Stream Gauging
Stream Gauging
Stream Gauging
g g
Di h
Discharge Estimation
E ti ti
• In this method, the vertical in which the velocity
measurements are made (by one‐point
one point or two‐points
two points
method) is taken as the middle of the strip, and the
water depth (d) in the vertical (determined by sounding)
is taken as the mean depth of the strip.
– Difference
Diff off the
th velocities
l iti in i adjacent
dj t segments
t
should not be more than 20%
• The ffollowing
g data were collected ffor a stream
at a gauging station. Compute the discharge.
Equation of current meter: v = 0.3
0 3 N + 0.05
0 05
• Width of each strip, b = 3 m, mean depth of strip = d, and the
total discharge, Q = Σ ΔQ
Compute the stream flow for the measurement data
given
i b l columns
below l 1 to 5 off table
bl 1 below.
b l T k the
Take h
meter rating from equation. V= a+bN with a=0.03 and
b=0 66
b=0.66
Solution
As V = a + bN
So V = 0.03 + 0.66 N
– The
Th concentrationi at the
h samplingli point
i rises
i
rapidly to a peak and then slowly diminishes.
Q = q (C1 – C2 ) / (C2 – Co )
Where Co
Wh C = Concentration
C i off chemical
h i l already
l d existing
i i in i flowing
fl i
fluid of stream
• 1ppm=0.001g/litre
• 1ppm=1mg/litre
• 1ppm = 1000 parts per billion
• 1ppb = 1/1000 ppm
• A 30 g/l solution of a chemical was discharged
into a stream at a constant rate of 10x10‐6
m3//sec. The same chemical was not found in
stream water at all. The concentration of
chemical at sampling section was found to be
5000 parts per million. Estimate the stream
di h
discharge
Stage ~ Discharge relationship
• The graphical curve between stage and
discharge is called the stage‐discharge curve
or Rating curve.
curve
Q = C (g‐a) n
log Q = log C + n log (g‐a)
y c m x
Q = C when (g
(g‐a)
a) = 1
– Zero gauge height “a” a is determined by assuming
the various values of ‘a” until log Q” when plotted
against log (g
(g‐a)
a), forms a straight line.
line
– This
Thi straight
i h line
li can then
h b extended
be d d to
extrapolate discharge corresponding to the
measuredd gauge height.
h i h
• Correction has to be applied for the discharge obtained from
the rating curve during a rising or falling stage i.e., during a
flood.
(g a) n
Q = C (g‐a)
• Plot Q vs.
vs (g – a) on a log paper paper assuming a value
for the constant a = 0.6 m (say); the curve obtained
may be concave downwards. Now assume a value a =
1 2 m (say)
1.2 ( ) and d the
h curve obtained
b i d may be b concave
upward. Now try an intermediate value a = 0.9 m,
which plots a straight line and represents the stage
discharge relationship.
0 52
0.52 24 43
24.43 0 46
0.46 29 16 57
16.57
0.76 62.62 0.55 76 46.44
1.06 111.5 0.64 139 89.20
1 23
1.23 145 86
145.86 0 85
0.85 187 134 48
134.48
1.3 166.3 0.98 218 164.63
1.55 199.74 1.19 268 217.89
1 71
1.71 221 11
221.11 14
1.4 303 261 62
261.62
1.82 270.35 1.49 371 330.00
2.04 304.72 1.58 428 383.03
2.08 317.73 1.65 456 408.13
2.38 367.9 1.74 538 485.29
2.67 447.79 1.83 682 605.76
2.81 464.52 1.86 708 633.52
3.02 487.74 1.98 773 686.31
4.42 761.81 2.74 1261.02
Extension Of Rating Curve by Chezy's
2000 Method
e (Q m³³/s)
1500
1000
scharge
500
Dis
0
0 200 400 600 800 1000 1200 1400
Value of AxSQRT(D)
Stream Flow Units
• Rate of Run Off:
– It mayy be measured in cubic foot per
p second or
cubic meter per second. One cubic foot per
second is a volume of one ft³ when collected in
one second.
– The ft³/second
ft /second are also called cusec or cfs
cfs. In the
metric system the cubic meter per second are also
called cumec.
cumec
Stream Flow Units
• Volume Run Off:
– Volume of flow is expressed
p in cubic feet,, cubic
meters, cubic inches and also in Acre foot and
second foot days.
y
Second Foot Day (SFD)
• IIt iis the
h volume
l off water collected
ll d iin 24 hhours ((one
day) at the rate of 1 cubic foot per second.
1 Sfd = 24 x 60
60x60
60 =86400
86400 ft³.f³
• The smaller unit is second foot hour i.e. volume
collected
ll d in
i one hour
h at the
h rate off 11cfs.
f
1 sfh = 60x60 =3600 ft³.
Acre Foot
• If an area of one acre is converted by a
p of 1ft of water.
uniform depth
• The total volume thus collected is 1 Acre foot.
One A
O Acre = 4840 ((yards)²
d )²
1 Acre ‐ foot = (4840x9)x1 = 43560 ft³
and 1 Sfd = 1.9835 Acre foot.
Hectare Meter
• If an area of one hectare is covered by a
p of 1m of water.
uniform depth
• The total volume thus collected is 1 Hectare‐
meter.
meter
One Hectare‐meter = 104 m³
Inches of Run Off
• If a certain catchment area is having a
uniform depthp of 1 cm of water, the total Run
off is 1 cm for that very catchment area.