head Report within 24
hours
Final Report
KRC Safety
Reviewed Manager
Victim / Witness
Incident Occurred
10 | P a g e
9. FIRST AID CASES
First aid case means work related incident which results in one time minor treatment.
Examples – Minor Scratches, superficial cuts, burns, splinters, taking x-ray which turns out
to be normal, cleaning, flushing or soaking of wounds on the surface of the skin and so forth
which do not require ongoing medical care.
This section defines how to facilitate basic First-Aid treatment to the injured and analysis of
causes of first-Aid cases so as to take necessary preventive action.
Procedure:
11 | P a g e
10. PERSONAL PROTECTIVE EQUIPMENT
Colour Coding:
Colour To be used by
WHITE Staff
BLUE Supervisor
YELLOW Workmen
GREEN Safety Stewards
RED Electricians
Conformance to standard: - General Safety Belt / Full Body Harness shall be certified to
IS 3521 – 1999 (Third Revision) or shall have DGMS certification or any internationally
recognized certification such as CE, UL mark.
Lanyard: - Lanyard shall be of 12mm polypropylene rope and of length not more than 2 m.
The ends shall be spliced and covered with transparent sleeve & the curved portion
protected with thimble. The hook shall be non separable from the lanyard. It can be single
or double lanyard, based on the requirement.
Hook: - Hooks shall be of self-closing type. The hooks should not disengage if the pressure
is exerted accidentally on the tongue or latch. The opening in the hook shall be minimum 18
mm.
Carabineer
12 | P a g e
Snap Hook
Scaffold Hook
Class of Full body harness: - Approved Classes: Class A & Class L. Only Class L harness
shall be used in conjunction with rope grab fall arrestor.
LIFE LINE: - Minimum 20mm diameter polypropylene rope or Minimum 8 mm wire rope
shall be used as a lifeline.
ROPE GRAB FALL ARRESTOR: - Rope grab type fall arrestors shall be certified to EN 353
– 2 standards.
Conformance to standard: - The safety shoe used shall be certified to any one of the
Indian Standard given below or DGMS Certification or any internationally recognized
certification like CE, UL mark.
IS 1989: Part 1: 1986 Specification for Leather Safety Boots and Shoes - Part 1: For
Miners.
IS 1989: Part 2: 1986 Specification for Leather Safety Boots and Shoes - Part 2: For
Heavy Metal Industries.
IS 11226: 1993 - Leather safety footwear having direct moulded rubber sole –
Specification.
IS 14544: 1998 Leather safety footwear with direct moulded PVC soles –
Specification.
IS 15298: Part 1: 2002 Safety, Protective and Occupational Footwear for Professional
Use - Part 1: Requirements and Test Methods.
IS 15298: Part 2: 2002 Safety, Protective and Occupational Footwear for Professional
use - Part 2 to Part 10: Specification for Safety Footwear.
Optional Requirements
Shock-proof Safety Shoes - Shock proof shoes shall be used wherever hazard of
electric shock exist. Non-conductive hard toe is used instead of steel toe.
Safety Shoes with Puncture Resistance - Where ever hazard of puncture exist
safety shoes with steel mid sole can be used to protect against the objects like nails
etc.
13 | P a g e
10.1.4 WARNING TAPE
HDPE or LDPE: - Made of 50 micron thick, non-adhesive, width 75mm – KRC Logo
embossed at every foot with white and red strips on both sides in Tubular form.
RCCB shall conform to: - IS 12640: Part 1: 2000 Residual Current Operated Circuit -
Breakers for Household and Similar Uses - Part 1: Circuit-Breakers Without Integral
Over current Protection.
RCBO shall conform to: - IS 12640: Part 2: 2001 Residual Current Operated Circuit -
Breakers for Household and Similar Uses - Part 2 Circuit - Breakers with Integral
Over current Protection.
Standard Specifications:
The size of the net shall be as per site requirement. Unit of measurement for Safety Net
shall be Sq.m (square meters)
The Gum Boot or ankle shoe used shall be certified to any one of the Indian Standard given
below or shall have certification of DGMS or any international certification like CE, UL Mark.
IS 5557: 2004, Industrial and Protective Rubber Knee and Ankle Boots –
Specification
IS 12254: 1993, Polyvinyl Chloride (PVC) Industrial Boots - Specification
With Steel Toe: - GUM BOOT / ANKLE SHOE with steel toe shall be used wherever impact
hazard exist.
14 | P a g e
10.1.8 EAR MUFF/PLUG
Ear Muff / Ear Pug shall conform to IS: 9167-1979 or shall have the certification from DGMS
or any other international certification such as CE or UL Mark.
Goggles, Safety Spectacles, Face Shield shall conform to IS: 5983 – 1980 or shall have the
certification from DGMS or any other international certification such as CE or UL Mark.
The fit of gloves should be such that the fingers should have ample room.
CANVAS Gloves canvas – stitching with nylon thread – conforming to IS: 6994-(part-
I) 1973.
CROME LEATHER gloves – 14” stitching with nylon thread - conforming to IS: 6994-
(part-I) 1973.
RUBBER Gloves – 18” (380/450mm long) electrical grade, tested to 15000 volts -
conforming to IS: 4770-1991.
COTTON Gloves (for material handling) Leather cum canvas-304mm long, double
leather for five finger type, double stitching spaced at 1mm. - conforming to IS:
6994-(part-I) 1973.
Shall be certified to IS 2878 : 2004 (Fire Extinguisher, Carbon Dioxide Type (Portable
and Trolley Mounted) – Specification)
Internal discharge tube with 1m discharge hose (2m in case of more than 6.8kg
cap.) Wheel type valve with lock pin (conforming to IS: 3224).
Shall be certified to IS 2171: 1999 Specification for portable fire extinguishers, dry
powder (cartridge type)
Refill of dry chemical powder shall conform to IS 4308 : 1982 (Specification for dry
powder for fire fighting)
CO2 cartridge (120 gms for 5 kg cap., 180 gms for 10 kg cap.) shall conform to IS
4947 : 1985 (Specification for gas cartridges for use in fire extinguishers)
15 | P a g e
DRY CHEMICAL POWDER (CONSTANT PRESSURE TYPE) for ABC Fires:
Shall be certified to IS 13849 : 1993 (Specification for portable fire extinguisher dry
powder type (constant pressure)
The powder used shall conform to IS 14609 : 1999 (Dry chemical powder for fighting
A, B and C class fires – Specification)
16 | P a g e
10.2 PPE MATRIX
Nose/Dust Mask
Head Protection
resistant Glove
Foot Protection
Safety Harness
Safety Coverall
Welding Shield
PPE
Reflective vest
Leather Apron
Rubber Hand
Safety Glass
Cotton Hand
Fall Arrestor
with helmet
Face Shield
Respiratory
Leather/cut
Protection
Protection
Gum Boot
Hearing
Gloves
Gloves
Category
Executives/Supervisors
Foreman
Formwork
Scaffolding
Masonry work
Bar-bending works
Grinding & Polishing
Rigging
Welding / cutting
Handling chemical
Painting
Liquid Bitumen works
Stone/ tile fixing
Concreting
Concrete breaking
Carpentry shop
Working at height above 1.8m
17 | P a g e
11. SAFETY COMMUNICATION
Every employee assigned to the project shall receive safety Induction / Orientation
training appropriate for the tasks that they will be performing.
The KRC provided safety Induction shall not be considered a substitute for new hire
safety orientation training or task specific safety training by
Contractor/Subcontractor.
Each project new-hire and visitor shall receive the KRC provided safety orientation
training prior to entering construction work areas.
Visitors shall be escorted at all times when entering construction work areas, if safety
orientation has not been completed.
Contractor shall notify the KRC of application for orientation one day before the
applied orientation to ensure adequate coordination and preparation. Roster of new
hires, 2 copies of photo, copy of ID card and certificate for special trades (safety
officers, welders, crane operators, electricians, scaffolding erectors and others) shall
be submitted to the KRC for review.
Induction completion Stickers on helmet have to be provided before actual site entry.
Following are the minimum topics to be covered during Safety Induction.
18 | P a g e
SN Designation / Topics to be covered Frequency
Trade
This section explains KRC's guidelines for posting safety signage’s at the site.
1. All signs must be removed promptly when the hazard no longer exists.
2. All employees must obey all sign warnings and instructions. Defacing a sign is grounds
for termination.
19 | P a g e
3. All signage’s FONT should have at least 2 ½ inches height and ½ inch thick.
4. Board must be made of semi-permanent materials like ply boards, thick plastic,
linoleum, etc.
7. DANGER signs are used only where an immediate hazard exists. Danger signs shall have
red as the predominating colour for the upper panel; black outline on the borders; and
a white lower panel for additional sign wording. - for example, "High Voltage," "Open
Floor Hole," "Falling Debris," "No Smoking," and so on.
For Example:
8. CAUTION signs are used to warn of potential hazards or to caution against unsafe
practices. Caution signs shall have yellow as the predominating color; black upper panel
and borders; yellow lettering of "caution" on the black panel; and the lower yellow
panel for additional sign wording. Black lettering shall be used for additional wording,—
for example, "Eye Protection Required," "Look before backing," "Hard Hat Area," HOT
WORK IN PROGRESS, Erection works and so on.
For Example:
9. MANDATORY signs are used where this type of symbol conveys actions that must be
taken to avoid hazards. This symbol consists of a white image within a solid blue or
black circle.
10. PROHIBITION - For actions that should not be taken, this surround shape is required. It
consists of a red or black circle with a diagonal slash at 45° from the upper-left to the
20 | P a g e
lower-right. For example Smoking Prohibited, Do not use Cell phone, No access for
unauthorized persons etc.
11. TRAFFIC signs should be posted in all construction traffic areas advising of various
hazards. Standard highway traffic signs should be used. Speed limit signs should be
posted on site.
12. All signs must comply with the color code requirements listed in appropriate
governmental regulations.
13. When applicable, signs must have a reflective backing to ensure night time visibility.
14. Signs denoting the "Construction Area" must be posted every 50 feet (15.2 meters) /
specific work related on the outer edge of the defined construction area.
15. Signs must be hung (at least 5 to 6 feet above from ground) in the clear and
conspicuous areas so they will not be missed by personnel nearing the protected area.
Area Requirements
21 | P a g e
Area Requirements
Pedestrian walkway
Temporary No smoking
sub station Electricity danger signage’s
Live terminals
Fire Extinguishers
22 | P a g e
Area Requirements
Excavation Excavation
Deep Excavation
Procedure:
Corporate Level
Project Level
23 | P a g e
5th June - World Environment day
14th Dec - National Energy Conservation
Day
Optional:
22nd April - Earth Day
22nd March - World Water Day
1st December - World AIDS day
1st July - National Recycling Day
4 Organize Housekeeping campaign once in a EHSO Campaign
quarter. reports
Region wise
7 Compile reports from all projects and send to HOD- Regional EHS Campaign
EHS. Manager reports
24 | P a g e
12. INTERNAL AUDIT
Form each project a set of people as identified by project head along with safety in charge
will be a member of Internal HSE Audit Team. CO Head – Safety will utilize those personnel
to conduct cross project audit as per predefined audit plan for a financial year.
Project Head
Dy. Project Head
Project 1
Safety In Charge
Building Manager
Project Head
Dy. Project Head
Project 2
Safety In Charge
Building Manager
25 | P a g e
Sl. Procedure Responsibility Record
No.
Non-Conformity reports, Observations, Noteworthy
efforts to MR & Corporate HSE.
9 Send a written explanation to MR in case of any Auditor Internal
deviation of more than 10 days in conducting the Communication
audit as scheduled.
Closing of NCR
10 Retain the Non-Conformity reports until they are Auditee Appendix H.2
closed out
11 Follow up immediately after the due date of Corporate HSE Appendix H.2
implementation to determine if corrective action
has been implemented and whether it is effective.
Decide a new follow up date if more is required to
fully implement the action.
12 Close the Non-Conformity reports (generated at Corporate HSE Appendix H.2
the projects) upon satisfactory implementation of
corrective actions and retain the reports.
13 Close the Non-Conformity reports (generated at MR Appendix H.2
HQ and those projects where Corporate HSE’s are
posted) upon satisfactory implementations of
corrective actions and retain the reports.
Analysis of Audit Results
14 Analyze the audit findings to assess the Corporate HSE Appendix H.3
performance of Project / BU and send the
summary of audit results every quarter to MR.
Summarize the results of all internal audits for MR Appendix H.4
discussion in MRM.
26 | P a g e
Results of internal and external audits of BU /
projects
Results of Incident investigation of other OC /
BU projects
Opportunity for improvement noted by
function head himself in his functional area.
4 Record the identified preventive actions and the HOD-HSE, Appendix H.5
actions in CAPA register maintained at respective Corporate
functions HSE, HSEO
Review
5 Review CAPA in MRM and Project HSE Committee HOD- Appendix H.4
meetings. HSE,HSEO Appendix H.6
27 | P a g e
13. HSE BUDGET
A standard safety budget is established as per requirement; however same can be modified
as per specific requirement of the project.
Note:- For 5-7 lakh sqft per annum - 2 safety officer, 3-4 safety stewert, 1 Male nurse
One manager for 1.5-2 million sqft per annum
Gross INR /
S.N Items Nos. Rate Amount
Amount Sqft
Safety Helmets 50 120 6,000
Safety Shoes- Ordinary 50 480 24,000
Gum Boots 30 385 11,550
Ear Plug 500 12 6,000
Ear Muf 10 112 1,120
Safety Goggles - White 100 18 1,800
Safety Goggles - Black 50 14 700
Safety Goggles - Splash proof (MSA) 10 95 950
Welder Face Shield 18 80 1,440
Nose Mask 7 10,500
1,500
Nose Mask Special 10 55 550
PPE
1,61,297 0.323
Hand Gloves - Cotton 12 24,000
2,000
Hand Gloves - Anti Cut 100 65 6,500
Hand Gloves - leather 40 35 1,400
Grinder face shield with helmet 6 200 1,200
Welder Face Shield with helmet 10 500 5,000
Rubber Hand Gloves 500 15 7,500
Rubber Hand Gloves - HV 3 207 621
Rubber Hand Gloves - LV 3 422 1,266
Rain Coat 15 250 3,750
Flourocent Jacket 150 90 13,500
Safety Belt 45 710 31,950
Fire Blanket 2 1000 2,000
Fire Extinguishers - 5 kg (DCP) 12 1250 15,000
Fire Extinguishers - 4.5 Kg (CO2) 4 4200 16,800
First Aid Box 10 350 3,500
S.C.B.A 1 22500 22,500
Carbolic acid 10 960 9,600
Barricading Tape 20 350 5,250
Oxygen Canisters 2 3000 6,000
SAFETY
28 | P a g e
Note:- For 5-7 lakh sqft per annum - 2 safety officer, 3-4 safety stewert, 1 Male nurse
One manager for 1.5-2 million sqft per annum
Gross INR /
S.N Items Nos. Rate Amount
Amount Sqft
Safety Award Application (CII, NSC etc) 2 75000 1,50,000
Safety Training from Third party, First
4 25000 1,00,000
Aid Training, Fire Mock Drill
Safety Reward 36 250 9,000
Safety Promotional Activity (National
Safety Day, World Environment Day,
4 25000
Celebration of Safety Man-hours Work, 1,00,000
HEALTH/Medical Facilities/Hygiene
29 | P a g e
APPENDIX A – JOB SAFETY
ANALYSIS
30 | P a g e
A.1 Hot Work
Date:
Ref No:
Company:
Project:
Location:
The tools and equipment use: Pneumatic breaker/Electrical, Welding Machine, Grinding Machine, Drilling Machine.
The training and skill required for the job: Tool box meeting regarding safe work practices and JSA briefing.
Personal Protective Equipment Required: Safety Shoes, Helmet, Leather Apron, Leather hand gloves, ear plugs, Face shield, Safety Goggles.
31 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION
SN JOB STEP
BY/RECORD
32 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION
SN JOB STEP
BY/RECORD
33 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION
SN JOB STEP
BY/RECORD
34 | P a g e
A.2 Fabrication and Erection of Structural Steel & Welding
JOB SAFETY ANALYSIS WORKSHEET- Fabrication and Erection of Structural Steel & Welding
Company:
Project:
Location:
The type of work, nature of work: Fabrication of Steel structures, welding of supports, Erection and Bolting of the steel structures,
Roofing works.
The tools and equipment used: Welding Equipment, hand tools, Portable power tools, crane, lifting tools and tackles, Scissor Lifts
etc.
The training and skill required for the job: Tool box meeting regarding safe work practices and OCP briefing.
Personal Protective Equipment Required: Helmet, Safety Goggles, Safety Shoes, Leather hand gloves, Aprons, welder’s helmet and
face shield.
35 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION BY/RECORD
SN JOB STEP
1 Handling of steel structures Use of crane and lifting tools. Use only inspected and certified crane and Site Supervisor,
using crane and lifting lifting tackles for lifting of structures, Only Competent Person
equipment’s authorized riggers and crane operators shall (Crane and lifting)
be allowed to work. Check all the
equipment’s prior to lifting for its safe
condition and ensure.
2 Cutting of steel structures Material handling hazards (Both Use proper manual handling techniques. Site Supervisor
using power tools. mechanical and manual) and first aid Hand gloves and other required PPE must
injuries. be worn while handling steel structures.
Cutting wheel may break and fly Use proper and standard quality cutting
wheels.
36 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION BY/RECORD
SN JOB STEP
extinguishers at site.
Electrical Hazards Use only outlets protected with ELCB. All Site Supervisor.
portable tools and machines should be
inspected prior to use by the competent
person. Ensure all equipment having current
inspection records. .
3 Welding of steel structures. Fire Proper housekeeping is to be maintained. All Site Supervisor
flammable /combustible materials to be
removed from site or to covered with fire
blanket if physically removing them is not
possible.
37 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION BY/RECORD
SN JOB STEP
Electrical Hazards portable tools and machines using should be Site Supervisor,
inspected prior to use by the competent Eelectrical Site Engineer
person. Ensure all equipment having current
inspection records.
4 Drilling of the bolt holes in Electrical hazards Use only outlets protected with ELCB. All Site Supervisor
the structures portable tools and machines using should be
inspected prior to use by the competent
person. Ensure all equipment having current
inspection records.
38 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION BY/RECORD
SN JOB STEP
5 Installing the roofing sheets Work at height, Fall of Materials and The area should be barricade before starting Site Supervisor
on the structural frames. Fall hazards of Personnel. working at height. There should not be any
work underneath of the work at height. Use
Personal fall arrest System. There should be
sufficient anchor points for the fall arrestor
rope. Use Lifelines (Minimum dia. of 12 mm
as per procedure) having sufficient capacity
and inspected and approved by competent
third party. The life line should be tightened
and the tying points for lifelines also should
have the same rating for load withstanding.
Improper access to height Use Man lift or Suitable ladders for access.
The ladder rules to be followed while using Site Supervisor
the ladders. It should have sufficient load
rating and of good construction. It should be
inspected regularly.
Use of Portable power tools Use only inspected and approved portable
Site Supervisor,
power tools. All tools should have valid be
Competent Person-
inspected. Use ELCB protected Electrical
Electrical.
connections with Industrial sockets for using
in the work.
39 | P a g e
A.3 Stone & Tile Fixing
Company:
Project:
Location:
The training and skill required for the job: Safety induction, Job Specific training and JSA briefing before starting activity.
Personal Protective Equipment Required: Cut resistant Gloves, safety shoes, safety helmets, safety glasses, dust masks, hearing
protection.
40 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
1 Use of hand tools All workers should be undertaking Job Specific training
Workers informed of requirement to provide all
Workers, experts and hand tools in a safe condition. Site Engineer/
support staff exposed to hazards
Trowels Worker hand tools inspected by Competent Person Site Supervisor
like cut injury, hit injury by flying
Cutting tools (hand) objects, puncture etc. before Use
Hammers Damaged/defective tools to be taken out of use
Screwdrivers immediately
Saw
Workers to be instructed by joining instructions to
provide all necessary PPE (gloves, safety shoes,
safety helmets, safety glasses)
Experts to carry out periodic visual inspections
throughout competition, defective tools to be
removed immediately.
41 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
2 Use of Power Tools Practical demonstration by experts to small groups of
workers
Pre use visual inspection for damage/defects to
Drills All persons using power tools tools, cables, plugs - defective tools to be taken out
exposed to hazards like serious
Grinders of use immediately Site Engineer/
cut injury, hit injury by flying
Sanders Workers to be informed by joining instructions to Site Supervisor
objects, punctures caught in
Saws moving parts. Electrocution provide all necessary PPE (gloves, hearing
protection, defenders/plugs, dust masks)
Cables to be routed away from aisles and walkways
where they could create trip hazards to other persons
and/or expose cables to potential damage
Workers to be assessed individually before approval
given to operate power tools
All power tools to be 110v/240v or battery powered.
Grinder disc/abrasive wheels must be verified with test
certificate.
Technical expert to periodically check tools for
damage/defects and where necessary take out of
action and label "Do not use".
42 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
3 Manual handling Safety shoes must be worn whilst working within the
construction area.
Fork lifts truck/pallet truck to be provided for transport of Site Engineer/
Site
Boxed tiles/Stone large pallets and waste skip. Supervisor
Adhesive containers Back pains, cuts, fall of object, Transport of small amounts of mixed mortar to be by
Sand/cement respiratory & visual irritation due wheelbarrow.
Mortar to dust, trip, hit by mobile
equipment etc. PPE to be worn when mixing mortar and/or
adhesives to include goggles, dust mask, overalls,
safety shoes.
Mixer, barrows and shovels to be periodically
inspected for damage/defects and taken out of use for
repair if faults discovered.
4 Working at height , Safe All workers will be undertaking Job specific Training
use of Site Engineer/
Demonstration by experts in safe use of erection, Site
Securing, stabilizing steps, hop ups, Trestles.
trestles Supervisor
Slip & trip fall hazard Provision of safe means of access to steps, hop ups,
steps
trestles.
hop ups
Provision and use of PPE, safety helmets, gloves
Work area to be fenced off.
Use of warning signs at all access points to work
area where work is being carried out above
ground level.
5 Materials All materials to be stored in dedicated store or location
approved by experts within competition area. Site Engineer/
Adhesives Body contact with adhesives, Substance Data sheets available for each product in Site
Joint fillers ingestion, and hazard due to office. Supervisor
Polyester resins improper manual handling also Workers instructed by equipment experts in safe use and
Wall tiles included. handling of materials
Floor tiles/Stone Provision and use of PPE (gloves, goggles, dust masks)
Workers informed of personal hygiene requirements,
wash hands after use/contact and before eating,
drinking.
43 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
6 Housekeeping
Workers given verbal instructions to maintain and/or
General work area Slip, trip, cut, irritation in clean/tidy up individual workplaces during and after Site Engineer/
cleaning competition work times Site
breathing, contact with hot
Demolition of Experts/support staff to dismantle work after Supervisor
surface, electrocution etc.
worker work completion
Dust/plaster debris Appropriate PPE to be worn during such work i.e. dust
masks, goggles, safety shoes
Wet/damp sweeping techniques to be used for general
cleaning of competition area to control dust levels.
Tools/equipment to be stored in lockable tool box.
44 | P a g e
A.4 Painting Work
Company:
Project:
Location:
The training and skill required for the job: Tool box meeting regarding safe work practices and JSA briefing.
Personal Protective Equipment Required: Safety Shoes, Hard hat, Hi-viz Jacket, Safety glasses, Nose mask, and Rubber gloves.
45 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED BY/RECORD
1-Fumes of thinner and paint 1-Nose mask will be provided throughout the activity
2-Exposure to paint and thinner 2-Hand gloves and full fitting cloths shall be used
throughout the activity
3-Fire hazard
Site Engineer/
3. Applying paint 3-Fire extinguisher shall be provided in Paint storage area
4-Falling of paint may lead to Supervisor
environment incident 4-Falling of paint on ground must be prevented by using
sheet below the work location
5-Fall of painter if painting to be
done at height 5-Body Harness shall be used while painting at height
46 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED BY/RECORD
5. Supervision Illness, Holiday, Evening cover Ensure adequately trained staff is available at all time. HESO
47 | P a g e
A.5 Scaffolding
Company:
Project:
Location:
The training and skill required for the job: Safety TBT, Safe practices and OCP Briefing before starting the work.
Personal Protective Equipment Required: Safety Shoes, Hard hat, Hi-viz. jacket, Safety glasses and Cotton Hand gloves.
48 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION
SN JOB STEP
BY/RECORD
Slip and trip of person. 1.Engage trained/inducted workforce for the task
1 Workplace set up Poor housekeeping. Stack the material in arranged manner. Supervisor/Workers
Nails Maintain good housekeeping.
Maintain good housekeeping at workplace and keep all
Slip and trip hazard
walkways obstruction free.
Fall of material, fall of
person on same ground. Carry the load according to personal capacity if the load seems
Manual handling of unbearable then seek the help of other workers.
2 Back strain, cut injury due to Supervisor/Workers
scaffold material. Wear job specific personal protective equipment (hand gloves,
sharp edge.
safety shoes, hard hat etc.)
Fingers caught in between
While placing the form work on the ground provide wooden
the floor and form work
packing under the form work.
Engage approved scaffold contractor .Full time supervision
during erection of scaffold.
Scaffold supervision & erectors must be qualified and trained
for the job & must be appointed.
All scaffolds to be registered. Register to be kept up –to date
by scaffold supervisor.
All scaffold materials must be checked before use and if found
to be defective, must be removed for site.
Barrier to be erected around scaffold erection areas. Warning
3 Erection of scaffolds Collapse of structure signs to be placed.
Scaffold Erecter
Ensure all personnel not to over load scaffold with working
materials.
Do not overload the scaffold.
Ensure that all joint pins and clamps properly used.
Ensure that the soil must compact and surface must be even.
Ensure sole plate & base plates are rigid and stable.
Provided proper platform as blanking ,toe guards, top rail, mid
rail & access ladder not more than 6m in
Height.
49 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION
SN JOB STEP
BY/RECORD
Personnel are to wear harness with double lanyards and be
properly anchored during the course of erection – 100% tie-off.
Harness user to be site trained by EHS department or approved
Falling from height training providers.
No standing on mid rail or top rail while erection in progress. Supervisor/Workers
All work platforms must be fully secured with steel wire.
All workers should be done by standing on platform only.
Use proper ladder to reach the height .Climbing through ledger
is not allowed.
Barricade work areas and display warning signages.
Secure all hand tools.
Use toolbox & bag to carry tools.
Falling objects No lose items should be placed on the scaffolding.
Supervisor/Workers
Provide toe boards soon after completing platform erection
work.
Ensure all clamps /joint pins are fixed properly.
Materials overlapping activity should be controlled.
Check scaffold green tag (after inspection) is in place, Valid 7
days and safe to use & no work shall proceed with red tag.
Inform scaffold supervisor, if scaffold seems to be unsafe to
use.
Do not remove or modify scaffold components without site
Use of Scaffolds /Cup supervisor’s instruction.
4 Scaffolds topple
lock scaffolds Do not over load the scaffold; scaffold should be adequately Scaffold Erecter
strengthened by cross bracing /ties/putlogs etc.
Scaffold to be erected by qualified scaffold erectors only and
with immediate supervision by scaffold supervisor.
Do not place the scaffold very near to groove edges.
Design could be strictly followed in the case of coup lock
scaffold.
Barricade work areas and display warning signages.
Falling objects
Secure all hand tools in a particular box or bag. Supervisor/Workers
No loose item should be placed on the scaffolding.
50 | P a g e
HAZARDS IDENTIFIED CONTROLS REQUIRED ACTION
SN JOB STEP
BY/RECORD
Overlapping of materials is allowed.
Don’t keep any extra materials on scaffold platforms.
Personnel are to wear harness with double lanyards and be
properly anchored during the course of erection-100% tie-off.
Falling from Height Harness user to be site trained by EHS Dept. or approved
training providers.
Supervisor/Workers
No standing on mid rail while erection in progress.
Do not pull or shift scaffold when someone is on top of
scaffold.
Ensure cop locks are lock. Do not over load the scaffold.
Ensure the ladder is inspected & colour coded.
Ensure buddy system when using ladder.
All full body harness user must be trained by EHS Dept.
5 Ladder Usage Fall from Height Ensure ladders are used for light duty and short period work
Supervisor/Workers
scope.
First three steps should be lock off.
Ladder should be secured at both ends.
Use three point contact system while using ladder.
Falling objects
Site supervisor to remind workers not to put loose materials
left on top off ladder./platform
Supervisor/Workers
Do not leave ladder unattended.
Ladder shall be fold and kept neatly when not in use.
51 | P a g e
A.6 Concreting
Date:
Ref No:
Company:
Project:
Location:
The tools and equipment used: Static Pump with pipes, Vibrator machine, Hammer.
The training and skill required for the job: Tool box meeting regarding safe work procedure and MSDS briefing with all workers.
Personal Protective Equipment Required: Safety Shoes, Helmet, Hi-visibility Jacket, Safety glasses, Hand gloves, dust mask.
52 | P a g e
SN HAZARDS ACTION
JOB STEP CONTROLS REQUIRED
IDENTIFIED BY/RECORD
1 Static pump set up Pump can be Clean the area. Supervisor / Pump
toppled down Surface should be firm and leveled. Operator
Choke the wheels before starting the pump.
Outriggers should be fully extended.
Diesel pump to be set in open area so that fumes will release
outside
2 Fixing of pipeline up Manual handling Pre-start training to the working crews. Supervisor / Pump
to the pour area. (Injury to the Use proper tools for fixing the pipeline. operators /
personals). Do not lift the heavy load alone; seek the help of other worker to workers
lift.(not beyond 35kg individually)
Do not put finger or hand while interlocking the pipes.
Provide the proper support to the pipe line.
Do not use damaged pipes
Fall of person on Put some wooden ply on re-bar for proper access. Supervisor
same level
3 Concreting Skin infection, Eye Ensure that all workers must use job specific personal Supervisor
injury protective equipment i.e. gum boots, goggles, Helmet & Hi-
visible vest.
Fall, slip & trip Engage trained workforce for the task Site Engineer
Electrocution All electrical cables should be kept overhead. Supervisor /
Use tested and tagged electrical equipment workers
Vibratory Rotate the workers (After one hour) for the task. Supervisor
syndrome
4 Changing the pipe Injury to the Ensure the static pump is off and no concrete pressure in the pipe Supervisor /
line from one location personals line Worker
to another location. Use proper tools for fixing the pipeline.
Does not lift the heavy load alone; seek the help of other worker to
lift the pipes.
Do not put finger or hand while interlocking the pipes.
53 | P a g e
SN HAZARDS ACTION
JOB STEP CONTROLS REQUIRED
IDENTIFIED BY/RECORD
54 | P a g e
A.7 De-shuttering
Date:
Ref No:
Company:
Project:
Location:
The tools and equipment used: Push pull jack, spanner, hammer etc.
The training and skill required for the job: Tool box meeting regarding safe work procedure with all workers.
Personal Protective Equipment Required: Safety Shoes, Helmet, and Hi-via Jacket, Safety glasses, and Cotton Hand gloves.
55 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED BY/RECORD
56 | P a g e
ACTION
SN JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED BY/RECORD
Being struck by materials. Ensure the de-nailing soon after removal of wooden runner.
Seek the help of co-workers whilst shifting the heavy
formwork.
Store the nails in suitable container. Do not throw the nails at
workplace.
Stack the material properly and keep area clean and tidy.
Need presence of mind whilst lifting and shifting the shutter
boards.
Slip and trip hazard After completion of the work do proper housekeeping of all
Site Engineer
5 Housekeeping Environmental hazard – Soil area and stack all material uniformly.
and Foreman
Pollution (Concrete waste) Dispose, reuse or recycle the concrete waste.
57 | P a g e
A.8 Backfilling
Ref No:
Date:
The training and skill required for the job: Safety induction,
Company: flagmen / operator training and JSA Briefing before starting the
backfilling activity.
Personal Protective Equipment Required: Safety Shoes, Hard hat, Hi-vis Jacket, Safety glasses, Hand gloves, Nose mask (if required)
58 | P a g e
Sl. ACTION
No. JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
Engage experienced and skilled operator and make sure
that operator must possess a driving license.
Need to complete the training of safe vehicle operation with all
Operator error. drivers and helper. Site Engineer
Need to complete the competency assessment training for all
drivers/operators.
59 | P a g e
Sl. ACTION
No. JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
precautions to be taken.
60 | P a g e
Sl. ACTION
No. JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED
BY/RECORD
Appoint dedicated banks man for each heavy machinery.
Ensure reverse horn, both side mirrors in JCB as well as in
roller.
Ensure the moving area of Roller is clear of peoples.
Restrict the limit of roller and JCB to avoid collision
Ensure the work to be done under competent supervision.
61 | P a g e
APPENDIX B – WORK PERMIT
62 | P a g e
WORK AT HEIGHT PERMIT
PERMIT NO.: (To be renewed daily, After three working days new permit to be issued)
Contractor Name:
3 Has the scaffolding been declared safe by the scaffolding supervisor? Green tag
provided.
4 Is there proper access to the place of work?
Contractor Name:
3 Have fire extinguishers / fire buckets been kept near working location?
4 Has tin sheet/ wet gunny bag/ fire retardant cloth / sheet been placed to prevent
sparks from causing fire?
5 Has water hose connection been made for continuous water spray? (if applicable)
6 Have proper staging, platform handrails been provided for welding at heights/
ducts?
7 Do the workmen deployed for welding have adequate experience?
Contractor Name:
3 Has the electrical cable been laid above ground level up-to a minimum height of 8 ft.?
7 Is there a provision for looking out supply at the source at DG room/ control panel?
8 Have adequate and proper PPE like helmets, rubber shoes, gloves been issued and
being used while carrying out electrical work?
9 Have the workers been briefed on the hazard present at the location and tool box talks
given?
10 Have temporary cables routed underground and route markers provided.
11 All DB’s provided with primary earth and measured with adequate earth value.
12 All outdoor connections are weatherproof and shaded.
13 Any other precautions taken (specify):______________
Contractor Name:
Engineering Services
3 Description of underground facilities/ Utilities existing at the proposed location.
7 Use of PPE’s ensured: Dust Mask, Eye Protection, Hand tools with insulated handles.
8 Vehicle movement restricted near the edge of excavation. Wheel stoppers provided.
Contractor Name:
Details about the Vehicle to be mentioned. Tick mark in the box for the type of Vehicle.
D. Permit Surrendered:
Name: __________________________ Time: ____________
Signature: ________________________ Date: ___________
ELECTRICIAN PERMIT
K RAHEJA CORP
WORK PERMIT SYSTEM
Details about the Vehicle to be mentioned. Tick mark in the box for the type of Vehicle.
1.………………………………………………………………………………………………………
2………………………………………………………………………………………………………
3………………………………………………………………………………………………………
D. Permit Surrendered:
Name: __________________________ Time: ____________
Signature: ________________________ Date: ___________
----------------------
APPENDIX C – HSE INSPECTION
CHECKLIST
70 | P a g e
HOUSEKEEPING INSPECTION CHECKLIST (WEEKLY)
Name of Project :
Location :
Inspected By :
Date :
Sl.
Points YES/NO/NA Remark
No.
STRUCTURAL FABRICATION / REBAR YARD
1 Walkways, passages kept clear of materials?
Area & roads kept clear for manoeuvring of
2
cranes and material handling equipment?
Scrap, cut-pieces, welding electrode stubs, hand-
3 tools kept tidy in workplace and disposed
suitably?
4 Scrap-bin available in adequate number?
Welding cables, power cables routed properly to
5
avoid run-over by vehicle or tripping hazards?
At least 1 metre on both sides of gantry rails is
6
kept clear of material?
Floor kept clear of water, oil spillage /
7
accumulation?
CIVIL WORK AREA
1 All approach, aisle, ingress / egress to and from
work area, excavated pits, ramps, walkways kept
clear of debris, tools etc?
2
Scaffolding materials – frame & shuttering
materials etc. are stacked properly at site?
71 | P a g e
Sl.
Points YES/NO/NA Measures
No.
ELECTRICAL INSTALLATIONS & BOOTHS
1 Approach to DB, Panels, Switches kept clear?
Fire extinguishers installed at locations where
2
they are easily accessible?
Welding cables and power cables are routed
3
separately?
Routing of cables is done properly to avoid
4
obstruction & tripping hazards?
5 Floor of electrical room / station kept dry?
6 Rubber mats are in place at electrical panels?
STORES
1 Walkways, entry and exits kept clear?
2 Materials placed on racks safely accessible?
Compressed gas cylinders are segregated as full
3
or empty and type of gas?
Vertically stored cylinders are secured / chained
4 to avoid toppling and horizontal ones guarded
against rolling down?
Flammable storage areas are isolated from store,
5
office and work areas?
Cement bags are stacked in proper gradient
6
safely?
Corrosive material (e.g. acids, alkalis) stored away
7 from other material & kept on collection trays to
safeguard against accidental leakage?
Storing area for lifting tools & tackles, ropes, wire
8 ropes & PPE is dry, clean & free of corrosive
material?
Easy accessibility to installed fire extinguishers
9
ensured in store?
Flammable & combustible materials stored
10
separately.
GENERAL
1 Separate scrap yard allocated for the project?
Approach to workstations, offices, time offices,
2
stores, P&M are well laid and demarcated?
Roads are kept clear of stacked material for free
3
& safe vehicular movement?
Heavy materials stacking are taken care of to
4
prevent slips, collapse and rolling?
72 | P a g e
CHECKLIST FOR SCAFFOLDING TAGGING (AFTER ERECTION)
Name of Project :
Location :
Inspected By :
Date :
Verticality of Standards
Horizontality of Transoms
Bay Length
Bay Width
Bay Lift
Diagonal Bracing
Tie/Lock
Platform
Spacing of Bearer
Guardrails (Top rail & Mid
rail)
Toe Board
Ladder/Access
Condition of Ladder
Earthing (If any)
Other (if any)
B. Checked by
Name: __________________________ Time: ____________
Signature: __________________________ Date: ____________
C. Verified by
Name: __________________________ Time: ____________
Signature: ________________________ Date: ____________
73 | P a g e
CHECKLIST FOR SCAFFOLDING INSPECTION (FORTNIGHTLY)
Name of Project :
Location :
Inspected By :
Date :
Sl.
Points YES/NO/NA Remark
No.
SCAFFOLD TAG
1 Whether "Safe to use" tag is displayed and
signed?
2 Have there been any alteration / modification
done to the scaffold after "Safe to use" tag is
issued / displayed?
FOUNDATIONS
3 Are the soil or ground on which going to stand is
firm and examined?
4 Is scaffolds structure having a solid base avoiding
Pavements and Manhole covers etc?
GENERAL REQUIREMENTS
5 Have all components been inspected for defects
such as broken welds, corroded members, and
missing locks, bent or dented tubes?
6 Are all braces, bearer, and clamps secured all
sections pinned or appropriately secured?
WORKING PLATFORM
7 Is working platform prepared tied / fixed
adequately with scaffold?
8 Are platform kept free from unnecessary
obstructions and projecting nails?
9 Is the platform cleaned to avoid slippage?
10 Are the guardrails and toe boards fitted at the
edge of decking?
11 Is railing provided for all working platform higher
than 2m above the floor level?
12 Is top railing provided 900mm above the platform
level and intermediate rail half way between the
top rail and platform?
13 Is material Guards provided for material stacking
on a working platform or working place above the
74 | P a g e
Sl.
Points YES/NO/NA Remark
No.
height of the toe boards?
14 Are guardrails and toe boards in place on all open
sides?
15 Are opening in working platform kept safely
covered /fenced?
16 When employees are working on suspended
scaffolds, are lifelines firmly anchored to an
overhead structure and not to the scaffold?
17 Is the scaffold over 10 feet high, (if yes) is
personal / material fall protection available, or
are guardrails in place?
MOBILE SCAFFOLD
18 Are wheels used for scaffold tower of appropriate
SWL with locking arrangements?
19 Are mobile scaffolds used on a firm and level
surface?
20 Does the height of mobile scaffolds exceed four
times the smaller base dimension (if yes), extra
support provided?
21 Are all materials removed from the platform
while in motion?
Note: If answer is ‘NO’, Please mention actual condition/ reason in Remark.
75 | P a g e
ELECTRICAL SAFETY INSPECTION CHECKLIST (WEEKLY)
Name of Project :
Location :
Inspected By :
Date :
Sl.
Points YES/NO/NA Remark
No.
CABLES
1 Whether the condition of Cable is checked?
Are Cables received from other site checked for
2 Insulation Resistance before putting them into
use?
Are all main Cables, taken either underground /
3
Overhead?
Are welding Cables routed properly above the
4
Ground?
5 Are welding & electrical Cables overlapping?
Is there any improper jointing of Cables, wires
6
prevailing at Site?
DBs / SDBs
76 | P a g e
Sl.
Points YES/NO/NA Remark
No.
RCBO / RCCB
77 | P a g e
DIESEL GENERATOR (DG) INSPECTION CHECKLIST (FORTNIGHTLY)
Name of Project :
Location : Asset Code :
Inspected By : Date :
Sl.
Points YES/NO/NA Remark
No.
Whether the continuity and tightness of earth
1
conductor are checked?
Is the SWG of the earth conductor used adequate? If
2
yes, mention here.
Whether earth resistance is measured? If yes, mention
3
the value of Earth Resistance.
6 Is DG provided under shed / cover?
7 Whether entry is restricted into the DG room?
8 Are cable trenches are covered?
9 Is insulation provided on the battery terminals?
10 Is thermal insulation done for the DG exhaust?
Whether stack height is maintained as per PCB
11
regulations?
12 Whether DG exhaust is diverted outside the shed?
Are all the rotating parts (coupling, radiator fan) of DG
13
guarded?
14 Whether any leakage of fuel / oil in the DG room?
Whether DG surrounding is free from flammable
15
material?
Whether fire extinguisher / fire buckets with stand are
16
provided?
Whether DG is fitted with Acoustics & Silencer
17
insulations?
Note: If answer is ‘NO’, Please mention actual condition/ reason in Remark.
--------------------------------
78 | P a g e
MOBILE CRANE / HYDRAULIC ARTICULATED INSPECTION CHECKLIST (MONTHLY)
Name of Project :
Location :
Inspected By :
Date :
79 | P a g e
TOWER CRANE INSPECTION CHECKLIST (MONTHLY)
----------------------------------------
81 | P a g e
VEHICLE & EARTH MOVING EQUIPMENT INSPECTION CHECKLIST
Sl.
Points YES/NO/NA Remark
No.
1 Is engine condition safe to operate?
2 Clutch / brake / Hand brake checked.
3 Hydraulic System checked.
4 Guards / Covers / Doors in place.
5 Fastener locks pins / Keys available.
Horn / Reverse horn / Lights in working
6
condition.
Indicators / Wiper Blades in working
7
condition.
8 Operator’s fitness ensured.
9 Tyre pressure / Tyre Condition checked.
10 Condition of Battery and Lamps working.
11 Operating levers / steering checked.
Gauges & warning devices available &
12
working.
13 Fire extinguisher provided.
14 Rear Side Mirror available.
15 Seat Belt available and in use.
82 | P a g e
PLANT INSPECTION CHECKLIST (MONTHLY)
Name of Project :
Location :
Inspected By :
Date :
Sl.
Points Observation Measures
No
Plant boundary are demarcated to avoid hazards
1
arising out of unintended operations
2 Plant supports are as per the design drawing
3 Demarcation of working area, vehicular movements
4 All rotating parts are adequately guarded
Emergency stoppers for moving conveyers & plant are
5
provided at accessible areas
Doors of the moving parts are interlocked to avoid
6
unauthorized operation during plant running
Adequate accesses are provided to reach all working
7
locations.
8 Safety of the Loading ramps
Protection against entrapping of peoples in the
9
loading hoppers
10 Illumination adequate
11 Earthing provided
12 Environment Protection measures implemented
13 Lightning arrestors are provided
14 Daily check procedure is followed
15 Operator Fitness
16 LOTO system implemented
Effective functioning of pressure relief arrangement in
17
silos.
18 Maintenance permit system is followed regularly
Fire Protection & Fire Fighting arrangement are
19
adequate
Note: This checklist shall be used for Batching Plant. Additional checklist points shall be
developed at project level on need basis.
83 | P a g e
LABOUR CAMP INSPECTION CHECKLIST (FORTNIGHTLY)
Name of Project :
Location :
Inspected By :
Date :
No. Of Workmen :
Residing in the
Labour camp
Sl.
Points YES/NO/NA Remark
No.
ACCESS & EGRESS
Are the entry roads / walkways / passages to camp
1.
kept clear?
Are the walkways & roads are even and free from
2.
water logging?
3. Is the entry inside workmen camp restricted?
4. Is Illumination level OK in access / egress?
GENERAL
Are dustbin / garbage bins allocated for each &
1.
every colony?
Is the garbage being disposed off on regular
2.
basis?
Are the drinking water facilities adequate in the
3.
Workmen camp?
Is there any emergency communication system
4.
established?
Is the workmen camp constructed with materials,
5.
which are not readily flammable?
Are Fire Extinguishers & Fire Buckets available
6.
and maintained regularly?
Are locations of Fire Extinguishers & Fire Buckets
7.
listed out & displayed?
8. Are First-aid facilities available?
Whether disinfection activities carried out on
9.
weekly basis?
LIVING AREA
1. Whether Cement Flooring provided?
2. Condition of the Side walls / Roof Sheet
Is shelter strong enough to withstand wind
3.
pressure?
Whether the electrical connections provided are
4.
safe?
5. Is the ventilation of the rooms adequate?
84 | P a g e
Sl.
Points YES/NO/NA Remark
No.
6. Is the illumination of the rooms adequate?
7. Are the doors and windows in good condition?
Is the general hygienic condition of the rooms
8.
adequate?
KITCHEN
1. Is separate kitchen provided?
2. Are kitchens kept clean and tidy?
3. Is the water supply adequate for cooking?
UTILITIES AREA
Other Information
85 | P a g e
APPENDIX D – FIELD
OBSERVATION REPORT
86 | P a g e
K RAHEJA CORP
FIELD OBSERVATION REPORT
Project Name:
Unsafe Condition Unsafe Action Unsafe Equipment Unsafe use of Equipment Others
Details of Field Observation (Description & Location): Proposed Action to be taken / Rectification details:
88 | P a g e
Ref: E.1
PRELIMINARY INCIDENT REPORT
Name of the Project / Job No. :
Witness :
(_________________________________)
Site Supervisor / In-charge
Name:
Note: This Report is applicable for Near miss case / Reportable lost time injuries / Dangerous
occurrences and shall be sent:
Within 12 hrs. by the concerned supervisor to HSEO
Within 24 hrs. by HSEO to BU-HSEM
89 | P a g e
Ref: E.2
Job No
Business Unit
Name of the Site Engineer /
Section In charge
Name of the P&M In charge
(if P&M related incident)
Name of the HSEO
Unsafe Condition
Type of Incident
Working at Height Equipment/Automobile Electrical
90 | P a g e
3.2) Exact Location where the Incident occurred:
3.5) Describe briefly how the incident occurred (Add sketches and additional sheets to support the
description):
91 | P a g e
5. Precautionary Measures
5.1) What are the precautions taken / being taken to prevent similar occurrence?
___________________
(HSEO / BU-HSEM)
92 | P a g e
Ref: E.3
93 | P a g e
Mention the names of all the concerned who failed to
implement the control measures suggested,
4.5
1. ______
2. ______
5 HSE INSPECTION
7 LEGAL COMPLIANCE
94 | P a g e
APPENDIX F – FIRST AID
95 | P a g e
Ref: F.1
FIRST AID REGISTER
96 | P a g e
ANALYSIS OF FIRST-AID CASES
Ref: F.2
NAME OF THE PROJECT:
BUSINESS UNIT : MONTH:
G ROUPI NG OF CASES B ASED ON
SL NO. N UMB ER OF CASES
C A USAT I VES
1 Adopting improper work methodology
2 Defective tools
3 Electrocution
4 Failure in design
5 Failure of tools & tackles
6 Failure to implement work permit
7 Failure to provide barrication
8 Failure to provide edge protection
9 Failure to provide fall protection
10 Failure to provide slope or shoring
11 Failure to use fall protection
12 Failure to wear eye protection
13 Improper access
14 Rash drive
15 Run over by hydra crane
16 Unsecured Material
17 Failure to follow safety norm
18 Fall from height
19 Failure of Communication
20 Fall of Material
21 Caught in Between
22 Hit by Object
23 Insect bites
____________________
HSEO Signature
Man-hours Worked
97 | P a g e
APPENDIX G – SAFETY SIGNAGE’S
98 | P a g e
List of Safety Signages
3 Caution 4 Caution,
– Danger
Electrici of falling
ty
5 Wet 6 Drinking
Floor Water
7 Smokin 8 PPE
g Area Zone
99 | P a g e
Sl. Descrip Signage Sl. Descripti Signage
tion on
9 Emerge 10 Caution –
ncy Low
Assemb Headroo
ly Point m
11 Mandat 12 Emergen
ory PPE cy
Signage Shower
13 HT 14 Overhea
Danger d Hazard
15 Emerge 16 Caution –
ncy Exit Floor
Opening
17 Pedestri 18 Pedestria
an/ n Access
Access
Prohibit
ed. / No
Entry.
100 | P a g e
Sl. Descrip Signage Sl. Descripti Signage
tion on
19 Flamma 20 Caution:
ble Lifting
material Hazard.
Storage
21 First 22 Fire
Aid Box Extinguis
Locatio her
n location
23 Caution 24 Parking
- area
Suspend
ed loads
25 Authori 26 Wear
zed Safety
Entry Harness
Only
27 Compre 29 Corrosiv
ssed gas e
cylinder Substanc
storage e
101 | P a g e
Sl. Descrip Signage Sl. Descripti Signage
tion on
29 Fuel 30 Hazardo
Storage us Waste
Area- storage
No Area
smokin
g
31 Power 31 Eye
Lines Protectio
Above n
32 Hand 33 Canteen
Protecti
on
102 | P a g e
Sl. Descrip Signage Sl. Descripti Signage
tion on
40. Constru 41. Danger-
ction Flammab
area/Do le gas
not
enter
42. Hazard 43. Explosiv
ous e
Substan Substanc
ce e
103 | P a g e
Sl. Descrip Signage Sl. Descripti Signage
tion on
52. CCTV 53. No
Monitor Parking
ing
104 | P a g e
Display of Various Safety Poster at Labor camp, contractor office, Project
office, Safety Park, training room and other conspicuous location
105 | P a g e
106 | P a g e
SAFETY Statistics Board:
PROJECT NAME
MONTH DATE
NEARMISS REPORTED
107 | P a g e
APPENDIX H – AUDIT REPORT
108 | P a g e
Ref: Annexure 1
-------------------
Signature: MR
Date:
109 | P a g e
Ref: Annexure 2
NON CONFORMITY REPORT
Audit Report No. :
Requirement :
Function : Date of Audit :
Auditor : Auditee:
110 | P a g e
Ref: Annexure 3
AUDIT SUMMARY & STATUS
STATUS OF AUDIT
Sl. No. Name of BU / Project Date of Audit Rating % Status of NCR’s
1
2
3
4
5
SUMMARY OF NCR’s
Sl. Requirement Audit report Non-Conformity Identified Action Proposed Status
No. no.
1
Corporate HSE
__________________
111 | P a g e
Ref: Annexure 4
Page 1
___(Date)___ at _____(Location)_____
Attended by:
Distribution:
Page 2
Action By /
Sl No. Discussions / Decisions
Target Date
Date:
--------------------
Signature: HOD - HSE / MR
112 | P a g e
Ref: Annexure 5
Nature of complaint /
Sl. Corrective / Preventive Date of
Date Opportunity for Received from Remarks
No Action Proposed action taken
Improvement
113 | P a g e
Ref: Annexure 6
Meeting No.
Project:
Date of Meeting:
Business Unit: Job No: Location of Meeting:
MEMBERS PRESENT MEMBERS ABSENT
INVITEES
(K Raheja) (K Raheja)
REPORT SENT TO
No. of No. of No. of
Name / Dept. Name / Dept. Name / Dept.
Copies Copies Copies
114 | P a g e
MINUTES OF HSE MEETING
Item
Description of Discussion Action By Target Remarks
No.
Status of implementation of
5
Objectives & Programmes
115 | P a g e
APPENDIX I – MONTHLY REPORT
116 | P a g e
MONTHLY REPORT
Fatalities
Environmental Incidents
117 | P a g e
APPENDIX J – MODEL LABOUR
CAMP GUIDELINES
118 | P a g e
MODEL LABOR CAMP GUIDELINES
The employer shall provide free temporary living accommodation within the
work site or as near to it as may be possible, to all building workers employed
by him for such period as the construction work progresses.
The temporary accommodation provided as mentioned above shall have
separate cooking place, bathing, washing and lavatory facilities.
After the building or other construction work is over, as soon as possible the
employer at his own cost shall cause removal or demolition of the temporary
structures erected by him for the purpose of providing living accommodation
and restore the ground in good level and clean condition.
In case an employer is given any land by a Municipal Board or any other local
authority for the purposes of providing temporary accommodation for the
building workers, he shall, as soon as may be after the construction work is
over, return the possession of such land in the same condition in which he
received the same.
Crèches:
In every place wherein, more than fifty female building workers are ordinarily employed, a
suitable room or rooms for the use of children under the age of six years of such female
workers shall be provided and maintained.
Welfare Facilities:
119 | P a g e
The walls, ceilings and partitions shall be white washed or color washed once in
every period of four months.
Where both male and female building workers are employed, there shall be displayed
outside each block of toilet a notice containing therein "For Men Only" or "For
Women Only", as the case may be, written in the language understood by the
majority of such workers. Such notice shall also bear the figure of a man or of a
woman, as the case may be.
The tanks should be fitted with taps and dust proof cover.
The elevated tanks to be placed raised stands or platforms.
Proper shades to be provided for the water tanks.
Suitable arrangements to be done for drainage to carry away the spilt water.
Tanks shall be kept clean and water renewed at least once every day.
Practicable measures to be taken to ensure that the water is from contamination.
Water shall not be supplied from any open well or reservoir unless it is maintained as
to be free from the possibility of pollution by chemical or bacterial and extraneous
impurities.
Drinking Water tanks to be marked “Drinking Water”.
Capacity of tank to be labeled on it.
The water tanks/taps should be placed away from washing place, urinals & latrine
(At least 6 meter).
The tank must be protected from entry of a child or animal falling into a tank.
Make sure tanks are vented as required to prevent pressure or vacuum from
developing.
Prevent excessive heat near or inside the tank.
Regard tanks as confined spaces.
Follow proper entry procedures during entry inside the tank.
Do not stand on tank domes as the surface may be flexible and slippery.
Do not move tanks while holding water.
Water tanks should be inspected on a routine basis
Clean the exterior and interior of the tank.
Inspect fittings and exterior gaskets for leaks and signs of general corrosion and
deterioration.
Canteen:
In every place wherein not less than 250 (two hundred and fifty) building
workers are ordinarily employed, the employer of such building workers shall
provide an adequate canteen in the manner as specified in this rule for the use
of such building workers.
License and registration of Site canteen has to be obtained from the canteen
owner.
This has to be identified as a legal requirement in legal register as well.
shall apply to a petty manufacturer who himself manufactures or sells any
article of food or a petty retailer, hawker, itinerant vendor or a temporary stall
120 | P a g e
holder or small scale or cottage or such other industries relating to food
business or tiny food business operator; but they shall register themselves with
such authority and in such manner as may be specified by regulations, without
prejudice to the availability of safe and wholesome food for human
consumption or affecting the interests of the consumers.
The canteen shall consist of a dining hall with furniture sufficient to accommodate
building workers using such canteen, a kitchen, and store-room, pantry and washing
places separately for building workers and for utensils.
The canteen shall be sufficiently lighted at all times when any person has access to
it.
The floor of such canteen shall be made of smooth and impervious material and
inside walls of such canteen shall be lime-washed or color-washed at least once in
every six months and kitchen walls of such canteen shall be lime-washed once in
every three months.
The precincts of the canteen shall be maintained in a clean and sanitary condition.
Waste water from such canteen shall be carried away in suitable covered drains and
shall not be allowed to accumulate in the surroundings of such canteen.
Suitable arrangements shall be made for the collection and disposal of garbage from
such canteen.
Building of the canteen shall be situated at the distance not less than 15.2 meters
from any toilet facility or any source of dust, smoke or obnoxious fumes.
The foodstuffs and other items to be served in the canteen shall be in conformity
with the normal dietary habits of the building workers.
Where a work place is situated at a distance of more than 200 meter from the
canteen shall be made by the employer employing building workers at such place for
serving tea and light refreshment to such building workers at such place.
Charges of foodstuff:
The charges for foodstuffs, beverages and other items served in the canteen shall be
based on "no profit no loss" and the price list of such items shall be conspicuously
displayed in such canteen.